SlideShare a Scribd company logo
1 of 13
Construction Method and Application
 Diaphragm Wall:
Diaphragm wall is an underground wall constructed from
the ground level to support excavation sides from lateral
earth pressure and water pressure and to provide water
tightness to the underground structure.
Features:
1. As a cut-off provision to support deep excavation.
2. As a retaining wall.
3. It is also used as a permanent basement walls for
facilitating Top-down construction method.
4. Typical wall thickness varies between 0.6 to 1.5m
5. Panel width varies from 2.5m to about 6.5m or even more
depending on various conditions.
1. Construct the
guide wall.
2. Excavation to form
the diaphragm wall
trench.
3. Support the trench
cutting using
bentonite slurry.
4. Installation of stop
ends and cage.
5. Concreting.
Trench Cutter Mechanical Hydraulic Grab Reverse Mud Circulation Rig
 Guide wall is two parallel concrete
beams constructed along the side of
the wall as a guide to the clamshell
which is used for the excavation of
the diaphragm wall trenches.
 Typically 1-1.5 meter deep.
 Trench excavation
 In normal soil condition excavation is done
using a clamshell or grab suspended by
cables to a crane
 Excavation support
 The sides inside the trench cut can collapse
easily.
 Bentonite slurry is used to protect the sides
of soil.
 Bentonite is a specially selected fine clay,
when added to water, forms an impervious
cakelike slurry with very large viscosity.
 The slurry will produce a great lateral
pressure sufficient enough to retain the
vertical soil.
 Reinforcement Cage
 Reinforcement is inserted in the form of a
steel cage, but may be required to lap a few
sections in order to reach the required length.
 Concreting
 Placing of concrete is done using tremie
pipes to avoid the segregation of concrete.
 As Concrete being poured down, bentonite
will be displaced due to its lower density than
concrete.
 Bentonite is then collected and reused.
Concreting
 The process of constructing the wall is relatively quiet &
has small vibration.
 Can be constructed to a great depth.
 The wall provides temporary supports during
excavation hence expensive steelwork is eliminated.
 Good water cutoff. No dewatering is necessary.
 Serves both as external work for the basement and
foundation for superstructure.
 Suitable for deep basement. It can be up to 50m depth.
 Commonly used in congested areas.
 Installed in close proximity to existing structure.
 Suitable for unstable soil profiles below water table.
 Limited construction time.
 Designable to carry vertical loads.
 Minimize the settlement of adjacent building.
 The cost is higher than conventional
methods.
 Special Equipment is necessary.
 Larger space is required at site for the
special equipment.
Construction Diaphragm Wall Guide
Construction Diaphragm Wall Guide

More Related Content

What's hot (20)

types of coffer dam
types of coffer dam types of coffer dam
types of coffer dam
 
Caisson
CaissonCaisson
Caisson
 
Chapter 3 caisson
Chapter 3 caissonChapter 3 caisson
Chapter 3 caisson
 
Diaphragm wall: Construction and Design
Diaphragm wall: Construction and DesignDiaphragm wall: Construction and Design
Diaphragm wall: Construction and Design
 
Chapter 3 shallow foundations
Chapter 3 shallow foundationsChapter 3 shallow foundations
Chapter 3 shallow foundations
 
Well Foundation
Well FoundationWell Foundation
Well Foundation
 
Diaphragm Wall Presentation By Gagan
Diaphragm Wall Presentation By GaganDiaphragm Wall Presentation By Gagan
Diaphragm Wall Presentation By Gagan
 
1.1 box jacking
1.1 box jacking1.1 box jacking
1.1 box jacking
 
Prestressed Concrete
Prestressed ConcretePrestressed Concrete
Prestressed Concrete
 
Retaining wall
Retaining wallRetaining wall
Retaining wall
 
Driven & Bored Piles
Driven & Bored PilesDriven & Bored Piles
Driven & Bored Piles
 
Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile foundation ppt 2 (usefulsearch.org) (useful search)Pile foundation ppt 2 (usefulsearch.org) (useful search)
Pile foundation ppt 2 (usefulsearch.org) (useful search)
 
Soil exploration part i
Soil exploration part  iSoil exploration part  i
Soil exploration part i
 
Deep excavation
Deep excavationDeep excavation
Deep excavation
 
Deep excavations
Deep excavationsDeep excavations
Deep excavations
 
PILE FOUNDATION and METHODS OF INSTALLING PILE FOUNDATIONS
PILE FOUNDATION and METHODS OF INSTALLING PILE FOUNDATIONSPILE FOUNDATION and METHODS OF INSTALLING PILE FOUNDATIONS
PILE FOUNDATION and METHODS OF INSTALLING PILE FOUNDATIONS
 
Retaining wall
 Retaining wall  Retaining wall
Retaining wall
 
Construction of substructure
Construction of substructureConstruction of substructure
Construction of substructure
 
Underpinning
UnderpinningUnderpinning
Underpinning
 
BCT MODULE 2 - Caisson
BCT MODULE 2 - CaissonBCT MODULE 2 - Caisson
BCT MODULE 2 - Caisson
 

Viewers also liked

Lecture 2 thoracic wall & Diaphragm
Lecture 2 thoracic wall & DiaphragmLecture 2 thoracic wall & Diaphragm
Lecture 2 thoracic wall & DiaphragmDr. Noura El Tahawy
 
Pile Foundations and Diaphragm Walls
Pile Foundations and Diaphragm WallsPile Foundations and Diaphragm Walls
Pile Foundations and Diaphragm WallsAkash Tilokani
 
Soil Properties and Foundation
Soil Properties and FoundationSoil Properties and Foundation
Soil Properties and FoundationReasat E Noor
 
Hill Claims Services Presentation Linkedin Ppt
Hill Claims Services Presentation Linkedin PptHill Claims Services Presentation Linkedin Ppt
Hill Claims Services Presentation Linkedin Pptkenbaker
 
What is a construction management and who is a construction manager?
What is a construction management and who is a construction manager?What is a construction management and who is a construction manager?
What is a construction management and who is a construction manager?kesouth
 
Dw final (inside)
Dw final (inside)Dw final (inside)
Dw final (inside)juwes
 
60 auto cad_tips_in_60_minutes_final
60 auto cad_tips_in_60_minutes_final60 auto cad_tips_in_60_minutes_final
60 auto cad_tips_in_60_minutes_finalSE3D
 
Methodology construction
Methodology construction Methodology construction
Methodology construction Ehsan Alirezaei
 
Anchored Secant Pile Wall Presentation
Anchored Secant Pile Wall PresentationAnchored Secant Pile Wall Presentation
Anchored Secant Pile Wall PresentationKyle Beaudry, P.Eng
 
Top 5 construction manager cover letter samples
Top 5 construction manager cover letter samplesTop 5 construction manager cover letter samples
Top 5 construction manager cover letter samplesdonriferi
 
Session-02 17-09-2011
Session-02 17-09-2011Session-02 17-09-2011
Session-02 17-09-2011Tahir B Mirza
 
Quantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesQuantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesMichael Pink
 
Transfer Slabs Beams Design Tall Building- تصميم بلا طات وجوائز التحويل الأب...
 Transfer Slabs Beams Design Tall Building- تصميم بلا طات وجوائز التحويل الأب... Transfer Slabs Beams Design Tall Building- تصميم بلا طات وجوائز التحويل الأب...
Transfer Slabs Beams Design Tall Building- تصميم بلا طات وجوائز التحويل الأب...Dr.Youssef Hammida
 
Secant piled walls dsign - تصميم خوازيق الجدران الساندة - ميكرو بايل
Secant piled walls  dsign - تصميم خوازيق الجدران الساندة - ميكرو بايلSecant piled walls  dsign - تصميم خوازيق الجدران الساندة - ميكرو بايل
Secant piled walls dsign - تصميم خوازيق الجدران الساندة - ميكرو بايلDr.youssef hamida
 

Viewers also liked (18)

Diaphragm wall
Diaphragm wallDiaphragm wall
Diaphragm wall
 
Lecture 2 thoracic wall & Diaphragm
Lecture 2 thoracic wall & DiaphragmLecture 2 thoracic wall & Diaphragm
Lecture 2 thoracic wall & Diaphragm
 
Cement .pptx
Cement .pptxCement .pptx
Cement .pptx
 
Pile Foundations and Diaphragm Walls
Pile Foundations and Diaphragm WallsPile Foundations and Diaphragm Walls
Pile Foundations and Diaphragm Walls
 
Polavaram project
Polavaram projectPolavaram project
Polavaram project
 
Soil Properties and Foundation
Soil Properties and FoundationSoil Properties and Foundation
Soil Properties and Foundation
 
Hill Claims Services Presentation Linkedin Ppt
Hill Claims Services Presentation Linkedin PptHill Claims Services Presentation Linkedin Ppt
Hill Claims Services Presentation Linkedin Ppt
 
What is a construction management and who is a construction manager?
What is a construction management and who is a construction manager?What is a construction management and who is a construction manager?
What is a construction management and who is a construction manager?
 
Dw final (inside)
Dw final (inside)Dw final (inside)
Dw final (inside)
 
60 auto cad_tips_in_60_minutes_final
60 auto cad_tips_in_60_minutes_final60 auto cad_tips_in_60_minutes_final
60 auto cad_tips_in_60_minutes_final
 
Methodology construction
Methodology construction Methodology construction
Methodology construction
 
Diaphragm
Diaphragm Diaphragm
Diaphragm
 
Anchored Secant Pile Wall Presentation
Anchored Secant Pile Wall PresentationAnchored Secant Pile Wall Presentation
Anchored Secant Pile Wall Presentation
 
Top 5 construction manager cover letter samples
Top 5 construction manager cover letter samplesTop 5 construction manager cover letter samples
Top 5 construction manager cover letter samples
 
Session-02 17-09-2011
Session-02 17-09-2011Session-02 17-09-2011
Session-02 17-09-2011
 
Quantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesQuantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficiencies
 
Transfer Slabs Beams Design Tall Building- تصميم بلا طات وجوائز التحويل الأب...
 Transfer Slabs Beams Design Tall Building- تصميم بلا طات وجوائز التحويل الأب... Transfer Slabs Beams Design Tall Building- تصميم بلا طات وجوائز التحويل الأب...
Transfer Slabs Beams Design Tall Building- تصميم بلا طات وجوائز التحويل الأب...
 
Secant piled walls dsign - تصميم خوازيق الجدران الساندة - ميكرو بايل
Secant piled walls  dsign - تصميم خوازيق الجدران الساندة - ميكرو بايلSecant piled walls  dsign - تصميم خوازيق الجدران الساندة - ميكرو بايل
Secant piled walls dsign - تصميم خوازيق الجدران الساندة - ميكرو بايل
 

Similar to Construction Diaphragm Wall Guide

diaphragmwall-141223040711-conversion-gate02.pdf
diaphragmwall-141223040711-conversion-gate02.pdfdiaphragmwall-141223040711-conversion-gate02.pdf
diaphragmwall-141223040711-conversion-gate02.pdfJeevanandanKanagavel1
 
Soldier Bored and Diaphragm
Soldier Bored and DiaphragmSoldier Bored and Diaphragm
Soldier Bored and DiaphragmYingHongKang
 
Diaphragm walls
Diaphragm wallsDiaphragm walls
Diaphragm wallsNguyen Bao
 
Tutor cavity wall construction .ppt 1
Tutor cavity wall construction .ppt 1Tutor cavity wall construction .ppt 1
Tutor cavity wall construction .ppt 1Luke D'Arcy
 
Lesson 3 Floor screeds _suspended floors.pptx
Lesson 3 Floor screeds _suspended floors.pptxLesson 3 Floor screeds _suspended floors.pptx
Lesson 3 Floor screeds _suspended floors.pptxsydneyaugust1
 
Btech compile 6 oct 4am
Btech compile 6 oct 4amBtech compile 6 oct 4am
Btech compile 6 oct 4amCeline Tan
 
Cut and cover_sections
Cut and cover_sectionsCut and cover_sections
Cut and cover_sectionsjuwes
 
WRE II construction of galleries in gravity dams
WRE II construction of galleries in gravity damsWRE II construction of galleries in gravity dams
WRE II construction of galleries in gravity damsMitaliShelke
 
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining StructuresEXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining StructuresShivananda Roy
 
diaphragm and basement construction.pptx
diaphragm and basement construction.pptxdiaphragm and basement construction.pptx
diaphragm and basement construction.pptxChinnuNinan
 
1619929813526_College Deep Well Foundation Project.pptx
1619929813526_College Deep Well Foundation Project.pptx1619929813526_College Deep Well Foundation Project.pptx
1619929813526_College Deep Well Foundation Project.pptxAkshayGhorpade19
 
Rehabilitation and strengthening of existing structures
Rehabilitation and strengthening of existing structuresRehabilitation and strengthening of existing structures
Rehabilitation and strengthening of existing structuresShahrukh Niaz
 

Similar to Construction Diaphragm Wall Guide (20)

diaphragmwall-141223040711-conversion-gate02.pdf
diaphragmwall-141223040711-conversion-gate02.pdfdiaphragmwall-141223040711-conversion-gate02.pdf
diaphragmwall-141223040711-conversion-gate02.pdf
 
Soldier Bored and Diaphragm
Soldier Bored and DiaphragmSoldier Bored and Diaphragm
Soldier Bored and Diaphragm
 
1.2 Diaphragm walls.pptx
1.2 Diaphragm walls.pptx1.2 Diaphragm walls.pptx
1.2 Diaphragm walls.pptx
 
Diaphragm walls
Diaphragm wallsDiaphragm walls
Diaphragm walls
 
Tutor cavity wall construction .ppt 1
Tutor cavity wall construction .ppt 1Tutor cavity wall construction .ppt 1
Tutor cavity wall construction .ppt 1
 
Retaining wall
Retaining wallRetaining wall
Retaining wall
 
Diaphragm Wall
Diaphragm WallDiaphragm Wall
Diaphragm Wall
 
Retaining wall
Retaining wallRetaining wall
Retaining wall
 
pile wall
pile wallpile wall
pile wall
 
Lesson 3 Floor screeds _suspended floors.pptx
Lesson 3 Floor screeds _suspended floors.pptxLesson 3 Floor screeds _suspended floors.pptx
Lesson 3 Floor screeds _suspended floors.pptx
 
Btech compile 6 oct 4am
Btech compile 6 oct 4amBtech compile 6 oct 4am
Btech compile 6 oct 4am
 
Cut and cover_sections
Cut and cover_sectionsCut and cover_sections
Cut and cover_sections
 
WRE II construction of galleries in gravity dams
WRE II construction of galleries in gravity damsWRE II construction of galleries in gravity dams
WRE II construction of galleries in gravity dams
 
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining StructuresEXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
 
diaphragm and basement construction.pptx
diaphragm and basement construction.pptxdiaphragm and basement construction.pptx
diaphragm and basement construction.pptx
 
1619929813526_College Deep Well Foundation Project.pptx
1619929813526_College Deep Well Foundation Project.pptx1619929813526_College Deep Well Foundation Project.pptx
1619929813526_College Deep Well Foundation Project.pptx
 
Unit 3
Unit 3Unit 3
Unit 3
 
Rehabilitation and strengthening of existing structures
Rehabilitation and strengthening of existing structuresRehabilitation and strengthening of existing structures
Rehabilitation and strengthening of existing structures
 
Theory of structures
Theory of structuresTheory of structures
Theory of structures
 
Micropile
MicropileMicropile
Micropile
 

Recently uploaded

Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 

Recently uploaded (20)

Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 

Construction Diaphragm Wall Guide

  • 2.  Diaphragm Wall: Diaphragm wall is an underground wall constructed from the ground level to support excavation sides from lateral earth pressure and water pressure and to provide water tightness to the underground structure. Features: 1. As a cut-off provision to support deep excavation. 2. As a retaining wall. 3. It is also used as a permanent basement walls for facilitating Top-down construction method. 4. Typical wall thickness varies between 0.6 to 1.5m 5. Panel width varies from 2.5m to about 6.5m or even more depending on various conditions.
  • 3. 1. Construct the guide wall. 2. Excavation to form the diaphragm wall trench. 3. Support the trench cutting using bentonite slurry. 4. Installation of stop ends and cage. 5. Concreting.
  • 4. Trench Cutter Mechanical Hydraulic Grab Reverse Mud Circulation Rig
  • 5.  Guide wall is two parallel concrete beams constructed along the side of the wall as a guide to the clamshell which is used for the excavation of the diaphragm wall trenches.  Typically 1-1.5 meter deep.
  • 6.  Trench excavation  In normal soil condition excavation is done using a clamshell or grab suspended by cables to a crane  Excavation support  The sides inside the trench cut can collapse easily.  Bentonite slurry is used to protect the sides of soil.  Bentonite is a specially selected fine clay, when added to water, forms an impervious cakelike slurry with very large viscosity.  The slurry will produce a great lateral pressure sufficient enough to retain the vertical soil.
  • 7.  Reinforcement Cage  Reinforcement is inserted in the form of a steel cage, but may be required to lap a few sections in order to reach the required length.  Concreting  Placing of concrete is done using tremie pipes to avoid the segregation of concrete.  As Concrete being poured down, bentonite will be displaced due to its lower density than concrete.  Bentonite is then collected and reused.
  • 9.
  • 10.  The process of constructing the wall is relatively quiet & has small vibration.  Can be constructed to a great depth.  The wall provides temporary supports during excavation hence expensive steelwork is eliminated.  Good water cutoff. No dewatering is necessary.  Serves both as external work for the basement and foundation for superstructure.  Suitable for deep basement. It can be up to 50m depth.  Commonly used in congested areas.  Installed in close proximity to existing structure.  Suitable for unstable soil profiles below water table.  Limited construction time.  Designable to carry vertical loads.  Minimize the settlement of adjacent building.
  • 11.  The cost is higher than conventional methods.  Special Equipment is necessary.  Larger space is required at site for the special equipment.