This document provides a report on a technical site visit to an Andes Construction site. The following key points are made:
- The site visit allowed students to understand construction processes in practice compared to theory, and exposed them to the working environment and safety practices.
- The site was separated into three zones, with the foundation completed in Zone A and in progress in Zone B. Pile cap foundation was used due to unstable soil conditions.
- Advantages of pile cap foundations include increased bearing capacity and ability to use in areas with underground water pressure. Disadvantages include higher costs and need for heavy equipment.
- Concrete grade 25 was used for casting beams, columns, slabs and foundations. Light