SlideShare a Scribd company logo
SUBSTATIONSUBSTATION
HIGH VOLTAGEHIGH VOLTAGE
COMPONENTSCOMPONENTS
POWER PLANT
SWITCHING STATION
(SWITCHYARD)
SUBSTATION
• SUBSTATION - A station in the power transmission system at
which electric power is transformed to a conveniently used
form. The station may consist of transformers, switches,
circuit breakers and other auxilliary equipment. Its main
function is to receive energy transmitted at high voltage from
the generating station, by either step-up or step-down the
voltage to a value appropriate for local use and provide
facilities for switching. Substations have some additional
functions. Its provide points where safety devices may be
installed to disconnect circuits or equipment in the event of
trouble.
Some substation, such as power plant switchyard are
simply switching stations where different connections can be
made between various transmission lines.
Typical Components of a Power Plant
Substation (Switchyard)
•A - Busbar
•B - Disconnector
•C - Circuit Breaker
•D - Current Transformer
•E - Voltage Transformer
•F - Earthing Switch
•G - Surge Arrestor
• CONNECT
• CONNECT & DIS-CONNECT
• CONNECT, DIS-CONNECT & DETECT
• DETECT & TRANSFORM
• DETECT & TRANSFORM
• PROTECT & SAFETY
• PROTECT
A. BUSBAR
• BUSBAR (or bus, for short) – is a term we use for a main bar
or conductor carrying an electric current to which many
connection may be made.
Buses are merely convenient means of connecting
switches and other equipment into various arrangements.
The usual arrangement of connections in most substations
permit working on almost any piece of equipment without
interruption to incoming or outgoing feeders. In the
switchyard or substation, buses are open to the air.
Aluminum or copper conductors supported on porcelain
insulators, carry the electric energy from point to point.
Busbars
(long heavy
tube type)
B. DISCONNECTS
• DISCONNECT – is an easily removed piece of the actual
conductor of a circuit. The purpose of disconnects is to isolate
equipment. Disconnects are not used to interrupt circuits;
they are no-load devices. A typical use of disconnects is to
isolate a circuit breaker by installing one disconnect on either
side of the circuit breaker (in series with the breaker).
Operation of disconnects is one of the most important and
responsible jobs of a power plant operator. One error in
isolation of equipment, or the accidental grounding of line
equipment, can be a fatal mistake.
A
B
Disconnect Switch
( moving contact rod (A) &
contacts with flexible
fingers (B) )
C. CIRCUIT BREAKER
• CIRCUIT BREAKER – is used to interrupt circuits while current
is flowing through them. The making and breaking of contacts
in a Oil type circuit breaker are done under oil, this oil serves
to quench the arc when the circuit is opened. The operation
of the breaker is very rapid when opening. As with the
transformer, the high voltage connections are made through
bushings. Circuit breakers of this type are usually arranged for
remote electrical control from a suitably located switchboard.
Some recently developed circuit breakers have no oil, but
put out the arc by a blast of compressed air; these are called
air circuit breakers. Another type encloses the contacts in a
vacuum or a gas (sulfur hexafluoride, SF6) which tends to self
maintain the arc.
Circuit Breakers
( Connected in a typical 3-
phase circuit )
Operating
Mechanism
Panel
Position
Indicator
D. CURRENT TRANSFORMER
• CURRENT TRANSFORMER – Current transformer are used
with ammeters, watt meters, power-factor meters, watt-hour
meters,compensators, protective and regulating relays and
the trip coil of circuit breakers. One current transformer can
be used to operate several instruments, provided that the
combined burden does not exceed that for which the
transformer is designed and compensated. The current
transformer is connected directly in series with the line.
E. VOLTAGE TRANSFORMER
• VOLTAGE TRANSFORMER – also know as potential
transformer, are used with volt-meters, wattmeters, watt-
hour meters, power-factor meters, frequency meters,
synchroscopes and synchronizing apparatus, protective and
regulating relays and the no-voltage and over-voltage trip
coils of automatic circuit breakers. One transformer can be
used for a number of instruments at the same time if the total
current taken by the instrument does not exceed that for
which the transformer is designed and compensated. The
ordinary voltage transformer is connected across the line, and
the magnetic flux in the core depends upon the primary
voltage
F. EARTHING SWITCH
• EARTHING SWITCH – also known as ground disconnect, which
used to connects the equipment to a grid of electrical
conductors buried in the earth on the station property. It is
intended to protect people working on the grounded
equipment. It does this by completing a circuit path, thereby
reducing the voltage difference between the equipment and
its surroundings. For safety reasons, it is important that
ground disconnects and all associated connections have good
contact and low resistance. It is also important that the
protective ground not be accidentally remove, that is why all
the earthing switches, disconnect switches and circuit
breakers are all interlocked to each other and proper/correct
sequencing must be followed.
G. SURGE ARRESTOR
• SURGE ARRESTOR – are devices used to provide the
necessary path to ground for such surges, yet prevent any
power current from following the surge. An ideal arrester
must therefore have the following properties:
1. Ability to remove the surge energy from the line in a min. time.
2. High resistive to flow of power current.
3. A valve action automatically allowing surge to pass and then
closing up so as not to permit power current to flow to
ground.
4. Always ready to perform.
5. Performance such that no system disturbances are introduced
by its operation.
6. Economically feasible
• OVERHEAD GROUND WIRE – by a ground wire is meant a
wire, generally of steel, supported from the top of
transmission-line towers and solidly grounded at each tower.
It is considered a preventive device, but it does not entirely
prevent the formation of travelling waves on a line.
Furthermore, those lines which are not equipped with ground
wires will be subjected to disturbances which produce surges
that must be allowed to escaped to ground, or the apparatus
connected to the line must be strong enough to reflect or
absorb these surges until they are entirely damped out.
PREVENTIVE MAINTENANCE
• BUSBARS & OVERHEAD GROUND WIRE
At least once a year
 Visual Inspection & Examination of all wiring connectors.
 Check Insulator , clean or apply HVIC if necessary.
 Check the physical condition of bus (cables or bars)
 For ground wire, check or test the grounding system.
• DISCONNECT & EARTHING SWITCHES
At least once a month
 Visual Inspection.
 Check heating resistor located at its control panel for proper functioning.
At least once a year
 Clean contacts of disconnectors as well as earthing switches and apply electrical
contact grease , if necessary.
 Check disconnectors and earthing switches, joints and bearings of the operating
linkages for deformed bearing points.
 Check flexible connections of earthing switches.
 Check all screwed joints for tight fit.
 Clean insulators if necessary, when an excessive amount of dirt has
accumulated.
 Carry-out the maintenance of operating mechanism.
• VOLTAGE TRANSFORMER
At least once a month
 Inspect the voltage divider to be sure that no oil leak or serious accumulation of
soot, dust or salt composite is present.
 Inspect the intermediate voltage transformer and check the minimum
permissible oil level.
At least once a year
 Check all screwed joints & contact for tight fit.
 Clean insulators if necessary, when an excessive amount of dirt has
accumulated.
CURRENT TRANSFORMER
At least once a month
Visual Inspection to check oil level and defects or possible oil leaks.
At least once a year
Check all screwed joints & contact for tight fit.
Clean insulators if necessary, when an excessive amount of dirt has
accumulated.
Check primary and secondary connectors and conduct necessary tightening.
Note: Never open a secondary winding of a CT while on service.
•SURGE ARRESTOR
At least once a year
Visual Inspection & Examination of all wiring connectors.
Check Insulator and metal circular ring, clean or apply HVIC if necessary.
Check the physical condition of bus (cables or bars)
 For ground wire, check or test the grounding system.
Note: Arrestors should never be touched unless completely disconnected from all
live lines and equipment and effectively connected to ground at the line side of
the arrestor.

More Related Content

What's hot

Electrical 132kv substation project .. shakir
Electrical 132kv substation project .. shakirElectrical 132kv substation project .. shakir
Electrical 132kv substation project .. shakir
Sheikh Shakir
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear
johny renoald
 
substation protection basics.ppt
substation protection basics.pptsubstation protection basics.ppt
substation protection basics.ppt
Salim Palayi
 
EE6702 Protection and Switchgear notes R2013
EE6702 Protection and Switchgear notes R2013EE6702 Protection and Switchgear notes R2013
EE6702 Protection and Switchgear notes R2013
Velalar College of Engineering and Technology
 
Report on 220kv substation at Jassure
Report on 220kv substation at JassureReport on 220kv substation at Jassure
Report on 220kv substation at Jassure
Shuvam Pathania
 
Introduction to mv switchgear
Introduction to mv switchgearIntroduction to mv switchgear
Introduction to mv switchgear
Modal Holong Education
 
high voltage circuit breaker
high voltage circuit breakerhigh voltage circuit breaker
high voltage circuit breaker
Hanif Pathan
 
Electrical Grid Substation
Electrical Grid SubstationElectrical Grid Substation
Electrical Grid Substation
Ang Sovann
 
Mcb Breaker
Mcb Breaker Mcb Breaker
Mcb Breaker
nazimtiger
 
relay-distance relay basics
relay-distance relay basicsrelay-distance relay basics
relay-distance relay basics
अनिल कुमावत
 
Relays and its types - complete guide
Relays and its types - complete guideRelays and its types - complete guide
Relays and its types - complete guide
Slides Hub
 
High voltage circuit breakers
High voltage circuit breakersHigh voltage circuit breakers
High voltage circuit breakers
Kabilesh K
 
switchgear and protection by vala kamlesh
switchgear and protection by vala kamleshswitchgear and protection by vala kamlesh
switchgear and protection by vala kamleshKamlesh Vala
 
Switch yard & Protection
Switch yard & ProtectionSwitch yard & Protection
Switch yard & Protection
MANOJ KUMAR MAHARANA
 
2.components in a substation breaker
2.components in a substation   breaker2.components in a substation   breaker
2.components in a substation breaker
ayyadurai SHANMUGAM
 
Electrical SUBSTATION ppt
Electrical SUBSTATION pptElectrical SUBSTATION ppt
Electrical SUBSTATION ppt
TanvirkabirShishir
 
Design of substation (with Transformer Design)
Design of substation (with Transformer Design) Design of substation (with Transformer Design)
Design of substation (with Transformer Design)
SayanSarkar55
 
Power System Protection basics
Power System Protection basicsPower System Protection basics
Power System Protection basics
Rajan Singh Tanwar
 
2015 Arc Flash Conference MV Switchgear Standards
2015 Arc Flash Conference MV Switchgear Standards2015 Arc Flash Conference MV Switchgear Standards
2015 Arc Flash Conference MV Switchgear Standards
Bryan Johnson
 
Power system protection devices
Power system protection devicesPower system protection devices
Power system protection devices
Prakash_13209
 

What's hot (20)

Electrical 132kv substation project .. shakir
Electrical 132kv substation project .. shakirElectrical 132kv substation project .. shakir
Electrical 132kv substation project .. shakir
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear
 
substation protection basics.ppt
substation protection basics.pptsubstation protection basics.ppt
substation protection basics.ppt
 
EE6702 Protection and Switchgear notes R2013
EE6702 Protection and Switchgear notes R2013EE6702 Protection and Switchgear notes R2013
EE6702 Protection and Switchgear notes R2013
 
Report on 220kv substation at Jassure
Report on 220kv substation at JassureReport on 220kv substation at Jassure
Report on 220kv substation at Jassure
 
Introduction to mv switchgear
Introduction to mv switchgearIntroduction to mv switchgear
Introduction to mv switchgear
 
high voltage circuit breaker
high voltage circuit breakerhigh voltage circuit breaker
high voltage circuit breaker
 
Electrical Grid Substation
Electrical Grid SubstationElectrical Grid Substation
Electrical Grid Substation
 
Mcb Breaker
Mcb Breaker Mcb Breaker
Mcb Breaker
 
relay-distance relay basics
relay-distance relay basicsrelay-distance relay basics
relay-distance relay basics
 
Relays and its types - complete guide
Relays and its types - complete guideRelays and its types - complete guide
Relays and its types - complete guide
 
High voltage circuit breakers
High voltage circuit breakersHigh voltage circuit breakers
High voltage circuit breakers
 
switchgear and protection by vala kamlesh
switchgear and protection by vala kamleshswitchgear and protection by vala kamlesh
switchgear and protection by vala kamlesh
 
Switch yard & Protection
Switch yard & ProtectionSwitch yard & Protection
Switch yard & Protection
 
2.components in a substation breaker
2.components in a substation   breaker2.components in a substation   breaker
2.components in a substation breaker
 
Electrical SUBSTATION ppt
Electrical SUBSTATION pptElectrical SUBSTATION ppt
Electrical SUBSTATION ppt
 
Design of substation (with Transformer Design)
Design of substation (with Transformer Design) Design of substation (with Transformer Design)
Design of substation (with Transformer Design)
 
Power System Protection basics
Power System Protection basicsPower System Protection basics
Power System Protection basics
 
2015 Arc Flash Conference MV Switchgear Standards
2015 Arc Flash Conference MV Switchgear Standards2015 Arc Flash Conference MV Switchgear Standards
2015 Arc Flash Conference MV Switchgear Standards
 
Power system protection devices
Power system protection devicesPower system protection devices
Power system protection devices
 

Viewers also liked

Substation overview
Substation overviewSubstation overview
Substation overview
BHAGWAN PRASAD
 
Substation
SubstationSubstation
SUBSTATION OVERVIEW - A presentation on substation
SUBSTATION OVERVIEW - A presentation on substationSUBSTATION OVERVIEW - A presentation on substation
SUBSTATION OVERVIEW - A presentation on substation
raiamitesh8
 
Substation Training presentation
Substation Training presentationSubstation Training presentation
Substation Training presentation
Kamal Mittal
 
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMSSWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMSPartha Parida
 
Types Of Substations
Types Of SubstationsTypes Of Substations
Types Of Substations
sapna186
 
Typical layout of a Sub-Station
Typical layout of a Sub-StationTypical layout of a Sub-Station
Typical layout of a Sub-StationTowfiqur Rahman
 
ESI Electro Service India - Float Cum Battery Charger
ESI Electro Service India - Float Cum Battery ChargerESI Electro Service India - Float Cum Battery Charger
ESI Electro Service India - Float Cum Battery Charger
Radhika Goyal
 
PhD Admission for the Semester April 2010
PhD Admission for the Semester  April 2010PhD Admission for the Semester  April 2010
PhD Admission for the Semester April 2010Mamunur Rashid Center
 
Switchyards (outdoor substations), part 1
Switchyards (outdoor substations), part 1Switchyards (outdoor substations), part 1
Switchyards (outdoor substations), part 1
H. Kheir
 
Testing and Condition Monitoring of Substation Equipments
Testing and Condition Monitoring of Substation EquipmentsTesting and Condition Monitoring of Substation Equipments
Testing and Condition Monitoring of Substation Equipments
Sumeet Ratnawat
 
Ashwani kumar
Ashwani kumarAshwani kumar
Ashwani kumar
Ashwani Kumar
 
Energypac Engineering New Corporate Presentation
Energypac Engineering New Corporate PresentationEnergypac Engineering New Corporate Presentation
Energypac Engineering New Corporate Presentation
sample_m2000
 
Improving substation reliability & availability
Improving substation reliability & availability Improving substation reliability & availability
Improving substation reliability & availability
Vincent Wedelich, PE MBA
 
High voltage transmission
High voltage transmissionHigh voltage transmission
High voltage transmission
SHIVLAL MOHAL
 
2010 11 18 Substation Automation Systems By Gin Quesada
2010 11 18  Substation Automation Systems By Gin Quesada2010 11 18  Substation Automation Systems By Gin Quesada
2010 11 18 Substation Automation Systems By Gin Quesadaginquesada
 
Tl pre-foundation
Tl pre-foundationTl pre-foundation
Tl pre-foundation
Nitesh Sinha
 
Vocational trainning presentation at ESSAR Power Salaya (Electrical Engineering)
Vocational trainning presentation at ESSAR Power Salaya (Electrical Engineering)Vocational trainning presentation at ESSAR Power Salaya (Electrical Engineering)
Vocational trainning presentation at ESSAR Power Salaya (Electrical Engineering)
Lakhan Vadher
 

Viewers also liked (20)

Substation overview
Substation overviewSubstation overview
Substation overview
 
Substation
SubstationSubstation
Substation
 
SUBSTATION OVERVIEW - A presentation on substation
SUBSTATION OVERVIEW - A presentation on substationSUBSTATION OVERVIEW - A presentation on substation
SUBSTATION OVERVIEW - A presentation on substation
 
Substation Training presentation
Substation Training presentationSubstation Training presentation
Substation Training presentation
 
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMSSWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
 
Types Of Substations
Types Of SubstationsTypes Of Substations
Types Of Substations
 
Typical layout of a Sub-Station
Typical layout of a Sub-StationTypical layout of a Sub-Station
Typical layout of a Sub-Station
 
ESI Electro Service India - Float Cum Battery Charger
ESI Electro Service India - Float Cum Battery ChargerESI Electro Service India - Float Cum Battery Charger
ESI Electro Service India - Float Cum Battery Charger
 
PhD Admission for the Semester April 2010
PhD Admission for the Semester  April 2010PhD Admission for the Semester  April 2010
PhD Admission for the Semester April 2010
 
Switchyards (outdoor substations), part 1
Switchyards (outdoor substations), part 1Switchyards (outdoor substations), part 1
Switchyards (outdoor substations), part 1
 
Company Profile
Company ProfileCompany Profile
Company Profile
 
Testing and Condition Monitoring of Substation Equipments
Testing and Condition Monitoring of Substation EquipmentsTesting and Condition Monitoring of Substation Equipments
Testing and Condition Monitoring of Substation Equipments
 
Ashwani kumar
Ashwani kumarAshwani kumar
Ashwani kumar
 
Energypac Engineering New Corporate Presentation
Energypac Engineering New Corporate PresentationEnergypac Engineering New Corporate Presentation
Energypac Engineering New Corporate Presentation
 
Improving substation reliability & availability
Improving substation reliability & availability Improving substation reliability & availability
Improving substation reliability & availability
 
High voltage transmission
High voltage transmissionHigh voltage transmission
High voltage transmission
 
2010 11 18 Substation Automation Systems By Gin Quesada
2010 11 18  Substation Automation Systems By Gin Quesada2010 11 18  Substation Automation Systems By Gin Quesada
2010 11 18 Substation Automation Systems By Gin Quesada
 
Tl pre-foundation
Tl pre-foundationTl pre-foundation
Tl pre-foundation
 
Power transformer
Power transformerPower transformer
Power transformer
 
Vocational trainning presentation at ESSAR Power Salaya (Electrical Engineering)
Vocational trainning presentation at ESSAR Power Salaya (Electrical Engineering)Vocational trainning presentation at ESSAR Power Salaya (Electrical Engineering)
Vocational trainning presentation at ESSAR Power Salaya (Electrical Engineering)
 

Similar to Electrical substation general_equipments

Electrical_substation_general_equipments.ppt
Electrical_substation_general_equipments.pptElectrical_substation_general_equipments.ppt
Electrical_substation_general_equipments.ppt
BrijeshKumar33410
 
UNIT-5 TD_Study Notes.pptx
UNIT-5 TD_Study Notes.pptxUNIT-5 TD_Study Notes.pptx
UNIT-5 TD_Study Notes.pptx
sasitharjaisankaran1
 
10 different equipment used in Distribution Substation
10 different equipment used in Distribution Substation10 different equipment used in Distribution Substation
10 different equipment used in Distribution Substation
DevanshVarma1
 
Switchgear & Rectifier ppt
Switchgear & Rectifier pptSwitchgear & Rectifier ppt
Switchgear & Rectifier ppt
vikas kumar
 
Presentation on substations
Presentation on substationsPresentation on substations
Presentation on substations
vishalgohel12195
 
Ppt on 132 kv gss by ashok khoja
Ppt on  132 kv gss  by ashok khojaPpt on  132 kv gss  by ashok khoja
Ppt on 132 kv gss by ashok khojaASHOK KHOJA
 
Switchgear and protection lecture 1
Switchgear and protection lecture 1Switchgear and protection lecture 1
Switchgear and protection lecture 1
anuphowlader1
 
SUB-STATION DESIGN AND PROTECTION (AN OVERVIEW)
SUB-STATION DESIGN AND PROTECTION  (AN OVERVIEW)SUB-STATION DESIGN AND PROTECTION  (AN OVERVIEW)
SUB-STATION DESIGN AND PROTECTION (AN OVERVIEW)
Ameh Messiah Edache
 
Substation_equipment_ (1).pptx
Substation_equipment_ (1).pptxSubstation_equipment_ (1).pptx
Substation_equipment_ (1).pptx
Satish Pydimarla
 
Introduction to switchgear
Introduction to switchgearIntroduction to switchgear
Introduction to switchgear
Adnan Sayed
 
Relays
  Relays  Relays
400 kv Heerapura gss ppt by ishan pdf
400 kv Heerapura gss ppt by ishan pdf 400 kv Heerapura gss ppt by ishan pdf
400 kv Heerapura gss ppt by ishan pdf
Ishan Khandelwal
 
TOPIC 2.1- Relays.pptx
TOPIC 2.1- Relays.pptxTOPIC 2.1- Relays.pptx
TOPIC 2.1- Relays.pptx
MartMantilla1
 
Presentation on 132/33KV BSPTCL(Bodhgaya Substation)
Presentation on 132/33KV BSPTCL(Bodhgaya Substation)Presentation on 132/33KV BSPTCL(Bodhgaya Substation)
Presentation on 132/33KV BSPTCL(Bodhgaya Substation)
Rahul Prajapati
 
Design of substation
Design of substationDesign of substation
Design of substation
SayanSarkar55
 
Electrical Basics-VBR
Electrical Basics-VBRElectrical Basics-VBR
Electrical Basics-VBR
Vijay Raskar
 
rough.pptx
rough.pptxrough.pptx
rough.pptx
virat217995
 
33/11 KV TRANSMISSION LINE
33/11 KV TRANSMISSION LINE 33/11 KV TRANSMISSION LINE
33/11 KV TRANSMISSION LINE
Lalit Kumar
 
switchgearpresentation-151030171028-lva1-app6892.pptx
switchgearpresentation-151030171028-lva1-app6892.pptxswitchgearpresentation-151030171028-lva1-app6892.pptx
switchgearpresentation-151030171028-lva1-app6892.pptx
DrNiveditaSingh3
 

Similar to Electrical substation general_equipments (20)

Electrical_substation_general_equipments.ppt
Electrical_substation_general_equipments.pptElectrical_substation_general_equipments.ppt
Electrical_substation_general_equipments.ppt
 
UNIT-5 TD_Study Notes.pptx
UNIT-5 TD_Study Notes.pptxUNIT-5 TD_Study Notes.pptx
UNIT-5 TD_Study Notes.pptx
 
10 different equipment used in Distribution Substation
10 different equipment used in Distribution Substation10 different equipment used in Distribution Substation
10 different equipment used in Distribution Substation
 
ntpc ppt
ntpc pptntpc ppt
ntpc ppt
 
Switchgear & Rectifier ppt
Switchgear & Rectifier pptSwitchgear & Rectifier ppt
Switchgear & Rectifier ppt
 
Presentation on substations
Presentation on substationsPresentation on substations
Presentation on substations
 
Ppt on 132 kv gss by ashok khoja
Ppt on  132 kv gss  by ashok khojaPpt on  132 kv gss  by ashok khoja
Ppt on 132 kv gss by ashok khoja
 
Switchgear and protection lecture 1
Switchgear and protection lecture 1Switchgear and protection lecture 1
Switchgear and protection lecture 1
 
SUB-STATION DESIGN AND PROTECTION (AN OVERVIEW)
SUB-STATION DESIGN AND PROTECTION  (AN OVERVIEW)SUB-STATION DESIGN AND PROTECTION  (AN OVERVIEW)
SUB-STATION DESIGN AND PROTECTION (AN OVERVIEW)
 
Substation_equipment_ (1).pptx
Substation_equipment_ (1).pptxSubstation_equipment_ (1).pptx
Substation_equipment_ (1).pptx
 
Introduction to switchgear
Introduction to switchgearIntroduction to switchgear
Introduction to switchgear
 
Relays
  Relays  Relays
Relays
 
400 kv Heerapura gss ppt by ishan pdf
400 kv Heerapura gss ppt by ishan pdf 400 kv Heerapura gss ppt by ishan pdf
400 kv Heerapura gss ppt by ishan pdf
 
TOPIC 2.1- Relays.pptx
TOPIC 2.1- Relays.pptxTOPIC 2.1- Relays.pptx
TOPIC 2.1- Relays.pptx
 
Presentation on 132/33KV BSPTCL(Bodhgaya Substation)
Presentation on 132/33KV BSPTCL(Bodhgaya Substation)Presentation on 132/33KV BSPTCL(Bodhgaya Substation)
Presentation on 132/33KV BSPTCL(Bodhgaya Substation)
 
Design of substation
Design of substationDesign of substation
Design of substation
 
Electrical Basics-VBR
Electrical Basics-VBRElectrical Basics-VBR
Electrical Basics-VBR
 
rough.pptx
rough.pptxrough.pptx
rough.pptx
 
33/11 KV TRANSMISSION LINE
33/11 KV TRANSMISSION LINE 33/11 KV TRANSMISSION LINE
33/11 KV TRANSMISSION LINE
 
switchgearpresentation-151030171028-lva1-app6892.pptx
switchgearpresentation-151030171028-lva1-app6892.pptxswitchgearpresentation-151030171028-lva1-app6892.pptx
switchgearpresentation-151030171028-lva1-app6892.pptx
 

Recently uploaded

一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
dxobcob
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
insn4465
 
Low power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniquesLow power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniques
nooriasukmaningtyas
 
bank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdfbank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdf
Divyam548318
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
symbo111
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
ChristineTorrepenida1
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
aqil azizi
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
nooriasukmaningtyas
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
camseq
 
01-GPON Fundamental fttx ftth basic .pptx
01-GPON Fundamental fttx ftth basic .pptx01-GPON Fundamental fttx ftth basic .pptx
01-GPON Fundamental fttx ftth basic .pptx
benykoy2024
 
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.pptPROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
bhadouriyakaku
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Christina Lin
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Soumen Santra
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
gestioneergodomus
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
NidhalKahouli2
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
ClaraZara1
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
sieving analysis and results interpretation
sieving analysis and results interpretationsieving analysis and results interpretation
sieving analysis and results interpretation
ssuser36d3051
 

Recently uploaded (20)

一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
 
Low power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniquesLow power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniques
 
bank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdfbank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdf
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
 
01-GPON Fundamental fttx ftth basic .pptx
01-GPON Fundamental fttx ftth basic .pptx01-GPON Fundamental fttx ftth basic .pptx
01-GPON Fundamental fttx ftth basic .pptx
 
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.pptPROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
PROJECT FORMAT FOR EVS AMITY UNIVERSITY GWALIOR.ppt
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
sieving analysis and results interpretation
sieving analysis and results interpretationsieving analysis and results interpretation
sieving analysis and results interpretation
 

Electrical substation general_equipments

  • 2. SUBSTATION • SUBSTATION - A station in the power transmission system at which electric power is transformed to a conveniently used form. The station may consist of transformers, switches, circuit breakers and other auxilliary equipment. Its main function is to receive energy transmitted at high voltage from the generating station, by either step-up or step-down the voltage to a value appropriate for local use and provide facilities for switching. Substations have some additional functions. Its provide points where safety devices may be installed to disconnect circuits or equipment in the event of trouble. Some substation, such as power plant switchyard are simply switching stations where different connections can be made between various transmission lines.
  • 3. Typical Components of a Power Plant Substation (Switchyard) •A - Busbar •B - Disconnector •C - Circuit Breaker •D - Current Transformer •E - Voltage Transformer •F - Earthing Switch •G - Surge Arrestor • CONNECT • CONNECT & DIS-CONNECT • CONNECT, DIS-CONNECT & DETECT • DETECT & TRANSFORM • DETECT & TRANSFORM • PROTECT & SAFETY • PROTECT
  • 4. A. BUSBAR • BUSBAR (or bus, for short) – is a term we use for a main bar or conductor carrying an electric current to which many connection may be made. Buses are merely convenient means of connecting switches and other equipment into various arrangements. The usual arrangement of connections in most substations permit working on almost any piece of equipment without interruption to incoming or outgoing feeders. In the switchyard or substation, buses are open to the air. Aluminum or copper conductors supported on porcelain insulators, carry the electric energy from point to point.
  • 6. B. DISCONNECTS • DISCONNECT – is an easily removed piece of the actual conductor of a circuit. The purpose of disconnects is to isolate equipment. Disconnects are not used to interrupt circuits; they are no-load devices. A typical use of disconnects is to isolate a circuit breaker by installing one disconnect on either side of the circuit breaker (in series with the breaker). Operation of disconnects is one of the most important and responsible jobs of a power plant operator. One error in isolation of equipment, or the accidental grounding of line equipment, can be a fatal mistake.
  • 7. A B Disconnect Switch ( moving contact rod (A) & contacts with flexible fingers (B) )
  • 8. C. CIRCUIT BREAKER • CIRCUIT BREAKER – is used to interrupt circuits while current is flowing through them. The making and breaking of contacts in a Oil type circuit breaker are done under oil, this oil serves to quench the arc when the circuit is opened. The operation of the breaker is very rapid when opening. As with the transformer, the high voltage connections are made through bushings. Circuit breakers of this type are usually arranged for remote electrical control from a suitably located switchboard. Some recently developed circuit breakers have no oil, but put out the arc by a blast of compressed air; these are called air circuit breakers. Another type encloses the contacts in a vacuum or a gas (sulfur hexafluoride, SF6) which tends to self maintain the arc.
  • 9. Circuit Breakers ( Connected in a typical 3- phase circuit ) Operating Mechanism Panel Position Indicator
  • 10. D. CURRENT TRANSFORMER • CURRENT TRANSFORMER – Current transformer are used with ammeters, watt meters, power-factor meters, watt-hour meters,compensators, protective and regulating relays and the trip coil of circuit breakers. One current transformer can be used to operate several instruments, provided that the combined burden does not exceed that for which the transformer is designed and compensated. The current transformer is connected directly in series with the line.
  • 11.
  • 12. E. VOLTAGE TRANSFORMER • VOLTAGE TRANSFORMER – also know as potential transformer, are used with volt-meters, wattmeters, watt- hour meters, power-factor meters, frequency meters, synchroscopes and synchronizing apparatus, protective and regulating relays and the no-voltage and over-voltage trip coils of automatic circuit breakers. One transformer can be used for a number of instruments at the same time if the total current taken by the instrument does not exceed that for which the transformer is designed and compensated. The ordinary voltage transformer is connected across the line, and the magnetic flux in the core depends upon the primary voltage
  • 13.
  • 14. F. EARTHING SWITCH • EARTHING SWITCH – also known as ground disconnect, which used to connects the equipment to a grid of electrical conductors buried in the earth on the station property. It is intended to protect people working on the grounded equipment. It does this by completing a circuit path, thereby reducing the voltage difference between the equipment and its surroundings. For safety reasons, it is important that ground disconnects and all associated connections have good contact and low resistance. It is also important that the protective ground not be accidentally remove, that is why all the earthing switches, disconnect switches and circuit breakers are all interlocked to each other and proper/correct sequencing must be followed.
  • 15. G. SURGE ARRESTOR • SURGE ARRESTOR – are devices used to provide the necessary path to ground for such surges, yet prevent any power current from following the surge. An ideal arrester must therefore have the following properties: 1. Ability to remove the surge energy from the line in a min. time. 2. High resistive to flow of power current. 3. A valve action automatically allowing surge to pass and then closing up so as not to permit power current to flow to ground. 4. Always ready to perform. 5. Performance such that no system disturbances are introduced by its operation. 6. Economically feasible
  • 16.
  • 17. • OVERHEAD GROUND WIRE – by a ground wire is meant a wire, generally of steel, supported from the top of transmission-line towers and solidly grounded at each tower. It is considered a preventive device, but it does not entirely prevent the formation of travelling waves on a line. Furthermore, those lines which are not equipped with ground wires will be subjected to disturbances which produce surges that must be allowed to escaped to ground, or the apparatus connected to the line must be strong enough to reflect or absorb these surges until they are entirely damped out.
  • 18.
  • 19. PREVENTIVE MAINTENANCE • BUSBARS & OVERHEAD GROUND WIRE At least once a year  Visual Inspection & Examination of all wiring connectors.  Check Insulator , clean or apply HVIC if necessary.  Check the physical condition of bus (cables or bars)  For ground wire, check or test the grounding system. • DISCONNECT & EARTHING SWITCHES At least once a month  Visual Inspection.  Check heating resistor located at its control panel for proper functioning. At least once a year  Clean contacts of disconnectors as well as earthing switches and apply electrical contact grease , if necessary.
  • 20.  Check disconnectors and earthing switches, joints and bearings of the operating linkages for deformed bearing points.  Check flexible connections of earthing switches.  Check all screwed joints for tight fit.  Clean insulators if necessary, when an excessive amount of dirt has accumulated.  Carry-out the maintenance of operating mechanism. • VOLTAGE TRANSFORMER At least once a month  Inspect the voltage divider to be sure that no oil leak or serious accumulation of soot, dust or salt composite is present.  Inspect the intermediate voltage transformer and check the minimum permissible oil level. At least once a year  Check all screwed joints & contact for tight fit.  Clean insulators if necessary, when an excessive amount of dirt has accumulated.
  • 21. CURRENT TRANSFORMER At least once a month Visual Inspection to check oil level and defects or possible oil leaks. At least once a year Check all screwed joints & contact for tight fit. Clean insulators if necessary, when an excessive amount of dirt has accumulated. Check primary and secondary connectors and conduct necessary tightening. Note: Never open a secondary winding of a CT while on service. •SURGE ARRESTOR At least once a year Visual Inspection & Examination of all wiring connectors. Check Insulator and metal circular ring, clean or apply HVIC if necessary. Check the physical condition of bus (cables or bars)
  • 22.  For ground wire, check or test the grounding system. Note: Arrestors should never be touched unless completely disconnected from all live lines and equipment and effectively connected to ground at the line side of the arrestor.