Planning and control
Programme Evaluation and Review
Technique – PERT
8/27/2020
1
Anju George
Introduction
• In this method, the time required to complete each task or
activity is identified and then the minimum time required in
completing the total project is calculated.
• It is based on network analysis.
• This model helps to reduce the patients hospital stay by
judging beforehand the actual care time, manpower, money
and material required.
8/27/2020
2
Anju George
Definition
• PERT is a method to analyze the time required to
complete a project.
• A PERT chart is a graphical representation of the
activities of a project, showing the sequence that has to
be performed continuously. This chart helps to focus
only on the needed activities and omit the unwanted
ones.
8/27/2020
3
Anju George
8/27/2020Anju George
4
Concept
• The duration of activities is measured by 3 parameters: most optimum
duration, most likely duration and most pessimistic duration.
• The CIRCLES mark the beginnings and end of tasks to be done in the project. Also
called NODES.
• The ARROWS are the tasks.
• The NUMBERS after the task names are the DURATION of the task.
• When a node has two or more task branching from it , means that those tasks can
be done concurrently.
• When a node has incoming arrows, it means that the incoming task must be
completed before progressing to the next node.
8/27/2020
5
Anju George
Components of PERT model
• Predecessor event : it is an event that precedes some
other event.
• Successor events: it is an event that immediately follows
some other event.
• Optimistic time (O): it is the minimum possible time
required to complete the task anticipating that every
event has occurred better than usually expected.
8/27/2020
6
Anju George
8/27/2020Anju George
7
• Pessimistic time (P): this means the maximum possible time required to
complete the given task, expecting or assuming everything goes wrong
except the main catastrophes.
• Most likely time (M): the actual and best time required to complete the
task assuming everything goes in a usual way.
• Expected time or the very best time (TE): the accurate or the actual time
required to complete the task. TE = (O+4M+P)/6
8/27/2020Anju George
8
• Slack : it is a measure of the excess time and resources available in achieving an
event. There are 3 types of slack – Positive slack – indicate ahead of schedule:
Negative slack – indicate behind schedule : zero slack – indicate on schedule.
• Float /Slack time :it the amount of time that can be floated without causing
delay in the total completion of a project
• Free float – it is the excess time and resources available in achieving an task.
• Total float - it is the excess time and resources available in achieving an whole
project .
8/27/2020Anju George
9
• Critical path – it is the longest possible continuous pathway
taken from the initial event to the terminal event.
• Critical total float activity – it is an activity that has total float
equal to zero.
• Lead time – it is the time taken by the predecessor to complete
the task.
• Lag time – the earliest time taken by the successor event to take
place which follows the specific PERT activity.
8/27/2020Anju George
10
• Fast tracking time – it means the time required to
complete more critical activities at the same time.
• Crash critical path – this means shortening the duration
of critical activities.
Steps involved in PERT planning process
• Identifying the specific activities and milestones
• Determining the proper sequence of the activities
• Constructing a network diagram
• Estimating the time required for each activity
• Determining the critical path
• Updating the PERT chart as the programme progresses.
8/27/2020
11
Anju George
Benefits of PERT
• Enables to determine the exact date of completion of the task.
• Completion of work is possible before the specified time.
• Critical path activities specify the main impact in completion of
activities in time.
• Slack time can be noted out early.
• Entire project data can be organized and used for decision making.
• and evaluate the work done in time.
8/27/2020
12
Anju George
Contd..
Benefits contd…
• Prevents overlapping of activities, creates better understanding of the task
activities.
• Helps to identify early start, late start, and slack time activity.
• Identify the accurate critical path visible and clear to all.
• Helps to prevent loss of money, material and time.
• Allows the management to use the resources, estimate time management
8/27/2020
13
Anju George
Limitations of PERT
• Expert guidance is always needed for proper judgment of time.
• It will be difficult to categorize the activities if there is more than hundreds or thousands
of them.
• Mere guess or approximation of time estimate can lead to errors in evaluation of time
during work.
• PERT uses beta distribution probability, but the actual distribution may be different.
• PERT chart is usually very large and requires several pages for printing.
• Before planning a PERT chart, one needs to do a proper planning to estimate the time
frames for each activity.
8/27/2020
14
Anju George
Gantt chart / activity plan 8/27/2020Anju George
15
Definition
• It is defined as a graphical device that illustrates the tasks,
machines, personnel and resources used to complete a
task. It is always done on a calendar oriented grid.
• Gantt charts are used in nursing field to represent
mortality & morbidity rates and also indicate duty rosters.
8/27/2020Anju George
16
8/27/2020Anju George
17
Components of Gantt chart
• It has a horizontal bar with a open triangular drawing showing the
start and finish date of a project.
• Horizontal axis – represents the time scale expressed as absolute
time from the start of the project to its end.
• Vertical axis – it represents the present point in time. Vertical lines
are indicated to denote progress and completion. It has a open start
triangle and finish triangle in vertical line that helps everybody to
understand progress and end of the project schedule.
8/27/2020Anju George
18
8/27/2020Anju George
19
• Broken lines – these indicate gap or slippage times
during the project schedule.
• Diamond symbol - it indicates rescheduled work.
Marking in the Gantt chart
• Vertical marker indicates the present point in time
• Activity as it progresses, is shown by shading the bar
• At one glance we will come to know about the progress of
any activity
• Milestones are represented in the chart
• Color codes are used for certain specific task
8/27/2020Anju George
20
Advantages
• Excellent tool to communicate with population around the world
• At a single glance, work done can be analyzed quickly through the
breakdown structure.
• It is used as a reporting tool for larger projects
• It gives cost, time and scope of the project
8/27/2020Anju George
21
Disadvantages
• It cannot effortlessly display more than 30 activities.
• It is valuable only for short projects
• Chart can communicate only little information at a time
• Magnitude behind the schedule is easily miscommunicated, since it
doesn't represent full size of the project
• It is not suitable for most computer displays
8/27/2020Anju George
22
8/27/2020
23
Anju George

PERT & Gantt Chart

  • 1.
    Planning and control ProgrammeEvaluation and Review Technique – PERT 8/27/2020 1 Anju George
  • 2.
    Introduction • In thismethod, the time required to complete each task or activity is identified and then the minimum time required in completing the total project is calculated. • It is based on network analysis. • This model helps to reduce the patients hospital stay by judging beforehand the actual care time, manpower, money and material required. 8/27/2020 2 Anju George
  • 3.
    Definition • PERT isa method to analyze the time required to complete a project. • A PERT chart is a graphical representation of the activities of a project, showing the sequence that has to be performed continuously. This chart helps to focus only on the needed activities and omit the unwanted ones. 8/27/2020 3 Anju George
  • 4.
  • 5.
    Concept • The durationof activities is measured by 3 parameters: most optimum duration, most likely duration and most pessimistic duration. • The CIRCLES mark the beginnings and end of tasks to be done in the project. Also called NODES. • The ARROWS are the tasks. • The NUMBERS after the task names are the DURATION of the task. • When a node has two or more task branching from it , means that those tasks can be done concurrently. • When a node has incoming arrows, it means that the incoming task must be completed before progressing to the next node. 8/27/2020 5 Anju George
  • 6.
    Components of PERTmodel • Predecessor event : it is an event that precedes some other event. • Successor events: it is an event that immediately follows some other event. • Optimistic time (O): it is the minimum possible time required to complete the task anticipating that every event has occurred better than usually expected. 8/27/2020 6 Anju George
  • 7.
    8/27/2020Anju George 7 • Pessimistictime (P): this means the maximum possible time required to complete the given task, expecting or assuming everything goes wrong except the main catastrophes. • Most likely time (M): the actual and best time required to complete the task assuming everything goes in a usual way. • Expected time or the very best time (TE): the accurate or the actual time required to complete the task. TE = (O+4M+P)/6
  • 8.
    8/27/2020Anju George 8 • Slack: it is a measure of the excess time and resources available in achieving an event. There are 3 types of slack – Positive slack – indicate ahead of schedule: Negative slack – indicate behind schedule : zero slack – indicate on schedule. • Float /Slack time :it the amount of time that can be floated without causing delay in the total completion of a project • Free float – it is the excess time and resources available in achieving an task. • Total float - it is the excess time and resources available in achieving an whole project .
  • 9.
    8/27/2020Anju George 9 • Criticalpath – it is the longest possible continuous pathway taken from the initial event to the terminal event. • Critical total float activity – it is an activity that has total float equal to zero. • Lead time – it is the time taken by the predecessor to complete the task. • Lag time – the earliest time taken by the successor event to take place which follows the specific PERT activity.
  • 10.
    8/27/2020Anju George 10 • Fasttracking time – it means the time required to complete more critical activities at the same time. • Crash critical path – this means shortening the duration of critical activities.
  • 11.
    Steps involved inPERT planning process • Identifying the specific activities and milestones • Determining the proper sequence of the activities • Constructing a network diagram • Estimating the time required for each activity • Determining the critical path • Updating the PERT chart as the programme progresses. 8/27/2020 11 Anju George
  • 12.
    Benefits of PERT •Enables to determine the exact date of completion of the task. • Completion of work is possible before the specified time. • Critical path activities specify the main impact in completion of activities in time. • Slack time can be noted out early. • Entire project data can be organized and used for decision making. • and evaluate the work done in time. 8/27/2020 12 Anju George Contd..
  • 13.
    Benefits contd… • Preventsoverlapping of activities, creates better understanding of the task activities. • Helps to identify early start, late start, and slack time activity. • Identify the accurate critical path visible and clear to all. • Helps to prevent loss of money, material and time. • Allows the management to use the resources, estimate time management 8/27/2020 13 Anju George
  • 14.
    Limitations of PERT •Expert guidance is always needed for proper judgment of time. • It will be difficult to categorize the activities if there is more than hundreds or thousands of them. • Mere guess or approximation of time estimate can lead to errors in evaluation of time during work. • PERT uses beta distribution probability, but the actual distribution may be different. • PERT chart is usually very large and requires several pages for printing. • Before planning a PERT chart, one needs to do a proper planning to estimate the time frames for each activity. 8/27/2020 14 Anju George
  • 15.
    Gantt chart /activity plan 8/27/2020Anju George 15
  • 16.
    Definition • It isdefined as a graphical device that illustrates the tasks, machines, personnel and resources used to complete a task. It is always done on a calendar oriented grid. • Gantt charts are used in nursing field to represent mortality & morbidity rates and also indicate duty rosters. 8/27/2020Anju George 16
  • 17.
  • 18.
    Components of Ganttchart • It has a horizontal bar with a open triangular drawing showing the start and finish date of a project. • Horizontal axis – represents the time scale expressed as absolute time from the start of the project to its end. • Vertical axis – it represents the present point in time. Vertical lines are indicated to denote progress and completion. It has a open start triangle and finish triangle in vertical line that helps everybody to understand progress and end of the project schedule. 8/27/2020Anju George 18
  • 19.
    8/27/2020Anju George 19 • Brokenlines – these indicate gap or slippage times during the project schedule. • Diamond symbol - it indicates rescheduled work.
  • 20.
    Marking in theGantt chart • Vertical marker indicates the present point in time • Activity as it progresses, is shown by shading the bar • At one glance we will come to know about the progress of any activity • Milestones are represented in the chart • Color codes are used for certain specific task 8/27/2020Anju George 20
  • 21.
    Advantages • Excellent toolto communicate with population around the world • At a single glance, work done can be analyzed quickly through the breakdown structure. • It is used as a reporting tool for larger projects • It gives cost, time and scope of the project 8/27/2020Anju George 21
  • 22.
    Disadvantages • It cannoteffortlessly display more than 30 activities. • It is valuable only for short projects • Chart can communicate only little information at a time • Magnitude behind the schedule is easily miscommunicated, since it doesn't represent full size of the project • It is not suitable for most computer displays 8/27/2020Anju George 22
  • 23.