Tools for project management is described some of the commonly used tools such as gantt chart, pert chart, logic network, product breakdown structure, work breakdown structure is defined briefly.
The Gantt chart is a bar chart that illustrates the timing of project activities and their relationships. It displays activities on one chart against time to provide a simple representation of project scheduling. Gantt charts are useful for planning and overview but have limitations like difficulty updating and lack of cost/resource data. Alternatives for project planning include PERT, WBS, critical path and resource leveling.
In this chapter, you will learn how to:
✔ Use the Backstage view to open and save Project files.
✔ Work with commands on different tabs of the ribbon interface, the major visual
change introduced in Project 2010.
✔ Use different views to see Project information presented in different ways.
The Work Breakdown Structure (WBS) is a key project management tool used to define and group the total scope of work to be performed by the project team. It provides a common understanding of the project and can be used for planning, estimating costs and schedules, tracking progress, and assigning responsibilities. The WBS breaks down the project into smaller, more manageable components, typically in a hierarchical structure with up to six levels of detail. It helps ensure all required work is defined and accounted for and provides a framework for managing the project.
Project Management Techniques ( CPM & PERT Techniques )
A revised PPT from other shared PPT available
Project management is a scientific way of planning, implementing, monitoring & controlling the various aspects of a project such as time, money, materials, manpower & other resources.
By,
Mr. AKARESH JOSE
Kerala Agricultural University
akareshjose@gmail.com
Making Project schedule using precedence Diagram Method (PDM) includes four types of dependencies or logical relationships. Many PMP® aspirants find Finish to start (FS) relationship easy to understand and practice with but other three confuses them a bit.
This presentation describes all four at detail.
• Finish-to-start (FS)
• Finish-to-finish (FF)
• Start-to-start (SS)
• Start-to-finish (SF)
This document discusses several project scheduling techniques including PERT, CPM, and GERT. It provides background on the development of PERT for the Polaris missile program and CPM for chemical plant construction. Key aspects of each technique are summarized, such as how PERT uses three time estimates to model uncertainty and calculate activity mean and variance. The document also covers topics like crashing, resource constraints, and limitations of PERT/CPM that GERT addresses.
Tools for project management is described some of the commonly used tools such as gantt chart, pert chart, logic network, product breakdown structure, work breakdown structure is defined briefly.
The Gantt chart is a bar chart that illustrates the timing of project activities and their relationships. It displays activities on one chart against time to provide a simple representation of project scheduling. Gantt charts are useful for planning and overview but have limitations like difficulty updating and lack of cost/resource data. Alternatives for project planning include PERT, WBS, critical path and resource leveling.
In this chapter, you will learn how to:
✔ Use the Backstage view to open and save Project files.
✔ Work with commands on different tabs of the ribbon interface, the major visual
change introduced in Project 2010.
✔ Use different views to see Project information presented in different ways.
The Work Breakdown Structure (WBS) is a key project management tool used to define and group the total scope of work to be performed by the project team. It provides a common understanding of the project and can be used for planning, estimating costs and schedules, tracking progress, and assigning responsibilities. The WBS breaks down the project into smaller, more manageable components, typically in a hierarchical structure with up to six levels of detail. It helps ensure all required work is defined and accounted for and provides a framework for managing the project.
Project Management Techniques ( CPM & PERT Techniques )
A revised PPT from other shared PPT available
Project management is a scientific way of planning, implementing, monitoring & controlling the various aspects of a project such as time, money, materials, manpower & other resources.
By,
Mr. AKARESH JOSE
Kerala Agricultural University
akareshjose@gmail.com
Making Project schedule using precedence Diagram Method (PDM) includes four types of dependencies or logical relationships. Many PMP® aspirants find Finish to start (FS) relationship easy to understand and practice with but other three confuses them a bit.
This presentation describes all four at detail.
• Finish-to-start (FS)
• Finish-to-finish (FF)
• Start-to-start (SS)
• Start-to-finish (SF)
This document discusses several project scheduling techniques including PERT, CPM, and GERT. It provides background on the development of PERT for the Polaris missile program and CPM for chemical plant construction. Key aspects of each technique are summarized, such as how PERT uses three time estimates to model uncertainty and calculate activity mean and variance. The document also covers topics like crashing, resource constraints, and limitations of PERT/CPM that GERT addresses.
This document provides an overview of critical path method (CPM) and network analysis techniques for project management. It defines key CPM terms like critical path, float, crashing and activities. It explains the 6 steps to using CPM including specifying activities, establishing dependencies, drawing the network diagram, estimating times, identifying the critical path, and updating the diagram. An example network diagram is provided. Advantages of CPM include establishing a framework for planning, scheduling, and controlling projects. Disadvantages include reliance on accurate estimates and the potential complexity of large network diagrams.
The document discusses network analysis and the critical path method (CPM). It explains that CPM can be used to determine the minimum time required to complete a project if activity durations are known. CPM was developed in the 1950s by researchers at DuPont and Sperry Rand. It also discusses the Program Evaluation and Review Technique (PERT) which can estimate project completion probabilities when durations are uncertain. Both CPM and PERT helped reduce the Polaris missile development time. The document provides examples of CPM and PERT applications and rules for constructing a project network diagram.
The Critical Path Method (CPM) is a technique for scheduling a set of project activities. It identifies the longest continuous chain of activities from start to finish required to complete the project on time. This longest chain is called the critical path. CPM calculates the earliest and latest times each activity can start and finish without making the project longer. Activities on the critical path have no scheduling flexibility, while other activities have "float" or slack time that can be used for scheduling flexibility. CPM is useful for determining the minimum project duration and identifying which activities must be carefully managed and monitored to avoid project delays.
This document outlines the project life cycle and key aspects of project management. It discusses the initiation, planning, execution, monitoring, control, and closure phases of a project. It also identifies important skills for project managers, such as strategic strength, communication, scope control, and determining levels of success. Finally, it provides a formula for project success that emphasizes realistic expectations, managing stakeholder expectations, and delivering the project as planned.
The document discusses project planning and scheduling. It covers topics like work breakdown structure, project time scheduling, network diagrams, critical path method, Program Evaluation and Review Technique (PERT), Gantt charts, and key terms used in project management like activities, milestones, float, baselines. Project planning involves preparing schedules of activities, resources, capital, and mitigation plans. Work breakdown structure is used to divide large projects into simpler, more manageable components. Network diagrams and critical path method are used to schedule project activities and identify the critical path. PERT uses three time estimates to calculate expected activity durations. Gantt charts graphically show project schedules and status.
A Gantt chart shows the start and finish dates of tasks, milestones, and resources for a project. It was designed by American engineer Henry Gantt. A PERT chart provides a graphical timeline of a project and allows tasks to be analyzed for dependencies. While PERT charts identify dependencies more clearly, they can be more difficult to interpret than Gantt charts. Both charts are project management tools.
SHORT NOTE ABOUT PROJECT MANAGEMENT:
contents of this note:-
What is Project Management?,
What does Project Management Entail?,
Measuring,
How much time does Project Management take?,
Why is Project Management Important?,
Advantages,
Road to Better Project Management,
Implementation,
Consequences of not using PMT,
The document discusses fundamentals of project scheduling including scheduling philosophy, terms and definitions, types of schedules, relationships between activities, and developing a project schedule. The key points are:
- Scheduling allows project managers to better control projects, monitor progress, and satisfy requirements.
- Important scheduling terms include activities, durations, relationships, critical path, float.
- Common schedule types include bar charts, logic networks, and milestone charts.
- Relationships define dependencies between activities like finish-to-start.
- Developing a good schedule requires defining activities and sequences, estimating durations, and incorporating resources and calendars.
This document discusses various aspects of project management and control tools. It covers topics like project organization, the human aspect of project management, planning and control. Specific tools discussed include Gantt charts and Line of Balance (LOB) charts. Gantt charts illustrate a project schedule visually using bars to represent tasks and their duration. LOB charts are an extension of Gantt charts used for scheduling repetitive projects through a series of inclined lines showing the rate of work. The document provides details on how to construct, analyze, and use these charts to manage projects.
In this presentation we have done earlier a project for Phillip Morris (Pakistan) for the access control system and canteen management system. It is the project presentation for our subject Planning and Scheduling. i hope it is the best for the understanding Project planning and scheduling.
GANTT charts are a type of bar chart used to illustrate project schedules. They show the start and end dates of tasks, their duration, and dependencies between tasks. To construct a GANTT chart, critical tasks are scheduled first followed by non-critical tasks within their time windows. Staff and resources are then allocated to tasks based on availability. The chart can be re-scheduled if needed due to changes in staffing or equipment availability. Project management software helps automate GANTT chart creation and resource smoothing but decisions still require human judgment.
CPM and PERT are network analysis techniques used for project planning and scheduling. CPM was developed in the 1950s by DuPont for chemical plant projects and focuses on minimizing project duration. PERT was developed by the US Navy for the Polaris missile program and handles uncertain activity times using probability. Both techniques represent activities as nodes and their dependencies as arrows to build a network that identifies the critical path showing the shortest time to complete the project.
Favorite Delay Analysis Methodologies Town Hall SEIChris Carson
Presentation from a Town Hall session to discuss favorite forensic schedule analysis methodologies, based on the Forensic Analysis Recommended Practice from AACE International. The Best Practices and Guidelines for Schedule Impact Analysis project is discussing methods.
The document defines key project management concepts including what constitutes a project, project characteristics, the differences between project and program management, the six basic project functions, common pitfalls, and the triple constraints of time, cost and scope. It also outlines the nine knowledge areas that comprise the project management framework: integration management, scope management, time management, cost management, quality management, human resource management, communications management, risk management, and procurement management.
The document discusses project planning and control, covering what a project is, the stages of project management, and network planning using the Critical Path Method (CPM). It describes the five stages of project management as understanding the project environment, defining the project, planning the project, technical execution, and project control. Project planning determines the cost, duration, resource needs, and helps allocate work and monitor progress. The CPM represents activities diagrammatically and identifies the critical path which determines the minimum project duration.
The document discusses project management, including its definition, characteristics, parameters, classification, and relationship to programs and line management. It also covers the project management process, which includes initiation, planning, organizing, controlling, and closing phases. Key project stakeholders are defined as those directly or indirectly involved or affected by the project. Organizational influences on projects include systems, culture, structure, and more.
The document defines key project management terms like critical path, total float, free float, and project float. It explains that the critical path is the longest sequence of activities that determines the shortest project duration, and float is the amount of time an activity can be delayed without impacting subsequent activities or the project end date. The document also provides an example critical path diagram and calculations for early start, late start, early finish, late finish, and float.
The document provides an overview of the critical path method (CPM), a technique for scheduling projects. It was developed in the 1950s by the US Navy to consider logical dependencies between tasks. CPM calculates the longest sequence of tasks to complete a project and the earliest and latest each task can start. It determines critical tasks on the longest path. The method breaks a project into tasks, estimates durations, and identifies dependencies to create a schedule and establish critical paths. CPM is a useful tool for project management to optimize schedules and resources.
Understand what projects are and how they differ from ongoing operations
Define and explain several key terms; Project, Project Management, Software Project Management
Understand Organization structures
Understand Project Management Processes
Understand Project Life Cycle
Project planning involves carefully breaking down a project into logical components using tools like the work breakdown structure and network diagrams to identify dependencies between tasks. This allows project teams to develop accurate schedules, usually in the form of Gantt charts, to coordinate resources and activities to achieve goals on time and on budget. Production planning establishes production rates and resource usage to satisfy customer demand as expressed in sales forecasts, while balancing inventory levels and maintaining a stable workforce over a 6-18 month horizon. The process begins with a sales forecast and may incorporate desired inventory changes to determine the production plan.
This document provides an overview of Gantt charts, including their history, evolution, and uses. Gantt charts are a type of bar chart used to display a project schedule and track progress over time. They show the tasks or activities within the project arranged on the vertical axis and time intervals on the horizontal axis, allowing project managers to visualize the timeline and dependencies between tasks. The document discusses the basic components of a Gantt chart, including variants that show milestones, resources, status, and dependencies. Examples are also provided of different Gantt chart types like daily, stoplight, summary, and earned value charts.
This document discusses planning and the planning process. It covers the purpose of planning, setting objectives, developing plans, and types of plans. It also discusses potential pitfalls in planning. The document is from a course on planning and was presented by the instructor, Michael Crandall, covering elements of the planning process like developing premises, choosing goals and actions, and assessing future consequences.
This document provides an overview of critical path method (CPM) and network analysis techniques for project management. It defines key CPM terms like critical path, float, crashing and activities. It explains the 6 steps to using CPM including specifying activities, establishing dependencies, drawing the network diagram, estimating times, identifying the critical path, and updating the diagram. An example network diagram is provided. Advantages of CPM include establishing a framework for planning, scheduling, and controlling projects. Disadvantages include reliance on accurate estimates and the potential complexity of large network diagrams.
The document discusses network analysis and the critical path method (CPM). It explains that CPM can be used to determine the minimum time required to complete a project if activity durations are known. CPM was developed in the 1950s by researchers at DuPont and Sperry Rand. It also discusses the Program Evaluation and Review Technique (PERT) which can estimate project completion probabilities when durations are uncertain. Both CPM and PERT helped reduce the Polaris missile development time. The document provides examples of CPM and PERT applications and rules for constructing a project network diagram.
The Critical Path Method (CPM) is a technique for scheduling a set of project activities. It identifies the longest continuous chain of activities from start to finish required to complete the project on time. This longest chain is called the critical path. CPM calculates the earliest and latest times each activity can start and finish without making the project longer. Activities on the critical path have no scheduling flexibility, while other activities have "float" or slack time that can be used for scheduling flexibility. CPM is useful for determining the minimum project duration and identifying which activities must be carefully managed and monitored to avoid project delays.
This document outlines the project life cycle and key aspects of project management. It discusses the initiation, planning, execution, monitoring, control, and closure phases of a project. It also identifies important skills for project managers, such as strategic strength, communication, scope control, and determining levels of success. Finally, it provides a formula for project success that emphasizes realistic expectations, managing stakeholder expectations, and delivering the project as planned.
The document discusses project planning and scheduling. It covers topics like work breakdown structure, project time scheduling, network diagrams, critical path method, Program Evaluation and Review Technique (PERT), Gantt charts, and key terms used in project management like activities, milestones, float, baselines. Project planning involves preparing schedules of activities, resources, capital, and mitigation plans. Work breakdown structure is used to divide large projects into simpler, more manageable components. Network diagrams and critical path method are used to schedule project activities and identify the critical path. PERT uses three time estimates to calculate expected activity durations. Gantt charts graphically show project schedules and status.
A Gantt chart shows the start and finish dates of tasks, milestones, and resources for a project. It was designed by American engineer Henry Gantt. A PERT chart provides a graphical timeline of a project and allows tasks to be analyzed for dependencies. While PERT charts identify dependencies more clearly, they can be more difficult to interpret than Gantt charts. Both charts are project management tools.
SHORT NOTE ABOUT PROJECT MANAGEMENT:
contents of this note:-
What is Project Management?,
What does Project Management Entail?,
Measuring,
How much time does Project Management take?,
Why is Project Management Important?,
Advantages,
Road to Better Project Management,
Implementation,
Consequences of not using PMT,
The document discusses fundamentals of project scheduling including scheduling philosophy, terms and definitions, types of schedules, relationships between activities, and developing a project schedule. The key points are:
- Scheduling allows project managers to better control projects, monitor progress, and satisfy requirements.
- Important scheduling terms include activities, durations, relationships, critical path, float.
- Common schedule types include bar charts, logic networks, and milestone charts.
- Relationships define dependencies between activities like finish-to-start.
- Developing a good schedule requires defining activities and sequences, estimating durations, and incorporating resources and calendars.
This document discusses various aspects of project management and control tools. It covers topics like project organization, the human aspect of project management, planning and control. Specific tools discussed include Gantt charts and Line of Balance (LOB) charts. Gantt charts illustrate a project schedule visually using bars to represent tasks and their duration. LOB charts are an extension of Gantt charts used for scheduling repetitive projects through a series of inclined lines showing the rate of work. The document provides details on how to construct, analyze, and use these charts to manage projects.
In this presentation we have done earlier a project for Phillip Morris (Pakistan) for the access control system and canteen management system. It is the project presentation for our subject Planning and Scheduling. i hope it is the best for the understanding Project planning and scheduling.
GANTT charts are a type of bar chart used to illustrate project schedules. They show the start and end dates of tasks, their duration, and dependencies between tasks. To construct a GANTT chart, critical tasks are scheduled first followed by non-critical tasks within their time windows. Staff and resources are then allocated to tasks based on availability. The chart can be re-scheduled if needed due to changes in staffing or equipment availability. Project management software helps automate GANTT chart creation and resource smoothing but decisions still require human judgment.
CPM and PERT are network analysis techniques used for project planning and scheduling. CPM was developed in the 1950s by DuPont for chemical plant projects and focuses on minimizing project duration. PERT was developed by the US Navy for the Polaris missile program and handles uncertain activity times using probability. Both techniques represent activities as nodes and their dependencies as arrows to build a network that identifies the critical path showing the shortest time to complete the project.
Favorite Delay Analysis Methodologies Town Hall SEIChris Carson
Presentation from a Town Hall session to discuss favorite forensic schedule analysis methodologies, based on the Forensic Analysis Recommended Practice from AACE International. The Best Practices and Guidelines for Schedule Impact Analysis project is discussing methods.
The document defines key project management concepts including what constitutes a project, project characteristics, the differences between project and program management, the six basic project functions, common pitfalls, and the triple constraints of time, cost and scope. It also outlines the nine knowledge areas that comprise the project management framework: integration management, scope management, time management, cost management, quality management, human resource management, communications management, risk management, and procurement management.
The document discusses project planning and control, covering what a project is, the stages of project management, and network planning using the Critical Path Method (CPM). It describes the five stages of project management as understanding the project environment, defining the project, planning the project, technical execution, and project control. Project planning determines the cost, duration, resource needs, and helps allocate work and monitor progress. The CPM represents activities diagrammatically and identifies the critical path which determines the minimum project duration.
The document discusses project management, including its definition, characteristics, parameters, classification, and relationship to programs and line management. It also covers the project management process, which includes initiation, planning, organizing, controlling, and closing phases. Key project stakeholders are defined as those directly or indirectly involved or affected by the project. Organizational influences on projects include systems, culture, structure, and more.
The document defines key project management terms like critical path, total float, free float, and project float. It explains that the critical path is the longest sequence of activities that determines the shortest project duration, and float is the amount of time an activity can be delayed without impacting subsequent activities or the project end date. The document also provides an example critical path diagram and calculations for early start, late start, early finish, late finish, and float.
The document provides an overview of the critical path method (CPM), a technique for scheduling projects. It was developed in the 1950s by the US Navy to consider logical dependencies between tasks. CPM calculates the longest sequence of tasks to complete a project and the earliest and latest each task can start. It determines critical tasks on the longest path. The method breaks a project into tasks, estimates durations, and identifies dependencies to create a schedule and establish critical paths. CPM is a useful tool for project management to optimize schedules and resources.
Understand what projects are and how they differ from ongoing operations
Define and explain several key terms; Project, Project Management, Software Project Management
Understand Organization structures
Understand Project Management Processes
Understand Project Life Cycle
Project planning involves carefully breaking down a project into logical components using tools like the work breakdown structure and network diagrams to identify dependencies between tasks. This allows project teams to develop accurate schedules, usually in the form of Gantt charts, to coordinate resources and activities to achieve goals on time and on budget. Production planning establishes production rates and resource usage to satisfy customer demand as expressed in sales forecasts, while balancing inventory levels and maintaining a stable workforce over a 6-18 month horizon. The process begins with a sales forecast and may incorporate desired inventory changes to determine the production plan.
This document provides an overview of Gantt charts, including their history, evolution, and uses. Gantt charts are a type of bar chart used to display a project schedule and track progress over time. They show the tasks or activities within the project arranged on the vertical axis and time intervals on the horizontal axis, allowing project managers to visualize the timeline and dependencies between tasks. The document discusses the basic components of a Gantt chart, including variants that show milestones, resources, status, and dependencies. Examples are also provided of different Gantt chart types like daily, stoplight, summary, and earned value charts.
This document discusses planning and the planning process. It covers the purpose of planning, setting objectives, developing plans, and types of plans. It also discusses potential pitfalls in planning. The document is from a course on planning and was presented by the instructor, Michael Crandall, covering elements of the planning process like developing premises, choosing goals and actions, and assessing future consequences.
The document discusses the benefits of meditation for reducing stress and anxiety. Regular meditation practice can help calm the mind and body by lowering heart rate and blood pressure. Studies have shown that meditating for just 10-20 minutes per day can have significant positive impacts on both mental and physical health.
A Gantt chart is a type of bar chart used to illustrate a project schedule. It was developed by Henry Gantt and shows the tasks, durations, and dependencies of activities within a project. The document outlines how to construct a Gantt chart by listing activities, estimating their time requirements, ordering them, and drawing the chart with start/end dates for each activity based on duration and dependencies. Gantt charts provide a simple visual representation of a project plan but can be limited in visualizing dependencies between tasks.
A Gantt chart is a project scheduling tool used to plan and track tasks and milestones. It displays tasks, or activities, as horizontal bars against a calendar timescale, allowing visualization of schedules and dependencies. Key elements shown on a Gantt chart include task bars indicating duration, milestones, resources, and dependencies between tasks. An example Gantt chart is provided to illustrate making a cup of tea, showing the tasks, durations, and dependencies between steps.
TID Chapter 6 Introduction To Microsoft ProjectWanBK Leo
- The document discusses various charts used for project management including Gantt charts, PERT charts, and work breakdown structures.
- Gantt charts show the duration of tasks visually on a timeline and are useful for planning, scheduling, and monitoring project progress. PERT charts model the dependencies between tasks through network diagrams.
- Microsoft Project is a project management software that allows creating and editing Gantt charts, PERT charts, work breakdown structures, and performing tasks like determining critical paths.
The document discusses various tools and techniques for managing projects, including work breakdown structures (WBS), network diagrams, and Gantt charts. It provides information on sequencing activities and using PERT and CPM for network diagrams. The benefits of a WBS for breaking down a project into manageable parts are described. Gantt charts are introduced as a way to display project schedules and activity relationships over time. Finally, the use of project management software to help plan and control projects is mentioned.
PERT (Program Evaluation and Review Technique) is a project management tool developed by the US Navy to analyze complex projects by breaking them into tasks, estimating activity times, and identifying the critical path of tasks. It facilitates decision making by determining the earliest and latest start/finish times and calculating slack time to reduce project time and costs. PERT uses a network diagram and beta distribution to model activity times and account for uncertainty in complex, non-routine projects.
The document discusses three examples of project managers and their responsibilities on different projects:
1) Construction of a retail development with 26 units and a supermarket. Responsible for coordinating contractors to ensure on-time and on-budget completion.
2) Directing trials of a new analgesic drug. Responsible for designing experiments and ensuring proper scientific and legal procedures are followed.
3) Introducing multimedia resources at a teacher training college in New Delhi. Responsible for purchasing and developing resources as well as encouraging acceptance by lecturers and students.
Network analysis techniques such as critical path method (CPM) and program evaluation and review technique (PERT) can be used to plan, manage, and control projects. CPM involves identifying all activities, their durations, and their logical sequence or precedence relationships using a network diagram of nodes and arrows. It allows determining the critical path that dictates the minimum project duration and identifying any activities that could delay the project if they slip. PERT extends CPM by using three time estimates per activity to model the uncertainty in activity durations through probability distributions.
This document discusses project management techniques CPM and PERT. It begins by defining a project and project management. It then discusses network planning methods including CPM and PERT. The four steps to managing a project with these methods are described: describing the project, diagramming the network, estimating time of completion, and monitoring progress. Key concepts like activities, precedence relationships, and events are also defined. The document goes on to provide details on CPM and PERT, including estimating time, determining critical paths, and differences between the two methods.
PERT Ghant chart and bench marking with application to nursingHariasha
The document discusses Gantt charts, which are bar charts used to illustrate project schedules. A Gantt chart shows the tasks or activities within a project along a timeline, making relationships between activities and time periods visual. The document provides examples of simple Gantt charts and outlines the steps to create one, including determining activities and durations, evaluating dependencies, and using forward or backward scheduling to populate the chart. Both advantages and limitations of Gantt charts are discussed. Alternatives to Gantt charts for project scheduling like PERT and CPM are also mentioned.
This document discusses Gantt charts and PERT charts, which are project management tools used to organize tasks, resources, and timelines. It provides information on how to create a basic Gantt chart by listing tasks, durations, and dependencies. PERT charts take a similar approach but use nodes and arrows to represent tasks and dependencies. The document also discusses key terms like critical path, slack time, and dummy tasks. It provides examples of using Gantt and PERT charts to plan a construction project and family routine. Overall, the document introduces the basic concepts and components of Gantt and PERT charts for project scheduling and management.
The document discusses Gantt charts and the Critical Path Method (CPM) for project scheduling. Gantt charts are bar charts used to illustrate project schedules by showing tasks, milestones, resources and deliveries. CPM is a technique for planning projects made up of individual activities, showing the graphical relationship between tasks and identifying the critical path. Both methods provide benefits for project management by planning timelines, dependencies and identifying critical activities.
The document discusses the Gantt chart, a project management tool used to illustrate the timeline of project activities. It provides examples of how to create a basic Gantt chart, including determining the project start/end dates, listing activities with durations and dependencies, and using forward or backward scheduling to populate the chart. The Gantt chart provides a simple visual representation of a project schedule but has limitations like difficulty updating and lack of cost/resource information. Alternative project planning techniques like PERT and GERT are also discussed.
The document provides an overview of Program Evaluation Review Technique (PERT). It defines PERT and its purpose, compares it to Critical Path Method (CPM), discusses its historical background, and outlines the key steps and terminologies used in PERT including how to create a PERT diagram and calculate activity durations, critical paths, and uncertainties.
This document provides an overview of PERT/CPM (Program/Project Evaluation and Review Technique/Critical Path Method). It describes PERT/CPM as methods used to plan, schedule, and control projects involving complex sequences of interdependent activities. The document outlines the history, framework, basic terms, and differences between PERT and CPM. It also discusses the advantages and disadvantages of using PERT/CPM for project management.
Henry Gantt was an American mechanical engineer and management consultant in the early 20th century best known for developing the Gantt Chart, a production scheduling chart. He graduated from Johns Hopkins University and worked as an engineer before collaborating with Frederick Winslow Taylor on applying scientific management principles. Gantt later developed his own task and bonus system and the Gantt Chart, which helped visualize work schedules and became foundational for later project management tools. He received honors like the American Society of Mechanical Engineers medal for his contributions to workforce and productivity management.
Gantt’s contribution to scientific managementNixon Johny
Henry Gantt made several important contributions to scientific management including developing the Gantt chart, task and bonus system, and emphasizing the social responsibility of businesses. The Gantt chart visually depicts the tasks, start/end dates, durations, and dependencies of a project. Gantt's task and bonus system rewarded workers for completing tasks ahead of schedule. He believed businesses have a duty to improve society and workers' welfare, not just maximize profits.
This document discusses project scheduling and the critical path method (CPM) of scheduling. It provides an example of a 5 activity project network to demonstrate how to calculate:
1) Early and late start/finish times for each activity by performing forward and backward passes through the network
2) Total float for each activity based on the difference between early and late times
3) The critical path, which is the longest path of minimum duration activities that determines the project completion time.
The document describes various project management tools and techniques including: work breakdown structures, network diagrams, critical path analysis, Gantt charts, resource planning, procurement planning, cash flow statements, quality, risk, and communication plans. It provides examples and explanations of how to develop and use these tools to plan, schedule, and manage a project. Key terms like floats, early and late start/finish dates are defined. Methods for accelerating a project schedule through crashing or fast tracking are also outlined.
The document discusses project scheduling techniques like PERT and CPM. It provides an example of using these methods to schedule the building of an elaborate parade float. Key activities, durations, and dependencies are laid out. Calculations are shown to determine the critical path, earliest and latest start/finish times, and project completion time. For activities with uncertain durations, a three-time estimate approach is described to model duration as a distribution and calculate the probability of on-time completion.
The document discusses project scheduling techniques PERT and CPM. It provides an example of using these methods to schedule the building of an elaborate parade float. Key activities, durations, and dependencies are laid out. Earliest and latest start/finish times are calculated. The critical path is identified as several critical activities that must be completed on schedule. The project completion time is estimated at 18 days based on the critical path. Uncertain activity times and calculating the probability of on-time project completion are also discussed.
The document discusses network analysis techniques used for project planning and management. It covers key concepts like work breakdown structure, network diagrams, critical path method (CPM), program evaluation and review technique (PERT), activity times, event relationships, slack, floats, crashing, and normal vs crash schedules. The document contains examples of network diagrams and questions related to calculating activity times, identifying critical paths, and crashing project schedules.
Project management involves planning, directing, and controlling resources to complete a project on time, within budget, and according to specifications. A key tool is the work breakdown structure, which defines the hierarchy of tasks and subtasks. The critical path method identifies the longest path of activities in a project as the critical path. It is important for scheduling and determining which activities have slack time. Time-cost tradeoff models determine the least costly way to reduce a project's duration.
This document discusses project management and the critical path method technique. It defines project management as planning, directing, and controlling resources to meet time, cost, and technical constraints. The critical path method allows project managers to identify the critical activities and completion time of a project by determining the earliest and latest times of each activity. The document provides examples of constructing critical path networks and calculating key timing metrics to schedule and control a project.
The document describes common causes of software project failures and techniques for project scheduling and monitoring. It lists unrealistic deadlines, changing requirements, underestimating effort, unforeseen risks and difficulties, and miscommunication as potential causes of failure. It emphasizes the importance of defining tasks, dependencies, timelines, responsibilities, and milestones to effectively schedule and track progress to recognize and address delays.
The document discusses the importance of proper planning for project success. It describes key elements of the planning phase including creating a project scope statement, communication plan, work breakdown structure (WBS), Gantt chart, and network diagram. Conducting a critical path analysis to determine project duration and identifying required resources are also covered. The planning phase is emphasized as the time when the greatest value can be added to a project by minimizing future costs and changes.
This document discusses key aspects of project management including defining a project, project management activities, structuring project organizations, work breakdown structures, critical path scheduling, and time-cost tradeoff models. It provides examples to illustrate work breakdown structures, critical path diagrams, expected time calculations, and probability calculations for project duration. The document outlines assumptions and limitations of critical path methodology for project scheduling.
This document discusses scheduling techniques for projects including network diagrams, PERT charts, and critical path analysis. It provides examples of how to construct network diagrams showing the logical dependencies and precedence relationships between tasks. It also demonstrates how to determine the critical path of a project by calculating the earliest and latest start/finish times for each task and identifying which tasks have zero slack and must be completed on schedule for the project to finish on time. Key terms discussed include activities, events, slack, critical path, and the importance of focusing resources on critical path tasks.
This document discusses scheduling techniques for projects including PERT (Program Evaluation and Review Technique) and CPM (Critical Path Method). It provides examples of how to create network diagrams for projects showing the logical dependencies and precedence relationships between tasks. The network diagrams are then used to calculate the earliest and latest start and finish times for each task, identify the critical path, and determine the float or slack time for non-critical tasks. The critical path identifies the minimum time needed to complete the project and any delays to critical path tasks will delay the overall project completion.
EXAMPLES OF THE USE OF DUMMYACTIVITY.pdfssuserc9c6261
This document discusses scheduling techniques for projects including network diagrams, PERT charts, and critical path analysis. It provides examples of how to construct network diagrams showing the logical dependencies and precedence relationships between tasks. It also demonstrates how to determine the critical path of a project by calculating the earliest and latest start/finish times for each task and identifying which tasks have zero slack and must be completed on schedule for the project to finish on time. Key terms discussed include activities, events, slack, critical path, and the importance of focusing resources on critical path tasks.
This document discusses network techniques like PERT (Program Evaluation and Review Technique) and CPM (Critical Path Method) which are used for scheduling projects. It provides examples of networking activities with earliest and latest start/finish times to identify the critical path. The critical path is the longest path through the network that determines the minimum project duration. Non-critical activities have float or slack time and can be delayed without extending the project completion time. The document also discusses using three time estimates (optimistic, most likely, pessimistic) for activities when there is uncertainty to calculate the expected duration and variance for each activity in a PERT network analysis.
This document discusses network techniques like PERT (Program Evaluation and Review Technique) and CPM (Critical Path Method) which are used for scheduling projects. It provides examples of networking activities with earliest and latest start/finish times to identify the critical path. The critical path is the longest path through the network that determines the minimum project duration. Non-critical activities have float or slack time and can be delayed without extending the project completion time. The document also discusses using three time estimates (optimistic, most likely, pessimistic) for activities when there is uncertainty to calculate the expected duration and variance for each activity in a PERT network.
This document discusses network techniques for scheduling projects, including PERT (Program Evaluation and Review Technique) and CPM (Critical Path Method). It provides examples of networking activities with dependencies and calculating earliest and latest start/finish times. The critical path is identified as the longest path through the network with no slack. Slack time shows how long an activity can be delayed without impacting the project completion date. The document also discusses using three time estimates (optimistic, most likely, pessimistic) for activities when there is uncertainty to calculate the expected duration and variance.
This document discusses network techniques like PERT (Program Evaluation and Review Technique) and CPM (Critical Path Method) which are used for scheduling projects. It provides examples of networking activities with earliest and latest start/finish times to identify the critical path. The critical path is the longest path through the network that determines the minimum project duration. Non-critical activities have float or slack time and can be delayed without extending the project completion time. The document also discusses using three time estimates (optimistic, most likely, pessimistic) for activities when there is uncertainty to calculate the expected duration and variance for each activity in a PERT network.
This document discusses scheduling techniques for projects including network diagrams, PERT charts, and critical path analysis. It provides examples of how to construct network diagrams showing the logical dependencies and precedence relationships between tasks. It also demonstrates how to determine the critical path of a project by calculating the earliest and latest start/finish times for each task and identifying which tasks have zero slack and must be completed on schedule for the project to finish on time. Key terms discussed include activities, events, slack, critical path, and the importance of focusing resources on critical path tasks.
This document discusses network techniques like PERT (Program Evaluation and Review Technique) and CPM (Critical Path Method) which are used for scheduling projects. It provides examples of networking activities with earliest and latest start/finish times to identify the critical path. The critical path is the longest path through the network that determines the minimum project duration. Non-critical activities have float or slack time and can be delayed without extending the project completion time. The document also discusses using three time estimates (optimistic, most likely, pessimistic) for activities when there is uncertainty to calculate the expected duration and variance for each activity in a PERT network.
Similar to Project Management Through Gantt & Pert Chart (20)
RFID Shopping Cart - Ahmedabad Mirror - 26 May 2012Vinay Prajapati
Residents of Ahmedabad lost an average of over Rs 8 lakh daily to fraudsters in the past 5 months, with a total loss of Rs 12.47 crore according to police data. Common fraud methods included promises of high returns on investments, jobs, college admissions, prizes, and visa assistance. Notable past fraud cases involved Remo Marketing and Dorado Marketing. Experts call for greater government assistance and awareness for haemophilia patients given the high treatment costs. A daycare centre for seniors and a career counselling workshop on chartered accountancy were also announced. Britain has no plans to upgrade its Ahmedabad office due to ongoing concerns over the 2002 Gujarat riots.
1) BJP leaders LK Advani and Sushma Swaraj did not attend a key party rally in Mumbai due to prior engagements.
2) Party spokesperson said Advani's absence was pre-planned due to a throat infection, while Sushma Swaraj had to attend a program in Ghaziabad the next morning.
3) The party denied there were any rifts among leaders regarding a recent amendment allowing the party president a second term.
This document provides a summary of a presentation comparing successful and failed entrepreneurs. It discusses N.R. Narayana Murthy, the successful founder and former CEO of Infosys, highlighting his education and role in founding the major Indian IT company. It then outlines common attributes of successful entrepreneurs and strategies used by Infosys. In contrast, it examines B. Ramalinga Raju, the founder of Satyam Computers, discussing how he built the company but then orchestrated a major accounting scandal, inflating financial reports for personal gain until the fraud was discovered. The document analyzes reasons for Raju's failed entrepreneurship compared to Murthy's success.
The document provides an overview of Modelama Exports Ltd., an apparel production company based in Gurgaon, India. It details the company's history, facilities, organizational structure, production capacity, major departments, and the products it manufactures. The report serves as an account of a 3-month internship at Modelama Exports Ltd. across its various production departments.
The document provides information about Modelama Exports Pvt Ltd, an Indian garment manufacturing company. It details the company's address, leadership, annual turnover, facilities, vision, mission and manufacturing process. The company has over 500,000 square feet of production space and 5,500 employees. It aims to balance ethics and profits while expanding into new business sectors. Production involves cutting, spreading, marker planning, and quality checkpoints.
The presentation is about a website called "Fashion Reveries" created by Vinay Prajapati and Urvi Shanischara. The website aims to be a platform for models to showcase their talents and achieve their dreams of becoming successful models by allowing them to freely register and upload their biodata and pictures.
This presentation was prepared by 4 students (Atul, Kuldeep, Navneet & Vinay Prajapati). Subject was Entrepreneurship Management & Business Development.
The document provides technical specifications for several CAD/CAM systems:
The GERBER XLc7000 can cut materials up to 7.2 cm thick and 2 meters wide, with features like a bristle cutting surface, touchscreen interface, and vacuum system to hold materials firmly.
The Lectra VectorAuto MP9 can cut materials up to 9 cm thick and is suited for automotive interior parts, with an intuitive interface, variable vacuum, and software to guide operators.
The Investronica Diamond has a 70 mm cutting height, automatic material conveyance, digital control unit, and balanced knife technology to accurately cut difficult fabrics like denim.
This document outlines quality procedures and responsibilities for a garment manufacturing organization. It defines quality, quality control, and total quality management. It then describes the organizational structure and responsibilities of key quality roles, including the managing director, general manager of quality assurance central, manager of quality assurance central, and manager of quality assurance at the factory level. Their responsibilities include developing and implementing quality systems, conducting inspections, ensuring standards are met, and facilitating continuous improvement.
This presentation provides an overview of the Levi's brand and company. Some key points:
- Levi Strauss & Co. was founded in 1853 and is best known for its Levi's jeans brand.
- It has experienced growth internationally since the 1960s and now has over 10,500 employees worldwide.
- Levi's has a wide product line of jeans, shirts, jackets and other apparel for men, women and kids at various price points.
- The company focuses on promotion through advertising, sponsorships and CSR initiatives.
The document provides a summary of Navneet Kr. Yadav and Vinay Prajapati's internship report from their internship at Bharat Vijay Mills (BVM) in Kalol, India. It acknowledges those who supported and guided them during their internship. It then provides an overview of BVM, including details about the company's history, products, infrastructure, processes from fiber to fabric, and organizational hierarchy. The document describes the various departments within BVM such as spinning, weaving, dyeing and processing.
The document discusses social networking and defines it as communicating and sharing information between individuals online. It provides details on how social networking works, popular sites like Facebook and Twitter, and common activities on social networks like creating profiles, sharing photos and messages. The document also covers privacy, security issues, and options for creating your own social networking site.
Role of IPR in creativity and knowledge economy vinay & kathirVinay Prajapati
Intellectual property rights play an important role in creativity and knowledge economy in three key ways:
1) IPR provides incentives for individuals and organizations to invest time and resources into developing innovative products, technologies, and expanding knowledge by allowing them to benefit financially from their innovations.
2) IPR protects creators' work by preventing others from copying or unfairly profiting from their creative works and innovations without permission.
3) Strong IPR protections are essential for knowledge economy companies and industries that rely on developing and commercializing new knowledge, as it allows them to protect their valuable intellectual assets and recoup investments in research and development.
A review of the growth of the Israel Genealogy Research Association Database Collection for the last 12 months. Our collection is now passed the 3 million mark and still growing. See which archives have contributed the most. See the different types of records we have, and which years have had records added. You can also see what we have for the future.
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...PECB
Denis is a dynamic and results-driven Chief Information Officer (CIO) with a distinguished career spanning information systems analysis and technical project management. With a proven track record of spearheading the design and delivery of cutting-edge Information Management solutions, he has consistently elevated business operations, streamlined reporting functions, and maximized process efficiency.
Certified as an ISO/IEC 27001: Information Security Management Systems (ISMS) Lead Implementer, Data Protection Officer, and Cyber Risks Analyst, Denis brings a heightened focus on data security, privacy, and cyber resilience to every endeavor.
His expertise extends across a diverse spectrum of reporting, database, and web development applications, underpinned by an exceptional grasp of data storage and virtualization technologies. His proficiency in application testing, database administration, and data cleansing ensures seamless execution of complex projects.
What sets Denis apart is his comprehensive understanding of Business and Systems Analysis technologies, honed through involvement in all phases of the Software Development Lifecycle (SDLC). From meticulous requirements gathering to precise analysis, innovative design, rigorous development, thorough testing, and successful implementation, he has consistently delivered exceptional results.
Throughout his career, he has taken on multifaceted roles, from leading technical project management teams to owning solutions that drive operational excellence. His conscientious and proactive approach is unwavering, whether he is working independently or collaboratively within a team. His ability to connect with colleagues on a personal level underscores his commitment to fostering a harmonious and productive workplace environment.
Date: May 29, 2024
Tags: Information Security, ISO/IEC 27001, ISO/IEC 42001, Artificial Intelligence, GDPR
-------------------------------------------------------------------------------
Find out more about ISO training and certification services
Training: ISO/IEC 27001 Information Security Management System - EN | PECB
ISO/IEC 42001 Artificial Intelligence Management System - EN | PECB
General Data Protection Regulation (GDPR) - Training Courses - EN | PECB
Webinars: https://pecb.com/webinars
Article: https://pecb.com/article
-------------------------------------------------------------------------------
For more information about PECB:
Website: https://pecb.com/
LinkedIn: https://www.linkedin.com/company/pecb/
Facebook: https://www.facebook.com/PECBInternational/
Slideshare: http://www.slideshare.net/PECBCERTIFICATION
LAND USE LAND COVER AND NDVI OF MIRZAPUR DISTRICT, UPRAHUL
This Dissertation explores the particular circumstances of Mirzapur, a region located in the
core of India. Mirzapur, with its varied terrains and abundant biodiversity, offers an optimal
environment for investigating the changes in vegetation cover dynamics. Our study utilizes
advanced technologies such as GIS (Geographic Information Systems) and Remote sensing to
analyze the transformations that have taken place over the course of a decade.
The complex relationship between human activities and the environment has been the focus
of extensive research and worry. As the global community grapples with swift urbanization,
population expansion, and economic progress, the effects on natural ecosystems are becoming
more evident. A crucial element of this impact is the alteration of vegetation cover, which plays a
significant role in maintaining the ecological equilibrium of our planet.Land serves as the foundation for all human activities and provides the necessary materials for
these activities. As the most crucial natural resource, its utilization by humans results in different
'Land uses,' which are determined by both human activities and the physical characteristics of the
land.
The utilization of land is impacted by human needs and environmental factors. In countries
like India, rapid population growth and the emphasis on extensive resource exploitation can lead
to significant land degradation, adversely affecting the region's land cover.
Therefore, human intervention has significantly influenced land use patterns over many
centuries, evolving its structure over time and space. In the present era, these changes have
accelerated due to factors such as agriculture and urbanization. Information regarding land use and
cover is essential for various planning and management tasks related to the Earth's surface,
providing crucial environmental data for scientific, resource management, policy purposes, and
diverse human activities.
Accurate understanding of land use and cover is imperative for the development planning
of any area. Consequently, a wide range of professionals, including earth system scientists, land
and water managers, and urban planners, are interested in obtaining data on land use and cover
changes, conversion trends, and other related patterns. The spatial dimensions of land use and
cover support policymakers and scientists in making well-informed decisions, as alterations in
these patterns indicate shifts in economic and social conditions. Monitoring such changes with the
help of Advanced technologies like Remote Sensing and Geographic Information Systems is
crucial for coordinated efforts across different administrative levels. Advanced technologies like
Remote Sensing and Geographic Information Systems
9
Changes in vegetation cover refer to variations in the distribution, composition, and overall
structure of plant communities across different temporal and spatial scales. These changes can
occur natural.
This document provides an overview of wound healing, its functions, stages, mechanisms, factors affecting it, and complications.
A wound is a break in the integrity of the skin or tissues, which may be associated with disruption of the structure and function.
Healing is the body’s response to injury in an attempt to restore normal structure and functions.
Healing can occur in two ways: Regeneration and Repair
There are 4 phases of wound healing: hemostasis, inflammation, proliferation, and remodeling. This document also describes the mechanism of wound healing. Factors that affect healing include infection, uncontrolled diabetes, poor nutrition, age, anemia, the presence of foreign bodies, etc.
Complications of wound healing like infection, hyperpigmentation of scar, contractures, and keloid formation.
বাংলাদেশের অর্থনৈতিক সমীক্ষা ২০২৪ [Bangladesh Economic Review 2024 Bangla.pdf] কম্পিউটার , ট্যাব ও স্মার্ট ফোন ভার্সন সহ সম্পূর্ণ বাংলা ই-বুক বা pdf বই " সুচিপত্র ...বুকমার্ক মেনু 🔖 ও হাইপার লিংক মেনু 📝👆 যুক্ত ..
আমাদের সবার জন্য খুব খুব গুরুত্বপূর্ণ একটি বই ..বিসিএস, ব্যাংক, ইউনিভার্সিটি ভর্তি ও যে কোন প্রতিযোগিতা মূলক পরীক্ষার জন্য এর খুব ইম্পরট্যান্ট একটি বিষয় ...তাছাড়া বাংলাদেশের সাম্প্রতিক যে কোন ডাটা বা তথ্য এই বইতে পাবেন ...
তাই একজন নাগরিক হিসাবে এই তথ্য গুলো আপনার জানা প্রয়োজন ...।
বিসিএস ও ব্যাংক এর লিখিত পরীক্ষা ...+এছাড়া মাধ্যমিক ও উচ্চমাধ্যমিকের স্টুডেন্টদের জন্য অনেক কাজে আসবে ...
A workshop hosted by the South African Journal of Science aimed at postgraduate students and early career researchers with little or no experience in writing and publishing journal articles.
This slide is special for master students (MIBS & MIFB) in UUM. Also useful for readers who are interested in the topic of contemporary Islamic banking.
हिंदी वर्णमाला पीपीटी, hindi alphabet PPT presentation, hindi varnamala PPT, Hindi Varnamala pdf, हिंदी स्वर, हिंदी व्यंजन, sikhiye hindi varnmala, dr. mulla adam ali, hindi language and literature, hindi alphabet with drawing, hindi alphabet pdf, hindi varnamala for childrens, hindi language, hindi varnamala practice for kids, https://www.drmullaadamali.com
How to Make a Field Mandatory in Odoo 17Celine George
In Odoo, making a field required can be done through both Python code and XML views. When you set the required attribute to True in Python code, it makes the field required across all views where it's used. Conversely, when you set the required attribute in XML views, it makes the field required only in the context of that particular view.
How to Setup Warehouse & Location in Odoo 17 InventoryCeline George
In this slide, we'll explore how to set up warehouses and locations in Odoo 17 Inventory. This will help us manage our stock effectively, track inventory levels, and streamline warehouse operations.
3. PERT Chart
Background
∞PERT stands for Program Evaluation & Review
Technique.
∞PERT chart is a task and event oriented
technique.
∞PERT was developed by consultants at Booz
Allen Hamilton for the U.S. Navy in 1957 to
support the development of missile programs.
4. PERT Chart
Uses
∞To plan, analyze and coordinate tasks within a
project.
∞PERT is used in projects where time rather
than cost is the major consideration.
∞Useful for organizing tasks and establishing
time frames, and for showing tasks that
depend on other tasks.
5. PERT Chart
Merits
∞Gives a clear way of representing the
dependencies and order of work/tasks to be
completed.
∞PERT is helpful to plan what tasks can go on
simultaneously to reduce time.
∞Allows identification of the critical path and the
minimum time needed to complete the total
project.
∞Provides for potentially reduced project duration
due to better understanding of dependencies.
6. Project
Network
∞ Activity-on-node (AON)
- Nodes represent activities, and
arrows show precedence Node
relationships
∞ Activity-on-arrow (AOA)
- Arrows represent activities and 1 2 3
nodes are events for points in
time
∞ Event Branch
- Completion or beginning of an
activity in a project
7. Critical
Path
Definition The longest path through a
PERT chart/Network diagram
and determines the shortest
time to complete the project
8. Slack/
Float
The amount of time an activity can be
TOTAL SLACK delayed without delaying the project
end date
The amount of time an activity can be
FREE SLACK delayed without delaying the early start
date of its successor(s)
PROJECT SLACK The amount of time a Project can be
delayed without delaying the externally
imposed project completion date
required by the customer
9. Slack/Float
Calculation
Forward
ES EF Pass
Slack/Float
Backward LS LF
Pass
ES: Early Start Slack/Float= LS-ES
LS: Late Start Slack/Float= EF-LF
EF: Early Finish
LF: Late Finish
10. Critical Path
Example
D=4
2 5
A=1 H=6
E=5
B=2 F=4 J=3
1 3 6 8
I=2
C=3
4 7
G=6
Path 1: A-D-H-J Length=1+4+6+3=14 day Since the critical path is the longest path
Path 2: B-E-H-J Length=2+5+6+3=16 day through the network diagram, Path 2,
Path 3: B-F-J Length=2+4+3=9 day B-E-H-J, is the critical path.
Path 4: C-G-I-J Length=3+6+2+3=14 day
12. Gantt Chart
Background
∞A Gantt chart is a graphical representation of
the duration of tasks against the progression
of time.
∞A Gantt chart is a useful tool for planning and
scheduling projects.
∞The chart is named after Henry Gantt, who
developed it between1910 and1915.
13. Gantt Chart
Uses
∞A Gantt Chart helps to visualize and plan project
tasks with start and finish dates.
∞ A Gantt chart is helpful when monitoring a project's
progress.
∞Gantt Charts are able to show the dependency
relationships between tasks, the critical path, and
the current completion status.
14. Gantt Chart
Merits
∞Gives a clear way of representing the
dependencies and order of work/tasks to be
completed.
∞Gantt is helpful to plan what tasks can go on
simultaneously to reduce time.
∞Allows identification of the critical path and the
minimum time needed to complete the total
project.
∞Allows both planning and monitoring/control.
16. Gantt Chart
Example
Sample Work Breakdown Structure
Immediate
Activity Duration Predecessor
A 14 Start of Project
B 3 Start of Project
14
C 3 A,B
Task A D 7 B
3 E 4 C,D
Task B F 10 E
3
Task C
7
31
Task D 4
Task E 10
Task F . . . . . . . . .
Time
18. Setup
MS Project 2010
∞ Select File, Options, click on “Schedule” tab
∞ For Calendar options for this project: “Select “All New
Projects”
∞ For Scheduling options for this project: select “All New
Projects”
∞ For New Tasks Created: select “Auto Scheduled”
∞ For Duration is entered in: select “weeks”
∞ For default task type: select “fixed duration”
∞ Make sure New tasks are effort driven is NOT checked
∞ Click OK when finished
20. Creating
First Project
∞ Click on Project, Project Information, select
10/3/11 as the Start date, click OK
∞ Click on Save as, type in project name such as
Demo, click OK
∞ Your project is saved as Project1.mpp
22. Example
Project
Task, Duration, and Immediate Predecessor Information for Construction Project
IMMEDIATE DURATION
TASK DESCRIPTION PREDECESSORS (WEEKS)
1 START -- 0
2 Excavate and Pour Footers 1 3
3 Pour Concrete Foundation 2 1
4 Erect Rough Wall & Roof 3 4
5 Install Siding 4 6
6 Install Plumbing 4 3
7 Install Electrical 4 4
8 Install Wallboard 6,7 5
9 Lay Flooring 8 6
10 Do Interior Painting 8 3
11 Install Interior Fixtures 9,10 3
12 Install Gutters & Downspouts 5 2
13 Do Grading & Landscaping 12 3
14 FINISH 11,13 0
23. Entering
Task Information
∞ Default view, Entry table on left, Gantt Chart on right
∞ You can delete the two left-most columns, “i” and “task
mode” by highlighting these columns and pressing the
“delete” key (not needed by us)
- Task numbers now in left-most column
∞ Enter task name and duration in their field
- The default is weeks or “w”
- “d” for days and “h” for hours can be used
∞ Enter predecessor task number(s) in the “Predecessors”
field
∞ MS Project automatically gives start and finish dates based
on critical path analysis
25. Task
Information
Double-clicking on a task name opens the Task Information” screen
26. Project
Charts
∞ The Gantt Chart view shows task linkages
- Since START and FINISH are dummy activities with 0
duration, they are milestones in MS Project (black
diamonds)
- Right-click on dates in the chart and then “zoom” as
desired
∞ Change view to Network Diagram by clicking on
“View” in the menu and then select “Network
Diagram” (zoom as desired)
29. Analysis
Critical Path
∞ MS Project 2010 automatically computes the
critical path and the earliest and latest start and
finish times and slack
∞ Project, Project Information, Statistics shows the
critical path is 26 weeks in our project
31. Analysis
Critical Path
∞ Use the “Detail Gantt” to best display the critical
path
- Select “View”, “Other Views”, “More Views”, “Detail
Gantt” then “Apply”
∞ Use the “Schedule Table” to display all of the early
and late start and finish information, along with
total and free slack
- Again from “View”, select “Table”, and then
“Schedule”
33. Analysis
Critical Path
∞ Critical path tasks can be identified as those have zero
total slack (TS) or float
- TS = LF – EF = LS – ES
- The TS of only 1 task can be used if we want to be certain
about not delaying the project
∞ Free slack (FS) of a task is the difference between the
smallest of the ES’s of the task’s immediate successors
and the task’s EF.
- Using FS does not affect the start times of a task’s
successors
- FS <= TS
- FS of multiple tasks can be used without delaying the
project
∞ FS is shown on the Detail Gantt
34. Analysis
Critical Path
∞ Notice that tasks 12 and 13 both have 7 weeks of total
slack
∞ However, if task 12 uses this slack, it is not available to task
13, so its slack is not free
- Tasks 12 and 13 are linked, so delaying the start of 12 delays
the start of 13 by the same amount
35. Summary
Tasks
∞ Summary tasks can be used to better organize a
project (see constructions.mpp)
∞ We add three summary tasks: Structure, Interior,
and Exterior
∞ Structure includes current tasks 2 – 4, Interior
includes 6 – 11, Exterior includes 5, 12, 13
∞ Example: highlight “Excavate and Pour Footers,” click
on “Tasks”, click on” Summary,” enter “Structure”
- Indent first three tasks under “Structure” by
highlighting them and selecting “indent” (thick green
arrow going to the right)
37. Video
Tutorials
Introduction to Microsoft Project 2010 Part 1 of 2 [OPEN]
Introduction to Microsoft Project 2010 Part 2 of 2 [OPEN]
Microsoft Project 2010 Video Training Tutorial - Creating a Project [OPEN]
Microsoft Project 2010 Video Training Tutorial - The Workspace - Part 1 [OPEN]
Microsoft Project 2010 Video Training Tutorial - The Workspace - Part 2 [OPEN]
Microsoft Project 2010 Video Training Tutorial - Tracking Costs [OPEN]
Project 2010 - Create a Project Plan [OPEN]
Tour of the Microsoft Project 2010 Interface [OPEN]