2. PROGRAM (PROJECT) EVALUATION AND REVIEW
TECHNIQUE (PERT)
Program (Project) Evaluation and Review
Technique (PERT) is a project management tool
used to schedule, organize, and coordinate tasks
within a project
It is basically a method to analyze the tasks
involved in completing a given project, especially
the time needed to complete each task, and to
identify the minimum time needed to complete the
total project.
3. OBJECTIVE
The main objective of PERT is to facilitate decision
making and to reduce both the time and cost
required to complete a project.
4. PREREQUISITES
Personnel should already have a good
understanding of formal project management
terminology, tools, and techniques
PERT form template of equivalent tool (e.g.
software)
Create of project plan
Choose the most appropriate scheduling method
Select and organize a team to perform project
tasks.
5. STEPS
Identify the specific
activities and milestones.
Determine the proper
sequence of the activities.
Construct a network
diagram
Estimate the time
required for each activity.
Determine the critical
path.
Update the PERT chart
as the project progresses
6. IDENTIFY THE SPECIFIC ACTIVITIES AND
MILESTONES.
The activities are the tasks required to complete a
project. The milestones are the events marking the
beginning and the end of one or more activities. It is
helpful to list the tasks in a table that in later steps
can be expanded to include information on
sequence and duration.
7. DETERMINE THE PROPER SEQUENCE OF THE
ACTIVITIES
This step may be combined with the activity
identification step since the activity sequence is
evident for some tasks. Other tasks may require
more analysis to determine the exact order in which
they must be performed.
8. CONSTRUCT A NETWORK DIAGRAM.
Using the activity sequence information, a network
diagram can be drawn showing the sequence of the
serial and parallel activities.
Each activity represents a node in the network, and
the arrows represent the relation between activities.
Software packages simplify this step by
automatically converting tabular activity information
into a network diagram.
9. ESTIMATE THE TIME REQUIRED FOR EACH
ACTIVITY
Weeks are a commonly used unit of time for activity
completion, but any consistent unit of time can be
used. A distinguishing feature of PERT is its ability
to deal with uncertainty in activity completion time.
For each activity, the model usually includes four
time estimates:
Optimistic time
Most likely time
Pessimistic time
Expected time
10. TIMES
Optimistic time
It is generally the shortest time in which the activity
can be completed.
Most likely time – the completion time having the
highest probability. Note that this time is different
from the expected time.
Pessimistic time – the longest time that an activity
might require.
Expected time = (Optimistic + 4 x Most likely +
Pessimistic) / 6
This expected time may be displayed on the
network diagram.
11. DETERMINE THE CRITICAL PATH.
The critical path is determined by adding the times
for the activities in each sequence and determining
the longest path in the project.
The critical path determines the total calendar time
required for the project.
12. UPDATE THE PERT CHART AS THE PROJECT
PROGRESSES.
Make adjustments in the PERT chart as the project
progresses.
As the project unfolds, the estimated times can be
replaced with actual times.
In cases where there are delays, additional
resources may be needed to stay on schedule and
the PERT chart may be modified to reflect the new
situation.
13. BENEFITS OF PERT
PERT is useful because it provides the following
information:
Expected project completion time;
Probability of completion before a specified date
The critical path activities that directly impact the
completion time;
The activities that have slack time and that can be
lend resources to critical path activities;
Activity start and end date.
14. EXAMPLES – CASE STUDY
In the following example, the Project manager
knows the succession of the project activities and
the optimistic, pessimistic and most likely time (in
weeks) for the following activities:
15.
16.
17.
18.
19. GANTT CHART
A Gantt chart is a type of bar chart that illustrates
a project schedule, named after its inventor, Henry
Gantt (1861–1919), who designed such a chart
around the years 1910–1915.
Modern Gantt charts also show the dependency
relationships between activities and current
schedule status.
20. DEFINITION
A Gantt chart is a type of bar chart that illustrates a
project schedule.
This chart lists the tasks to be performed on the
vertical axis, and time intervals on the horizontal
axis.
The width of the horizontal bars in the graph shows
the duration of each activity.
Gantt charts illustrate the start and finish dates of
the terminal elements and summary elements of
a project
21.
22. ELEMENTS OF GANTT CHART
Task list: Runs vertically down the left of the Gantt
chart to describe project work and may be
organized into groups and subgroups
Timeline: Runs horizontally across the top of the
Gantt chart and shows months, weeks, days, and
years
Dateline: A vertical line that highlights the current
date on the Gantt chart
Bars: Horizontal markers on the right side of the
Gantt chart that represent tasks and show
progress, duration, and start and end dates
23. ELEMENTS OF GANTT CHART
Milestones: The diamonds that call out major
events, dates, decisions, and deliverables
Dependencies: The lines that connect tasks that
need to happen in a certain order
Progress: Shows how far along work is and may
be indicated by % Complete and/or bar shading
Resource assigned: Indicates the person or team
responsible for completing a task
24.
25. USES OF GANTT CHART
To show the current schedule status
To measure task duration in the project
To represent cost, time and scope of the project
A useful tool for planning and scheduling projects
To plan how long a project should take
Lays out the order in which the tasks need to be carried
out
Modern Gantt chart software provides dependencies
between tasks
To monitor a project’s progress
To visualize immediately what should have been
achieved at any point in time
To assist in taking remedial action to bring the project
back on course , if required
26. ADVANTAGES OF GANTT CHART
It helps in planning and monitoring the work of
project
Time is explicitly expressed in the chart
All tasks are visible at a glance in relation to other
Deadlines are depicted in the chart
It organizes your thoughts.
It demonstrates that you know what you’re
doing.
It (should) help you to set realistic time frames.
27. DISADVANTAGES OF GANTT CHART
They can become extraordinarily complex.
The size of the bar does not indicate the amount of
work
They need to be constantly updated.
Difficult to see on one sheet of paper.
28. REFERENCE
Vati J (20113),principles and practice of nursing management
and administration ,First edt,Jay Pee publishers , New delhi :
p 184-188
Archibald & Villoria, "Network-Based Management Systems
(PERT/CPM)," John Wiley & Sons, 1967
Cagle, Ronald B. Blueprint for project recovery: a project
management guide : the complete process for getting derailed
projects back on the track. New York : AMACOM, 2002
Clet, Étienne and Henri-Pierre Maders. Comment manager un
projet. 2nd ed. Paris: Éditions d'Organisation, 2005.
Denis Lock, Managementul de proiect. Ed. CODECS,
Bucureşti, 2000
DeWitte, "Manpower Leveling of PERT Networks," Data
Processing for Science/Engineering, March-April 1964
29. RESEARCH STUDY
Title: Application and impact of Gantt chart in task
based team English learning
Author :He Chen , School of Foreign Studies,
Northwest University of Politics and Law, xi'an,
710122, (CHINA)
Results
By using the Gantt chart they can conclude and
analyze the progress and quality of learning, realize
the problems and shortcomings in learning, and
summary solutions.
30. RESEARCH REPORT
Title: Application of PERT Technique in Health
Programme Monitoring and Control
Author: Susmit Jain, Indian Institute of Health
Managment Research
Results
This technique helps in answering the expected
time of completion of projects, identifying the jobs
and activities and their start and finish times, the
effect of delay of certain activities, what resources
are required at various points of time, revising and
rescheduling the projects and what additional
resources are required, etc.