SlideShare a Scribd company logo
helpdesk@construction-productivity.co.uk
htt://www.construction-productivity.co.uk
WORK BREAK DOWNWORK BREAK DOWN
STRUCTURE (WBS)STRUCTURE (WBS)
WORK BRAEK DOWN STRUCTURE (WBS)
A technique by which
the work of a project is
divided and sub divided
for management, and
control purposes.
WORK BRAEK DOWN STRUCTURE
(WBS)
The work is developed through successive
increasing levels of details.
Advantage
• work delegated into coherent packages
• work defined at appropriate levels of detail
for cost control
WORK BRAEK DOWN STRUCTURE
(WBS)
• work defined at appropriate levels of detail
for nesting plans i.e. rolling wave of
program.
• Variances can be measured between
Planned and Actual.
• The work packages are more stable than
long chains of discontinuous work
activities.
• As a result risk is more contained and
measured more accurately.
WORK BRAEK DOWN STRUCTURE
(WBS)
• successive levels of detail may be evolved
• the project sponsor may call for reports
from the Project manager based on the
work content at Level 1, 2 and sometimes
at Level 3,
WORK BRAEK DOWN STRUCTURE
(WBS)
• the Project Manger may call for Reports
from Project Contributors based on work
content at Level 3, 4 and 5,
• the contractor’s Construction Management
Team also may ask for report from Site
Engineers at Level 5 and below Level 5,
WORK BRAEK DOWN STRUCTURE
(WBS)
• Different Levels Breakdown
and Work Package require
different Project Contributors
with different Responsibilities.
• The flow is from Left to Right.
WORK BRAEK DOWN STRUCTURE
(WBS)
• successively at each Level, may be
made to mirror the timing of the work;
• and facilities a Rolling Wave or
Nested Programme;
• from project level down to the lowest
task orientated package level.
WORK BRAEK DOWN STRUCTURE
(WBS)
• each work package can be identified with
a unique cost code;
• and Actual and Planned Cost variances
compared;
• each work package can be fully described,
for example:
• Content;
• what is included and what is excluded in a
package statement.
• WBS (Food Process Factory)-Level
1
Project Definition/Scope
Management Site
Procurement
Outline
Design &
State
Approval
Detail
Design &
Costing
Procurement
And
Construction
Commision
&
Handover
Left to right
WORK BRAEK DOWN STRUCTURE (WBS)
Procurement&
Construction
Bill of
Quantity
Tender &
Negotiation
Work on
Site
Management
Fees
LEFT TO RIGHT
WBS (Food Process Factory)-Level 3
WORK BRAEK DOWN STRUCTURE (WBS)
Work on Site
Preliminary
Works
Sub-
structure
Super-
structure
Claddind &
Envelope
External
Work
Internal
Work
WBS (Food Process Factory)-Level 4 and 5
WORK BRAEK DOWN STRUCTURE (WBS)
Work on Site
Total cost £1, 900, 250.00
Preliminary
Works
£105.000.00
Sub-
structure
£270.00
Super-
Structure
£
Claddind &
Envelope
£
External
Work
£
Internal
Work
£
Site
Clearance
£
Piling
£
Foundation
s
£
Drainage
£
Floor slab
£
WORK BRAEK DOWN STRUCTURE
(WBS)
Project Mgmt
Prelim Design
1.1.1
Title I Design
1.1.2
Final Design
1.1.3
Design
1.1
Procurement
1.2
Construction
1.3 1.4
ACME Project X
1.0
Resource allocation
Project Mgmt
Prelim Design
1.1.1
Title I Design
1.1.2
Final Design
1.1.3
Design
1.1
Procurement
1.2
Construction
1.3 1.4
ACME Project X
1.0
Preliminary Design 1.1.1 Jan Feb Mar Apr May
1.1.1.1 Define Specifications & Req.
1.1.1.2 Develop Preliminary Design
1.1.1.3 Review Preliminary Design
1.1.1.4 Incorporate Comments
1.1.1.5 Preliminary Design Complete
Resource allocation
Project Mgmt
Prelim Design
1.1.1
Title I Design
1.1.2
Final Design
1.1.3
Design
1.1
Procurement
1.2
Construction
1.3 1.4
ACME Project X
1.0
Preliminary Design 1.1.1 Hours Jan Feb Mar Apr May
1.1.1.1 Define Specifications & Req. 1,500 1,000
1.1.1.2 Develop Preliminary Design 2,000 2,000
1.1.1.3 Review Preliminary Design 500 500
1.1.1.4 Incorporate Comments 320 320
1.1.1.5 Preliminary Design Complete 1,000
Resource allocation for each
activity
Project Mgmt
Prelim Design
1.1.1
Title I Design
1.1.2
Final Design
1.1.3
Design
1.1
Procurement
1.2
Construction
1.3 1.4
ACME Project X
1.0
Preliminary Design 1.1.1 Hours Jan Feb Mar Apr May
1.1.1.1 Define Specifications & Req.
1,500 1,000
1.1.1.2 Develop Preliminary Design
2,000 2,000
1.1.1.3 Review Preliminary Design
500 500
1.1.1.4 Incorporate Comments
320 320
1.1.1.5 Preliminary Design Complete
1,000
Resource allocation
ACME Housing Corporation
1
House Building
Project
1.1
Concrete
1.1.1
Framing
1.1.2
Plumbing
1.1.3
Electrical
1.1.4
Interior
1.1.5
Roofing
1.1.6
Resource allocation-after WBS
ACME Housing Corporation
1
House Building
Project
1.1
Concrete
1.1.1
Pour Foundation
1.1.1.1
Install Patio
1.1.1.2
Stairway
1.1.1.3
Framing
1.1.2
Frame Exterior
Walls
1.1.2.1
Frame Interior
Walls
1.1.2.2
Install Roofing
Trusses
1.1.2.3
Plumbing
1.1.3
Install Water
Lines
1.1.3.1
Install Gas Lines
1.1.3.2
Install B/K
Fixtures
1.1.3.3
Electrical
1.1.4
Install Wiring
1.1.4.1
Install Outlets/
Switches
1.1.4.2
Install Fixtures
1.1.4.3
Interior
1.1.5
Install Drywall
1.1.5.1
Install Carpets
1.1.5.2
Install Painting
1.1.5.3
Roofing
1.1.6
Install Felt
1.1.6.1
Install Shingles
1.1.6.2
Install Vents
1.1.6.3
MILESTONE PROGRAMMING
• The Milestone programmes provide the
‘administrative level’ in the planning
hierarchy.
• The activity programme provides the
detailed ‘technical level’.
• It focused on goals and not on the method of
reaching them.
• The Milestones and Objectives remain
reasonably constant through out the project.
• Methods of reaching goals may change.
MILESTONE PROGRAMMING
• Goal Directed Project Management
(GDPM) is a powerful, pragmatic
approach for gaining consensus from
all stakeholders on the overall
objectives of a business program or
project.
MILESTONE PROGRAMMING
• The approach is fully compatible with
industry standards such as:
• PRINCE2
• SUMMIT
• V-Model or HERMES
• It provides a single-page, top-level view of
the goals of the project (a milestone plan).
DEVELOPING THE MILESTONE PROGRAMME
1-The planning team
• The team responsible for ensuring
that the project objectives are met
should be present to formulate the
Milestone programme.
2-The result paths
• The project Objectives and Scope are
set out in the project definition
Document.
MILESTONE PROGRAMMING
• The team considers at each level, the
Primary Objectives such as:
• How will success be judged?
• What are the critical factors to monitor?
• What are Key Performance Indicators for
this project?
DEVELOPING THE MILESTONE PROGRAMME
3-Milestones
• The team actively generates ideas for the
like list of Milestones.
• Each Milestone description should:
• form a check point towards the final
objective,
• describe a condition or state that the
project must occupy at various stages in
order to reach it’s final objective,
DEVELOPING THE MILESTONE
PROGRAMME
• show a logical sequence towards the final
objective;
• state what to achieve, and not how to
achieve;
• focus on the goal;
• state a specific outcome, such as,
approval of a report and who approve it;
DEVELOPING THE MILESTONE
PROGRAMME
• Also Milestone should:
• be natural;
• represent important decisions;
• be controllable, either quantitively or
qualitatively;
• be few in number (10 TO 20);
• be at useful intervals(ie monthly);
4- Drafting the Milestone Plan
NESTED PROGRAMMING
• The primary objectives of the project
are provided in the Level 1 Project
Programme.
• Below The Work Breakdown Structure
(WBS) most projects are capable of
being split into a member of Stages or
Phases (Work Packages).
NESTED PROGRAMMING
• A milestoneplan may be produced
for each of these phases.
• for example at Level 1-Reported at
20 max controlled Milestones.
• Or at Level-2- let us say 4 Stages –
each Reported at 20 max controlled
Milestones.
NESTED PROGRAMMING
• At Level 3 and below, the influence of
detail activities can make it difficult to
develop meaningful Milestone
Programme.
• At this level down on the WBS, it is
normal to revert to activity
programmes.
NESTED PROGRAMMING
• At the lowest activity and task levels,
Milestones occur along the path of
networked activities (CPM) and are shown
as ‘Flagging’ up on the network or Gantt
chart.
• Some packages allow them to be fixed
and generate ‘Supper Critical Paths’. (See
Oxford Brookes University-Micro Planner).
DEVELOPING THE MILESTONE
PROGRAMME
Conclusion
• The Milestone methods is purely a means of
monitoring and controlling progress towards the
Projects Objectives at the highest level of WBS.
• It is useful where there is insufficient detailed
information to produce meaningful accurate
lower level Activities based programmes.
Define Goals
Tchnological Communication
s
Cost
Latest Process
plant
Latest Road Rail Package
Latest Hygiene Finishes
Latest Building Management System
Latest Computer Process System
Latest Robotics
Negociation
And
Completion
of Rdad/Rail
link to EU
To Cmply with Finacial and
Strategic Plans
Example of Level 1- Factory Project
134 work break break down structure
134 work break break down structure

More Related Content

What's hot

Project cost management
Project cost managementProject cost management
Project cost management
Mohammad Ashraf Khan, PMP
 
Lect-5: Work Breakdown Structure and Project Cost Estimation
Lect-5: Work Breakdown Structure and Project Cost EstimationLect-5: Work Breakdown Structure and Project Cost Estimation
Lect-5: Work Breakdown Structure and Project Cost Estimation
Mubashir Ali
 
Construction Project Process Flow
Construction Project Process FlowConstruction Project Process Flow
Construction Project Process Flow
Rajasekar M
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Scheduling
sslovepk
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
Michael Pink
 
MICROSOFT PROJECT TUTORIAL
MICROSOFT PROJECT TUTORIALMICROSOFT PROJECT TUTORIAL
MICROSOFT PROJECT TUTORIAL
Vismay Shah
 
MS Project Presentation
MS Project PresentationMS Project Presentation
MS Project Presentation
Khem Singh
 
Wbs For Building Project
Wbs For Building ProjectWbs For Building Project
Wbs For Building Project
project management
 
5.1 quantity take-off
5.1 quantity take-off5.1 quantity take-off
5.1 quantity take-off
Ali Juma Albahrani
 
Ms Project Workshop
Ms Project WorkshopMs Project Workshop
Ms Project Workshop
Eder Alves
 
Project Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP WorkgroupProject Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP Workgroup
Tùng Trần Thanh
 
Quantity surveying drawing FNBE 2014
Quantity surveying drawing FNBE 2014Quantity surveying drawing FNBE 2014
Quantity surveying drawing FNBE 2014
Felix Vong
 
Resource allocation and smoothing
Resource allocation and smoothingResource allocation and smoothing
Resource allocation and smoothing
Dr. Mahmoud Al-Naimi
 
Introduction to MS project
Introduction to MS projectIntroduction to MS project
Introduction to MS project
Samir Paralikar
 
Reasons for project failure
Reasons for project failureReasons for project failure
Reasons for project failure
David Tennant
 
3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project management
Kabilan Kabi
 
Scheduling by using microsoft project 2013
Scheduling by using microsoft project 2013Scheduling by using microsoft project 2013
Scheduling by using microsoft project 2013
Chetanraj M
 
Top Ten Reasons Why Projects Fail
Top Ten Reasons Why Projects FailTop Ten Reasons Why Projects Fail
Top Ten Reasons Why Projects Fail
jpstewar
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
Aravind Samala
 
What is a Work Breakdown Structure?
What is a Work Breakdown Structure?What is a Work Breakdown Structure?
What is a Work Breakdown Structure?
Kenny Hirschmann
 

What's hot (20)

Project cost management
Project cost managementProject cost management
Project cost management
 
Lect-5: Work Breakdown Structure and Project Cost Estimation
Lect-5: Work Breakdown Structure and Project Cost EstimationLect-5: Work Breakdown Structure and Project Cost Estimation
Lect-5: Work Breakdown Structure and Project Cost Estimation
 
Construction Project Process Flow
Construction Project Process FlowConstruction Project Process Flow
Construction Project Process Flow
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Scheduling
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
 
MICROSOFT PROJECT TUTORIAL
MICROSOFT PROJECT TUTORIALMICROSOFT PROJECT TUTORIAL
MICROSOFT PROJECT TUTORIAL
 
MS Project Presentation
MS Project PresentationMS Project Presentation
MS Project Presentation
 
Wbs For Building Project
Wbs For Building ProjectWbs For Building Project
Wbs For Building Project
 
5.1 quantity take-off
5.1 quantity take-off5.1 quantity take-off
5.1 quantity take-off
 
Ms Project Workshop
Ms Project WorkshopMs Project Workshop
Ms Project Workshop
 
Project Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP WorkgroupProject Schedule Management - Estimate Activity Durations - PMP Workgroup
Project Schedule Management - Estimate Activity Durations - PMP Workgroup
 
Quantity surveying drawing FNBE 2014
Quantity surveying drawing FNBE 2014Quantity surveying drawing FNBE 2014
Quantity surveying drawing FNBE 2014
 
Resource allocation and smoothing
Resource allocation and smoothingResource allocation and smoothing
Resource allocation and smoothing
 
Introduction to MS project
Introduction to MS projectIntroduction to MS project
Introduction to MS project
 
Reasons for project failure
Reasons for project failureReasons for project failure
Reasons for project failure
 
3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project management
 
Scheduling by using microsoft project 2013
Scheduling by using microsoft project 2013Scheduling by using microsoft project 2013
Scheduling by using microsoft project 2013
 
Top Ten Reasons Why Projects Fail
Top Ten Reasons Why Projects FailTop Ten Reasons Why Projects Fail
Top Ten Reasons Why Projects Fail
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
What is a Work Breakdown Structure?
What is a Work Breakdown Structure?What is a Work Breakdown Structure?
What is a Work Breakdown Structure?
 

Viewers also liked

Work Breakdown Structure
Work Breakdown StructureWork Breakdown Structure
Work Breakdown Structure
project management
 
Wbs Building Use This
Wbs Building Use ThisWbs Building Use This
Wbs Building Use This
project management
 
Construction safety management
Construction safety managementConstruction safety management
Construction safety management
GERServices
 
Work breakdown structure ppt
Work breakdown structure pptWork breakdown structure ppt
Work breakdown structure ppt
nazi2020
 
Certified Master Project Manager MPM
Certified Master Project Manager MPMCertified Master Project Manager MPM
Certified Master Project Manager MPM
Dr Zulk Certified Project Consultant
 
Work breakdown structure
Work breakdown structureWork breakdown structure
Work breakdown structure
MD SABBIR SHARIF
 
Project scheduling and work break down structure(wbs) 12 cs18
Project scheduling and work break down structure(wbs) 12 cs18Project scheduling and work break down structure(wbs) 12 cs18
Project scheduling and work break down structure(wbs) 12 cs18
Engr Imran Ashraf
 
Work Break Down Structure
Work Break Down StructureWork Break Down Structure
Work Break Down Structure
Somtel
 
USAID HOUSING PROGRAM IN HAITI FALLS SHORT
USAID HOUSING PROGRAM IN HAITI FALLS SHORTUSAID HOUSING PROGRAM IN HAITI FALLS SHORT
USAID HOUSING PROGRAM IN HAITI FALLS SHORT
Stanleylucas
 
Sustainable development and project management
Sustainable development and project managementSustainable development and project management
Sustainable development and project management
Omar Latif
 
Work Breakdown Structures (WBS)
Work Breakdown Structures (WBS)Work Breakdown Structures (WBS)
Work Breakdown Structures (WBS)
stakeholdermap
 
Construction Site Health & Safety
Construction Site Health & SafetyConstruction Site Health & Safety
Construction Site Health & Safety
SAURABH SINGH
 
Avoiding Common Legal Billing pitfalls
Avoiding Common Legal Billing pitfallsAvoiding Common Legal Billing pitfalls
Avoiding Common Legal Billing pitfalls
Rakesh (Rick) Kabra
 
Project Management Overview
Project Management OverviewProject Management Overview
Project Management Overview
Madhumalti Sharma
 
Managing Cash Flows On Construction Projects
Managing Cash Flows On Construction ProjectsManaging Cash Flows On Construction Projects
Managing Cash Flows On Construction Projects
AGC of California
 
Hands on Measurement for K-2 Learners
Hands on Measurement for K-2 LearnersHands on Measurement for K-2 Learners
Hands on Measurement for K-2 Learners
mflaming
 
Construction Project Management.
Construction Project Management.Construction Project Management.
Construction Project Management.
Yousef Abujubba
 
Cashbook, Passbook and BRC
Cashbook, Passbook and BRCCashbook, Passbook and BRC
Cashbook, Passbook and BRC
SUDARSHAN KUMAR PATEL
 
Measurements
MeasurementsMeasurements
Work Breakdown Structure Use This
Work Breakdown Structure Use ThisWork Breakdown Structure Use This
Work Breakdown Structure Use This
project management
 

Viewers also liked (20)

Work Breakdown Structure
Work Breakdown StructureWork Breakdown Structure
Work Breakdown Structure
 
Wbs Building Use This
Wbs Building Use ThisWbs Building Use This
Wbs Building Use This
 
Construction safety management
Construction safety managementConstruction safety management
Construction safety management
 
Work breakdown structure ppt
Work breakdown structure pptWork breakdown structure ppt
Work breakdown structure ppt
 
Certified Master Project Manager MPM
Certified Master Project Manager MPMCertified Master Project Manager MPM
Certified Master Project Manager MPM
 
Work breakdown structure
Work breakdown structureWork breakdown structure
Work breakdown structure
 
Project scheduling and work break down structure(wbs) 12 cs18
Project scheduling and work break down structure(wbs) 12 cs18Project scheduling and work break down structure(wbs) 12 cs18
Project scheduling and work break down structure(wbs) 12 cs18
 
Work Break Down Structure
Work Break Down StructureWork Break Down Structure
Work Break Down Structure
 
USAID HOUSING PROGRAM IN HAITI FALLS SHORT
USAID HOUSING PROGRAM IN HAITI FALLS SHORTUSAID HOUSING PROGRAM IN HAITI FALLS SHORT
USAID HOUSING PROGRAM IN HAITI FALLS SHORT
 
Sustainable development and project management
Sustainable development and project managementSustainable development and project management
Sustainable development and project management
 
Work Breakdown Structures (WBS)
Work Breakdown Structures (WBS)Work Breakdown Structures (WBS)
Work Breakdown Structures (WBS)
 
Construction Site Health & Safety
Construction Site Health & SafetyConstruction Site Health & Safety
Construction Site Health & Safety
 
Avoiding Common Legal Billing pitfalls
Avoiding Common Legal Billing pitfallsAvoiding Common Legal Billing pitfalls
Avoiding Common Legal Billing pitfalls
 
Project Management Overview
Project Management OverviewProject Management Overview
Project Management Overview
 
Managing Cash Flows On Construction Projects
Managing Cash Flows On Construction ProjectsManaging Cash Flows On Construction Projects
Managing Cash Flows On Construction Projects
 
Hands on Measurement for K-2 Learners
Hands on Measurement for K-2 LearnersHands on Measurement for K-2 Learners
Hands on Measurement for K-2 Learners
 
Construction Project Management.
Construction Project Management.Construction Project Management.
Construction Project Management.
 
Cashbook, Passbook and BRC
Cashbook, Passbook and BRCCashbook, Passbook and BRC
Cashbook, Passbook and BRC
 
Measurements
MeasurementsMeasurements
Measurements
 
Work Breakdown Structure Use This
Work Breakdown Structure Use ThisWork Breakdown Structure Use This
Work Breakdown Structure Use This
 

Similar to 134 work break break down structure

PositioningPositioning of Product or ServiceParis based weig.docx
PositioningPositioning of Product or ServiceParis based weig.docxPositioningPositioning of Product or ServiceParis based weig.docx
PositioningPositioning of Product or ServiceParis based weig.docx
ChantellPantoja184
 
PME UNIT-3.pptx
PME UNIT-3.pptxPME UNIT-3.pptx
PME UNIT-3.pptx
MayankVasisthGandhi
 
Babu 143
Babu 143Babu 143
Babu 143
babasahebkadam3
 
unit-vpart-2.ppt
unit-vpart-2.pptunit-vpart-2.ppt
unit-vpart-2.ppt
TejaTeja57
 
Sameer Mitter - What is Project Management and How to Handle it
Sameer Mitter - What is Project Management and How to Handle itSameer Mitter - What is Project Management and How to Handle it
Sameer Mitter - What is Project Management and How to Handle it
Sameer Mitter
 
SPM_UNIT-2.pptx
SPM_UNIT-2.pptxSPM_UNIT-2.pptx
SPM_UNIT-2.pptx
Sushant895574
 
Software management disciplines
Software management disciplinesSoftware management disciplines
Software management disciplines
Kuppusamy P
 
Chap 4 Defining A Project
Chap 4 Defining A ProjectChap 4 Defining A Project
Chap 4 Defining A Project
project management
 
Defining The Project
Defining The ProjectDefining The Project
Defining The Project
Earl Tongol
 
Project management-professional-free-sample
Project management-professional-free-sampleProject management-professional-free-sample
Project management-professional-free-sample
ReadytoTrain .
 
1 Work Breakdown Structures (WBS) 2 WBS .docx
1 Work Breakdown Structures (WBS) 2 WBS .docx1 Work Breakdown Structures (WBS) 2 WBS .docx
1 Work Breakdown Structures (WBS) 2 WBS .docx
SONU61709
 
D22MB040_Unit_6.pptx
D22MB040_Unit_6.pptxD22MB040_Unit_6.pptx
D22MB040_Unit_6.pptx
kiranroy6777
 
Pmp project management professional free sample
Pmp project management professional free samplePmp project management professional free sample
Pmp project management professional free sample
Annsstand
 
Project management-professional-free-sample
Project management-professional-free-sampleProject management-professional-free-sample
Project management-professional-free-sample
ReadytoTrain .
 
MIS485 Capstone Project in MIS 2MGT 400 - Project M
MIS485 Capstone Project in MIS 2MGT 400 - Project MMIS485 Capstone Project in MIS 2MGT 400 - Project M
MIS485 Capstone Project in MIS 2MGT 400 - Project M
IlonaThornburg83
 
Gantt Charts.ppt
Gantt Charts.pptGantt Charts.ppt
Gantt Charts.ppt
Sampath Sredharran
 
PMP Exam Prep Training Materials based on PMBOK Guide 5th edition for Trainers
PMP Exam Prep Training Materials based on PMBOK Guide 5th edition for TrainersPMP Exam Prep Training Materials based on PMBOK Guide 5th edition for Trainers
PMP Exam Prep Training Materials based on PMBOK Guide 5th edition for Trainers
Ready to Train
 
802003 634318955109991250
802003 634318955109991250802003 634318955109991250
802003 634318955109991250
rajat898
 
Lecture 3.pptx
Lecture 3.pptxLecture 3.pptx
Lecture 3.pptx
PhocasSebastian1
 
Project scope management
 Project scope management Project scope management
Project scope management
SidraSaleem17
 

Similar to 134 work break break down structure (20)

PositioningPositioning of Product or ServiceParis based weig.docx
PositioningPositioning of Product or ServiceParis based weig.docxPositioningPositioning of Product or ServiceParis based weig.docx
PositioningPositioning of Product or ServiceParis based weig.docx
 
PME UNIT-3.pptx
PME UNIT-3.pptxPME UNIT-3.pptx
PME UNIT-3.pptx
 
Babu 143
Babu 143Babu 143
Babu 143
 
unit-vpart-2.ppt
unit-vpart-2.pptunit-vpart-2.ppt
unit-vpart-2.ppt
 
Sameer Mitter - What is Project Management and How to Handle it
Sameer Mitter - What is Project Management and How to Handle itSameer Mitter - What is Project Management and How to Handle it
Sameer Mitter - What is Project Management and How to Handle it
 
SPM_UNIT-2.pptx
SPM_UNIT-2.pptxSPM_UNIT-2.pptx
SPM_UNIT-2.pptx
 
Software management disciplines
Software management disciplinesSoftware management disciplines
Software management disciplines
 
Chap 4 Defining A Project
Chap 4 Defining A ProjectChap 4 Defining A Project
Chap 4 Defining A Project
 
Defining The Project
Defining The ProjectDefining The Project
Defining The Project
 
Project management-professional-free-sample
Project management-professional-free-sampleProject management-professional-free-sample
Project management-professional-free-sample
 
1 Work Breakdown Structures (WBS) 2 WBS .docx
1 Work Breakdown Structures (WBS) 2 WBS .docx1 Work Breakdown Structures (WBS) 2 WBS .docx
1 Work Breakdown Structures (WBS) 2 WBS .docx
 
D22MB040_Unit_6.pptx
D22MB040_Unit_6.pptxD22MB040_Unit_6.pptx
D22MB040_Unit_6.pptx
 
Pmp project management professional free sample
Pmp project management professional free samplePmp project management professional free sample
Pmp project management professional free sample
 
Project management-professional-free-sample
Project management-professional-free-sampleProject management-professional-free-sample
Project management-professional-free-sample
 
MIS485 Capstone Project in MIS 2MGT 400 - Project M
MIS485 Capstone Project in MIS 2MGT 400 - Project MMIS485 Capstone Project in MIS 2MGT 400 - Project M
MIS485 Capstone Project in MIS 2MGT 400 - Project M
 
Gantt Charts.ppt
Gantt Charts.pptGantt Charts.ppt
Gantt Charts.ppt
 
PMP Exam Prep Training Materials based on PMBOK Guide 5th edition for Trainers
PMP Exam Prep Training Materials based on PMBOK Guide 5th edition for TrainersPMP Exam Prep Training Materials based on PMBOK Guide 5th edition for Trainers
PMP Exam Prep Training Materials based on PMBOK Guide 5th edition for Trainers
 
802003 634318955109991250
802003 634318955109991250802003 634318955109991250
802003 634318955109991250
 
Lecture 3.pptx
Lecture 3.pptxLecture 3.pptx
Lecture 3.pptx
 
Project scope management
 Project scope management Project scope management
Project scope management
 

More from Dr Fereidoun Dejahang

27 j20 my news punch -dr f dejahang 27-01-2020
27 j20 my news punch -dr f dejahang  27-01-202027 j20 my news punch -dr f dejahang  27-01-2020
27 j20 my news punch -dr f dejahang 27-01-2020
Dr Fereidoun Dejahang
 
28 dej my news punch rev 28-12-2019
28 dej my news punch rev 28-12-201928 dej my news punch rev 28-12-2019
28 dej my news punch rev 28-12-2019
Dr Fereidoun Dejahang
 
16 fd my news punch rev 16-12-2019
16 fd my news punch rev 16-12-201916 fd my news punch rev 16-12-2019
16 fd my news punch rev 16-12-2019
Dr Fereidoun Dejahang
 
029 fast-tracking projects
029 fast-tracking projects029 fast-tracking projects
029 fast-tracking projects
Dr Fereidoun Dejahang
 
028 fast-tracking projects & cost overrun
028 fast-tracking projects & cost overrun028 fast-tracking projects & cost overrun
028 fast-tracking projects & cost overrun
Dr Fereidoun Dejahang
 
027 fast-tracked projects-materials
027 fast-tracked projects-materials027 fast-tracked projects-materials
027 fast-tracked projects-materials
Dr Fereidoun Dejahang
 
026 fast react-productivity improvement
026 fast react-productivity improvement026 fast react-productivity improvement
026 fast react-productivity improvement
Dr Fereidoun Dejahang
 
025 enterprise resources management
025 enterprise resources management025 enterprise resources management
025 enterprise resources management
Dr Fereidoun Dejahang
 
022 b construction productivity-write
022 b construction productivity-write022 b construction productivity-write
022 b construction productivity-write
Dr Fereidoun Dejahang
 
022 a construction productivity (2)
022 a construction productivity (2)022 a construction productivity (2)
022 a construction productivity (2)
Dr Fereidoun Dejahang
 
021 construction productivity (1)
021 construction productivity (1)021 construction productivity (1)
021 construction productivity (1)
Dr Fereidoun Dejahang
 
019 competencies-managers
019 competencies-managers019 competencies-managers
019 competencies-managers
Dr Fereidoun Dejahang
 
018 company productivity
018 company productivity018 company productivity
018 company productivity
Dr Fereidoun Dejahang
 
017 communication
017 communication017 communication
017 communication
Dr Fereidoun Dejahang
 
016 communication in construction sector
016 communication in construction sector016 communication in construction sector
016 communication in construction sector
Dr Fereidoun Dejahang
 
015 changes-process model
015 changes-process model015 changes-process model
015 changes-process model
Dr Fereidoun Dejahang
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
Dr Fereidoun Dejahang
 
013 changes in construction projects
013 changes in construction projects013 changes in construction projects
013 changes in construction projects
Dr Fereidoun Dejahang
 
012 bussiness planning process
012 bussiness planning process012 bussiness planning process
012 bussiness planning process
Dr Fereidoun Dejahang
 
011 business performance management
011 business performance management011 business performance management
011 business performance management
Dr Fereidoun Dejahang
 

More from Dr Fereidoun Dejahang (20)

27 j20 my news punch -dr f dejahang 27-01-2020
27 j20 my news punch -dr f dejahang  27-01-202027 j20 my news punch -dr f dejahang  27-01-2020
27 j20 my news punch -dr f dejahang 27-01-2020
 
28 dej my news punch rev 28-12-2019
28 dej my news punch rev 28-12-201928 dej my news punch rev 28-12-2019
28 dej my news punch rev 28-12-2019
 
16 fd my news punch rev 16-12-2019
16 fd my news punch rev 16-12-201916 fd my news punch rev 16-12-2019
16 fd my news punch rev 16-12-2019
 
029 fast-tracking projects
029 fast-tracking projects029 fast-tracking projects
029 fast-tracking projects
 
028 fast-tracking projects & cost overrun
028 fast-tracking projects & cost overrun028 fast-tracking projects & cost overrun
028 fast-tracking projects & cost overrun
 
027 fast-tracked projects-materials
027 fast-tracked projects-materials027 fast-tracked projects-materials
027 fast-tracked projects-materials
 
026 fast react-productivity improvement
026 fast react-productivity improvement026 fast react-productivity improvement
026 fast react-productivity improvement
 
025 enterprise resources management
025 enterprise resources management025 enterprise resources management
025 enterprise resources management
 
022 b construction productivity-write
022 b construction productivity-write022 b construction productivity-write
022 b construction productivity-write
 
022 a construction productivity (2)
022 a construction productivity (2)022 a construction productivity (2)
022 a construction productivity (2)
 
021 construction productivity (1)
021 construction productivity (1)021 construction productivity (1)
021 construction productivity (1)
 
019 competencies-managers
019 competencies-managers019 competencies-managers
019 competencies-managers
 
018 company productivity
018 company productivity018 company productivity
018 company productivity
 
017 communication
017 communication017 communication
017 communication
 
016 communication in construction sector
016 communication in construction sector016 communication in construction sector
016 communication in construction sector
 
015 changes-process model
015 changes-process model015 changes-process model
015 changes-process model
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
 
013 changes in construction projects
013 changes in construction projects013 changes in construction projects
013 changes in construction projects
 
012 bussiness planning process
012 bussiness planning process012 bussiness planning process
012 bussiness planning process
 
011 business performance management
011 business performance management011 business performance management
011 business performance management
 

Recently uploaded

Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
IJECEIAES
 
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdfIron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
RadiNasr
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
University of Maribor
 
bank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdfbank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdf
Divyam548318
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
gerogepatton
 
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
awadeshbabu
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
drwaing
 
sieving analysis and results interpretation
sieving analysis and results interpretationsieving analysis and results interpretation
sieving analysis and results interpretation
ssuser36d3051
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
nooriasukmaningtyas
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
wisnuprabawa3
 
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
Mukeshwaran Balu
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
IJNSA Journal
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
Madan Karki
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
Madan Karki
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
insn4465
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
anoopmanoharan2
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
Hitesh Mohapatra
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
rpskprasana
 
Low power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniquesLow power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniques
nooriasukmaningtyas
 

Recently uploaded (20)

Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
 
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdfIron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
 
bank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdfbank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdf
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
 
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
 
sieving analysis and results interpretation
sieving analysis and results interpretationsieving analysis and results interpretation
sieving analysis and results interpretation
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
 
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
 
Low power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniquesLow power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniques
 

134 work break break down structure

  • 2. WORK BRAEK DOWN STRUCTURE (WBS) A technique by which the work of a project is divided and sub divided for management, and control purposes.
  • 3. WORK BRAEK DOWN STRUCTURE (WBS) The work is developed through successive increasing levels of details. Advantage • work delegated into coherent packages • work defined at appropriate levels of detail for cost control
  • 4. WORK BRAEK DOWN STRUCTURE (WBS) • work defined at appropriate levels of detail for nesting plans i.e. rolling wave of program. • Variances can be measured between Planned and Actual. • The work packages are more stable than long chains of discontinuous work activities. • As a result risk is more contained and measured more accurately.
  • 5. WORK BRAEK DOWN STRUCTURE (WBS) • successive levels of detail may be evolved • the project sponsor may call for reports from the Project manager based on the work content at Level 1, 2 and sometimes at Level 3,
  • 6. WORK BRAEK DOWN STRUCTURE (WBS) • the Project Manger may call for Reports from Project Contributors based on work content at Level 3, 4 and 5, • the contractor’s Construction Management Team also may ask for report from Site Engineers at Level 5 and below Level 5,
  • 7. WORK BRAEK DOWN STRUCTURE (WBS) • Different Levels Breakdown and Work Package require different Project Contributors with different Responsibilities. • The flow is from Left to Right.
  • 8. WORK BRAEK DOWN STRUCTURE (WBS) • successively at each Level, may be made to mirror the timing of the work; • and facilities a Rolling Wave or Nested Programme; • from project level down to the lowest task orientated package level.
  • 9. WORK BRAEK DOWN STRUCTURE (WBS) • each work package can be identified with a unique cost code; • and Actual and Planned Cost variances compared; • each work package can be fully described, for example: • Content; • what is included and what is excluded in a package statement.
  • 10. • WBS (Food Process Factory)-Level 1 Project Definition/Scope Management Site Procurement Outline Design & State Approval Detail Design & Costing Procurement And Construction Commision & Handover Left to right
  • 11. WORK BRAEK DOWN STRUCTURE (WBS) Procurement& Construction Bill of Quantity Tender & Negotiation Work on Site Management Fees LEFT TO RIGHT WBS (Food Process Factory)-Level 3
  • 12. WORK BRAEK DOWN STRUCTURE (WBS) Work on Site Preliminary Works Sub- structure Super- structure Claddind & Envelope External Work Internal Work WBS (Food Process Factory)-Level 4 and 5
  • 13. WORK BRAEK DOWN STRUCTURE (WBS) Work on Site Total cost £1, 900, 250.00 Preliminary Works £105.000.00 Sub- structure £270.00 Super- Structure £ Claddind & Envelope £ External Work £ Internal Work £ Site Clearance £ Piling £ Foundation s £ Drainage £ Floor slab £
  • 14. WORK BRAEK DOWN STRUCTURE (WBS) Project Mgmt Prelim Design 1.1.1 Title I Design 1.1.2 Final Design 1.1.3 Design 1.1 Procurement 1.2 Construction 1.3 1.4 ACME Project X 1.0
  • 15. Resource allocation Project Mgmt Prelim Design 1.1.1 Title I Design 1.1.2 Final Design 1.1.3 Design 1.1 Procurement 1.2 Construction 1.3 1.4 ACME Project X 1.0 Preliminary Design 1.1.1 Jan Feb Mar Apr May 1.1.1.1 Define Specifications & Req. 1.1.1.2 Develop Preliminary Design 1.1.1.3 Review Preliminary Design 1.1.1.4 Incorporate Comments 1.1.1.5 Preliminary Design Complete
  • 16. Resource allocation Project Mgmt Prelim Design 1.1.1 Title I Design 1.1.2 Final Design 1.1.3 Design 1.1 Procurement 1.2 Construction 1.3 1.4 ACME Project X 1.0 Preliminary Design 1.1.1 Hours Jan Feb Mar Apr May 1.1.1.1 Define Specifications & Req. 1,500 1,000 1.1.1.2 Develop Preliminary Design 2,000 2,000 1.1.1.3 Review Preliminary Design 500 500 1.1.1.4 Incorporate Comments 320 320 1.1.1.5 Preliminary Design Complete 1,000
  • 17. Resource allocation for each activity Project Mgmt Prelim Design 1.1.1 Title I Design 1.1.2 Final Design 1.1.3 Design 1.1 Procurement 1.2 Construction 1.3 1.4 ACME Project X 1.0 Preliminary Design 1.1.1 Hours Jan Feb Mar Apr May 1.1.1.1 Define Specifications & Req. 1,500 1,000 1.1.1.2 Develop Preliminary Design 2,000 2,000 1.1.1.3 Review Preliminary Design 500 500 1.1.1.4 Incorporate Comments 320 320 1.1.1.5 Preliminary Design Complete 1,000
  • 18. Resource allocation ACME Housing Corporation 1 House Building Project 1.1 Concrete 1.1.1 Framing 1.1.2 Plumbing 1.1.3 Electrical 1.1.4 Interior 1.1.5 Roofing 1.1.6
  • 19. Resource allocation-after WBS ACME Housing Corporation 1 House Building Project 1.1 Concrete 1.1.1 Pour Foundation 1.1.1.1 Install Patio 1.1.1.2 Stairway 1.1.1.3 Framing 1.1.2 Frame Exterior Walls 1.1.2.1 Frame Interior Walls 1.1.2.2 Install Roofing Trusses 1.1.2.3 Plumbing 1.1.3 Install Water Lines 1.1.3.1 Install Gas Lines 1.1.3.2 Install B/K Fixtures 1.1.3.3 Electrical 1.1.4 Install Wiring 1.1.4.1 Install Outlets/ Switches 1.1.4.2 Install Fixtures 1.1.4.3 Interior 1.1.5 Install Drywall 1.1.5.1 Install Carpets 1.1.5.2 Install Painting 1.1.5.3 Roofing 1.1.6 Install Felt 1.1.6.1 Install Shingles 1.1.6.2 Install Vents 1.1.6.3
  • 20. MILESTONE PROGRAMMING • The Milestone programmes provide the ‘administrative level’ in the planning hierarchy. • The activity programme provides the detailed ‘technical level’. • It focused on goals and not on the method of reaching them. • The Milestones and Objectives remain reasonably constant through out the project. • Methods of reaching goals may change.
  • 21. MILESTONE PROGRAMMING • Goal Directed Project Management (GDPM) is a powerful, pragmatic approach for gaining consensus from all stakeholders on the overall objectives of a business program or project.
  • 22. MILESTONE PROGRAMMING • The approach is fully compatible with industry standards such as: • PRINCE2 • SUMMIT • V-Model or HERMES • It provides a single-page, top-level view of the goals of the project (a milestone plan).
  • 23. DEVELOPING THE MILESTONE PROGRAMME 1-The planning team • The team responsible for ensuring that the project objectives are met should be present to formulate the Milestone programme. 2-The result paths • The project Objectives and Scope are set out in the project definition Document.
  • 24. MILESTONE PROGRAMMING • The team considers at each level, the Primary Objectives such as: • How will success be judged? • What are the critical factors to monitor? • What are Key Performance Indicators for this project?
  • 25. DEVELOPING THE MILESTONE PROGRAMME 3-Milestones • The team actively generates ideas for the like list of Milestones. • Each Milestone description should: • form a check point towards the final objective, • describe a condition or state that the project must occupy at various stages in order to reach it’s final objective,
  • 26. DEVELOPING THE MILESTONE PROGRAMME • show a logical sequence towards the final objective; • state what to achieve, and not how to achieve; • focus on the goal; • state a specific outcome, such as, approval of a report and who approve it;
  • 27. DEVELOPING THE MILESTONE PROGRAMME • Also Milestone should: • be natural; • represent important decisions; • be controllable, either quantitively or qualitatively; • be few in number (10 TO 20); • be at useful intervals(ie monthly); 4- Drafting the Milestone Plan
  • 28. NESTED PROGRAMMING • The primary objectives of the project are provided in the Level 1 Project Programme. • Below The Work Breakdown Structure (WBS) most projects are capable of being split into a member of Stages or Phases (Work Packages).
  • 29. NESTED PROGRAMMING • A milestoneplan may be produced for each of these phases. • for example at Level 1-Reported at 20 max controlled Milestones. • Or at Level-2- let us say 4 Stages – each Reported at 20 max controlled Milestones.
  • 30. NESTED PROGRAMMING • At Level 3 and below, the influence of detail activities can make it difficult to develop meaningful Milestone Programme. • At this level down on the WBS, it is normal to revert to activity programmes.
  • 31. NESTED PROGRAMMING • At the lowest activity and task levels, Milestones occur along the path of networked activities (CPM) and are shown as ‘Flagging’ up on the network or Gantt chart. • Some packages allow them to be fixed and generate ‘Supper Critical Paths’. (See Oxford Brookes University-Micro Planner).
  • 32. DEVELOPING THE MILESTONE PROGRAMME Conclusion • The Milestone methods is purely a means of monitoring and controlling progress towards the Projects Objectives at the highest level of WBS. • It is useful where there is insufficient detailed information to produce meaningful accurate lower level Activities based programmes.
  • 33. Define Goals Tchnological Communication s Cost Latest Process plant Latest Road Rail Package Latest Hygiene Finishes Latest Building Management System Latest Computer Process System Latest Robotics Negociation And Completion of Rdad/Rail link to EU To Cmply with Finacial and Strategic Plans Example of Level 1- Factory Project