SCHOOL OF ARCHITECTURE, BUILDING AND DESIGN
Bachelor of Quantity Surveying (Honours)
INTEGRATED ASSIGNMENT:
MEASUREMENT I (QSB60104)
CONSTRUCTION TECHNOLOGY I (BLD 60104)
BUILDING MATERIALS (BLD 62003)
SITE VISIT REPORT
STUDENT NAME: LAM WEE WEE
STUDENT ID NO.: 0320129
DATE OF SUBMISSION: 27 NOVEMBER 2015
In this assignment, we are require to summit a report based on what we have studied
during our site visit at Sekyen A2, Antara Gapi, Hulu Selangor, Selangor. This site visit is
to enable us to have the chance of elaborating the method and process of construction on
site. The task which are given to us is mainly require us to be able to elaborate on Pad
Footing such as how it is constructed and the materials involved in constructing it.
Site clearance before constructing.
The first of constructing process is setting out. The positions of the pad footing are
set out according to the plan dimensions. To mark out the size of the pad footing is going
to be, they would use cement powder. After that comes the very first step of constructing
a pad footing. First, is excavation. They excavate the earth to the required depth by using
an excavator.
Excavator used to excavate until it obtains the required depth and plan dimensions.
Next, hardcore is placed on top of the surface of the excavated earth. The hardcore are used
in a layer of at least a 150mm thick but no greater than 600mm in selected aggregate. After that,
it is then compacted down in layers with a plate compactor. Formwork is then placed according to
the plan dimensions which they have to build themselves. For the formwork, they used traditional
formwork which are temporary and have to be removed after it is done. The material used for the
formwork mainly consist of timber and plywood. They had to read the plan for any adjustments
and then adjusting it to fit the size and position of the formwork. After that, they added stud to
prevent the falling of the formwork. Bracing and pegs are used to ensure that the formwork would
be strong enough to withstand the horizontal forces of the concrete when it is poured.
A layer of lean concrete is then poured and leveled. It helps to provide an even surface tot he
foundation concrete. Besides that, it also helps to prevent direct contact of foundation concrete
with the soil.
Next would be the rebar work. The reinforcement is placed on top of the concrete
spacers whereas the spacers are used to maintain the reinforcement in the proper position.
It also helps prevent rebars from corrosion. Protecting them from fire for a certain amount
of time, helps to provide proper transfer of stresses from concrete to steel rebars.
Even thought concrete is durable, and has a very good compression of strength, it has
a weak tension strength. This is why reinforcement is used as it will carry tensile load of
a structure. Starter bar is then placed after placing down the reinforcement. The starter bar
is tied to the reinforcement so that the reinforcement of the column can be tied to it. They
have to make sure that the position of the starter bars are correct.
Ground beam rebar
Stirrup tying the rebars together.
The final step is concreting. Concrete are poured into the formwork and adequate
compaction is ensured by using either vibrators or self-compacting concrete. The concrete
will then be allowed to be cured before proceeding to the next stage of the construction.
The concrete will then set to dry until it gains sufficient strength. The formwork will then
be dismantled which will lead to a complete pad footing.
Overall view.
A closer view of the formwork of the pad footing.
Starter bars
Cement and sand setting aside. Soon to be
concrete.
Construction Joint
Retaining Wall
Diagram showed to us of pad footing.
Giving us information of pad footing.
Staircase formwork
Scaffolding
Piles
Throughout this assignment, I learned that in construction site you have to ask
question in order to obtain more valuable information as it might not be the same as you
are studying in school. Further information such as the type of materials that they used.
For example, rebar Y20, Y16 for their reinforcement, 1by2 timber and plywood of 12mm
thick for their formwork. I also learn that there are different types of housing area such as
Type 2A. Type 2A basically means that it is above ground level. Depending on the SI of
the soil, they will either use pile cap or pad footing. The SI of the soil are calculated by
the engineer which will then be conclude whether that specific area is suitable to use pile
cap or pad footing.
individual site report sem 1 degree

More Related Content

What's hot

Ms ct-bm
Ms ct-bmMs ct-bm
Ms ct-bmLin Hui
 
Ct & bm & mea assignment brickwall report
Ct & bm & mea assignment brickwall reportCt & bm & mea assignment brickwall report
Ct & bm & mea assignment brickwall reportSheng Zhe
 
Types of masonry and its failure types
Types of masonry and its failure typesTypes of masonry and its failure types
Types of masonry and its failure typesUdayram Patil
 
Snecked rubble step by step
Snecked rubble step by stepSnecked rubble step by step
Snecked rubble step by stepdoogstone
 
A collection of articles on concrete formwork design and construction
A collection of articles on concrete formwork design and constructionA collection of articles on concrete formwork design and construction
A collection of articles on concrete formwork design and constructionByron Smith
 
Site visit report 2017
Site visit report 2017Site visit report 2017
Site visit report 2017bee_by
 
Tutor brickwork below ground level
Tutor brickwork below ground level Tutor brickwork below ground level
Tutor brickwork below ground level Luke D'Arcy
 
Site visit report
Site visit reportSite visit report
Site visit reportshensin1015
 
Brick Construction techniques
Brick Construction techniques Brick Construction techniques
Brick Construction techniques Mohamed Faseehun
 
Fixing to plasterboard and plasterboard fixings
Fixing to plasterboard and plasterboard fixingsFixing to plasterboard and plasterboard fixings
Fixing to plasterboard and plasterboard fixingsPraveen Sudarsan
 
Dr. Subash.T- Module-1_Construction materials
Dr. Subash.T- Module-1_Construction materialsDr. Subash.T- Module-1_Construction materials
Dr. Subash.T- Module-1_Construction materialsDrSubashThanappan
 
Site-Report (1).docx
Site-Report (1).docxSite-Report (1).docx
Site-Report (1).docxShze Hwa Lee
 
Murphy's Masonry - Masonry Service in Toronto
Murphy's Masonry - Masonry Service in TorontoMurphy's Masonry - Masonry Service in Toronto
Murphy's Masonry - Masonry Service in Torontomurphysmasonry
 
Cam flick group
Cam flick groupCam flick group
Cam flick groupRothna sou
 

What's hot (19)

Ms ct-bm
Ms ct-bmMs ct-bm
Ms ct-bm
 
Ct & bm & mea assignment brickwall report
Ct & bm & mea assignment brickwall reportCt & bm & mea assignment brickwall report
Ct & bm & mea assignment brickwall report
 
Brick Masonry Fall 09
Brick Masonry Fall 09Brick Masonry Fall 09
Brick Masonry Fall 09
 
Types of masonry and its failure types
Types of masonry and its failure typesTypes of masonry and its failure types
Types of masonry and its failure types
 
Site Report
Site Report Site Report
Site Report
 
Snecked rubble step by step
Snecked rubble step by stepSnecked rubble step by step
Snecked rubble step by step
 
A collection of articles on concrete formwork design and construction
A collection of articles on concrete formwork design and constructionA collection of articles on concrete formwork design and construction
A collection of articles on concrete formwork design and construction
 
Site visit report 2017
Site visit report 2017Site visit report 2017
Site visit report 2017
 
Brick Bonds
Brick BondsBrick Bonds
Brick Bonds
 
Tutor brickwork below ground level
Tutor brickwork below ground level Tutor brickwork below ground level
Tutor brickwork below ground level
 
Site visit report
Site visit reportSite visit report
Site visit report
 
Brick Construction techniques
Brick Construction techniques Brick Construction techniques
Brick Construction techniques
 
Fundamentals walls
Fundamentals wallsFundamentals walls
Fundamentals walls
 
Fixing to plasterboard and plasterboard fixings
Fixing to plasterboard and plasterboard fixingsFixing to plasterboard and plasterboard fixings
Fixing to plasterboard and plasterboard fixings
 
Dr. Subash.T- Module-1_Construction materials
Dr. Subash.T- Module-1_Construction materialsDr. Subash.T- Module-1_Construction materials
Dr. Subash.T- Module-1_Construction materials
 
Site-Report (1).docx
Site-Report (1).docxSite-Report (1).docx
Site-Report (1).docx
 
Murphy's Masonry - Masonry Service in Toronto
Murphy's Masonry - Masonry Service in TorontoMurphy's Masonry - Masonry Service in Toronto
Murphy's Masonry - Masonry Service in Toronto
 
Cam flick group
Cam flick groupCam flick group
Cam flick group
 
Site report
Site reportSite report
Site report
 

Viewers also liked

Industrial_Brochure_Template_3
Industrial_Brochure_Template_3Industrial_Brochure_Template_3
Industrial_Brochure_Template_3Adam Pestka
 
Programmaboekje MWF 2014
Programmaboekje MWF 2014Programmaboekje MWF 2014
Programmaboekje MWF 2014Esther Hagen
 
Reportct1bmm1
Reportct1bmm1Reportct1bmm1
Reportct1bmm1Lam Wee
 
Alytics - Александр Егоров - Минусы и плюсы автоматизации контекстной рекламы
Alytics - Александр Егоров - Минусы и плюсы автоматизации контекстной рекламыAlytics - Александр Егоров - Минусы и плюсы автоматизации контекстной рекламы
Alytics - Александр Егоров - Минусы и плюсы автоматизации контекстной рекламыAlytics
 
English II assignment II report
English II assignment II reportEnglish II assignment II report
English II assignment II reportLam Wee
 
bs1 slide
bs1 slidebs1 slide
bs1 slideLam Wee
 
Industrial_Brochure_Template_8
Industrial_Brochure_Template_8Industrial_Brochure_Template_8
Industrial_Brochure_Template_8Adam Pestka
 
English II assignment II
English II assignment IIEnglish II assignment II
English II assignment IILam Wee
 

Viewers also liked (15)

Industrial_Brochure_Template_3
Industrial_Brochure_Template_3Industrial_Brochure_Template_3
Industrial_Brochure_Template_3
 
Programmaboekje MWF 2014
Programmaboekje MWF 2014Programmaboekje MWF 2014
Programmaboekje MWF 2014
 
Antenas transmisoras
Antenas transmisorasAntenas transmisoras
Antenas transmisoras
 
Reportct1bmm1
Reportct1bmm1Reportct1bmm1
Reportct1bmm1
 
Grow_Adapt_or_Perish
Grow_Adapt_or_PerishGrow_Adapt_or_Perish
Grow_Adapt_or_Perish
 
Unit 1
Unit 1Unit 1
Unit 1
 
English
EnglishEnglish
English
 
Pieza
PiezaPieza
Pieza
 
History assignment help
History assignment helpHistory assignment help
History assignment help
 
Alytics - Александр Егоров - Минусы и плюсы автоматизации контекстной рекламы
Alytics - Александр Егоров - Минусы и плюсы автоматизации контекстной рекламыAlytics - Александр Егоров - Минусы и плюсы автоматизации контекстной рекламы
Alytics - Александр Егоров - Минусы и плюсы автоматизации контекстной рекламы
 
English II assignment II report
English II assignment II reportEnglish II assignment II report
English II assignment II report
 
Physics Assignment Help
Physics Assignment HelpPhysics Assignment Help
Physics Assignment Help
 
bs1 slide
bs1 slidebs1 slide
bs1 slide
 
Industrial_Brochure_Template_8
Industrial_Brochure_Template_8Industrial_Brochure_Template_8
Industrial_Brochure_Template_8
 
English II assignment II
English II assignment IIEnglish II assignment II
English II assignment II
 

Similar to individual site report sem 1 degree

Site Visit Report CT BM M1
Site Visit Report CT BM M1Site Visit Report CT BM M1
Site Visit Report CT BM M1Zi Shan
 
Site visit report
Site visit reportSite visit report
Site visit reportJordon Wong
 
Site visit-report-nov2015
Site visit-report-nov2015Site visit-report-nov2015
Site visit-report-nov2015Joyce HweeMin
 
Integrated assignment site report
Integrated assignment site reportIntegrated assignment site report
Integrated assignment site reportw ss
 
Assignment of Site Report
Assignment of Site Report Assignment of Site Report
Assignment of Site Report I'mMiss Lily
 
SITE REPORT (PAD FOOTING)
SITE REPORT (PAD FOOTING)SITE REPORT (PAD FOOTING)
SITE REPORT (PAD FOOTING)I'mMiss Lily
 
Site report
Site reportSite report
Site reportHuiYik
 
Site visit report
Site visit reportSite visit report
Site visit reportDoreen Yeo
 
SITE VISIT REPORT
SITE VISIT REPORTSITE VISIT REPORT
SITE VISIT REPORTWan Nee
 
Integrated Assignment : Measurement & CT & BM
Integrated Assignment : Measurement & CT & BMIntegrated Assignment : Measurement & CT & BM
Integrated Assignment : Measurement & CT & BMJaey Chai
 
Technical site visit report
Technical site visit reportTechnical site visit report
Technical site visit reportMomo Poyi
 
Construction of Brick Wall
Construction of Brick WallConstruction of Brick Wall
Construction of Brick WallI'mMiss Lily
 

Similar to individual site report sem 1 degree (20)

Site visit report
Site visit reportSite visit report
Site visit report
 
Site Report
Site ReportSite Report
Site Report
 
Site Visit Report CT BM M1
Site Visit Report CT BM M1Site Visit Report CT BM M1
Site Visit Report CT BM M1
 
Site visit report
Site visit reportSite visit report
Site visit report
 
Site visit-report-nov2015
Site visit-report-nov2015Site visit-report-nov2015
Site visit-report-nov2015
 
Integrated assignment site report
Integrated assignment site reportIntegrated assignment site report
Integrated assignment site report
 
Assignment of Site Report
Assignment of Site Report Assignment of Site Report
Assignment of Site Report
 
SITE REPORT (PAD FOOTING)
SITE REPORT (PAD FOOTING)SITE REPORT (PAD FOOTING)
SITE REPORT (PAD FOOTING)
 
Suraj presentation.pptx
Suraj presentation.pptxSuraj presentation.pptx
Suraj presentation.pptx
 
Shinchan presentation.pptx
Shinchan presentation.pptxShinchan presentation.pptx
Shinchan presentation.pptx
 
Site report
Site reportSite report
Site report
 
Site visit report
Site visit reportSite visit report
Site visit report
 
Site visit report
Site visit reportSite visit report
Site visit report
 
SITE VISIT REPORT
SITE VISIT REPORTSITE VISIT REPORT
SITE VISIT REPORT
 
site report
site reportsite report
site report
 
Site report 1
Site report 1Site report 1
Site report 1
 
Site report
Site reportSite report
Site report
 
Integrated Assignment : Measurement & CT & BM
Integrated Assignment : Measurement & CT & BMIntegrated Assignment : Measurement & CT & BM
Integrated Assignment : Measurement & CT & BM
 
Technical site visit report
Technical site visit reportTechnical site visit report
Technical site visit report
 
Construction of Brick Wall
Construction of Brick WallConstruction of Brick Wall
Construction of Brick Wall
 

More from Lam Wee

Individual assignment brief ct2-2016
Individual assignment brief ct2-2016Individual assignment brief ct2-2016
Individual assignment brief ct2-2016Lam Wee
 
Individual assignment brief ct2-2014
Individual assignment brief ct2-2014Individual assignment brief ct2-2014
Individual assignment brief ct2-2014Lam Wee
 
Integrated assignment m1 ct1 and bm mac 2016
Integrated assignment m1 ct1 and bm mac 2016Integrated assignment m1 ct1 and bm mac 2016
Integrated assignment m1 ct1 and bm mac 2016Lam Wee
 
Assignment no.2 brief m1 sem1 degree
Assignment no.2  brief m1 sem1 degreeAssignment no.2  brief m1 sem1 degree
Assignment no.2 brief m1 sem1 degreeLam Wee
 
Integrated assignment m1 ct1 and bm aug2015
Integrated assignment m1 ct1 and bm aug2015Integrated assignment m1 ct1 and bm aug2015
Integrated assignment m1 ct1 and bm aug2015Lam Wee
 
Accounting
AccountingAccounting
AccountingLam Wee
 
Business assignment-secrect-roses
Business assignment-secrect-rosesBusiness assignment-secrect-roses
Business assignment-secrect-rosesLam Wee
 
Video report
Video reportVideo report
Video reportLam Wee
 
Video presentation
Video presentationVideo presentation
Video presentationLam Wee
 
Comic presentation
Comic presentationComic presentation
Comic presentationLam Wee
 
S.psychology
S.psychologyS.psychology
S.psychologyLam Wee
 
English II essay assignment I
English II essay assignment IEnglish II essay assignment I
English II essay assignment ILam Wee
 

More from Lam Wee (12)

Individual assignment brief ct2-2016
Individual assignment brief ct2-2016Individual assignment brief ct2-2016
Individual assignment brief ct2-2016
 
Individual assignment brief ct2-2014
Individual assignment brief ct2-2014Individual assignment brief ct2-2014
Individual assignment brief ct2-2014
 
Integrated assignment m1 ct1 and bm mac 2016
Integrated assignment m1 ct1 and bm mac 2016Integrated assignment m1 ct1 and bm mac 2016
Integrated assignment m1 ct1 and bm mac 2016
 
Assignment no.2 brief m1 sem1 degree
Assignment no.2  brief m1 sem1 degreeAssignment no.2  brief m1 sem1 degree
Assignment no.2 brief m1 sem1 degree
 
Integrated assignment m1 ct1 and bm aug2015
Integrated assignment m1 ct1 and bm aug2015Integrated assignment m1 ct1 and bm aug2015
Integrated assignment m1 ct1 and bm aug2015
 
Accounting
AccountingAccounting
Accounting
 
Business assignment-secrect-roses
Business assignment-secrect-rosesBusiness assignment-secrect-roses
Business assignment-secrect-roses
 
Video report
Video reportVideo report
Video report
 
Video presentation
Video presentationVideo presentation
Video presentation
 
Comic presentation
Comic presentationComic presentation
Comic presentation
 
S.psychology
S.psychologyS.psychology
S.psychology
 
English II essay assignment I
English II essay assignment IEnglish II essay assignment I
English II essay assignment I
 

Recently uploaded

Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphThiyagu K
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Celine George
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxRoyAbrique
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppCeline George
 
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991RKavithamani
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactPECB
 

Recently uploaded (20)

Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
Staff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSDStaff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSD
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website App
 
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 

individual site report sem 1 degree

  • 1. SCHOOL OF ARCHITECTURE, BUILDING AND DESIGN Bachelor of Quantity Surveying (Honours) INTEGRATED ASSIGNMENT: MEASUREMENT I (QSB60104) CONSTRUCTION TECHNOLOGY I (BLD 60104) BUILDING MATERIALS (BLD 62003) SITE VISIT REPORT STUDENT NAME: LAM WEE WEE STUDENT ID NO.: 0320129 DATE OF SUBMISSION: 27 NOVEMBER 2015 In this assignment, we are require to summit a report based on what we have studied during our site visit at Sekyen A2, Antara Gapi, Hulu Selangor, Selangor. This site visit is to enable us to have the chance of elaborating the method and process of construction on site. The task which are given to us is mainly require us to be able to elaborate on Pad Footing such as how it is constructed and the materials involved in constructing it.
  • 2. Site clearance before constructing. The first of constructing process is setting out. The positions of the pad footing are set out according to the plan dimensions. To mark out the size of the pad footing is going to be, they would use cement powder. After that comes the very first step of constructing a pad footing. First, is excavation. They excavate the earth to the required depth by using an excavator.
  • 3. Excavator used to excavate until it obtains the required depth and plan dimensions. Next, hardcore is placed on top of the surface of the excavated earth. The hardcore are used in a layer of at least a 150mm thick but no greater than 600mm in selected aggregate. After that, it is then compacted down in layers with a plate compactor. Formwork is then placed according to the plan dimensions which they have to build themselves. For the formwork, they used traditional formwork which are temporary and have to be removed after it is done. The material used for the formwork mainly consist of timber and plywood. They had to read the plan for any adjustments and then adjusting it to fit the size and position of the formwork. After that, they added stud to prevent the falling of the formwork. Bracing and pegs are used to ensure that the formwork would be strong enough to withstand the horizontal forces of the concrete when it is poured. A layer of lean concrete is then poured and leveled. It helps to provide an even surface tot he foundation concrete. Besides that, it also helps to prevent direct contact of foundation concrete with the soil. Next would be the rebar work. The reinforcement is placed on top of the concrete spacers whereas the spacers are used to maintain the reinforcement in the proper position. It also helps prevent rebars from corrosion. Protecting them from fire for a certain amount of time, helps to provide proper transfer of stresses from concrete to steel rebars.
  • 4. Even thought concrete is durable, and has a very good compression of strength, it has a weak tension strength. This is why reinforcement is used as it will carry tensile load of a structure. Starter bar is then placed after placing down the reinforcement. The starter bar is tied to the reinforcement so that the reinforcement of the column can be tied to it. They have to make sure that the position of the starter bars are correct. Ground beam rebar
  • 5. Stirrup tying the rebars together. The final step is concreting. Concrete are poured into the formwork and adequate compaction is ensured by using either vibrators or self-compacting concrete. The concrete will then be allowed to be cured before proceeding to the next stage of the construction. The concrete will then set to dry until it gains sufficient strength. The formwork will then be dismantled which will lead to a complete pad footing. Overall view.
  • 6. A closer view of the formwork of the pad footing. Starter bars Cement and sand setting aside. Soon to be concrete.
  • 8. Diagram showed to us of pad footing. Giving us information of pad footing.
  • 10. Scaffolding Piles Throughout this assignment, I learned that in construction site you have to ask question in order to obtain more valuable information as it might not be the same as you are studying in school. Further information such as the type of materials that they used. For example, rebar Y20, Y16 for their reinforcement, 1by2 timber and plywood of 12mm thick for their formwork. I also learn that there are different types of housing area such as Type 2A. Type 2A basically means that it is above ground level. Depending on the SI of the soil, they will either use pile cap or pad footing. The SI of the soil are calculated by the engineer which will then be conclude whether that specific area is suitable to use pile cap or pad footing.