SlideShare a Scribd company logo
1
MEASUREMENT 1 (QSB 60104)
BUILDING MATERIALS (BLD 62003)
CONSTRUCTION TECHNOLOGY I (BLD 60104)
NAME : TEE WAN NEE
STUDENT ID : 0325074
COURSE : BQS SEM 1
SITE
REPORT
2
Introduction
On the 23rd of November 2016, all us which is the Semester 1 students which
consists of 46 students went to a site visit which was being planned by the integrated
modules which are Measurement 1, Building Materials and also Construction Technology 1
lecturers in Semester 1. We were being assigned to do a report that we had compiled the
information that we got from the site visit. Upon reaching the site, all the 46 of us were
being brief by the Construction Manager, Mr. Lim Yang.
Picture showsstudentlistening onthe brief givenbyMr.Lim Yang
Picture of site
3
The brief introduction of the project are as follow :-
Name Of Project Taman Impian Murni by Purcon Sdn. Bhd
Location of the project
Taman Impian Murni (Lot 3607), Jalan Tanjung Balai
(Lorong Haji Yusof) Seksyen 30, 40460 Shah Alam,
Selangor
Pupose of the project
Build 42 bungalows for the bumiputeras in the area
- 8 units triple-storey terrace house
- 38 units double storey terrace house
Cost of the whole Project Approximately RM 1.1 million
Selling Price RM 585, 000 to RM 985, 000
Duration of the Project 1 year 6 months
Estimated time to Complete October 2017
Land Area 20’ x 63’
Developer Khas Perkasa Sdn Bhd
Method Of Project Conventional Method
SITE PLAN OF THE PROJECT
4
Objectives
Upon coming back from the site, I have :
 Understand the basic of the construction process such as working spaces,
observing and also recalling back the topics that had been taught by the
lecturers in the class instead of looking at the notes only.
 Experience and learn more about construction and knowledge that I need to
know before entering the construction site and also after becoming a Quantity
Surveyor which is dealing with the weather and the risk that may occur on
site.
 Understand on the importance of safety and also notes that should be taken
before entering to a construction site before any incidents happened. For
example, we need to wear a helmet and also suitable shoes and also not
slippers before entering a construction site.
 Better understanding on the construction drawing and also details for taking
off.
 Chance to learn about different types of machinery and the uses by
observing, such as excavator, concrete mixer, crane and also bar cutting
machine.
5
FOUNDATION AND SLAB
For this section, RC pile foundation (rough foundation) is used as a foundation for
the house. By using this foundation, it helps them to save a lot of cost on the piling,
because, lesser piles would be used. The method that they used are friction piling,
because, the soil on that area is soft. Thus, it is the best to use friction piling in the
site because the load carried by a pile is borne by the friction developed between the
sides of the pile and the surrounding ground. Not only that, based on the picture
below, the method of the slab and ground beam arrangement are a more unusual,
because there are no pile caps for the pile. This method is being used by the
structural engineer whereby the floor slab used is non-suspended slab and the
ground beam is being built in advance and later the concrete of the slab will be
poured on top of the hardcore and also the ground beam. Moreover, the mesh fabric
reinforcement (BRC) and the reinforcement bar of the slab and beam are not
connected together. By using this method, settlement can be avoided but the
concrete used would be more.
Picture of slab
PILE
GROUND BEAM
HARDCORE
CONCRETE BED / SLAB
BRICKWALL
SLAB
GROUND BEAMSTARTER BAR
6
CONCRETE FRAME
The concrete frame consists of a frame or skeleton of concrete. It is divided into two
which are the horizontal member and also the vertical member. Horizontal member
consists of beams, vertical member consists of column and the human walk on flat
planes of concrete are called as slab. The concrete that are being used for all the
concrete frame is Grade 25.
COLUMN
ATTACHED
BEAM
SUSPENDED FLOOR
SLAB
7
BEAM
Beams are traditionally description of building or civil engineering structural elements
and it is the horizontal member of the concrete frame structure and carries the
diagonal load. The shape of beam in cross-section is rectangle in shape. The
bending force induced to the material of the beam is a result of external load, own
weight, span and external reactions to these loads called bending moment. Usually,
beams are characterized by their profile (shape of cross-section),their length and
also the material used.
In this project, there are three types of beams which are ground beam, isolated
beam and also attached beam. The concrete used is Concrete Grade 25
ISOLATED BEAM
Picture above shown is an isolated beam. Isolated beam is a beam whereby it is not
attached to a floor slab. An isolated beam usually stands alone. Usually isolated
beams are on the roof which is also called as roof beam.
ISOLATED
BEAM
8
ATTACHED BEAM
Picture below shown is an attached beam. Attached beam is a beam whereby it is
attached to the floor slab. An isolated beam is usually attached to the slab. Usually
attached beam is located on the floors between roofs and also ground beams.
Sometimes, there is attached beam on the roof to locate the tank of the house.
The attached beam on the right on the picture shown above are bigger than usual to
place the window. They made the beam bigger to replace the lintol. The beam on the
left is smaller because the strength that it require doesn’t have to be too big because
there are no windows or doors.
ATTACHED
BEAM
9
GROUND BEAM
Picture above shows ground beam on site. Ground beams are designed to support
the brick/ brickwork or to form a permanent shutter to the edge of the insitu concrete
of the floor slab. The amount of reinforcement bars introduced to the design will be
used to balance the specific loading requirements. Not only that, the beams are also
to design to withstand any heavy forces with the use to void forming or compressible
materials.
Installation may require pilling, then once it is completed, the excavation of the
ground to a width and depth required by the design or shuttered above.
Reinforcement bars is then placed and the pile reinforcement is tied into the ground
beam. After inspection of the relevant authorities, the beam will be concreted.
GROUND
BEAM
10
COLUMN
Column is a vertical member of the concrete frame structure. Loads from ceiling,
floor slab and also beam, including the self-weight are transferred from column to the
foundation. Construction site uses R.C.C columns widely nowadays. The term itself
applied especially to a large round support with a capital base or pedestal and made
of stone, or may be appearing to be so. A post, which is a small wooden or metal
supports with a rectangular or other non-round sections are called as piers. For the
purpose of wind or earthquake engineering, columns may be designed to resist
lateral forces. Other compression members are often termed "columns" because of
the similar stress conditions.
The above picture shows the column on the second floor of the terrace house. Some of the
walls don’t have stiffeners to stiffen the columns. When the wall is short, there are starter
bars for the brickwork where it is being tied with the bricks. It is also known as the 40d/42d of
starter bar in measurement. It is being used like this to prevent the wall from cracking by the
contractor, especially when bricks is joint with concrete. When doing construction, there are
vibration therefore the starter bars are there to protect the column from collapsing.
COLUMN
STARTER
BAR
Picture showsthe timberformworkforthe
column.Forthisproject,theyare usingtimber
formworkwhichisalsocalledthe traditional
formwork.We were alsoseeingthe workers
sawingthe timberforthe formwork.
TIMBER
FORMWORK
11
FORMWORK
The formwork that are being used by this project is timber formwork. Timber
formwork is a traditional formwork. The formwork is built on site out of timber and
plywood or moisture-resistant particleboard. It is easy to produce but time-
consuming for larger structures, and the plywood facing has a relatively short
lifespan. It is still used extensively where the labour costs are lower than the costs
for procuring reusable formwork. It is also the most flexible type of formwork, so even
where other systems are in use, complicated sections may use it.
REINFORCEMENT BAR
The reinforcement bar is being placed
like the picture above is to tie the
formwork together when they pour the
concrete in.
Picture shows the worker sawing
a part of the timber formwork for
the column.
12
SLAB
The type of slab for second floor for this project is suspended slab. Suspended slab
are slabs that are not direct contact to the ground. This forms roofs or floors above
ground level. Suspended slabs are grouped into two types: one which is supported
on two sides. The other one is two way slabs which are supported on all four sides.
Suspended slab are attached to the beam.
When measuring the finishing level and the concrete level wouldn’t be the same.
This is because when the tiles are being applied on the concrete, the level wouldn’t
be the same because of the depth of the concrete.
FLOOR
SLAB
ATTACHED
BEAM
This happened because column
cannot reach the same level of
the soffit because of the beam
size. Sometimes, column and
column aren’t the same because
there are drop.
13
MATERIALS USED
The materials used in the construction of concrete framed building is concrete,
reinforcement bars and also mesh fabric reinforcement.
ROOF
SLAB
Picture shows cement which is also a
mixture of concrete. Concrete Grade 25
is being used as the concrete. Mixture of
Grade 25 is 1:2:4 (cement : sand : coarse
aggregate ) These concrete are being
used in the floor slab, piling, column and
also beams.
CONCRETE
14
Photos and Description
Picture shows the reinforcement bars of the
slab. The concrete cover for the reinforcement
bars are 12mm thick. The purpose of concrete
cover is to protect the reinforcement bars when
there are fire. Thus, fire will burn the concrete
cover first. The reinforcement bars are being
bent in shape before the concrete is being
poured in.
Picture shows the mesh fabric
reinforcement (BRC) that is being used
on site. BRC is being laid in the slab.
REINFORCEMENT BARS
MESH FABRIC REINFORCEMENT
(BRC)
LINTOL
Lintol is placed above the door.
When there are no lintol, and there’s
door frame or window frame, after a
period, the door will not be able to be
opened. The presence of lintol is to
push the pressure back up. Lintol
needs to be longer than the door
minimum 6 inch.
15
BRICKS
These bricks are arranged in stretcher
bond method. This bond is sometimes
known as running bond. This bond is
the simplest bond that is used today.
Stretcher Bond is normally used a
farcade for the main structural building.
It can look very plain, but with the
introduction of other patterns can look
very affective
SAND BRICKS AND
CLAY BRICKS
They used clay brick wall between
houses because when house 1 gets on
fire, it will take time to burn down house
2. This is because clay brick will take
aprroximately 1 hour to burn. Not only
that, it is also the bomba’s requirement
to put on the clay brick.
ROOF
The roof that they used is a aluminium
roof. It is more durable and leak
resistant. The disadvantage of using
this aluminium roof is that it makes a lot
of noises when it rains.
16
Conclusion
This site visit had been a wonderful site visit. This is because I had gained a
lot of knowledge and not only that, I have also saw a lot of things that I learned in
lecture classes becoming real in front of my eyes. Other than that, I also have the
chance to see all the slabs, beams, concrete, BRCs and also got the picture of how it
really looks like.
Unlike in lecture halls, lecturer also give us pictures and also slides to
understand a materials and how it works, but students can’t really get the real picture
of the materials, for example, mesh fabric reinforcement. So, by following this site
visit, I have already have the real picture of what is happening in the construction site
PVC PIPE
The PVC Pipe is being inserted into the
wall for wiring. This is to protect the wire
and also the wiring man. With the
presence of PVC, the wireman can
detect if there is a wire or not. Without
the PVC, the wireman might drill into the
wire, and that might cause a lot of
problems.
SCAFFOLDING
The Scaffolding that are being used
in the site is independent
scaffolding. It consists of double row
of standards. The distance between
the lines of standards should be the
minimum necessary to
accommodate the required number
of boards and toe boards.
17
and what is needed to be used so that it can make the building stiffer and nicer
despite the soft soil and also the humid weather.
Other than that, on the day of site visit, I have also learnt to be patient despite
the scorching hot weather outside. This made me thought that whenever I want to
learn something I need to be patient and nothing can stop me from learning
something new. Not only that, I also realized that, working in a construction industry
is not as easy as I thought it would be because we need to bear the hot weather and
also the soft soil, but, when there is a will there is a way.
This site visit is also add points whereby it is an unique experience to be
exposed to the actual working site that I will be working at in the near future. This site
visit had brought more benefits to me and I do hope that I could join more site visits
in the near future to gain more and more knowledge.

More Related Content

What's hot

Site Visit Report
Site Visit ReportSite Visit Report
Site Visit ReportZIyeeTan
 
Site Visit Report CT BM M1
Site Visit Report CT BM M1Site Visit Report CT BM M1
Site Visit Report CT BM M1
Zi Shan
 
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTION
AN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTIONAN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTION
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTIONAbhishek Singh
 
Building Construction 1: project 1
Building Construction 1: project 1Building Construction 1: project 1
Building Construction 1: project 1
Nabeel Joomun
 
Residential building construction ppt
Residential building construction pptResidential building construction ppt
Residential building construction ppt
Being Deepak
 
bqs Site report
bqs Site reportbqs Site report
bqs Site report
Felix Vong
 
CT site visit report
CT site visit report CT site visit report
CT site visit report Yap Xin
 
Site visit report
Site visit report Site visit report
Site visit report
Liming Hiew
 
Report on Residential Construction
Report on Residential ConstructionReport on Residential Construction
Report on Residential ConstructionMayank Walecha
 
Construction of residential building summer training ppt
 Construction of residential building summer training ppt Construction of residential building summer training ppt
Construction of residential building summer training ppt
Sumit Singh
 
PROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDING
PROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDINGPROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDING
PROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDINGAmritpal Singh
 
Types of formwork
Types of formworkTypes of formwork
Types of formwork
Aglaia Connect
 
Chapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONSChapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONS
KHUSHBU SHAH
 
Construction site report
Construction site reportConstruction site report
Construction site report
Ravi Kant Sahu
 
Internship review (Civil Engineering)
Internship review (Civil Engineering)Internship review (Civil Engineering)
Internship review (Civil Engineering)
Syeda Nusrath Fathima
 
Underwater construction
Underwater construction Underwater construction
Underwater construction
Pranay Kumar
 
Civil Engineering Internship Presentation-Anis Rahman Khokan
Civil Engineering Internship Presentation-Anis Rahman KhokanCivil Engineering Internship Presentation-Anis Rahman Khokan
Civil Engineering Internship Presentation-Anis Rahman Khokan
Anis Rahman Khokan
 

What's hot (20)

Site Visit Report
Site Visit ReportSite Visit Report
Site Visit Report
 
Site Visit Report CT BM M1
Site Visit Report CT BM M1Site Visit Report CT BM M1
Site Visit Report CT BM M1
 
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTION
AN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTIONAN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTION
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTION
 
Building Construction 1: project 1
Building Construction 1: project 1Building Construction 1: project 1
Building Construction 1: project 1
 
Site visit report
Site visit reportSite visit report
Site visit report
 
Residential building construction ppt
Residential building construction pptResidential building construction ppt
Residential building construction ppt
 
bqs Site report
bqs Site reportbqs Site report
bqs Site report
 
CT site visit report
CT site visit report CT site visit report
CT site visit report
 
Site visit report
Site visit report Site visit report
Site visit report
 
Report on Residential Construction
Report on Residential ConstructionReport on Residential Construction
Report on Residential Construction
 
Construction of residential building summer training ppt
 Construction of residential building summer training ppt Construction of residential building summer training ppt
Construction of residential building summer training ppt
 
Objective of site visit
Objective of site visitObjective of site visit
Objective of site visit
 
Formwork
FormworkFormwork
Formwork
 
PROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDING
PROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDINGPROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDING
PROJECT REPORT ON DESIGN OF A RESIDENTIAL BUILDING
 
Types of formwork
Types of formworkTypes of formwork
Types of formwork
 
Chapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONSChapter 1 PILE FOUNDATIONS
Chapter 1 PILE FOUNDATIONS
 
Construction site report
Construction site reportConstruction site report
Construction site report
 
Internship review (Civil Engineering)
Internship review (Civil Engineering)Internship review (Civil Engineering)
Internship review (Civil Engineering)
 
Underwater construction
Underwater construction Underwater construction
Underwater construction
 
Civil Engineering Internship Presentation-Anis Rahman Khokan
Civil Engineering Internship Presentation-Anis Rahman KhokanCivil Engineering Internship Presentation-Anis Rahman Khokan
Civil Engineering Internship Presentation-Anis Rahman Khokan
 

Viewers also liked

Site Visit Report
Site Visit ReportSite Visit Report
Site Visit Report
XinYee Khoo
 
Assignment 1 Site Visit Report
Assignment 1 Site Visit ReportAssignment 1 Site Visit Report
Assignment 1 Site Visit Reportarmada7000
 
Visit to a construction site
Visit to a construction siteVisit to a construction site
Visit to a construction site
Umair Ali
 
Building Construction 2 Project 1 Report
Building Construction 2 Project 1 ReportBuilding Construction 2 Project 1 Report
Building Construction 2 Project 1 Report
hiewyennee
 
Technical site visit report
Technical site visit reportTechnical site visit report
Technical site visit report
Momo Poyi
 
BUILDING CONSTRUCTION 2 ; PROJECT 1 REPORT
BUILDING CONSTRUCTION 2 ; PROJECT 1 REPORTBUILDING CONSTRUCTION 2 ; PROJECT 1 REPORT
BUILDING CONSTRUCTION 2 ; PROJECT 1 REPORT
Darshiini Vig
 
Site report
Site reportSite report
Site reportYunshi94
 
Visiting report
Visiting reportVisiting report
Visiting report
drfez86
 
Building construction-report (1)
Building construction-report (1)Building construction-report (1)
Building construction-report (1)Soh Shing
 
Industrial Visit Report
Industrial Visit ReportIndustrial Visit Report
Industrial Visit ReportBabu Rao
 
Essay 3 Relationships at Work
Essay 3 Relationships at WorkEssay 3 Relationships at Work
Essay 3 Relationships at WorkMai Lee Yang
 
electric Site visit
electric Site visitelectric Site visit
electric Site visit
Deepak Sharma
 
Building Construction 1 Project 1
Building Construction 1 Project 1Building Construction 1 Project 1
Building Construction 1 Project 1
dtan97
 
Building construction project 1 report
Building construction project 1 reportBuilding construction project 1 report
Building construction project 1 reportchenliang923
 
rajghat-power-house-new-delhi-training-report
rajghat-power-house-new-delhi-training-reportrajghat-power-house-new-delhi-training-report
rajghat-power-house-new-delhi-training-reportRaj Sharma
 
Contribution of Women in our society
Contribution of Women in our societyContribution of Women in our society
Contribution of Women in our society
Student
 
building construction project 1 report
building construction project 1 reportbuilding construction project 1 report
building construction project 1 report
Yq Chong
 
Building construction 2 project 1 report
Building construction 2 project 1 reportBuilding construction 2 project 1 report
Building construction 2 project 1 report
Ong Seng Peng Jeff
 
Site visit report
Site visit reportSite visit report
Site visit report
Jordon Wong
 
Building Construction Project 1 Shelter Report
Building Construction Project 1 Shelter ReportBuilding Construction Project 1 Shelter Report
Building Construction Project 1 Shelter ReportJoyeeLee0131
 

Viewers also liked (20)

Site Visit Report
Site Visit ReportSite Visit Report
Site Visit Report
 
Assignment 1 Site Visit Report
Assignment 1 Site Visit ReportAssignment 1 Site Visit Report
Assignment 1 Site Visit Report
 
Visit to a construction site
Visit to a construction siteVisit to a construction site
Visit to a construction site
 
Building Construction 2 Project 1 Report
Building Construction 2 Project 1 ReportBuilding Construction 2 Project 1 Report
Building Construction 2 Project 1 Report
 
Technical site visit report
Technical site visit reportTechnical site visit report
Technical site visit report
 
BUILDING CONSTRUCTION 2 ; PROJECT 1 REPORT
BUILDING CONSTRUCTION 2 ; PROJECT 1 REPORTBUILDING CONSTRUCTION 2 ; PROJECT 1 REPORT
BUILDING CONSTRUCTION 2 ; PROJECT 1 REPORT
 
Site report
Site reportSite report
Site report
 
Visiting report
Visiting reportVisiting report
Visiting report
 
Building construction-report (1)
Building construction-report (1)Building construction-report (1)
Building construction-report (1)
 
Industrial Visit Report
Industrial Visit ReportIndustrial Visit Report
Industrial Visit Report
 
Essay 3 Relationships at Work
Essay 3 Relationships at WorkEssay 3 Relationships at Work
Essay 3 Relationships at Work
 
electric Site visit
electric Site visitelectric Site visit
electric Site visit
 
Building Construction 1 Project 1
Building Construction 1 Project 1Building Construction 1 Project 1
Building Construction 1 Project 1
 
Building construction project 1 report
Building construction project 1 reportBuilding construction project 1 report
Building construction project 1 report
 
rajghat-power-house-new-delhi-training-report
rajghat-power-house-new-delhi-training-reportrajghat-power-house-new-delhi-training-report
rajghat-power-house-new-delhi-training-report
 
Contribution of Women in our society
Contribution of Women in our societyContribution of Women in our society
Contribution of Women in our society
 
building construction project 1 report
building construction project 1 reportbuilding construction project 1 report
building construction project 1 report
 
Building construction 2 project 1 report
Building construction 2 project 1 reportBuilding construction 2 project 1 report
Building construction 2 project 1 report
 
Site visit report
Site visit reportSite visit report
Site visit report
 
Building Construction Project 1 Shelter Report
Building Construction Project 1 Shelter ReportBuilding Construction Project 1 Shelter Report
Building Construction Project 1 Shelter Report
 

Similar to SITE VISIT REPORT

Site Report
Site Report Site Report
Site Report
Sow Wei Henn
 
Sem 1 degree ct assignment 1
Sem 1 degree ct assignment 1Sem 1 degree ct assignment 1
Sem 1 degree ct assignment 1Parham Farhadpoor
 
Integrated Assignment : Measurement & CT & BM
Integrated Assignment : Measurement & CT & BMIntegrated Assignment : Measurement & CT & BM
Integrated Assignment : Measurement & CT & BM
Jaey Chai
 
Site report
Site reportSite report
Site report
Penny3688
 
Ishfaq Rashid.pptx
Ishfaq Rashid.pptxIshfaq Rashid.pptx
Ishfaq Rashid.pptx
lovish34
 
Site visit report
Site visit reportSite visit report
Site visit report
shensin1015
 
Ct 1 report
Ct 1 reportCt 1 report
Ct 1 report
Ah Lai
 
REINFORCED CEMENT CONCRETE
REINFORCED CEMENT CONCRETEREINFORCED CEMENT CONCRETE
REINFORCED CEMENT CONCRETE
Brijesh Alig
 
RCC Elements column, beam.
RCC Elements  column, beam.RCC Elements  column, beam.
RCC Elements column, beam.
Puneet Chhonker
 
Ct assignment
Ct assignmentCt assignment
Ct assignment
Shao Xun Sean Thun
 
Construction Technology Report
Construction Technology ReportConstruction Technology Report
Construction Technology Report
Shao Xun Sean Thun
 
Ct assignment (2)
Ct assignment (2)Ct assignment (2)
Ct assignment (2)
Shane Ah
 
Building construction 02
Building construction 02Building construction 02
Building construction 02
Sarah Esa
 

Similar to SITE VISIT REPORT (20)

Site Report
Site Report Site Report
Site Report
 
Sem 1 degree ct assignment 1
Sem 1 degree ct assignment 1Sem 1 degree ct assignment 1
Sem 1 degree ct assignment 1
 
Integrated Assignment : Measurement & CT & BM
Integrated Assignment : Measurement & CT & BMIntegrated Assignment : Measurement & CT & BM
Integrated Assignment : Measurement & CT & BM
 
Site report
Site reportSite report
Site report
 
Ishfaq Rashid.pptx
Ishfaq Rashid.pptxIshfaq Rashid.pptx
Ishfaq Rashid.pptx
 
Site visit report
Site visit reportSite visit report
Site visit report
 
Ct 1 report
Ct 1 reportCt 1 report
Ct 1 report
 
Ct report
Ct reportCt report
Ct report
 
Ct report
Ct reportCt report
Ct report
 
REINFORCED CEMENT CONCRETE
REINFORCED CEMENT CONCRETEREINFORCED CEMENT CONCRETE
REINFORCED CEMENT CONCRETE
 
RCC Elements column, beam.
RCC Elements  column, beam.RCC Elements  column, beam.
RCC Elements column, beam.
 
Ct report
Ct reportCt report
Ct report
 
Ct report
Ct reportCt report
Ct report
 
Ct report
Ct reportCt report
Ct report
 
Ct assignment
Ct assignmentCt assignment
Ct assignment
 
Ct assignment
Ct assignmentCt assignment
Ct assignment
 
Construction Technology Report
Construction Technology ReportConstruction Technology Report
Construction Technology Report
 
Ct assignment (2)
Ct assignment (2)Ct assignment (2)
Ct assignment (2)
 
Ct assignment
Ct assignmentCt assignment
Ct assignment
 
Building construction 02
Building construction 02Building construction 02
Building construction 02
 

More from Wan Nee

Presentation 7-pp-final
Presentation 7-pp-finalPresentation 7-pp-final
Presentation 7-pp-final
Wan Nee
 
Professional practice-1-1-1-autosaved (1)
Professional practice-1-1-1-autosaved (1)Professional practice-1-1-1-autosaved (1)
Professional practice-1-1-1-autosaved (1)
Wan Nee
 
Structures final 20th june
Structures final 20th juneStructures final 20th june
Structures final 20th june
Wan Nee
 
Eca presentation slide (group a)
Eca presentation slide (group a)Eca presentation slide (group a)
Eca presentation slide (group a)
Wan Nee
 
Estimating final
Estimating  final Estimating  final
Estimating final
Wan Nee
 
Seminar question
Seminar questionSeminar question
Seminar question
Wan Nee
 
Estimating presentation
Estimating presentation Estimating presentation
Estimating presentation
Wan Nee
 
Evaluation brief qsb2134 tender (1)
Evaluation brief qsb2134 tender (1)Evaluation brief qsb2134 tender (1)
Evaluation brief qsb2134 tender (1)
Wan Nee
 
Estimating Assignment Brief
Estimating Assignment BriefEstimating Assignment Brief
Estimating Assignment Brief
Wan Nee
 
Estimating Assignment
Estimating AssignmentEstimating Assignment
Estimating Assignment
Wan Nee
 
Supply Chain
Supply Chain Supply Chain
Supply Chain
Wan Nee
 
Supply chain
Supply chain  Supply chain
Supply chain
Wan Nee
 
Supply chain
Supply chainSupply chain
Supply chain
Wan Nee
 
Management Science
Management Science Management Science
Management Science
Wan Nee
 
Qsb 2413 group project august 2017
Qsb 2413 group project august 2017 Qsb 2413 group project august 2017
Qsb 2413 group project august 2017
Wan Nee
 
BS 2 PRESENTATION
BS 2 PRESENTATION BS 2 PRESENTATION
BS 2 PRESENTATION
Wan Nee
 
CT 3 Group Assignment Presentation Slide
CT 3 Group Assignment Presentation SlideCT 3 Group Assignment Presentation Slide
CT 3 Group Assignment Presentation Slide
Wan Nee
 
CT3 Group Assignment Report
CT3 Group Assignment ReportCT3 Group Assignment Report
CT3 Group Assignment Report
Wan Nee
 
Ct2 latest1-1 (3)
Ct2 latest1-1 (3)Ct2 latest1-1 (3)
Ct2 latest1-1 (3)
Wan Nee
 
INTEGRATED ASSIGNMENT - CT BM M
INTEGRATED ASSIGNMENT - CT BM MINTEGRATED ASSIGNMENT - CT BM M
INTEGRATED ASSIGNMENT - CT BM M
Wan Nee
 

More from Wan Nee (20)

Presentation 7-pp-final
Presentation 7-pp-finalPresentation 7-pp-final
Presentation 7-pp-final
 
Professional practice-1-1-1-autosaved (1)
Professional practice-1-1-1-autosaved (1)Professional practice-1-1-1-autosaved (1)
Professional practice-1-1-1-autosaved (1)
 
Structures final 20th june
Structures final 20th juneStructures final 20th june
Structures final 20th june
 
Eca presentation slide (group a)
Eca presentation slide (group a)Eca presentation slide (group a)
Eca presentation slide (group a)
 
Estimating final
Estimating  final Estimating  final
Estimating final
 
Seminar question
Seminar questionSeminar question
Seminar question
 
Estimating presentation
Estimating presentation Estimating presentation
Estimating presentation
 
Evaluation brief qsb2134 tender (1)
Evaluation brief qsb2134 tender (1)Evaluation brief qsb2134 tender (1)
Evaluation brief qsb2134 tender (1)
 
Estimating Assignment Brief
Estimating Assignment BriefEstimating Assignment Brief
Estimating Assignment Brief
 
Estimating Assignment
Estimating AssignmentEstimating Assignment
Estimating Assignment
 
Supply Chain
Supply Chain Supply Chain
Supply Chain
 
Supply chain
Supply chain  Supply chain
Supply chain
 
Supply chain
Supply chainSupply chain
Supply chain
 
Management Science
Management Science Management Science
Management Science
 
Qsb 2413 group project august 2017
Qsb 2413 group project august 2017 Qsb 2413 group project august 2017
Qsb 2413 group project august 2017
 
BS 2 PRESENTATION
BS 2 PRESENTATION BS 2 PRESENTATION
BS 2 PRESENTATION
 
CT 3 Group Assignment Presentation Slide
CT 3 Group Assignment Presentation SlideCT 3 Group Assignment Presentation Slide
CT 3 Group Assignment Presentation Slide
 
CT3 Group Assignment Report
CT3 Group Assignment ReportCT3 Group Assignment Report
CT3 Group Assignment Report
 
Ct2 latest1-1 (3)
Ct2 latest1-1 (3)Ct2 latest1-1 (3)
Ct2 latest1-1 (3)
 
INTEGRATED ASSIGNMENT - CT BM M
INTEGRATED ASSIGNMENT - CT BM MINTEGRATED ASSIGNMENT - CT BM M
INTEGRATED ASSIGNMENT - CT BM M
 

Recently uploaded

Polish students' mobility in the Czech Republic
Polish students' mobility in the Czech RepublicPolish students' mobility in the Czech Republic
Polish students' mobility in the Czech Republic
Anna Sz.
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
TechSoup
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
Jisc
 
The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
Delapenabediema
 
Additional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdfAdditional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdf
joachimlavalley1
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
Vivekanand Anglo Vedic Academy
 
The Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve ThomasonThe Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve Thomason
Steve Thomason
 
How to Break the cycle of negative Thoughts
How to Break the cycle of negative ThoughtsHow to Break the cycle of negative Thoughts
How to Break the cycle of negative Thoughts
Col Mukteshwar Prasad
 
Introduction to Quality Improvement Essentials
Introduction to Quality Improvement EssentialsIntroduction to Quality Improvement Essentials
Introduction to Quality Improvement Essentials
Excellence Foundation for South Sudan
 
Template Jadual Bertugas Kelas (Boleh Edit)
Template Jadual Bertugas Kelas (Boleh Edit)Template Jadual Bertugas Kelas (Boleh Edit)
Template Jadual Bertugas Kelas (Boleh Edit)
rosedainty
 
Instructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptxInstructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptx
Jheel Barad
 
Fish and Chips - have they had their chips
Fish and Chips - have they had their chipsFish and Chips - have they had their chips
Fish and Chips - have they had their chips
GeoBlogs
 
The geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideasThe geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideas
GeoBlogs
 
PART A. Introduction to Costumer Service
PART A. Introduction to Costumer ServicePART A. Introduction to Costumer Service
PART A. Introduction to Costumer Service
PedroFerreira53928
 
The Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdfThe Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdf
kaushalkr1407
 
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCECLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
BhavyaRajput3
 
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptxMARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
bennyroshan06
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
RaedMohamed3
 
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
Nguyen Thanh Tu Collection
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
Sandy Millin
 

Recently uploaded (20)

Polish students' mobility in the Czech Republic
Polish students' mobility in the Czech RepublicPolish students' mobility in the Czech Republic
Polish students' mobility in the Czech Republic
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
 
The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
 
Additional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdfAdditional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdf
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
 
The Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve ThomasonThe Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve Thomason
 
How to Break the cycle of negative Thoughts
How to Break the cycle of negative ThoughtsHow to Break the cycle of negative Thoughts
How to Break the cycle of negative Thoughts
 
Introduction to Quality Improvement Essentials
Introduction to Quality Improvement EssentialsIntroduction to Quality Improvement Essentials
Introduction to Quality Improvement Essentials
 
Template Jadual Bertugas Kelas (Boleh Edit)
Template Jadual Bertugas Kelas (Boleh Edit)Template Jadual Bertugas Kelas (Boleh Edit)
Template Jadual Bertugas Kelas (Boleh Edit)
 
Instructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptxInstructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptx
 
Fish and Chips - have they had their chips
Fish and Chips - have they had their chipsFish and Chips - have they had their chips
Fish and Chips - have they had their chips
 
The geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideasThe geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideas
 
PART A. Introduction to Costumer Service
PART A. Introduction to Costumer ServicePART A. Introduction to Costumer Service
PART A. Introduction to Costumer Service
 
The Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdfThe Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdf
 
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCECLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
 
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptxMARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
 
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
 
2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...2024.06.01 Introducing a competency framework for languag learning materials ...
2024.06.01 Introducing a competency framework for languag learning materials ...
 

SITE VISIT REPORT

  • 1. 1 MEASUREMENT 1 (QSB 60104) BUILDING MATERIALS (BLD 62003) CONSTRUCTION TECHNOLOGY I (BLD 60104) NAME : TEE WAN NEE STUDENT ID : 0325074 COURSE : BQS SEM 1 SITE REPORT
  • 2. 2 Introduction On the 23rd of November 2016, all us which is the Semester 1 students which consists of 46 students went to a site visit which was being planned by the integrated modules which are Measurement 1, Building Materials and also Construction Technology 1 lecturers in Semester 1. We were being assigned to do a report that we had compiled the information that we got from the site visit. Upon reaching the site, all the 46 of us were being brief by the Construction Manager, Mr. Lim Yang. Picture showsstudentlistening onthe brief givenbyMr.Lim Yang Picture of site
  • 3. 3 The brief introduction of the project are as follow :- Name Of Project Taman Impian Murni by Purcon Sdn. Bhd Location of the project Taman Impian Murni (Lot 3607), Jalan Tanjung Balai (Lorong Haji Yusof) Seksyen 30, 40460 Shah Alam, Selangor Pupose of the project Build 42 bungalows for the bumiputeras in the area - 8 units triple-storey terrace house - 38 units double storey terrace house Cost of the whole Project Approximately RM 1.1 million Selling Price RM 585, 000 to RM 985, 000 Duration of the Project 1 year 6 months Estimated time to Complete October 2017 Land Area 20’ x 63’ Developer Khas Perkasa Sdn Bhd Method Of Project Conventional Method SITE PLAN OF THE PROJECT
  • 4. 4 Objectives Upon coming back from the site, I have :  Understand the basic of the construction process such as working spaces, observing and also recalling back the topics that had been taught by the lecturers in the class instead of looking at the notes only.  Experience and learn more about construction and knowledge that I need to know before entering the construction site and also after becoming a Quantity Surveyor which is dealing with the weather and the risk that may occur on site.  Understand on the importance of safety and also notes that should be taken before entering to a construction site before any incidents happened. For example, we need to wear a helmet and also suitable shoes and also not slippers before entering a construction site.  Better understanding on the construction drawing and also details for taking off.  Chance to learn about different types of machinery and the uses by observing, such as excavator, concrete mixer, crane and also bar cutting machine.
  • 5. 5 FOUNDATION AND SLAB For this section, RC pile foundation (rough foundation) is used as a foundation for the house. By using this foundation, it helps them to save a lot of cost on the piling, because, lesser piles would be used. The method that they used are friction piling, because, the soil on that area is soft. Thus, it is the best to use friction piling in the site because the load carried by a pile is borne by the friction developed between the sides of the pile and the surrounding ground. Not only that, based on the picture below, the method of the slab and ground beam arrangement are a more unusual, because there are no pile caps for the pile. This method is being used by the structural engineer whereby the floor slab used is non-suspended slab and the ground beam is being built in advance and later the concrete of the slab will be poured on top of the hardcore and also the ground beam. Moreover, the mesh fabric reinforcement (BRC) and the reinforcement bar of the slab and beam are not connected together. By using this method, settlement can be avoided but the concrete used would be more. Picture of slab PILE GROUND BEAM HARDCORE CONCRETE BED / SLAB BRICKWALL SLAB GROUND BEAMSTARTER BAR
  • 6. 6 CONCRETE FRAME The concrete frame consists of a frame or skeleton of concrete. It is divided into two which are the horizontal member and also the vertical member. Horizontal member consists of beams, vertical member consists of column and the human walk on flat planes of concrete are called as slab. The concrete that are being used for all the concrete frame is Grade 25. COLUMN ATTACHED BEAM SUSPENDED FLOOR SLAB
  • 7. 7 BEAM Beams are traditionally description of building or civil engineering structural elements and it is the horizontal member of the concrete frame structure and carries the diagonal load. The shape of beam in cross-section is rectangle in shape. The bending force induced to the material of the beam is a result of external load, own weight, span and external reactions to these loads called bending moment. Usually, beams are characterized by their profile (shape of cross-section),their length and also the material used. In this project, there are three types of beams which are ground beam, isolated beam and also attached beam. The concrete used is Concrete Grade 25 ISOLATED BEAM Picture above shown is an isolated beam. Isolated beam is a beam whereby it is not attached to a floor slab. An isolated beam usually stands alone. Usually isolated beams are on the roof which is also called as roof beam. ISOLATED BEAM
  • 8. 8 ATTACHED BEAM Picture below shown is an attached beam. Attached beam is a beam whereby it is attached to the floor slab. An isolated beam is usually attached to the slab. Usually attached beam is located on the floors between roofs and also ground beams. Sometimes, there is attached beam on the roof to locate the tank of the house. The attached beam on the right on the picture shown above are bigger than usual to place the window. They made the beam bigger to replace the lintol. The beam on the left is smaller because the strength that it require doesn’t have to be too big because there are no windows or doors. ATTACHED BEAM
  • 9. 9 GROUND BEAM Picture above shows ground beam on site. Ground beams are designed to support the brick/ brickwork or to form a permanent shutter to the edge of the insitu concrete of the floor slab. The amount of reinforcement bars introduced to the design will be used to balance the specific loading requirements. Not only that, the beams are also to design to withstand any heavy forces with the use to void forming or compressible materials. Installation may require pilling, then once it is completed, the excavation of the ground to a width and depth required by the design or shuttered above. Reinforcement bars is then placed and the pile reinforcement is tied into the ground beam. After inspection of the relevant authorities, the beam will be concreted. GROUND BEAM
  • 10. 10 COLUMN Column is a vertical member of the concrete frame structure. Loads from ceiling, floor slab and also beam, including the self-weight are transferred from column to the foundation. Construction site uses R.C.C columns widely nowadays. The term itself applied especially to a large round support with a capital base or pedestal and made of stone, or may be appearing to be so. A post, which is a small wooden or metal supports with a rectangular or other non-round sections are called as piers. For the purpose of wind or earthquake engineering, columns may be designed to resist lateral forces. Other compression members are often termed "columns" because of the similar stress conditions. The above picture shows the column on the second floor of the terrace house. Some of the walls don’t have stiffeners to stiffen the columns. When the wall is short, there are starter bars for the brickwork where it is being tied with the bricks. It is also known as the 40d/42d of starter bar in measurement. It is being used like this to prevent the wall from cracking by the contractor, especially when bricks is joint with concrete. When doing construction, there are vibration therefore the starter bars are there to protect the column from collapsing. COLUMN STARTER BAR Picture showsthe timberformworkforthe column.Forthisproject,theyare usingtimber formworkwhichisalsocalledthe traditional formwork.We were alsoseeingthe workers sawingthe timberforthe formwork. TIMBER FORMWORK
  • 11. 11 FORMWORK The formwork that are being used by this project is timber formwork. Timber formwork is a traditional formwork. The formwork is built on site out of timber and plywood or moisture-resistant particleboard. It is easy to produce but time- consuming for larger structures, and the plywood facing has a relatively short lifespan. It is still used extensively where the labour costs are lower than the costs for procuring reusable formwork. It is also the most flexible type of formwork, so even where other systems are in use, complicated sections may use it. REINFORCEMENT BAR The reinforcement bar is being placed like the picture above is to tie the formwork together when they pour the concrete in. Picture shows the worker sawing a part of the timber formwork for the column.
  • 12. 12 SLAB The type of slab for second floor for this project is suspended slab. Suspended slab are slabs that are not direct contact to the ground. This forms roofs or floors above ground level. Suspended slabs are grouped into two types: one which is supported on two sides. The other one is two way slabs which are supported on all four sides. Suspended slab are attached to the beam. When measuring the finishing level and the concrete level wouldn’t be the same. This is because when the tiles are being applied on the concrete, the level wouldn’t be the same because of the depth of the concrete. FLOOR SLAB ATTACHED BEAM This happened because column cannot reach the same level of the soffit because of the beam size. Sometimes, column and column aren’t the same because there are drop.
  • 13. 13 MATERIALS USED The materials used in the construction of concrete framed building is concrete, reinforcement bars and also mesh fabric reinforcement. ROOF SLAB Picture shows cement which is also a mixture of concrete. Concrete Grade 25 is being used as the concrete. Mixture of Grade 25 is 1:2:4 (cement : sand : coarse aggregate ) These concrete are being used in the floor slab, piling, column and also beams. CONCRETE
  • 14. 14 Photos and Description Picture shows the reinforcement bars of the slab. The concrete cover for the reinforcement bars are 12mm thick. The purpose of concrete cover is to protect the reinforcement bars when there are fire. Thus, fire will burn the concrete cover first. The reinforcement bars are being bent in shape before the concrete is being poured in. Picture shows the mesh fabric reinforcement (BRC) that is being used on site. BRC is being laid in the slab. REINFORCEMENT BARS MESH FABRIC REINFORCEMENT (BRC) LINTOL Lintol is placed above the door. When there are no lintol, and there’s door frame or window frame, after a period, the door will not be able to be opened. The presence of lintol is to push the pressure back up. Lintol needs to be longer than the door minimum 6 inch.
  • 15. 15 BRICKS These bricks are arranged in stretcher bond method. This bond is sometimes known as running bond. This bond is the simplest bond that is used today. Stretcher Bond is normally used a farcade for the main structural building. It can look very plain, but with the introduction of other patterns can look very affective SAND BRICKS AND CLAY BRICKS They used clay brick wall between houses because when house 1 gets on fire, it will take time to burn down house 2. This is because clay brick will take aprroximately 1 hour to burn. Not only that, it is also the bomba’s requirement to put on the clay brick. ROOF The roof that they used is a aluminium roof. It is more durable and leak resistant. The disadvantage of using this aluminium roof is that it makes a lot of noises when it rains.
  • 16. 16 Conclusion This site visit had been a wonderful site visit. This is because I had gained a lot of knowledge and not only that, I have also saw a lot of things that I learned in lecture classes becoming real in front of my eyes. Other than that, I also have the chance to see all the slabs, beams, concrete, BRCs and also got the picture of how it really looks like. Unlike in lecture halls, lecturer also give us pictures and also slides to understand a materials and how it works, but students can’t really get the real picture of the materials, for example, mesh fabric reinforcement. So, by following this site visit, I have already have the real picture of what is happening in the construction site PVC PIPE The PVC Pipe is being inserted into the wall for wiring. This is to protect the wire and also the wiring man. With the presence of PVC, the wireman can detect if there is a wire or not. Without the PVC, the wireman might drill into the wire, and that might cause a lot of problems. SCAFFOLDING The Scaffolding that are being used in the site is independent scaffolding. It consists of double row of standards. The distance between the lines of standards should be the minimum necessary to accommodate the required number of boards and toe boards.
  • 17. 17 and what is needed to be used so that it can make the building stiffer and nicer despite the soft soil and also the humid weather. Other than that, on the day of site visit, I have also learnt to be patient despite the scorching hot weather outside. This made me thought that whenever I want to learn something I need to be patient and nothing can stop me from learning something new. Not only that, I also realized that, working in a construction industry is not as easy as I thought it would be because we need to bear the hot weather and also the soft soil, but, when there is a will there is a way. This site visit is also add points whereby it is an unique experience to be exposed to the actual working site that I will be working at in the near future. This site visit had brought more benefits to me and I do hope that I could join more site visits in the near future to gain more and more knowledge.