SlideShare a Scribd company logo
1 of 29
EE 369
POWER SYSTEM ANALYSIS
Lecture 17
Optimal Power Flow, LMPs
Tom Overbye and Ross Baldick
1
Announcements
Read Chapter 7.
Homework 12 is 6.59, 6.61, 12.19, 12.22,
12.24, 12.26, 12.28, 7.1, 7.3, 7.4, 7.5, 7.6,
7.9, 7.12, 7.16; due Thursday, 12/3.
2
Electricity Markets
• Over last 20 years electricity markets have
moved from bilateral contracts between
utilities to also include centralized markets
operated by Independent System
Operators/Regional Transmission Operators:
– Day-ahead market that establishes unit
commitment and “forward financial positions,”
– Real-time market, run every 5 or 15 minutes that
arranges for physical dispatch, the “spot” market.
• Basic “engine” for operating centralized
markets is Optimal Power Flow (OPF). 3
Electricity Markets
OPF is used as basis for day-ahead and real-
time dispatch pricing in US ISO/RTO electricity
markets:
MISO, PJM, ISO-NE, NYISO, SPP, CA, and ERCOT.
Electricity (MWh) is treated as a commodity
(like corn, coffee, natural gas) but with the
extent of the market limited by transmission
system constraints.
Tools of commodity trading have been widely
adopted (options, forwards, hedges, swaps).
4
Electricity Futures Example
Source: Wall Street Journal Online, 10/30/08 5
“Ideal” Power Market
Ideal power market is analogous to a lake.
Generators supply energy to lake and loads
remove energy.
Ideal power market has no transmission
constraints
Single marginal cost associated with enforcing
constraint that supply = demand
– buy from the least cost unit that is not at a limit
– this price is the marginal cost.
This solution is identical to the economic
dispatch problem solution. 6
Two Bus ED Example
Total Hourly Cost :
Bus A Bus B
300.0 MWMW
199.6 MWMW 400.4 MWMW
300.0 MWMW
8459 $/hr
Area Lambda : 13.02
AGC ON AGC ON
7
Market Marginal (Incremental)
Cost
0 175 350 525 700
Generator Power (MW)
12.00
13.00
14.00
15.00
16.00
Below are some graphs associated with this two bus system. The graph on left
shows the marginal cost for each of the generators. The graph on the right
shows the system supply curve, assuming the system is optimally dispatched.
Current generator operating point
0 350 700 1050 1400
Total Area Generation (MW)
12.00
13.00
14.00
15.00
16.00
8
Real Power Markets
Different operating regions impose
constraints – may limit ability to achieve
economic dispatch “globally.”
Transmission system imposes constraints on
the market:
Marginal costs differ at different buses.
Optimal dispatch solution requires solution by
an optimal power flow
Charging for energy based on marginal costs
at different buses is called “locational
marginal pricing” (LMP) or “nodal” pricing. 9
Pricing Electricity
LMP indicates the additional cost to supply an
additional amount of electricity to bus.
All North American ISO/RTO electricicity markets
price wholesale energy at LMP.
If there were no transmission limitations then the
LMPs would be the same at all buses:
Equal to value of lambda from economic dispatch.
Transmission constraints result in differing LMPs at
buses.
Determination of LMPs requires the solution of an
“Optimal Power Flow” (OPF).
10
Optimal Power Flow (OPF)
OPF functionally combines the power flow
with economic dispatch.
Minimize cost function, such as operating
cost, taking into account realistic equality and
inequality constraints.
Equality constraints:
– bus real and reactive power balance
– generator voltage setpoints
– area MW interchange
11
OPF, cont’d
Inequality constraints:
– transmission line/transformer/interface flow
limits
– generator MW limits
– generator reactive power capability curves
– bus voltage magnitudes (not yet implemented in
Simulator OPF)
Available Controls:
– generator MW outputs
– transformer taps and phase angles 12
OPF Solution Methods
Non-linear approach using Newton’s method:
– handles marginal losses well, but is relatively slow
and has problems determining binding constraints
Linear Programming (LP):
– fast and efficient in determining binding
constraints, but can have difficulty with marginal
losses.
– used in PowerWorld Simulator
13
LP OPF Solution Method
Solution iterates between:
– solving a full ac power flow solution
enforces real/reactive power balance at each bus
enforces generator reactive limits
system controls are assumed fixed
takes into account non-linearities
– solving an LP
changes system controls to enforce linearized
constraints while minimizing cost
14
Two Bus with Unconstrained Line
Total Hourly Cost :
Bus A Bus B
300.0 MWMW
197.0 MWMW 403.0 MWMW
300.0 MWMW
8459 $/hr
Area Lambda : 13.01
AGC ON AGC ON
13.01 $/MWh 13.01 $/MWh
Transmission line
is not overloaded
With no
overloads the
OPF matches
the economic
dispatch
Marginal cost of supplying
power to each bus (locational
marginal costs)
This would be price paid by load
and paid to the generators. 15
Two Bus with Constrained Line
Total Hourly Cost :
Bus A Bus B
380.0 MWMW
260.9 MWMW 419.1 MWMW
300.0 MWMW
9513 $/hr
Area Lambda : 13.26
AGC ON AGC ON
13.43 $/MWh 13.08 $/MWh
With the line loaded to its limit, additional load at Bus A must be supplied
locally, causing the marginal costs to diverge.
Similarly, prices paid by load and paid to generators will differ bus by bus.
(In practice, some markets such as ERCOT charge zonal averaged price to load.)
16
Three Bus (B3) Example
Consider a three bus case (bus 1 is system
slack), with all buses connected through 0.1
pu reactance lines, each with a 100 MVA limit.
Let the generator marginal costs be:
– Bus 1: 10 $ / MWhr; Range = 0 to 400 MW,
– Bus 2: 12 $ / MWhr; Range = 0 to 400 MW,
– Bus 3: 20 $ / MWhr; Range = 0 to 400 MW,
Assume a single 180 MW load at bus 2.
17
Bus 2 Bus 1
Bus 3
Total Cost
0.0 MW
0 MW
180 MW
10.00 $/MWh
60 MW 60 MW
60 MW
60 MW
120 MW
120 MW
10.00 $/MWh
10.00 $/MWh
180.0 MW
0 MW
1800 $/hr
120%
120%
B3 with Line Limits NOT Enforced
Line from Bus 1
to Bus 3 is over-
loaded; all buses
have same
marginal cost
(but not allowed to
dispatch to overload
line!)
18
B3 with Line Limits Enforced
Bus 2 Bus 1
Bus 3
Total Cost
60.0 MW
0 MW
180 MW
12.00 $/MWh
20 MW 20 MW
80 MW
80 MW
100 MW
100 MW
10.00 $/MWh
14.00 $/MWh
120.0 MW
0 MW
1920 $/hr
100%
100%
LP OPF redispatches
to remove violation.
Bus marginal
costs are now
different.
Prices will be different
at each bus.
19
Bus 2 Bus 1
Bus 3
Total Cost
62.0 MW
0 MW
181 MW
12.00 $/MWh
19 MW 19 MW
81 MW
81 MW
100 MW
100 MW
10.00 $/MWh
14.00 $/MWh
119.0 MW
0 MW
1934 $/hr
81%
81%
100%
100%
Verify Bus 3 Marginal Cost
One additional MW
of load at bus 3
raised total cost by
14 $/hr, as G2 went
up by 2 MW and G1
went down by 1MW.
20
Why is bus 3 LMP = $14 /MWh ?
All lines have equal impedance. Power flow
in a simple network distributes inversely to
impedance of path.
– For bus 1 to supply 1 MW to bus 3, 2/3 MW would
take direct path from 1 to 3, while 1/3 MW would
“loop around” from 1 to 2 to 3.
– Likewise, for bus 2 to supply 1 MW to bus 3,
2/3MW would go from 2 to 3, while 1/3 MW
would go from 2 to 1to 3.
21
Why is bus 3 LMP $ 14 / MWh,
cont’d
With the line from 1 to 3 limited, no
additional power flows are allowed on it.
To supply 1 more MW to bus 3 we need:
– Extra production of 1MW: Pg1 + Pg2 = 1 MW
– No more flow on line 1 to 3: 2/3 Pg1 + 1/3 Pg2 = 0;
 Solving requires we increase Pg2 by 2 MW and
decrease Pg1 by 1 MW – for a net increase of
$14/h for the 1 MW increase.
That is, the marginal cost of delivering power22
Both lines into Bus 3 Congested
Bus 2 Bus 1
Bus 3
Total Cost
100.0 MW
4 MW
204 MW
12.00 $/MWh
0 MW 0 MW
100 MW
100 MW
100 MW
100 MW
10.00 $/MWh
20.00 $/MWh
100.0 MW
0 MW
2280 $/hr
100% 100%
100% 100% For bus 3 loads
above 200 MW,
the load must be
supplied locally.
Then what if the
bus 3 generator
breaker opens?
23
Typical Electricity Markets
Electricity markets trade various
commodities, with MWh being the most
important.
A typical market has two settlement periods:
day ahead and real-time:
– Day Ahead: Generators (and possibly loads)
submit offers for the next day (offer roughly
represents marginal costs); OPF is used to
determine who gets dispatched based upon
forecasted conditions. Results are “financially”
binding: either generate or pay for someone else.
– Real-time: Modifies the conditions from the day 24
Payment
Generators are not paid their offer, rather they
are paid the LMP at their bus, while the loads
pay the LMP:
In most systems, loads are charged based on a
zonal weighted average of LMPs.
At the residential/small commercial level the
LMP costs are usually not passed on directly to
the end consumer. Rather, these consumers
typically pay a fixed rate that reflects time and
geographical average of LMPs.
LMPs differ across the system due to
transmission system “congestion.” 25
LMPs at 8:55 AM on one day
in Midwest.
Source: www.midwestmarket.org
26
LMPs at 9:30 AM on same day
27
MISO LMP Contours – 10/30/08
28
Limiting Carbon Dioxide Emissions
• There is growing concern about the need to
limit carbon dioxide emissions.
• The two main approaches are 1) a carbon tax,
or 2) a cap-and-trade system (emissions
trading)
• The tax approach involves setting a price and
emitter of CO2 pays based upon how much CO2 is
emitted.
• A cap-and-trade system limits emissions by
requiring permits (allowances) to emit CO2. The
government sets the number of allowances,
allocates them initially, and then private markets set
their prices and allow trade.
29

More Related Content

What's hot

Energy Storage Systems – Grid Connection Using Synchronverters
Energy Storage Systems – Grid Connection Using SynchronvertersEnergy Storage Systems – Grid Connection Using Synchronverters
Energy Storage Systems – Grid Connection Using SynchronvertersGal Barzilai
 
Exp 5 (1)5. Newton Raphson load flow analysis Matlab Software
Exp 5 (1)5.	Newton Raphson load flow analysis Matlab SoftwareExp 5 (1)5.	Newton Raphson load flow analysis Matlab Software
Exp 5 (1)5. Newton Raphson load flow analysis Matlab SoftwareShweta Yadav
 
POWER SYSTEM ANALYSIS-2
POWER SYSTEM ANALYSIS-2POWER SYSTEM ANALYSIS-2
POWER SYSTEM ANALYSIS-2M Ugur Kebir
 
Fundamentals of power system
Fundamentals of power systemFundamentals of power system
Fundamentals of power systemBalaram Das
 
Synchronverters: Inverters that Mimic Synchronous Generators
Synchronverters: Inverters that Mimic Synchronous GeneratorsSynchronverters: Inverters that Mimic Synchronous Generators
Synchronverters: Inverters that Mimic Synchronous GeneratorsQing-Chang Zhong
 
Newton raphson method
Newton raphson methodNewton raphson method
Newton raphson methodNazrul Kabir
 
Exp 4 (1)4. Gauss Siedal Load flow analysis using Matlab Software.
Exp 4 (1)4.	Gauss Siedal Load flow analysis using Matlab Software.Exp 4 (1)4.	Gauss Siedal Load flow analysis using Matlab Software.
Exp 4 (1)4. Gauss Siedal Load flow analysis using Matlab Software.Shweta Yadav
 
Power system analysis material -Mathankumar.s VMKVEC
Power system analysis material -Mathankumar.s  VMKVECPower system analysis material -Mathankumar.s  VMKVEC
Power system analysis material -Mathankumar.s VMKVECMathankumar S
 
L 3,t-1,eee, 2018-2019
L 3,t-1,eee, 2018-2019L 3,t-1,eee, 2018-2019
L 3,t-1,eee, 2018-2019TamimAhmed43
 

What's hot (20)

Energy Storage Systems – Grid Connection Using Synchronverters
Energy Storage Systems – Grid Connection Using SynchronvertersEnergy Storage Systems – Grid Connection Using Synchronverters
Energy Storage Systems – Grid Connection Using Synchronverters
 
Exp 5 (1)5. Newton Raphson load flow analysis Matlab Software
Exp 5 (1)5.	Newton Raphson load flow analysis Matlab SoftwareExp 5 (1)5.	Newton Raphson load flow analysis Matlab Software
Exp 5 (1)5. Newton Raphson load flow analysis Matlab Software
 
Power flow analysis
Power flow analysisPower flow analysis
Power flow analysis
 
Presentación5
Presentación5Presentación5
Presentación5
 
Load flow study
Load flow studyLoad flow study
Load flow study
 
EE6501 - Power System Analysis
EE6501 - Power System AnalysisEE6501 - Power System Analysis
EE6501 - Power System Analysis
 
POWER SYSTEM ANALYSIS-2
POWER SYSTEM ANALYSIS-2POWER SYSTEM ANALYSIS-2
POWER SYSTEM ANALYSIS-2
 
Lecture1
Lecture1Lecture1
Lecture1
 
UDSLF
UDSLFUDSLF
UDSLF
 
Lecture 10
Lecture 10Lecture 10
Lecture 10
 
Fundamentals of power system
Fundamentals of power systemFundamentals of power system
Fundamentals of power system
 
Synchronverters: Inverters that Mimic Synchronous Generators
Synchronverters: Inverters that Mimic Synchronous GeneratorsSynchronverters: Inverters that Mimic Synchronous Generators
Synchronverters: Inverters that Mimic Synchronous Generators
 
PFC - Ducati ANIE 2009
PFC - Ducati ANIE 2009PFC - Ducati ANIE 2009
PFC - Ducati ANIE 2009
 
Newton raphson method
Newton raphson methodNewton raphson method
Newton raphson method
 
Exp 4 (1)4. Gauss Siedal Load flow analysis using Matlab Software.
Exp 4 (1)4.	Gauss Siedal Load flow analysis using Matlab Software.Exp 4 (1)4.	Gauss Siedal Load flow analysis using Matlab Software.
Exp 4 (1)4. Gauss Siedal Load flow analysis using Matlab Software.
 
Per unit analysis
Per unit analysisPer unit analysis
Per unit analysis
 
Fault analysis using z bus
Fault analysis using z busFault analysis using z bus
Fault analysis using z bus
 
Power system analysis material -Mathankumar.s VMKVEC
Power system analysis material -Mathankumar.s  VMKVECPower system analysis material -Mathankumar.s  VMKVEC
Power system analysis material -Mathankumar.s VMKVEC
 
Load flow study
Load flow studyLoad flow study
Load flow study
 
L 3,t-1,eee, 2018-2019
L 3,t-1,eee, 2018-2019L 3,t-1,eee, 2018-2019
L 3,t-1,eee, 2018-2019
 

Viewers also liked

Lecture 17
Lecture 17Lecture 17
Lecture 17farooqdd
 
Health & Beauty Trends Nicolas SCHRIVER (2)
Health & Beauty Trends Nicolas SCHRIVER (2)Health & Beauty Trends Nicolas SCHRIVER (2)
Health & Beauty Trends Nicolas SCHRIVER (2)Nicolas Schriver
 
Scheduling in next generation os
Scheduling in next generation osScheduling in next generation os
Scheduling in next generation osSantosh Nage
 
Development of a Multipurpose Audio Transmission System on the Internet
Development of a Multipurpose Audio Transmission System on the InternetDevelopment of a Multipurpose Audio Transmission System on the Internet
Development of a Multipurpose Audio Transmission System on the InternetTakashi Kishida
 
On-line Power System Static Security Assessment in a Distributed Computing Fr...
On-line Power System Static Security Assessment in a Distributed Computing Fr...On-line Power System Static Security Assessment in a Distributed Computing Fr...
On-line Power System Static Security Assessment in a Distributed Computing Fr...idescitation
 
Study of using particle swarm for optimal power flow
Study of using particle swarm for optimal power flowStudy of using particle swarm for optimal power flow
Study of using particle swarm for optimal power flowMohamed Abuella
 
Thesis for Power System protection in Brief
Thesis for Power System protection in BriefThesis for Power System protection in Brief
Thesis for Power System protection in BriefResident engineer
 
Broadway & Oni: 2015 Africa Financial Intelligence Review
Broadway & Oni: 2015 Africa Financial Intelligence ReviewBroadway & Oni: 2015 Africa Financial Intelligence Review
Broadway & Oni: 2015 Africa Financial Intelligence ReviewBroadway & Oni
 
TRANSIENT STABILITY CONSTRAINTS FOR OPTIMAL POWER FLOW - MATHANKUMAR.S - VMKVEC
TRANSIENT STABILITY CONSTRAINTS FOR OPTIMAL POWER FLOW  - MATHANKUMAR.S - VMKVECTRANSIENT STABILITY CONSTRAINTS FOR OPTIMAL POWER FLOW  - MATHANKUMAR.S - VMKVEC
TRANSIENT STABILITY CONSTRAINTS FOR OPTIMAL POWER FLOW - MATHANKUMAR.S - VMKVECMathankumar S
 
ENHANCEMENT OF POWER SYSTEM SECURITY USING PSO-NR OPTIMIZATION TECHNIQUE
ENHANCEMENT OF POWER SYSTEM SECURITY USING PSO-NR OPTIMIZATION TECHNIQUEENHANCEMENT OF POWER SYSTEM SECURITY USING PSO-NR OPTIMIZATION TECHNIQUE
ENHANCEMENT OF POWER SYSTEM SECURITY USING PSO-NR OPTIMIZATION TECHNIQUEIAEME Publication
 
Optimal generation scheduling of hydropower plant with pumped storage unit
Optimal generation scheduling of hydropower plant with pumped storage unitOptimal generation scheduling of hydropower plant with pumped storage unit
Optimal generation scheduling of hydropower plant with pumped storage unitAlexander Decker
 
Economic dispatch in power systems - Question Bank
Economic dispatch in power systems - Question Bank  Economic dispatch in power systems - Question Bank
Economic dispatch in power systems - Question Bank Mathankumar S
 
11. grid scheduling and resource managament
11. grid scheduling and resource managament11. grid scheduling and resource managament
11. grid scheduling and resource managamentDr Sandeep Kumar Poonia
 
power flow and optimal power flow
power flow and optimal power flowpower flow and optimal power flow
power flow and optimal power flowAhmed M. Elkholy
 
Lect 4 power system protection
Lect 4  power system protectionLect 4  power system protection
Lect 4 power system protectionArslan Ahmed Amin
 

Viewers also liked (20)

Lecture 17
Lecture 17Lecture 17
Lecture 17
 
Shoaib Report
Shoaib ReportShoaib Report
Shoaib Report
 
Ybus
YbusYbus
Ybus
 
Health & Beauty Trends Nicolas SCHRIVER (2)
Health & Beauty Trends Nicolas SCHRIVER (2)Health & Beauty Trends Nicolas SCHRIVER (2)
Health & Beauty Trends Nicolas SCHRIVER (2)
 
Scheduling in next generation os
Scheduling in next generation osScheduling in next generation os
Scheduling in next generation os
 
Development of a Multipurpose Audio Transmission System on the Internet
Development of a Multipurpose Audio Transmission System on the InternetDevelopment of a Multipurpose Audio Transmission System on the Internet
Development of a Multipurpose Audio Transmission System on the Internet
 
On-line Power System Static Security Assessment in a Distributed Computing Fr...
On-line Power System Static Security Assessment in a Distributed Computing Fr...On-line Power System Static Security Assessment in a Distributed Computing Fr...
On-line Power System Static Security Assessment in a Distributed Computing Fr...
 
Lecture 4
Lecture 4Lecture 4
Lecture 4
 
Study of using particle swarm for optimal power flow
Study of using particle swarm for optimal power flowStudy of using particle swarm for optimal power flow
Study of using particle swarm for optimal power flow
 
Mysql Optimization
Mysql OptimizationMysql Optimization
Mysql Optimization
 
Thesis for Power System protection in Brief
Thesis for Power System protection in BriefThesis for Power System protection in Brief
Thesis for Power System protection in Brief
 
Broadway & Oni: 2015 Africa Financial Intelligence Review
Broadway & Oni: 2015 Africa Financial Intelligence ReviewBroadway & Oni: 2015 Africa Financial Intelligence Review
Broadway & Oni: 2015 Africa Financial Intelligence Review
 
TRANSIENT STABILITY CONSTRAINTS FOR OPTIMAL POWER FLOW - MATHANKUMAR.S - VMKVEC
TRANSIENT STABILITY CONSTRAINTS FOR OPTIMAL POWER FLOW  - MATHANKUMAR.S - VMKVECTRANSIENT STABILITY CONSTRAINTS FOR OPTIMAL POWER FLOW  - MATHANKUMAR.S - VMKVEC
TRANSIENT STABILITY CONSTRAINTS FOR OPTIMAL POWER FLOW - MATHANKUMAR.S - VMKVEC
 
ENHANCEMENT OF POWER SYSTEM SECURITY USING PSO-NR OPTIMIZATION TECHNIQUE
ENHANCEMENT OF POWER SYSTEM SECURITY USING PSO-NR OPTIMIZATION TECHNIQUEENHANCEMENT OF POWER SYSTEM SECURITY USING PSO-NR OPTIMIZATION TECHNIQUE
ENHANCEMENT OF POWER SYSTEM SECURITY USING PSO-NR OPTIMIZATION TECHNIQUE
 
Optimal generation scheduling of hydropower plant with pumped storage unit
Optimal generation scheduling of hydropower plant with pumped storage unitOptimal generation scheduling of hydropower plant with pumped storage unit
Optimal generation scheduling of hydropower plant with pumped storage unit
 
Lecture 16
Lecture 16Lecture 16
Lecture 16
 
Economic dispatch in power systems - Question Bank
Economic dispatch in power systems - Question Bank  Economic dispatch in power systems - Question Bank
Economic dispatch in power systems - Question Bank
 
11. grid scheduling and resource managament
11. grid scheduling and resource managament11. grid scheduling and resource managament
11. grid scheduling and resource managament
 
power flow and optimal power flow
power flow and optimal power flowpower flow and optimal power flow
power flow and optimal power flow
 
Lect 4 power system protection
Lect 4  power system protectionLect 4  power system protection
Lect 4 power system protection
 

Similar to Lecture 17

DFisher ETLS 747 Paper - Optimal Power Flow
DFisher ETLS 747 Paper - Optimal Power FlowDFisher ETLS 747 Paper - Optimal Power Flow
DFisher ETLS 747 Paper - Optimal Power FlowDan Fisher
 
Value Quantification of State-of-the-Art Condition Monitoring in 400kV Transm...
Value Quantification of State-of-the-Art Condition Monitoring in 400kV Transm...Value Quantification of State-of-the-Art Condition Monitoring in 400kV Transm...
Value Quantification of State-of-the-Art Condition Monitoring in 400kV Transm...Power System Operation
 
Towards a whole sale electricity market in India
Towards a whole sale electricity market in IndiaTowards a whole sale electricity market in India
Towards a whole sale electricity market in IndiaAmitava Nag
 
Balanced Three Phase Presentation Bansal Berger
Balanced Three Phase Presentation Bansal BergerBalanced Three Phase Presentation Bansal Berger
Balanced Three Phase Presentation Bansal BergerKarl Berger, P.E.
 
Cost of electricity generation
Cost of electricity generationCost of electricity generation
Cost of electricity generationSerajul Haque
 
Multi-Objective based Optimal Energy and Reactive Power Dispatch in Deregulat...
Multi-Objective based Optimal Energy and Reactive Power Dispatch in Deregulat...Multi-Objective based Optimal Energy and Reactive Power Dispatch in Deregulat...
Multi-Objective based Optimal Energy and Reactive Power Dispatch in Deregulat...IJECEIAES
 
Balanced Three-Phase Grid Supply for Traction Power
Balanced Three-Phase Grid Supply for Traction PowerBalanced Three-Phase Grid Supply for Traction Power
Balanced Three-Phase Grid Supply for Traction PowerKarl Berger, P.E.
 
IRJET- Power Management System for Electric Vehicle Charging Stations using F...
IRJET- Power Management System for Electric Vehicle Charging Stations using F...IRJET- Power Management System for Electric Vehicle Charging Stations using F...
IRJET- Power Management System for Electric Vehicle Charging Stations using F...IRJET Journal
 
USAGE BASED COST ALLOCATION TECHNIQUE FOR EHV NETWORKS USING NON-LINEAR UTILI...
USAGE BASED COST ALLOCATION TECHNIQUE FOR EHV NETWORKS USING NON-LINEAR UTILI...USAGE BASED COST ALLOCATION TECHNIQUE FOR EHV NETWORKS USING NON-LINEAR UTILI...
USAGE BASED COST ALLOCATION TECHNIQUE FOR EHV NETWORKS USING NON-LINEAR UTILI...ELELIJ
 
Computer Application in Power system: Chapter six - optimization and security
Computer Application in Power system: Chapter six - optimization and securityComputer Application in Power system: Chapter six - optimization and security
Computer Application in Power system: Chapter six - optimization and securityAdama Science and Technology University
 
Rehabilitation of nablus electrical network by adding a new connection point
Rehabilitation of nablus electrical network by adding a new connection pointRehabilitation of nablus electrical network by adding a new connection point
Rehabilitation of nablus electrical network by adding a new connection pointslmnsvn
 
Economic operation of power system
Economic operation of power systemEconomic operation of power system
Economic operation of power systemBalaram Das
 
Congestion Management Approaches in Deregulated Electricity Market: A Compreh...
Congestion Management Approaches in Deregulated Electricity Market: A Compreh...Congestion Management Approaches in Deregulated Electricity Market: A Compreh...
Congestion Management Approaches in Deregulated Electricity Market: A Compreh...Dr. Sudhir Kumar Srivastava
 

Similar to Lecture 17 (20)

Unit 5.pptx
Unit 5.pptxUnit 5.pptx
Unit 5.pptx
 
DFisher ETLS 747 Paper - Optimal Power Flow
DFisher ETLS 747 Paper - Optimal Power FlowDFisher ETLS 747 Paper - Optimal Power Flow
DFisher ETLS 747 Paper - Optimal Power Flow
 
Value Quantification of State-of-the-Art Condition Monitoring in 400kV Transm...
Value Quantification of State-of-the-Art Condition Monitoring in 400kV Transm...Value Quantification of State-of-the-Art Condition Monitoring in 400kV Transm...
Value Quantification of State-of-the-Art Condition Monitoring in 400kV Transm...
 
Towards a whole sale electricity market in India
Towards a whole sale electricity market in IndiaTowards a whole sale electricity market in India
Towards a whole sale electricity market in India
 
Lecture_15.ppt
Lecture_15.pptLecture_15.ppt
Lecture_15.ppt
 
Lecture_15.ppt
Lecture_15.pptLecture_15.ppt
Lecture_15.ppt
 
Balanced Three Phase Presentation Bansal Berger
Balanced Three Phase Presentation Bansal BergerBalanced Three Phase Presentation Bansal Berger
Balanced Three Phase Presentation Bansal Berger
 
Cost of electricity generation
Cost of electricity generationCost of electricity generation
Cost of electricity generation
 
2010IEEE
2010IEEE2010IEEE
2010IEEE
 
Multi-Objective based Optimal Energy and Reactive Power Dispatch in Deregulat...
Multi-Objective based Optimal Energy and Reactive Power Dispatch in Deregulat...Multi-Objective based Optimal Energy and Reactive Power Dispatch in Deregulat...
Multi-Objective based Optimal Energy and Reactive Power Dispatch in Deregulat...
 
Finite-Control-Set Predictive Current Control Based Real and Reactive Power C...
Finite-Control-Set Predictive Current Control Based Real and Reactive Power C...Finite-Control-Set Predictive Current Control Based Real and Reactive Power C...
Finite-Control-Set Predictive Current Control Based Real and Reactive Power C...
 
Balanced Three-Phase Grid Supply for Traction Power
Balanced Three-Phase Grid Supply for Traction PowerBalanced Three-Phase Grid Supply for Traction Power
Balanced Three-Phase Grid Supply for Traction Power
 
Ch01-ESR-L02.pdf
Ch01-ESR-L02.pdfCh01-ESR-L02.pdf
Ch01-ESR-L02.pdf
 
IRJET- Power Management System for Electric Vehicle Charging Stations using F...
IRJET- Power Management System for Electric Vehicle Charging Stations using F...IRJET- Power Management System for Electric Vehicle Charging Stations using F...
IRJET- Power Management System for Electric Vehicle Charging Stations using F...
 
USAGE BASED COST ALLOCATION TECHNIQUE FOR EHV NETWORKS USING NON-LINEAR UTILI...
USAGE BASED COST ALLOCATION TECHNIQUE FOR EHV NETWORKS USING NON-LINEAR UTILI...USAGE BASED COST ALLOCATION TECHNIQUE FOR EHV NETWORKS USING NON-LINEAR UTILI...
USAGE BASED COST ALLOCATION TECHNIQUE FOR EHV NETWORKS USING NON-LINEAR UTILI...
 
Computer Application in Power system: Chapter six - optimization and security
Computer Application in Power system: Chapter six - optimization and securityComputer Application in Power system: Chapter six - optimization and security
Computer Application in Power system: Chapter six - optimization and security
 
Rehabilitation of nablus electrical network by adding a new connection point
Rehabilitation of nablus electrical network by adding a new connection pointRehabilitation of nablus electrical network by adding a new connection point
Rehabilitation of nablus electrical network by adding a new connection point
 
PFI GUIDE
PFI GUIDEPFI GUIDE
PFI GUIDE
 
Economic operation of power system
Economic operation of power systemEconomic operation of power system
Economic operation of power system
 
Congestion Management Approaches in Deregulated Electricity Market: A Compreh...
Congestion Management Approaches in Deregulated Electricity Market: A Compreh...Congestion Management Approaches in Deregulated Electricity Market: A Compreh...
Congestion Management Approaches in Deregulated Electricity Market: A Compreh...
 

More from Forward2025

Radar 2009 a 19 electronic counter measures
Radar 2009 a 19 electronic counter measuresRadar 2009 a 19 electronic counter measures
Radar 2009 a 19 electronic counter measuresForward2025
 
Radar 2009 a 18 synthetic aperture radar
Radar 2009 a 18 synthetic aperture radarRadar 2009 a 18 synthetic aperture radar
Radar 2009 a 18 synthetic aperture radarForward2025
 
Radar 2009 a 17 transmitters and receivers
Radar 2009 a 17 transmitters and receiversRadar 2009 a 17 transmitters and receivers
Radar 2009 a 17 transmitters and receiversForward2025
 
Radar 2009 a 16 parameter estimation and tracking part2
Radar 2009 a 16 parameter estimation and tracking part2Radar 2009 a 16 parameter estimation and tracking part2
Radar 2009 a 16 parameter estimation and tracking part2Forward2025
 
Radar 2009 a 15 parameter estimation and tracking part 1
Radar 2009 a 15 parameter estimation and tracking part 1Radar 2009 a 15 parameter estimation and tracking part 1
Radar 2009 a 15 parameter estimation and tracking part 1Forward2025
 
Radar 2009 a 14 airborne pulse doppler radar
Radar 2009 a 14 airborne pulse doppler radarRadar 2009 a 14 airborne pulse doppler radar
Radar 2009 a 14 airborne pulse doppler radarForward2025
 
Radar 2009 a 13 clutter rejection doppler filtering
Radar 2009 a 13 clutter rejection   doppler filteringRadar 2009 a 13 clutter rejection   doppler filtering
Radar 2009 a 13 clutter rejection doppler filteringForward2025
 
Radar 2009 a 12 clutter rejection basics and mti
Radar 2009 a 12 clutter rejection   basics and mtiRadar 2009 a 12 clutter rejection   basics and mti
Radar 2009 a 12 clutter rejection basics and mtiForward2025
 

More from Forward2025 (20)

Lecture 6
Lecture 6Lecture 6
Lecture 6
 
Lecture 5
Lecture 5Lecture 5
Lecture 5
 
Lecture 3
Lecture 3Lecture 3
Lecture 3
 
Lecture 2
Lecture 2Lecture 2
Lecture 2
 
Lecture 18
Lecture 18Lecture 18
Lecture 18
 
Lecture 14
Lecture 14Lecture 14
Lecture 14
 
Lecture 13
Lecture 13Lecture 13
Lecture 13
 
Lecture 12
Lecture 12Lecture 12
Lecture 12
 
Lecture 11
Lecture 11Lecture 11
Lecture 11
 
Lecture 9
Lecture 9Lecture 9
Lecture 9
 
Lecture 8
Lecture 8Lecture 8
Lecture 8
 
Lecture 7
Lecture 7Lecture 7
Lecture 7
 
Radar 2009 a 19 electronic counter measures
Radar 2009 a 19 electronic counter measuresRadar 2009 a 19 electronic counter measures
Radar 2009 a 19 electronic counter measures
 
Radar 2009 a 18 synthetic aperture radar
Radar 2009 a 18 synthetic aperture radarRadar 2009 a 18 synthetic aperture radar
Radar 2009 a 18 synthetic aperture radar
 
Radar 2009 a 17 transmitters and receivers
Radar 2009 a 17 transmitters and receiversRadar 2009 a 17 transmitters and receivers
Radar 2009 a 17 transmitters and receivers
 
Radar 2009 a 16 parameter estimation and tracking part2
Radar 2009 a 16 parameter estimation and tracking part2Radar 2009 a 16 parameter estimation and tracking part2
Radar 2009 a 16 parameter estimation and tracking part2
 
Radar 2009 a 15 parameter estimation and tracking part 1
Radar 2009 a 15 parameter estimation and tracking part 1Radar 2009 a 15 parameter estimation and tracking part 1
Radar 2009 a 15 parameter estimation and tracking part 1
 
Radar 2009 a 14 airborne pulse doppler radar
Radar 2009 a 14 airborne pulse doppler radarRadar 2009 a 14 airborne pulse doppler radar
Radar 2009 a 14 airborne pulse doppler radar
 
Radar 2009 a 13 clutter rejection doppler filtering
Radar 2009 a 13 clutter rejection   doppler filteringRadar 2009 a 13 clutter rejection   doppler filtering
Radar 2009 a 13 clutter rejection doppler filtering
 
Radar 2009 a 12 clutter rejection basics and mti
Radar 2009 a 12 clutter rejection   basics and mtiRadar 2009 a 12 clutter rejection   basics and mti
Radar 2009 a 12 clutter rejection basics and mti
 

Recently uploaded

chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 

Recently uploaded (20)

chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 

Lecture 17

  • 1. EE 369 POWER SYSTEM ANALYSIS Lecture 17 Optimal Power Flow, LMPs Tom Overbye and Ross Baldick 1
  • 2. Announcements Read Chapter 7. Homework 12 is 6.59, 6.61, 12.19, 12.22, 12.24, 12.26, 12.28, 7.1, 7.3, 7.4, 7.5, 7.6, 7.9, 7.12, 7.16; due Thursday, 12/3. 2
  • 3. Electricity Markets • Over last 20 years electricity markets have moved from bilateral contracts between utilities to also include centralized markets operated by Independent System Operators/Regional Transmission Operators: – Day-ahead market that establishes unit commitment and “forward financial positions,” – Real-time market, run every 5 or 15 minutes that arranges for physical dispatch, the “spot” market. • Basic “engine” for operating centralized markets is Optimal Power Flow (OPF). 3
  • 4. Electricity Markets OPF is used as basis for day-ahead and real- time dispatch pricing in US ISO/RTO electricity markets: MISO, PJM, ISO-NE, NYISO, SPP, CA, and ERCOT. Electricity (MWh) is treated as a commodity (like corn, coffee, natural gas) but with the extent of the market limited by transmission system constraints. Tools of commodity trading have been widely adopted (options, forwards, hedges, swaps). 4
  • 5. Electricity Futures Example Source: Wall Street Journal Online, 10/30/08 5
  • 6. “Ideal” Power Market Ideal power market is analogous to a lake. Generators supply energy to lake and loads remove energy. Ideal power market has no transmission constraints Single marginal cost associated with enforcing constraint that supply = demand – buy from the least cost unit that is not at a limit – this price is the marginal cost. This solution is identical to the economic dispatch problem solution. 6
  • 7. Two Bus ED Example Total Hourly Cost : Bus A Bus B 300.0 MWMW 199.6 MWMW 400.4 MWMW 300.0 MWMW 8459 $/hr Area Lambda : 13.02 AGC ON AGC ON 7
  • 8. Market Marginal (Incremental) Cost 0 175 350 525 700 Generator Power (MW) 12.00 13.00 14.00 15.00 16.00 Below are some graphs associated with this two bus system. The graph on left shows the marginal cost for each of the generators. The graph on the right shows the system supply curve, assuming the system is optimally dispatched. Current generator operating point 0 350 700 1050 1400 Total Area Generation (MW) 12.00 13.00 14.00 15.00 16.00 8
  • 9. Real Power Markets Different operating regions impose constraints – may limit ability to achieve economic dispatch “globally.” Transmission system imposes constraints on the market: Marginal costs differ at different buses. Optimal dispatch solution requires solution by an optimal power flow Charging for energy based on marginal costs at different buses is called “locational marginal pricing” (LMP) or “nodal” pricing. 9
  • 10. Pricing Electricity LMP indicates the additional cost to supply an additional amount of electricity to bus. All North American ISO/RTO electricicity markets price wholesale energy at LMP. If there were no transmission limitations then the LMPs would be the same at all buses: Equal to value of lambda from economic dispatch. Transmission constraints result in differing LMPs at buses. Determination of LMPs requires the solution of an “Optimal Power Flow” (OPF). 10
  • 11. Optimal Power Flow (OPF) OPF functionally combines the power flow with economic dispatch. Minimize cost function, such as operating cost, taking into account realistic equality and inequality constraints. Equality constraints: – bus real and reactive power balance – generator voltage setpoints – area MW interchange 11
  • 12. OPF, cont’d Inequality constraints: – transmission line/transformer/interface flow limits – generator MW limits – generator reactive power capability curves – bus voltage magnitudes (not yet implemented in Simulator OPF) Available Controls: – generator MW outputs – transformer taps and phase angles 12
  • 13. OPF Solution Methods Non-linear approach using Newton’s method: – handles marginal losses well, but is relatively slow and has problems determining binding constraints Linear Programming (LP): – fast and efficient in determining binding constraints, but can have difficulty with marginal losses. – used in PowerWorld Simulator 13
  • 14. LP OPF Solution Method Solution iterates between: – solving a full ac power flow solution enforces real/reactive power balance at each bus enforces generator reactive limits system controls are assumed fixed takes into account non-linearities – solving an LP changes system controls to enforce linearized constraints while minimizing cost 14
  • 15. Two Bus with Unconstrained Line Total Hourly Cost : Bus A Bus B 300.0 MWMW 197.0 MWMW 403.0 MWMW 300.0 MWMW 8459 $/hr Area Lambda : 13.01 AGC ON AGC ON 13.01 $/MWh 13.01 $/MWh Transmission line is not overloaded With no overloads the OPF matches the economic dispatch Marginal cost of supplying power to each bus (locational marginal costs) This would be price paid by load and paid to the generators. 15
  • 16. Two Bus with Constrained Line Total Hourly Cost : Bus A Bus B 380.0 MWMW 260.9 MWMW 419.1 MWMW 300.0 MWMW 9513 $/hr Area Lambda : 13.26 AGC ON AGC ON 13.43 $/MWh 13.08 $/MWh With the line loaded to its limit, additional load at Bus A must be supplied locally, causing the marginal costs to diverge. Similarly, prices paid by load and paid to generators will differ bus by bus. (In practice, some markets such as ERCOT charge zonal averaged price to load.) 16
  • 17. Three Bus (B3) Example Consider a three bus case (bus 1 is system slack), with all buses connected through 0.1 pu reactance lines, each with a 100 MVA limit. Let the generator marginal costs be: – Bus 1: 10 $ / MWhr; Range = 0 to 400 MW, – Bus 2: 12 $ / MWhr; Range = 0 to 400 MW, – Bus 3: 20 $ / MWhr; Range = 0 to 400 MW, Assume a single 180 MW load at bus 2. 17
  • 18. Bus 2 Bus 1 Bus 3 Total Cost 0.0 MW 0 MW 180 MW 10.00 $/MWh 60 MW 60 MW 60 MW 60 MW 120 MW 120 MW 10.00 $/MWh 10.00 $/MWh 180.0 MW 0 MW 1800 $/hr 120% 120% B3 with Line Limits NOT Enforced Line from Bus 1 to Bus 3 is over- loaded; all buses have same marginal cost (but not allowed to dispatch to overload line!) 18
  • 19. B3 with Line Limits Enforced Bus 2 Bus 1 Bus 3 Total Cost 60.0 MW 0 MW 180 MW 12.00 $/MWh 20 MW 20 MW 80 MW 80 MW 100 MW 100 MW 10.00 $/MWh 14.00 $/MWh 120.0 MW 0 MW 1920 $/hr 100% 100% LP OPF redispatches to remove violation. Bus marginal costs are now different. Prices will be different at each bus. 19
  • 20. Bus 2 Bus 1 Bus 3 Total Cost 62.0 MW 0 MW 181 MW 12.00 $/MWh 19 MW 19 MW 81 MW 81 MW 100 MW 100 MW 10.00 $/MWh 14.00 $/MWh 119.0 MW 0 MW 1934 $/hr 81% 81% 100% 100% Verify Bus 3 Marginal Cost One additional MW of load at bus 3 raised total cost by 14 $/hr, as G2 went up by 2 MW and G1 went down by 1MW. 20
  • 21. Why is bus 3 LMP = $14 /MWh ? All lines have equal impedance. Power flow in a simple network distributes inversely to impedance of path. – For bus 1 to supply 1 MW to bus 3, 2/3 MW would take direct path from 1 to 3, while 1/3 MW would “loop around” from 1 to 2 to 3. – Likewise, for bus 2 to supply 1 MW to bus 3, 2/3MW would go from 2 to 3, while 1/3 MW would go from 2 to 1to 3. 21
  • 22. Why is bus 3 LMP $ 14 / MWh, cont’d With the line from 1 to 3 limited, no additional power flows are allowed on it. To supply 1 more MW to bus 3 we need: – Extra production of 1MW: Pg1 + Pg2 = 1 MW – No more flow on line 1 to 3: 2/3 Pg1 + 1/3 Pg2 = 0;  Solving requires we increase Pg2 by 2 MW and decrease Pg1 by 1 MW – for a net increase of $14/h for the 1 MW increase. That is, the marginal cost of delivering power22
  • 23. Both lines into Bus 3 Congested Bus 2 Bus 1 Bus 3 Total Cost 100.0 MW 4 MW 204 MW 12.00 $/MWh 0 MW 0 MW 100 MW 100 MW 100 MW 100 MW 10.00 $/MWh 20.00 $/MWh 100.0 MW 0 MW 2280 $/hr 100% 100% 100% 100% For bus 3 loads above 200 MW, the load must be supplied locally. Then what if the bus 3 generator breaker opens? 23
  • 24. Typical Electricity Markets Electricity markets trade various commodities, with MWh being the most important. A typical market has two settlement periods: day ahead and real-time: – Day Ahead: Generators (and possibly loads) submit offers for the next day (offer roughly represents marginal costs); OPF is used to determine who gets dispatched based upon forecasted conditions. Results are “financially” binding: either generate or pay for someone else. – Real-time: Modifies the conditions from the day 24
  • 25. Payment Generators are not paid their offer, rather they are paid the LMP at their bus, while the loads pay the LMP: In most systems, loads are charged based on a zonal weighted average of LMPs. At the residential/small commercial level the LMP costs are usually not passed on directly to the end consumer. Rather, these consumers typically pay a fixed rate that reflects time and geographical average of LMPs. LMPs differ across the system due to transmission system “congestion.” 25
  • 26. LMPs at 8:55 AM on one day in Midwest. Source: www.midwestmarket.org 26
  • 27. LMPs at 9:30 AM on same day 27
  • 28. MISO LMP Contours – 10/30/08 28
  • 29. Limiting Carbon Dioxide Emissions • There is growing concern about the need to limit carbon dioxide emissions. • The two main approaches are 1) a carbon tax, or 2) a cap-and-trade system (emissions trading) • The tax approach involves setting a price and emitter of CO2 pays based upon how much CO2 is emitted. • A cap-and-trade system limits emissions by requiring permits (allowances) to emit CO2. The government sets the number of allowances, allocates them initially, and then private markets set their prices and allow trade. 29