SCHOOL OF ARCHITECTURE, BUILDING & DESIGN (SABD)
BACHELOR OF QUANTITY SURVEYING (HONOURS)
INTEGRATEDASSIGNMENT – SITE VISIT REPORT
MEASUREMENT 1 (QSB 60104)
BUILDING MATERIALS (BLD 62003)
CONSTRUCTION TECHNOLOGY (BLD 60104)
NAME: WONG SHER SHENG
STUDENTID: 0329950
LECTURES: MS ANG FUEY LIN
MS MYZATULAISHAH KAMARAZALY
MS AZRINA MD YAAKOB
.
Table of content
Title Pages
Introduction 1
Objective 2
Content 3
Materials used for concrete
framed building
4
Photos & descriptions 5-12
Conclusion 13
Introduction
We are given an assignment that involves three modules, which are
Measurement 1, Building Materials and Construction Technology 1. All of us are
required to write a report for our construction site visit.
The site visit was held on 23rd November 2016(Wednesday). Lecturers have
briefed us about the safety precaution which we need to obey. Among the
precautions are we need to dress appropriately by wearing long pants with collar t-
shirt, sports shoes with socks and most importantly is wearing safety helmet on site.
The construction site is located at Taman Impian Murni(Lot 3607), Jalan
Tanjung Balai(Lorong Haji Yusof) Seksyen 30, 40460 Shah Alam, Selangor. This
project is to construct 42 units 2&3 storey terrace with land size of 20'x63'. The
contractor of the project is Purcon Group.
The purpose of the site visit is to expose us so that we are able to describe,
explain and understand the method and process of construction in
accordance to the sequence of work on site.
Objective
 To understand the practical aspect of construction techniques in comparison
to theory in the books and its application on site.
 To understand the basics of the construction process.
 To observe the usage of construction equipment on site including mechanical
plants.
 To explore and identify types of building materials and construction
technology used on site.
 To expose us the working environment as a Quantity Surveyor and be able to
deal with some uncertain circumstances such as weather.
 To be aware of the importance of safety on site and understand the safety
problems and site conditions.
 To broaden our horizon with the latest technology used in construction.
 To give us an opportunity to understand the significance of communication
skills while working together as a construction team.
Content
Item in the site that are considered as a concrete frame
Concrete frame building are the most common type of modern building. This
type of building consists of a frame of concrete. The items to be considered that are
considered as a concrete frames in the sites are beams, column and slab.
Horizontal members of the concrete frame are called beams. There are two
types of beam namely suspended beam and non-suspended beam. Suspended beam
are located on the upper floor. Non- suspended beam which also known as ground
beam are used to support brick.
Moving on, the vertical members of the concrete frame are called column.
Column is designed to withstand compressive loads. Column is the most significant
part of the building as it carries the primary load of the building. For example, if you
damage a beam in a building, it will usually affect only one floor, but if damage to a
column could bring down the entire building.
Besides that, a flat plate of concrete that human can walk on it is called slabs.
Suspended slabs are above ground and supported by beams whereas non-
suspended slabs sit on the ground directly.
Materials involved in constructing concrete framed
structure
The concrete used for the whole concrete frame structures is grade 25.
Concrete is a composite materials composed of aggregate bonded with fluid cement
which hardens over time. The ratio of cement to sand to coarse aggregate for
concrete grade 25 is 1:1:2. The grade of the concrete refers to the compression
strength resistance for 28 days. Concrete grade 25 is considered standard concrete.
Concrete in the building trade actually mean reinforced concrete. The full
name of it is reinforced cement concrete(RCC). RCC is concrete that contains steel
bars which also known as reinforcement bar or rebar. This combination works well
as the concrete is very strong in compression, easy to produce at site and affordable.
To make reinforced concrete, one must makes a mould called formwork that
will contain the liquid concrete and give it in the form or shape we need. Secondly,
one should look at the structural engineer’s drawings and places in the steel
reinforcement bar and ties them in place using wire. Once the steel is in place,
concrete is prepared by mixing the cement, sand, aggregates according to the ratio
of certain concrete grade. Concrete will harden in hours but takes months to achieve
its full strength. During this time, concrete must be supplied with water on its
surface.
Photo & description
Steel bar and temporary accommodation for workers
Excavator on site
Portland composite cement
Non-suspended beam
Reinforcement bar
Reinforcement bar in concrete slab
Common burnt clay bricks are well stacked on the floor
Pre-cast concrete bricks
Suspended beam
Column
Suspended slab
Concrete Staircase
Steel bars come out from the column
Pipe structure and wiring system of the house
Plastering wall finishes Zincalume door frames
Zincalume roofing
Conclusion
After the site visit, I have gained some valuable knowledge that we can’t
learn from the textbooks and lectures. I have fully understood the practical aspects
of construction techniques in comparison to theory in the books and its application.
It is more tougher than I thought. Moreover, I have learnt how a construction site
works after the site visit. I have seen various type of tools and equipments used on
site. We were taught by the site contractor about the usage of those equipments.
Besides, I’mable to identify and differentiate types of building materials used
in construction. Through the site visit, I have better understanding about the
working environment as a Quantity Surveyor. They work under uncertainty
circumstances. They need to be careful about the working environment as risks exist
everywhere on site.
Furthermore, I had the opportunity to witness how the construction team
emphasis the safety on the construction site. Safety is their top priorities. Every
workers need to wear safety helmet on site. Even visitors like us need to obey the
rule. This is to ensure our safety during our site visit.
I have learnt that communication skills is crucial. As a construction team, we
need to communicate and works together so that the project can be carried out
smoothly. Teamwork is also an essential element in construction.
We only learn the new knowledge by memorizing those important points due
to our exam-oriented education system. Because of this we can’t experience the real
life working. So through the site visit, we can learn something that we can’t get from
books.
The site visit have brought tons of benefits to me. I am very grateful to have a
chance to site visit. I wish I could have more of this kind of opportunities in the
future as it can prepare a better me for my working in the future.

More Related Content

What's hot

Site report
Site reportSite report
Site report
vaylu
 
Site visit report
Site visit reportSite visit report
Site visit report
Jıa Yıı
 
BQS Site Visit Report
BQS Site Visit ReportBQS Site Visit Report
BQS Site Visit Report
Hasif Alias
 
Introduction
IntroductionIntroduction
Introduction
Lam Yu
 
Site visit report
Site visit reportSite visit report
Site visit report
shensin1015
 
CT site visit report
CT site visit report CT site visit report
CT site visit report Yap Xin
 
Technical site visit report
Technical site visit reportTechnical site visit report
Technical site visit report
Momo Poyi
 
Site visit report qs semester 1
Site visit report   qs semester 1Site visit report   qs semester 1
Site visit report qs semester 1
KhangWei Chin
 
Technical report writing and research methodology course
Technical report writing and research methodology courseTechnical report writing and research methodology course
Technical report writing and research methodology course
Nahom Balcha
 
Site report for Measurement 1
Site report for Measurement 1Site report for Measurement 1
Site report for Measurement 1Yap Xin
 
SITE VISIT ARCHITECTRE
SITE VISIT ARCHITECTRE  SITE VISIT ARCHITECTRE
SITE VISIT ARCHITECTRE
Shourya Puri
 
Site visit report
Site visit report Site visit report
Site visit report
Liming Hiew
 
Site visit report
Site visit reportSite visit report
Site visit report
Jordon Wong
 
site report
site reportsite report
site report
dhirazain
 
Assignment of Site Report
Assignment of Site Report Assignment of Site Report
Assignment of Site Report
I'mMiss Lily
 
Site visit report
Site visit reportSite visit report
Site visit report
foongmei yap
 
site visit report (final)
site visit report (final)site visit report (final)
site visit report (final)
Jia Hong Mui
 
Site visit report
Site visit reportSite visit report
Site visit report
Wen Crystal
 

What's hot (20)

Site report
Site reportSite report
Site report
 
Site visit report
Site visit reportSite visit report
Site visit report
 
Site visit report
Site visit reportSite visit report
Site visit report
 
BQS Site Visit Report
BQS Site Visit ReportBQS Site Visit Report
BQS Site Visit Report
 
Introduction
IntroductionIntroduction
Introduction
 
Site visit report
Site visit reportSite visit report
Site visit report
 
CT site visit report
CT site visit report CT site visit report
CT site visit report
 
Technical site visit report
Technical site visit reportTechnical site visit report
Technical site visit report
 
Site visit report qs semester 1
Site visit report   qs semester 1Site visit report   qs semester 1
Site visit report qs semester 1
 
Technical report writing and research methodology course
Technical report writing and research methodology courseTechnical report writing and research methodology course
Technical report writing and research methodology course
 
Site report
Site reportSite report
Site report
 
Site report for Measurement 1
Site report for Measurement 1Site report for Measurement 1
Site report for Measurement 1
 
SITE VISIT ARCHITECTRE
SITE VISIT ARCHITECTRE  SITE VISIT ARCHITECTRE
SITE VISIT ARCHITECTRE
 
Site visit report
Site visit report Site visit report
Site visit report
 
Site visit report
Site visit reportSite visit report
Site visit report
 
site report
site reportsite report
site report
 
Assignment of Site Report
Assignment of Site Report Assignment of Site Report
Assignment of Site Report
 
Site visit report
Site visit reportSite visit report
Site visit report
 
site visit report (final)
site visit report (final)site visit report (final)
site visit report (final)
 
Site visit report
Site visit reportSite visit report
Site visit report
 

Similar to Integrated assignment site report

Ct bm measurement report
Ct bm measurement reportCt bm measurement report
Ct bm measurement report
Kailyn Lee
 
Measurement 1-site-visit
Measurement 1-site-visitMeasurement 1-site-visit
Measurement 1-site-visit
Pui San
 
Site Visit Report
Site Visit ReportSite Visit Report
Site Visit ReportZIyeeTan
 
Ctw site report(pg 1 to 8, 14)
Ctw site report(pg 1 to 8, 14)Ctw site report(pg 1 to 8, 14)
Ctw site report(pg 1 to 8, 14)Chin Tze Wei
 
Site report
Site reportSite report
Site report
yongseenyee
 
Project SlideShare
Project SlideShareProject SlideShare
Project SlideShare
Yung Kai
 
Site report
Site reportSite report
Site report
Penny3688
 
Site Report
Site Report Site Report
Site Report
Sow Wei Henn
 
bqs Site report
bqs Site reportbqs Site report
bqs Site report
Felix Vong
 
Bachelor in quantity surveying 2
Bachelor in quantity surveying 2Bachelor in quantity surveying 2
Bachelor in quantity surveying 2Arthur Wilson
 
Ez
EzEz
Site report
Site reportSite report
Site report
HuiYik
 
MCB Final report
MCB Final reportMCB Final report
MCB Final report
Lucas ChinSheng
 
Site report
Site reportSite report
Site report
Eric Teo
 
SITE REPORT (PAD FOOTING)
SITE REPORT (PAD FOOTING)SITE REPORT (PAD FOOTING)
SITE REPORT (PAD FOOTING)
I'mMiss Lily
 
Site visit report
Site visit reportSite visit report
Site visit reportDoreen Yeo
 
individual site report sem 1 degree
individual site report sem 1 degreeindividual site report sem 1 degree
individual site report sem 1 degree
Lam Wee
 
A collection of articles on concrete formwork design and construction
A collection of articles on concrete formwork design and constructionA collection of articles on concrete formwork design and construction
A collection of articles on concrete formwork design and construction
Byron Smith
 
Final Report
Final Report Final Report
Final Report
Jack Ng
 

Similar to Integrated assignment site report (20)

Ct bm measurement report
Ct bm measurement reportCt bm measurement report
Ct bm measurement report
 
Measurement 1-site-visit
Measurement 1-site-visitMeasurement 1-site-visit
Measurement 1-site-visit
 
Site Visit Report
Site Visit ReportSite Visit Report
Site Visit Report
 
Ctw site report(pg 1 to 8, 14)
Ctw site report(pg 1 to 8, 14)Ctw site report(pg 1 to 8, 14)
Ctw site report(pg 1 to 8, 14)
 
Site report
Site reportSite report
Site report
 
Site report
Site reportSite report
Site report
 
Project SlideShare
Project SlideShareProject SlideShare
Project SlideShare
 
Site report
Site reportSite report
Site report
 
Site Report
Site Report Site Report
Site Report
 
bqs Site report
bqs Site reportbqs Site report
bqs Site report
 
Bachelor in quantity surveying 2
Bachelor in quantity surveying 2Bachelor in quantity surveying 2
Bachelor in quantity surveying 2
 
Ez
EzEz
Ez
 
Site report
Site reportSite report
Site report
 
MCB Final report
MCB Final reportMCB Final report
MCB Final report
 
Site report
Site reportSite report
Site report
 
SITE REPORT (PAD FOOTING)
SITE REPORT (PAD FOOTING)SITE REPORT (PAD FOOTING)
SITE REPORT (PAD FOOTING)
 
Site visit report
Site visit reportSite visit report
Site visit report
 
individual site report sem 1 degree
individual site report sem 1 degreeindividual site report sem 1 degree
individual site report sem 1 degree
 
A collection of articles on concrete formwork design and construction
A collection of articles on concrete formwork design and constructionA collection of articles on concrete formwork design and construction
A collection of articles on concrete formwork design and construction
 
Final Report
Final Report Final Report
Final Report
 

More from w ss

Est 22222
Est 22222Est 22222
Est 22222
w ss
 
Course outline august 2015 qsb 2813 software application for qs
Course outline august 2015 qsb 2813 software application for qsCourse outline august 2015 qsb 2813 software application for qs
Course outline august 2015 qsb 2813 software application for qs
w ss
 
Structure project brief march 2018 (updated)
Structure project brief march 2018 (updated)Structure project brief march 2018 (updated)
Structure project brief march 2018 (updated)
w ss
 
Pp presentation 1
Pp presentation 1Pp presentation 1
Pp presentation 1
w ss
 
Assignment brief qsb2134 tender
Assignment brief qsb2134 tenderAssignment brief qsb2134 tender
Assignment brief qsb2134 tender
w ss
 
Evaluation brief qsb2134 tender
Evaluation brief qsb2134 tenderEvaluation brief qsb2134 tender
Evaluation brief qsb2134 tender
w ss
 
Management science
Management scienceManagement science
Management science
w ss
 
Ctiii steel framing system [ cold form structures + composite floor slab ]
Ctiii steel framing system  [ cold form structures + composite floor slab ]Ctiii steel framing system  [ cold form structures + composite floor slab ]
Ctiii steel framing system [ cold form structures + composite floor slab ]
w ss
 
Steel framing system report
Steel framing system reportSteel framing system report
Steel framing system report
w ss
 
Group assignment brief ct3-aug2017
Group assignment brief ct3-aug2017Group assignment brief ct3-aug2017
Group assignment brief ct3-aug2017
w ss
 
Site surveying 2 done
Site surveying 2   done Site surveying 2   done
Site surveying 2 done
w ss
 
Site surveying 1 - done
Site surveying 1 - done Site surveying 1 - done
Site surveying 1 - done
w ss
 
Final presentation
Final presentationFinal presentation
Final presentation
w ss
 
Site surveying 1 - done
Site surveying 1 - done Site surveying 1 - done
Site surveying 1 - done
w ss
 
Building services assignment
Building services assignmentBuilding services assignment
Building services assignment
w ss
 
Group project bs1
Group project bs1 Group project bs1
Group project bs1
w ss
 
M2 project assignment mar 2017
M2 project assignment mar 2017M2 project assignment mar 2017
M2 project assignment mar 2017
w ss
 
Assignment 1 bld60204 mac2017
Assignment 1 bld60204 mac2017Assignment 1 bld60204 mac2017
Assignment 1 bld60204 mac2017
w ss
 
Assignment 2 bld60204 sketching
Assignment 2 bld60204 sketchingAssignment 2 bld60204 sketching
Assignment 2 bld60204 sketching
w ss
 
Aluminium formwork(t 4 a)
Aluminium formwork(t 4 a)Aluminium formwork(t 4 a)
Aluminium formwork(t 4 a)
w ss
 

More from w ss (20)

Est 22222
Est 22222Est 22222
Est 22222
 
Course outline august 2015 qsb 2813 software application for qs
Course outline august 2015 qsb 2813 software application for qsCourse outline august 2015 qsb 2813 software application for qs
Course outline august 2015 qsb 2813 software application for qs
 
Structure project brief march 2018 (updated)
Structure project brief march 2018 (updated)Structure project brief march 2018 (updated)
Structure project brief march 2018 (updated)
 
Pp presentation 1
Pp presentation 1Pp presentation 1
Pp presentation 1
 
Assignment brief qsb2134 tender
Assignment brief qsb2134 tenderAssignment brief qsb2134 tender
Assignment brief qsb2134 tender
 
Evaluation brief qsb2134 tender
Evaluation brief qsb2134 tenderEvaluation brief qsb2134 tender
Evaluation brief qsb2134 tender
 
Management science
Management scienceManagement science
Management science
 
Ctiii steel framing system [ cold form structures + composite floor slab ]
Ctiii steel framing system  [ cold form structures + composite floor slab ]Ctiii steel framing system  [ cold form structures + composite floor slab ]
Ctiii steel framing system [ cold form structures + composite floor slab ]
 
Steel framing system report
Steel framing system reportSteel framing system report
Steel framing system report
 
Group assignment brief ct3-aug2017
Group assignment brief ct3-aug2017Group assignment brief ct3-aug2017
Group assignment brief ct3-aug2017
 
Site surveying 2 done
Site surveying 2   done Site surveying 2   done
Site surveying 2 done
 
Site surveying 1 - done
Site surveying 1 - done Site surveying 1 - done
Site surveying 1 - done
 
Final presentation
Final presentationFinal presentation
Final presentation
 
Site surveying 1 - done
Site surveying 1 - done Site surveying 1 - done
Site surveying 1 - done
 
Building services assignment
Building services assignmentBuilding services assignment
Building services assignment
 
Group project bs1
Group project bs1 Group project bs1
Group project bs1
 
M2 project assignment mar 2017
M2 project assignment mar 2017M2 project assignment mar 2017
M2 project assignment mar 2017
 
Assignment 1 bld60204 mac2017
Assignment 1 bld60204 mac2017Assignment 1 bld60204 mac2017
Assignment 1 bld60204 mac2017
 
Assignment 2 bld60204 sketching
Assignment 2 bld60204 sketchingAssignment 2 bld60204 sketching
Assignment 2 bld60204 sketching
 
Aluminium formwork(t 4 a)
Aluminium formwork(t 4 a)Aluminium formwork(t 4 a)
Aluminium formwork(t 4 a)
 

Recently uploaded

Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345
beazzy04
 
How to Break the cycle of negative Thoughts
How to Break the cycle of negative ThoughtsHow to Break the cycle of negative Thoughts
How to Break the cycle of negative Thoughts
Col Mukteshwar Prasad
 
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdfUnit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Thiyagu K
 
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptxMARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
bennyroshan06
 
The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
Delapenabediema
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
siemaillard
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
Pavel ( NSTU)
 
ESC Beyond Borders _From EU to You_ InfoPack general.pdf
ESC Beyond Borders _From EU to You_ InfoPack general.pdfESC Beyond Borders _From EU to You_ InfoPack general.pdf
ESC Beyond Borders _From EU to You_ InfoPack general.pdf
Fundacja Rozwoju Społeczeństwa Przedsiębiorczego
 
Introduction to Quality Improvement Essentials
Introduction to Quality Improvement EssentialsIntroduction to Quality Improvement Essentials
Introduction to Quality Improvement Essentials
Excellence Foundation for South Sudan
 
Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
AzmatAli747758
 
Chapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptxChapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptx
Mohd Adib Abd Muin, Senior Lecturer at Universiti Utara Malaysia
 
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCECLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
BhavyaRajput3
 
Unit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdfUnit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdf
Thiyagu K
 
Ethnobotany and Ethnopharmacology ......
Ethnobotany and Ethnopharmacology ......Ethnobotany and Ethnopharmacology ......
Ethnobotany and Ethnopharmacology ......
Ashokrao Mane college of Pharmacy Peth-Vadgaon
 
PART A. Introduction to Costumer Service
PART A. Introduction to Costumer ServicePART A. Introduction to Costumer Service
PART A. Introduction to Costumer Service
PedroFerreira53928
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
Sandy Millin
 
How to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS ModuleHow to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS Module
Celine George
 
Sectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdfSectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdf
Vivekanand Anglo Vedic Academy
 
Additional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdfAdditional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdf
joachimlavalley1
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
RaedMohamed3
 

Recently uploaded (20)

Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345
 
How to Break the cycle of negative Thoughts
How to Break the cycle of negative ThoughtsHow to Break the cycle of negative Thoughts
How to Break the cycle of negative Thoughts
 
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdfUnit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdf
 
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptxMARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
 
The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
 
ESC Beyond Borders _From EU to You_ InfoPack general.pdf
ESC Beyond Borders _From EU to You_ InfoPack general.pdfESC Beyond Borders _From EU to You_ InfoPack general.pdf
ESC Beyond Borders _From EU to You_ InfoPack general.pdf
 
Introduction to Quality Improvement Essentials
Introduction to Quality Improvement EssentialsIntroduction to Quality Improvement Essentials
Introduction to Quality Improvement Essentials
 
Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
 
Chapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptxChapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptx
 
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCECLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
 
Unit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdfUnit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdf
 
Ethnobotany and Ethnopharmacology ......
Ethnobotany and Ethnopharmacology ......Ethnobotany and Ethnopharmacology ......
Ethnobotany and Ethnopharmacology ......
 
PART A. Introduction to Costumer Service
PART A. Introduction to Costumer ServicePART A. Introduction to Costumer Service
PART A. Introduction to Costumer Service
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
 
How to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS ModuleHow to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS Module
 
Sectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdfSectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdf
 
Additional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdfAdditional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdf
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
 

Integrated assignment site report

  • 1. SCHOOL OF ARCHITECTURE, BUILDING & DESIGN (SABD) BACHELOR OF QUANTITY SURVEYING (HONOURS) INTEGRATEDASSIGNMENT – SITE VISIT REPORT MEASUREMENT 1 (QSB 60104) BUILDING MATERIALS (BLD 62003) CONSTRUCTION TECHNOLOGY (BLD 60104) NAME: WONG SHER SHENG STUDENTID: 0329950 LECTURES: MS ANG FUEY LIN MS MYZATULAISHAH KAMARAZALY MS AZRINA MD YAAKOB .
  • 2. Table of content Title Pages Introduction 1 Objective 2 Content 3 Materials used for concrete framed building 4 Photos & descriptions 5-12 Conclusion 13
  • 3. Introduction We are given an assignment that involves three modules, which are Measurement 1, Building Materials and Construction Technology 1. All of us are required to write a report for our construction site visit. The site visit was held on 23rd November 2016(Wednesday). Lecturers have briefed us about the safety precaution which we need to obey. Among the precautions are we need to dress appropriately by wearing long pants with collar t- shirt, sports shoes with socks and most importantly is wearing safety helmet on site. The construction site is located at Taman Impian Murni(Lot 3607), Jalan Tanjung Balai(Lorong Haji Yusof) Seksyen 30, 40460 Shah Alam, Selangor. This project is to construct 42 units 2&3 storey terrace with land size of 20'x63'. The contractor of the project is Purcon Group. The purpose of the site visit is to expose us so that we are able to describe, explain and understand the method and process of construction in accordance to the sequence of work on site.
  • 4. Objective  To understand the practical aspect of construction techniques in comparison to theory in the books and its application on site.  To understand the basics of the construction process.  To observe the usage of construction equipment on site including mechanical plants.  To explore and identify types of building materials and construction technology used on site.  To expose us the working environment as a Quantity Surveyor and be able to deal with some uncertain circumstances such as weather.  To be aware of the importance of safety on site and understand the safety problems and site conditions.  To broaden our horizon with the latest technology used in construction.  To give us an opportunity to understand the significance of communication skills while working together as a construction team.
  • 5. Content Item in the site that are considered as a concrete frame Concrete frame building are the most common type of modern building. This type of building consists of a frame of concrete. The items to be considered that are considered as a concrete frames in the sites are beams, column and slab. Horizontal members of the concrete frame are called beams. There are two types of beam namely suspended beam and non-suspended beam. Suspended beam are located on the upper floor. Non- suspended beam which also known as ground beam are used to support brick. Moving on, the vertical members of the concrete frame are called column. Column is designed to withstand compressive loads. Column is the most significant part of the building as it carries the primary load of the building. For example, if you damage a beam in a building, it will usually affect only one floor, but if damage to a column could bring down the entire building. Besides that, a flat plate of concrete that human can walk on it is called slabs. Suspended slabs are above ground and supported by beams whereas non- suspended slabs sit on the ground directly.
  • 6. Materials involved in constructing concrete framed structure The concrete used for the whole concrete frame structures is grade 25. Concrete is a composite materials composed of aggregate bonded with fluid cement which hardens over time. The ratio of cement to sand to coarse aggregate for concrete grade 25 is 1:1:2. The grade of the concrete refers to the compression strength resistance for 28 days. Concrete grade 25 is considered standard concrete. Concrete in the building trade actually mean reinforced concrete. The full name of it is reinforced cement concrete(RCC). RCC is concrete that contains steel bars which also known as reinforcement bar or rebar. This combination works well as the concrete is very strong in compression, easy to produce at site and affordable. To make reinforced concrete, one must makes a mould called formwork that will contain the liquid concrete and give it in the form or shape we need. Secondly, one should look at the structural engineer’s drawings and places in the steel reinforcement bar and ties them in place using wire. Once the steel is in place, concrete is prepared by mixing the cement, sand, aggregates according to the ratio of certain concrete grade. Concrete will harden in hours but takes months to achieve its full strength. During this time, concrete must be supplied with water on its surface.
  • 7. Photo & description Steel bar and temporary accommodation for workers Excavator on site
  • 10. Common burnt clay bricks are well stacked on the floor Pre-cast concrete bricks
  • 13. Steel bars come out from the column Pipe structure and wiring system of the house
  • 14. Plastering wall finishes Zincalume door frames Zincalume roofing
  • 15. Conclusion After the site visit, I have gained some valuable knowledge that we can’t learn from the textbooks and lectures. I have fully understood the practical aspects of construction techniques in comparison to theory in the books and its application. It is more tougher than I thought. Moreover, I have learnt how a construction site works after the site visit. I have seen various type of tools and equipments used on site. We were taught by the site contractor about the usage of those equipments. Besides, I’mable to identify and differentiate types of building materials used in construction. Through the site visit, I have better understanding about the working environment as a Quantity Surveyor. They work under uncertainty circumstances. They need to be careful about the working environment as risks exist everywhere on site. Furthermore, I had the opportunity to witness how the construction team emphasis the safety on the construction site. Safety is their top priorities. Every workers need to wear safety helmet on site. Even visitors like us need to obey the rule. This is to ensure our safety during our site visit. I have learnt that communication skills is crucial. As a construction team, we need to communicate and works together so that the project can be carried out smoothly. Teamwork is also an essential element in construction. We only learn the new knowledge by memorizing those important points due to our exam-oriented education system. Because of this we can’t experience the real life working. So through the site visit, we can learn something that we can’t get from books. The site visit have brought tons of benefits to me. I am very grateful to have a chance to site visit. I wish I could have more of this kind of opportunities in the future as it can prepare a better me for my working in the future.