Construction management
Introduction
Resource leveling
Resource allocation
Other schedules derived from project schedules
Network crashing and cost-time trade-off
Contents
The scheduling of activities, so that none of the precedence
relationships are violated and none of the resource availabilities
are exceeded, is a difficult task and can result in a number of
combinations of possible early start and late start schedules.
In literature, scheduling problems with limited resources is
classified as large combinatorial problem.
A number of programs based on some rules of thumb (also called
heuristic) have been developed to solve such problems.
These heuristic programs for resource scheduling can be broadly
classified under two categories: (1) Resource leveling and (2)
Resource allocation
Introduction
The resource allocation procedure mainly consists of two activities:
(i) Resource smoothing
(ii) Resource levelling.
Resource Leveling and Resource Smoothing are two resource optimization
techniques. Resource Leveling is performed to balance the demand and
supply of resources. Resource Smoothing is performed to achieve a more
uniform resource utilization over a period of time. Resource Leveling may
change the critical path of the project, whereas Resource Smoothing does
not.
Methods of resource allocation
Resource smoothing
Resource Smoothing: Resource Smoothing is a resource optimization
technique in which the Project Manager adjusts the timing of different
activities so that the requirement for resources does not exceed a certain
pre-defined limit. The objective is to complete the work by the required
date while avoiding peaks resource demand.
The intelligent utilization of floats can smoothen the demand of resources
to the maximum possible extent is called resource Smoothing. In other
words, activities may only be delayed within their free and total float.
The resource smoothing is applied in such a way that the total project
duration remains the same i.e. there is no change in the total duration of
the project. First, the periods of minimum demand for resources are
determined or located and the activities are shifted according to the
availability of float and requirement of resources. Thus the intelligent use
of floats can smoothen the demand to the maximum possible extent. This
type of resource allocation is known as resource smoothing
Resource leveling
Resource Leveling is a resource optimization technique in which the
Project Manager adjusts the start dates and finish dates of different
activities in order to balance the demand for resources vs available supply.
If the demand of a resource is more than its availability, then the only
alternative is to delay the activity having maximum float. This process is
called resource levelling. If there are more than one activities requiring
the same amount of resources, in that case activity having minimum
duration is chosen for resource reallocation. Resource levelling is
adopted in case there is restriction on the availability resources
Resource levelling, Scenario A:
 For example, if there are two task on project network diagram and they are
scheduled on the same time period and both required the same resource,
“X”.
 Task A is on critical path, Task B is on non-critical path which means
which has float.
 Further assume, the task A is high priority task than the task B.
 In this situation, if we perform resource levelling, the project schedule or
critical path may or may not change.
 If the levelling delay within the free or total float the project schedule will
not change otherwise it will get changed.
Resource levelling, Scenario B:
 For example, if both task A and B are on critical path and they are
scheduled on the same time period and required the same resource, “X”.
 If we perform resource leveling in this situation then the project schedule or
critical path will surely get changed.
 It doesn’t matter which task of the two are high-priority than other.
Complete within given time
Complete within given resources
Scheduling is a process for setting in order the various planned activities by fixing the
starting and finishing dates to each part of the work in such a manner that the whole
work should be done in an orderly and systematic way.
For example, a railway map will show a passenger, the route by which he will travel from
one place to another and stations along that route. But the time table will give him the
time element that is the hour when his journey will begin, the time at which the train will
reach at various stations and also the total time that will be required to reach the
destination.
In the same way the planning department will have to frame a time schedule for a
project which will assign definite timings for individual constructional operations
leading to finished product.
SCHEDULING
1) Construction schedule
2) Staff schedule
3) Labor schedule
4) Material schedule
5) Financial schedule
6) Equipment schedule
7) Invoice schedule
8) Estimation of direct and indirect costs
Schedules derived from project schedule
The main objective of network planning is to complete the job within the stipulated
time at minimum cost. At times it becomes necessary to accelerate the completion of
work. This be made possible only by reducing the duration of critical activities. The
duration of critical path can be reduced by the deployment of additional resources e. g
additional labour, shuttering, centering etc., which again increases the cost.
While exploring the possibility of accelerating project completion by arranging additional
critical activities, the following questions require careful consideration.
To what extent the project duration be reduced ?
What is the lowest cost for reducing the project duration to the specified date?
What is the project duration for which the total project cost is the lowest?
Cost time analysis provides answers to these questions. The durations of critical
activities may be reduced in two ways (i) by deploying more resources for early
completion of such activities. (ii) by relaxing the technical specifications for such
activities.
TIME - COST TRADE OFF
If the duration is made longer, cost will be reduced. on the other hand, reducing the
project duration would increase the cost of the project. A decision on this will depend on
whether the commitment of additional resources and expenses is worthwhile.
The Optimum duration will be one which gives the most economic cost for completing
the project. In CPM there are two time cost estimates for each activity:
1. Normal estimate : In normal estimate, highlighting on cost, time being associated
with minimum cost.
2. Crash estimate : In crash estimate emphasis is given to absolute minimum time
required to complete the job. The necessary cost to complete the project with in the
minimum time is provided.
Updating can be defined as planning and programming of the
remaining portion of an activity job, by introducing the latest
information available.
At the end of day of work, the activities of the project must either be
completed, in progress or they may not have started yet.
Some of the activities may not have achieved the required percentage
of progress, which was planned to have achieved on the day of
updating.
Updating
As far as progress is concerned, three possibilities exists:
i) Some or all activities are progressing as per schedule.
ii) Some or all activities are ahead of schedule.
iii) Some or all activities are behind schedule.
If all activities are progressing as per schedule, there is no need for
updating the
network. But, in case of activities are behind schedule, the process of
updating is required to revive the time schedule of various activities on
the arrow diagram. Such revision is known as updating.
Construction Management Guide

More Related Content

What's hot

Critical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksCritical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksPrasad Thanthratey
 
Project management tools and techniques
Project management tools and techniquesProject management tools and techniques
Project management tools and techniquesTata Dinyuy
 
Presentation on Cost Overrun ( Project Management)
Presentation on Cost Overrun ( Project Management)Presentation on Cost Overrun ( Project Management)
Presentation on Cost Overrun ( Project Management)FahadHasan36
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost ManagementBhuWan Khadka
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULEAjeesh Mk
 
Construction Project management
Construction Project management Construction Project management
Construction Project management Anupama holla
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project ManagementAravind Samala
 
Work breakdown structure ppt
Work breakdown structure pptWork breakdown structure ppt
Work breakdown structure pptnazi2020
 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Akaresh Jose Kaviyil JY
 
construction project planing
 construction project planing construction project planing
construction project planingSANJEEV Wazir
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESPundlik Rathod
 
Project controls
Project controlsProject controls
Project controlsAshok Kumar
 
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...Zulfiquer Ahmed Amin
 
Line of Balance
Line of BalanceLine of Balance
Line of BalanceIJMER
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management Rajat Nainwal
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project managementRahul Dubey
 

What's hot (20)

Critical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksCritical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/Slacks
 
Project management tools and techniques
Project management tools and techniquesProject management tools and techniques
Project management tools and techniques
 
Presentation on Cost Overrun ( Project Management)
Presentation on Cost Overrun ( Project Management)Presentation on Cost Overrun ( Project Management)
Presentation on Cost Overrun ( Project Management)
 
Construction Cost Control
Construction Cost ControlConstruction Cost Control
Construction Cost Control
 
09. Project Cost Management
09. Project Cost Management09. Project Cost Management
09. Project Cost Management
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
crashing of project
crashing of project crashing of project
crashing of project
 
Construction Project management
Construction Project management Construction Project management
Construction Project management
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
Work breakdown structure ppt
Work breakdown structure pptWork breakdown structure ppt
Work breakdown structure ppt
 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )
 
construction project planing
 construction project planing construction project planing
construction project planing
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPES
 
Pert and CPM
Pert and CPMPert and CPM
Pert and CPM
 
Project controls
Project controlsProject controls
Project controls
 
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
 
Line of Balance
Line of BalanceLine of Balance
Line of Balance
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
 
Pert & Cpm
Pert & CpmPert & Cpm
Pert & Cpm
 

Similar to Construction Management Guide

TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWAREKHUSHBU SHAH
 
Project schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & TechniquesProject schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & TechniquesSHAZEBALIKHAN1
 
Resource-Allocation.ppt
Resource-Allocation.pptResource-Allocation.ppt
Resource-Allocation.pptTecnicoItca
 
Resource Optimization of Construction Project Using Primavera P6
Resource Optimization of Construction Project Using Primavera P6Resource Optimization of Construction Project Using Primavera P6
Resource Optimization of Construction Project Using Primavera P6IOSRJMCE
 
Planning and scheduling Techniques.ppt
Planning and scheduling  Techniques.pptPlanning and scheduling  Techniques.ppt
Planning and scheduling Techniques.pptDejeneTsegaye6
 
Modul 06 penentuan durasi kegiatan
Modul 06 penentuan durasi kegiatanModul 06 penentuan durasi kegiatan
Modul 06 penentuan durasi kegiatanmelchioreq
 
Scheduling coordination and control of projects
Scheduling coordination and control of projects Scheduling coordination and control of projects
Scheduling coordination and control of projects Somashekar S.M
 
An Introduction To The Resource Constrained Project Scheduling Problem Solvin...
An Introduction To The Resource Constrained Project Scheduling Problem Solvin...An Introduction To The Resource Constrained Project Scheduling Problem Solvin...
An Introduction To The Resource Constrained Project Scheduling Problem Solvin...Courtney Esco
 
PMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docxPMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docxstilliegeorgiana
 
Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...
Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...
Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...HIMADRI BANERJI
 
Most Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsMost Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsSHAZEBALIKHAN1
 
PM Session 6
PM Session 6PM Session 6
PM Session 6dmdk12
 
Network diagrams
Network diagramsNetwork diagrams
Network diagramsLii Van
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Schedulingsslovepk
 
Earned value analysis for a construction project
Earned value analysis for a construction projectEarned value analysis for a construction project
Earned value analysis for a construction projectIAEME Publication
 

Similar to Construction Management Guide (20)

TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
 
Project schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & TechniquesProject schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & Techniques
 
Resource-Allocation.ppt
Resource-Allocation.pptResource-Allocation.ppt
Resource-Allocation.ppt
 
B012440511
B012440511B012440511
B012440511
 
Resource Optimization of Construction Project Using Primavera P6
Resource Optimization of Construction Project Using Primavera P6Resource Optimization of Construction Project Using Primavera P6
Resource Optimization of Construction Project Using Primavera P6
 
Planning and scheduling Techniques.ppt
Planning and scheduling  Techniques.pptPlanning and scheduling  Techniques.ppt
Planning and scheduling Techniques.ppt
 
Modul 06 penentuan durasi kegiatan
Modul 06 penentuan durasi kegiatanModul 06 penentuan durasi kegiatan
Modul 06 penentuan durasi kegiatan
 
Scheduling coordination and control of projects
Scheduling coordination and control of projects Scheduling coordination and control of projects
Scheduling coordination and control of projects
 
An Introduction To The Resource Constrained Project Scheduling Problem Solvin...
An Introduction To The Resource Constrained Project Scheduling Problem Solvin...An Introduction To The Resource Constrained Project Scheduling Problem Solvin...
An Introduction To The Resource Constrained Project Scheduling Problem Solvin...
 
PMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docxPMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docx
 
Pm chapter 5...
Pm chapter 5...Pm chapter 5...
Pm chapter 5...
 
Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...
Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...
Project Management Series By Himadri Banerji: The New Frontiers From Himadri ...
 
ch09s.ppt
ch09s.pptch09s.ppt
ch09s.ppt
 
Most Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsMost Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management Terms
 
PM Session 6
PM Session 6PM Session 6
PM Session 6
 
Network diagrams
Network diagramsNetwork diagrams
Network diagrams
 
Pert Cpm Nis
Pert   Cpm NisPert   Cpm Nis
Pert Cpm Nis
 
Ch6 resources
Ch6 resourcesCh6 resources
Ch6 resources
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Scheduling
 
Earned value analysis for a construction project
Earned value analysis for a construction projectEarned value analysis for a construction project
Earned value analysis for a construction project
 

More from Shree Swami atmanand saraswati inst. of technology, surat

More from Shree Swami atmanand saraswati inst. of technology, surat (20)

INFRASTRUCTURE FOR SMART CITIES_MOD 2_planning for smart cities
INFRASTRUCTURE FOR SMART CITIES_MOD 2_planning for smart citiesINFRASTRUCTURE FOR SMART CITIES_MOD 2_planning for smart cities
INFRASTRUCTURE FOR SMART CITIES_MOD 2_planning for smart cities
 
INFRASTRUCTURE FOR SMART CITIES_MOD 3_Intelligent transport systems
INFRASTRUCTURE FOR SMART CITIES_MOD 3_Intelligent transport systemsINFRASTRUCTURE FOR SMART CITIES_MOD 3_Intelligent transport systems
INFRASTRUCTURE FOR SMART CITIES_MOD 3_Intelligent transport systems
 
Sem 5 mod-1 disaster management introduction (CIVIL, ELE, MECH, EC, COMP)
Sem 5 mod-1 disaster management introduction (CIVIL, ELE, MECH, EC, COMP)Sem 5 mod-1 disaster management introduction (CIVIL, ELE, MECH, EC, COMP)
Sem 5 mod-1 disaster management introduction (CIVIL, ELE, MECH, EC, COMP)
 
BCT Mod 4 demolition of structure (Updated)
BCT Mod 4 demolition of structure (Updated)BCT Mod 4 demolition of structure (Updated)
BCT Mod 4 demolition of structure (Updated)
 
MOD 3 CONSTRUCTION ECONOMICS (UPDATED)
MOD 3 CONSTRUCTION ECONOMICS (UPDATED)MOD 3 CONSTRUCTION ECONOMICS (UPDATED)
MOD 3 CONSTRUCTION ECONOMICS (UPDATED)
 
MODULE 2 PROJECT ORGANIZATION (updated)
MODULE 2 PROJECT ORGANIZATION (updated)MODULE 2 PROJECT ORGANIZATION (updated)
MODULE 2 PROJECT ORGANIZATION (updated)
 
BCT- Module 5 a coffer-dam (Part_2)
BCT- Module 5 a coffer-dam (Part_2)BCT- Module 5 a coffer-dam (Part_2)
BCT- Module 5 a coffer-dam (Part_2)
 
BCT - Module 5 special work
BCT - Module 5 special workBCT - Module 5 special work
BCT - Module 5 special work
 
Module :- 8 Job layout (PART 2)
Module :- 8 Job layout (PART 2)Module :- 8 Job layout (PART 2)
Module :- 8 Job layout (PART 2)
 
Module :- 8 material management
Module :- 8 material managementModule :- 8 material management
Module :- 8 material management
 
Mod 3 construction economics
Mod 3 construction economicsMod 3 construction economics
Mod 3 construction economics
 
MODULE 2 project organization
MODULE 2 project organizationMODULE 2 project organization
MODULE 2 project organization
 
MODULE 1 Introduction to Construction Management
MODULE 1 Introduction to Construction ManagementMODULE 1 Introduction to Construction Management
MODULE 1 Introduction to Construction Management
 
Che 10 engineering fundamental
Che  10 engineering fundamentalChe  10 engineering fundamental
Che 10 engineering fundamental
 
Chapter 9 introduction to construction equipments
Chapter  9 introduction to construction equipmentsChapter  9 introduction to construction equipments
Chapter 9 introduction to construction equipments
 
CHE :- 6 form work (MODULE 3)
CHE :- 6 form work (MODULE 3)CHE :- 6 form work (MODULE 3)
CHE :- 6 form work (MODULE 3)
 
Che 1 pile foundation
Che 1 pile foundationChe 1 pile foundation
Che 1 pile foundation
 
Ch 5 b remote sensing
Ch 5 b remote sensingCh 5 b remote sensing
Ch 5 b remote sensing
 
Ch 5 a gps
Ch 5 a gpsCh 5 a gps
Ch 5 a gps
 
Ch 5 levelling
Ch 5 levellingCh 5 levelling
Ch 5 levelling
 

Recently uploaded

BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docxPoojaSen20
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxRoyAbrique
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfakmcokerachita
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesFatimaKhan178732
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 

Recently uploaded (20)

BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docx
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
Staff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSDStaff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSD
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdf
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and Actinides
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 

Construction Management Guide

  • 1. PREPARED BY:- Karm Balar Asst. Prof. S.S.A.S.I.T. S.S.A.S.I.T G.T.U SHREE SWAMI ATMANAND SARASWATI INSTITUTE OF TECHNOLOGY, SURAT Construction management
  • 2. Introduction Resource leveling Resource allocation Other schedules derived from project schedules Network crashing and cost-time trade-off Contents
  • 3. The scheduling of activities, so that none of the precedence relationships are violated and none of the resource availabilities are exceeded, is a difficult task and can result in a number of combinations of possible early start and late start schedules. In literature, scheduling problems with limited resources is classified as large combinatorial problem. A number of programs based on some rules of thumb (also called heuristic) have been developed to solve such problems. These heuristic programs for resource scheduling can be broadly classified under two categories: (1) Resource leveling and (2) Resource allocation Introduction
  • 4. The resource allocation procedure mainly consists of two activities: (i) Resource smoothing (ii) Resource levelling. Resource Leveling and Resource Smoothing are two resource optimization techniques. Resource Leveling is performed to balance the demand and supply of resources. Resource Smoothing is performed to achieve a more uniform resource utilization over a period of time. Resource Leveling may change the critical path of the project, whereas Resource Smoothing does not. Methods of resource allocation
  • 5. Resource smoothing Resource Smoothing: Resource Smoothing is a resource optimization technique in which the Project Manager adjusts the timing of different activities so that the requirement for resources does not exceed a certain pre-defined limit. The objective is to complete the work by the required date while avoiding peaks resource demand. The intelligent utilization of floats can smoothen the demand of resources to the maximum possible extent is called resource Smoothing. In other words, activities may only be delayed within their free and total float.
  • 6. The resource smoothing is applied in such a way that the total project duration remains the same i.e. there is no change in the total duration of the project. First, the periods of minimum demand for resources are determined or located and the activities are shifted according to the availability of float and requirement of resources. Thus the intelligent use of floats can smoothen the demand to the maximum possible extent. This type of resource allocation is known as resource smoothing
  • 7. Resource leveling Resource Leveling is a resource optimization technique in which the Project Manager adjusts the start dates and finish dates of different activities in order to balance the demand for resources vs available supply. If the demand of a resource is more than its availability, then the only alternative is to delay the activity having maximum float. This process is called resource levelling. If there are more than one activities requiring the same amount of resources, in that case activity having minimum duration is chosen for resource reallocation. Resource levelling is adopted in case there is restriction on the availability resources
  • 8. Resource levelling, Scenario A:  For example, if there are two task on project network diagram and they are scheduled on the same time period and both required the same resource, “X”.  Task A is on critical path, Task B is on non-critical path which means which has float.  Further assume, the task A is high priority task than the task B.  In this situation, if we perform resource levelling, the project schedule or critical path may or may not change.  If the levelling delay within the free or total float the project schedule will not change otherwise it will get changed. Resource levelling, Scenario B:  For example, if both task A and B are on critical path and they are scheduled on the same time period and required the same resource, “X”.  If we perform resource leveling in this situation then the project schedule or critical path will surely get changed.  It doesn’t matter which task of the two are high-priority than other.
  • 9. Complete within given time Complete within given resources
  • 10. Scheduling is a process for setting in order the various planned activities by fixing the starting and finishing dates to each part of the work in such a manner that the whole work should be done in an orderly and systematic way. For example, a railway map will show a passenger, the route by which he will travel from one place to another and stations along that route. But the time table will give him the time element that is the hour when his journey will begin, the time at which the train will reach at various stations and also the total time that will be required to reach the destination. In the same way the planning department will have to frame a time schedule for a project which will assign definite timings for individual constructional operations leading to finished product. SCHEDULING
  • 11. 1) Construction schedule 2) Staff schedule 3) Labor schedule 4) Material schedule 5) Financial schedule 6) Equipment schedule 7) Invoice schedule 8) Estimation of direct and indirect costs Schedules derived from project schedule
  • 12.
  • 13.
  • 14.
  • 15.
  • 16. The main objective of network planning is to complete the job within the stipulated time at minimum cost. At times it becomes necessary to accelerate the completion of work. This be made possible only by reducing the duration of critical activities. The duration of critical path can be reduced by the deployment of additional resources e. g additional labour, shuttering, centering etc., which again increases the cost. While exploring the possibility of accelerating project completion by arranging additional critical activities, the following questions require careful consideration. To what extent the project duration be reduced ? What is the lowest cost for reducing the project duration to the specified date? What is the project duration for which the total project cost is the lowest? Cost time analysis provides answers to these questions. The durations of critical activities may be reduced in two ways (i) by deploying more resources for early completion of such activities. (ii) by relaxing the technical specifications for such activities. TIME - COST TRADE OFF
  • 17. If the duration is made longer, cost will be reduced. on the other hand, reducing the project duration would increase the cost of the project. A decision on this will depend on whether the commitment of additional resources and expenses is worthwhile. The Optimum duration will be one which gives the most economic cost for completing the project. In CPM there are two time cost estimates for each activity: 1. Normal estimate : In normal estimate, highlighting on cost, time being associated with minimum cost. 2. Crash estimate : In crash estimate emphasis is given to absolute minimum time required to complete the job. The necessary cost to complete the project with in the minimum time is provided.
  • 18. Updating can be defined as planning and programming of the remaining portion of an activity job, by introducing the latest information available. At the end of day of work, the activities of the project must either be completed, in progress or they may not have started yet. Some of the activities may not have achieved the required percentage of progress, which was planned to have achieved on the day of updating. Updating
  • 19. As far as progress is concerned, three possibilities exists: i) Some or all activities are progressing as per schedule. ii) Some or all activities are ahead of schedule. iii) Some or all activities are behind schedule. If all activities are progressing as per schedule, there is no need for updating the network. But, in case of activities are behind schedule, the process of updating is required to revive the time schedule of various activities on the arrow diagram. Such revision is known as updating.