SlideShare a Scribd company logo
Tanoj patidar
1ST YEAR M.SC. NURSING
PROGRAMME EVALUATION
REVIEW TECHNIQUE (PERT)
PROGRAMME EVALUATION REVIEW TECHNIQUE
(PERT)
OBJECTIVE:
• To understand the formula, the use and the benefits of Program, Evaluation, and
Review Technic (PERT) analysis.
INTRODUCTION:
PERT is a method of analysing the tasks involved in completing a given project,
especially the time needed to complete each task, and to identify the minimum
time needed to complete the total project. PERT was developed primarily to
simplify the planning and scheduling of large and complex projects.
Developed by the US Navy for the planning and control of the
Polaris missile program. The emphasis was on completing the program in the
shortest possible time.
DEFINITION:
PERT is a work model devised to complete the project work in time. It analyses
the actual work time required to complete a task.
CONCEPT AND MEANING:
PERT is a very famous project model that has found its use in various
professions, including nursing.
 This model helps in judging the time required in completing an activity.
 Nurse administrators can use this model to delegate and assign the work
schedule to the nurses in a hospital.
 It not only evidences the cost effectiveness of nursing care but also has
great impact on reducing the expenditure by the patient.
This model helps to reduce the patient’s hospital stay by judging beforehand the
actual care time, manpower, money and the material required.
Therefore, following this model helps to prevent waste of time, money and
material, benefiting the patient and the hospital management.
WHEN WE USE PERT?
PERT is used when activity times are uncertain.
 Determine the duration of the project.
 Decision making under risk.
PERT INCLUDES:
steps or activities.
It Is a model for project management designed to analyse and represent the
task involved in completing a given project.
COMPONENTS OF PERT MODEL:
Every activity consume time and needs adequate resources such as manpower,
material, space and machinery to change or move one event to other.
Predecessor event – It is an event that precedes some other event, it can be
single or multiple.
Successor events – It is an event that immediately follows some other events,
it can have single multiple successor events.
Optimistic Time (O) – It is the minimum possible time required to complete
the task anticipating that every event has occurred better than usually expected.
Pessimistic Time (P) - This means the maximum possible time required to
complete the given task, expecting or assuming everything goes wrong except
the main catastrophes.
Most likely Time (M) – The actual and the best time required to complete the
task assuming everything goes in a usual way.
Expected time or the very best time (TH) – The accurate or the actual time
required to complete the task, it is the most reliable and valid time estimated to
complete a task. It can be calculated using the following relation
TH = (O + 4M – P) ÷ 6
e.g. TH = (5min + 4X 10 min – 15 min) ÷ 6 = 5 min
Float or slack time – it is the amount of time that can be floated without
causing delay in the total completion of the work.
Critical paths – it is the longest possible and the actual total time required to
complete the full task. It is otherwise called as total calendar time.
Critical total float activity – it is an activity that has total float equal to zero.
No float time is required in the critical path.
Lead time – this refers to the time taken by the predecessor to complete the
task. In this there is sufficient time for the subsequent activities that can follow
the predecessor.
Lag time – the earliest time taken by the successor event to take place, which
follows the specific PERT activity
PERT CHART:
A PERT chart is a graphical representation of the activities of a project, showing
the sequence that has to be performed continuously.
therefore it saves time, energy and material.
PURPOSES:
To schedule the project.
To manage the time.
e the work.
STEPS IN THE PERT PLANNING PROCESS:
PERT involves the following steps
IDENTIFY THE SPECIFIC ACTIVITIES AND MILESTONE
e tasks in a table.
DETERMINE THE PROPER SEQUENCE OF THE ACTIVITY
identification step.
-Since the activity sequence is evident for some tasks.
asks may require more analysis.
-To determine the exact order in which they must be performed.
CONSTRUCT A NETWORK DIAGRAM
-A network diagram can be drawn showing the sequence of the serial
and parallel activities.
Each activity represents: A node in the network,
The arrows represent: The relation between activities.
re packages simplify this task: By automatically converting tabular
activity information into a network diagram.
ESTIMATE THE TIME REQURIED FOR EACH ACTIVITY
distinguishing feature of PERT: Its ability to deal with uncertainty in
activity completion time.
Optimistic time(O)- The shortest time in which the activity can be completed.
Most likely time(M)- The completion time having the highest probability.
Pessimistic time (P)- the maximum possible time required to accomplish a
task, assuming everything goes wrong (but excluding major catastrophes).
Estimated Time(TE)- The best estimate of the time required to accomplish a
task, accounting for the fact that things don't always proceed as normal. TE = (O
+ 4M + P) ÷ 6
DETERMINE THE CRITICAL PATH
-Determined by adding the times for the activities in each sequence.
-Determining the longest path in the project.
time required for the project.
total project time does not change.
– critical path activity can be delayed without
the project is referred to as a slack time.
ES – Earliest Start time
EF - Earliest Finish time
LS – Latest Start time
LF - Latest Finish time
variances in the completion times of the activities in the critical path.
time for the activities in the critical path.
Project Crashing.
UPDATE THE PERT CHART AS THE PROJECT PROGRESSES
-Additional resources may be needed to stay on schedule.
-The PERT chart may be modified to reflect the new situation.
BENEFITS OF PERT:
activities.
USES:
Nurse managers use the PERT system for controlling
the program.
– looking.
PERT is generally used for complicated and extensive projects or programs.
• personnel staffing reports.
• overtime reports.
• monthly financial reports and others.
evaluate the use of people and money as a part of the controlling process.
ADVANTAGES:
project.
plans, schedules and time and cost – performance.
focusing management
attention i.e. most constraining on the schedule.
l changes on overall schedules.
between the WBS elements.
of dependencies leading to improved overlapping of activities and tasking where
feasible.
DISADVANTAGES:
dependency relationship.
iring several pages to
print and requiring special size paper.
makes it harder to show status although colours can help (e.g. specific colour for
completed nodes)
(Critical path method) charts become unwieldy, they
are no longer used to manage the project.
LIMITATIONS:
In other cases, if the person or group performing the activity estimates the time
there may be bias in the estimate.
– estimated, PERT assumes a beta
distribution for these time estimates, but the actual distribution may be different.
ds, PERT assumes that the
probability distribution of the project completion time is the same as the that of
the critical path.
BY TANOJ PATIDAR
MSc NURSING

More Related Content

What's hot

Gantt chart
Gantt chartGantt chart
Gantt chart
Tanoj Patidar
 
Cost benefit analysis
Cost benefit analysisCost benefit analysis
Cost benefit analysis
Harsh Rastogi
 
Budgeting
BudgetingBudgeting
Budgeting
Monika Kanwar
 
Budgeting in nursing
Budgeting in nursingBudgeting in nursing
Budgeting in nursing
Pratibha Srivastava
 
Job description
Job descriptionJob description
Job description
praveenPatel57
 
Staffing- Nursing Management
Staffing- Nursing ManagementStaffing- Nursing Management
Staffing philosophy , norms
Staffing philosophy , normsStaffing philosophy , norms
Staffing philosophy , norms
Princy Francis M
 
Budget for hospital and nursing college
Budget for hospital and nursing collegeBudget for hospital and nursing college
Budget for hospital and nursing college
Devangi Sharma
 
Introduction to management in nursing
Introduction to management in nursingIntroduction to management in nursing
Introduction to management in nursing
DR .PALLAVI PATHANIA
 
Material management in nursing
Material management in nursingMaterial management in nursing
Material management in nursing
Drisya Nidhin
 
PERT & Gantt Chart
PERT & Gantt Chart PERT & Gantt Chart
PERT & Gantt Chart
Anju George
 
Recruitment&selection of nursing personnel
Recruitment&selection of nursing personnelRecruitment&selection of nursing personnel
Recruitment&selection of nursing personnel
AHMED ZINHOM
 
Theories of management
Theories of managementTheories of management
Theories of management
Harsh Rastogi
 
Role of nursing personnel in material management
Role of nursing personnel in material managementRole of nursing personnel in material management
Role of nursing personnel in material management
Indra Mani Mishra
 
continuing education
continuing education continuing education
continuing education
praveenPatel57
 
Staff development and welfare
Staff development and welfareStaff development and welfare
Staff development and welfare
KULDEEP VYAS
 
Performance appraisal- Nursing Management
Performance appraisal- Nursing ManagementPerformance appraisal- Nursing Management
Performance appraisal- Nursing Management
Sherwood College of Nursing, Barabanki, Uttar Pradesh
 
Recruitment (Nursing Management)
Recruitment (Nursing Management)Recruitment (Nursing Management)
Recruitment (Nursing Management)
Uttam Vaishnav
 
Role of Nurse as a Manager.pptx
Role of Nurse as a Manager.pptxRole of Nurse as a Manager.pptx
Role of Nurse as a Manager.pptx
Ramar GURUSAMY
 

What's hot (20)

Gantt chart
Gantt chartGantt chart
Gantt chart
 
Cost benefit analysis
Cost benefit analysisCost benefit analysis
Cost benefit analysis
 
Budgeting
BudgetingBudgeting
Budgeting
 
Budgeting in nursing
Budgeting in nursingBudgeting in nursing
Budgeting in nursing
 
Job description
Job descriptionJob description
Job description
 
Planning of Nursing Unit
Planning of Nursing UnitPlanning of Nursing Unit
Planning of Nursing Unit
 
Staffing- Nursing Management
Staffing- Nursing ManagementStaffing- Nursing Management
Staffing- Nursing Management
 
Staffing philosophy , norms
Staffing philosophy , normsStaffing philosophy , norms
Staffing philosophy , norms
 
Budget for hospital and nursing college
Budget for hospital and nursing collegeBudget for hospital and nursing college
Budget for hospital and nursing college
 
Introduction to management in nursing
Introduction to management in nursingIntroduction to management in nursing
Introduction to management in nursing
 
Material management in nursing
Material management in nursingMaterial management in nursing
Material management in nursing
 
PERT & Gantt Chart
PERT & Gantt Chart PERT & Gantt Chart
PERT & Gantt Chart
 
Recruitment&selection of nursing personnel
Recruitment&selection of nursing personnelRecruitment&selection of nursing personnel
Recruitment&selection of nursing personnel
 
Theories of management
Theories of managementTheories of management
Theories of management
 
Role of nursing personnel in material management
Role of nursing personnel in material managementRole of nursing personnel in material management
Role of nursing personnel in material management
 
continuing education
continuing education continuing education
continuing education
 
Staff development and welfare
Staff development and welfareStaff development and welfare
Staff development and welfare
 
Performance appraisal- Nursing Management
Performance appraisal- Nursing ManagementPerformance appraisal- Nursing Management
Performance appraisal- Nursing Management
 
Recruitment (Nursing Management)
Recruitment (Nursing Management)Recruitment (Nursing Management)
Recruitment (Nursing Management)
 
Role of Nurse as a Manager.pptx
Role of Nurse as a Manager.pptxRole of Nurse as a Manager.pptx
Role of Nurse as a Manager.pptx
 

Similar to PERT (Program evaluation review technique)

Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Zulfiquer Ahmed Amin
 
Programme evaluation & review technique (pert)
Programme evaluation & review technique (pert)Programme evaluation & review technique (pert)
Programme evaluation & review technique (pert)
AnkitaKadam20
 
Pert n gantt
Pert n gantt Pert n gantt
Pert n gantt
PREETHYDAVID
 
Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Abhishek Pachisia
 
Pert and mbo
Pert and mboPert and mbo
Pert and mbo
angel90thomas
 
or-pert
or-pertor-pert
or-pert
Rohit Raina
 
PERT.pptx
PERT.pptxPERT.pptx
PERT.pptx
Snehal Athawale
 
Pert and its applications
Pert and its applicationsPert and its applications
Pert and its applications
Amrit Mty
 
Pert Cpm Nis
Pert   Cpm NisPert   Cpm Nis
Pert Cpm Nis
Naveed Salman
 
Program_Evaluation_and_Review_Technique.pptx
Program_Evaluation_and_Review_Technique.pptxProgram_Evaluation_and_Review_Technique.pptx
Program_Evaluation_and_Review_Technique.pptx
mamtabisht10
 
PERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSPERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLS
Zulfiquer Ahmed Amin
 
project management-cpm and pert methods for managers
project management-cpm and pert methods for managersproject management-cpm and pert methods for managers
project management-cpm and pert methods for managers
Naganna Chetty
 
Program Evaluation and Review Technique
Program Evaluation and Review TechniqueProgram Evaluation and Review Technique
Program Evaluation and Review Technique
Raymund Sanchez
 
Cpm n pert
Cpm n pertCpm n pert
Cpm n pert
Sheetu Goel
 
S pert cpm
S pert cpmS pert cpm
S pert cpm
Sujith Bhaskar .R
 
CPM AND PERT
CPM AND PERTCPM AND PERT
CPM AND PERT
SimranGrewal33
 
time mamangement.ppt
time mamangement.ppttime mamangement.ppt
time mamangement.ppt
Madhusha15
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
BetshaTizazu2
 
PERT Ghant chart and bench marking with application to nursing
PERT Ghant chart and bench marking with application to nursingPERT Ghant chart and bench marking with application to nursing
PERT Ghant chart and bench marking with application to nursing
Hariasha
 
Programme Evaluation and Review Technique
Programme Evaluation and Review TechniqueProgramme Evaluation and Review Technique
Programme Evaluation and Review Technique
DrAsifMohammad
 

Similar to PERT (Program evaluation review technique) (20)

Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
 
Programme evaluation & review technique (pert)
Programme evaluation & review technique (pert)Programme evaluation & review technique (pert)
Programme evaluation & review technique (pert)
 
Pert n gantt
Pert n gantt Pert n gantt
Pert n gantt
 
Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)
 
Pert and mbo
Pert and mboPert and mbo
Pert and mbo
 
or-pert
or-pertor-pert
or-pert
 
PERT.pptx
PERT.pptxPERT.pptx
PERT.pptx
 
Pert and its applications
Pert and its applicationsPert and its applications
Pert and its applications
 
Pert Cpm Nis
Pert   Cpm NisPert   Cpm Nis
Pert Cpm Nis
 
Program_Evaluation_and_Review_Technique.pptx
Program_Evaluation_and_Review_Technique.pptxProgram_Evaluation_and_Review_Technique.pptx
Program_Evaluation_and_Review_Technique.pptx
 
PERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSPERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLS
 
project management-cpm and pert methods for managers
project management-cpm and pert methods for managersproject management-cpm and pert methods for managers
project management-cpm and pert methods for managers
 
Program Evaluation and Review Technique
Program Evaluation and Review TechniqueProgram Evaluation and Review Technique
Program Evaluation and Review Technique
 
Cpm n pert
Cpm n pertCpm n pert
Cpm n pert
 
S pert cpm
S pert cpmS pert cpm
S pert cpm
 
CPM AND PERT
CPM AND PERTCPM AND PERT
CPM AND PERT
 
time mamangement.ppt
time mamangement.ppttime mamangement.ppt
time mamangement.ppt
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
 
PERT Ghant chart and bench marking with application to nursing
PERT Ghant chart and bench marking with application to nursingPERT Ghant chart and bench marking with application to nursing
PERT Ghant chart and bench marking with application to nursing
 
Programme Evaluation and Review Technique
Programme Evaluation and Review TechniqueProgramme Evaluation and Review Technique
Programme Evaluation and Review Technique
 

More from Tanoj Patidar

Systemic changes during antenatal period by tanoj patidar msc nursing
Systemic changes during antenatal period by tanoj patidar msc nursingSystemic changes during antenatal period by tanoj patidar msc nursing
Systemic changes during antenatal period by tanoj patidar msc nursing
Tanoj Patidar
 
ANECDOTAL RECORD/ REPORT
ANECDOTAL RECORD/ REPORTANECDOTAL RECORD/ REPORT
ANECDOTAL RECORD/ REPORT
Tanoj Patidar
 
Inventory
InventoryInventory
Inventory
Tanoj Patidar
 
Job description
Job descriptionJob description
Job description
Tanoj Patidar
 
GROUP DYNAMICS
GROUP DYNAMICSGROUP DYNAMICS
GROUP DYNAMICS
Tanoj Patidar
 
Research critiquing (Nursing Research) Critiques
Research critiquing (Nursing Research) CritiquesResearch critiquing (Nursing Research) Critiques
Research critiquing (Nursing Research) Critiques
Tanoj Patidar
 
Cumulative record for students
Cumulative record for studentsCumulative record for students
Cumulative record for students
Tanoj Patidar
 
procedure checklist for bedmaking.
procedure checklist for bedmaking.procedure checklist for bedmaking.
procedure checklist for bedmaking.
Tanoj Patidar
 
Oxygen administration
Oxygen administrationOxygen administration
Oxygen administration
Tanoj Patidar
 
Antepartum hemorrhage BY TANOJ PATIDAR
Antepartum hemorrhage BY TANOJ PATIDARAntepartum hemorrhage BY TANOJ PATIDAR
Antepartum hemorrhage BY TANOJ PATIDAR
Tanoj Patidar
 
Multiple pregnancy by tanoj patidar
Multiple pregnancy by tanoj patidarMultiple pregnancy by tanoj patidar
Multiple pregnancy by tanoj patidar
Tanoj Patidar
 
Immunization
ImmunizationImmunization
Immunization
Tanoj Patidar
 
Fracture
FractureFracture
Fracture
Tanoj Patidar
 
Personality test
Personality testPersonality test
Personality test
Tanoj Patidar
 
Image of nursing by Tanoj Patidar Msc Nursing (MSN)
Image of nursing by Tanoj Patidar Msc Nursing (MSN)Image of nursing by Tanoj Patidar Msc Nursing (MSN)
Image of nursing by Tanoj Patidar Msc Nursing (MSN)
Tanoj Patidar
 
Homeostasis mechanism
Homeostasis mechanismHomeostasis mechanism
Homeostasis mechanism
Tanoj Patidar
 
Evidence based practice model
Evidence based practice modelEvidence based practice model
Evidence based practice model
Tanoj Patidar
 
Group dynamics
Group dynamicsGroup dynamics
Group dynamics
Tanoj Patidar
 
Evidence based practice by Tanoj Patidar MSc Nursing (MSN)
Evidence based practice by Tanoj Patidar MSc Nursing (MSN)Evidence based practice by Tanoj Patidar MSc Nursing (MSN)
Evidence based practice by Tanoj Patidar MSc Nursing (MSN)
Tanoj Patidar
 
Electrolyte imbalance
Electrolyte imbalanceElectrolyte imbalance
Electrolyte imbalance
Tanoj Patidar
 

More from Tanoj Patidar (20)

Systemic changes during antenatal period by tanoj patidar msc nursing
Systemic changes during antenatal period by tanoj patidar msc nursingSystemic changes during antenatal period by tanoj patidar msc nursing
Systemic changes during antenatal period by tanoj patidar msc nursing
 
ANECDOTAL RECORD/ REPORT
ANECDOTAL RECORD/ REPORTANECDOTAL RECORD/ REPORT
ANECDOTAL RECORD/ REPORT
 
Inventory
InventoryInventory
Inventory
 
Job description
Job descriptionJob description
Job description
 
GROUP DYNAMICS
GROUP DYNAMICSGROUP DYNAMICS
GROUP DYNAMICS
 
Research critiquing (Nursing Research) Critiques
Research critiquing (Nursing Research) CritiquesResearch critiquing (Nursing Research) Critiques
Research critiquing (Nursing Research) Critiques
 
Cumulative record for students
Cumulative record for studentsCumulative record for students
Cumulative record for students
 
procedure checklist for bedmaking.
procedure checklist for bedmaking.procedure checklist for bedmaking.
procedure checklist for bedmaking.
 
Oxygen administration
Oxygen administrationOxygen administration
Oxygen administration
 
Antepartum hemorrhage BY TANOJ PATIDAR
Antepartum hemorrhage BY TANOJ PATIDARAntepartum hemorrhage BY TANOJ PATIDAR
Antepartum hemorrhage BY TANOJ PATIDAR
 
Multiple pregnancy by tanoj patidar
Multiple pregnancy by tanoj patidarMultiple pregnancy by tanoj patidar
Multiple pregnancy by tanoj patidar
 
Immunization
ImmunizationImmunization
Immunization
 
Fracture
FractureFracture
Fracture
 
Personality test
Personality testPersonality test
Personality test
 
Image of nursing by Tanoj Patidar Msc Nursing (MSN)
Image of nursing by Tanoj Patidar Msc Nursing (MSN)Image of nursing by Tanoj Patidar Msc Nursing (MSN)
Image of nursing by Tanoj Patidar Msc Nursing (MSN)
 
Homeostasis mechanism
Homeostasis mechanismHomeostasis mechanism
Homeostasis mechanism
 
Evidence based practice model
Evidence based practice modelEvidence based practice model
Evidence based practice model
 
Group dynamics
Group dynamicsGroup dynamics
Group dynamics
 
Evidence based practice by Tanoj Patidar MSc Nursing (MSN)
Evidence based practice by Tanoj Patidar MSc Nursing (MSN)Evidence based practice by Tanoj Patidar MSc Nursing (MSN)
Evidence based practice by Tanoj Patidar MSc Nursing (MSN)
 
Electrolyte imbalance
Electrolyte imbalanceElectrolyte imbalance
Electrolyte imbalance
 

Recently uploaded

Navigating Women's Health: Understanding Prenatal Care and Beyond
Navigating Women's Health: Understanding Prenatal Care and BeyondNavigating Women's Health: Understanding Prenatal Care and Beyond
Navigating Women's Health: Understanding Prenatal Care and Beyond
Aboud Health Group
 
Dimensions of Healthcare Quality
Dimensions of Healthcare QualityDimensions of Healthcare Quality
Dimensions of Healthcare Quality
Naeemshahzad51
 
Navigating Challenges: Mental Health, Legislation, and the Prison System in B...
Navigating Challenges: Mental Health, Legislation, and the Prison System in B...Navigating Challenges: Mental Health, Legislation, and the Prison System in B...
Navigating Challenges: Mental Health, Legislation, and the Prison System in B...
Guillermo Rivera
 
GURGAON Call Girls ❤8901183002❤ #ℂALL# #gIRLS# In GURGAON ₹,2500 Cash Payment...
GURGAON Call Girls ❤8901183002❤ #ℂALL# #gIRLS# In GURGAON ₹,2500 Cash Payment...GURGAON Call Girls ❤8901183002❤ #ℂALL# #gIRLS# In GURGAON ₹,2500 Cash Payment...
GURGAON Call Girls ❤8901183002❤ #ℂALL# #gIRLS# In GURGAON ₹,2500 Cash Payment...
ranishasharma67
 
Medical Technology Tackles New Health Care Demand - Research Report - March 2...
Medical Technology Tackles New Health Care Demand - Research Report - March 2...Medical Technology Tackles New Health Care Demand - Research Report - March 2...
Medical Technology Tackles New Health Care Demand - Research Report - March 2...
pchutichetpong
 
Neuro Saphirex Cranial Brochure
Neuro Saphirex Cranial BrochureNeuro Saphirex Cranial Brochure
Neuro Saphirex Cranial Brochure
RXOOM Healthcare Pvt. Ltd. ​
 
Deep Leg Vein Thrombosis (DVT): Meaning, Causes, Symptoms, Treatment, and Mor...
Deep Leg Vein Thrombosis (DVT): Meaning, Causes, Symptoms, Treatment, and Mor...Deep Leg Vein Thrombosis (DVT): Meaning, Causes, Symptoms, Treatment, and Mor...
Deep Leg Vein Thrombosis (DVT): Meaning, Causes, Symptoms, Treatment, and Mor...
The Lifesciences Magazine
 
Nursing Care of Client With Acute And Chronic Renal Failure.ppt
Nursing Care of Client With Acute And Chronic Renal Failure.pptNursing Care of Client With Acute And Chronic Renal Failure.ppt
Nursing Care of Client With Acute And Chronic Renal Failure.ppt
Rommel Luis III Israel
 
CHAPTER 1 SEMESTER V PREVENTIVE-PEDIATRICS.pdf
CHAPTER 1 SEMESTER V PREVENTIVE-PEDIATRICS.pdfCHAPTER 1 SEMESTER V PREVENTIVE-PEDIATRICS.pdf
CHAPTER 1 SEMESTER V PREVENTIVE-PEDIATRICS.pdf
Sachin Sharma
 
Tips for Pet Care in winters How to take care of pets.
Tips for Pet Care in winters How to take care of pets.Tips for Pet Care in winters How to take care of pets.
Tips for Pet Care in winters How to take care of pets.
Dinesh Chauhan
 
Introduction to Forensic Pathology course
Introduction to Forensic Pathology courseIntroduction to Forensic Pathology course
Introduction to Forensic Pathology course
fprxsqvnz5
 
The Importance of Community Nursing Care.pdf
The Importance of Community Nursing Care.pdfThe Importance of Community Nursing Care.pdf
The Importance of Community Nursing Care.pdf
AD Healthcare
 
The Importance of COVID-19 PCR Tests for Travel in 2024.pptx
The Importance of COVID-19 PCR Tests for Travel in 2024.pptxThe Importance of COVID-19 PCR Tests for Travel in 2024.pptx
The Importance of COVID-19 PCR Tests for Travel in 2024.pptx
Global Travel Clinics
 
NKTI Annual Report - Annual Report FY 2022
NKTI Annual Report - Annual Report FY 2022NKTI Annual Report - Annual Report FY 2022
NKTI Annual Report - Annual Report FY 2022
nktiacc3
 
ventilator, child on ventilator, newborn
ventilator, child on ventilator, newbornventilator, child on ventilator, newborn
ventilator, child on ventilator, newborn
Pooja Rani
 
Jaipur ❤cALL gIRLS 89O1183002 ❤ℂall Girls IN JaiPuR ESCORT SERVICE
Jaipur ❤cALL gIRLS 89O1183002 ❤ℂall Girls IN JaiPuR ESCORT SERVICEJaipur ❤cALL gIRLS 89O1183002 ❤ℂall Girls IN JaiPuR ESCORT SERVICE
Jaipur ❤cALL gIRLS 89O1183002 ❤ℂall Girls IN JaiPuR ESCORT SERVICE
ranishasharma67
 
一比一原版纽约大学毕业证(NYU毕业证)成绩单留信认证
一比一原版纽约大学毕业证(NYU毕业证)成绩单留信认证一比一原版纽约大学毕业证(NYU毕业证)成绩单留信认证
一比一原版纽约大学毕业证(NYU毕业证)成绩单留信认证
o6ov5dqmf
 
VVIP Dehradun Girls 9719300533 Heat-bake { Dehradun } Genteel ℂall Serviℂe By...
VVIP Dehradun Girls 9719300533 Heat-bake { Dehradun } Genteel ℂall Serviℂe By...VVIP Dehradun Girls 9719300533 Heat-bake { Dehradun } Genteel ℂall Serviℂe By...
VVIP Dehradun Girls 9719300533 Heat-bake { Dehradun } Genteel ℂall Serviℂe By...
rajkumar669520
 
定制(wsu毕业证书)美国华盛顿州立大学毕业证学位证书实拍图原版一模一样
定制(wsu毕业证书)美国华盛顿州立大学毕业证学位证书实拍图原版一模一样定制(wsu毕业证书)美国华盛顿州立大学毕业证学位证书实拍图原版一模一样
定制(wsu毕业证书)美国华盛顿州立大学毕业证学位证书实拍图原版一模一样
khvdq584
 
CHAPTER 1 SEMESTER V - ROLE OF PEADIATRIC NURSE.pdf
CHAPTER 1 SEMESTER V - ROLE OF PEADIATRIC NURSE.pdfCHAPTER 1 SEMESTER V - ROLE OF PEADIATRIC NURSE.pdf
CHAPTER 1 SEMESTER V - ROLE OF PEADIATRIC NURSE.pdf
Sachin Sharma
 

Recently uploaded (20)

Navigating Women's Health: Understanding Prenatal Care and Beyond
Navigating Women's Health: Understanding Prenatal Care and BeyondNavigating Women's Health: Understanding Prenatal Care and Beyond
Navigating Women's Health: Understanding Prenatal Care and Beyond
 
Dimensions of Healthcare Quality
Dimensions of Healthcare QualityDimensions of Healthcare Quality
Dimensions of Healthcare Quality
 
Navigating Challenges: Mental Health, Legislation, and the Prison System in B...
Navigating Challenges: Mental Health, Legislation, and the Prison System in B...Navigating Challenges: Mental Health, Legislation, and the Prison System in B...
Navigating Challenges: Mental Health, Legislation, and the Prison System in B...
 
GURGAON Call Girls ❤8901183002❤ #ℂALL# #gIRLS# In GURGAON ₹,2500 Cash Payment...
GURGAON Call Girls ❤8901183002❤ #ℂALL# #gIRLS# In GURGAON ₹,2500 Cash Payment...GURGAON Call Girls ❤8901183002❤ #ℂALL# #gIRLS# In GURGAON ₹,2500 Cash Payment...
GURGAON Call Girls ❤8901183002❤ #ℂALL# #gIRLS# In GURGAON ₹,2500 Cash Payment...
 
Medical Technology Tackles New Health Care Demand - Research Report - March 2...
Medical Technology Tackles New Health Care Demand - Research Report - March 2...Medical Technology Tackles New Health Care Demand - Research Report - March 2...
Medical Technology Tackles New Health Care Demand - Research Report - March 2...
 
Neuro Saphirex Cranial Brochure
Neuro Saphirex Cranial BrochureNeuro Saphirex Cranial Brochure
Neuro Saphirex Cranial Brochure
 
Deep Leg Vein Thrombosis (DVT): Meaning, Causes, Symptoms, Treatment, and Mor...
Deep Leg Vein Thrombosis (DVT): Meaning, Causes, Symptoms, Treatment, and Mor...Deep Leg Vein Thrombosis (DVT): Meaning, Causes, Symptoms, Treatment, and Mor...
Deep Leg Vein Thrombosis (DVT): Meaning, Causes, Symptoms, Treatment, and Mor...
 
Nursing Care of Client With Acute And Chronic Renal Failure.ppt
Nursing Care of Client With Acute And Chronic Renal Failure.pptNursing Care of Client With Acute And Chronic Renal Failure.ppt
Nursing Care of Client With Acute And Chronic Renal Failure.ppt
 
CHAPTER 1 SEMESTER V PREVENTIVE-PEDIATRICS.pdf
CHAPTER 1 SEMESTER V PREVENTIVE-PEDIATRICS.pdfCHAPTER 1 SEMESTER V PREVENTIVE-PEDIATRICS.pdf
CHAPTER 1 SEMESTER V PREVENTIVE-PEDIATRICS.pdf
 
Tips for Pet Care in winters How to take care of pets.
Tips for Pet Care in winters How to take care of pets.Tips for Pet Care in winters How to take care of pets.
Tips for Pet Care in winters How to take care of pets.
 
Introduction to Forensic Pathology course
Introduction to Forensic Pathology courseIntroduction to Forensic Pathology course
Introduction to Forensic Pathology course
 
The Importance of Community Nursing Care.pdf
The Importance of Community Nursing Care.pdfThe Importance of Community Nursing Care.pdf
The Importance of Community Nursing Care.pdf
 
The Importance of COVID-19 PCR Tests for Travel in 2024.pptx
The Importance of COVID-19 PCR Tests for Travel in 2024.pptxThe Importance of COVID-19 PCR Tests for Travel in 2024.pptx
The Importance of COVID-19 PCR Tests for Travel in 2024.pptx
 
NKTI Annual Report - Annual Report FY 2022
NKTI Annual Report - Annual Report FY 2022NKTI Annual Report - Annual Report FY 2022
NKTI Annual Report - Annual Report FY 2022
 
ventilator, child on ventilator, newborn
ventilator, child on ventilator, newbornventilator, child on ventilator, newborn
ventilator, child on ventilator, newborn
 
Jaipur ❤cALL gIRLS 89O1183002 ❤ℂall Girls IN JaiPuR ESCORT SERVICE
Jaipur ❤cALL gIRLS 89O1183002 ❤ℂall Girls IN JaiPuR ESCORT SERVICEJaipur ❤cALL gIRLS 89O1183002 ❤ℂall Girls IN JaiPuR ESCORT SERVICE
Jaipur ❤cALL gIRLS 89O1183002 ❤ℂall Girls IN JaiPuR ESCORT SERVICE
 
一比一原版纽约大学毕业证(NYU毕业证)成绩单留信认证
一比一原版纽约大学毕业证(NYU毕业证)成绩单留信认证一比一原版纽约大学毕业证(NYU毕业证)成绩单留信认证
一比一原版纽约大学毕业证(NYU毕业证)成绩单留信认证
 
VVIP Dehradun Girls 9719300533 Heat-bake { Dehradun } Genteel ℂall Serviℂe By...
VVIP Dehradun Girls 9719300533 Heat-bake { Dehradun } Genteel ℂall Serviℂe By...VVIP Dehradun Girls 9719300533 Heat-bake { Dehradun } Genteel ℂall Serviℂe By...
VVIP Dehradun Girls 9719300533 Heat-bake { Dehradun } Genteel ℂall Serviℂe By...
 
定制(wsu毕业证书)美国华盛顿州立大学毕业证学位证书实拍图原版一模一样
定制(wsu毕业证书)美国华盛顿州立大学毕业证学位证书实拍图原版一模一样定制(wsu毕业证书)美国华盛顿州立大学毕业证学位证书实拍图原版一模一样
定制(wsu毕业证书)美国华盛顿州立大学毕业证学位证书实拍图原版一模一样
 
CHAPTER 1 SEMESTER V - ROLE OF PEADIATRIC NURSE.pdf
CHAPTER 1 SEMESTER V - ROLE OF PEADIATRIC NURSE.pdfCHAPTER 1 SEMESTER V - ROLE OF PEADIATRIC NURSE.pdf
CHAPTER 1 SEMESTER V - ROLE OF PEADIATRIC NURSE.pdf
 

PERT (Program evaluation review technique)

  • 1. Tanoj patidar 1ST YEAR M.SC. NURSING PROGRAMME EVALUATION REVIEW TECHNIQUE (PERT)
  • 2. PROGRAMME EVALUATION REVIEW TECHNIQUE (PERT) OBJECTIVE: • To understand the formula, the use and the benefits of Program, Evaluation, and Review Technic (PERT) analysis. INTRODUCTION: PERT is a method of analysing the tasks involved in completing a given project, especially the time needed to complete each task, and to identify the minimum time needed to complete the total project. PERT was developed primarily to simplify the planning and scheduling of large and complex projects. Developed by the US Navy for the planning and control of the Polaris missile program. The emphasis was on completing the program in the shortest possible time. DEFINITION: PERT is a work model devised to complete the project work in time. It analyses the actual work time required to complete a task. CONCEPT AND MEANING: PERT is a very famous project model that has found its use in various professions, including nursing.  This model helps in judging the time required in completing an activity.  Nurse administrators can use this model to delegate and assign the work schedule to the nurses in a hospital.  It not only evidences the cost effectiveness of nursing care but also has great impact on reducing the expenditure by the patient. This model helps to reduce the patient’s hospital stay by judging beforehand the actual care time, manpower, money and the material required.
  • 3. Therefore, following this model helps to prevent waste of time, money and material, benefiting the patient and the hospital management. WHEN WE USE PERT? PERT is used when activity times are uncertain.  Determine the duration of the project.  Decision making under risk. PERT INCLUDES: steps or activities. It Is a model for project management designed to analyse and represent the task involved in completing a given project. COMPONENTS OF PERT MODEL: Every activity consume time and needs adequate resources such as manpower, material, space and machinery to change or move one event to other. Predecessor event – It is an event that precedes some other event, it can be single or multiple. Successor events – It is an event that immediately follows some other events, it can have single multiple successor events. Optimistic Time (O) – It is the minimum possible time required to complete the task anticipating that every event has occurred better than usually expected. Pessimistic Time (P) - This means the maximum possible time required to complete the given task, expecting or assuming everything goes wrong except the main catastrophes.
  • 4. Most likely Time (M) – The actual and the best time required to complete the task assuming everything goes in a usual way. Expected time or the very best time (TH) – The accurate or the actual time required to complete the task, it is the most reliable and valid time estimated to complete a task. It can be calculated using the following relation TH = (O + 4M – P) ÷ 6 e.g. TH = (5min + 4X 10 min – 15 min) ÷ 6 = 5 min Float or slack time – it is the amount of time that can be floated without causing delay in the total completion of the work. Critical paths – it is the longest possible and the actual total time required to complete the full task. It is otherwise called as total calendar time. Critical total float activity – it is an activity that has total float equal to zero. No float time is required in the critical path. Lead time – this refers to the time taken by the predecessor to complete the task. In this there is sufficient time for the subsequent activities that can follow the predecessor. Lag time – the earliest time taken by the successor event to take place, which follows the specific PERT activity PERT CHART: A PERT chart is a graphical representation of the activities of a project, showing the sequence that has to be performed continuously. therefore it saves time, energy and material.
  • 5.
  • 6. PURPOSES: To schedule the project. To manage the time. e the work. STEPS IN THE PERT PLANNING PROCESS: PERT involves the following steps
  • 7. IDENTIFY THE SPECIFIC ACTIVITIES AND MILESTONE e tasks in a table. DETERMINE THE PROPER SEQUENCE OF THE ACTIVITY identification step. -Since the activity sequence is evident for some tasks. asks may require more analysis. -To determine the exact order in which they must be performed. CONSTRUCT A NETWORK DIAGRAM -A network diagram can be drawn showing the sequence of the serial and parallel activities. Each activity represents: A node in the network, The arrows represent: The relation between activities. re packages simplify this task: By automatically converting tabular activity information into a network diagram. ESTIMATE THE TIME REQURIED FOR EACH ACTIVITY distinguishing feature of PERT: Its ability to deal with uncertainty in activity completion time.
  • 8. Optimistic time(O)- The shortest time in which the activity can be completed. Most likely time(M)- The completion time having the highest probability. Pessimistic time (P)- the maximum possible time required to accomplish a task, assuming everything goes wrong (but excluding major catastrophes). Estimated Time(TE)- The best estimate of the time required to accomplish a task, accounting for the fact that things don't always proceed as normal. TE = (O + 4M + P) ÷ 6 DETERMINE THE CRITICAL PATH -Determined by adding the times for the activities in each sequence. -Determining the longest path in the project. time required for the project. total project time does not change. – critical path activity can be delayed without the project is referred to as a slack time. ES – Earliest Start time EF - Earliest Finish time LS – Latest Start time LF - Latest Finish time variances in the completion times of the activities in the critical path. time for the activities in the critical path. Project Crashing.
  • 9. UPDATE THE PERT CHART AS THE PROJECT PROGRESSES -Additional resources may be needed to stay on schedule. -The PERT chart may be modified to reflect the new situation. BENEFITS OF PERT: activities. USES: Nurse managers use the PERT system for controlling the program. – looking. PERT is generally used for complicated and extensive projects or programs. • personnel staffing reports. • overtime reports. • monthly financial reports and others.
  • 10. evaluate the use of people and money as a part of the controlling process. ADVANTAGES: project. plans, schedules and time and cost – performance. focusing management attention i.e. most constraining on the schedule. l changes on overall schedules. between the WBS elements. of dependencies leading to improved overlapping of activities and tasking where feasible. DISADVANTAGES: dependency relationship. iring several pages to print and requiring special size paper. makes it harder to show status although colours can help (e.g. specific colour for completed nodes) (Critical path method) charts become unwieldy, they are no longer used to manage the project.
  • 11. LIMITATIONS: In other cases, if the person or group performing the activity estimates the time there may be bias in the estimate. – estimated, PERT assumes a beta distribution for these time estimates, but the actual distribution may be different. ds, PERT assumes that the probability distribution of the project completion time is the same as the that of the critical path. BY TANOJ PATIDAR MSc NURSING