20.1: Contractor's Claim (General Conditions of Cotract, VOL- I)
FIDIC 1999 Construction, The MDB Harmonised Edition Fakhar-un-nisa (PE)
IN CASE OF REJECTION OR NO RESPONSE FROM THE ENGINEER , ANY OF
THE PARTIES (EMPLOYER & CONTRACTOR) MAY REFER TO THE DISPUTE
BOARD (DB)
EVENT
(Occurance of Event)
• 28 Days
NOTICE TO
CLAIM
• By the Contractor
SUBMISSION OF DETAILED CLAIM
INCLUDING PARTICULARS
• By the Contractor
•42 Days
OR
•As agreed b/w
the Eng &
Contractor
•28 Days
FINAL SUBMISSION OF
CLAIM
END OF EVENT OR EFFECTS OF
EVENT
•By the Contractor
APPROVAL OR DISAPPROVAL
OR DETAIL COMMENT
OR REQUEST FOR MORE DATA/DOCUMENT
•By the Engineer
•42 Days
OR
•Agreed Period for
substantiation
•42 Days OR
•Agreed Period for
substantiation
D:T4Contract DocsClaims 20.1 (Flow chart)

Claims 20.1 (Flow chart)

  • 1.
    20.1: Contractor's Claim(General Conditions of Cotract, VOL- I) FIDIC 1999 Construction, The MDB Harmonised Edition Fakhar-un-nisa (PE) IN CASE OF REJECTION OR NO RESPONSE FROM THE ENGINEER , ANY OF THE PARTIES (EMPLOYER & CONTRACTOR) MAY REFER TO THE DISPUTE BOARD (DB) EVENT (Occurance of Event) • 28 Days NOTICE TO CLAIM • By the Contractor SUBMISSION OF DETAILED CLAIM INCLUDING PARTICULARS • By the Contractor •42 Days OR •As agreed b/w the Eng & Contractor •28 Days FINAL SUBMISSION OF CLAIM END OF EVENT OR EFFECTS OF EVENT •By the Contractor APPROVAL OR DISAPPROVAL OR DETAIL COMMENT OR REQUEST FOR MORE DATA/DOCUMENT •By the Engineer •42 Days OR •Agreed Period for substantiation •42 Days OR •Agreed Period for substantiation D:T4Contract DocsClaims 20.1 (Flow chart)