Brief description is given about different types of estimates of buildings in civil engineering with basic technical terminology used in civil engineering field
Presentation describes important designing parameters, reasons for formwork failures and prevention of such failures. It also touches upon remedial measures.
Detailed specification of an item of work specifies the quantities of materials, proportion of mortar, workmanship, method of preparation & execution and method of measurement.
Detailed specifications of different items of works are prepared separately and describe what the work should be and these shall be executed and constructed.
in this presentation, we should discuss what is the need for a survey in bridge construction site and what are the needed equipment use in construction. in this presentation, you should learn about how to locate activity of bridge construction.the different method should be learning in this presentation and it more effectively. it is more helpful in your career growth.
thank you
ASWINI & SAGAR
Brief description is given about different types of estimates of buildings in civil engineering with basic technical terminology used in civil engineering field
Presentation describes important designing parameters, reasons for formwork failures and prevention of such failures. It also touches upon remedial measures.
Detailed specification of an item of work specifies the quantities of materials, proportion of mortar, workmanship, method of preparation & execution and method of measurement.
Detailed specifications of different items of works are prepared separately and describe what the work should be and these shall be executed and constructed.
in this presentation, we should discuss what is the need for a survey in bridge construction site and what are the needed equipment use in construction. in this presentation, you should learn about how to locate activity of bridge construction.the different method should be learning in this presentation and it more effectively. it is more helpful in your career growth.
thank you
ASWINI & SAGAR
The goal of this project was to maximize the productive use of the available space in Loram's manufacturing facility. The team wanted to create designated work spaces known as Large Work Centers (LWC) to improve the product flow through the manufacturing facility. This will then minimize unproductive touches of product which will reduce the time it takes it to move through the shop and minimize the risk of damage when it is handled. The project also focused on the layout of the LWC to maximize efficient access and organization of tools and equipment needed to assemble Loram's machines.
I functioned as the engineering representative on the cross functional team and provided technical knowledge on the size of the parts and assemblies, the bill of materials, and the work breakdown structure for the Loram's machines that were to be assembled in the LWC. I then used these key pieces of information to layout out the LWC and helped the team finalize the layout for the manufacturing facility. The result was $45,000 in annual savings due to reduced product movements, a reduction in damage to products when moving them within the facility, and proving that a $100,000+ expenditure on a crane was unnecessary.
It is a presentation on facility layout which covers the definition of layout, objectives of good layout, factors affecting layout and types of layout.
planning for smart cities
sustainable green building,
safety, security, disaster management, economy, cyber security, Project management.
AS PER GTU 7TH SEM SYLLABUS MODULE 2
Intelligent transport systems
Smart vehicles and fuels, GIS, GPS, Navigation system, traffic safety management,
mobility services, E-ticketing
AS PER GTU 7TH SEM SYLLABUS MODULE 3
Disaster Management can be defined as the organization and management of resources and responsibilities for dealing with all humanitarian aspects of emergencies, in particular preparedness, response and recovery in order to lessen the impact of disasters.
for the subject offered in GTU, BCT, ace, cm
module 4 demolition of the structure
for the 3rd sem & also for the 6th sem subject and for the master of construction management
for the subject offered in GTU in the final year (8th semester), construction management
final year
Module:- 5 project scheduling and resource leveling
Synthetic Fiber Construction in lab .pptxPavel ( NSTU)
Synthetic fiber production is a fascinating and complex field that blends chemistry, engineering, and environmental science. By understanding these aspects, students can gain a comprehensive view of synthetic fiber production, its impact on society and the environment, and the potential for future innovations. Synthetic fibers play a crucial role in modern society, impacting various aspects of daily life, industry, and the environment. ynthetic fibers are integral to modern life, offering a range of benefits from cost-effectiveness and versatility to innovative applications and performance characteristics. While they pose environmental challenges, ongoing research and development aim to create more sustainable and eco-friendly alternatives. Understanding the importance of synthetic fibers helps in appreciating their role in the economy, industry, and daily life, while also emphasizing the need for sustainable practices and innovation.
Operation “Blue Star” is the only event in the history of Independent India where the state went into war with its own people. Even after about 40 years it is not clear if it was culmination of states anger over people of the region, a political game of power or start of dictatorial chapter in the democratic setup.
The people of Punjab felt alienated from main stream due to denial of their just demands during a long democratic struggle since independence. As it happen all over the word, it led to militant struggle with great loss of lives of military, police and civilian personnel. Killing of Indira Gandhi and massacre of innocent Sikhs in Delhi and other India cities was also associated with this movement.
2024.06.01 Introducing a competency framework for languag learning materials ...Sandy Millin
http://sandymillin.wordpress.com/iateflwebinar2024
Published classroom materials form the basis of syllabuses, drive teacher professional development, and have a potentially huge influence on learners, teachers and education systems. All teachers also create their own materials, whether a few sentences on a blackboard, a highly-structured fully-realised online course, or anything in between. Despite this, the knowledge and skills needed to create effective language learning materials are rarely part of teacher training, and are mostly learnt by trial and error.
Knowledge and skills frameworks, generally called competency frameworks, for ELT teachers, trainers and managers have existed for a few years now. However, until I created one for my MA dissertation, there wasn’t one drawing together what we need to know and do to be able to effectively produce language learning materials.
This webinar will introduce you to my framework, highlighting the key competencies I identified from my research. It will also show how anybody involved in language teaching (any language, not just English!), teacher training, managing schools or developing language learning materials can benefit from using the framework.
The Art Pastor's Guide to Sabbath | Steve ThomasonSteve Thomason
What is the purpose of the Sabbath Law in the Torah. It is interesting to compare how the context of the law shifts from Exodus to Deuteronomy. Who gets to rest, and why?
The French Revolution, which began in 1789, was a period of radical social and political upheaval in France. It marked the decline of absolute monarchies, the rise of secular and democratic republics, and the eventual rise of Napoleon Bonaparte. This revolutionary period is crucial in understanding the transition from feudalism to modernity in Europe.
For more information, visit-www.vavaclasses.com
Ethnobotany and Ethnopharmacology:
Ethnobotany in herbal drug evaluation,
Impact of Ethnobotany in traditional medicine,
New development in herbals,
Bio-prospecting tools for drug discovery,
Role of Ethnopharmacology in drug evaluation,
Reverse Pharmacology.
Model Attribute Check Company Auto PropertyCeline George
In Odoo, the multi-company feature allows you to manage multiple companies within a single Odoo database instance. Each company can have its own configurations while still sharing common resources such as products, customers, and suppliers.
How to Create Map Views in the Odoo 17 ERPCeline George
The map views are useful for providing a geographical representation of data. They allow users to visualize and analyze the data in a more intuitive manner.
1. What is Job Layout?
• A job layout is prepared to promise that work proceeds smoothly
without any obstruction. The various construction resources such as
material, men, machinery etc. should be arranged in such way to
achieve optimal utilization of space. The larger and more complex
the project, greater will be the need for planned
detailing at site. And job layout can be defined as a
job layout and
site drawing of
the proposed construction showing the location of entry, exit,
temporary services, material stores and stocks, plant or equipment
and site offices.
2. as mixer
o A job layout is a scaled drawing of the propose construction
all relevant features
site showing
• Entry point
• Exit point
• Storage are of materials-bricks-cement-sand-aggregate
• Temporary services-washing and toilet
• Contractor site office
• Area of keeping equipment such
• Bar bending area
• Labor housing
3. • To save time in delivering construction material at the side of construction
• To safeguard construction material from damage and deterioration
• To adopt the best mode of working
• To complete the work with the minimum use of equipment and machinery
• To take maximum output from labor and machinery
6
Purpose of job layout
4. Factor affection job layout
• Nature of the project
• Construction method
• Availability of resources
• Material facility
• Constructer’s, site engineer’s offices
• Provision for temporary roads
• Other facility’s
9
5. Principal preparation of job layout
• Administrative block
• Warehouse
• Entry and exits
• Location of workshop
• Services
• Temporary roads
• Staff accommodation
10
6. Identification of facility
• The Following are the temporary facilities are identified to be
constructed on site
1) Site Office 2) Booking office 3) Subcontractor’s office 4) First•
Aid and Medical Room 5) Guard Room 6) Toilet on Site 7)
Engineer and Staff quarters 8) Labor quarters 9) Equipment
Maintenance room 10) Parking for machines 11) Bar bending shop
12) Fabricated rebar storage yard 13) Carpentry shop 14) Cement
warehouse 15) Batching plant and aggregates storage 16) Testing
Lab 17) Material storage lab 18) Water tank 19) Scaffolding storage
20) Canteen