SlideShare a Scribd company logo
1 of 51
SUBSTATION
HIGH VOLTAGE
COMPONENTS
SWITCHING STATION
(SWITCHYARD)
SUBSTATION
•SUBSTATION - A station in the power transmission
system at which electric power is transformed to a
conveniently used form. The station may consist of
transformers, switches, circuit breakers and other
auxiliary equipment. Its main function is to receive
energy transmitted at high voltage from the
generating station, by either step-up or step-down
the voltage to a value appropriate for local use and
provide facilities for switching. Substations have
some additional functions. Its provide points where
safety devices may be installed to disconnect circuits
or equipment in the event of trouble.
Some substation, such as power plant
switchyard are simply switching stations where
different connections can be made between various
transmission lines.
SUBSTATION
SUBSTATION
 Rated Voltage/ Maximum Voltage
 Rated Current
 Rated Frequency
 BIL or Basic Insulation Level
 1 minute power frequency with stand voltage
 Short time current for 3 sec
 Auxiliary Operating supply
Basic & Common Specification of Substation Equipment's
Rated Voltage/ Maximum Voltage
 The voltage value of electrical equipment for which it is designed to be
used is called nominal voltage or rated Voltage.
 The voltage that can be applied to equipment to operate safely is called
Maximum voltage. The maximum tolerance value that we can apply
Rated Current
 This is the maximum rms current the equipment can continuously operate
at, under normal conditions. This rating is based on an , within an
allowable maximum temperature rise. For temperatures above 40°C,
switchgear rated current must be derated
Rated Frequency
 This is the rated test frequency of the switchgear and must match the
operating frequency of the installation. Two medium voltage mains supply
frequencies are used globally:
BIL or Basic Insulation Level
 When lightning impulse over voltage appears in the system, it is
discharged through surge protecting devices before the equipment's of
the system gets damaged.
 Hence, the insulation of such equipment must be designed to withstand a
certain minimum voltage before the lightning impulse over voltage gets
discharged through surge protecting devices.
 Therefore, operating voltage level of surge protecting devices must be
lower than the said minimum voltage withstanding level of the
equipment. This minimum voltage rating is defined as BIL or basic
insulation level of electrical equipment.
BIL or Basic Insulation Level
1 Minute Power frequency with stand voltage
 This is the maximum rms voltage that the equipment can withstand at mains
frequency for 1 minute. It simulates power surges originated from within a
power system from such events as switching transients, resonance, etc.
Short time current for 3 sec
 This is the period of time that the equipment is rated to carry the short-time
withstand current. IEC 62271-1 specifies a standard rating of 1 second,
although durations of 0.5, 2 and 3 seconds are allowed
 This is the level of symmetrical rms fault current the switchgear can carry in
the closed position for a short time period (typically 1 second), without
temperature rise exceeding predefined levels. IEC 62271-1 specifies standard
ratings as base 10 multiples of 1, 1.25, 1.6, 2, 2.5, 3.15, 4, 5, 6.3, 8
Short time current for 3 sec
 This is the period of time that the equipment is rated to carry the short-time
withstand current. IEC 62271-1 specifies a standard rating of 1 second,
although durations of 0.5, 2 and 3 seconds are allowed
 This is the level of symmetrical rms fault current the switchgear can carry in
the closed position for a short time period (typically 1 second), without
temperature rise exceeding predefined levels. IEC 62271-1 specifies standard
ratings as base 10 multiples of 1, 1.25, 1.6, 2, 2.5, 3.15, 4, 5, 6.3, 8
TYPICAL COMPONENTS OF A POWER
PLANT SUBSTATION (SWITCHYARD)
•A - Busbar
•B - Disconnector
•C - Circuit Breaker
•D - Current Transformer
•E - Voltage Transformer
•F - Earthing Switch
•G - Surge Arrestor
• CONNECT
• CONNECT & DIS-CONNECT
• CONNECT, DIS-CONNECT & DETECT
• DETECT & TRANSFORM
• DETECT & TRANSFORM
• PROTECT & SAFETY
• PROTECT
A. BUSBAR
BUSBAR (or bus, for short) – is a term we use for a
main bar or conductor carrying an electric current to
which many connection may be made.
Buses are merely convenient means of
connecting switches and other equipment into
various arrangements. The usual arrangement of
connections in most substations permit working on
almost any piece of equipment without interruption
to incoming or outgoing feeders. In the switchyard or
substation, buses are open to the air. Aluminum or
copper conductors supported on porcelain insulators,
carry the electric energy from point to point.
Busbars
(long heavy
tube type)
B. DISCONNECTS
DISCONNECT – is an easily removed piece of the
actual conductor of a circuit.
The purpose of disconnects is to isolate equipment.
Disconnects are not used to interrupt circuits; they
are no-load devices.
A typical use of disconnects is to isolate a circuit
breaker by installing one disconnect on either side of
the circuit breaker (in series with the breaker).
Operation of disconnects is one of the most
important and responsible jobs of a power plant
operator.
One error in isolation of equipment, or the accidental
grounding of line equipment, can be a fatal mistake.
ACSR Conductor IEC 61089 Standard.
A
B
Disconnect Switch
( moving contact rod (A) &
contacts with flexible
fingers (B) )
A
B
Disconnect Switch
( moving contact rod (A) &
contacts with flexible
fingers (B) )
C. CIRCUIT BREAKER
CIRCUIT BREAKER – is used to interrupt circuits while
current is flowing through them. The making and
breaking of contacts in a Oil type circuit breaker are
done under oil, this oil serves to quench the arc when
the circuit is opened. The operation of the breaker is
very rapid when opening. As with the transformer, the
high voltage connections are made through bushings.
Circuit breakers of this type are usually arranged for
remote electrical control from a suitably located
switchboard.
Some recently developed circuit breakers have
no oil, but put out the arc by a blast of compressed
air; these are called air circuit breakers. Another type
encloses the contacts in a vacuum or a gas (sulfur
hexafluoride, SF6) which tends to self maintain the
arc.
https://youtu.be/ncQYYTXgB28
Circuit Breakers
( Connected in a typical 3-
phase circuit )
Operating
Mechanism
Panel
Position
Indicator
Circuit Breakers
( Connected in a typical 3-
phase circuit )
Operating
Mechanism
Panel
Position
Indicator
WHAT IS THE DUTY CYCLE/ OPERATING SEQUENCE OF
CB?
IT IS THE MECHANICAL DUTY REQUIREMENT TO BE
FULFILLED BY THE OPERATING MECHANISM OF THE
BREAKER AND SPECIFIED ON THE NAME PLATE OF THE
BREAKER BY THE MANUFACTURER.
IT IS MAINLY USED DURING CIRCUIT BREAKER AUTO
RECLOSING.
IT SPECIFIED AS: O-T-CO-T’-CO AND GENERALLY
GIVEN AS O-0.3 SEC-CO-3 MIN-CO, WHERE O IS CB
TRIPPING, T IS THE DEAD TIME, CO IS RECLOSE WITH
IMMEDIATE TRIPPING (AR UNSUCCESSFUL) AND T’ IS
THE RECLAIM TIME AND THEN THE CYCLE
CONTINUOUS, IF ITS A MULTISPORT AR OR THE
FAULT RECOURSE.
Sequence of Operation:
1. When there is a fault, the concerned relay operates, which inturn
operates the Master Trip Relay (86).
2. CB Trip initiates and at the same time Auto Reclose Initiates.
3. CB Trips in about 30ms, which is indicated by “O” in the Duty Cycle.
4. Then CB will remain open for some time (0.3 sec) to complete the Arc
Quenching which is called as Dead Time and is indicated by “0.3Sec” in
the Duty Cycle.
5. After 0.3 sec, if AR is in Service, a Reclose will be attempted, and if the
fault persists, CB Trips immediately ( AR Unsuccessful ) which is
indicated by “CO” in the duty cycle.
6. If its a Single Shot Auto-reclose, the Breaker will go into Auto Reclose
Lockout, that means , the Auto Reclose Relay will not give any further
Reclose Command to the Breaker.
7. After CO, there is a Reclaim Time of 3 Minutes, in which the CB gets
ready for Closing, which includes CB Spring Charging Time, indicated by
“3 Min” in the Duty Cycle.
8. After the Reclaim Time has completed, Second Reclose will be attempted
in following two cases:
D. CURRENT TRANSFORMER
CURRENT TRANSFORMER – Current transformer are
used with ammeters, watt meters, power-factor
meters, watt-hour meters, compensators, protective
and regulating relays and the trip coil of circuit
breakers. One current transformer can be used to
operate several instruments, provided that the
combined burden does not exceed that for which the
transformer is designed and compensated. The
current transformer is connected directly in series
with the line.
E. VOLTAGE TRANSFORMER
VOLTAGE TRANSFORMER – also know as potential
transformer, are used with volt-meters, wattmeters,
watt-hour meters, power-factor meters, frequency
meters, synchroscopes and synchronizing apparatus,
protective and regulating relays and the no-voltage
and over-voltage trip coils of automatic circuit
breakers. One transformer can be used for a number
of instruments at the same time if the total current
taken by the instrument does not exceed that for
which the transformer is designed and compensated.
The ordinary voltage transformer is connected across
the line, and the magnetic flux in the core depends
upon the primary voltage
F. EARTHING SWITCH
EARTHING SWITCH – also known as ground
disconnect, which used to connects the equipment to
a grid of electrical conductors buried in the earth on
the station property. It is intended to protect people
working on the grounded equipment. It does this by
completing a circuit path, thereby reducing the
voltage difference between the equipment and its
surroundings. For safety reasons, it is important that
ground disconnects and all associated connections
have good contact and low resistance. It is also
important that the protective ground not be
accidentally remove, that is why all the earthing
switches, disconnect switches and circuit breakers are
all interlocked to each other and proper/correct
sequencing must be followed.
G. SURGE ARRESTOR
SURGE ARRESTOR – are devices used to provide the
necessary path to ground for such surges, yet prevent
any power current from following the surge. An ideal
arrester must therefore have the following properties:
1. Ability to remove the surge energy from the line in a
min. time.
2. High resistive to flow of power current.
3. A valve action automatically allowing surge to pass
and then closing up so as not to permit power
current to flow to ground.
4. Always ready to perform.
5. Performance such that no system disturbances are
introduced by its operation.
6. Economically feasible
OVERHEAD GROUND WIRE – by a ground wire is
meant a wire, generally of steel, supported from the
top of transmission-line towers and solidly grounded
at each tower. It is considered a preventive device,
but it does not entirely prevent the formation of
travelling waves on a line. Furthermore, those lines
which are not equipped with ground wires will be
subjected to disturbances which produce surges that
must be allowed to escaped to ground, or the
apparatus connected to the line must be strong
enough to reflect or absorb these surges until they
are entirely damped out.
PREVENTIVE MAINTENANCE
BUSBARS & OVERHEAD GROUND WIRE
At least once a year
 Visual Inspection & Examination of all wiring connectors.
 Check Insulator , clean or apply HVIC if necessary.
 Check the physical condition of bus (cables or bars)
 For ground wire, check or test the grounding system.
DISCONNECT & EARTHING SWITCHES
At least once a month
 Visual Inspection.
 Check heating resistor located at its control panel for proper
functioning.
At least once a year
 Clean contacts of disconnectors as well as earthing switches and apply
electrical contact grease , if necessary.
 Check disconnectors and earthing switches, joints and bearings of the
operating linkages for deformed bearing points.
 Check flexible connections of earthing switches.
 Check all screwed joints for tight fit.
 Clean insulators if necessary, when an excessive amount of dirt has
accumulated.
 Carry-out the maintenance of operating mechanism.
VOLTAGE TRANSFORMER
At least once a month
 Inspect the voltage divider to be sure that no oil leak or serious
accumulation of soot, dust or salt composite is present.
 Inspect the intermediate voltage transformer and check the minimum
permissible oil level.
At least once a year
 Check all screwed joints & contact for tight fit.
 Clean insulators if necessary, when an excessive amount of dirt has
accumulated.
CURRENT TRANSFORMER
At least once a month
 Visual Inspection to check oil level and defects or possible oil leaks.
At least once a year
 Check all screwed joints & contact for tight fit.
 Clean insulators if necessary, when an excessive amount of dirt has
accumulated.
 Check primary and secondary connectors and conduct necessary
tightening.
Note: Never open a secondary winding of a CT while on service.
SURGE ARRESTOR
At least once a year
 Visual Inspection & Examination of all wiring connectors.
 Check Insulator and metal circular ring, clean or apply HVIC if
necessary.
 Check the physical condition of bus (cables or bars)
 For ground wire, check or test the grounding system.
Note: Arrestors should never be touched unless completely
disconnected from all live lines and equipment and effectively
connected to ground at the line side of the arrestor.
THANKS FOR YOUR TIME

More Related Content

Similar to Substation_equipment_ (1).pptx

switchgear and protection by vala kamlesh
switchgear and protection by vala kamleshswitchgear and protection by vala kamlesh
switchgear and protection by vala kamleshKamlesh Vala
 
Substation Training presentation
Substation Training presentationSubstation Training presentation
Substation Training presentationKamal Mittal
 
Presentation1.pptx power system
Presentation1.pptx power systemPresentation1.pptx power system
Presentation1.pptx power systemArvind Nathan
 
Switchgear & Rectifier ppt
Switchgear & Rectifier pptSwitchgear & Rectifier ppt
Switchgear & Rectifier pptvikas kumar
 
powersystemprotectiondevices-161120193617 (1).pdf
powersystemprotectiondevices-161120193617 (1).pdfpowersystemprotectiondevices-161120193617 (1).pdf
powersystemprotectiondevices-161120193617 (1).pdfMonalPandey1
 
Unit 03 Protective relays
Unit  03 Protective relaysUnit  03 Protective relays
Unit 03 Protective relaysPremanandDesai
 
220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance220 KV Substation Operation & Maintenance
220 KV Substation Operation & MaintenanceHimansu Pradhan
 
Power system protection devices
Power system protection devicesPower system protection devices
Power system protection devicesPrakash_13209
 
Schneider Technical Guide - Medium Voltage Equipment Designers
Schneider Technical Guide - Medium Voltage Equipment DesignersSchneider Technical Guide - Medium Voltage Equipment Designers
Schneider Technical Guide - Medium Voltage Equipment DesignersThorne & Derrick International
 
SGP-4 PROTECTION OF ALTRNTR.pptx
SGP-4 PROTECTION OF ALTRNTR.pptxSGP-4 PROTECTION OF ALTRNTR.pptx
SGP-4 PROTECTION OF ALTRNTR.pptxSHIVANICHAUUHAN1
 
Introduction to switchgear
Introduction to switchgearIntroduction to switchgear
Introduction to switchgearAdnan Sayed
 
“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...
“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...
“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...rohit nadella
 
Switchyard final
Switchyard finalSwitchyard final
Switchyard finalHAIDER ALI
 
DISTRIBUTION SYSTEM OPERATION AND CONTROL
DISTRIBUTION SYSTEM OPERATION AND CONTROLDISTRIBUTION SYSTEM OPERATION AND CONTROL
DISTRIBUTION SYSTEM OPERATION AND CONTROLyohannes feleke
 
ELECTRIC SUB-STATION IN BRIEF
ELECTRIC SUB-STATION IN BRIEFELECTRIC SUB-STATION IN BRIEF
ELECTRIC SUB-STATION IN BRIEFjang041
 
Electrical substation general_equipments
Electrical substation general_equipmentsElectrical substation general_equipments
Electrical substation general_equipmentsEman Dacanay
 

Similar to Substation_equipment_ (1).pptx (20)

switchgear and protection by vala kamlesh
switchgear and protection by vala kamleshswitchgear and protection by vala kamlesh
switchgear and protection by vala kamlesh
 
Substation Training presentation
Substation Training presentationSubstation Training presentation
Substation Training presentation
 
Presentation1.pptx power system
Presentation1.pptx power systemPresentation1.pptx power system
Presentation1.pptx power system
 
Switchgear & Rectifier ppt
Switchgear & Rectifier pptSwitchgear & Rectifier ppt
Switchgear & Rectifier ppt
 
powersystemprotectiondevices-161120193617 (1).pdf
powersystemprotectiondevices-161120193617 (1).pdfpowersystemprotectiondevices-161120193617 (1).pdf
powersystemprotectiondevices-161120193617 (1).pdf
 
Unit 03 Protective relays
Unit  03 Protective relaysUnit  03 Protective relays
Unit 03 Protective relays
 
220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance
 
Power system protection devices
Power system protection devicesPower system protection devices
Power system protection devices
 
Schneider Technical Guide - Medium Voltage Equipment Designers
Schneider Technical Guide - Medium Voltage Equipment DesignersSchneider Technical Guide - Medium Voltage Equipment Designers
Schneider Technical Guide - Medium Voltage Equipment Designers
 
Ashish.pptx
Ashish.pptxAshish.pptx
Ashish.pptx
 
Summer Training presentation on 132/33 KV sub-station Minto park, Allahabad
Summer Training presentation on 132/33 KV sub-station Minto park, AllahabadSummer Training presentation on 132/33 KV sub-station Minto park, Allahabad
Summer Training presentation on 132/33 KV sub-station Minto park, Allahabad
 
SGP-4 PROTECTION OF ALTRNTR.pptx
SGP-4 PROTECTION OF ALTRNTR.pptxSGP-4 PROTECTION OF ALTRNTR.pptx
SGP-4 PROTECTION OF ALTRNTR.pptx
 
Introduction to switchgear
Introduction to switchgearIntroduction to switchgear
Introduction to switchgear
 
“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...
“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...
“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...
 
Switchyard final
Switchyard finalSwitchyard final
Switchyard final
 
132kV GSS ppt
132kV GSS ppt132kV GSS ppt
132kV GSS ppt
 
ntpc ppt
ntpc pptntpc ppt
ntpc ppt
 
DISTRIBUTION SYSTEM OPERATION AND CONTROL
DISTRIBUTION SYSTEM OPERATION AND CONTROLDISTRIBUTION SYSTEM OPERATION AND CONTROL
DISTRIBUTION SYSTEM OPERATION AND CONTROL
 
ELECTRIC SUB-STATION IN BRIEF
ELECTRIC SUB-STATION IN BRIEFELECTRIC SUB-STATION IN BRIEF
ELECTRIC SUB-STATION IN BRIEF
 
Electrical substation general_equipments
Electrical substation general_equipmentsElectrical substation general_equipments
Electrical substation general_equipments
 

More from Satish Pydimarla

Testing_of_transformers_adjusted.ppt
Testing_of_transformers_adjusted.pptTesting_of_transformers_adjusted.ppt
Testing_of_transformers_adjusted.pptSatish Pydimarla
 
Zaragoza Factory_Our product_ EN.ppt
Zaragoza Factory_Our product_ EN.pptZaragoza Factory_Our product_ EN.ppt
Zaragoza Factory_Our product_ EN.pptSatish Pydimarla
 
transformerprotection-180102061059.pdf
transformerprotection-180102061059.pdftransformerprotection-180102061059.pdf
transformerprotection-180102061059.pdfSatish Pydimarla
 
3-Phase-Transformer (1).pptx
3-Phase-Transformer (1).pptx3-Phase-Transformer (1).pptx
3-Phase-Transformer (1).pptxSatish Pydimarla
 
Presentation-Kalinga Stadium.pptx
Presentation-Kalinga Stadium.pptxPresentation-Kalinga Stadium.pptx
Presentation-Kalinga Stadium.pptxSatish Pydimarla
 
understandingtransformervectorgroup-180629014651.pptx
understandingtransformervectorgroup-180629014651.pptxunderstandingtransformervectorgroup-180629014651.pptx
understandingtransformervectorgroup-180629014651.pptxSatish Pydimarla
 
transformeronno-load-200825063948.pptx
transformeronno-load-200825063948.pptxtransformeronno-load-200825063948.pptx
transformeronno-load-200825063948.pptxSatish Pydimarla
 
332038674-Vector-Group-of-Transformers.ppt
332038674-Vector-Group-of-Transformers.ppt332038674-Vector-Group-of-Transformers.ppt
332038674-Vector-Group-of-Transformers.pptSatish Pydimarla
 
Parall Operation Transformers
Parall Operation TransformersParall Operation Transformers
Parall Operation TransformersSatish Pydimarla
 
Understanding_lightning_protection.pptx
Understanding_lightning_protection.pptxUnderstanding_lightning_protection.pptx
Understanding_lightning_protection.pptxSatish Pydimarla
 
Construction of HV Transmission Lines etc.pptx
Construction of HV Transmission Lines etc.pptxConstruction of HV Transmission Lines etc.pptx
Construction of HV Transmission Lines etc.pptxSatish Pydimarla
 

More from Satish Pydimarla (20)

9310091.ppt
9310091.ppt9310091.ppt
9310091.ppt
 
control room.pptx
control room.pptxcontrol room.pptx
control room.pptx
 
Thermovision Test.ppt
Thermovision Test.pptThermovision Test.ppt
Thermovision Test.ppt
 
4143813.ppt
4143813.ppt4143813.ppt
4143813.ppt
 
Transformer_theory.pptx
Transformer_theory.pptxTransformer_theory.pptx
Transformer_theory.pptx
 
Testing_of_transformers_adjusted.ppt
Testing_of_transformers_adjusted.pptTesting_of_transformers_adjusted.ppt
Testing_of_transformers_adjusted.ppt
 
Zaragoza Factory_Our product_ EN.ppt
Zaragoza Factory_Our product_ EN.pptZaragoza Factory_Our product_ EN.ppt
Zaragoza Factory_Our product_ EN.ppt
 
transformerprotection-180102061059.pdf
transformerprotection-180102061059.pdftransformerprotection-180102061059.pdf
transformerprotection-180102061059.pdf
 
3-Phase-Transformer (1).pptx
3-Phase-Transformer (1).pptx3-Phase-Transformer (1).pptx
3-Phase-Transformer (1).pptx
 
Electrical_Engg_Basic.PPT
Electrical_Engg_Basic.PPTElectrical_Engg_Basic.PPT
Electrical_Engg_Basic.PPT
 
Presentation-Kalinga Stadium.pptx
Presentation-Kalinga Stadium.pptxPresentation-Kalinga Stadium.pptx
Presentation-Kalinga Stadium.pptx
 
understandingtransformervectorgroup-180629014651.pptx
understandingtransformervectorgroup-180629014651.pptxunderstandingtransformervectorgroup-180629014651.pptx
understandingtransformervectorgroup-180629014651.pptx
 
transformeronno-load-200825063948.pptx
transformeronno-load-200825063948.pptxtransformeronno-load-200825063948.pptx
transformeronno-load-200825063948.pptx
 
332038674-Vector-Group-of-Transformers.ppt
332038674-Vector-Group-of-Transformers.ppt332038674-Vector-Group-of-Transformers.ppt
332038674-Vector-Group-of-Transformers.ppt
 
tcee-161003100321.pptx
tcee-161003100321.pptxtcee-161003100321.pptx
tcee-161003100321.pptx
 
Parall Operation Transformers
Parall Operation TransformersParall Operation Transformers
Parall Operation Transformers
 
Understanding_lightning_protection.pptx
Understanding_lightning_protection.pptxUnderstanding_lightning_protection.pptx
Understanding_lightning_protection.pptx
 
Understanding VCB.pptx
Understanding VCB.pptxUnderstanding VCB.pptx
Understanding VCB.pptx
 
CT & PT.pptx
CT & PT.pptxCT & PT.pptx
CT & PT.pptx
 
Construction of HV Transmission Lines etc.pptx
Construction of HV Transmission Lines etc.pptxConstruction of HV Transmission Lines etc.pptx
Construction of HV Transmission Lines etc.pptx
 

Recently uploaded

Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture designssuser87fa0c1
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 

Recently uploaded (20)

Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture design
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 

Substation_equipment_ (1).pptx

  • 2. SUBSTATION •SUBSTATION - A station in the power transmission system at which electric power is transformed to a conveniently used form. The station may consist of transformers, switches, circuit breakers and other auxiliary equipment. Its main function is to receive energy transmitted at high voltage from the generating station, by either step-up or step-down the voltage to a value appropriate for local use and provide facilities for switching. Substations have some additional functions. Its provide points where safety devices may be installed to disconnect circuits or equipment in the event of trouble. Some substation, such as power plant switchyard are simply switching stations where different connections can be made between various transmission lines.
  • 5.  Rated Voltage/ Maximum Voltage  Rated Current  Rated Frequency  BIL or Basic Insulation Level  1 minute power frequency with stand voltage  Short time current for 3 sec  Auxiliary Operating supply Basic & Common Specification of Substation Equipment's
  • 6. Rated Voltage/ Maximum Voltage  The voltage value of electrical equipment for which it is designed to be used is called nominal voltage or rated Voltage.  The voltage that can be applied to equipment to operate safely is called Maximum voltage. The maximum tolerance value that we can apply Rated Current  This is the maximum rms current the equipment can continuously operate at, under normal conditions. This rating is based on an , within an allowable maximum temperature rise. For temperatures above 40°C, switchgear rated current must be derated Rated Frequency  This is the rated test frequency of the switchgear and must match the operating frequency of the installation. Two medium voltage mains supply frequencies are used globally:
  • 7. BIL or Basic Insulation Level  When lightning impulse over voltage appears in the system, it is discharged through surge protecting devices before the equipment's of the system gets damaged.  Hence, the insulation of such equipment must be designed to withstand a certain minimum voltage before the lightning impulse over voltage gets discharged through surge protecting devices.  Therefore, operating voltage level of surge protecting devices must be lower than the said minimum voltage withstanding level of the equipment. This minimum voltage rating is defined as BIL or basic insulation level of electrical equipment.
  • 8. BIL or Basic Insulation Level
  • 9. 1 Minute Power frequency with stand voltage  This is the maximum rms voltage that the equipment can withstand at mains frequency for 1 minute. It simulates power surges originated from within a power system from such events as switching transients, resonance, etc. Short time current for 3 sec  This is the period of time that the equipment is rated to carry the short-time withstand current. IEC 62271-1 specifies a standard rating of 1 second, although durations of 0.5, 2 and 3 seconds are allowed  This is the level of symmetrical rms fault current the switchgear can carry in the closed position for a short time period (typically 1 second), without temperature rise exceeding predefined levels. IEC 62271-1 specifies standard ratings as base 10 multiples of 1, 1.25, 1.6, 2, 2.5, 3.15, 4, 5, 6.3, 8
  • 10. Short time current for 3 sec  This is the period of time that the equipment is rated to carry the short-time withstand current. IEC 62271-1 specifies a standard rating of 1 second, although durations of 0.5, 2 and 3 seconds are allowed  This is the level of symmetrical rms fault current the switchgear can carry in the closed position for a short time period (typically 1 second), without temperature rise exceeding predefined levels. IEC 62271-1 specifies standard ratings as base 10 multiples of 1, 1.25, 1.6, 2, 2.5, 3.15, 4, 5, 6.3, 8
  • 11. TYPICAL COMPONENTS OF A POWER PLANT SUBSTATION (SWITCHYARD) •A - Busbar •B - Disconnector •C - Circuit Breaker •D - Current Transformer •E - Voltage Transformer •F - Earthing Switch •G - Surge Arrestor • CONNECT • CONNECT & DIS-CONNECT • CONNECT, DIS-CONNECT & DETECT • DETECT & TRANSFORM • DETECT & TRANSFORM • PROTECT & SAFETY • PROTECT
  • 12. A. BUSBAR BUSBAR (or bus, for short) – is a term we use for a main bar or conductor carrying an electric current to which many connection may be made. Buses are merely convenient means of connecting switches and other equipment into various arrangements. The usual arrangement of connections in most substations permit working on almost any piece of equipment without interruption to incoming or outgoing feeders. In the switchyard or substation, buses are open to the air. Aluminum or copper conductors supported on porcelain insulators, carry the electric energy from point to point.
  • 14. B. DISCONNECTS DISCONNECT – is an easily removed piece of the actual conductor of a circuit. The purpose of disconnects is to isolate equipment. Disconnects are not used to interrupt circuits; they are no-load devices. A typical use of disconnects is to isolate a circuit breaker by installing one disconnect on either side of the circuit breaker (in series with the breaker). Operation of disconnects is one of the most important and responsible jobs of a power plant operator. One error in isolation of equipment, or the accidental grounding of line equipment, can be a fatal mistake. ACSR Conductor IEC 61089 Standard.
  • 15. A B Disconnect Switch ( moving contact rod (A) & contacts with flexible fingers (B) )
  • 16. A B Disconnect Switch ( moving contact rod (A) & contacts with flexible fingers (B) )
  • 17.
  • 18. C. CIRCUIT BREAKER CIRCUIT BREAKER – is used to interrupt circuits while current is flowing through them. The making and breaking of contacts in a Oil type circuit breaker are done under oil, this oil serves to quench the arc when the circuit is opened. The operation of the breaker is very rapid when opening. As with the transformer, the high voltage connections are made through bushings. Circuit breakers of this type are usually arranged for remote electrical control from a suitably located switchboard. Some recently developed circuit breakers have no oil, but put out the arc by a blast of compressed air; these are called air circuit breakers. Another type encloses the contacts in a vacuum or a gas (sulfur hexafluoride, SF6) which tends to self maintain the arc. https://youtu.be/ncQYYTXgB28
  • 19. Circuit Breakers ( Connected in a typical 3- phase circuit ) Operating Mechanism Panel Position Indicator
  • 20. Circuit Breakers ( Connected in a typical 3- phase circuit ) Operating Mechanism Panel Position Indicator
  • 21.
  • 22.
  • 23.
  • 24. WHAT IS THE DUTY CYCLE/ OPERATING SEQUENCE OF CB? IT IS THE MECHANICAL DUTY REQUIREMENT TO BE FULFILLED BY THE OPERATING MECHANISM OF THE BREAKER AND SPECIFIED ON THE NAME PLATE OF THE BREAKER BY THE MANUFACTURER. IT IS MAINLY USED DURING CIRCUIT BREAKER AUTO RECLOSING. IT SPECIFIED AS: O-T-CO-T’-CO AND GENERALLY GIVEN AS O-0.3 SEC-CO-3 MIN-CO, WHERE O IS CB TRIPPING, T IS THE DEAD TIME, CO IS RECLOSE WITH IMMEDIATE TRIPPING (AR UNSUCCESSFUL) AND T’ IS THE RECLAIM TIME AND THEN THE CYCLE CONTINUOUS, IF ITS A MULTISPORT AR OR THE FAULT RECOURSE.
  • 25. Sequence of Operation: 1. When there is a fault, the concerned relay operates, which inturn operates the Master Trip Relay (86). 2. CB Trip initiates and at the same time Auto Reclose Initiates. 3. CB Trips in about 30ms, which is indicated by “O” in the Duty Cycle. 4. Then CB will remain open for some time (0.3 sec) to complete the Arc Quenching which is called as Dead Time and is indicated by “0.3Sec” in the Duty Cycle. 5. After 0.3 sec, if AR is in Service, a Reclose will be attempted, and if the fault persists, CB Trips immediately ( AR Unsuccessful ) which is indicated by “CO” in the duty cycle. 6. If its a Single Shot Auto-reclose, the Breaker will go into Auto Reclose Lockout, that means , the Auto Reclose Relay will not give any further Reclose Command to the Breaker. 7. After CO, there is a Reclaim Time of 3 Minutes, in which the CB gets ready for Closing, which includes CB Spring Charging Time, indicated by “3 Min” in the Duty Cycle. 8. After the Reclaim Time has completed, Second Reclose will be attempted in following two cases:
  • 26.
  • 27.
  • 28. D. CURRENT TRANSFORMER CURRENT TRANSFORMER – Current transformer are used with ammeters, watt meters, power-factor meters, watt-hour meters, compensators, protective and regulating relays and the trip coil of circuit breakers. One current transformer can be used to operate several instruments, provided that the combined burden does not exceed that for which the transformer is designed and compensated. The current transformer is connected directly in series with the line.
  • 29.
  • 30.
  • 31.
  • 32.
  • 33.
  • 34.
  • 35.
  • 36.
  • 37. E. VOLTAGE TRANSFORMER VOLTAGE TRANSFORMER – also know as potential transformer, are used with volt-meters, wattmeters, watt-hour meters, power-factor meters, frequency meters, synchroscopes and synchronizing apparatus, protective and regulating relays and the no-voltage and over-voltage trip coils of automatic circuit breakers. One transformer can be used for a number of instruments at the same time if the total current taken by the instrument does not exceed that for which the transformer is designed and compensated. The ordinary voltage transformer is connected across the line, and the magnetic flux in the core depends upon the primary voltage
  • 38.
  • 39.
  • 40.
  • 41. F. EARTHING SWITCH EARTHING SWITCH – also known as ground disconnect, which used to connects the equipment to a grid of electrical conductors buried in the earth on the station property. It is intended to protect people working on the grounded equipment. It does this by completing a circuit path, thereby reducing the voltage difference between the equipment and its surroundings. For safety reasons, it is important that ground disconnects and all associated connections have good contact and low resistance. It is also important that the protective ground not be accidentally remove, that is why all the earthing switches, disconnect switches and circuit breakers are all interlocked to each other and proper/correct sequencing must be followed.
  • 42. G. SURGE ARRESTOR SURGE ARRESTOR – are devices used to provide the necessary path to ground for such surges, yet prevent any power current from following the surge. An ideal arrester must therefore have the following properties: 1. Ability to remove the surge energy from the line in a min. time. 2. High resistive to flow of power current. 3. A valve action automatically allowing surge to pass and then closing up so as not to permit power current to flow to ground. 4. Always ready to perform. 5. Performance such that no system disturbances are introduced by its operation. 6. Economically feasible
  • 43.
  • 44.
  • 45. OVERHEAD GROUND WIRE – by a ground wire is meant a wire, generally of steel, supported from the top of transmission-line towers and solidly grounded at each tower. It is considered a preventive device, but it does not entirely prevent the formation of travelling waves on a line. Furthermore, those lines which are not equipped with ground wires will be subjected to disturbances which produce surges that must be allowed to escaped to ground, or the apparatus connected to the line must be strong enough to reflect or absorb these surges until they are entirely damped out.
  • 46.
  • 47. PREVENTIVE MAINTENANCE BUSBARS & OVERHEAD GROUND WIRE At least once a year  Visual Inspection & Examination of all wiring connectors.  Check Insulator , clean or apply HVIC if necessary.  Check the physical condition of bus (cables or bars)  For ground wire, check or test the grounding system. DISCONNECT & EARTHING SWITCHES At least once a month  Visual Inspection.  Check heating resistor located at its control panel for proper functioning. At least once a year  Clean contacts of disconnectors as well as earthing switches and apply electrical contact grease , if necessary.
  • 48.  Check disconnectors and earthing switches, joints and bearings of the operating linkages for deformed bearing points.  Check flexible connections of earthing switches.  Check all screwed joints for tight fit.  Clean insulators if necessary, when an excessive amount of dirt has accumulated.  Carry-out the maintenance of operating mechanism. VOLTAGE TRANSFORMER At least once a month  Inspect the voltage divider to be sure that no oil leak or serious accumulation of soot, dust or salt composite is present.  Inspect the intermediate voltage transformer and check the minimum permissible oil level. At least once a year  Check all screwed joints & contact for tight fit.  Clean insulators if necessary, when an excessive amount of dirt has accumulated.
  • 49. CURRENT TRANSFORMER At least once a month  Visual Inspection to check oil level and defects or possible oil leaks. At least once a year  Check all screwed joints & contact for tight fit.  Clean insulators if necessary, when an excessive amount of dirt has accumulated.  Check primary and secondary connectors and conduct necessary tightening. Note: Never open a secondary winding of a CT while on service. SURGE ARRESTOR At least once a year  Visual Inspection & Examination of all wiring connectors.  Check Insulator and metal circular ring, clean or apply HVIC if necessary.  Check the physical condition of bus (cables or bars)
  • 50.  For ground wire, check or test the grounding system. Note: Arrestors should never be touched unless completely disconnected from all live lines and equipment and effectively connected to ground at the line side of the arrestor.