PROGRAM EVALUATION REVIEW TECHNIQUE




             VINCI VIVEKA
VINCI VIVEKA

•A statistical tool, used in project management

• It is designed to analyze and represent the tasks
involved in completing a given project.

•A decision making tool designed to save time in
achieving end objectives.

•It is one of the techniques of scientific management.

•It was developed for the U.S. Navy Special Projects
Office in 1957 to support the U.S. Navy's Polaris
nuclear submarine project
PERT
PERT chart is a tool that facilitates decision making.

PERT is a method to analyze the involved tasks in completing
a given project, especially the time needed to complete each
task and to identify the minimum time needed to complete the
total project.

PERT is valuable to manage where multiple tasks are
occurring simultaneously to reduce idleness.

For this it takes into consideration three factors:
  1. Time
   2. Resources
    3. Technical Performance Specifications.
                  VINCI VIVEKA
TERMINOLOGY
PERT Event: a point that marks the start or completion of one or
more activities. It consumes no time and uses no resources. When it
marks the completion of one or more tasks, it is not “reached” (does
not occur) until all of the activities leading to that event have been
completed.eg- start and finish*

Predecessor Event: an event that immediately precedes some other
event without any other events intervening. An event can have
multiple predecessor events and can be the predecessor of multiple
events. Eg: A and b are predecessor of C*

Successor Event: an event that immediately follows some other
event without any other intervening events. An event can have
multiple successor events and can be the successor of multiple
events.eg: D is the successor of C*.

*(refer Gantt Diagram)



                          VINCI VIVEKA
Optimistic Time (O): the minimum possible time required to
accomplish a task, assuming everything proceeds better than
is normally expected

Pessimistic Time (P): the maximum possible time
required to accomplish a task, assuming everything goes
wrong (but excluding major catastrophes).

Most Likely Time (M): the best estimate of the time
required to accomplish a task, assuming everything proceeds
as normal.

Expected Time (TE): the best estimate of the time
required to accomplish a task, accounting for the fact that
things don't always proceed as normal (the implication being
that the expected time is the average time the task would
require if the task were repeated on a number of occasions
over an extended period of time).

               TE = (O + 4M + P) ÷ 6
                       VINCI VIVEKA
PERT Activity: the actual performance of a task which
consumes time and requires resources (such as
labor, materials, space, machinery). It can be understood as
representing the time, effort, and resources required to move
from one event to another. A PERT activity cannot be
performed until the predecessor event has occurred. Eg:
A,B,C,D*

Float or Slack is a measure of the excess time and
resources available to complete a task. It is the amount of time
that a project task can be delayed without causing a delay in
any subsequent tasks (free float) or the whole project (total
float). Positive slack would indicate ahead of schedule; negative
slack would indicate behind schedule; and zero slack would
indicate on schedule.

Critical Path: the longest possible continuous pathway taken
from the initial event to the terminal event. It determines the
total calendar time required for the project; and, therefore, any
time delays along the critical path will delay the reaching of the
terminal event by at least the same amount.
                          VINCI VIVEKA
Activity   Predecessor                Time Estimates            Te


                              O                 M        P


   A       -             2                  8       6        4.00


   B       -             3                  5       9        5.33


   C       A,B           4                  5       7        5.17


   D       C             4                  6       10       6.13




                 TE = (O + 4M + P) ÷ 6

                             VINCI VIVEKA
Gantt Chart
( According to the table in previous chart)




     Activity On Node (AON) Diagram
              VINCI VIVEKA
EARLY     DURATION   EARLY
       START                FINISH




                   A
          LATE    SLACK      LATE
         START              FINISH




VINCI VIVEKA
In order to determine these following are the steps-
EARLY FINISH [ EF ]
Formula for EF= ES + Duration.

Duration can be taken from the table it is represented by Te
For the first activity i.e. START Early Start [ ES] =0,




                                                                          VINCI VIVEKA
As start is a pert event its duration is zero.
Therefore, for START
ES=0 Duration =0 ; EF= ES + Duration => EF=0

EF of the predecessor event becomes ES of its successor.

Therefore, for A
ES=0 Duration=4, EF=4

For B,( as A&B both have same Predecessor i.e. START hence B----
ES=0 Duration= 5.33 EF=5.33

For C ( as A&B both are C predecessor hence we take the one with higher
value)
ES=5.33 Duration=5.17 EF=10.5
For D,
ES= 10.5 Duration=6.13 EF=16.63

For FINISH [as FINISH is a pert event its duration is zero]
ES=16.63 Duration=0 EF=16.63

LATE START [ LS ]
Formula LS=LF – DURATION

In this we start with FINISH, as it is the last activity. LATE FINISH [LF ] of
FINISH = its EF.
Therefore, LF=EF=16.63 Duration= 0 LS=LF- Duration , Hence LS=16.63

For D, [ LS of successor event becomes LF for its predecessor event ]
LF=16.63 Duration=6.13 LS=10.5

For C,
LF=10.5 Duration=5.17 LS=5.33

For B,
LF=5.33 Duration=5.33 LS= 0

VINCI VIVEKA
For A, [ as C is also its successor ]
LF=5.33 Duration=4 LS=1.33

For START [as A&B both are successor but we take here one with the lower
value ]
LF=1.33 Duration =0 LS=1.33




                                                                                   VINCI VIVEKA
SLACK
To determine the critical path we have to find whether any activity has a slack.
Activity on the critical path has slack zero.
Formula SLACK=LF-EF or SLACK= LS-ES

For START                                     For C
LS=1.33 ES=0 SLACK=1.33                       LS=5.33     ES=5.33 SLACK=0

For A                                         For D
LS=1.33 ES=0 SLACK=1.33                       LS= 10.5 ES=10.5        SLACK=0

For B                                         For FINISH
LS=5.33 ES=0 SLACK=5.33                        LS=1.33 ES=0         SLACK=1.33
ES=0        DUR=0         EF=0          ES=0        DUR=4      EF=4
              START                                     A
LS=1.33    SLACK=1.33     LF=1.33       LS=0      SLACK=1.33   LF=5.33




ES=0         DUR=5.33      EF=5.33     ES=5.33     DUR=5.17    EF=10.5

                 B                                     C

LS=0       SLACK=5.33      LF=5.33     LS=5.33     SLACK=0     LF=10.5



 ES=10.5     DUR=6.13       EF=16.33   ES=16.63    DUR=0       EF=16.63
                  D                                  FINISH
 LS=10.5     SLACK=0        LF=16.63   LS=16.63   SLACK=1.33   LF=16.63


                      VINCI VIVEKA
CRITICAL PATH
It is the longest continous -path way. There can be
more than one critical path or the path can change.
In the drawn Gantt diagram there are two
alternatives to reach FINISH and adding there
SLACK timing-
START+A+C+D+FINISH=3.99
START+B+C+D+FINISH=7.99

Hence , the path START+B+C+D+FINISH is the
longest it is the critical path, shown in the diagram
in the next slide.

                        VINCI VIVEKA
VINCI VIVEKA




CRITICAL PATH
    [ in red ink ]
•PERT chart explicitly defines and makes visible
dependencies (precedence relationships) between the
work breakdown structure (commonly WBS) elements

•PERT facilitates identification of the critical path and
makes this visible

•PERT facilitates identification of early start, late start,
and slack for each activity

•PERT provides for potentially reduced project duration
due to better understanding of dependencies leading to
improved overlapping of activities and tasks where
feasible.
•The large amount of project data can be organized &
presented in diagram for use in decision making.
                        VINCI VIVEKA
DISADVANTAGES:
•There can be potentially hundreds or thousands of activities and
individual dependency relationships

•PERT is not easily scalable for smaller projects

•The network charts tend to be large and unwieldy requiring
several pages to print and requiring special size paper

•The lack of a timeframe on most PERT/CPM charts makes it
harder to show status although colours can help (e.g., specific
colour for completed nodes)

•When the PERT/CPM charts become unwieldy, they are no
longer used to manage the project.

                   VINCI VIVEKA
VINCI VIVEKA
Prepared by:
VINCI VIVEKA
M.ED SCHOLAR [2012-2013]
ST. XAVIER’S COLLEGE OF EDUCATION, PATNA.
vivekavinci@gmail.com
REFERENCE:
http://en.wikipedia.org/wiki/Program_Evaluation_and_Review_Technique

More Related Content

What's hot

The Gantt Chart
The Gantt ChartThe Gantt Chart
The Gantt Chart
Nicola2903
 
Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)
chandkec
 
PERT (Program evaluation review technique)
PERT (Program evaluation review technique) PERT (Program evaluation review technique)
PERT (Program evaluation review technique)
Tanoj Patidar
 
Programme evaluation and review technique &Gantt Chart
Programme evaluation and review technique &Gantt ChartProgramme evaluation and review technique &Gantt Chart
Programme evaluation and review technique &Gantt Chart
Mathew Varghese V
 
Critical path method
Critical path methodCritical path method
Critical path method
Shubhi Verma
 
Critical path method
Critical path methodCritical path method
Critical path method
Dushyant Nasit
 
PERT MBO GANTT CHART
PERT MBO GANTT CHARTPERT MBO GANTT CHART
PERT MBO GANTT CHART
NAVANEETA KUSUM
 
Delegation
DelegationDelegation
Delegation
Mahmoud Shaqria
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
S.Vijaya Bhaskar
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
Mr. Ramesh Nayaka
 
CPM/PERT and Gantt charts
CPM/PERT and Gantt chartsCPM/PERT and Gantt charts
CPM/PERT and Gantt charts
VARSHA RUSTAGI
 
Gantt chart
Gantt chartGantt chart
Gantt chart
PREETHYDAVID
 
PERT & Gantt Chart
PERT & Gantt Chart PERT & Gantt Chart
PERT & Gantt Chart
Anju George
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
Alecsis Roe Frasco
 
PERT, GANTT CHART and BENCHMARKING
PERT, GANTT CHART and BENCHMARKINGPERT, GANTT CHART and BENCHMARKING
PERT, GANTT CHART and BENCHMARKING
Alam Nuzhathalam
 
Gantt Charts
Gantt ChartsGantt Charts
Gantt Charts
Nadine Fisher
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
Ajeesh Mk
 
Programme evaluation & review technique (pert)
Programme evaluation & review technique (pert)Programme evaluation & review technique (pert)
Programme evaluation & review technique (pert)
AnkitaKadam20
 
PERT and CPM
PERT and CPMPERT and CPM
PERT and CPM
student
 
PLANNING IN MANAGEMENT,DEFINITION CHARACTERISTICS, IMPORTANCE AND LIMITATIONS
PLANNING IN MANAGEMENT,DEFINITION CHARACTERISTICS, IMPORTANCE AND LIMITATIONSPLANNING IN MANAGEMENT,DEFINITION CHARACTERISTICS, IMPORTANCE AND LIMITATIONS
PLANNING IN MANAGEMENT,DEFINITION CHARACTERISTICS, IMPORTANCE AND LIMITATIONS
AMALDASKH
 

What's hot (20)

The Gantt Chart
The Gantt ChartThe Gantt Chart
The Gantt Chart
 
Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)
 
PERT (Program evaluation review technique)
PERT (Program evaluation review technique) PERT (Program evaluation review technique)
PERT (Program evaluation review technique)
 
Programme evaluation and review technique &Gantt Chart
Programme evaluation and review technique &Gantt ChartProgramme evaluation and review technique &Gantt Chart
Programme evaluation and review technique &Gantt Chart
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Critical path method
Critical path methodCritical path method
Critical path method
 
PERT MBO GANTT CHART
PERT MBO GANTT CHARTPERT MBO GANTT CHART
PERT MBO GANTT CHART
 
Delegation
DelegationDelegation
Delegation
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
CPM/PERT and Gantt charts
CPM/PERT and Gantt chartsCPM/PERT and Gantt charts
CPM/PERT and Gantt charts
 
Gantt chart
Gantt chartGantt chart
Gantt chart
 
PERT & Gantt Chart
PERT & Gantt Chart PERT & Gantt Chart
PERT & Gantt Chart
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
PERT, GANTT CHART and BENCHMARKING
PERT, GANTT CHART and BENCHMARKINGPERT, GANTT CHART and BENCHMARKING
PERT, GANTT CHART and BENCHMARKING
 
Gantt Charts
Gantt ChartsGantt Charts
Gantt Charts
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Programme evaluation & review technique (pert)
Programme evaluation & review technique (pert)Programme evaluation & review technique (pert)
Programme evaluation & review technique (pert)
 
PERT and CPM
PERT and CPMPERT and CPM
PERT and CPM
 
PLANNING IN MANAGEMENT,DEFINITION CHARACTERISTICS, IMPORTANCE AND LIMITATIONS
PLANNING IN MANAGEMENT,DEFINITION CHARACTERISTICS, IMPORTANCE AND LIMITATIONSPLANNING IN MANAGEMENT,DEFINITION CHARACTERISTICS, IMPORTANCE AND LIMITATIONS
PLANNING IN MANAGEMENT,DEFINITION CHARACTERISTICS, IMPORTANCE AND LIMITATIONS
 

Viewers also liked

Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERT
Pulchowk Campus
 
Pert and its applications
Pert and its applicationsPert and its applications
Pert and its applications
Amrit Mty
 
PERT Ghant chart and bench marking with application to nursing
PERT Ghant chart and bench marking with application to nursingPERT Ghant chart and bench marking with application to nursing
PERT Ghant chart and bench marking with application to nursing
Hariasha
 
Gantt
GanttGantt
Gantt
Balaji P
 
TID Chapter 6 Introduction To Microsoft Project
TID Chapter 6 Introduction To Microsoft ProjectTID Chapter 6 Introduction To Microsoft Project
TID Chapter 6 Introduction To Microsoft Project
WanBK Leo
 
Project Management Through Gantt & Pert Chart
Project Management Through Gantt & Pert ChartProject Management Through Gantt & Pert Chart
Project Management Through Gantt & Pert Chart
Vinay Prajapati
 
The gantt Chart
The gantt Chart The gantt Chart
The gantt Chart
Nicola2903
 
Lecture5---Gantt Chart
Lecture5---Gantt ChartLecture5---Gantt Chart
Lecture5---Gantt Chart
danishrafiq
 
Project Management PERT and CPM
Project Management PERT and CPMProject Management PERT and CPM
Project Management PERT and CPM
Institute of Rural Management
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
Rahul Dubey
 
Paper_26338_handout_2010_0
Paper_26338_handout_2010_0Paper_26338_handout_2010_0
Paper_26338_handout_2010_0
Cee Cee Feng
 
Controlling
ControllingControlling
Controlling
Kumar
 
Chapter 10 controlling
Chapter 10   controllingChapter 10   controlling
Chapter 10 controlling
Argon David
 
Advertisements
AdvertisementsAdvertisements
Advertisements
Sagar
 
Ali Pert
Ali PertAli Pert
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...
yang lu
 
Project management
Project managementProject management
Project management
Kwesi Kissiedu
 
PM scheduling techniques
PM scheduling techniquesPM scheduling techniques
PM scheduling techniques
Nazish khalid
 
Gantt pert
Gantt pertGantt pert
Gantt pert
atoypakiss
 
Programme evaluation and review technique (pert)
Programme evaluation and review technique (pert)Programme evaluation and review technique (pert)
Programme evaluation and review technique (pert)
Anupam Kumar
 

Viewers also liked (20)

Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERT
 
Pert and its applications
Pert and its applicationsPert and its applications
Pert and its applications
 
PERT Ghant chart and bench marking with application to nursing
PERT Ghant chart and bench marking with application to nursingPERT Ghant chart and bench marking with application to nursing
PERT Ghant chart and bench marking with application to nursing
 
Gantt
GanttGantt
Gantt
 
TID Chapter 6 Introduction To Microsoft Project
TID Chapter 6 Introduction To Microsoft ProjectTID Chapter 6 Introduction To Microsoft Project
TID Chapter 6 Introduction To Microsoft Project
 
Project Management Through Gantt & Pert Chart
Project Management Through Gantt & Pert ChartProject Management Through Gantt & Pert Chart
Project Management Through Gantt & Pert Chart
 
The gantt Chart
The gantt Chart The gantt Chart
The gantt Chart
 
Lecture5---Gantt Chart
Lecture5---Gantt ChartLecture5---Gantt Chart
Lecture5---Gantt Chart
 
Project Management PERT and CPM
Project Management PERT and CPMProject Management PERT and CPM
Project Management PERT and CPM
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
 
Paper_26338_handout_2010_0
Paper_26338_handout_2010_0Paper_26338_handout_2010_0
Paper_26338_handout_2010_0
 
Controlling
ControllingControlling
Controlling
 
Chapter 10 controlling
Chapter 10   controllingChapter 10   controlling
Chapter 10 controlling
 
Advertisements
AdvertisementsAdvertisements
Advertisements
 
Ali Pert
Ali PertAli Pert
Ali Pert
 
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...
 
Project management
Project managementProject management
Project management
 
PM scheduling techniques
PM scheduling techniquesPM scheduling techniques
PM scheduling techniques
 
Gantt pert
Gantt pertGantt pert
Gantt pert
 
Programme evaluation and review technique (pert)
Programme evaluation and review technique (pert)Programme evaluation and review technique (pert)
Programme evaluation and review technique (pert)
 

Similar to Pert- program evaluation and review technique

Critical path method (CPM).pptx
Critical path method (CPM).pptxCritical path method (CPM).pptx
Critical path method (CPM).pptx
HimanshuKaklotar1
 
Day 2 Revision
Day 2 RevisionDay 2 Revision
Day 2 Revision
Joyce Wong
 
Pert cpm
Pert cpmPert cpm
Pert cpm
Ann vasquez
 
Pert cpm
Pert cpmPert cpm
Pert cpm
Ann vasquez
 
Section 6 :Project Scheduling: PERT/CPM (1)
Section 6 :Project Scheduling: PERT/CPM (1)Section 6 :Project Scheduling: PERT/CPM (1)
Section 6 :Project Scheduling: PERT/CPM (1)
Zakaria Hasaneen
 
Pert and CPM
Pert and CPMPert and CPM
Pert and CPM
Sachin Kapoor
 
PERT CPM.pptggfyufydtyfydyfyydyhffhhhydydyfu
PERT CPM.pptggfyufydtyfydyfyydyhffhhhydydyfuPERT CPM.pptggfyufydtyfydyfyydyhffhhhydydyfu
PERT CPM.pptggfyufydtyfydyfyydyhffhhhydydyfu
infinitepestcontrol
 
Cpm and pert
Cpm and pertCpm and pert
Cpm and pert
Vignesh Jayakumar
 
Cpm pert
Cpm pertCpm pert
Cpm pert
Ashutosh Rai
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1
adeelmunir158
 
Cm ch4 scheduling
Cm ch4 schedulingCm ch4 scheduling
Cm ch4 scheduling
Ahmed Gamal
 
Critical path and fw bw pass
Critical path and fw bw passCritical path and fw bw pass
Critical path and fw bw pass
Martin Bailey
 
Program Evaluation And Review Technique
Program Evaluation And Review TechniqueProgram Evaluation And Review Technique
Program Evaluation And Review Technique
SimonRobertson
 
Lu3 – the planning phase lectures
Lu3 – the planning phase lecturesLu3 – the planning phase lectures
Lu3 – the planning phase lectures
jillmitchell8778
 
Project Management Techniques
Project Management TechniquesProject Management Techniques
Project Management Techniques
project management
 
Gantt PERT and CPM
Gantt PERT and CPMGantt PERT and CPM
Gantt PERT and CPM
Gurbakash Phonsa
 
cpmpertmy (1)
cpmpertmy (1)cpmpertmy (1)
cpmpertmy (1)
Dr. Divya Khandelwal
 
Critical Path Analysis
Critical Path AnalysisCritical Path Analysis
Critical Path Analysis
tutor2u
 
The Network Diagram and Critical Path
The Network Diagram and Critical PathThe Network Diagram and Critical Path
The Network Diagram and Critical Path
dmdk12
 
Chapter seven lecture slides
Chapter seven lecture slidesChapter seven lecture slides
Chapter seven lecture slides
William Perkins
 

Similar to Pert- program evaluation and review technique (20)

Critical path method (CPM).pptx
Critical path method (CPM).pptxCritical path method (CPM).pptx
Critical path method (CPM).pptx
 
Day 2 Revision
Day 2 RevisionDay 2 Revision
Day 2 Revision
 
Pert cpm
Pert cpmPert cpm
Pert cpm
 
Pert cpm
Pert cpmPert cpm
Pert cpm
 
Section 6 :Project Scheduling: PERT/CPM (1)
Section 6 :Project Scheduling: PERT/CPM (1)Section 6 :Project Scheduling: PERT/CPM (1)
Section 6 :Project Scheduling: PERT/CPM (1)
 
Pert and CPM
Pert and CPMPert and CPM
Pert and CPM
 
PERT CPM.pptggfyufydtyfydyfyydyhffhhhydydyfu
PERT CPM.pptggfyufydtyfydyfyydyhffhhhydydyfuPERT CPM.pptggfyufydtyfydyfyydyhffhhhydydyfu
PERT CPM.pptggfyufydtyfydyfyydyhffhhhydydyfu
 
Cpm and pert
Cpm and pertCpm and pert
Cpm and pert
 
Cpm pert
Cpm pertCpm pert
Cpm pert
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1
 
Cm ch4 scheduling
Cm ch4 schedulingCm ch4 scheduling
Cm ch4 scheduling
 
Critical path and fw bw pass
Critical path and fw bw passCritical path and fw bw pass
Critical path and fw bw pass
 
Program Evaluation And Review Technique
Program Evaluation And Review TechniqueProgram Evaluation And Review Technique
Program Evaluation And Review Technique
 
Lu3 – the planning phase lectures
Lu3 – the planning phase lecturesLu3 – the planning phase lectures
Lu3 – the planning phase lectures
 
Project Management Techniques
Project Management TechniquesProject Management Techniques
Project Management Techniques
 
Gantt PERT and CPM
Gantt PERT and CPMGantt PERT and CPM
Gantt PERT and CPM
 
cpmpertmy (1)
cpmpertmy (1)cpmpertmy (1)
cpmpertmy (1)
 
Critical Path Analysis
Critical Path AnalysisCritical Path Analysis
Critical Path Analysis
 
The Network Diagram and Critical Path
The Network Diagram and Critical PathThe Network Diagram and Critical Path
The Network Diagram and Critical Path
 
Chapter seven lecture slides
Chapter seven lecture slidesChapter seven lecture slides
Chapter seven lecture slides
 

More from Vinci Viveka

Cognitive development bruner
Cognitive development brunerCognitive development bruner
Cognitive development bruner
Vinci Viveka
 
chief minister’s girls cycle scheme-front pages
chief minister’s girls cycle scheme-front pageschief minister’s girls cycle scheme-front pages
chief minister’s girls cycle scheme-front pages
Vinci Viveka
 
chief minister girls cycle scheme-suggestion, reccommendation Chief minister ...
chief minister girls cycle scheme-suggestion, reccommendation Chief minister ...chief minister girls cycle scheme-suggestion, reccommendation Chief minister ...
chief minister girls cycle scheme-suggestion, reccommendation Chief minister ...
Vinci Viveka
 
chief ministers girls cycle scheme-analysis of data ch 04
chief ministers girls cycle scheme-analysis of data ch 04chief ministers girls cycle scheme-analysis of data ch 04
chief ministers girls cycle scheme-analysis of data ch 04
Vinci Viveka
 
chief minister girls cycle scheme-review of related literature
chief minister girls cycle scheme-review of related literaturechief minister girls cycle scheme-review of related literature
chief minister girls cycle scheme-review of related literature
Vinci Viveka
 
chief minister girls cycle scheme-introduction and conceptual framework
chief minister girls cycle scheme-introduction and conceptual frameworkchief minister girls cycle scheme-introduction and conceptual framework
chief minister girls cycle scheme-introduction and conceptual framework
Vinci Viveka
 
Finance
FinanceFinance
Finance
Vinci Viveka
 
research methodology- Chief MInister Girls Cycle Scheme
research methodology- Chief MInister Girls Cycle Schemeresearch methodology- Chief MInister Girls Cycle Scheme
research methodology- Chief MInister Girls Cycle Scheme
Vinci Viveka
 
Bibliography- research thesis
Bibliography- research thesisBibliography- research thesis
Bibliography- research thesis
Vinci Viveka
 
Appendix
AppendixAppendix
Appendix
Vinci Viveka
 
Computer assisted instruction
Computer assisted instructionComputer assisted instruction
Computer assisted instruction
Vinci Viveka
 
Concept attainment strategy
Concept attainment strategyConcept attainment strategy
Concept attainment strategy
Vinci Viveka
 
Marxism philosophy
Marxism philosophyMarxism philosophy
Marxism philosophy
Vinci Viveka
 
Research practicum
Research practicumResearch practicum
Research practicum
Vinci Viveka
 
Marxism
MarxismMarxism
Marxism
Vinci Viveka
 

More from Vinci Viveka (15)

Cognitive development bruner
Cognitive development brunerCognitive development bruner
Cognitive development bruner
 
chief minister’s girls cycle scheme-front pages
chief minister’s girls cycle scheme-front pageschief minister’s girls cycle scheme-front pages
chief minister’s girls cycle scheme-front pages
 
chief minister girls cycle scheme-suggestion, reccommendation Chief minister ...
chief minister girls cycle scheme-suggestion, reccommendation Chief minister ...chief minister girls cycle scheme-suggestion, reccommendation Chief minister ...
chief minister girls cycle scheme-suggestion, reccommendation Chief minister ...
 
chief ministers girls cycle scheme-analysis of data ch 04
chief ministers girls cycle scheme-analysis of data ch 04chief ministers girls cycle scheme-analysis of data ch 04
chief ministers girls cycle scheme-analysis of data ch 04
 
chief minister girls cycle scheme-review of related literature
chief minister girls cycle scheme-review of related literaturechief minister girls cycle scheme-review of related literature
chief minister girls cycle scheme-review of related literature
 
chief minister girls cycle scheme-introduction and conceptual framework
chief minister girls cycle scheme-introduction and conceptual frameworkchief minister girls cycle scheme-introduction and conceptual framework
chief minister girls cycle scheme-introduction and conceptual framework
 
Finance
FinanceFinance
Finance
 
research methodology- Chief MInister Girls Cycle Scheme
research methodology- Chief MInister Girls Cycle Schemeresearch methodology- Chief MInister Girls Cycle Scheme
research methodology- Chief MInister Girls Cycle Scheme
 
Bibliography- research thesis
Bibliography- research thesisBibliography- research thesis
Bibliography- research thesis
 
Appendix
AppendixAppendix
Appendix
 
Computer assisted instruction
Computer assisted instructionComputer assisted instruction
Computer assisted instruction
 
Concept attainment strategy
Concept attainment strategyConcept attainment strategy
Concept attainment strategy
 
Marxism philosophy
Marxism philosophyMarxism philosophy
Marxism philosophy
 
Research practicum
Research practicumResearch practicum
Research practicum
 
Marxism
MarxismMarxism
Marxism
 

Recently uploaded

一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理
一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理
一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理
taqyea
 
Lukas Rycek - GreenChemForCE - project structure.pptx
Lukas Rycek - GreenChemForCE - project structure.pptxLukas Rycek - GreenChemForCE - project structure.pptx
Lukas Rycek - GreenChemForCE - project structure.pptx
pavelborek
 
Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...
Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...
Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...
Niswey
 
1 Circular 003_2023 ISO 27001_2022 Transition Arrangments v3.pdf
1 Circular 003_2023 ISO 27001_2022 Transition Arrangments v3.pdf1 Circular 003_2023 ISO 27001_2022 Transition Arrangments v3.pdf
1 Circular 003_2023 ISO 27001_2022 Transition Arrangments v3.pdf
ISONIKELtd
 
欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】
欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】
欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】
concepsionchomo153
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results
 
Cover Story - China's Investment Leader - Dr. Alyce SU
Cover Story - China's Investment Leader - Dr. Alyce SUCover Story - China's Investment Leader - Dr. Alyce SU
Cover Story - China's Investment Leader - Dr. Alyce SU
msthrill
 
NIMA2024 | De toegevoegde waarde van DEI en ESG in campagnes | Nathalie Lam |...
NIMA2024 | De toegevoegde waarde van DEI en ESG in campagnes | Nathalie Lam |...NIMA2024 | De toegevoegde waarde van DEI en ESG in campagnes | Nathalie Lam |...
NIMA2024 | De toegevoegde waarde van DEI en ESG in campagnes | Nathalie Lam |...
BBPMedia1
 
Science Around Us Module 2 Matter Around Us
Science Around Us Module 2 Matter Around UsScience Around Us Module 2 Matter Around Us
Science Around Us Module 2 Matter Around Us
PennapaKeavsiri
 
list of states and organizations .pdf
list of  states  and  organizations .pdflist of  states  and  organizations .pdf
list of states and organizations .pdf
Rbc Rbcua
 
2024.06 CPMN Cambridge - Beyond Now-Next-Later.pdf
2024.06 CPMN Cambridge - Beyond Now-Next-Later.pdf2024.06 CPMN Cambridge - Beyond Now-Next-Later.pdf
2024.06 CPMN Cambridge - Beyond Now-Next-Later.pdf
Cambridge Product Management Network
 
8328958814KALYAN MATKA | MATKA RESULT | KALYAN
8328958814KALYAN MATKA | MATKA RESULT | KALYAN8328958814KALYAN MATKA | MATKA RESULT | KALYAN
8328958814KALYAN MATKA | MATKA RESULT | KALYAN
➑➌➋➑➒➎➑➑➊➍
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results
 
欧洲杯赌球-欧洲杯赌球买球官方官网-欧洲杯赌球比赛投注官网|【​网址​🎉ac55.net🎉​】
欧洲杯赌球-欧洲杯赌球买球官方官网-欧洲杯赌球比赛投注官网|【​网址​🎉ac55.net🎉​】欧洲杯赌球-欧洲杯赌球买球官方官网-欧洲杯赌球比赛投注官网|【​网址​🎉ac55.net🎉​】
欧洲杯赌球-欧洲杯赌球买球官方官网-欧洲杯赌球比赛投注官网|【​网址​🎉ac55.net🎉​】
valvereliz227
 
Virtual Leadership and the managing work
Virtual Leadership and the managing workVirtual Leadership and the managing work
Virtual Leadership and the managing work
IruniUshara1
 
The latest Heat Pump Manual from Newentide
The latest Heat Pump Manual from NewentideThe latest Heat Pump Manual from Newentide
The latest Heat Pump Manual from Newentide
JoeYangGreatMachiner
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results
 
IMG_20240615_091110.pdf dpboss guessing
IMG_20240615_091110.pdf dpboss  guessingIMG_20240615_091110.pdf dpboss  guessing
Ellen Burstyn: From Detroit Dreamer to Hollywood Legend | CIO Women Magazine
Ellen Burstyn: From Detroit Dreamer to Hollywood Legend | CIO Women MagazineEllen Burstyn: From Detroit Dreamer to Hollywood Legend | CIO Women Magazine
Ellen Burstyn: From Detroit Dreamer to Hollywood Legend | CIO Women Magazine
CIOWomenMagazine
 
Presentation by Herman Kienhuis (Curiosity VC) on Investing in AI for ABS Alu...
Presentation by Herman Kienhuis (Curiosity VC) on Investing in AI for ABS Alu...Presentation by Herman Kienhuis (Curiosity VC) on Investing in AI for ABS Alu...
Presentation by Herman Kienhuis (Curiosity VC) on Investing in AI for ABS Alu...
Herman Kienhuis
 

Recently uploaded (20)

一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理
一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理
一比一原版(QMUE毕业证书)英国爱丁堡玛格丽特女王大学毕业证文凭如何办理
 
Lukas Rycek - GreenChemForCE - project structure.pptx
Lukas Rycek - GreenChemForCE - project structure.pptxLukas Rycek - GreenChemForCE - project structure.pptx
Lukas Rycek - GreenChemForCE - project structure.pptx
 
Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...
Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...
Unlocking WhatsApp Marketing with HubSpot: Integrating Messaging into Your Ma...
 
1 Circular 003_2023 ISO 27001_2022 Transition Arrangments v3.pdf
1 Circular 003_2023 ISO 27001_2022 Transition Arrangments v3.pdf1 Circular 003_2023 ISO 27001_2022 Transition Arrangments v3.pdf
1 Circular 003_2023 ISO 27001_2022 Transition Arrangments v3.pdf
 
欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】
欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】
欧洲杯投注-欧洲杯投注外围盘口-欧洲杯投注盘口app|【​网址​🎉ac22.net🎉​】
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
 
Cover Story - China's Investment Leader - Dr. Alyce SU
Cover Story - China's Investment Leader - Dr. Alyce SUCover Story - China's Investment Leader - Dr. Alyce SU
Cover Story - China's Investment Leader - Dr. Alyce SU
 
NIMA2024 | De toegevoegde waarde van DEI en ESG in campagnes | Nathalie Lam |...
NIMA2024 | De toegevoegde waarde van DEI en ESG in campagnes | Nathalie Lam |...NIMA2024 | De toegevoegde waarde van DEI en ESG in campagnes | Nathalie Lam |...
NIMA2024 | De toegevoegde waarde van DEI en ESG in campagnes | Nathalie Lam |...
 
Science Around Us Module 2 Matter Around Us
Science Around Us Module 2 Matter Around UsScience Around Us Module 2 Matter Around Us
Science Around Us Module 2 Matter Around Us
 
list of states and organizations .pdf
list of  states  and  organizations .pdflist of  states  and  organizations .pdf
list of states and organizations .pdf
 
2024.06 CPMN Cambridge - Beyond Now-Next-Later.pdf
2024.06 CPMN Cambridge - Beyond Now-Next-Later.pdf2024.06 CPMN Cambridge - Beyond Now-Next-Later.pdf
2024.06 CPMN Cambridge - Beyond Now-Next-Later.pdf
 
8328958814KALYAN MATKA | MATKA RESULT | KALYAN
8328958814KALYAN MATKA | MATKA RESULT | KALYAN8328958814KALYAN MATKA | MATKA RESULT | KALYAN
8328958814KALYAN MATKA | MATKA RESULT | KALYAN
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
 
欧洲杯赌球-欧洲杯赌球买球官方官网-欧洲杯赌球比赛投注官网|【​网址​🎉ac55.net🎉​】
欧洲杯赌球-欧洲杯赌球买球官方官网-欧洲杯赌球比赛投注官网|【​网址​🎉ac55.net🎉​】欧洲杯赌球-欧洲杯赌球买球官方官网-欧洲杯赌球比赛投注官网|【​网址​🎉ac55.net🎉​】
欧洲杯赌球-欧洲杯赌球买球官方官网-欧洲杯赌球比赛投注官网|【​网址​🎉ac55.net🎉​】
 
Virtual Leadership and the managing work
Virtual Leadership and the managing workVirtual Leadership and the managing work
Virtual Leadership and the managing work
 
The latest Heat Pump Manual from Newentide
The latest Heat Pump Manual from NewentideThe latest Heat Pump Manual from Newentide
The latest Heat Pump Manual from Newentide
 
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan ChartSatta Matka Dpboss Kalyan Matka Results Kalyan Chart
Satta Matka Dpboss Kalyan Matka Results Kalyan Chart
 
IMG_20240615_091110.pdf dpboss guessing
IMG_20240615_091110.pdf dpboss  guessingIMG_20240615_091110.pdf dpboss  guessing
IMG_20240615_091110.pdf dpboss guessing
 
Ellen Burstyn: From Detroit Dreamer to Hollywood Legend | CIO Women Magazine
Ellen Burstyn: From Detroit Dreamer to Hollywood Legend | CIO Women MagazineEllen Burstyn: From Detroit Dreamer to Hollywood Legend | CIO Women Magazine
Ellen Burstyn: From Detroit Dreamer to Hollywood Legend | CIO Women Magazine
 
Presentation by Herman Kienhuis (Curiosity VC) on Investing in AI for ABS Alu...
Presentation by Herman Kienhuis (Curiosity VC) on Investing in AI for ABS Alu...Presentation by Herman Kienhuis (Curiosity VC) on Investing in AI for ABS Alu...
Presentation by Herman Kienhuis (Curiosity VC) on Investing in AI for ABS Alu...
 

Pert- program evaluation and review technique

  • 1. PROGRAM EVALUATION REVIEW TECHNIQUE VINCI VIVEKA
  • 2. VINCI VIVEKA •A statistical tool, used in project management • It is designed to analyze and represent the tasks involved in completing a given project. •A decision making tool designed to save time in achieving end objectives. •It is one of the techniques of scientific management. •It was developed for the U.S. Navy Special Projects Office in 1957 to support the U.S. Navy's Polaris nuclear submarine project
  • 3. PERT PERT chart is a tool that facilitates decision making. PERT is a method to analyze the involved tasks in completing a given project, especially the time needed to complete each task and to identify the minimum time needed to complete the total project. PERT is valuable to manage where multiple tasks are occurring simultaneously to reduce idleness. For this it takes into consideration three factors: 1. Time 2. Resources 3. Technical Performance Specifications. VINCI VIVEKA
  • 4. TERMINOLOGY PERT Event: a point that marks the start or completion of one or more activities. It consumes no time and uses no resources. When it marks the completion of one or more tasks, it is not “reached” (does not occur) until all of the activities leading to that event have been completed.eg- start and finish* Predecessor Event: an event that immediately precedes some other event without any other events intervening. An event can have multiple predecessor events and can be the predecessor of multiple events. Eg: A and b are predecessor of C* Successor Event: an event that immediately follows some other event without any other intervening events. An event can have multiple successor events and can be the successor of multiple events.eg: D is the successor of C*. *(refer Gantt Diagram) VINCI VIVEKA
  • 5. Optimistic Time (O): the minimum possible time required to accomplish a task, assuming everything proceeds better than is normally expected Pessimistic Time (P): the maximum possible time required to accomplish a task, assuming everything goes wrong (but excluding major catastrophes). Most Likely Time (M): the best estimate of the time required to accomplish a task, assuming everything proceeds as normal. Expected Time (TE): the best estimate of the time required to accomplish a task, accounting for the fact that things don't always proceed as normal (the implication being that the expected time is the average time the task would require if the task were repeated on a number of occasions over an extended period of time). TE = (O + 4M + P) ÷ 6 VINCI VIVEKA
  • 6. PERT Activity: the actual performance of a task which consumes time and requires resources (such as labor, materials, space, machinery). It can be understood as representing the time, effort, and resources required to move from one event to another. A PERT activity cannot be performed until the predecessor event has occurred. Eg: A,B,C,D* Float or Slack is a measure of the excess time and resources available to complete a task. It is the amount of time that a project task can be delayed without causing a delay in any subsequent tasks (free float) or the whole project (total float). Positive slack would indicate ahead of schedule; negative slack would indicate behind schedule; and zero slack would indicate on schedule. Critical Path: the longest possible continuous pathway taken from the initial event to the terminal event. It determines the total calendar time required for the project; and, therefore, any time delays along the critical path will delay the reaching of the terminal event by at least the same amount. VINCI VIVEKA
  • 7. Activity Predecessor Time Estimates Te O M P A - 2 8 6 4.00 B - 3 5 9 5.33 C A,B 4 5 7 5.17 D C 4 6 10 6.13 TE = (O + 4M + P) ÷ 6 VINCI VIVEKA
  • 8. Gantt Chart ( According to the table in previous chart) Activity On Node (AON) Diagram VINCI VIVEKA
  • 9. EARLY DURATION EARLY START FINISH A LATE SLACK LATE START FINISH VINCI VIVEKA
  • 10. In order to determine these following are the steps- EARLY FINISH [ EF ] Formula for EF= ES + Duration. Duration can be taken from the table it is represented by Te For the first activity i.e. START Early Start [ ES] =0, VINCI VIVEKA As start is a pert event its duration is zero. Therefore, for START ES=0 Duration =0 ; EF= ES + Duration => EF=0 EF of the predecessor event becomes ES of its successor. Therefore, for A ES=0 Duration=4, EF=4 For B,( as A&B both have same Predecessor i.e. START hence B---- ES=0 Duration= 5.33 EF=5.33 For C ( as A&B both are C predecessor hence we take the one with higher value) ES=5.33 Duration=5.17 EF=10.5
  • 11. For D, ES= 10.5 Duration=6.13 EF=16.63 For FINISH [as FINISH is a pert event its duration is zero] ES=16.63 Duration=0 EF=16.63 LATE START [ LS ] Formula LS=LF – DURATION In this we start with FINISH, as it is the last activity. LATE FINISH [LF ] of FINISH = its EF. Therefore, LF=EF=16.63 Duration= 0 LS=LF- Duration , Hence LS=16.63 For D, [ LS of successor event becomes LF for its predecessor event ] LF=16.63 Duration=6.13 LS=10.5 For C, LF=10.5 Duration=5.17 LS=5.33 For B, LF=5.33 Duration=5.33 LS= 0 VINCI VIVEKA
  • 12. For A, [ as C is also its successor ] LF=5.33 Duration=4 LS=1.33 For START [as A&B both are successor but we take here one with the lower value ] LF=1.33 Duration =0 LS=1.33 VINCI VIVEKA SLACK To determine the critical path we have to find whether any activity has a slack. Activity on the critical path has slack zero. Formula SLACK=LF-EF or SLACK= LS-ES For START For C LS=1.33 ES=0 SLACK=1.33 LS=5.33 ES=5.33 SLACK=0 For A For D LS=1.33 ES=0 SLACK=1.33 LS= 10.5 ES=10.5 SLACK=0 For B For FINISH LS=5.33 ES=0 SLACK=5.33 LS=1.33 ES=0 SLACK=1.33
  • 13. ES=0 DUR=0 EF=0 ES=0 DUR=4 EF=4 START A LS=1.33 SLACK=1.33 LF=1.33 LS=0 SLACK=1.33 LF=5.33 ES=0 DUR=5.33 EF=5.33 ES=5.33 DUR=5.17 EF=10.5 B C LS=0 SLACK=5.33 LF=5.33 LS=5.33 SLACK=0 LF=10.5 ES=10.5 DUR=6.13 EF=16.33 ES=16.63 DUR=0 EF=16.63 D FINISH LS=10.5 SLACK=0 LF=16.63 LS=16.63 SLACK=1.33 LF=16.63 VINCI VIVEKA
  • 14. CRITICAL PATH It is the longest continous -path way. There can be more than one critical path or the path can change. In the drawn Gantt diagram there are two alternatives to reach FINISH and adding there SLACK timing- START+A+C+D+FINISH=3.99 START+B+C+D+FINISH=7.99 Hence , the path START+B+C+D+FINISH is the longest it is the critical path, shown in the diagram in the next slide. VINCI VIVEKA
  • 15. VINCI VIVEKA CRITICAL PATH [ in red ink ]
  • 16. •PERT chart explicitly defines and makes visible dependencies (precedence relationships) between the work breakdown structure (commonly WBS) elements •PERT facilitates identification of the critical path and makes this visible •PERT facilitates identification of early start, late start, and slack for each activity •PERT provides for potentially reduced project duration due to better understanding of dependencies leading to improved overlapping of activities and tasks where feasible. •The large amount of project data can be organized & presented in diagram for use in decision making. VINCI VIVEKA
  • 17. DISADVANTAGES: •There can be potentially hundreds or thousands of activities and individual dependency relationships •PERT is not easily scalable for smaller projects •The network charts tend to be large and unwieldy requiring several pages to print and requiring special size paper •The lack of a timeframe on most PERT/CPM charts makes it harder to show status although colours can help (e.g., specific colour for completed nodes) •When the PERT/CPM charts become unwieldy, they are no longer used to manage the project. VINCI VIVEKA
  • 18. VINCI VIVEKA Prepared by: VINCI VIVEKA M.ED SCHOLAR [2012-2013] ST. XAVIER’S COLLEGE OF EDUCATION, PATNA. vivekavinci@gmail.com REFERENCE: http://en.wikipedia.org/wiki/Program_Evaluation_and_Review_Technique