SlideShare a Scribd company logo
INDUSTRIAL TRAINING
2013
NTPC LIMITED
BADARPUR THERMAL POWER STATION
MADE BY :
Jatan Singh Soni
11BEE0061
Training at BTPS
I was appointed to do 4 week training at this esteemed
organization from 3rd June to 4th July, 2013. I was
assigned to visit various divisions of the plant, which
were:
Electrical Maintenance Department I (EMD-I)
Electrical Maintenance Department II (EMD-II)
Control and Instrumentation Department (C&I)
It was really amazing to see the power plant and learn
how electricity, which is one of our daily requirements of
life, is produced.
INDEX
• OPERATION OF POWER PLANT
• PARTS OF A POWER PLANT
• VARIOUS CYCLES AT POWER
STATION
• ELECTRICAL MAINTENANCE
DEPARTMENT-I
• ELECTRICAL MAINETNANCE
DEPARTMENT-II
• CONTROL AND
INSTRUMENTATION
The basic steps in the generation
of electricity from coal involves
following steps:
• Coal to steam – Steam Generator
or Boiler
• Steam to mechanical power -
Steam Turbine
• Mechanical power to electrical
power – Electric Generator
BASIC POWER PLANT CYCLE
PARTS OF A POWER
PLANT
1. Cooling tower
2. Cooling water pump
3. Transmission line (3-phase)
4. Unit transformer (3-phase)
5. Electric generator (3-phase)
6. Low pressure turbine
7. Condensate extraction pump
8. Condenser
9. Intermediate pressure turbine
10. Steam governor valve
11. High pressure turbine
12. Deaerator
13. Feed heater
14. Coal conveyor
15. Coal hopper
16. Pulverized fuel mill
17. Boiler drum
18. Ash hopper
19. Super heater
20. Forced draught fan
21. Reheater
22. Air intake
23. Economizer
24. Air preheater
25. Precipitator
26. Induced draught fan
27. Flue Gas
THE EQUIPMENTS THAT NORMALLY FALL IN
THIS CATEGORY ARE:-ISOLATOR
• Isolator cannot operate unless breaker is open
• Bus 1 and bus 2 isolators cannot be closed simultaneously
• The interlock can be bypass in the event of closing of bus coupler breaker.
• No isolator can operate when the corresponding earth switch is on
SWITCHING ISOLATOR
• Switching isolator is capable of:
• Interrupting charging current
• Interrupting transformer magnetizing current
• Load transformer switching. Its main application is in connection with the transformer feeder as the unit
makes it possible to switch gear one transformer while the other is still on load.
CIRCUIT BREAKER
• One which can make or break the circuit on load and even on faults is referred to as circuit breakers. This
equipment is the most important and is heavy duty equipment mainly utilized for protection of various
circuits and operations on load. Normally circuit breakers installed are accompanied by isolators.
LOAD BREAK SWITCHES
• These are those interrupting devices which can make or break circuits. These are normally on same
circuit, which are backed by circuit breakers
EARTH SWITCHES
• Devices which are used normally to earth a particular system, to avoid any accident happening due to
induction on account of live adjoining circuits. These equipments do not handle any appreciable current
at all. Apart from this equipment there are a number of relays etc. which are used in switchgear.
OIL CIRCUIT
BREAKERS
AIR CIRCUIT
BREAKERS
SF6
CIRCUIT
BREAKERS
RATINGS OF THE GENERATORS USED
• Turbo generator 100MW
• TURBO GENERATOR 210 MW
•
• The 100 MW generator generates 10.75 KV and
210 MW generates 15.75 KV. The voltage is
stepped up to 220 KV with the help of generator
transformer and is connected to the grid.
• The voltage is stepped down to 6.6 KV with the
help of UNIT AUXILLARY TRANSFORMER (UAT)
and this voltage is used to drive the HT motors.
The voltage is further stepped down to 415 V and
then to 220 V and this voltage is used to drive Lt
Motors.
COOLING OF TRANSFORMERS
OF LARGE MVA
As size of transformer becomes large, the rate of the oil circulating becomes insufficient to dissipate
all the heat produced & artificial means of increasing the circulation by electric pumps. In very large
transformers, special coolers with water circulation may have to be employed.
TYPES OF COOLING:
Air cooling
Air Natural (AN)
Air Forced (AF)
Oil immersed cooling
Oil Natural Air Natural (ONAN)
Oil Natural Air Forced (ONAF)
Oil Forced Air Natural (OFAN)
Oil Forced Air Forced (OFAF)
Oil immersed Water cooling
Oil Natural Water Forced (ONWF)
Oil Forced Water Forced (OFWF)
UNIT AUXILIARY TRANSFORMER (UAT)
Unit I & V- 12.5 MVA
The UAT draws its input from the main bus-ducts. The total KVA capacity
of UAT required can be determined by assuming 0.85 power factor & 90%
efficiency for total auxiliary motor load. It is safe & desirable to provide
about 20% excess capacity then circulated to provide for miscellaneous
auxiliaries & possible increase in auxiliary.
STATION TRANSFORMER
It is required to feed power to the auxiliaries during startups. This
transformer is normally rated for initial auxiliary load requirements of the
unit in typical cases; this load is of the order of 60% of the load at full
generating capacity. It is provided with on load tap change to cater to the
fluctuating voltage of the grid.
NEUTRAL GROUNDED TRANSFORMER
This transformer is connected with supply coming out of UAT in stage-2.
This is used to ground the excess voltage if occurs in the secondary of
UAT in spite of rated voltage.
BUS BAR
Bus bars generally are of high conductive aluminum conforming to IS-5082 or copper
of adequate cross section. Bus bar located in air insulated enclosures & segregated from all
other components .Bus bar is preferably cover with polyurethane.
BY PASS BUS
This bus is a backup bus which comes handy when any of the buses become faulty. When any
operation bus has fault, this bus is brought into circuit and then faulty line is removed there
by restoring healthy power line.
LIGHTENING ARRESTOR
It saves the transformer and reactor from over voltage and over currents. It grounds the
overload if there is fault on the line and it prevents the generator transformer.
WAVE TRAP
WAVETRAP is connected in series with the power (transmission) line. It blocks the high
frequency carrier waves (24 KHz to 500 KHz) and let power waves (50 Hz - 60 Hz) to pass-
through.
BREAKER
Circuit breaker is an arrangement by which we can break the circuit or flow of current. A
circuit breaker in station serves the same purpose as switch but it has many added and
complex features. The basic construction of any circuit breaker requires the separation of
contact in an insulating fluid that servers two functions:
• extinguishes the arc drawn between the contacts when circuit breaker opens.
• It provides adequate insulation between the contacts and from each contact to earth.
EARTHING ROD
Normally un-galvanized mild steel flats are used for earthling. Separate earthing electrodes are
provided to earth the lightening arrestor whereas the other equipments are earthed by connecting
their earth leads to the rid/ser of the ground mar.
CURRENT TRANSFORMER
It is essentially a step up transformer which step down the current to a known ratio. It is a type of
instrument transformer designed to provide a current in its secondary winding proportional to the
alternating current flowing in its primary.
POTENTIAL TRANSFORMER
It is essentially a step down transformer and it step downs the voltage to a known ratio.
RELAYS
Relay is a sensing device that makes your circuit ON or OFF. They detect the abnormal conditions in
the electrical circuits by continuously measuring the electrical quantities, which are different under
normal and faulty conditions, like current, voltage frequency. Having detected the fault the relay
operates to complete the trip circuit, which results in the opening of the circuit breakers
and disconnect the faulty circuit.
There are different types of relays:
Current relay
Potential relay
Electromagnetic relay
Numerical relay etc.
AIR BREAK EARTHING SWITCH
The work of this equipment comes into picture when we want to shut down the supply for
maintenance purpose. This help to neutralize the system from induced voltage from extra high
voltage. This induced power is up to 2KV in case of 400 KV lines.
INTRODUCTION
This division basically calibrates various instruments and
takes care of any faults occur in any of the auxiliaries in
the plant.
“Instrumentation can be well defined as a technology of
using instruments to measure and control the physical and
chemical properties of a material.”
C&I LABS
Control and Instrumentation Department has following
labs:
• Manometry Lab.
• Protection and Interlocks Lab.
• Automation Lab.
• Electronics Lab.
• Water Treatment Plant.
• Furnaces Safety Supervisory System Lab
THANK YOU

More Related Content

What's hot

Ntpc barh (bstpp)
Ntpc barh (bstpp)Ntpc barh (bstpp)
Ntpc barh (bstpp)
Dheeraj Kashyap
 
Ntpc badarpur summer training
Ntpc badarpur summer trainingNtpc badarpur summer training
Ntpc badarpur summer training
Shivam Jain
 
NTPC BARH, BIHAR
NTPC BARH, BIHARNTPC BARH, BIHAR
NTPC BARH, BIHAR
Aditya Empire
 
SUMMER Training report AT NTPC FOR INSTRUMENTATION (kbunl)
SUMMER Training report AT NTPC FOR INSTRUMENTATION (kbunl)SUMMER Training report AT NTPC FOR INSTRUMENTATION (kbunl)
SUMMER Training report AT NTPC FOR INSTRUMENTATION (kbunl)
guru nanak institute of technology
 
Shivesh ntpc ppt
Shivesh ntpc pptShivesh ntpc ppt
Shivesh ntpc ppt
Shivesh Sourabh
 
Power plants in bangladesh
Power plants in bangladeshPower plants in bangladesh
Power plants in bangladesh
Imran Hossain
 
Tarun Project Report On NTPC Kanti
Tarun  Project Report On NTPC KantiTarun  Project Report On NTPC Kanti
Tarun Project Report On NTPC Kanti
Tarun Kumar
 
NTPC FARIDABAD TRAINING REPORT
NTPC FARIDABAD TRAINING REPORTNTPC FARIDABAD TRAINING REPORT
NTPC FARIDABAD TRAINING REPORT
Anil Jadon
 
Lovely Amit
Lovely AmitLovely Amit
Lovely Amit
Amit Kumar
 
Pintu raj
Pintu rajPintu raj
Pintu raj
ritchaubey
 
NTPC DADRI THERMAL PLANT PPT
NTPC DADRI THERMAL PLANT PPTNTPC DADRI THERMAL PLANT PPT
NTPC DADRI THERMAL PLANT PPT
Shivam Sharma
 
My gtc presentation
My gtc presentationMy gtc presentation
My gtc presentation
mdosmankabir
 
power station in bangladesh
power station in bangladeshpower station in bangladesh
power station in bangladesh
jubaraj baidya
 
Abdul hadi rahmani presentation (2018 19)at ntpc gas power plant dadri
Abdul hadi rahmani presentation (2018 19)at ntpc gas power plant dadriAbdul hadi rahmani presentation (2018 19)at ntpc gas power plant dadri
Abdul hadi rahmani presentation (2018 19)at ntpc gas power plant dadri
Abdul Hadi Rahmani
 
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
haxxo24
 
IPGCL PPCL SUMMER TRAINING PPT
IPGCL PPCL SUMMER TRAINING PPTIPGCL PPCL SUMMER TRAINING PPT
IPGCL PPCL SUMMER TRAINING PPT
AjayBhartiya2
 
Narora Atomic Power Station (NAPS) Vocational Training Report for ECE
Narora Atomic Power Station (NAPS) Vocational Training Report for ECENarora Atomic Power Station (NAPS) Vocational Training Report for ECE
Narora Atomic Power Station (NAPS) Vocational Training Report for ECE
Kushal Varshney
 
NTPC Project KORBA(SUPER THEMAL POWER PLANT)
NTPC Project KORBA(SUPER THEMAL POWER PLANT)NTPC Project KORBA(SUPER THEMAL POWER PLANT)
NTPC Project KORBA(SUPER THEMAL POWER PLANT)Rajan Kumar Choudhary
 
Kstps Report, KOTA ,Rajasthan (India)
Kstps Report, KOTA ,Rajasthan (India)Kstps Report, KOTA ,Rajasthan (India)
Kstps Report, KOTA ,Rajasthan (India)
Ajit Singh Rajawat
 

What's hot (20)

Ntpc barh (bstpp)
Ntpc barh (bstpp)Ntpc barh (bstpp)
Ntpc barh (bstpp)
 
Ntpc badarpur summer training
Ntpc badarpur summer trainingNtpc badarpur summer training
Ntpc badarpur summer training
 
NTPC BARH, BIHAR
NTPC BARH, BIHARNTPC BARH, BIHAR
NTPC BARH, BIHAR
 
SUMMER Training report AT NTPC FOR INSTRUMENTATION (kbunl)
SUMMER Training report AT NTPC FOR INSTRUMENTATION (kbunl)SUMMER Training report AT NTPC FOR INSTRUMENTATION (kbunl)
SUMMER Training report AT NTPC FOR INSTRUMENTATION (kbunl)
 
Shivesh ntpc ppt
Shivesh ntpc pptShivesh ntpc ppt
Shivesh ntpc ppt
 
Power plants in bangladesh
Power plants in bangladeshPower plants in bangladesh
Power plants in bangladesh
 
Tarun Project Report On NTPC Kanti
Tarun  Project Report On NTPC KantiTarun  Project Report On NTPC Kanti
Tarun Project Report On NTPC Kanti
 
NTPC FARIDABAD TRAINING REPORT
NTPC FARIDABAD TRAINING REPORTNTPC FARIDABAD TRAINING REPORT
NTPC FARIDABAD TRAINING REPORT
 
Lovely Amit
Lovely AmitLovely Amit
Lovely Amit
 
Pintu raj
Pintu rajPintu raj
Pintu raj
 
NTPC DADRI THERMAL PLANT PPT
NTPC DADRI THERMAL PLANT PPTNTPC DADRI THERMAL PLANT PPT
NTPC DADRI THERMAL PLANT PPT
 
My gtc presentation
My gtc presentationMy gtc presentation
My gtc presentation
 
NTPC training
NTPC trainingNTPC training
NTPC training
 
power station in bangladesh
power station in bangladeshpower station in bangladesh
power station in bangladesh
 
Abdul hadi rahmani presentation (2018 19)at ntpc gas power plant dadri
Abdul hadi rahmani presentation (2018 19)at ntpc gas power plant dadriAbdul hadi rahmani presentation (2018 19)at ntpc gas power plant dadri
Abdul hadi rahmani presentation (2018 19)at ntpc gas power plant dadri
 
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
 
IPGCL PPCL SUMMER TRAINING PPT
IPGCL PPCL SUMMER TRAINING PPTIPGCL PPCL SUMMER TRAINING PPT
IPGCL PPCL SUMMER TRAINING PPT
 
Narora Atomic Power Station (NAPS) Vocational Training Report for ECE
Narora Atomic Power Station (NAPS) Vocational Training Report for ECENarora Atomic Power Station (NAPS) Vocational Training Report for ECE
Narora Atomic Power Station (NAPS) Vocational Training Report for ECE
 
NTPC Project KORBA(SUPER THEMAL POWER PLANT)
NTPC Project KORBA(SUPER THEMAL POWER PLANT)NTPC Project KORBA(SUPER THEMAL POWER PLANT)
NTPC Project KORBA(SUPER THEMAL POWER PLANT)
 
Kstps Report, KOTA ,Rajasthan (India)
Kstps Report, KOTA ,Rajasthan (India)Kstps Report, KOTA ,Rajasthan (India)
Kstps Report, KOTA ,Rajasthan (India)
 

Similar to ntpc ppt

Ashwani kumar
Ashwani kumarAshwani kumar
Ashwani kumar
Ashwani Kumar
 
rough.pptx
rough.pptxrough.pptx
rough.pptx
virat217995
 
Presentation 2014
Presentation 2014Presentation 2014
Presentation 2014
pinki199319
 
Report on 220kv substation at Jassure
Report on 220kv substation at JassureReport on 220kv substation at Jassure
Report on 220kv substation at Jassure
Shuvam Pathania
 
Ashish.pptx
Ashish.pptxAshish.pptx
Ashish.pptx
AkhilKanyal1
 
BHEL Vocational Training
BHEL Vocational TrainingBHEL Vocational Training
BHEL Vocational TrainingRehan Fazal
 
400 kv Heerapura gss ppt by ishan pdf
400 kv Heerapura gss ppt by ishan pdf 400 kv Heerapura gss ppt by ishan pdf
400 kv Heerapura gss ppt by ishan pdf
Ishan Khandelwal
 
Substation Training presentation
Substation Training presentationSubstation Training presentation
Substation Training presentation
Kamal Mittal
 
Summer Training presentation on 132/33 KV sub-station Minto park, Allahabad
Summer Training presentation on 132/33 KV sub-station Minto park, AllahabadSummer Training presentation on 132/33 KV sub-station Minto park, Allahabad
Summer Training presentation on 132/33 KV sub-station Minto park, Allahabad
Sudhir Cement Industries Pvt. Ltd. Meerut
 
Chic export company_catalogue
Chic export company_catalogueChic export company_catalogue
Chic export company_catalogue
Unicorn Chemicals Co.
 
ELECTRIC SUB-STATION IN BRIEF
ELECTRIC SUB-STATION IN BRIEFELECTRIC SUB-STATION IN BRIEF
ELECTRIC SUB-STATION IN BRIEF
jang041
 
Gss ppt by kanhaiya
Gss ppt  by kanhaiyaGss ppt  by kanhaiya
Gss ppt by kanhaiya
imkanhaiyalal
 
Sharavati receiving station
Sharavati  receiving stationSharavati  receiving station
Sharavati receiving station
H.C.Naveen Kumar
 
Electrical substation general_equipments
Electrical substation general_equipmentsElectrical substation general_equipments
Electrical substation general_equipments
Eman Dacanay
 
Introduction to switchgear
Introduction to switchgearIntroduction to switchgear
Introduction to switchgear
Adnan Sayed
 
Presentation training
Presentation trainingPresentation training
Presentation trainingSrajan Raj
 
Substation presentation by ram
Substation presentation by ramSubstation presentation by ram
Substation presentation by ram
GRBabu Naidu
 
220 kV GSS Mansarovar Jaipur (RVPNL) Training PPT SM54
220 kV GSS Mansarovar Jaipur (RVPNL) Training PPT SM54220 kV GSS Mansarovar Jaipur (RVPNL) Training PPT SM54
220 kV GSS Mansarovar Jaipur (RVPNL) Training PPT SM54
Subhash Mahla
 
POWER DISTRIBUTION 2.docx
POWER DISTRIBUTION 2.docxPOWER DISTRIBUTION 2.docx
POWER DISTRIBUTION 2.docxJeffrey Dorsey
 

Similar to ntpc ppt (20)

Ashwani kumar
Ashwani kumarAshwani kumar
Ashwani kumar
 
rough.pptx
rough.pptxrough.pptx
rough.pptx
 
Presentation 2014
Presentation 2014Presentation 2014
Presentation 2014
 
Report on 220kv substation at Jassure
Report on 220kv substation at JassureReport on 220kv substation at Jassure
Report on 220kv substation at Jassure
 
ntpc
ntpcntpc
ntpc
 
Ashish.pptx
Ashish.pptxAshish.pptx
Ashish.pptx
 
BHEL Vocational Training
BHEL Vocational TrainingBHEL Vocational Training
BHEL Vocational Training
 
400 kv Heerapura gss ppt by ishan pdf
400 kv Heerapura gss ppt by ishan pdf 400 kv Heerapura gss ppt by ishan pdf
400 kv Heerapura gss ppt by ishan pdf
 
Substation Training presentation
Substation Training presentationSubstation Training presentation
Substation Training presentation
 
Summer Training presentation on 132/33 KV sub-station Minto park, Allahabad
Summer Training presentation on 132/33 KV sub-station Minto park, AllahabadSummer Training presentation on 132/33 KV sub-station Minto park, Allahabad
Summer Training presentation on 132/33 KV sub-station Minto park, Allahabad
 
Chic export company_catalogue
Chic export company_catalogueChic export company_catalogue
Chic export company_catalogue
 
ELECTRIC SUB-STATION IN BRIEF
ELECTRIC SUB-STATION IN BRIEFELECTRIC SUB-STATION IN BRIEF
ELECTRIC SUB-STATION IN BRIEF
 
Gss ppt by kanhaiya
Gss ppt  by kanhaiyaGss ppt  by kanhaiya
Gss ppt by kanhaiya
 
Sharavati receiving station
Sharavati  receiving stationSharavati  receiving station
Sharavati receiving station
 
Electrical substation general_equipments
Electrical substation general_equipmentsElectrical substation general_equipments
Electrical substation general_equipments
 
Introduction to switchgear
Introduction to switchgearIntroduction to switchgear
Introduction to switchgear
 
Presentation training
Presentation trainingPresentation training
Presentation training
 
Substation presentation by ram
Substation presentation by ramSubstation presentation by ram
Substation presentation by ram
 
220 kV GSS Mansarovar Jaipur (RVPNL) Training PPT SM54
220 kV GSS Mansarovar Jaipur (RVPNL) Training PPT SM54220 kV GSS Mansarovar Jaipur (RVPNL) Training PPT SM54
220 kV GSS Mansarovar Jaipur (RVPNL) Training PPT SM54
 
POWER DISTRIBUTION 2.docx
POWER DISTRIBUTION 2.docxPOWER DISTRIBUTION 2.docx
POWER DISTRIBUTION 2.docx
 

ntpc ppt

  • 1. INDUSTRIAL TRAINING 2013 NTPC LIMITED BADARPUR THERMAL POWER STATION MADE BY : Jatan Singh Soni 11BEE0061
  • 2.
  • 3. Training at BTPS I was appointed to do 4 week training at this esteemed organization from 3rd June to 4th July, 2013. I was assigned to visit various divisions of the plant, which were: Electrical Maintenance Department I (EMD-I) Electrical Maintenance Department II (EMD-II) Control and Instrumentation Department (C&I) It was really amazing to see the power plant and learn how electricity, which is one of our daily requirements of life, is produced.
  • 4. INDEX • OPERATION OF POWER PLANT • PARTS OF A POWER PLANT • VARIOUS CYCLES AT POWER STATION • ELECTRICAL MAINTENANCE DEPARTMENT-I • ELECTRICAL MAINETNANCE DEPARTMENT-II • CONTROL AND INSTRUMENTATION
  • 5. The basic steps in the generation of electricity from coal involves following steps: • Coal to steam – Steam Generator or Boiler • Steam to mechanical power - Steam Turbine • Mechanical power to electrical power – Electric Generator
  • 7. PARTS OF A POWER PLANT 1. Cooling tower 2. Cooling water pump 3. Transmission line (3-phase) 4. Unit transformer (3-phase) 5. Electric generator (3-phase) 6. Low pressure turbine 7. Condensate extraction pump 8. Condenser 9. Intermediate pressure turbine 10. Steam governor valve 11. High pressure turbine 12. Deaerator 13. Feed heater 14. Coal conveyor 15. Coal hopper 16. Pulverized fuel mill 17. Boiler drum 18. Ash hopper 19. Super heater 20. Forced draught fan 21. Reheater 22. Air intake 23. Economizer 24. Air preheater 25. Precipitator 26. Induced draught fan 27. Flue Gas
  • 8.
  • 9.
  • 10.
  • 11.
  • 12.
  • 13.
  • 14.
  • 15.
  • 16.
  • 17.
  • 18.
  • 19.
  • 20. THE EQUIPMENTS THAT NORMALLY FALL IN THIS CATEGORY ARE:-ISOLATOR • Isolator cannot operate unless breaker is open • Bus 1 and bus 2 isolators cannot be closed simultaneously • The interlock can be bypass in the event of closing of bus coupler breaker. • No isolator can operate when the corresponding earth switch is on SWITCHING ISOLATOR • Switching isolator is capable of: • Interrupting charging current • Interrupting transformer magnetizing current • Load transformer switching. Its main application is in connection with the transformer feeder as the unit makes it possible to switch gear one transformer while the other is still on load. CIRCUIT BREAKER • One which can make or break the circuit on load and even on faults is referred to as circuit breakers. This equipment is the most important and is heavy duty equipment mainly utilized for protection of various circuits and operations on load. Normally circuit breakers installed are accompanied by isolators. LOAD BREAK SWITCHES • These are those interrupting devices which can make or break circuits. These are normally on same circuit, which are backed by circuit breakers EARTH SWITCHES • Devices which are used normally to earth a particular system, to avoid any accident happening due to induction on account of live adjoining circuits. These equipments do not handle any appreciable current at all. Apart from this equipment there are a number of relays etc. which are used in switchgear.
  • 21.
  • 22.
  • 24.
  • 25.
  • 26. RATINGS OF THE GENERATORS USED • Turbo generator 100MW • TURBO GENERATOR 210 MW • • The 100 MW generator generates 10.75 KV and 210 MW generates 15.75 KV. The voltage is stepped up to 220 KV with the help of generator transformer and is connected to the grid. • The voltage is stepped down to 6.6 KV with the help of UNIT AUXILLARY TRANSFORMER (UAT) and this voltage is used to drive the HT motors. The voltage is further stepped down to 415 V and then to 220 V and this voltage is used to drive Lt Motors.
  • 27.
  • 28. COOLING OF TRANSFORMERS OF LARGE MVA As size of transformer becomes large, the rate of the oil circulating becomes insufficient to dissipate all the heat produced & artificial means of increasing the circulation by electric pumps. In very large transformers, special coolers with water circulation may have to be employed. TYPES OF COOLING: Air cooling Air Natural (AN) Air Forced (AF) Oil immersed cooling Oil Natural Air Natural (ONAN) Oil Natural Air Forced (ONAF) Oil Forced Air Natural (OFAN) Oil Forced Air Forced (OFAF) Oil immersed Water cooling Oil Natural Water Forced (ONWF) Oil Forced Water Forced (OFWF)
  • 29. UNIT AUXILIARY TRANSFORMER (UAT) Unit I & V- 12.5 MVA The UAT draws its input from the main bus-ducts. The total KVA capacity of UAT required can be determined by assuming 0.85 power factor & 90% efficiency for total auxiliary motor load. It is safe & desirable to provide about 20% excess capacity then circulated to provide for miscellaneous auxiliaries & possible increase in auxiliary. STATION TRANSFORMER It is required to feed power to the auxiliaries during startups. This transformer is normally rated for initial auxiliary load requirements of the unit in typical cases; this load is of the order of 60% of the load at full generating capacity. It is provided with on load tap change to cater to the fluctuating voltage of the grid. NEUTRAL GROUNDED TRANSFORMER This transformer is connected with supply coming out of UAT in stage-2. This is used to ground the excess voltage if occurs in the secondary of UAT in spite of rated voltage.
  • 30.
  • 31. BUS BAR Bus bars generally are of high conductive aluminum conforming to IS-5082 or copper of adequate cross section. Bus bar located in air insulated enclosures & segregated from all other components .Bus bar is preferably cover with polyurethane. BY PASS BUS This bus is a backup bus which comes handy when any of the buses become faulty. When any operation bus has fault, this bus is brought into circuit and then faulty line is removed there by restoring healthy power line. LIGHTENING ARRESTOR It saves the transformer and reactor from over voltage and over currents. It grounds the overload if there is fault on the line and it prevents the generator transformer. WAVE TRAP WAVETRAP is connected in series with the power (transmission) line. It blocks the high frequency carrier waves (24 KHz to 500 KHz) and let power waves (50 Hz - 60 Hz) to pass- through. BREAKER Circuit breaker is an arrangement by which we can break the circuit or flow of current. A circuit breaker in station serves the same purpose as switch but it has many added and complex features. The basic construction of any circuit breaker requires the separation of contact in an insulating fluid that servers two functions: • extinguishes the arc drawn between the contacts when circuit breaker opens. • It provides adequate insulation between the contacts and from each contact to earth.
  • 32. EARTHING ROD Normally un-galvanized mild steel flats are used for earthling. Separate earthing electrodes are provided to earth the lightening arrestor whereas the other equipments are earthed by connecting their earth leads to the rid/ser of the ground mar. CURRENT TRANSFORMER It is essentially a step up transformer which step down the current to a known ratio. It is a type of instrument transformer designed to provide a current in its secondary winding proportional to the alternating current flowing in its primary. POTENTIAL TRANSFORMER It is essentially a step down transformer and it step downs the voltage to a known ratio. RELAYS Relay is a sensing device that makes your circuit ON or OFF. They detect the abnormal conditions in the electrical circuits by continuously measuring the electrical quantities, which are different under normal and faulty conditions, like current, voltage frequency. Having detected the fault the relay operates to complete the trip circuit, which results in the opening of the circuit breakers and disconnect the faulty circuit. There are different types of relays: Current relay Potential relay Electromagnetic relay Numerical relay etc. AIR BREAK EARTHING SWITCH The work of this equipment comes into picture when we want to shut down the supply for maintenance purpose. This help to neutralize the system from induced voltage from extra high voltage. This induced power is up to 2KV in case of 400 KV lines.
  • 33.
  • 34. INTRODUCTION This division basically calibrates various instruments and takes care of any faults occur in any of the auxiliaries in the plant. “Instrumentation can be well defined as a technology of using instruments to measure and control the physical and chemical properties of a material.” C&I LABS Control and Instrumentation Department has following labs: • Manometry Lab. • Protection and Interlocks Lab. • Automation Lab. • Electronics Lab. • Water Treatment Plant. • Furnaces Safety Supervisory System Lab