SlideShare a Scribd company logo
1 of 34
Chapter 2.0
Construction Project Planning and Scheduling
9/28/2020 1
Contents:
2.1. Construction Planning
2.2. Steps and stages in Planning
2.3 Planning by client and contractor
2.4 preparing schedule
2.5 Time-Cost Trade-off
© Subash K. Bhattarai
Initial date of Preparation 2070 B.S
2.1 Construction Planning
• "If you fail to plan, you are bound to fail"
– Planning is the most important constituent of the
construction management. In the simplest sense
planning is the mental process deciding about the
future line of actions.
• It forms the basis for the project scope, schedule,
resources, quality, risk, and integration
• Planning is done to
– Eliminate or reduce uncertainty
– Improve efficiency of the operations
– Obtain better understanding of the objectives
– Provide basis for monitoring and controlling
9/28/2020 2© Subash K. Bhattarai
Initial date of Preparation 2070 B.S
Objectives of planning
• The main objective of planning of a work is to execute
the project or work most economically in terms of money
and time both.
• The effective planning depends upon the following
factors:
– Proper design of each element of the project
– Proper selection of plant and equipment
– Proper arrangements of repair of plant and equipment at site
– Procurement of required materials well in advance
– Ensure employment of skilled and unskilled employees
– To arrange constant flow of funds in entire project duration
– To provide required level of safety and compensations
– Proper arrangements of communication and mobility in site
9/28/2020 3© Subash K. Bhattarai
Initial date of Preparation 2070 B.S
2.2 Steps and Stages in Planning
Steps involved in planning
– Identifying the likely problems to be encountered in the
execution of the work.
– Ascertaining alternative feasibility of execution of work
– Fixing the time of starting the execution of work
– Deciding the time of delivering the materials at site
– Deciding the quantities and duration of various types of
machines and equipment
– Deciding the number of different types of labors for various
works and duration of their employment
– Estimation of financial need
– Estimation of the duration of completion of the work
– Evaluation of the effectiveness of plan adopted
9/28/2020 4© Subash K. Bhattarai
Initial date of Preparation 2070 B.S
Stages of planning
Usually the stages of planning are as follows:
– Preplanning
• Setting out objectives
• Cost benefit analysis
• Project go / no-go decision
– Detailed planning
• Detailed design and drawings
• Specifications
• Quantities calculation
• WBS is done
• Sequence and scheduling of the activities are done
– Monitoring and controlling
• In this phase, the progress of construction is monitored as per proposed
scheduled.
• Updating of schedule can be carried out according to the actual
progress of work.
• Preparation of the revised forecasts regarding the availability of
various resources is done.
9/28/2020 5© Subash K. Bhattarai
Initial date of Preparation 2070 B.S
2.3 Planning by the Client /Owner/Employer
Pre-tender / pre-construction stage planning
– Clients sets clear objectives of the project
– Client communicate the objectives to all the parties and stakeholders
– After proper investigations of the project, client prepares quantity estimates and
determines the quantum of money required for the completion of the work.
– Take respective approval of the project from concerned authority
– Selection of project team and project appraisal
– Select the consultant (if required)
– Bidding and contract award (Selection of Contractor)
Construction stage planning
– Revision in objectives in responding unexpected events
– Make site available for the contractor
– Timely payment and settlement of claims
– Keep the changes less
– Update performance bond/ security of the contractor
– Timely decision
Post construction stage planning
– Prepares project operation schedule
– Prepares project maintenance schedule
– Project ownership
9/28/2020 6© Subash K. Bhattarai
Initial date of Preparation 2070 B.S
Planning by the Contractor
Pre-tender/ pre-construction stage planning
The planning undertaken by the contractor after receipt of tender notice and
before submitting the bid is known as pre-tender stage planning.
– Careful Study of tender documents and drawings to find out the
quantities of each item of work
– Study of specifications and workout the detailed quality of materials
required for different items
– Determine the availability of construction materials at site or nearby
site.
– Determine the method of work execution i.e. by labor or equipment
– Thorough study of site and site investigations
9/28/2020 7© Subash K. Bhattarai
Initial date of Preparation 2070 B.S
Construction stage planning
After the acceptance of the tender, the contractor further needs in-depth
planning. This stage of planning is also known as contract planning.
– Studying the alternative methods of construction and to decide about
subcontracting
– Working out detailed quantities of materials required and examine and
fixing the methods of procurement and sources of them
– Working out detailed about construction workforce like skilled and
unskilled manpower
– Working out details of plants, equipment their layout and repair &
maintenance strategy
– Planning for camp facilities, access, accommodations, site offices and
layout
– Planning for surveillance like proper lighting, ventilation, drinking
water, sanitation, first aid treatment
– Study interdependence of different items of works and fixing the
sequence of them
– Finalize the work program of each item of work and to decide the dates
of their starting and completing
Planning by the Contractor contd..
9/28/2020 8© Subash K. Bhattarai
Initial date of Preparation 2070 B.S
Post construction stage planning
• Demobilization of plants and equipment
• Demobilization of labors
• Clearance of materials inventory and its stock
• Handover the project to client in targeted date
• Responsible for the defect liability construction within its period
Planning by the Contractor contd..
9/28/2020 9© Subash K. Bhattarai
Initial date of Preparation 2070 B.S
2.4 Preparing Schedule
Scheduling
A construction schedule is a graphic representation which shows the
phasing rate of construction with the starting and completing dates
of each activity and the sequential relationship among various
operations in a construction project.
Use of scheduling
• Following are the use of scheduling
• The quantity of work involved, labor, material, equipment and
money required at each stage of work can be determined by
scheduling.
• The actual progress of the work can be checked from time to time
by scheduling
• The project can be carried out in systematic manner using
scheduling
9/28/2020 10© Subash K. Bhattarai
Initial date of Preparation 2070 B.S
Classification of scheduling
Schedules can be classified according to the requirements as
follows:
– Construction schedule
– Materials schedule
– Labor schedule
– Equipment schedule
– Financial schedule
– Control schedule
– Organizational schedule
– Summary schedule
Methods of scheduling
Bar chart or Gantt charts
Milestone charts
Network analysis
9/28/2020 11© Subash K. Bhattarai
Initial date of Preparation 2070 B.S
Construction schedule and its preparation
Before preparing construction schedule following information must be
known
– Various operations to be done in a particular project
– Quantum of works to be done in each operation
– Unit of measurement
– Rate of progress of work with due allowance of weather conditions
– Number of labors required
– Number and types of plants and equipment required
– Date of starting and completing the activity
– Correlation between different operations
The procedure of preparing construction schedule is as follows:
– The work or project is divided into number of operations and their inter
dependence or relationship is studied. After the careful study of their
interdependence the sequence of operation is decided
– The quantity of work involved in each operation is to be determined
– The time required for the completion of each operation as well as the
completion of total project is determined. This can be done by knowing
the quantum of work involved and the rate
9/28/2020 12© Subash K. Bhattarai
Initial date of Preparation 2070 B.S
9/28/2020 13© Subash K. Bhattarai
Initial date of Preparation 2070 B.S
S.N Descripti
ons of
Materials
Total
Quantity Month
I II III
P A P A P A
1 cement 1500 bags 500 502 50 48 700 701
2 re-bar 100 ton … … … ….
3 sand 1000 m3
Material Schedule
9/28/2020 14© Subash K. Bhattarai
Initial date of Preparation 2070 B.S
S.N Types of
Equipment
Total
Number
Required
Total Time
Required Month
I II III IV
P A P A
1 Excavator 1 20 hrs 10 8 1
0
9
2 Mixer 1 60 hrs 15 1
0
2
0
3 Vibrator 1 30 hrs
Equipment Schedule
9/28/2020 15© Subash K. Bhattarai
Initial date of Preparation 2070 B.S
Labor Schedule
S.N. Descriptions
of Labor
Total time
Required Month
I II III IV
P A P A P A
1 SL
Mason
Carpenter
Bar-bender
100md
50 md
20 md
30 md
50 20
2 USL
3
9/28/2020 16© Subash K. Bhattarai
Initial date of Preparation 2070 B.S
Indirect cost
The expenditures which cannot be allotted clearly to the individual activities of
the project but are assessed in total are called indirect costs. The indirect cost
includes overhead charges, administrative and establishment charges, supervision
charges, loss of revenue, loss in profit and penalty etc.
2.5 Time Cost Trade- Off
9/28/2020 17
Project cost
For any project, total expenditure incurred in terms of manpower, equipment,
machinery and materials to complete an activity/ies known as total cost of the
project. The total sum of the project is the sum of two distinct costs. Direct and
Indirect cost
The cost of materials, equipment and manpower spent on implementing an activity
/ ies refers to the direct cost. The direct costs of project are of major concern and
behavior pattern of direct costs with time is of importance. Direct cost of a project
depends on the completion time of project, but the variation is not linear.
Direct cost
© Subash K. Bhattarai
Initial date of Preparation 2070 B.S
9/28/2020 18
15
Quantity Considered for Rate Analysis= 1.000 cu.m.
S.N. Description Quantity Unit Unit Rate Amount
A Labor
A.1 Skilled Labor 0.500 m.d. Rs. 1,000.00 Rs. 500.00
A.2 Unskilled Labor 3.500 m.d. Rs. 735.00 Rs. 2,572.50
Total of Labor Cost Rs. 3,072.50
B Materials
B.1 Cement 320.000 kg. Rs. 16.90 Rs. 5,408.00
B.2 40mm Aggregate 0.520 cu.m. Rs. 3,386.88 Rs. 1,761.17
B.3 20mm Aggregate 0.330 cu.m. Rs. 3,492.72 Rs. 1,152.59
B.4 Sand (Rough Sand) 0.445 cu.m. Rs. 2,928.24 Rs. 1,303.06
B.5 Water 130.000 lit. Rs. 0.26 Rs. 33.80
B.6 Diesel 3.000 lit. Rs. 97.50 Rs. 292.50
B.5 Petrol 0.100 lit. Rs. 111.50 Rs. 11.15
Total of Materials Cost Rs. 9,962.27
C Equipments
C.1 Mixer 0.600 hour Rs. 1,875.00 Rs. 1,125.00
C.2 Vibrator 0.250 hour Rs. 120.00 Rs. 30.00
Total of Equipment Cost Rs. 1,155.00
Total Cost Rs. 14,189.77
Contractor's Overhead (15%) Rs. 2,128.46
Total Including Overhead Rs. 16,318.23
Unit Rate Rs. 16,318.23
PCC Work : Providing , laying, compacting and curing 100mm thick plain cement concrete, M15 (1
cement : 2 sand : 4 aggregate) on foundation, floor and other specified area with O.P. cement, sand
and stone ballast of 10-20mm size aggregate, proper mixing with mixture machine, laying & placing in
position compacting with vibrator, including curing the job to approved level, lines and dimensions all
complete as per drawings, specifications and instruction of the site engineer.
Direct Cost
Indirect Cost
© Subash K. Bhattarai
Initial date of Preparation 2070 B.S
Direct Cost Behavior With Time
9/28/2020 19
Cost
Tim
e
Direct Cost
Normal Time
10M
(Project duration)
Cost rises if project duration
is prolonged
Cost rises if
project is crashed
Normal
Cost:10000K
(Project Direct
Cost)
12M8M
© Subash K. Bhattarai
Initial date of Preparation 2070 B.S
Indirect Cost behavior with time
9/28/2020 20
Cost
Time
Indirect Cost
(Directly
proportional)
Normal
Time
Cost rises if project duration
is prolonged
Cost reduces if
project is crashed
Indirect
Cost
© Subash K. Bhattarai
Initial date of Preparation 2070 B.S
Total Cost Behavior With Time
9/28/2020 21
Cost
Time
Direct Cost
To
Indirect Cost
Total Cost
TnTc
Cc
Cm
Cn
A
C
B
© Subash K. Bhattarai
Initial date of Preparation 2070 B.S
Definitions of Terms
Normal time
The time usually allowed for an activity by the
estimator is known as normal time. It is the standard
time for that activity and is denoted by (Tn).
Crash time
The minimum possible time in which an activity can
be completed by deploying extra resources is known
as crash time. Beyond the crash time the duration of
an activity cannot be reduced or shortened by any
amount of increase in mobilization. It is denoted by
(Tc).
Normal cost
The direct cost required to complete the activity in
the normal duration is called normal cost and is
denoted by (Cn).
Crash cost
The direct cost corresponding to the crash time of
completing an activity is known as crash cost and is
denoted by (Cc).
9/28/2020
22
Minimum duration
The duration obtained after
possible crashing of
activities is known as
minimum duration (Tm).
Further reduction or
crashing of duration is not
possible after this point.
© Subash K. Bhattarai
Initial date of Preparation 2070 B.S
Cost slope
• The direct cost curve generally is a curve as shown below. But
this curve can be approximated by the straight line or more than
one straight lines depending upon the flatness of the curve. Thus
the slope of this straight line is cost slope.
9/28/2020 23
Cost slope (CS) =
Crash cost normal cost
Normal time crash time


Normal
Point ‘B’
Crash
Point ‘A’
Normal time (Tn)
(Regular time)
Crash time (Tc)
Normal Cost (Cn)
Crash Cost (Cc)
Direct Cost
Activity Time
© Subash K. Bhattarai
Initial date of Preparation 2070 B.S
Time cost trade-off
• Time and cost are the two most important resources that a
project manager deals with. Both resources have
constrained, and the job of a project manager is to have
judicious balance between them. The judicious balance
between time and cost is called Time-Cost trade-off and it
can be achieved by studying the availability and demand
of these resources for the given project.
9/28/2020 24© Subash K. Bhattarai
Initial date of Preparation 2070 B.S
Total project costs include both direct costs and
indirect costs of performing the activities of the
project.
If each activity of the project is scheduled for
the duration that results in the minimum direct
cost (normal duration) then the time to complete
the entire project might be too long and
substantial penalties associated with the late
project completion might be incurred.
At the other extreme, a manager might choose
to complete the activity in the minimum
possible time, called crash duration, but at a
maximum cost.
9/28/2020 25
Time cost trade-off
Non-linear time and cost trade-off for an activity Project time-cost relationship:
Thus, planners perform what is called time cost trade-off analysis to shorten the
project duration.
This can be done by selecting some activities on the critical path to shorten their
duration. As the direct cost for the project equals the sum of the direct costs of its
activities, then the project direct cost will increase by decreasing its duration. On the
other hand, the indirect cost will decrease by decreasing the project duration, as the
indirect cost are almost a linear function with the project duration. © Subash K. Bhattarai
Initial date of Preparation 2070 B.S
From the total cost ACB, the total cost of a project is minimum for certain time
duration. This duration is known as optimum duration (To) for the corresponding
minimum cost (Cm). Further, if the project duration is increased, the total cost will
also increase. On the other hand, if the project duration is decreased to the crash
value, the project cost will be the highest. The optimum duration is less than the
normal duration (Tn) corresponding to the direct costs. This is because both direct
and indirect cost increases beyond the normal duration, whereas below the normal
duration indirect cost decrease, but the direct cost increases.
9/28/2020 26© Subash K. Bhattarai
Initial date of Preparation 2070 B.S
Steps in optimization of cost (Cost optimization through Network)
1. First, draw the network diagram and find out all the possible paths. Critical path and
non-critical paths. Critical path duration is the normal project duration for that
project
2. Calculate the direct cost by adding the normal cost of all activities. Calculate
indirect cost by multiplying project duration with the indirect cost (overhead or
indirect expense) per unit time
3. Calculate the total cost by adding direct cost and indirect cost. This total cost is the
baseline cost for the calculation. Similarly, the longest duration (critical path
duration) is the project duration as a baseline duration for the calculation.
4. Calculate the cost slopes of all activities and rank them in ascending order of cost
slopes.
5. Start crashing the project from a critical path (since this is the project duration) by
selecting such critical activity having least cost slope as per ranking to the
maximum possible extent (observe other non-critical paths which are likely to be
critical)
6. Calculate the direct cost by adding the extra cost of crashing (cost slope X (Tn-Tc))
required for crashing that activity to the direct cost calculated in previous steps and
corresponding indirect cost of reduced project duration.
9/28/2020 27© Subash K. Bhattarai
Initial date of Preparation 2070 B.S
Crashing Contd..
After step six, three possible cases may arise:
Case I: If the same path remains critical (longest) then crashing is considered
for the critical activity serially in the ascending order to their cost slope as far
as possible.
Case II: While crashing the critical path, there may emerge a new critical
path/s then crashing is carried out for the common activity. If there is more
than one common activity, activity with the least cost slope is selected first and
continues serially as per the ranking of cost slopes.
Case III: After crashing as per the case II, if there is a possibility of crashing
then, one activity from each path is selected at one time for crashing. This
crashing is known as simultaneous crashing or parallel crashing. The process is
continued until the project shortening is possible.
Note:
Every time after crashing, the direct cost and indirect cost is calculated to find
out the total cost. If the total cost calculated after crashing is greater than the
earlier step, we come to the end of optimization.
Whereas, for the determination of minimum possible time (Tm), crashing
should be continued until the possibility.
9/28/2020 28© Subash K. Bhattarai
Initial date of Preparation 2070 B.S
Numerical
1. The following table shows the costs and duration of each activity of a
project. The network is shown. The indirect cost may be taken as Rs. 3150.-
per week. Determine the optimum duration of the project and
corresponding minimum cost.
Activity Predecessor Normal duration
(Tn)
Normal cost
(Cn)
Crash duration
(Tc)
Crash cost (Cc)
A
B
C
D
E
-
-
A
A
B,C
7
9
5
6
6
8000
5000
7000
9000
6000
4
6
2
4
4
15500
9500
10000
16000
12000
9/28/2020 29© Subash K. Bhattarai
Initial date of Preparation 2070 B.S
Solution
9/28/2020 30
2
3
41 18, 18
12, 12
9 6
6
E
D
7, 7
A
7
0, 0
B
5 C
Drawing the network diagram, finding possible paths, project
duration and total cost:
Possible
Paths
Duration
(w)
A – D 13
A – C – E 18
B – E 15
Here, The path A – C – E is the project duration as it is the critical path.
Therefore, The project duration in 18 Weeks
Direct Cost (Summation of normal
cost of all activities) =  normal
cost = 35000
Indirect Cost (Project duration x
indirect cost per week) = 18 ×
3150 = 5670
 Total project cost (Direct cost +
Indirect Cost) = 91700
© Subash K. Bhattarai
Initial date of Preparation 2070 B.S
Activity Difference in cost
Crash cost- normal cost
(Cc-Cn)
Difference in duration
Normal duration -
Crash duration (Tn-Tc)
Cost slope = (Cc-
Cn)/(Tn-Tc)
Rank
A
B
C
D
E
15500-8000 =7500
4500
3000
7000
6000
7-4 = 3
3
3
2
2
7500/3 = 2500
1500
1000
3500
3000
3
2
1
5
4
9/28/2020 31
Determining the cost slope of all activities.
Crashing
Path Duration
A – D 13 w
A – C – E 18 – 3 = 15 w
B – E 15 w
From Critical path A-C-E, select activity ‘C’ for crashing [activity 'C' has minimum cost slope amongst
critical activities] by 7-4 weeks = 3 weeks (i.e. maximum possible extent) and revised duration be:
(Note be aware of other non-critical path/s as well. We cannot reduce the project duration below other
path’s duration)
Extra cost of crashing activity 'C' by 3 weeks = 3 × 1000 = 3000
Increment in Direct cost = 35000 + 3000 = 38000
Decrement in Indirect cost = 15 × 3150 = 47250
Total Cost of project = 85250
Revised duration Revised Cost
As, this total cost is lesser than previous step further crashing is
possible
© Subash K. Bhattarai
Initial date of Preparation 2070 B.S
9/28/2020 32
Path Duration
A – D 13 w
A – C – E 15 – 2 = 13 w
B – E 13 w
After Crashing activity ‘C’, here we find two critical paths A – C – E and B – E with duration equal to 15
weeks. So, crashing must be carried by selecting common activity from both paths for an immediate
result.
Common Activity Crashing
As we see activity ‘E’ is common to both paths. So selecting activity ‘E’ for crashing by 6 – 4 = 2 weeks
and revised duration be:
Extra cost of crashing activity ‘E’ by 2
weeks=
2 × 3000 = 6000
Direct cost = 6000 + 38000 = 44000
Indirect cost = 13 × 3150 = 40950
Total cost = 84950
Revised duration
Revised Cost
As, this total cost is lesser than previous step further crashing is possible
© Subash K. Bhattarai
Initial date of Preparation 2070 B.S
Path Duration
A – D
A – C – E
B – E
13 – 3 = l0 w
13 – 3 = 10 w
13 – 3 = 10 w
9/28/2020 33
After Crashing activity E, here we find that all paths become critical at this stage with project duration
equal to 13weeks.
Simultaneous Crashing
Now, Selecting 'A' from path A – D and A – C – E to crash and simultaneously selecting 'B' from path B
– E. Activity 'A' is selected due to common of both paths A – D and A – C – E. So, crashing activities 'A'
and 'B' by 3 weeks simultaneously we get,
Extra cost of crashing activity A
and B by 3 weeks
= 3 × (2500 + 1500) = 12000
Direct cost 12000 + 44000 =
56000
Indirect cost = 10 × 3150 = 31500
Total Cost = 87500
Revised duration
Revised Cost
Here, the total cost is higher than previous step.
Hence, we come to the end of crashing.
The optimum duration of the project is 13 weeks
The minimum cost of the project is Rs. 84950
The minimum duration of the project is 10 weeks
© Subash K. Bhattarai
Initial date of Preparation 2070 B.S
Try This !
Activity Immediate
predecessor
Time (weeks) Cost (Rs)
Normal Crash Normal Crash
A
B
C
D
E
F
G
–
–
A
A
B
B
D. E
8
10
6
9
10
13
5
5
8
5
6
9
13
3
2000
4000
3000
5000
2500
5000
1000
2300
4300
3125
5225
2700
-
1700
If the indirect cost per week is Rs. 300, find the optimal crashed project completion time
and corresponding minimum cost.
9/28/2020 34© Subash K. Bhattarai
Initial date of Preparation 2070 B.S

More Related Content

What's hot

Construction planning & management
Construction planning & managementConstruction planning & management
Construction planning & managementManit Agarwal
 
Project management in construction.
Project management in construction.Project management in construction.
Project management in construction.NAVNEET KUMAR JHA
 
Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...A Makwana
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction ManagementShahin MB
 
Specifications 101
Specifications 101Specifications 101
Specifications 101Andrej_M
 
Estimation and costing of a commercial building
Estimation and costing of a commercial buildingEstimation and costing of a commercial building
Estimation and costing of a commercial buildinglckr117
 
Line of balance in civil engineering
Line of balance in civil engineeringLine of balance in civil engineering
Line of balance in civil engineeringrathodjaydeep2
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESPundlik Rathod
 
Construction Project management
Construction Project management Construction Project management
Construction Project management Anupama holla
 
QUALITY CONTROL AND SAFETY DURING CONSTRUCTIONIjmet 08 03_012
QUALITY CONTROL AND SAFETY DURING CONSTRUCTIONIjmet 08 03_012QUALITY CONTROL AND SAFETY DURING CONSTRUCTIONIjmet 08 03_012
QUALITY CONTROL AND SAFETY DURING CONSTRUCTIONIjmet 08 03_012IAEME Publication
 
Project cost stimating
Project cost stimatingProject cost stimating
Project cost stimatinghatim ahmed
 
Estimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provisionEstimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provisionAshwiniChaudhari13
 
Construction scheduling & Cost control
Construction scheduling & Cost controlConstruction scheduling & Cost control
Construction scheduling & Cost controlGuhan M
 
introduction to construction management
 introduction to construction management introduction to construction management
introduction to construction managementHira Atiq
 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-ContractsNikhil Kumar
 
Quality in Construction
Quality in ConstructionQuality in Construction
Quality in ConstructionDr K M SONI
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Managementjohnkirth1898
 

What's hot (20)

Module 3 - Construction quality and safety by Dr.Vinay Kumar B M
Module 3 - Construction quality and safety by Dr.Vinay Kumar B M Module 3 - Construction quality and safety by Dr.Vinay Kumar B M
Module 3 - Construction quality and safety by Dr.Vinay Kumar B M
 
Construction planning & management
Construction planning & managementConstruction planning & management
Construction planning & management
 
Project management in construction.
Project management in construction.Project management in construction.
Project management in construction.
 
Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction Management
 
Specifications 101
Specifications 101Specifications 101
Specifications 101
 
Estimation and costing of a commercial building
Estimation and costing of a commercial buildingEstimation and costing of a commercial building
Estimation and costing of a commercial building
 
Line of balance in civil engineering
Line of balance in civil engineeringLine of balance in civil engineering
Line of balance in civil engineering
 
CONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPESCONTRACTS AND ITS TYPES
CONTRACTS AND ITS TYPES
 
Construction Project management
Construction Project management Construction Project management
Construction Project management
 
QUALITY CONTROL AND SAFETY DURING CONSTRUCTIONIjmet 08 03_012
QUALITY CONTROL AND SAFETY DURING CONSTRUCTIONIjmet 08 03_012QUALITY CONTROL AND SAFETY DURING CONSTRUCTIONIjmet 08 03_012
QUALITY CONTROL AND SAFETY DURING CONSTRUCTIONIjmet 08 03_012
 
Project cost stimating
Project cost stimatingProject cost stimating
Project cost stimating
 
Estimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provisionEstimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provision
 
Construction scheduling & Cost control
Construction scheduling & Cost controlConstruction scheduling & Cost control
Construction scheduling & Cost control
 
introduction to construction management
 introduction to construction management introduction to construction management
introduction to construction management
 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-Contracts
 
Types of estimates
Types of estimatesTypes of estimates
Types of estimates
 
Quality in Construction
Quality in ConstructionQuality in Construction
Quality in Construction
 
Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 

Similar to Construction Project Planning Scheduling Guide

Mahmoud Makram-Planning Engineeer-CV
Mahmoud Makram-Planning Engineeer-CVMahmoud Makram-Planning Engineeer-CV
Mahmoud Makram-Planning Engineeer-CVMahmoud Makram
 
Fundamentals of estimating_and_costing
Fundamentals of estimating_and_costingFundamentals of estimating_and_costing
Fundamentals of estimating_and_costingPrasad Manerikar
 
Job Profile as a Planning Engineer
Job Profile as a Planning EngineerJob Profile as a Planning Engineer
Job Profile as a Planning EngineerMD TAUSIF ASLAM
 
3-Construction Management.pdf
3-Construction Management.pdf3-Construction Management.pdf
3-Construction Management.pdfGhulamQadirWaqar1
 
3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project managementKabilan Kabi
 
Resume of Islam M. Elshora MEP Technical Office & BIM Manager
Resume of Islam M. Elshora MEP Technical Office & BIM Manager Resume of Islam M. Elshora MEP Technical Office & BIM Manager
Resume of Islam M. Elshora MEP Technical Office & BIM Manager Islam Elshoura
 
A PPT ON CONSTRUction PROJECT PLANNING - RASHID HUSSAIN.pdf
A PPT ON CONSTRUction PROJECT PLANNING - RASHID HUSSAIN.pdfA PPT ON CONSTRUction PROJECT PLANNING - RASHID HUSSAIN.pdf
A PPT ON CONSTRUction PROJECT PLANNING - RASHID HUSSAIN.pdfssuserfc98db
 

Similar to Construction Project Planning Scheduling Guide (20)

81800178CV
81800178CV81800178CV
81800178CV
 
012741
012741012741
012741
 
12741
1274112741
12741
 
12741
1274112741
12741
 
EstimatesPresentation.pptx
EstimatesPresentation.pptxEstimatesPresentation.pptx
EstimatesPresentation.pptx
 
Mahmoud Makram-Planning Engineeer-CV
Mahmoud Makram-Planning Engineeer-CVMahmoud Makram-Planning Engineeer-CV
Mahmoud Makram-Planning Engineeer-CV
 
Fundamentals of estimating_and_costing
Fundamentals of estimating_and_costingFundamentals of estimating_and_costing
Fundamentals of estimating_and_costing
 
CM1CM1.pptx
CM1CM1.pptxCM1CM1.pptx
CM1CM1.pptx
 
Resume_[Sr. Estimator - Sr. QS]
Resume_[Sr. Estimator - Sr. QS]Resume_[Sr. Estimator - Sr. QS]
Resume_[Sr. Estimator - Sr. QS]
 
Resume of Hariom
Resume of HariomResume of Hariom
Resume of Hariom
 
CMMCMM.pptx
CMMCMM.pptxCMMCMM.pptx
CMMCMM.pptx
 
Job Profile as a Planning Engineer
Job Profile as a Planning EngineerJob Profile as a Planning Engineer
Job Profile as a Planning Engineer
 
CM1CM1.pptx
CM1CM1.pptxCM1CM1.pptx
CM1CM1.pptx
 
3-Construction Management.pdf
3-Construction Management.pdf3-Construction Management.pdf
3-Construction Management.pdf
 
3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project management
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
CV-Sounder
CV-SounderCV-Sounder
CV-Sounder
 
CV Shreenivash Chandra
CV Shreenivash ChandraCV Shreenivash Chandra
CV Shreenivash Chandra
 
Resume of Islam M. Elshora MEP Technical Office & BIM Manager
Resume of Islam M. Elshora MEP Technical Office & BIM Manager Resume of Islam M. Elshora MEP Technical Office & BIM Manager
Resume of Islam M. Elshora MEP Technical Office & BIM Manager
 
A PPT ON CONSTRUction PROJECT PLANNING - RASHID HUSSAIN.pdf
A PPT ON CONSTRUction PROJECT PLANNING - RASHID HUSSAIN.pdfA PPT ON CONSTRUction PROJECT PLANNING - RASHID HUSSAIN.pdf
A PPT ON CONSTRUction PROJECT PLANNING - RASHID HUSSAIN.pdf
 

Recently uploaded

Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 

Recently uploaded (20)

Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 

Construction Project Planning Scheduling Guide

  • 1. Chapter 2.0 Construction Project Planning and Scheduling 9/28/2020 1 Contents: 2.1. Construction Planning 2.2. Steps and stages in Planning 2.3 Planning by client and contractor 2.4 preparing schedule 2.5 Time-Cost Trade-off © Subash K. Bhattarai Initial date of Preparation 2070 B.S
  • 2. 2.1 Construction Planning • "If you fail to plan, you are bound to fail" – Planning is the most important constituent of the construction management. In the simplest sense planning is the mental process deciding about the future line of actions. • It forms the basis for the project scope, schedule, resources, quality, risk, and integration • Planning is done to – Eliminate or reduce uncertainty – Improve efficiency of the operations – Obtain better understanding of the objectives – Provide basis for monitoring and controlling 9/28/2020 2© Subash K. Bhattarai Initial date of Preparation 2070 B.S
  • 3. Objectives of planning • The main objective of planning of a work is to execute the project or work most economically in terms of money and time both. • The effective planning depends upon the following factors: – Proper design of each element of the project – Proper selection of plant and equipment – Proper arrangements of repair of plant and equipment at site – Procurement of required materials well in advance – Ensure employment of skilled and unskilled employees – To arrange constant flow of funds in entire project duration – To provide required level of safety and compensations – Proper arrangements of communication and mobility in site 9/28/2020 3© Subash K. Bhattarai Initial date of Preparation 2070 B.S
  • 4. 2.2 Steps and Stages in Planning Steps involved in planning – Identifying the likely problems to be encountered in the execution of the work. – Ascertaining alternative feasibility of execution of work – Fixing the time of starting the execution of work – Deciding the time of delivering the materials at site – Deciding the quantities and duration of various types of machines and equipment – Deciding the number of different types of labors for various works and duration of their employment – Estimation of financial need – Estimation of the duration of completion of the work – Evaluation of the effectiveness of plan adopted 9/28/2020 4© Subash K. Bhattarai Initial date of Preparation 2070 B.S
  • 5. Stages of planning Usually the stages of planning are as follows: – Preplanning • Setting out objectives • Cost benefit analysis • Project go / no-go decision – Detailed planning • Detailed design and drawings • Specifications • Quantities calculation • WBS is done • Sequence and scheduling of the activities are done – Monitoring and controlling • In this phase, the progress of construction is monitored as per proposed scheduled. • Updating of schedule can be carried out according to the actual progress of work. • Preparation of the revised forecasts regarding the availability of various resources is done. 9/28/2020 5© Subash K. Bhattarai Initial date of Preparation 2070 B.S
  • 6. 2.3 Planning by the Client /Owner/Employer Pre-tender / pre-construction stage planning – Clients sets clear objectives of the project – Client communicate the objectives to all the parties and stakeholders – After proper investigations of the project, client prepares quantity estimates and determines the quantum of money required for the completion of the work. – Take respective approval of the project from concerned authority – Selection of project team and project appraisal – Select the consultant (if required) – Bidding and contract award (Selection of Contractor) Construction stage planning – Revision in objectives in responding unexpected events – Make site available for the contractor – Timely payment and settlement of claims – Keep the changes less – Update performance bond/ security of the contractor – Timely decision Post construction stage planning – Prepares project operation schedule – Prepares project maintenance schedule – Project ownership 9/28/2020 6© Subash K. Bhattarai Initial date of Preparation 2070 B.S
  • 7. Planning by the Contractor Pre-tender/ pre-construction stage planning The planning undertaken by the contractor after receipt of tender notice and before submitting the bid is known as pre-tender stage planning. – Careful Study of tender documents and drawings to find out the quantities of each item of work – Study of specifications and workout the detailed quality of materials required for different items – Determine the availability of construction materials at site or nearby site. – Determine the method of work execution i.e. by labor or equipment – Thorough study of site and site investigations 9/28/2020 7© Subash K. Bhattarai Initial date of Preparation 2070 B.S
  • 8. Construction stage planning After the acceptance of the tender, the contractor further needs in-depth planning. This stage of planning is also known as contract planning. – Studying the alternative methods of construction and to decide about subcontracting – Working out detailed quantities of materials required and examine and fixing the methods of procurement and sources of them – Working out detailed about construction workforce like skilled and unskilled manpower – Working out details of plants, equipment their layout and repair & maintenance strategy – Planning for camp facilities, access, accommodations, site offices and layout – Planning for surveillance like proper lighting, ventilation, drinking water, sanitation, first aid treatment – Study interdependence of different items of works and fixing the sequence of them – Finalize the work program of each item of work and to decide the dates of their starting and completing Planning by the Contractor contd.. 9/28/2020 8© Subash K. Bhattarai Initial date of Preparation 2070 B.S
  • 9. Post construction stage planning • Demobilization of plants and equipment • Demobilization of labors • Clearance of materials inventory and its stock • Handover the project to client in targeted date • Responsible for the defect liability construction within its period Planning by the Contractor contd.. 9/28/2020 9© Subash K. Bhattarai Initial date of Preparation 2070 B.S
  • 10. 2.4 Preparing Schedule Scheduling A construction schedule is a graphic representation which shows the phasing rate of construction with the starting and completing dates of each activity and the sequential relationship among various operations in a construction project. Use of scheduling • Following are the use of scheduling • The quantity of work involved, labor, material, equipment and money required at each stage of work can be determined by scheduling. • The actual progress of the work can be checked from time to time by scheduling • The project can be carried out in systematic manner using scheduling 9/28/2020 10© Subash K. Bhattarai Initial date of Preparation 2070 B.S
  • 11. Classification of scheduling Schedules can be classified according to the requirements as follows: – Construction schedule – Materials schedule – Labor schedule – Equipment schedule – Financial schedule – Control schedule – Organizational schedule – Summary schedule Methods of scheduling Bar chart or Gantt charts Milestone charts Network analysis 9/28/2020 11© Subash K. Bhattarai Initial date of Preparation 2070 B.S
  • 12. Construction schedule and its preparation Before preparing construction schedule following information must be known – Various operations to be done in a particular project – Quantum of works to be done in each operation – Unit of measurement – Rate of progress of work with due allowance of weather conditions – Number of labors required – Number and types of plants and equipment required – Date of starting and completing the activity – Correlation between different operations The procedure of preparing construction schedule is as follows: – The work or project is divided into number of operations and their inter dependence or relationship is studied. After the careful study of their interdependence the sequence of operation is decided – The quantity of work involved in each operation is to be determined – The time required for the completion of each operation as well as the completion of total project is determined. This can be done by knowing the quantum of work involved and the rate 9/28/2020 12© Subash K. Bhattarai Initial date of Preparation 2070 B.S
  • 13. 9/28/2020 13© Subash K. Bhattarai Initial date of Preparation 2070 B.S
  • 14. S.N Descripti ons of Materials Total Quantity Month I II III P A P A P A 1 cement 1500 bags 500 502 50 48 700 701 2 re-bar 100 ton … … … …. 3 sand 1000 m3 Material Schedule 9/28/2020 14© Subash K. Bhattarai Initial date of Preparation 2070 B.S
  • 15. S.N Types of Equipment Total Number Required Total Time Required Month I II III IV P A P A 1 Excavator 1 20 hrs 10 8 1 0 9 2 Mixer 1 60 hrs 15 1 0 2 0 3 Vibrator 1 30 hrs Equipment Schedule 9/28/2020 15© Subash K. Bhattarai Initial date of Preparation 2070 B.S
  • 16. Labor Schedule S.N. Descriptions of Labor Total time Required Month I II III IV P A P A P A 1 SL Mason Carpenter Bar-bender 100md 50 md 20 md 30 md 50 20 2 USL 3 9/28/2020 16© Subash K. Bhattarai Initial date of Preparation 2070 B.S
  • 17. Indirect cost The expenditures which cannot be allotted clearly to the individual activities of the project but are assessed in total are called indirect costs. The indirect cost includes overhead charges, administrative and establishment charges, supervision charges, loss of revenue, loss in profit and penalty etc. 2.5 Time Cost Trade- Off 9/28/2020 17 Project cost For any project, total expenditure incurred in terms of manpower, equipment, machinery and materials to complete an activity/ies known as total cost of the project. The total sum of the project is the sum of two distinct costs. Direct and Indirect cost The cost of materials, equipment and manpower spent on implementing an activity / ies refers to the direct cost. The direct costs of project are of major concern and behavior pattern of direct costs with time is of importance. Direct cost of a project depends on the completion time of project, but the variation is not linear. Direct cost © Subash K. Bhattarai Initial date of Preparation 2070 B.S
  • 18. 9/28/2020 18 15 Quantity Considered for Rate Analysis= 1.000 cu.m. S.N. Description Quantity Unit Unit Rate Amount A Labor A.1 Skilled Labor 0.500 m.d. Rs. 1,000.00 Rs. 500.00 A.2 Unskilled Labor 3.500 m.d. Rs. 735.00 Rs. 2,572.50 Total of Labor Cost Rs. 3,072.50 B Materials B.1 Cement 320.000 kg. Rs. 16.90 Rs. 5,408.00 B.2 40mm Aggregate 0.520 cu.m. Rs. 3,386.88 Rs. 1,761.17 B.3 20mm Aggregate 0.330 cu.m. Rs. 3,492.72 Rs. 1,152.59 B.4 Sand (Rough Sand) 0.445 cu.m. Rs. 2,928.24 Rs. 1,303.06 B.5 Water 130.000 lit. Rs. 0.26 Rs. 33.80 B.6 Diesel 3.000 lit. Rs. 97.50 Rs. 292.50 B.5 Petrol 0.100 lit. Rs. 111.50 Rs. 11.15 Total of Materials Cost Rs. 9,962.27 C Equipments C.1 Mixer 0.600 hour Rs. 1,875.00 Rs. 1,125.00 C.2 Vibrator 0.250 hour Rs. 120.00 Rs. 30.00 Total of Equipment Cost Rs. 1,155.00 Total Cost Rs. 14,189.77 Contractor's Overhead (15%) Rs. 2,128.46 Total Including Overhead Rs. 16,318.23 Unit Rate Rs. 16,318.23 PCC Work : Providing , laying, compacting and curing 100mm thick plain cement concrete, M15 (1 cement : 2 sand : 4 aggregate) on foundation, floor and other specified area with O.P. cement, sand and stone ballast of 10-20mm size aggregate, proper mixing with mixture machine, laying & placing in position compacting with vibrator, including curing the job to approved level, lines and dimensions all complete as per drawings, specifications and instruction of the site engineer. Direct Cost Indirect Cost © Subash K. Bhattarai Initial date of Preparation 2070 B.S
  • 19. Direct Cost Behavior With Time 9/28/2020 19 Cost Tim e Direct Cost Normal Time 10M (Project duration) Cost rises if project duration is prolonged Cost rises if project is crashed Normal Cost:10000K (Project Direct Cost) 12M8M © Subash K. Bhattarai Initial date of Preparation 2070 B.S
  • 20. Indirect Cost behavior with time 9/28/2020 20 Cost Time Indirect Cost (Directly proportional) Normal Time Cost rises if project duration is prolonged Cost reduces if project is crashed Indirect Cost © Subash K. Bhattarai Initial date of Preparation 2070 B.S
  • 21. Total Cost Behavior With Time 9/28/2020 21 Cost Time Direct Cost To Indirect Cost Total Cost TnTc Cc Cm Cn A C B © Subash K. Bhattarai Initial date of Preparation 2070 B.S
  • 22. Definitions of Terms Normal time The time usually allowed for an activity by the estimator is known as normal time. It is the standard time for that activity and is denoted by (Tn). Crash time The minimum possible time in which an activity can be completed by deploying extra resources is known as crash time. Beyond the crash time the duration of an activity cannot be reduced or shortened by any amount of increase in mobilization. It is denoted by (Tc). Normal cost The direct cost required to complete the activity in the normal duration is called normal cost and is denoted by (Cn). Crash cost The direct cost corresponding to the crash time of completing an activity is known as crash cost and is denoted by (Cc). 9/28/2020 22 Minimum duration The duration obtained after possible crashing of activities is known as minimum duration (Tm). Further reduction or crashing of duration is not possible after this point. © Subash K. Bhattarai Initial date of Preparation 2070 B.S
  • 23. Cost slope • The direct cost curve generally is a curve as shown below. But this curve can be approximated by the straight line or more than one straight lines depending upon the flatness of the curve. Thus the slope of this straight line is cost slope. 9/28/2020 23 Cost slope (CS) = Crash cost normal cost Normal time crash time   Normal Point ‘B’ Crash Point ‘A’ Normal time (Tn) (Regular time) Crash time (Tc) Normal Cost (Cn) Crash Cost (Cc) Direct Cost Activity Time © Subash K. Bhattarai Initial date of Preparation 2070 B.S
  • 24. Time cost trade-off • Time and cost are the two most important resources that a project manager deals with. Both resources have constrained, and the job of a project manager is to have judicious balance between them. The judicious balance between time and cost is called Time-Cost trade-off and it can be achieved by studying the availability and demand of these resources for the given project. 9/28/2020 24© Subash K. Bhattarai Initial date of Preparation 2070 B.S
  • 25. Total project costs include both direct costs and indirect costs of performing the activities of the project. If each activity of the project is scheduled for the duration that results in the minimum direct cost (normal duration) then the time to complete the entire project might be too long and substantial penalties associated with the late project completion might be incurred. At the other extreme, a manager might choose to complete the activity in the minimum possible time, called crash duration, but at a maximum cost. 9/28/2020 25 Time cost trade-off Non-linear time and cost trade-off for an activity Project time-cost relationship: Thus, planners perform what is called time cost trade-off analysis to shorten the project duration. This can be done by selecting some activities on the critical path to shorten their duration. As the direct cost for the project equals the sum of the direct costs of its activities, then the project direct cost will increase by decreasing its duration. On the other hand, the indirect cost will decrease by decreasing the project duration, as the indirect cost are almost a linear function with the project duration. © Subash K. Bhattarai Initial date of Preparation 2070 B.S
  • 26. From the total cost ACB, the total cost of a project is minimum for certain time duration. This duration is known as optimum duration (To) for the corresponding minimum cost (Cm). Further, if the project duration is increased, the total cost will also increase. On the other hand, if the project duration is decreased to the crash value, the project cost will be the highest. The optimum duration is less than the normal duration (Tn) corresponding to the direct costs. This is because both direct and indirect cost increases beyond the normal duration, whereas below the normal duration indirect cost decrease, but the direct cost increases. 9/28/2020 26© Subash K. Bhattarai Initial date of Preparation 2070 B.S
  • 27. Steps in optimization of cost (Cost optimization through Network) 1. First, draw the network diagram and find out all the possible paths. Critical path and non-critical paths. Critical path duration is the normal project duration for that project 2. Calculate the direct cost by adding the normal cost of all activities. Calculate indirect cost by multiplying project duration with the indirect cost (overhead or indirect expense) per unit time 3. Calculate the total cost by adding direct cost and indirect cost. This total cost is the baseline cost for the calculation. Similarly, the longest duration (critical path duration) is the project duration as a baseline duration for the calculation. 4. Calculate the cost slopes of all activities and rank them in ascending order of cost slopes. 5. Start crashing the project from a critical path (since this is the project duration) by selecting such critical activity having least cost slope as per ranking to the maximum possible extent (observe other non-critical paths which are likely to be critical) 6. Calculate the direct cost by adding the extra cost of crashing (cost slope X (Tn-Tc)) required for crashing that activity to the direct cost calculated in previous steps and corresponding indirect cost of reduced project duration. 9/28/2020 27© Subash K. Bhattarai Initial date of Preparation 2070 B.S
  • 28. Crashing Contd.. After step six, three possible cases may arise: Case I: If the same path remains critical (longest) then crashing is considered for the critical activity serially in the ascending order to their cost slope as far as possible. Case II: While crashing the critical path, there may emerge a new critical path/s then crashing is carried out for the common activity. If there is more than one common activity, activity with the least cost slope is selected first and continues serially as per the ranking of cost slopes. Case III: After crashing as per the case II, if there is a possibility of crashing then, one activity from each path is selected at one time for crashing. This crashing is known as simultaneous crashing or parallel crashing. The process is continued until the project shortening is possible. Note: Every time after crashing, the direct cost and indirect cost is calculated to find out the total cost. If the total cost calculated after crashing is greater than the earlier step, we come to the end of optimization. Whereas, for the determination of minimum possible time (Tm), crashing should be continued until the possibility. 9/28/2020 28© Subash K. Bhattarai Initial date of Preparation 2070 B.S
  • 29. Numerical 1. The following table shows the costs and duration of each activity of a project. The network is shown. The indirect cost may be taken as Rs. 3150.- per week. Determine the optimum duration of the project and corresponding minimum cost. Activity Predecessor Normal duration (Tn) Normal cost (Cn) Crash duration (Tc) Crash cost (Cc) A B C D E - - A A B,C 7 9 5 6 6 8000 5000 7000 9000 6000 4 6 2 4 4 15500 9500 10000 16000 12000 9/28/2020 29© Subash K. Bhattarai Initial date of Preparation 2070 B.S
  • 30. Solution 9/28/2020 30 2 3 41 18, 18 12, 12 9 6 6 E D 7, 7 A 7 0, 0 B 5 C Drawing the network diagram, finding possible paths, project duration and total cost: Possible Paths Duration (w) A – D 13 A – C – E 18 B – E 15 Here, The path A – C – E is the project duration as it is the critical path. Therefore, The project duration in 18 Weeks Direct Cost (Summation of normal cost of all activities) =  normal cost = 35000 Indirect Cost (Project duration x indirect cost per week) = 18 × 3150 = 5670  Total project cost (Direct cost + Indirect Cost) = 91700 © Subash K. Bhattarai Initial date of Preparation 2070 B.S
  • 31. Activity Difference in cost Crash cost- normal cost (Cc-Cn) Difference in duration Normal duration - Crash duration (Tn-Tc) Cost slope = (Cc- Cn)/(Tn-Tc) Rank A B C D E 15500-8000 =7500 4500 3000 7000 6000 7-4 = 3 3 3 2 2 7500/3 = 2500 1500 1000 3500 3000 3 2 1 5 4 9/28/2020 31 Determining the cost slope of all activities. Crashing Path Duration A – D 13 w A – C – E 18 – 3 = 15 w B – E 15 w From Critical path A-C-E, select activity ‘C’ for crashing [activity 'C' has minimum cost slope amongst critical activities] by 7-4 weeks = 3 weeks (i.e. maximum possible extent) and revised duration be: (Note be aware of other non-critical path/s as well. We cannot reduce the project duration below other path’s duration) Extra cost of crashing activity 'C' by 3 weeks = 3 × 1000 = 3000 Increment in Direct cost = 35000 + 3000 = 38000 Decrement in Indirect cost = 15 × 3150 = 47250 Total Cost of project = 85250 Revised duration Revised Cost As, this total cost is lesser than previous step further crashing is possible © Subash K. Bhattarai Initial date of Preparation 2070 B.S
  • 32. 9/28/2020 32 Path Duration A – D 13 w A – C – E 15 – 2 = 13 w B – E 13 w After Crashing activity ‘C’, here we find two critical paths A – C – E and B – E with duration equal to 15 weeks. So, crashing must be carried by selecting common activity from both paths for an immediate result. Common Activity Crashing As we see activity ‘E’ is common to both paths. So selecting activity ‘E’ for crashing by 6 – 4 = 2 weeks and revised duration be: Extra cost of crashing activity ‘E’ by 2 weeks= 2 × 3000 = 6000 Direct cost = 6000 + 38000 = 44000 Indirect cost = 13 × 3150 = 40950 Total cost = 84950 Revised duration Revised Cost As, this total cost is lesser than previous step further crashing is possible © Subash K. Bhattarai Initial date of Preparation 2070 B.S
  • 33. Path Duration A – D A – C – E B – E 13 – 3 = l0 w 13 – 3 = 10 w 13 – 3 = 10 w 9/28/2020 33 After Crashing activity E, here we find that all paths become critical at this stage with project duration equal to 13weeks. Simultaneous Crashing Now, Selecting 'A' from path A – D and A – C – E to crash and simultaneously selecting 'B' from path B – E. Activity 'A' is selected due to common of both paths A – D and A – C – E. So, crashing activities 'A' and 'B' by 3 weeks simultaneously we get, Extra cost of crashing activity A and B by 3 weeks = 3 × (2500 + 1500) = 12000 Direct cost 12000 + 44000 = 56000 Indirect cost = 10 × 3150 = 31500 Total Cost = 87500 Revised duration Revised Cost Here, the total cost is higher than previous step. Hence, we come to the end of crashing. The optimum duration of the project is 13 weeks The minimum cost of the project is Rs. 84950 The minimum duration of the project is 10 weeks © Subash K. Bhattarai Initial date of Preparation 2070 B.S
  • 34. Try This ! Activity Immediate predecessor Time (weeks) Cost (Rs) Normal Crash Normal Crash A B C D E F G – – A A B B D. E 8 10 6 9 10 13 5 5 8 5 6 9 13 3 2000 4000 3000 5000 2500 5000 1000 2300 4300 3125 5225 2700 - 1700 If the indirect cost per week is Rs. 300, find the optimal crashed project completion time and corresponding minimum cost. 9/28/2020 34© Subash K. Bhattarai Initial date of Preparation 2070 B.S