SlideShare a Scribd company logo
S.S.A.S.I.T
GTU
1
2
Timbering in trenches
Control of Ground
water in excavation
types of
scaffoldings
shoring, underpinningCoffer Dams
Diaphragm
Walls
Demolition of
structures
3
 TIMBERING IN TRENCHES
 A trench is a type of excavation or depression in the ground that is
generally deeper than it is wide (as opposed to a wider gully, or ditch),
and narrow compared with its length (as opposed to a simple hole).
 When the depth of trench is large, or when the sub-soil is loose, the
sides of the trench may cave in.
 The problem can be solved by adopting a suitable method of
timbering. Timbering of trenches, sometimes also known as shoring
consists of providing timber planks or boards and struts to give
temporary support to the sides of the trench.
4
5
6
7
8
Timbering of deep
trenches can be done with
the help of the following
methods:
1. Stay bracing.
2. Box sheeting
3. Vertical sheeting
4. Runner system
5. Sheet piling.
1. Stay bracing. This method is used for supporting the sides or a
bench excavated in fairly firm soil, when the depth of excavation does
not exceed about 2 metres. The method consists of placing vertical
sheets (called sheathing) or polling boards opposite each other against
the two walls of the trench and holding them in position by one or two
rows of struts.
THE POLLING BOARDS
width 200 mm
thickness of 44 to 50 mm.
STRUTS
1OO x 100 mm for trench up to 2 m width
200 x 200 mm for trench up to 4 m width.
9
10
11
2. Box sheeting. This method is adopted in loose soils, when the depth
of excavation does not exceed 4 metres.
Its consisting of vertical sheets placed very near to each other (some
times touching each other) and keeping them in position by longitudinal
rows (usually two) of Wales. Struts are then provided across the Wales.
Another system of box sheeting, shown in Fig. 2.32(b), is adopted for
very loose soils. In this system, the sheeting is provided longitudinally,
and they are supported by vertical Wales and horizontal struts.
If the height is more, braces are also provided along with struts.
12
Fig. 2.32 (a) for loose soil
13
Fig. 2.32 (b) very loose soil
14
Fig. 2 (b) very loose soil
Fig. 2 (a) loose soil
15
3. Vertical sheeting.
 This system is adopted for Deep trenches (up to 10 m depth) in soft
ground.
 The method is similar to the box sheeting except that the excavation is
carried out in stages and at the end of each stage, an offset is
provided, so that the width of the trench goes on decreasing as the
depth increases.
 Each stage is limited to about 3 m in height and the offset may vary
from 25 to 50 cm per stage.
 For each stage, separate vertical sheeting, supported by horizontal
wailings and struts are provided.
16
stage height 3m
offset
17
4. Sheet piling
This method is adopted when
(i) soil to be excavated is soft or loose
(ii) depth of excavation is large
(iii) width of trench is also large and
(iv) there is sub-soil water.
Sheet piles are designed to resist lateral earth pressure. These are driven
in the ground by mechanical means (pile driving equipment). They can be
used for excavating to a very large depth.
18
19
20
21
 Shoring is the type of construction of a temporary structure to
support temporarily an unsafe structure.
 These support walls, supporting a building, structure, or trench with
shores (props) when in danger of collapse or during repairs or
alterations.
 Shoring comes from shore (props)
 a timber or metal prop use for shoring
 Shoring may be vertical, angled, or horizontal.
SHORING
22
THEY CAN BE USED UNDER…..
 When walls bulge out
 When walls crack due to unequal settlement of foundation and
repairs are to be carried out to the cracked wall.
 When an adjacent structure needs pulling down.
 When openings are to be newly made or enlarged in a wall.
 Shoring is used to support the beams and floors in a building while a
column or wall is removed.
 In this situation vertical supports are used as a temporary
replacement for the building columns or walls.
23
24
Raking Shores consist of one or more timbers sloping between the face of the
structure to be supported and the ground.
The most effective support is given if the raker meets the wall at an angle of 60 to 70
degrees.
A wall-plate is typically used to increase the area of support.
Its consists of the following components:
•Rakers or inclined member
•Wall plate
•Needles
•Cleats
•Bracing
•Sole plate
Raking Shore
25
The following points are to be kept in view for the use of the raking shores:
Rakers are to be inclined in the ground at 45⁰.
However the angle may be between 45 ⁰ and 75 ⁰.
Rakers should be properly braced at intervals.
The size of the rakers is to be decided on the basis of anticipated thrust from the
wall.
The sole plate should be properly embedded into the ground on an inclination and
should be of proper section and size.
Edges on raker should not be used on sole plates since they are likely to give way
under vibrations that are likely to occur.
26
27
28
29
30
31
 It is also known as horizontal shores
 It is a system of providing temporary supports to the party walls of the two
buildings where the intermediate building is to be pulled down and rebuilt.
 All types of arrangements of supporting the unsafe structure in which the shores do
not reach the ground come under this category.
 In this type, horizontal supports are provided for supporting temporarily the
parallel walls of the two adjacent buildings, which may tend to collapse or
damage when one of the intermediate buildings has to be pulled down and
rebuilt.
 The maximum distance of about 10 meter between the parallel walls can be
supported by single flying shore. For a distance more than 10 m, a double flying
shore, having a trussed form-work is employed
FLYING SHORES
32
33
34
35
36
37
38
39
40
41
This is the system of shoring which is used to render vertical support to
walls and roofs, floors, etc when the lower part of a wall has been
removed for the purpose of providing an opening in the wall or to
rebuild a defective load bearing wall in a structure.
The dead shore consists of an arrangement of beams and posts which
are required to support the weight of the structure above and
transfer same to the ground on firm foundation below.
DEAD SHORES
 When opening in the wall are to be made, holes are
cut in the wall at such a height as to allow sufficient
space for insertion of the beam or girder that will
be provided permanently to carry the weight of the
structure above.
 Distance at which the holes are cut depends upon
the type of masonry and it varies from 1.2m to
1.8m centre.
 Beams called needles are placed in the holes and are
supported by vertical props called dead shores at
their ends on either side of the wall.
 The needles may be of timber or steel and are of
sufficient section to carry the load above.
42
43
44
45
shoring
46
shoring
SHORING
47
SHORING
48
SHORING
49
SHORING
50
SHORING
51
52
UNDERPINNING
The process of providing a new foundation below an existing
foundation of an existing foundation, without dangering the stability
of an existing structure.
The method of underpinning help to strengthen the foundation of an
existing building or any other infrastructure. These involve
installation of permanent or temporary support to an already held
foundation so that additional depth and bearing capacity is
achieved.
CONDITION OF UNDERPINNING
 The original foundation is simply not strong or stable enough.
 The usage of the structure has changed.
 The properties of the soil supporting the foundation may have changed (possibly
through subsidence) or were mischaracterized during design.
 To increase the depth or load capacity of existing foundations to support the addition
of another storey to the building (above or below grade).
 Earthquake, flood, drought or other natural causes have caused the structure to
move, thereby requiring stabilization of foundation soils.
53
54
1. Mass Concrete Underpinning Method (Pit Method)
Mass concrete underpinning method is the traditional method of
underpinning, as it has been followed by centuries. The method
involves extending the old foundation till it reaches a stable stratum.
The soil below the existing foundation is excavated in a controlled
manner through stages or pins. When strata suitable is reached, the
excavation is filled with concrete and kept for curing, before next
excavation starts.
in order to transfer the load from old foundation to new one, a new
pin is provided by means of placing dry sand-cement pack. This is a
low-cost method suitable for the shallow foundation.
Stages divided into sections of 1.2 to 1.5 m lengths
DIFFERENT METHODS OF UNDERPINNING
UNDERPINNING CAN BE MADE IN VARIOUS WAYS, BUT TWO OF THEM ARE MOSTLY USED
*PIT METHOD
*PILE METHOD
Pit method Pile Method
55
56
By pit
57
If an interior strong column exists, or if the
foundation is to be extended only to one side,
cantilever needle beams may be used in place of
central needle beam.
A jack is placed between the column and wall.
58
Underpinning By Cantilever Needle Beam Method
Figure represents the arrangement of cantilever pit method of
underpinning, which is an extension of pit method.
If the foundation has to be extended only to one side and the plan
possess a stronger interior column, this method can be used for
underpinning.
Advantages of Cantilever Needle Beam Method:
•Faster than traditional method
•One side access only
•High load carrying capability
Disadvantages:
•Digging found uneconomical when existing foundation is deep
59
60
Pile Method
 In this method, piles are driven on adjacent sides of the wall that
supports the weak foundation.
 A needle or pin penetrates through the wall that is in turn
connected to the piles as shown in figure.
 These needles behave like pile caps.
 Use where Settlement in soil due to water clogging or clayey
nature can be treated by this method.
61
62
underpinning
63
underpinning
64
65
SCAFFOLDING
66
 Scaffolding is a temporary frame or structure used to support people and material
in the construction or repair of buildings and other large structures.
 It is used when height of wall or column or other structural member of a
building exceeds about 1.5m.
 Scaffolding is a temporary structure to support the original structure as well as
workmen used it as a platform to carry on the construction works.
 Types of scaffolding varies with the type of construction work.
 Scaffolding is made up of timber or steel.
 It should be stable and strong to support workmen and other construction
material placed on it.
67
COMPONENT
Standards
Ledgers
Braces
Putlogs
TransomsBridle
Boarding
Guard rail
Toe
board
68
Standards:- These are vertical members of the frame work, supporting on
the ground or embedded into the ground.
Ledgers:- these are the horizontal members, running parallel to the wall.
Braces:- These are diagonal members fixed on standards.
Putlogs:- These are the transverse members, placed at right angles to the
wall with one end supported on ledgers and other end on the wall.
Boarding:- These are horizontal platform to support workmen & material;
these are supported on putlogs.
Guard Rail:- This is a rail, provided like a ledger, at the working level.
69
70
71
72
Single scaffolding or brick layers scaffolding
Double scaffolding or mason’s scaffolding
Cantilever or needle scaffolding
Suspended scaffolding
Trestle scaffolding
Steel scaffolding
Patented scaffolding
1. SINGLE SCAFFOLDING OR BRICK
LAYERS SCAFFOLDING
73
74
7575
Single scaffolding is generally used for brick masonry and is also called
as brick layer’s scaffolding.
Single scaffolding consists of standards, ledgers, putlogs etc., which is
parallel to the wall at a distance of about 1.2 m.
Distance between the standards is about 2 to 2.5 m.
Ledgers connect the standards at vertical interval of 1.2 to 1.5 m.
Putlogs are taken out from the hole left in the wall to one end of the
ledgers.
Putlogs are placed at an interval of 1.2 to 1.5 m.
Single Scaffolding
76
2. DOUBLE SCAFFOLDING OR
MASON’S SCAFFOLDING
77
78
79
Double Scaffolding
 Double Scaffolding is generally used for stone masonry so, it is also
called as mason’s scaffolding.
 In stone walls, it is hard to make holes in the wall to support
putlogs. So, two rows of scaffolding is constructed to make it
strong.
 The first row is 20 – 30 cm away from the wall and the other one
is 1m away from the first row.
 Then putlogs are placed which are supported by the both frames.
 To make it more strong rakers and cross braces are provided.
 This is also called as independent scaffolding.
80
3. CANTILEVER OR NEEDLE
SCAFFOLDING
81
82
CANTILEVER SCAFFOLDING
This a type of scaffolding the standards are supported on series of
needles and these needles are taken out through holes in the wall.
This is called single frame type scaffolding.
In the other type needles are strutted inside the floors through the
openings and this is called independent or double frame type
scaffolding.
Care should be taken while construction of cantilever scaffolding.
Generally cantilever scaffoldings are used under conditions such as
•When the ground does not having the capacity to support standards
•When the Ground near the wall is Need to be free from traffic.
83
84
 Light weight scaffolding used for repair works like painting, pointing
etc.
 The working platform is suspended from roofs by means of wire
ropes or chains.
 Platform can be raised or lowered at any desired level.
4.SUSPENDED SCAFFOLDING
85
86
This is also used for repair works inside the room,
up to height of 5m.
The working platform is supported on the top of
movable contrivances like tripods, ladders may be
mounted on wheels.
In Trestle scaffolding, the working platform is
supported on movable tripods or ladders. This is
generally used for work inside the room, such as
paintings, repairs etc., up to a height of 5m.
5.TRESTLE SCAFFOLDING
87
88
Wooden members are replaced by steel tubes and rope lashings are
replaced by steel couplets or fittings.
Such scaffolding can be erected and dismantled rapidly.
It has greater strength, greater durability and higher fire resistance.
Can be used for stone and brick masonry construction.
6.STEEL SCAFFOLDING
89
90
91
Timbering in trenches
Control of Ground
water in excavation
types of
scaffoldings
shoring, underpinningCoffer Dams
Diaphragm
Walls
Demolition of
structures
92

More Related Content

What's hot

What is post tensioning
What is post tensioningWhat is post tensioning
What is post tensioning
Charlie Gupta
 
Chapter 3 shallow foundations
Chapter 3 shallow foundationsChapter 3 shallow foundations
Chapter 3 shallow foundations
KHUSHBU SHAH
 
Retaining wall
 Retaining wall  Retaining wall
Retaining wall
kamariya keyur
 
One Way Slabs
One Way SlabsOne Way Slabs
One Way Slabs
Gaurang Prajapati
 
Types of masonry and its failure types
Types of masonry and its failure typesTypes of masonry and its failure types
Types of masonry and its failure types
Udayram Patil
 
Final report
Final reportFinal report
Final report
Sumeet Divatagi
 
Static pile capacity formula (usefulsearch.org) (useful search)
Static pile capacity formula (usefulsearch.org)  (useful search)Static pile capacity formula (usefulsearch.org)  (useful search)
Static pile capacity formula (usefulsearch.org) (useful search)
Make Mannan
 
Chapter27(1)
Chapter27(1)Chapter27(1)
Chapter27(1)
Kashif Khan
 
Prefabrication
PrefabricationPrefabrication
Prefabrication
Bilal Ansari
 
Types of foundations
Types of foundationsTypes of foundations
Types of foundations
DeenaThayalan T
 
Foundations
FoundationsFoundations
Foundations
Aglaia Connect
 
Centering ppt
Centering pptCentering ppt
Centering ppt
Ayini Richard
 
Defects and remedies of building
Defects and remedies of buildingDefects and remedies of building
Defects and remedies of building
toshi gupta
 
UNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURES
UNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURESUNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURES
UNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURES
Venkateswaran S
 
How do Beam-Column Joints in RC Buildings Resist Earthquakes?
How do Beam-Column Joints in RC Buildings Resist Earthquakes?How do Beam-Column Joints in RC Buildings Resist Earthquakes?
How do Beam-Column Joints in RC Buildings Resist Earthquakes?
Malay Patel
 
PLANNING AND DESIGNING OF PRECAST STRUCTURES
PLANNING AND DESIGNING OF PRECAST STRUCTURESPLANNING AND DESIGNING OF PRECAST STRUCTURES
PLANNING AND DESIGNING OF PRECAST STRUCTURES
Ajit Sabnis
 
Presentation on Expansion Joint
Presentation on Expansion JointPresentation on Expansion Joint
Presentation on Expansion Joint
Rais Uddin
 
SCAFFOLDING SHORING & UNDERPINNING
SCAFFOLDING SHORING & UNDERPINNINGSCAFFOLDING SHORING & UNDERPINNING
SCAFFOLDING SHORING & UNDERPINNING
VISHNU VIJAYAN
 
7 english 2 2.5 brick thick bond
7 english 2 2.5 brick thick bond7 english 2 2.5 brick thick bond
7 english 2 2.5 brick thick bondVartika khandelwal
 

What's hot (20)

What is post tensioning
What is post tensioningWhat is post tensioning
What is post tensioning
 
Chapter 3 shallow foundations
Chapter 3 shallow foundationsChapter 3 shallow foundations
Chapter 3 shallow foundations
 
Retaining wall
 Retaining wall  Retaining wall
Retaining wall
 
One Way Slabs
One Way SlabsOne Way Slabs
One Way Slabs
 
Types of masonry and its failure types
Types of masonry and its failure typesTypes of masonry and its failure types
Types of masonry and its failure types
 
Final report
Final reportFinal report
Final report
 
Static pile capacity formula (usefulsearch.org) (useful search)
Static pile capacity formula (usefulsearch.org)  (useful search)Static pile capacity formula (usefulsearch.org)  (useful search)
Static pile capacity formula (usefulsearch.org) (useful search)
 
Chapter27(1)
Chapter27(1)Chapter27(1)
Chapter27(1)
 
Prefabrication
PrefabricationPrefabrication
Prefabrication
 
Types of foundations
Types of foundationsTypes of foundations
Types of foundations
 
Foundations
FoundationsFoundations
Foundations
 
Centering ppt
Centering pptCentering ppt
Centering ppt
 
Defects and remedies of building
Defects and remedies of buildingDefects and remedies of building
Defects and remedies of building
 
UNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURES
UNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURESUNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURES
UNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURES
 
How do Beam-Column Joints in RC Buildings Resist Earthquakes?
How do Beam-Column Joints in RC Buildings Resist Earthquakes?How do Beam-Column Joints in RC Buildings Resist Earthquakes?
How do Beam-Column Joints in RC Buildings Resist Earthquakes?
 
PLANNING AND DESIGNING OF PRECAST STRUCTURES
PLANNING AND DESIGNING OF PRECAST STRUCTURESPLANNING AND DESIGNING OF PRECAST STRUCTURES
PLANNING AND DESIGNING OF PRECAST STRUCTURES
 
Presentation on Expansion Joint
Presentation on Expansion JointPresentation on Expansion Joint
Presentation on Expansion Joint
 
SCAFFOLDING SHORING & UNDERPINNING
SCAFFOLDING SHORING & UNDERPINNINGSCAFFOLDING SHORING & UNDERPINNING
SCAFFOLDING SHORING & UNDERPINNING
 
7 english 2 2.5 brick thick bond
7 english 2 2.5 brick thick bond7 english 2 2.5 brick thick bond
7 english 2 2.5 brick thick bond
 
foundation
foundationfoundation
foundation
 

Similar to BCT - Module 5 special work

Chapter 11 temporary works
Chapter 11 temporary worksChapter 11 temporary works
Chapter 11 temporary works
KHUSHBU SHAH
 
Temporary Work in Building Construction
Temporary Work in Building ConstructionTemporary Work in Building Construction
Temporary Work in Building Construction
Er.Karan Chauhan
 
Notes on introduction and design ofTEMPORARY WORKS (BTECH).pdf
Notes on introduction and design ofTEMPORARY WORKS (BTECH).pdfNotes on introduction and design ofTEMPORARY WORKS (BTECH).pdf
Notes on introduction and design ofTEMPORARY WORKS (BTECH).pdf
VICTOR A. KIPLAGAT
 
ABC 1st Week(2hrs
ABC 1st Week(2hrsABC 1st Week(2hrs
ABC 1st Week(2hrs
pal892241
 
Unit iii braced_cuts
Unit iii braced_cutsUnit iii braced_cuts
Unit iii braced_cutsGimmick
 
Shoring.pdf
Shoring.pdfShoring.pdf
Shoring.pdf
steveshiku1233
 
Shoring
ShoringShoring
Braced cut in deep excavation
Braced cut in deep excavationBraced cut in deep excavation
Braced cut in deep excavationYogesh Pandey
 
Construction of substructure
Construction of substructureConstruction of substructure
Construction of substructure
guasiya
 
Braced cuts in deep excavation
Braced cuts in deep excavationBraced cuts in deep excavation
Braced cuts in deep excavation
Rakesh Reddy
 
Temporary works
Temporary worksTemporary works
Temporary works
Aditya Mistry
 
Diaphragm Wall
Diaphragm WallDiaphragm Wall
Diaphragm Wall
Things Simplified
 
Floor and wall ties
Floor and wall tiesFloor and wall ties
Floor and wall ties
SaratMishra4
 
Deep excavations
Deep excavationsDeep excavations
Deep excavations
Bhargava Ram
 
CONSTRUCTION OF MULTI STOREY BUILDING.pptx
CONSTRUCTION OF MULTI STOREY BUILDING.pptxCONSTRUCTION OF MULTI STOREY BUILDING.pptx
CONSTRUCTION OF MULTI STOREY BUILDING.pptx
VenkataRamana38198
 
Foundation Rehabilitation
Foundation RehabilitationFoundation Rehabilitation
Foundation Rehabilitation
Aani4
 
foundation.pptx
foundation.pptxfoundation.pptx
foundation.pptx
AnshSingh813445
 
Chapter 1 foundation
Chapter  1 foundationChapter  1 foundation
Chapter 1 foundation
karthikeyan kumarasamy
 

Similar to BCT - Module 5 special work (20)

Chapter 11 temporary works
Chapter 11 temporary worksChapter 11 temporary works
Chapter 11 temporary works
 
Temporary Work in Building Construction
Temporary Work in Building ConstructionTemporary Work in Building Construction
Temporary Work in Building Construction
 
Notes on introduction and design ofTEMPORARY WORKS (BTECH).pdf
Notes on introduction and design ofTEMPORARY WORKS (BTECH).pdfNotes on introduction and design ofTEMPORARY WORKS (BTECH).pdf
Notes on introduction and design ofTEMPORARY WORKS (BTECH).pdf
 
ABC 1st Week(2hrs
ABC 1st Week(2hrsABC 1st Week(2hrs
ABC 1st Week(2hrs
 
Unit iii braced_cuts
Unit iii braced_cutsUnit iii braced_cuts
Unit iii braced_cuts
 
Shoring.pdf
Shoring.pdfShoring.pdf
Shoring.pdf
 
Shoring
ShoringShoring
Shoring
 
Braced cut in deep excavation
Braced cut in deep excavationBraced cut in deep excavation
Braced cut in deep excavation
 
Construction of substructure
Construction of substructureConstruction of substructure
Construction of substructure
 
Braced cuts in deep excavation
Braced cuts in deep excavationBraced cuts in deep excavation
Braced cuts in deep excavation
 
Temporary works
Temporary worksTemporary works
Temporary works
 
Diaphragm Wall
Diaphragm WallDiaphragm Wall
Diaphragm Wall
 
Theory of structures
Theory of structuresTheory of structures
Theory of structures
 
Floor and wall ties
Floor and wall tiesFloor and wall ties
Floor and wall ties
 
Deep excavations
Deep excavationsDeep excavations
Deep excavations
 
Group no 9
Group no 9Group no 9
Group no 9
 
CONSTRUCTION OF MULTI STOREY BUILDING.pptx
CONSTRUCTION OF MULTI STOREY BUILDING.pptxCONSTRUCTION OF MULTI STOREY BUILDING.pptx
CONSTRUCTION OF MULTI STOREY BUILDING.pptx
 
Foundation Rehabilitation
Foundation RehabilitationFoundation Rehabilitation
Foundation Rehabilitation
 
foundation.pptx
foundation.pptxfoundation.pptx
foundation.pptx
 
Chapter 1 foundation
Chapter  1 foundationChapter  1 foundation
Chapter 1 foundation
 

More from Shree Swami atmanand saraswati inst. of technology, surat

INFRASTRUCTURE FOR SMART CITIES_MOD 2_planning for smart cities
INFRASTRUCTURE FOR SMART CITIES_MOD 2_planning for smart citiesINFRASTRUCTURE FOR SMART CITIES_MOD 2_planning for smart cities
INFRASTRUCTURE FOR SMART CITIES_MOD 2_planning for smart cities
Shree Swami atmanand saraswati inst. of technology, surat
 
INFRASTRUCTURE FOR SMART CITIES_MOD 3_Intelligent transport systems
INFRASTRUCTURE FOR SMART CITIES_MOD 3_Intelligent transport systemsINFRASTRUCTURE FOR SMART CITIES_MOD 3_Intelligent transport systems
INFRASTRUCTURE FOR SMART CITIES_MOD 3_Intelligent transport systems
Shree Swami atmanand saraswati inst. of technology, surat
 
Sem 5 mod-1 disaster management introduction (CIVIL, ELE, MECH, EC, COMP)
Sem 5 mod-1 disaster management introduction (CIVIL, ELE, MECH, EC, COMP)Sem 5 mod-1 disaster management introduction (CIVIL, ELE, MECH, EC, COMP)
Sem 5 mod-1 disaster management introduction (CIVIL, ELE, MECH, EC, COMP)
Shree Swami atmanand saraswati inst. of technology, surat
 
BCT Mod 4 demolition of structure (Updated)
BCT Mod 4 demolition of structure (Updated)BCT Mod 4 demolition of structure (Updated)
BCT Mod 4 demolition of structure (Updated)
Shree Swami atmanand saraswati inst. of technology, surat
 
MOD 3 CONSTRUCTION ECONOMICS (UPDATED)
MOD 3 CONSTRUCTION ECONOMICS (UPDATED)MOD 3 CONSTRUCTION ECONOMICS (UPDATED)
MOD 3 CONSTRUCTION ECONOMICS (UPDATED)
Shree Swami atmanand saraswati inst. of technology, surat
 
MODULE 2 PROJECT ORGANIZATION (updated)
MODULE 2 PROJECT ORGANIZATION (updated)MODULE 2 PROJECT ORGANIZATION (updated)
MODULE 2 PROJECT ORGANIZATION (updated)
Shree Swami atmanand saraswati inst. of technology, surat
 
BCT- Module 5 a coffer-dam (Part_2)
BCT- Module 5 a coffer-dam (Part_2)BCT- Module 5 a coffer-dam (Part_2)
Module :- 8 Job layout (PART 2)
Module :- 8 Job layout (PART 2)Module :- 8 Job layout (PART 2)
Module :- 8 material management
Module :- 8 material managementModule :- 8 material management
Module :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levellingModule :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levelling
Shree Swami atmanand saraswati inst. of technology, surat
 
Mod 3 construction economics
Mod 3 construction economicsMod 3 construction economics
MODULE 2 project organization
MODULE 2 project organizationMODULE 2 project organization
MODULE 1 Introduction to Construction Management
MODULE 1 Introduction to Construction ManagementMODULE 1 Introduction to Construction Management
MODULE 1 Introduction to Construction Management
Shree Swami atmanand saraswati inst. of technology, surat
 
Che 10 engineering fundamental
Che  10 engineering fundamentalChe  10 engineering fundamental
Chapter 9 introduction to construction equipments
Chapter  9 introduction to construction equipmentsChapter  9 introduction to construction equipments
Chapter 9 introduction to construction equipments
Shree Swami atmanand saraswati inst. of technology, surat
 
CHE :- 6 form work (MODULE 3)
CHE :- 6 form work (MODULE 3)CHE :- 6 form work (MODULE 3)
Che 1 pile foundation
Che 1 pile foundationChe 1 pile foundation
Ch 5 b remote sensing
Ch 5 b remote sensingCh 5 b remote sensing
Ch 5 a gps
Ch 5 a gpsCh 5 a gps
Ch 5 levelling
Ch 5 levellingCh 5 levelling

More from Shree Swami atmanand saraswati inst. of technology, surat (20)

INFRASTRUCTURE FOR SMART CITIES_MOD 2_planning for smart cities
INFRASTRUCTURE FOR SMART CITIES_MOD 2_planning for smart citiesINFRASTRUCTURE FOR SMART CITIES_MOD 2_planning for smart cities
INFRASTRUCTURE FOR SMART CITIES_MOD 2_planning for smart cities
 
INFRASTRUCTURE FOR SMART CITIES_MOD 3_Intelligent transport systems
INFRASTRUCTURE FOR SMART CITIES_MOD 3_Intelligent transport systemsINFRASTRUCTURE FOR SMART CITIES_MOD 3_Intelligent transport systems
INFRASTRUCTURE FOR SMART CITIES_MOD 3_Intelligent transport systems
 
Sem 5 mod-1 disaster management introduction (CIVIL, ELE, MECH, EC, COMP)
Sem 5 mod-1 disaster management introduction (CIVIL, ELE, MECH, EC, COMP)Sem 5 mod-1 disaster management introduction (CIVIL, ELE, MECH, EC, COMP)
Sem 5 mod-1 disaster management introduction (CIVIL, ELE, MECH, EC, COMP)
 
BCT Mod 4 demolition of structure (Updated)
BCT Mod 4 demolition of structure (Updated)BCT Mod 4 demolition of structure (Updated)
BCT Mod 4 demolition of structure (Updated)
 
MOD 3 CONSTRUCTION ECONOMICS (UPDATED)
MOD 3 CONSTRUCTION ECONOMICS (UPDATED)MOD 3 CONSTRUCTION ECONOMICS (UPDATED)
MOD 3 CONSTRUCTION ECONOMICS (UPDATED)
 
MODULE 2 PROJECT ORGANIZATION (updated)
MODULE 2 PROJECT ORGANIZATION (updated)MODULE 2 PROJECT ORGANIZATION (updated)
MODULE 2 PROJECT ORGANIZATION (updated)
 
BCT- Module 5 a coffer-dam (Part_2)
BCT- Module 5 a coffer-dam (Part_2)BCT- Module 5 a coffer-dam (Part_2)
BCT- Module 5 a coffer-dam (Part_2)
 
Module :- 8 Job layout (PART 2)
Module :- 8 Job layout (PART 2)Module :- 8 Job layout (PART 2)
Module :- 8 Job layout (PART 2)
 
Module :- 8 material management
Module :- 8 material managementModule :- 8 material management
Module :- 8 material management
 
Module :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levellingModule :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levelling
 
Mod 3 construction economics
Mod 3 construction economicsMod 3 construction economics
Mod 3 construction economics
 
MODULE 2 project organization
MODULE 2 project organizationMODULE 2 project organization
MODULE 2 project organization
 
MODULE 1 Introduction to Construction Management
MODULE 1 Introduction to Construction ManagementMODULE 1 Introduction to Construction Management
MODULE 1 Introduction to Construction Management
 
Che 10 engineering fundamental
Che  10 engineering fundamentalChe  10 engineering fundamental
Che 10 engineering fundamental
 
Chapter 9 introduction to construction equipments
Chapter  9 introduction to construction equipmentsChapter  9 introduction to construction equipments
Chapter 9 introduction to construction equipments
 
CHE :- 6 form work (MODULE 3)
CHE :- 6 form work (MODULE 3)CHE :- 6 form work (MODULE 3)
CHE :- 6 form work (MODULE 3)
 
Che 1 pile foundation
Che 1 pile foundationChe 1 pile foundation
Che 1 pile foundation
 
Ch 5 b remote sensing
Ch 5 b remote sensingCh 5 b remote sensing
Ch 5 b remote sensing
 
Ch 5 a gps
Ch 5 a gpsCh 5 a gps
Ch 5 a gps
 
Ch 5 levelling
Ch 5 levellingCh 5 levelling
Ch 5 levelling
 

Recently uploaded

The Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdfThe Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdf
kaushalkr1407
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
Celine George
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
siemaillard
 
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCECLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
BhavyaRajput3
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
Vivekanand Anglo Vedic Academy
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
TechSoup
 
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
Nguyen Thanh Tu Collection
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
Tamralipta Mahavidyalaya
 
The approach at University of Liverpool.pptx
The approach at University of Liverpool.pptxThe approach at University of Liverpool.pptx
The approach at University of Liverpool.pptx
Jisc
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
EugeneSaldivar
 
Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
Jisc
 
Chapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptxChapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptx
Mohd Adib Abd Muin, Senior Lecturer at Universiti Utara Malaysia
 
Additional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdfAdditional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdf
joachimlavalley1
 
The Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve ThomasonThe Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve Thomason
Steve Thomason
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
RaedMohamed3
 
How to Create Map Views in the Odoo 17 ERP
How to Create Map Views in the Odoo 17 ERPHow to Create Map Views in the Odoo 17 ERP
How to Create Map Views in the Odoo 17 ERP
Celine George
 
Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
AzmatAli747758
 
Ethnobotany and Ethnopharmacology ......
Ethnobotany and Ethnopharmacology ......Ethnobotany and Ethnopharmacology ......
Ethnobotany and Ethnopharmacology ......
Ashokrao Mane college of Pharmacy Peth-Vadgaon
 
PART A. Introduction to Costumer Service
PART A. Introduction to Costumer ServicePART A. Introduction to Costumer Service
PART A. Introduction to Costumer Service
PedroFerreira53928
 
Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
Atul Kumar Singh
 

Recently uploaded (20)

The Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdfThe Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdf
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
 
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCECLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
 
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
 
The approach at University of Liverpool.pptx
The approach at University of Liverpool.pptxThe approach at University of Liverpool.pptx
The approach at University of Liverpool.pptx
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
 
Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
 
Chapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptxChapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptx
 
Additional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdfAdditional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdf
 
The Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve ThomasonThe Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve Thomason
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
 
How to Create Map Views in the Odoo 17 ERP
How to Create Map Views in the Odoo 17 ERPHow to Create Map Views in the Odoo 17 ERP
How to Create Map Views in the Odoo 17 ERP
 
Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
 
Ethnobotany and Ethnopharmacology ......
Ethnobotany and Ethnopharmacology ......Ethnobotany and Ethnopharmacology ......
Ethnobotany and Ethnopharmacology ......
 
PART A. Introduction to Costumer Service
PART A. Introduction to Costumer ServicePART A. Introduction to Costumer Service
PART A. Introduction to Costumer Service
 
Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
 

BCT - Module 5 special work

  • 2. 2 Timbering in trenches Control of Ground water in excavation types of scaffoldings shoring, underpinningCoffer Dams Diaphragm Walls Demolition of structures
  • 3. 3  TIMBERING IN TRENCHES  A trench is a type of excavation or depression in the ground that is generally deeper than it is wide (as opposed to a wider gully, or ditch), and narrow compared with its length (as opposed to a simple hole).  When the depth of trench is large, or when the sub-soil is loose, the sides of the trench may cave in.  The problem can be solved by adopting a suitable method of timbering. Timbering of trenches, sometimes also known as shoring consists of providing timber planks or boards and struts to give temporary support to the sides of the trench.
  • 4. 4
  • 5. 5
  • 6. 6
  • 7. 7
  • 8. 8 Timbering of deep trenches can be done with the help of the following methods: 1. Stay bracing. 2. Box sheeting 3. Vertical sheeting 4. Runner system 5. Sheet piling.
  • 9. 1. Stay bracing. This method is used for supporting the sides or a bench excavated in fairly firm soil, when the depth of excavation does not exceed about 2 metres. The method consists of placing vertical sheets (called sheathing) or polling boards opposite each other against the two walls of the trench and holding them in position by one or two rows of struts. THE POLLING BOARDS width 200 mm thickness of 44 to 50 mm. STRUTS 1OO x 100 mm for trench up to 2 m width 200 x 200 mm for trench up to 4 m width. 9
  • 10. 10
  • 11. 11 2. Box sheeting. This method is adopted in loose soils, when the depth of excavation does not exceed 4 metres. Its consisting of vertical sheets placed very near to each other (some times touching each other) and keeping them in position by longitudinal rows (usually two) of Wales. Struts are then provided across the Wales. Another system of box sheeting, shown in Fig. 2.32(b), is adopted for very loose soils. In this system, the sheeting is provided longitudinally, and they are supported by vertical Wales and horizontal struts. If the height is more, braces are also provided along with struts.
  • 12. 12 Fig. 2.32 (a) for loose soil
  • 13. 13 Fig. 2.32 (b) very loose soil
  • 14. 14 Fig. 2 (b) very loose soil Fig. 2 (a) loose soil
  • 15. 15 3. Vertical sheeting.  This system is adopted for Deep trenches (up to 10 m depth) in soft ground.  The method is similar to the box sheeting except that the excavation is carried out in stages and at the end of each stage, an offset is provided, so that the width of the trench goes on decreasing as the depth increases.  Each stage is limited to about 3 m in height and the offset may vary from 25 to 50 cm per stage.  For each stage, separate vertical sheeting, supported by horizontal wailings and struts are provided.
  • 17. 17 4. Sheet piling This method is adopted when (i) soil to be excavated is soft or loose (ii) depth of excavation is large (iii) width of trench is also large and (iv) there is sub-soil water. Sheet piles are designed to resist lateral earth pressure. These are driven in the ground by mechanical means (pile driving equipment). They can be used for excavating to a very large depth.
  • 18. 18
  • 19. 19
  • 20. 20
  • 21. 21  Shoring is the type of construction of a temporary structure to support temporarily an unsafe structure.  These support walls, supporting a building, structure, or trench with shores (props) when in danger of collapse or during repairs or alterations.  Shoring comes from shore (props)  a timber or metal prop use for shoring  Shoring may be vertical, angled, or horizontal. SHORING
  • 22. 22 THEY CAN BE USED UNDER…..  When walls bulge out  When walls crack due to unequal settlement of foundation and repairs are to be carried out to the cracked wall.  When an adjacent structure needs pulling down.  When openings are to be newly made or enlarged in a wall.  Shoring is used to support the beams and floors in a building while a column or wall is removed.  In this situation vertical supports are used as a temporary replacement for the building columns or walls.
  • 23. 23
  • 24. 24 Raking Shores consist of one or more timbers sloping between the face of the structure to be supported and the ground. The most effective support is given if the raker meets the wall at an angle of 60 to 70 degrees. A wall-plate is typically used to increase the area of support. Its consists of the following components: •Rakers or inclined member •Wall plate •Needles •Cleats •Bracing •Sole plate Raking Shore
  • 25. 25 The following points are to be kept in view for the use of the raking shores: Rakers are to be inclined in the ground at 45⁰. However the angle may be between 45 ⁰ and 75 ⁰. Rakers should be properly braced at intervals. The size of the rakers is to be decided on the basis of anticipated thrust from the wall. The sole plate should be properly embedded into the ground on an inclination and should be of proper section and size. Edges on raker should not be used on sole plates since they are likely to give way under vibrations that are likely to occur.
  • 26. 26
  • 27. 27
  • 28. 28
  • 29. 29
  • 30. 30
  • 31. 31  It is also known as horizontal shores  It is a system of providing temporary supports to the party walls of the two buildings where the intermediate building is to be pulled down and rebuilt.  All types of arrangements of supporting the unsafe structure in which the shores do not reach the ground come under this category.  In this type, horizontal supports are provided for supporting temporarily the parallel walls of the two adjacent buildings, which may tend to collapse or damage when one of the intermediate buildings has to be pulled down and rebuilt.  The maximum distance of about 10 meter between the parallel walls can be supported by single flying shore. For a distance more than 10 m, a double flying shore, having a trussed form-work is employed FLYING SHORES
  • 32. 32
  • 33. 33
  • 34. 34
  • 35. 35
  • 36. 36
  • 37. 37
  • 38. 38
  • 39. 39
  • 40. 40
  • 41. 41 This is the system of shoring which is used to render vertical support to walls and roofs, floors, etc when the lower part of a wall has been removed for the purpose of providing an opening in the wall or to rebuild a defective load bearing wall in a structure. The dead shore consists of an arrangement of beams and posts which are required to support the weight of the structure above and transfer same to the ground on firm foundation below. DEAD SHORES
  • 42.  When opening in the wall are to be made, holes are cut in the wall at such a height as to allow sufficient space for insertion of the beam or girder that will be provided permanently to carry the weight of the structure above.  Distance at which the holes are cut depends upon the type of masonry and it varies from 1.2m to 1.8m centre.  Beams called needles are placed in the holes and are supported by vertical props called dead shores at their ends on either side of the wall.  The needles may be of timber or steel and are of sufficient section to carry the load above. 42
  • 43. 43
  • 44. 44
  • 52. 52 UNDERPINNING The process of providing a new foundation below an existing foundation of an existing foundation, without dangering the stability of an existing structure. The method of underpinning help to strengthen the foundation of an existing building or any other infrastructure. These involve installation of permanent or temporary support to an already held foundation so that additional depth and bearing capacity is achieved.
  • 53. CONDITION OF UNDERPINNING  The original foundation is simply not strong or stable enough.  The usage of the structure has changed.  The properties of the soil supporting the foundation may have changed (possibly through subsidence) or were mischaracterized during design.  To increase the depth or load capacity of existing foundations to support the addition of another storey to the building (above or below grade).  Earthquake, flood, drought or other natural causes have caused the structure to move, thereby requiring stabilization of foundation soils. 53
  • 54. 54 1. Mass Concrete Underpinning Method (Pit Method) Mass concrete underpinning method is the traditional method of underpinning, as it has been followed by centuries. The method involves extending the old foundation till it reaches a stable stratum. The soil below the existing foundation is excavated in a controlled manner through stages or pins. When strata suitable is reached, the excavation is filled with concrete and kept for curing, before next excavation starts. in order to transfer the load from old foundation to new one, a new pin is provided by means of placing dry sand-cement pack. This is a low-cost method suitable for the shallow foundation. Stages divided into sections of 1.2 to 1.5 m lengths
  • 55. DIFFERENT METHODS OF UNDERPINNING UNDERPINNING CAN BE MADE IN VARIOUS WAYS, BUT TWO OF THEM ARE MOSTLY USED *PIT METHOD *PILE METHOD Pit method Pile Method 55
  • 57. 57 If an interior strong column exists, or if the foundation is to be extended only to one side, cantilever needle beams may be used in place of central needle beam. A jack is placed between the column and wall.
  • 58. 58 Underpinning By Cantilever Needle Beam Method Figure represents the arrangement of cantilever pit method of underpinning, which is an extension of pit method. If the foundation has to be extended only to one side and the plan possess a stronger interior column, this method can be used for underpinning. Advantages of Cantilever Needle Beam Method: •Faster than traditional method •One side access only •High load carrying capability Disadvantages: •Digging found uneconomical when existing foundation is deep
  • 59. 59
  • 60. 60 Pile Method  In this method, piles are driven on adjacent sides of the wall that supports the weak foundation.  A needle or pin penetrates through the wall that is in turn connected to the piles as shown in figure.  These needles behave like pile caps.  Use where Settlement in soil due to water clogging or clayey nature can be treated by this method.
  • 61. 61
  • 64. 64
  • 65. 65
  • 66. SCAFFOLDING 66  Scaffolding is a temporary frame or structure used to support people and material in the construction or repair of buildings and other large structures.  It is used when height of wall or column or other structural member of a building exceeds about 1.5m.  Scaffolding is a temporary structure to support the original structure as well as workmen used it as a platform to carry on the construction works.  Types of scaffolding varies with the type of construction work.  Scaffolding is made up of timber or steel.  It should be stable and strong to support workmen and other construction material placed on it.
  • 68. 68 Standards:- These are vertical members of the frame work, supporting on the ground or embedded into the ground. Ledgers:- these are the horizontal members, running parallel to the wall. Braces:- These are diagonal members fixed on standards. Putlogs:- These are the transverse members, placed at right angles to the wall with one end supported on ledgers and other end on the wall. Boarding:- These are horizontal platform to support workmen & material; these are supported on putlogs. Guard Rail:- This is a rail, provided like a ledger, at the working level.
  • 69. 69
  • 70. 70
  • 71. 71
  • 72. 72 Single scaffolding or brick layers scaffolding Double scaffolding or mason’s scaffolding Cantilever or needle scaffolding Suspended scaffolding Trestle scaffolding Steel scaffolding Patented scaffolding
  • 73. 1. SINGLE SCAFFOLDING OR BRICK LAYERS SCAFFOLDING 73
  • 74. 74
  • 75. 7575 Single scaffolding is generally used for brick masonry and is also called as brick layer’s scaffolding. Single scaffolding consists of standards, ledgers, putlogs etc., which is parallel to the wall at a distance of about 1.2 m. Distance between the standards is about 2 to 2.5 m. Ledgers connect the standards at vertical interval of 1.2 to 1.5 m. Putlogs are taken out from the hole left in the wall to one end of the ledgers. Putlogs are placed at an interval of 1.2 to 1.5 m. Single Scaffolding
  • 76. 76
  • 77. 2. DOUBLE SCAFFOLDING OR MASON’S SCAFFOLDING 77
  • 78. 78
  • 79. 79 Double Scaffolding  Double Scaffolding is generally used for stone masonry so, it is also called as mason’s scaffolding.  In stone walls, it is hard to make holes in the wall to support putlogs. So, two rows of scaffolding is constructed to make it strong.  The first row is 20 – 30 cm away from the wall and the other one is 1m away from the first row.  Then putlogs are placed which are supported by the both frames.  To make it more strong rakers and cross braces are provided.  This is also called as independent scaffolding.
  • 80. 80
  • 81. 3. CANTILEVER OR NEEDLE SCAFFOLDING 81
  • 82. 82 CANTILEVER SCAFFOLDING This a type of scaffolding the standards are supported on series of needles and these needles are taken out through holes in the wall. This is called single frame type scaffolding. In the other type needles are strutted inside the floors through the openings and this is called independent or double frame type scaffolding. Care should be taken while construction of cantilever scaffolding. Generally cantilever scaffoldings are used under conditions such as •When the ground does not having the capacity to support standards •When the Ground near the wall is Need to be free from traffic.
  • 83. 83
  • 84. 84
  • 85.  Light weight scaffolding used for repair works like painting, pointing etc.  The working platform is suspended from roofs by means of wire ropes or chains.  Platform can be raised or lowered at any desired level. 4.SUSPENDED SCAFFOLDING 85
  • 86. 86
  • 87. This is also used for repair works inside the room, up to height of 5m. The working platform is supported on the top of movable contrivances like tripods, ladders may be mounted on wheels. In Trestle scaffolding, the working platform is supported on movable tripods or ladders. This is generally used for work inside the room, such as paintings, repairs etc., up to a height of 5m. 5.TRESTLE SCAFFOLDING 87
  • 88. 88
  • 89. Wooden members are replaced by steel tubes and rope lashings are replaced by steel couplets or fittings. Such scaffolding can be erected and dismantled rapidly. It has greater strength, greater durability and higher fire resistance. Can be used for stone and brick masonry construction. 6.STEEL SCAFFOLDING 89
  • 90. 90
  • 91. 91 Timbering in trenches Control of Ground water in excavation types of scaffoldings shoring, underpinningCoffer Dams Diaphragm Walls Demolition of structures
  • 92. 92