SlideShare a Scribd company logo
1 of 11
INTRODUCTION
In this assignment, we are required to write a site visit report,
which is, organized on the 26th of June 2015 by our Measurement I
lecturer Ms Ang Fuey Lin. This assignment is involved in three
modules, which are Measurement I, Construction Technology I and
building Materials. Before that, every one of us should prepare a safety
helmet to ensure our safety. During that day, we are gathered at
Taylor’s University at around 9am. It takes around 20 minutes to the
site, which is located at BukitJalil.
When we arrived at the site, the project manager gave us a 15
minutes briefing of the site about the project which is cost roughly
RM21.5 million. Besides, this is the biggest pilecap that they had ever
made which is 24BP1200A. After that, the project manager gave us
another short briefing about the safety precautions we have to take
while walking around at the site. We also need to be very careful on
our own safety and ensure that we do not slip and fall which can lead
to a lot of problems.
When the briefing is completed, we are divided into three groups,
each group consist of 9 to 10 people. Then, we follow the person who
in charge of us and finally given the tour on the site.
Type of foundation used for the site
The typeof foundation, whichis used in this projectis pile
foundation. A pilefoundation isa long slender foundation, itis made
by either timber , structuralsteel or concrete which might be cast-in-
situ or driven and acts as a structural member to transfer the load of
the structureto a required depthin deep foundationscarryingaload
which may be vertical or lateral or lateral plusvertical.
The gradeof concrete used for the column is grade 45, for beam
is grade 35. Moreover, the concrete gradefor slab is grade35 and for
the foundation itis grade30.
These are the advantagesand disadvantagesfor pile foundation:
Advantages Disadvantages
The size, length and shape can be
madein advanced and used at the site.
Advance planning is required for
handling and driving.
The work is neat and clean.
Required heavy equipment for
handling and driving.
High individual load capacity.
May suffer unseen damage, which
reduces carrying capacity.
Can be driven in very long length.
May break during driving
necessitating replacement piles.
Advantagesand disadvantagesof reinforced concrete:
Advantages Disadvantages
The reinforced concrete building
system is moredurable than any other
building system.
The tensile strength of reinforced
concrete is about one tenth of its
compressive strength.
The maintenance cost of reinforced
concrete is very low
The cost of the forms used for the
casting reinforced concrete is
relatively higher.
Compared to the use of steel in
structure, reinforcesconcrete requires
less killed labor for the erection of
structure.
Shrinkage causes crack development
and strength loss
Fire and weather resistance of
reinforced concrete is fair.
It needs mixing, casting, and curing, all
of which affect the final strength of
concrete.
PHOTOS AND DESCRIPTION
Temporary Work
This is a temporary place,
which is provided to the
workers of there to relax and
take a break.
A temporary work for the
drainage system since there is a
lot of ground water and
rainwater, which has to be
removed.
Plants and tools used:
This is a bar bending machine
which is used to bend the
reinforcement bars into ant
shapes and angles. This is more
convenient for the worker.
The blue machine is a welding
generator, which provides
current electrical to perform
welding.
Excavators are also used on the
site that is used for earth digging
and loading the excavated
materials into the loading trucks to
either for disposal or used later.
Construction Work:
This is acted as a balancing tool
for the formwork that can help to
make it straight.
The pile cap of the building is
found on the site.
The worker is tear apart the
formwork after the concrete is
dried over one night.
The links and the reinforced
concrete is found in the site. The
grade of the bars is Grade 500. It
is 12M long.
This is a concrete cover which is
35mm thick which has already
placed at the reinforcement bars
for column.
This is the column stump of the
foundation.
The links were tied to the
reinforcement bars of the
column.
The workers were making
concrete covers.
The formwork is done which is
ready for concrete to pour inside
it.
We found reinforcement bars,
which are inside the walls.
CONCLUSION
After this site visit, I had gained a lot of new experience and
knowledge, which I cannot get from the books. I realized that going to
the site is muchmore differentthan just learningthe theory from the
books.
Besides, after visiting the site, I truly understand thesituation of
the site visit includingthe scorching of sun and the dustin the site. I
also gained knowledgeaboutthe process of construction process, the
way of usingmachinery equipmentand can differentiatethe typesof
the buildingmaterials used in the construction.
As a conclusion, I really learn a lot and gained a lot for my future
which preparemeto overcomemany upcomingproblem throughout
the coursefrom this site visiting.
OBJECTIVES
 Understand the basic of the construction process.
 Understand the practical aspect of construction techniques in
comparison to the theory aspect in books and its application on site.
 Exposure to actual working environment on site including
uncertainty circumstancee.g. weather.
 Ability to communicate with the construction team members on site
and to see the importanceof teamwork in the buildingteam.
 Witness the usage of construction equipment on site including
mechanical plants.
 Explore and identify various types of building materials and
technology on site.
 Awareness of the importance of safety on site and understanding of
safety problemsand site conditions.
 Recognize the items measureable for sub-structure and reinforced
concrete frameworks.

More Related Content

What's hot

CT site visit report
CT site visit report CT site visit report
CT site visit report Yap Xin
 
SITE VISIT REPORT
SITE VISIT REPORTSITE VISIT REPORT
SITE VISIT REPORTWan Nee
 
Site visit report 2017
Site visit report 2017Site visit report 2017
Site visit report 2017bee_by
 
Site visit-report-nov2015
Site visit-report-nov2015Site visit-report-nov2015
Site visit-report-nov2015Joyce HweeMin
 
bqs Site report
bqs Site reportbqs Site report
bqs Site reportFelix Vong
 
Visit to a construction site
Visit to a construction siteVisit to a construction site
Visit to a construction siteUmair Ali
 
Civil engineering internship report
Civil engineering internship reportCivil engineering internship report
Civil engineering internship reportMd Mohsin Mohsin
 
BQS Site Visit Report
BQS Site Visit ReportBQS Site Visit Report
BQS Site Visit ReportHasif Alias
 
Site visit report
Site visit reportSite visit report
Site visit reportEyelynLee
 
Construction of residential building
Construction of residential buildingConstruction of residential building
Construction of residential buildingSumit Singh
 
Civil enginerring internship report
Civil enginerring internship reportCivil enginerring internship report
Civil enginerring internship reportZahid Khan
 
Building Construction
Building ConstructionBuilding Construction
Building ConstructionWilden How
 
Building project presentation
Building project presentationBuilding project presentation
Building project presentationemdad bhuiyan
 
Construction of residential building summer training ppt
 Construction of residential building summer training ppt Construction of residential building summer training ppt
Construction of residential building summer training pptSumit Singh
 
Ctw site report(pg 1 to 8, 14)
Ctw site report(pg 1 to 8, 14)Ctw site report(pg 1 to 8, 14)
Ctw site report(pg 1 to 8, 14)Chin Tze Wei
 
Construction site
Construction siteConstruction site
Construction siteTimun Loh
 
civil enginnering industrial training report
civil enginnering industrial training report civil enginnering industrial training report
civil enginnering industrial training report KRISHNA MURARI
 
Technical site visit report
Technical site visit reportTechnical site visit report
Technical site visit reportMomo Poyi
 

What's hot (20)

Site visit report
Site visit reportSite visit report
Site visit report
 
CT site visit report
CT site visit report CT site visit report
CT site visit report
 
SITE VISIT REPORT
SITE VISIT REPORTSITE VISIT REPORT
SITE VISIT REPORT
 
Site visit report 2017
Site visit report 2017Site visit report 2017
Site visit report 2017
 
Site visit-report-nov2015
Site visit-report-nov2015Site visit-report-nov2015
Site visit-report-nov2015
 
bqs Site report
bqs Site reportbqs Site report
bqs Site report
 
Visit to a construction site
Visit to a construction siteVisit to a construction site
Visit to a construction site
 
Civil engineering internship report
Civil engineering internship reportCivil engineering internship report
Civil engineering internship report
 
BQS Site Visit Report
BQS Site Visit ReportBQS Site Visit Report
BQS Site Visit Report
 
Site visit report
Site visit reportSite visit report
Site visit report
 
Construction of residential building
Construction of residential buildingConstruction of residential building
Construction of residential building
 
Civil enginerring internship report
Civil enginerring internship reportCivil enginerring internship report
Civil enginerring internship report
 
Building Construction
Building ConstructionBuilding Construction
Building Construction
 
Building project presentation
Building project presentationBuilding project presentation
Building project presentation
 
Construction of residential building summer training ppt
 Construction of residential building summer training ppt Construction of residential building summer training ppt
Construction of residential building summer training ppt
 
Site Survey Report
Site Survey ReportSite Survey Report
Site Survey Report
 
Ctw site report(pg 1 to 8, 14)
Ctw site report(pg 1 to 8, 14)Ctw site report(pg 1 to 8, 14)
Ctw site report(pg 1 to 8, 14)
 
Construction site
Construction siteConstruction site
Construction site
 
civil enginnering industrial training report
civil enginnering industrial training report civil enginnering industrial training report
civil enginnering industrial training report
 
Technical site visit report
Technical site visit reportTechnical site visit report
Technical site visit report
 

Viewers also liked

Assignment 1 Site Visit Report
Assignment 1 Site Visit ReportAssignment 1 Site Visit Report
Assignment 1 Site Visit Reportarmada7000
 
Building Construction Project 1 Shelter Report
Building Construction Project 1 Shelter ReportBuilding Construction Project 1 Shelter Report
Building Construction Project 1 Shelter ReportJoyeeLee0131
 
building construction project 1 report
building construction project 1 reportbuilding construction project 1 report
building construction project 1 reportYq Chong
 
Building construction 2 project 1 report
Building construction 2 project 1 reportBuilding construction 2 project 1 report
Building construction 2 project 1 reportOng Seng Peng Jeff
 
Site visit report
Site visit reportSite visit report
Site visit reportJordon Wong
 
Site Visit report- Measurement I, Building materials, Construction Technology I
Site Visit report- Measurement I, Building materials, Construction Technology ISite Visit report- Measurement I, Building materials, Construction Technology I
Site Visit report- Measurement I, Building materials, Construction Technology Ikaiwenyeo
 
Assignment 2 - Jaya Shopping Centre
Assignment 2 - Jaya Shopping CentreAssignment 2 - Jaya Shopping Centre
Assignment 2 - Jaya Shopping CentreKai Yun Pang
 
Fifth year report bc
Fifth year report bcFifth year report bc
Fifth year report bcRohit Digra
 
Building construction report
Building construction reportBuilding construction report
Building construction reportSoh Shing
 
Assignment 1 - Site Visit Report
Assignment 1 - Site Visit ReportAssignment 1 - Site Visit Report
Assignment 1 - Site Visit ReportKai Yun Pang
 
Site visit report.
Site visit report.Site visit report.
Site visit report.Man Yee
 
Building Construction 2 Project 1 Report
Building Construction 2 Project 1 ReportBuilding Construction 2 Project 1 Report
Building Construction 2 Project 1 Reporthiewyennee
 
Building Construction Analysis Report
Building Construction Analysis ReportBuilding Construction Analysis Report
Building Construction Analysis ReportDaniel Yap
 
Building construction I project 1 report
Building construction I project 1 reportBuilding construction I project 1 report
Building construction I project 1 reportAmos Tan
 
Building Construction Report
Building Construction ReportBuilding Construction Report
Building Construction ReportSheau Hui Tan
 
Site Visit Report
Site Visit ReportSite Visit Report
Site Visit ReportZIyeeTan
 
Multi story building construction training report anshul
Multi story building construction training report anshulMulti story building construction training report anshul
Multi story building construction training report anshulAnshul Shakya
 
Building construction ii report (1)
Building construction ii report  (1)Building construction ii report  (1)
Building construction ii report (1)Chong jiayi
 
Building Construction Project 01 Final Report
Building Construction Project 01 Final ReportBuilding Construction Project 01 Final Report
Building Construction Project 01 Final ReportjolynnTJL
 

Viewers also liked (20)

Site visit report
Site visit reportSite visit report
Site visit report
 
Assignment 1 Site Visit Report
Assignment 1 Site Visit ReportAssignment 1 Site Visit Report
Assignment 1 Site Visit Report
 
Building Construction Project 1 Shelter Report
Building Construction Project 1 Shelter ReportBuilding Construction Project 1 Shelter Report
Building Construction Project 1 Shelter Report
 
building construction project 1 report
building construction project 1 reportbuilding construction project 1 report
building construction project 1 report
 
Building construction 2 project 1 report
Building construction 2 project 1 reportBuilding construction 2 project 1 report
Building construction 2 project 1 report
 
Site visit report
Site visit reportSite visit report
Site visit report
 
Site Visit report- Measurement I, Building materials, Construction Technology I
Site Visit report- Measurement I, Building materials, Construction Technology ISite Visit report- Measurement I, Building materials, Construction Technology I
Site Visit report- Measurement I, Building materials, Construction Technology I
 
Assignment 2 - Jaya Shopping Centre
Assignment 2 - Jaya Shopping CentreAssignment 2 - Jaya Shopping Centre
Assignment 2 - Jaya Shopping Centre
 
Fifth year report bc
Fifth year report bcFifth year report bc
Fifth year report bc
 
Building construction report
Building construction reportBuilding construction report
Building construction report
 
Assignment 1 - Site Visit Report
Assignment 1 - Site Visit ReportAssignment 1 - Site Visit Report
Assignment 1 - Site Visit Report
 
Site visit report.
Site visit report.Site visit report.
Site visit report.
 
Building Construction 2 Project 1 Report
Building Construction 2 Project 1 ReportBuilding Construction 2 Project 1 Report
Building Construction 2 Project 1 Report
 
Building Construction Analysis Report
Building Construction Analysis ReportBuilding Construction Analysis Report
Building Construction Analysis Report
 
Building construction I project 1 report
Building construction I project 1 reportBuilding construction I project 1 report
Building construction I project 1 report
 
Building Construction Report
Building Construction ReportBuilding Construction Report
Building Construction Report
 
Site Visit Report
Site Visit ReportSite Visit Report
Site Visit Report
 
Multi story building construction training report anshul
Multi story building construction training report anshulMulti story building construction training report anshul
Multi story building construction training report anshul
 
Building construction ii report (1)
Building construction ii report  (1)Building construction ii report  (1)
Building construction ii report (1)
 
Building Construction Project 01 Final Report
Building Construction Project 01 Final ReportBuilding Construction Project 01 Final Report
Building Construction Project 01 Final Report
 

Similar to Site visit report

Project SlideShare
Project SlideShareProject SlideShare
Project SlideShareYung Kai
 
Site report
Site reportSite report
Site reportvaylu
 
Measurement 1-site-visit
Measurement 1-site-visitMeasurement 1-site-visit
Measurement 1-site-visitPui San
 
Site visit report
Site visit reportSite visit report
Site visit reportDoreen Yeo
 
om industrial training report.pptx
om industrial training report.pptxom industrial training report.pptx
om industrial training report.pptxRohitYadav530108
 
Final Report
Final Report Final Report
Final Report Jack Ng
 
Measurement 1 site report
Measurement 1 site reportMeasurement 1 site report
Measurement 1 site reportJessyca Than
 
Integrated assignment site report
Integrated assignment site reportIntegrated assignment site report
Integrated assignment site reportw ss
 
SITE REPORT (PAD FOOTING)
SITE REPORT (PAD FOOTING)SITE REPORT (PAD FOOTING)
SITE REPORT (PAD FOOTING)I'mMiss Lily
 
Ct bm measurement report
Ct bm measurement reportCt bm measurement report
Ct bm measurement reportKailyn Lee
 
Site report algel
Site report algelSite report algel
Site report algelAlgel Yee
 
Assignment 1 - Antara Gapi, Hulu Selangor, Selangor
Assignment 1 - Antara Gapi, Hulu Selangor, SelangorAssignment 1 - Antara Gapi, Hulu Selangor, Selangor
Assignment 1 - Antara Gapi, Hulu Selangor, SelangorKai Yun Pang
 

Similar to Site visit report (20)

Project SlideShare
Project SlideShareProject SlideShare
Project SlideShare
 
Site report
Site reportSite report
Site report
 
Ez
EzEz
Ez
 
Measurement 1-site-visit
Measurement 1-site-visitMeasurement 1-site-visit
Measurement 1-site-visit
 
Report
ReportReport
Report
 
Site report
Site reportSite report
Site report
 
Construction Site Report
Construction Site ReportConstruction Site Report
Construction Site Report
 
Site visit report
Site visit reportSite visit report
Site visit report
 
Site report
Site reportSite report
Site report
 
MCB Final report
MCB Final reportMCB Final report
MCB Final report
 
om industrial training report.pptx
om industrial training report.pptxom industrial training report.pptx
om industrial training report.pptx
 
Final Report
Final Report Final Report
Final Report
 
Site report
Site reportSite report
Site report
 
Site report
Site reportSite report
Site report
 
Measurement 1 site report
Measurement 1 site reportMeasurement 1 site report
Measurement 1 site report
 
Integrated assignment site report
Integrated assignment site reportIntegrated assignment site report
Integrated assignment site report
 
SITE REPORT (PAD FOOTING)
SITE REPORT (PAD FOOTING)SITE REPORT (PAD FOOTING)
SITE REPORT (PAD FOOTING)
 
Ct bm measurement report
Ct bm measurement reportCt bm measurement report
Ct bm measurement report
 
Site report algel
Site report algelSite report algel
Site report algel
 
Assignment 1 - Antara Gapi, Hulu Selangor, Selangor
Assignment 1 - Antara Gapi, Hulu Selangor, SelangorAssignment 1 - Antara Gapi, Hulu Selangor, Selangor
Assignment 1 - Antara Gapi, Hulu Selangor, Selangor
 

More from Liming Hiew

M2 project assignment aug 2015
M2 project assignment aug 2015M2 project assignment aug 2015
M2 project assignment aug 2015Liming Hiew
 
Construction technology report
Construction technology reportConstruction technology report
Construction technology reportLiming Hiew
 
Assignment brief for site report
Assignment brief for site report Assignment brief for site report
Assignment brief for site report Liming Hiew
 
Coffee table book
Coffee table bookCoffee table book
Coffee table bookLiming Hiew
 
Cn c brief2_ctb_201514sept
Cn c brief2_ctb_201514septCn c brief2_ctb_201514sept
Cn c brief2_ctb_201514septLiming Hiew
 
Cn c brief2_092014sept
Cn c brief2_092014septCn c brief2_092014sept
Cn c brief2_092014septLiming Hiew
 
Project 1 0214brief with tgc
Project 1 0214brief with tgcProject 1 0214brief with tgc
Project 1 0214brief with tgcLiming Hiew
 
Design p2 a april
Design p2 a aprilDesign p2 a april
Design p2 a aprilLiming Hiew
 
Design projectone-fullbrief-150210111409-conversion-gate01 (1)
Design projectone-fullbrief-150210111409-conversion-gate01 (1)Design projectone-fullbrief-150210111409-conversion-gate01 (1)
Design projectone-fullbrief-150210111409-conversion-gate01 (1)Liming Hiew
 
Design projectone-fullbrief-150210111409-conversion-gate01
Design projectone-fullbrief-150210111409-conversion-gate01Design projectone-fullbrief-150210111409-conversion-gate01
Design projectone-fullbrief-150210111409-conversion-gate01Liming Hiew
 
Psycho final-write-up
Psycho final-write-upPsycho final-write-up
Psycho final-write-upLiming Hiew
 
Assignment 3-final-project-and-group-presentation
Assignment 3-final-project-and-group-presentationAssignment 3-final-project-and-group-presentation
Assignment 3-final-project-and-group-presentationLiming Hiew
 
Assignment 2-comic-strip
Assignment 2-comic-stripAssignment 2-comic-strip
Assignment 2-comic-stripLiming Hiew
 
Assignment 1 individual journal
Assignment 1   individual journalAssignment 1   individual journal
Assignment 1 individual journalLiming Hiew
 
Titiwangsa lake garden
Titiwangsa lake gardenTitiwangsa lake garden
Titiwangsa lake gardenLiming Hiew
 
Oral presentation individual (b)
Oral presentation individual (b)Oral presentation individual (b)
Oral presentation individual (b)Liming Hiew
 

More from Liming Hiew (20)

M2 project assignment aug 2015
M2 project assignment aug 2015M2 project assignment aug 2015
M2 project assignment aug 2015
 
Construction technology report
Construction technology reportConstruction technology report
Construction technology report
 
Assignment brief for site report
Assignment brief for site report Assignment brief for site report
Assignment brief for site report
 
Coffee table book
Coffee table bookCoffee table book
Coffee table book
 
Cn c brief2_ctb_201514sept
Cn c brief2_ctb_201514septCn c brief2_ctb_201514sept
Cn c brief2_ctb_201514sept
 
Cn c brief2_092014sept
Cn c brief2_092014septCn c brief2_092014sept
Cn c brief2_092014sept
 
Project 1 0214brief with tgc
Project 1 0214brief with tgcProject 1 0214brief with tgc
Project 1 0214brief with tgc
 
bBrief 2 b
bBrief 2 bbBrief 2 b
bBrief 2 b
 
Design p2 a april
Design p2 a aprilDesign p2 a april
Design p2 a april
 
Design projectone-fullbrief-150210111409-conversion-gate01 (1)
Design projectone-fullbrief-150210111409-conversion-gate01 (1)Design projectone-fullbrief-150210111409-conversion-gate01 (1)
Design projectone-fullbrief-150210111409-conversion-gate01 (1)
 
Design projectone-fullbrief-150210111409-conversion-gate01
Design projectone-fullbrief-150210111409-conversion-gate01Design projectone-fullbrief-150210111409-conversion-gate01
Design projectone-fullbrief-150210111409-conversion-gate01
 
Psycho final-write-up
Psycho final-write-upPsycho final-write-up
Psycho final-write-up
 
Assignment 3-final-project-and-group-presentation
Assignment 3-final-project-and-group-presentationAssignment 3-final-project-and-group-presentation
Assignment 3-final-project-and-group-presentation
 
Assignment 2-comic-strip
Assignment 2-comic-stripAssignment 2-comic-strip
Assignment 2-comic-strip
 
Journal 2
Journal 2Journal 2
Journal 2
 
Psychology
PsychologyPsychology
Psychology
 
Assignment 1 individual journal
Assignment 1   individual journalAssignment 1   individual journal
Assignment 1 individual journal
 
Titiwangsa lake garden
Titiwangsa lake gardenTitiwangsa lake garden
Titiwangsa lake garden
 
Oral presentation individual (b)
Oral presentation individual (b)Oral presentation individual (b)
Oral presentation individual (b)
 
Epc part 1
Epc part 1Epc part 1
Epc part 1
 

Recently uploaded

mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting DataJhengPantaleon
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfUmakantAnnand
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesFatimaKhan178732
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxRoyAbrique
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppCeline George
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 

Recently uploaded (20)

mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.Compdf
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and Actinides
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website App
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 

Site visit report

  • 1. INTRODUCTION In this assignment, we are required to write a site visit report, which is, organized on the 26th of June 2015 by our Measurement I lecturer Ms Ang Fuey Lin. This assignment is involved in three modules, which are Measurement I, Construction Technology I and building Materials. Before that, every one of us should prepare a safety helmet to ensure our safety. During that day, we are gathered at Taylor’s University at around 9am. It takes around 20 minutes to the site, which is located at BukitJalil. When we arrived at the site, the project manager gave us a 15 minutes briefing of the site about the project which is cost roughly RM21.5 million. Besides, this is the biggest pilecap that they had ever made which is 24BP1200A. After that, the project manager gave us another short briefing about the safety precautions we have to take while walking around at the site. We also need to be very careful on our own safety and ensure that we do not slip and fall which can lead to a lot of problems. When the briefing is completed, we are divided into three groups, each group consist of 9 to 10 people. Then, we follow the person who in charge of us and finally given the tour on the site.
  • 2. Type of foundation used for the site The typeof foundation, whichis used in this projectis pile foundation. A pilefoundation isa long slender foundation, itis made by either timber , structuralsteel or concrete which might be cast-in- situ or driven and acts as a structural member to transfer the load of the structureto a required depthin deep foundationscarryingaload which may be vertical or lateral or lateral plusvertical. The gradeof concrete used for the column is grade 45, for beam is grade 35. Moreover, the concrete gradefor slab is grade35 and for the foundation itis grade30.
  • 3. These are the advantagesand disadvantagesfor pile foundation: Advantages Disadvantages The size, length and shape can be madein advanced and used at the site. Advance planning is required for handling and driving. The work is neat and clean. Required heavy equipment for handling and driving. High individual load capacity. May suffer unseen damage, which reduces carrying capacity. Can be driven in very long length. May break during driving necessitating replacement piles. Advantagesand disadvantagesof reinforced concrete: Advantages Disadvantages The reinforced concrete building system is moredurable than any other building system. The tensile strength of reinforced concrete is about one tenth of its compressive strength. The maintenance cost of reinforced concrete is very low The cost of the forms used for the casting reinforced concrete is relatively higher. Compared to the use of steel in structure, reinforcesconcrete requires less killed labor for the erection of structure. Shrinkage causes crack development and strength loss Fire and weather resistance of reinforced concrete is fair. It needs mixing, casting, and curing, all of which affect the final strength of concrete.
  • 4. PHOTOS AND DESCRIPTION Temporary Work This is a temporary place, which is provided to the workers of there to relax and take a break. A temporary work for the drainage system since there is a lot of ground water and rainwater, which has to be removed.
  • 5. Plants and tools used: This is a bar bending machine which is used to bend the reinforcement bars into ant shapes and angles. This is more convenient for the worker. The blue machine is a welding generator, which provides current electrical to perform welding. Excavators are also used on the site that is used for earth digging and loading the excavated materials into the loading trucks to either for disposal or used later.
  • 6. Construction Work: This is acted as a balancing tool for the formwork that can help to make it straight. The pile cap of the building is found on the site. The worker is tear apart the formwork after the concrete is dried over one night.
  • 7. The links and the reinforced concrete is found in the site. The grade of the bars is Grade 500. It is 12M long. This is a concrete cover which is 35mm thick which has already placed at the reinforcement bars for column. This is the column stump of the foundation.
  • 8. The links were tied to the reinforcement bars of the column. The workers were making concrete covers. The formwork is done which is ready for concrete to pour inside it.
  • 9. We found reinforcement bars, which are inside the walls.
  • 10. CONCLUSION After this site visit, I had gained a lot of new experience and knowledge, which I cannot get from the books. I realized that going to the site is muchmore differentthan just learningthe theory from the books. Besides, after visiting the site, I truly understand thesituation of the site visit includingthe scorching of sun and the dustin the site. I also gained knowledgeaboutthe process of construction process, the way of usingmachinery equipmentand can differentiatethe typesof the buildingmaterials used in the construction. As a conclusion, I really learn a lot and gained a lot for my future which preparemeto overcomemany upcomingproblem throughout the coursefrom this site visiting.
  • 11. OBJECTIVES  Understand the basic of the construction process.  Understand the practical aspect of construction techniques in comparison to the theory aspect in books and its application on site.  Exposure to actual working environment on site including uncertainty circumstancee.g. weather.  Ability to communicate with the construction team members on site and to see the importanceof teamwork in the buildingteam.  Witness the usage of construction equipment on site including mechanical plants.  Explore and identify various types of building materials and technology on site.  Awareness of the importance of safety on site and understanding of safety problemsand site conditions.  Recognize the items measureable for sub-structure and reinforced concrete frameworks.