This document provides a report on a technical site visit to an Andes Construction site. The following key points are made:
- The site visit allowed students to understand construction processes in practice compared to theory, and exposed them to the working environment and safety practices.
- The site was separated into three zones, with the foundation completed in Zone A and in progress in Zone B. Pile cap foundation was used due to unstable soil conditions.
- Advantages of pile cap foundations include increased bearing capacity and ability to use in areas with underground water pressure. Disadvantages include higher costs and need for heavy equipment.
- Concrete grade 25 was used for casting beams, columns, slabs and foundations. Light
Effect Of Lightweight Blocks On High Rise Commercial & Residential Building W...Meesum Zaidi
The objective of the study design non-load bearing lightweight blocks which are lighter in weight than standard blocks using polystyrene beads and to determine the effects of lighter blocks on the structure in terms of cost and weight of the building.
The project was carried out with the assistance from teachers and Costveyors (Pvt.) Ltd in which the lightweight blocks were prepared in progression of 0%, 20%, 40%, 60%, 80% substitution of coarse aggregate with polystyrene beads. Two samples sizes were selected for preparation, 4” x 8” x 12” and 6” x 8” x 12”.
After the preparation, blocks were cured for 3, 7, 14, & 28 days. Weight of the blocks were determined and then tested for compression using CTM machine. Results in weight and strength of the blocks were obtained and reduction in block weight was achieved as 27%.
To determine the effect of these blocks in building, first a commercial building was selected but after analyzing the building in load it was found that the building was not dominant in block masonry. So after, consultation with teachers and professional, the commercial building was converted into a residential apartment building by changing wall layout in the building only. The residential apartment building was then analyzed for concrete, reinforcement, block masonry and dead load using standard blocks.
The building was again analyzed for dead load using lightweight blocks. At reduced loads and moments structural members of the building were redesigned and estimation of concrete & reinforcement was done. Total weight and cost estimation was done for both structures. It was found that weight and cost of the building was reduced by 15% and 10%.
Major outputs of the project included
1) Conventional structure is expensive than lightweight.
2) Saving on materials, as structural members sizes reduced.
CELLULAR LIGHT WEIGHT CONCRETE BLOCKS WITH DIFFERENT MIX PROPORTIONSIjripublishers Ijri
Burnt Clay Brick is the predominant construction material in the country. The CO2 emissions in the brick manufacture
process have been acknowledged as a significant factor to global warming. Now-a-days there are so many technologies
involved in the recent development of concrete. Cellular Lightweight Concrete (CLC) is one of the recent emerging technology
in making concrete. The usage of Cellular Light-weight Concrete (CLC) gives a prospective solution to building
construction industry along with environmental preservation. By using this type of concrete, we have found so many
advantages when compared to the burnt clay bricks.
Cellular Light Weight Concrete Blocks Machine- Manufacturers & Suppliers
Our proficient and dedicated professionals make the utmost use of these facilities and work round the clock with a client centric approach to meet the industrial requirements. These professionals are well versed and have updated knowledge on the latest technology which ensures hassle free and efficient procurement and storage. We have been highly benefited by our facilities, this being one of the reasons for establishing ourselves as a prominent organization.
www.clcblockmachine.in, www.clcplant.com
Effect Of Lightweight Blocks On High Rise Commercial & Residential Building W...Meesum Zaidi
The objective of the study design non-load bearing lightweight blocks which are lighter in weight than standard blocks using polystyrene beads and to determine the effects of lighter blocks on the structure in terms of cost and weight of the building.
The project was carried out with the assistance from teachers and Costveyors (Pvt.) Ltd in which the lightweight blocks were prepared in progression of 0%, 20%, 40%, 60%, 80% substitution of coarse aggregate with polystyrene beads. Two samples sizes were selected for preparation, 4” x 8” x 12” and 6” x 8” x 12”.
After the preparation, blocks were cured for 3, 7, 14, & 28 days. Weight of the blocks were determined and then tested for compression using CTM machine. Results in weight and strength of the blocks were obtained and reduction in block weight was achieved as 27%.
To determine the effect of these blocks in building, first a commercial building was selected but after analyzing the building in load it was found that the building was not dominant in block masonry. So after, consultation with teachers and professional, the commercial building was converted into a residential apartment building by changing wall layout in the building only. The residential apartment building was then analyzed for concrete, reinforcement, block masonry and dead load using standard blocks.
The building was again analyzed for dead load using lightweight blocks. At reduced loads and moments structural members of the building were redesigned and estimation of concrete & reinforcement was done. Total weight and cost estimation was done for both structures. It was found that weight and cost of the building was reduced by 15% and 10%.
Major outputs of the project included
1) Conventional structure is expensive than lightweight.
2) Saving on materials, as structural members sizes reduced.
CELLULAR LIGHT WEIGHT CONCRETE BLOCKS WITH DIFFERENT MIX PROPORTIONSIjripublishers Ijri
Burnt Clay Brick is the predominant construction material in the country. The CO2 emissions in the brick manufacture
process have been acknowledged as a significant factor to global warming. Now-a-days there are so many technologies
involved in the recent development of concrete. Cellular Lightweight Concrete (CLC) is one of the recent emerging technology
in making concrete. The usage of Cellular Light-weight Concrete (CLC) gives a prospective solution to building
construction industry along with environmental preservation. By using this type of concrete, we have found so many
advantages when compared to the burnt clay bricks.
Cellular Light Weight Concrete Blocks Machine- Manufacturers & Suppliers
Our proficient and dedicated professionals make the utmost use of these facilities and work round the clock with a client centric approach to meet the industrial requirements. These professionals are well versed and have updated knowledge on the latest technology which ensures hassle free and efficient procurement and storage. We have been highly benefited by our facilities, this being one of the reasons for establishing ourselves as a prominent organization.
www.clcblockmachine.in, www.clcplant.com
DETAILED STUDY OF FOAM CONCRETE
1- MATERIALS USED
2- MACHINE USED( HAND MAKING WORKABLE EQUIPMENT FOR MIXING)
3-TESTING PROCEDURE
4- YOU GUYZ CAN ALSO LEARN THROUGH THE PHOTOGRAPHS
DETAILED STUDY OF FOAM CONCRETE
1- MATERIALS USED
2- MACHINE USED( HAND MAKING WORKABLE EQUIPMENT FOR MIXING)
3-TESTING PROCEDURE
4- YOU GUYZ CAN ALSO LEARN THROUGH THE PHOTOGRAPHS
Data Centers - Striving Within A Narrow Range - Research Report - MCG - May 2...pchutichetpong
M Capital Group (“MCG”) expects to see demand and the changing evolution of supply, facilitated through institutional investment rotation out of offices and into work from home (“WFH”), while the ever-expanding need for data storage as global internet usage expands, with experts predicting 5.3 billion users by 2023. These market factors will be underpinned by technological changes, such as progressing cloud services and edge sites, allowing the industry to see strong expected annual growth of 13% over the next 4 years.
Whilst competitive headwinds remain, represented through the recent second bankruptcy filing of Sungard, which blames “COVID-19 and other macroeconomic trends including delayed customer spending decisions, insourcing and reductions in IT spending, energy inflation and reduction in demand for certain services”, the industry has seen key adjustments, where MCG believes that engineering cost management and technological innovation will be paramount to success.
MCG reports that the more favorable market conditions expected over the next few years, helped by the winding down of pandemic restrictions and a hybrid working environment will be driving market momentum forward. The continuous injection of capital by alternative investment firms, as well as the growing infrastructural investment from cloud service providers and social media companies, whose revenues are expected to grow over 3.6x larger by value in 2026, will likely help propel center provision and innovation. These factors paint a promising picture for the industry players that offset rising input costs and adapt to new technologies.
According to M Capital Group: “Specifically, the long-term cost-saving opportunities available from the rise of remote managing will likely aid value growth for the industry. Through margin optimization and further availability of capital for reinvestment, strong players will maintain their competitive foothold, while weaker players exit the market to balance supply and demand.”
Levelwise PageRank with Loop-Based Dead End Handling Strategy : SHORT REPORT ...Subhajit Sahu
Abstract — Levelwise PageRank is an alternative method of PageRank computation which decomposes the input graph into a directed acyclic block-graph of strongly connected components, and processes them in topological order, one level at a time. This enables calculation for ranks in a distributed fashion without per-iteration communication, unlike the standard method where all vertices are processed in each iteration. It however comes with a precondition of the absence of dead ends in the input graph. Here, the native non-distributed performance of Levelwise PageRank was compared against Monolithic PageRank on a CPU as well as a GPU. To ensure a fair comparison, Monolithic PageRank was also performed on a graph where vertices were split by components. Results indicate that Levelwise PageRank is about as fast as Monolithic PageRank on the CPU, but quite a bit slower on the GPU. Slowdown on the GPU is likely caused by a large submission of small workloads, and expected to be non-issue when the computation is performed on massive graphs.
Chatty Kathy - UNC Bootcamp Final Project Presentation - Final Version - 5.23...John Andrews
SlideShare Description for "Chatty Kathy - UNC Bootcamp Final Project Presentation"
Title: Chatty Kathy: Enhancing Physical Activity Among Older Adults
Description:
Discover how Chatty Kathy, an innovative project developed at the UNC Bootcamp, aims to tackle the challenge of low physical activity among older adults. Our AI-driven solution uses peer interaction to boost and sustain exercise levels, significantly improving health outcomes. This presentation covers our problem statement, the rationale behind Chatty Kathy, synthetic data and persona creation, model performance metrics, a visual demonstration of the project, and potential future developments. Join us for an insightful Q&A session to explore the potential of this groundbreaking project.
Project Team: Jay Requarth, Jana Avery, John Andrews, Dr. Dick Davis II, Nee Buntoum, Nam Yeongjin & Mat Nicholas
Opendatabay - Open Data Marketplace.pptxOpendatabay
Opendatabay.com unlocks the power of data for everyone. Open Data Marketplace fosters a collaborative hub for data enthusiasts to explore, share, and contribute to a vast collection of datasets.
First ever open hub for data enthusiasts to collaborate and innovate. A platform to explore, share, and contribute to a vast collection of datasets. Through robust quality control and innovative technologies like blockchain verification, opendatabay ensures the authenticity and reliability of datasets, empowering users to make data-driven decisions with confidence. Leverage cutting-edge AI technologies to enhance the data exploration, analysis, and discovery experience.
From intelligent search and recommendations to automated data productisation and quotation, Opendatabay AI-driven features streamline the data workflow. Finding the data you need shouldn't be a complex. Opendatabay simplifies the data acquisition process with an intuitive interface and robust search tools. Effortlessly explore, discover, and access the data you need, allowing you to focus on extracting valuable insights. Opendatabay breaks new ground with a dedicated, AI-generated, synthetic datasets.
Leverage these privacy-preserving datasets for training and testing AI models without compromising sensitive information. Opendatabay prioritizes transparency by providing detailed metadata, provenance information, and usage guidelines for each dataset, ensuring users have a comprehensive understanding of the data they're working with. By leveraging a powerful combination of distributed ledger technology and rigorous third-party audits Opendatabay ensures the authenticity and reliability of every dataset. Security is at the core of Opendatabay. Marketplace implements stringent security measures, including encryption, access controls, and regular vulnerability assessments, to safeguard your data and protect your privacy.
Techniques to optimize the pagerank algorithm usually fall in two categories. One is to try reducing the work per iteration, and the other is to try reducing the number of iterations. These goals are often at odds with one another. Skipping computation on vertices which have already converged has the potential to save iteration time. Skipping in-identical vertices, with the same in-links, helps reduce duplicate computations and thus could help reduce iteration time. Road networks often have chains which can be short-circuited before pagerank computation to improve performance. Final ranks of chain nodes can be easily calculated. This could reduce both the iteration time, and the number of iterations. If a graph has no dangling nodes, pagerank of each strongly connected component can be computed in topological order. This could help reduce the iteration time, no. of iterations, and also enable multi-iteration concurrency in pagerank computation. The combination of all of the above methods is the STICD algorithm. [sticd] For dynamic graphs, unchanged components whose ranks are unaffected can be skipped altogether.
Explore our comprehensive data analysis project presentation on predicting product ad campaign performance. Learn how data-driven insights can optimize your marketing strategies and enhance campaign effectiveness. Perfect for professionals and students looking to understand the power of data analysis in advertising. for more details visit: https://bostoninstituteofanalytics.org/data-science-and-artificial-intelligence/
Show drafts
volume_up
Empowering the Data Analytics Ecosystem: A Laser Focus on Value
The data analytics ecosystem thrives when every component functions at its peak, unlocking the true potential of data. Here's a laser focus on key areas for an empowered ecosystem:
1. Democratize Access, Not Data:
Granular Access Controls: Provide users with self-service tools tailored to their specific needs, preventing data overload and misuse.
Data Catalogs: Implement robust data catalogs for easy discovery and understanding of available data sources.
2. Foster Collaboration with Clear Roles:
Data Mesh Architecture: Break down data silos by creating a distributed data ownership model with clear ownership and responsibilities.
Collaborative Workspaces: Utilize interactive platforms where data scientists, analysts, and domain experts can work seamlessly together.
3. Leverage Advanced Analytics Strategically:
AI-powered Automation: Automate repetitive tasks like data cleaning and feature engineering, freeing up data talent for higher-level analysis.
Right-Tool Selection: Strategically choose the most effective advanced analytics techniques (e.g., AI, ML) based on specific business problems.
4. Prioritize Data Quality with Automation:
Automated Data Validation: Implement automated data quality checks to identify and rectify errors at the source, minimizing downstream issues.
Data Lineage Tracking: Track the flow of data throughout the ecosystem, ensuring transparency and facilitating root cause analysis for errors.
5. Cultivate a Data-Driven Mindset:
Metrics-Driven Performance Management: Align KPIs and performance metrics with data-driven insights to ensure actionable decision making.
Data Storytelling Workshops: Equip stakeholders with the skills to translate complex data findings into compelling narratives that drive action.
Benefits of a Precise Ecosystem:
Sharpened Focus: Precise access and clear roles ensure everyone works with the most relevant data, maximizing efficiency.
Actionable Insights: Strategic analytics and automated quality checks lead to more reliable and actionable data insights.
Continuous Improvement: Data-driven performance management fosters a culture of learning and continuous improvement.
Sustainable Growth: Empowered by data, organizations can make informed decisions to drive sustainable growth and innovation.
By focusing on these precise actions, organizations can create an empowered data analytics ecosystem that delivers real value by driving data-driven decisions and maximizing the return on their data investment.
1. 1
SCHOOL OF ARCHITECTURE, BUILDING & DESIGN
Centre for Modern Architecture Studies in Southeast Asia
Bachelorof Quantity Surveyor[QSB 60104]
ConstructionTechnologyI [BLD 60104]
Building Materials [BLD 62003]
Title: Technical Site Visit to Andes Construction Site
AssignmentDate: 26 June 2015
Submission Date: 3 July 2015
Name: Ng Wai Khong
StudentID: 0317980
3. 3
Introduction
As a quantity surveyor, we are required to not only estimate the pricing and
quantity of the building materials needed for a construction, but also get to
discover the attempts of changes of the sites in daily routine. Hence, for this
assignment, which is a mixture of 3 main subjects, Measurement, Construction
Technology and Building Materials which are compactible to each other, the
lecturers had planned to bring us to a site visit to obtained the knowledge itself
practically rather than just on papers and books.
As a report introduction, the site is around 15km far from our departure
destinations. It takes us around 15minutes to reach that site. We are required to
wear a safety helmet in case that accidents happened can help to reduce the
injuries to as low as possible. The weather of that day is very humid and yet we
need to adapt to this kind of often-changed weather on site. Instantly, a brief talk
is given to all of us regarding the current progress of the site and the safety
measures that should be taken.
Based on the Project Manager of the site, the site is separate to 3 zones, which is
A, B and C. Furthermore, the foundation of Zone A is done and the foundation of
Zone B is progressing. The whole project estimated pricing is around MYR
12.5M, and the starting date of the construction is on July/2014. In addition, we
are separated to 3 groups each guided by one of the supervisor of the site.
Basically, without any rest, we approached quickly to the site which is full of
sand and mud.
We went up and down the construction site to experience how the workers work
to build and construct a building itself from the ground. From Zone A to Zone B,
it takes us around 45 minutes to explore the hidden knowledge in the site. For
Zone A, the foundation is completely constructed and we get to discover how
does a Mesh Fabric Reinforcement looks like and the details steel rods placement
inside a column before applying the concrete in it.
For Zone B, we get to discover in details of the work below ground floor level. We
are lucky enough to get a view of the work underground like piling and how they
drained out the water from the site. Although the journey is short, we get to rest
after an adventure throughout the site. We have our small meal there and visits
the working place of the supervisor which is a small cabin where they located
their drawings and stuffs.
4. 4
Objective
To understand the basics of the construction process.
To understand the pratical aspect of construction techniques in
comparison to the theory aspect in books and its application on site.
Exposure to actual working environment on site including uncertainty
circumstances.
Ability to communicate with the construction team members on site and
to see the importance of teamwork in the building team.
Witness the usage of construction equipment on site including mechanical
plants.
Explore and identify various types of building materials and technology
on site.
Awareness of the importance of safety on site and understanding of safety
problems and site conditions.
Recognize the items measurable for sub-structure and reinforced
concrete frame works.
5. 5
Construction Technology (Types of Foundation)
The types of foundation involve majorly in the construction site is Pile cap. Pile
cap foundation is basically more suitable to our site because for our building is
supposed to be a 25 level apartment. Yet, this is the only foundation which is
suitable for this type of high rise building compare to strip foundation and pad
footing foundation. While, the foundation for Zone A is finish constructed, but for
Zone B, they just started their piling work.
The image shown above is one the pile that is completely piled to the
underground and this is the biggest pilecap on-site. Due to the condition of the
soil which is unstable, this is quite a difficult task for them to figure how the size
of the pile cap should be. Hence, this is the largest volume of pile cap they done in
their recent project.
Furthermore, there will be a table showing the advantages and disadvantages of
pilecap foundation.
6. 6
Advantages of Pile Cap
Foundation
Disadvantages of Pile Cap
Foundation
Piles can precast to the required
specifications.
Precast or pre-stressed concrete piles
must be properly reinforced to
withstand handling stresses during the
transportation and driving.
Piles of any soil, length and shape
can be made in advance and used at
the site. The progress of the work
will be rapid.
Advance planning is required for
handling and driving.
A pile driven into granular soil
compacts the adjacent soil mass and
as a result the bearing capacity of
the pile is increased.
Requires heavy equipment for handling
and driving.
The work is neat and clean. The
supervision of work at the site can
be reduced to a minimum. The
storage space required is very much
less.
Since the exact lengths required at the
site cannot be determined in advance,
the method involves cutting off extra
lengths or adding more lengths.
Increases the cost of the project.
Driven piles may conveniently be
used in places where it is advisable
not to drill holes for fear of meeting
ground water under pressure.
Driven piles are not suitable in soils of
poor drainage qualities. If the driving of
piles is not properly phased and
arranged, there is every possibility of
heaving of the soil or the lifting of the
driven piles during the driving of the
new pile.
7. 7
Building Materials
Most of the beam, column, slab and even foundation is cast with concrete and in
the market there is lot of types of concrete grades where each different grade of
concrete bring different effects which is either good or bad and the suitability of
the grade of concrete to the beam, column, slab and foundation itself.
The grade of concrete identifies the content of the concrete and there are mainly
two types of grade of concrete which is light weight grade concrete and heavy
weight grade concrete. The concrete grade which is used in the site is Grade 25
which is the usual grade used in concrete casting for buildings. Grade 25 is
considered as light moderate grade of concrete.
The advantage and disadvantages of light weight concrete is shown in the table:
Advantages Disadvantages
It helps to reduce the dead load,
increase the progress of building and
lowers the hauling and handling cost.
Very sensitive with water content in
the mixtures.
The weight of building on foundation
is an important factor in the design,
particularly in case of weak soil and
tall structures, In framed structured,
the beam and column have to carry
load of wall and floor, If these wall
and floor made of light weight
concrete it will result in considerable
economy.
Mixing time is longer than
conventional concrete to assure
proper mixing.
Low Thermal Conductivity.
Structural lightweight aggregate’s
cellular structure provides internal
curing through water entrainment
which is especially beneficial for high-
performance concrete.
Difficult to place and finish because
the porosity and angularity of the
aggregate. In some mixes the cement
mortar may separate the aggregate
and float towards the surface.
Appendix
8. 8
Pilecap Plan from our site
visit.
Site office where all the files
and plans are located at.
9. 9
Zone B, where they are
starting to cast the concrete
on the foundation.
The Project Manager Office.
10. 10
The project manager itself
showing the stirrups that
will be used in the site.
More Steel rods that will be
used for the site.
13. 13
Conclusion
In a nutshell, the whole site visit is a valuable experience for me because I get to
learn all of these in practical than studying. I get to discover the plants and
different building materials obtained on site. Yet, this is crucial part for my life by
gaining experience of how a building is constructed from a drawing to a real
construction experience.
Instantly, this site visit tells me that how important it is for the mixture of the
main 3 core subject we learn in our first semester and this report brings to the
end of the overall modules that we learnt in classes. Of course, when we went to
the site, we get to be able to easily analyze all the types of materials and
construction technology involve in the site.
Thank You.