SlideShare a Scribd company logo
1 of 18
Download to read offline
ADVANCED BUILDING
CONSTRUCTION AND
EARTHQUAKE RESISTANT
TECHNOLOGY
5th Semester
List of books for reference:
SYLLABUS :
• Introduction.
• Pile foundation.
• Building planning and orientation.
• Fire protection and building acoustics.
• Earthquake.
• Seismic performance of RCC building.
• Ductile detailing of RCC building.
• Strengthening and retrofitting of existing building.
Introduction:
Excavation- Setting out of foundation trenches.
• Setting out of foundation trenches is the process of laying down the
excavation line and centerline etc.on the ground as per the drawing or
foundation plan. The setting out process is also called as ground tracing
that is performed before commencing the excavation process.
• Once the design of foundation is complete, a setting out plan or foundation
layout is prepared for a suitable scale and the plan is dimensioned
accordingly.
• There are two main purposes of this process-
1. The excavation of foundation trenches can be started immediately after
this setting out process is completed.
2. The lines or marks established by this process serve as a guide and
provides checks in the construction of the foundation work.
The basic steps involved in setting out the
foundation trenches are:
1.The initial step is to mark the corners of the building. After which, the
lengths of the sides are checked by diagonal measurements.
2. The centre line of the longest outer wall of the building is first laid down
over the ground by stretching a string between wooden pegs. For big
project reference pillars are used which are 20cm thick and 15cm wider
than the width of the foundation trenches.
3. Small nails are fixed at the head of the peg for accurate measurement.
Each peg may be projected about 2.5cm to 5cm from the ground level and
2m from the edge of the excavation.
4. The line can be transferred to the ground by using dry lime powder .
5. The centre lines of the other walls which are perpendicular to the longest
wall are then laid down by forming a 3,4,5 triangle or theodolite or
compass.
Excavation Procedure for Foundation
• After completion ground tracing or setting of foundation trenches,
excavation of foundation can be started.
• Workers should be instructed to dig only within the demarcated lines.
Excavated soil should be deposited on the both sides of the trench by
leaving some suitable space so that excavated soil may not fall back
into the trench.
• For small buildings, excavation is carried out manually by means of
pick axes, crow bars, spades etc. In case of large buildings and deep
excavation, mechanical earth cutting equipment can be used.
• For hard soils when the depth of excavation is less than 1.5 m, the
sides of the trench do not need any external support. If the soil is
loose or the excavation is deeper, some sort of shoring is required to
support the sides from falling.
1. Stay bracing
This method is used for supporting the sides or a trench excavated in
fairly firm soil, when the depth of excavation does not exceed about 2
metres. The method consists of placing vertical sheets or polling boards
opposite each other against the two walls of the trench and holding
them in position by one or two rows of struts.
The sheets are placed at an interval of 2 to 4 metres and generally,
they extend to the full height of the trench. The polling boards may
have width of about 200 mm and thickness of 44 to 50 mm. The struts
may have size 100 x 100 mm for trench upto 2 m width and 200 x 200
mm for trench upto 4 m width.
Stay bracing.
2.Box Sheeting:
• This method is adopted in loose soils, when the depth of excavation
does not exceed 4 metres. The box like structure, consisting of
vertical sheets placed very near to each other (some times touching
each other) and keeping them in position by longitudinal rows
(usually two) of wales. Struts are then provided across the wales.
Box sheeting
3.Vertical Sheeting:
This system is adopted for deep trenches (upto 10 m depth) in soft
ground.The method is similar to the box sheeting except that the
excavation is carried out in stages and at the end of each stage, an
offset is provided, so that the width of the trench goes on decreasing as
the depth increases. Each stage is limited to about 3 m height and the
offset may vary from 25 to 50 cm per stage. For each stage, separate
vertical sheeting, supported by horizontal wales and struts are
provided.
Vertical sheeting.
4. Runner System:
This system is used in extremely loose and soft ground, which needs
immediate support as excavation progresses.The system is similar to
vertical sheeting of box system, except that in the place of vertical
sheeting, runners made of long thick wooden sheets or planks with
iron shoe at the ends, are provided. Wales and struts are provided as
usual .These runners are driven about 30 cm in advance of the progress
of the work, by hammering.
Renner System.
5.Sheet piling:
• This method is adopted when
1. soil to be excavated is soft or loose .
2. depth of excavation is large.
3.width of trench is also large.
4.There is sub-soil water.
• Sheet piles are designed to resist lateral earth pressure. These are
driven in the ground by mechanical means (pile driving equipment).
They can be used for excavating to a very large depth.
ABC 1st Week(2hrs

More Related Content

Similar to ABC 1st Week(2hrs

foundation-shallow foundation.pptx
foundation-shallow foundation.pptxfoundation-shallow foundation.pptx
foundation-shallow foundation.pptxNisthaPathak2
 
sm-1_chap._6_geotechnical_investigation.pptx
sm-1_chap._6_geotechnical_investigation.pptxsm-1_chap._6_geotechnical_investigation.pptx
sm-1_chap._6_geotechnical_investigation.pptxpavuluri2014
 
Tunneling in soft ground and hard rock
Tunneling in soft ground and hard rockTunneling in soft ground and hard rock
Tunneling in soft ground and hard rockkamariya keyur
 
MODULE-V INFRASTRUCTURE ENGINEERING BTCVC702
MODULE-V INFRASTRUCTURE ENGINEERING BTCVC702MODULE-V INFRASTRUCTURE ENGINEERING BTCVC702
MODULE-V INFRASTRUCTURE ENGINEERING BTCVC702Dr. BASWESHWAR JIRWANKAR
 
building foundation kagemu SELEMANI
building foundation kagemu SELEMANIbuilding foundation kagemu SELEMANI
building foundation kagemu SELEMANISosthenes Laizer
 
METHODS OF TUNNELLING IN SOFT & HARD GROUND.pdf
METHODS OF TUNNELLING IN SOFT & HARD GROUND.pdfMETHODS OF TUNNELLING IN SOFT & HARD GROUND.pdf
METHODS OF TUNNELLING IN SOFT & HARD GROUND.pdfEr Adil Khan
 
Excavation and Ground water control1.pptx
Excavation and Ground water control1.pptxExcavation and Ground water control1.pptx
Excavation and Ground water control1.pptxssusercbae26
 
foundationtypes-161207082056.pdf
foundationtypes-161207082056.pdffoundationtypes-161207082056.pdf
foundationtypes-161207082056.pdfJitendraKumar999098
 
soil retention in construction -Group 7 powerpoint
    soil retention in construction -Group 7 powerpoint    soil retention in construction -Group 7 powerpoint
soil retention in construction -Group 7 powerpointLawin Langat
 
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining StructuresEXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining StructuresShivananda Roy
 
Chapter 4 control of ground water in excavations
Chapter 4 control of ground water in excavationsChapter 4 control of ground water in excavations
Chapter 4 control of ground water in excavationsKHUSHBU SHAH
 
Chapter-1-Soil Exploration.ppt
Chapter-1-Soil Exploration.pptChapter-1-Soil Exploration.ppt
Chapter-1-Soil Exploration.pptestifanosdemeke1
 

Similar to ABC 1st Week(2hrs (20)

Foundation
FoundationFoundation
Foundation
 
foundation-shallow foundation.pptx
foundation-shallow foundation.pptxfoundation-shallow foundation.pptx
foundation-shallow foundation.pptx
 
UNIT 1a.pdf
UNIT 1a.pdfUNIT 1a.pdf
UNIT 1a.pdf
 
sm-1_chap._6_geotechnical_investigation.pptx
sm-1_chap._6_geotechnical_investigation.pptxsm-1_chap._6_geotechnical_investigation.pptx
sm-1_chap._6_geotechnical_investigation.pptx
 
Tunneling in soft ground and hard rock
Tunneling in soft ground and hard rockTunneling in soft ground and hard rock
Tunneling in soft ground and hard rock
 
Foundation
FoundationFoundation
Foundation
 
MODULE-V INFRASTRUCTURE ENGINEERING BTCVC702
MODULE-V INFRASTRUCTURE ENGINEERING BTCVC702MODULE-V INFRASTRUCTURE ENGINEERING BTCVC702
MODULE-V INFRASTRUCTURE ENGINEERING BTCVC702
 
UNIT-2.pptx
UNIT-2.pptxUNIT-2.pptx
UNIT-2.pptx
 
Building foundation
Building foundationBuilding foundation
Building foundation
 
building foundation kagemu SELEMANI
building foundation kagemu SELEMANIbuilding foundation kagemu SELEMANI
building foundation kagemu SELEMANI
 
METHODS OF TUNNELLING IN SOFT & HARD GROUND.pdf
METHODS OF TUNNELLING IN SOFT & HARD GROUND.pdfMETHODS OF TUNNELLING IN SOFT & HARD GROUND.pdf
METHODS OF TUNNELLING IN SOFT & HARD GROUND.pdf
 
1.2 Diaphragm walls.pptx
1.2 Diaphragm walls.pptx1.2 Diaphragm walls.pptx
1.2 Diaphragm walls.pptx
 
Excavation and Ground water control1.pptx
Excavation and Ground water control1.pptxExcavation and Ground water control1.pptx
Excavation and Ground water control1.pptx
 
foundationtypes-161207082056.pdf
foundationtypes-161207082056.pdffoundationtypes-161207082056.pdf
foundationtypes-161207082056.pdf
 
Foundation types
Foundation typesFoundation types
Foundation types
 
soil retention in construction -Group 7 powerpoint
    soil retention in construction -Group 7 powerpoint    soil retention in construction -Group 7 powerpoint
soil retention in construction -Group 7 powerpoint
 
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining StructuresEXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
 
Chapter 4 control of ground water in excavations
Chapter 4 control of ground water in excavationsChapter 4 control of ground water in excavations
Chapter 4 control of ground water in excavations
 
Tunnel Engineering.pptx
Tunnel Engineering.pptxTunnel Engineering.pptx
Tunnel Engineering.pptx
 
Chapter-1-Soil Exploration.ppt
Chapter-1-Soil Exploration.pptChapter-1-Soil Exploration.ppt
Chapter-1-Soil Exploration.ppt
 

Recently uploaded

result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 

Recently uploaded (20)

result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 

ABC 1st Week(2hrs

  • 1. ADVANCED BUILDING CONSTRUCTION AND EARTHQUAKE RESISTANT TECHNOLOGY 5th Semester
  • 2. List of books for reference:
  • 3. SYLLABUS : • Introduction. • Pile foundation. • Building planning and orientation. • Fire protection and building acoustics. • Earthquake. • Seismic performance of RCC building. • Ductile detailing of RCC building. • Strengthening and retrofitting of existing building.
  • 4. Introduction: Excavation- Setting out of foundation trenches. • Setting out of foundation trenches is the process of laying down the excavation line and centerline etc.on the ground as per the drawing or foundation plan. The setting out process is also called as ground tracing that is performed before commencing the excavation process. • Once the design of foundation is complete, a setting out plan or foundation layout is prepared for a suitable scale and the plan is dimensioned accordingly. • There are two main purposes of this process- 1. The excavation of foundation trenches can be started immediately after this setting out process is completed. 2. The lines or marks established by this process serve as a guide and provides checks in the construction of the foundation work.
  • 5. The basic steps involved in setting out the foundation trenches are: 1.The initial step is to mark the corners of the building. After which, the lengths of the sides are checked by diagonal measurements. 2. The centre line of the longest outer wall of the building is first laid down over the ground by stretching a string between wooden pegs. For big project reference pillars are used which are 20cm thick and 15cm wider than the width of the foundation trenches. 3. Small nails are fixed at the head of the peg for accurate measurement. Each peg may be projected about 2.5cm to 5cm from the ground level and 2m from the edge of the excavation. 4. The line can be transferred to the ground by using dry lime powder . 5. The centre lines of the other walls which are perpendicular to the longest wall are then laid down by forming a 3,4,5 triangle or theodolite or compass.
  • 6.
  • 7. Excavation Procedure for Foundation • After completion ground tracing or setting of foundation trenches, excavation of foundation can be started. • Workers should be instructed to dig only within the demarcated lines. Excavated soil should be deposited on the both sides of the trench by leaving some suitable space so that excavated soil may not fall back into the trench. • For small buildings, excavation is carried out manually by means of pick axes, crow bars, spades etc. In case of large buildings and deep excavation, mechanical earth cutting equipment can be used. • For hard soils when the depth of excavation is less than 1.5 m, the sides of the trench do not need any external support. If the soil is loose or the excavation is deeper, some sort of shoring is required to support the sides from falling.
  • 8.
  • 9. 1. Stay bracing This method is used for supporting the sides or a trench excavated in fairly firm soil, when the depth of excavation does not exceed about 2 metres. The method consists of placing vertical sheets or polling boards opposite each other against the two walls of the trench and holding them in position by one or two rows of struts. The sheets are placed at an interval of 2 to 4 metres and generally, they extend to the full height of the trench. The polling boards may have width of about 200 mm and thickness of 44 to 50 mm. The struts may have size 100 x 100 mm for trench upto 2 m width and 200 x 200 mm for trench upto 4 m width.
  • 11. 2.Box Sheeting: • This method is adopted in loose soils, when the depth of excavation does not exceed 4 metres. The box like structure, consisting of vertical sheets placed very near to each other (some times touching each other) and keeping them in position by longitudinal rows (usually two) of wales. Struts are then provided across the wales.
  • 13. 3.Vertical Sheeting: This system is adopted for deep trenches (upto 10 m depth) in soft ground.The method is similar to the box sheeting except that the excavation is carried out in stages and at the end of each stage, an offset is provided, so that the width of the trench goes on decreasing as the depth increases. Each stage is limited to about 3 m height and the offset may vary from 25 to 50 cm per stage. For each stage, separate vertical sheeting, supported by horizontal wales and struts are provided.
  • 15. 4. Runner System: This system is used in extremely loose and soft ground, which needs immediate support as excavation progresses.The system is similar to vertical sheeting of box system, except that in the place of vertical sheeting, runners made of long thick wooden sheets or planks with iron shoe at the ends, are provided. Wales and struts are provided as usual .These runners are driven about 30 cm in advance of the progress of the work, by hammering.
  • 17. 5.Sheet piling: • This method is adopted when 1. soil to be excavated is soft or loose . 2. depth of excavation is large. 3.width of trench is also large. 4.There is sub-soil water. • Sheet piles are designed to resist lateral earth pressure. These are driven in the ground by mechanical means (pile driving equipment). They can be used for excavating to a very large depth.