SlideShare a Scribd company logo
PROJECT SCHEDULING &
TIME MANAGEMENT
LECTURE 4
CONTENT OF PRESENTATION
 WBS/ Activity Definition
 Scheduling (Planning and
Scheduling)
o Objectives
o Techniques
o Critical Path Method (CPM)
 Basic Definition of CPM
 Activity
 Activity Duration
 Network Construction
 Example 1
o Histogram
 Resource Histogram
 Constructing Resource histogram
o Procedure for Resource Leveling
o PERT
o Example
 Use of software for planning,
scheduling & control of projects
o Process overview
o Software application
o EVMS
Work Breakdown Structure (WBS)
• To be able to perform an accurate estimate of the
project targets it is very pertinent to divide project into
manageable sets of components or activities called as
(WBS) of the project.
• Patrick (2003) defines WBS as
“a hierarchical system that represents the total
project scope in increasing levels of detail to
define, organise, and display the project work
in measurable and manageable components”
3
Work Breakdown Structure (WBS)
PMI
• The WBS is a hierarchical decomposition of the total
scope of work to be carried out by the project team to
accomplish the project objectives and create the
required deliverables. Each descending level of the
WBS represents an increasingly detailed definition of
the project work.
• The WBS is finalized by assigning each work package
to a control account and establishing a unique identifier
for that work package from a code of accounts. These
identifiers provide a structure for hierarchical summation
of costs, schedule, and resource information.
4
Sample WBS
5
Sample WBS
6
Work Breakdown Structure (WBS)
• The WBS consists of different levels
where level one is the least detailed
level often representing the entire
project. The number of activities in the
WBS grows quite rapidly and it is not
unusual that a large construction project
is broken down into several hundreds of
activities. There is no specific rule about
which level of detail a WBS should have
but a low level of detail may result in
insufficient detail for effective planning,
whereas a too high level of detail may
become unmanageable and increase
planning costs. It is generally the case
that the WBS is poorly detailed rather
than too detailed. According to Jackson
(2004) the level of detail should correlate
with the control level desired, i.e. to have
enough activities and just the right
amount of detail so that the work-flow
effectively can be monitored and
managed.
7
A proposed WBS for an infrastructure project (multi-storey building project).
Creating the Work Breakdown Structure
(WBS)
• A WBS is a deliverable-oriented grouping of the work
involved in a project that defines the total scope of the
project
• WBS is a preliminary document that provides the basis for
planning and managing project schedules, costs and
resources
• Decomposition is subdividing project deliverables into
smaller pieces
• A work package is a task at the lowest level of the WBS
8
Sample Intranet WBS Organized by Phase
9
Intranet WBS in Tabular Form
1.0 Concept
1.1 Evaluate current systems
1.2 Define Requirements
1.2.1 Define user requirements
1.2.2 Define content requirements
1.2.3 Define system requirements
1.2.4 Define server owner requirements
1.3 Define specific functionality
1.4 Define risks and risk management approach
1.5 Develop project plan
1.6 Brief Web development team
2.0 Web Site Design
3.0 Web Site Development
4.0 Roll Out
5.0 Support
10
Intranet WBS and Gantt Chart in Microsoft
Project
11
Gantt Chart Organized by Project Management
Deptt.
12
USES OF WBS
13
Exercise: WBS
Draw hierarchal WBS of a project “Establishment 1122
Emergency Response Centers” in all nine divisions and 36
districts of Punjab. The following scope of work was to be
executed at each station.
• Design and Construction Supervision of facility
• Construction of Emergency Response Center
• Procurement of all furniture, fixtures, CCTV, attendance record
• Purchase and installation of one server, 20 computers and associated
software & hardware including scanner and printers
• Purchase and installation High quality telephone exchange
• Networking of computers, connectivity, internet and intranet
• Procurement of 4 Ambulances and associated medical equipment
• Procurement of Firefighting vehicle, 2 cranes and other emergency
response equipment
• Recruitment and Training of staff
SCHEDULE & TIME
MANAGEMENT
PROJECT TIME MANAGEMENT
6.1 ACTIVITY DEFINITION
1. Inputs
1. Enterprise environmental
factors .
2. Organizational process
assets
3. Project scope statement
4. Work Breakdown
structure
5. WBS Dictionary
6. Project management plan
2. Tools and Techniques
1. Decomposition
2. Templates
3. Rolling wave planning
4. Expert judgment
5. Planning component
3. Outputs
1. Activity list
2. Activity attributes
3. Milestone list
4. Requested changes
6.2 ACTIVITY SEQUENCING
1. Inputs
.1 Project scope statement
.2 Activity list
.3 Activity attributes
.4 Milestone List
.5 Approved change requests
2 . Tools and Techniques
.1 Precedence Diagramming
Method (PDM)
.2 Arrow Diagramming Method
(ADM)
.3 Schedule network templates
.4 Dependency determination
.5 Applying leads and lags
3. Outputs
.1 Project schedule network
diagrams
.2 Activity list (updates)
.3 Activity attributes (updates)
.4 Requested changes
6.3 ACTIVITY RESOURCE
ESTIMATING
1. Inputs
.1 Enterprise environmental
factors
.2 Organizational process assets
.3 Activity list
.4 Activity attributes
.5 Resource availability
.6 Project management plan
2. Tools and Techniques
.1 Expert judgment
.2 Alternatives analysis
.3 Published estimating data
.4 Project management software
.5 bottom-up-estimating
3. Outputs
.1 Activity resource requirements
.2 Activity attributes (updates)
.3 Resource breakdown structure
.4 Resource calendars (updates)
.5 Requested changes
Continue on
next slide
PMI Approach of Project Time Management (Cont..)
PMI Approach of Project Time Management (Cont..)
PROJECT TINE MANAGEMENT
6.4 ACTIVITY DURATION
ESTIMATING
1. Inputs
.1 Enterprise environmental
factors
.2 Organizational process assets
.3 Project scope statement
.4 Activity list
.5 Activity attributes
.6 Activity resource requirements
.7 Resource calendars
.8 Project Management plan
. Risk register
. Activity cost estimates
2. Tools and Techniques
.1 Expert judgment
.2 Analogous estimating
.3 Parametric estimating
.4 Three-point estimating
.5 Reserve analysis
3. Outputs
.1 Activity duration estimates
.2 Activity attributes (updates)
6.5 SCHEDULE DEVELOPMENT
1. Inputs
.1 Organizational process assets , .2 Project
scope statement, .3 Activity list
.4 Activity attributes, .5 Project schedule
network diagrams, .6 Activity resource
requirements, .7 Resource calendars
.8 Activity duration estimates
.9 Project management plan, 10. Risk
register
2. Tools and Techniques
.1 Schedule network analysis
.2 Critical path method
.3 Schedule compression
.4 What-if scenario analysis
.5 Resource leveling
.6 Critical chain method
.7 Project management software
.8 Applying calendars
.9 Adjusting leads & lags
10. Schedule model
3. Outputs
.1 Project schedule
.2 Schedule model data
.3 Schedule baseline
.4 resource requirements (Updates)
.5 Activity attributes (updates)
.6 Project calendars (updates)
.7 Requested changes
6.6 SCHEDULE CONTROL
1. Inputs
.1 Schedule management plan
.2 Schedule baseline
.3 Performance report
.4 Approved change request
2. Tools and Techniques
.1 Progress reporting
.2 Schedule change control
system
.3 Performance measurement
.4 Project management
software
.5 Variance analysis
.6 Schedule comparison bar
charts
3. Outputs
.1 Schedule model data
(updates)
.2 Schedule baseline (updates)
.3 Performance measurements
.4 Requested changes
.5 Recommended corrective
actions
.6 Organizational process assets
(updates)
.7 Activity list (updates)
.8 Activity attributes (updates)
.9 Project management plan
(updates)
Continu
e on
Previou
s slide
PROJECT SCHEDULING
• Project Planning:
Process of identifying all the activities necessary to successfully
complete the project is called project planning.
• Project Scheduling:
Process of determining sequential order of planned activities,
assigning realistic duration, to each activity and determining start
and finish dates of each activity is called project scheduling.
Project planning is prerequisite to project scheduling because there
is no way to determine the sequential order of activities until they
are identified. However, the terms planning and scheduling are often
used synonymously because they are performed interactively. E.g.
when some schedule is reviewed, it may be decided that additional
activities may be added or rearranged in order to get the best
schedule of events of projects.
OBJECTIVES OF PROJECT SCHEDULING
 Finish project on time.
 Finish project within cost.
 Continuous (uninterrupted) flow of work.
 Reduced amount of rework.
 Minimize confusion and misunderstanding.
 Increased knowledge of status of project to every one
(including management).
 Knowledge of distribution of costs of project.
 Accountability of people / defined responsibility and clear
understanding of who does what, when and how much.
 Optimum use of resources.
TECHNIQUES FOR SCHEDULING
Techniques used for scheduling depends upon the type, size,
complexity, duration, personal and owner requirement. It is preferred
to use a simpler technique which is simple to use and easily
interpreted by all project participants. There are two general
techniques which commonly used for planning and scheduling.
 Bar Chart (Gantt Chart):
It is the graphical representation of Time (X-axis) and Activities on Y-
axis, so that the status of project may be visualized and controlled.
 Net work analysis system (CPM and PERT):
It is the schematic representation of various activities. This method
calculates the minimum completion time for a project along with start
and finish time of project activities.
 Software application: (MS Project, Primavera, Pertmaster, Risky
Project.
BAR CHART
 Bar Chart was developed by Henery L. Gantt in 1917, which is the most
common planning tool even today, which provided basis for developing
planning and scheduling software.
 Bar Charts are the easiest and most widely used form of scheduling in
project management. Even with other scheduling techniques, the eventual
schedule is presented the form of a bar chart. The level of detail of the
activities depends on the intended use of the schedule. The most
commonly used bar chart for engineering works is called Gantt chart.
 A Gantt chart is a type of bar chart that illustrates a project schedule, start
and finish dates of the terminal elements and summary elements of civil
engineering project. Terminal elements and summary elements comprise
the work breakdown structure of the project. Some Gantt charts also show
the dependency (i.e. precedence network) relationships between activities.
Gantt charts can be used to show current schedule status using percent-
complete shadings.
 Gantt charts have become a common technique for representing the
phases and activities of a project work breakdown (WBS), so they can be
understood by a wide audience all over the world.
CRITICAL PATH METHOD (CPM)
The Critical Path Method is a method where activities are arranged
based on interrelationship. It is a planning and control technique that
provides an accurate, timely and easily understood picture of the
project. Its purpose is to allows effective scheduling and controlling.
One of the most important features of CPM is the logic diagram. The
logic diagram graphically portrays the relationship between project
activities.
 Critical path in a network is a longest path in terms of time unit, which
gives minimum overall duration to complete the project.
 CPM calls attention which activities must be completed before other
activities can begun.
A
B
D
F
G
E
C
H
ACTIVITY
A common technique used to understand and organize complex
undertaking is to break the project into smaller pieces. This technique is
used both planning and estimating. Each activity is a discrete task.
Activities should be only be specified as per level of management. The
number and detail of listed quality will vary from job to job and depend
on the intended level of control. Usually for planning purposes activity
doesn’t exceed from 25 days, if exceeds may be divided into further
components. The activities must have four characteristics.
1. Time consumption: An activity must consume time.
2. Use of resources: An activity usually consumes Labour, Material or Equipment
resources.
3. Definite Start and Finish time: An activity represents a definite scope of work
i.e. Starting and Ending point in time.
4. Activities are measurable. The progress towards completion of activity’s scope
of work must be measureable.
ACTIVITY DURATION
• One of the most important steps in planning a project is estimating the
time required to complete each activity. The duration of each activity
is a function of quantity of work and work production rate. Work
production rates are based on planned composition of labor and
equipment used to perform the task. Careless estimates of production
rates may cause un economical use of personnel, materials,
equipment and time.
• When the project bid estimate is prepared, the estimator calculates
the quantity of material that must be put in place and assumes a
production rate to get the cost of each work, which is based
construction method and technique. The bid preparation information
can be served as the tool for calculating g an activity duration.
• All Activities in a schedule should have same unit of time, which may
be in months, weeks, days and hours.
ESTIMATION: EXAMPLE-1 (a)
a) In estimating a five storey office building, it was determined that 480
light fixtures would be installed on each floor. The production rate of Five
fixtures per man hour may be used for installation. The company has
five electrician. The normal working day will be 8 hours. What will be the
duration (in days) to install all lights in the building.
b) If the cost of one fixture is 1500 PKR and electrician takes around
1500 PKR per 8 hour working day. Then, considered 5% breakage of
fixtures during installation, find the budget of the activity.
SOLUTION:
Production Rate: 5 fixture x 5 electrician = 25 fixtures per man hour
1-man hour
Activity Duration = 480 fixture x 5 floors = 96 hours
25
Activity Duration = 96 hours = 12 day
8 hours
ESTIMATION: EXAMPLE-1 (b)
The following items of works were to be conducted in a
project;
1. Excavation of 4768 cubic meter
2. Driving of RCC Piles (48 Nos.) Dia 2ft. 200 ft deep.
Find Duration and Budget of Project. Assume missing data.
SOLUTION:
IMPORTANCE OF ACCURATE ESTIMATES
29
 Inaccurate time estimates can result in unrealistic schedule
 Inaccurate time estimates can result in inefficient use of
resources and late delivery.
 Inaccurate cost estimates can result in insufficient budget being
allocated, or excess budget being set aside for the project when
it could be used for other projects.
 If the cost or benefits estimates are inaccurate this can lead to
incorrect decisions about proceeding with the project being
made.
BASIC DEFINITIONS OF CPM TERMS
• Activity:- The performance of a task required to complete the project e.g.
foundation design, contract document, RCC form work, pouring of concrete.
• Network:- A diagram to represents the relationship of activities to complete
the project.
• Duration:- The estimated time required to perform an activity.
• Early Start (ES):- The earliest time an activity can be start.
• Early Finish (EF):- The earliest time an activity can be finished.
• Late Finish (LF):- The latest time an activity can be finished.
• Late Start (LS):- The latest time an activity can be started without delaying
the completion of project. (LS = LF – D)
• Total Float (TF):- The amount of time an activity may be delayed without
delaying the completion date of project.
Mathematically, TF = LF – EF = LS – ES.
• Critical Activity:- If total float for an activity is zero, activity is called critical
activity.
• Critical path is a longest path in terms of time unit in a network, which
gives minimum overall duration to complete the project.
NETWORK CONSTRUCTION
The performance of a task required to complete the project. Activity must
have a specific duration except the dummy activity, having zero duration.
Each activity is represented as can arrow or node. Arrows are not drawn
according to scale. The brief description about activity is written over arrow
or node. Duration (hours, week, months) to complete that activity is written
under the arrow, where 1 and 2 are the event. Which are written inside the
circles or boxes. The starting event is masked at the tail and finish event at
the head of the arrow.
Rules:
1. Each activity should be represented by a separate arrow.
2. The arrow may be straight or inclined lines.
3. Dummy activity should be represented with dotted lines.
4. Critical path must be shown clearly with double line.
5. Intersection of activity is not allowed.
6. Boxes are provided for event times (ES, EF, LS, LF)
7. EST is some reference time, normally EST = 0 at the start of the project /
work. EFT = EST + Duration.
8. Each activity is followed by a predecessor and successor except start and
finish activities. Any starting activity must have predecessor none, or finish
activity must have no successor.
EXAMPLE 2. CPM
Activity Duration
(days)
Preceding
Activity
(Predecessor)
A 3 None
B 5 A
C 8 A
D 10 B
E 5 B
F 7 C
G 12 D
H 8 E, F
I 3 G,H
1. Construct AOA network
2. Find ES, EF, LS and LF
of all activities
3. Find total float of all
activities (days)
4. Find the project
duration (days)
5. Mark critical path on
the network
EXAMPLE 3. CPM
EXAMPLE-4. CPM
Activity Duration Predecessor Resource Early
Start
(ES)
Early
Finish
(EF)
Late
Start
(LS)
Late
Finish
(LF)
Total
Float
(TF)
Remark
O 8 None 10
N 3 O 2
M 13 N 5
L 7 O 15
K 12 O 8
J 3 K 4
I 10 L 3
H 8 L 10
G 6 H,M 8
F 20 I 4
E 16 I 6
D 8 J 4
C 4 G, E 20
B 5 F 6
A 3 B, C,D 3
1. Construct AOA network
2. Find ES, EF, LS and LF of all
activities
4. Find the project duration (days)
5. Mark critical path on the network
Find total float of all activities (days)
EXAMPLE 5. CPM
Activity Duration Predecessor Resource ES EF LS LF (TF) Remark
Q 8 None 5
P 10 Q 6
O 7 Q 10
N 6 O 2
M 9 Q 5
L 5 M 15
K 4 O 8
J 7 L, K 4
I 9 L, K 3
H 20 P 10
G 12 H 8
F 9 N 4
E 20 N 6
D 11 I 4
C 7 E, J 20
B 7 G, F 6
A 3 B, C,D 3
1. Construct AON network
2. Find ES, EF, LS and LF of all
activities
Find total float of all activities (days)
4. Find the project duration (days)
5. Mark critical path on the network
EXAMPLE-6: CRITICAL PATH
Solution: Critical Path = Q – P – H – G – B – A, Project Duration = 60 days
2nd Path = Q – O – N – F – B – A, Duration = 40 days
3rd Path = Q – O – N – E – C – A, Duration = 51days
4th Path = Q – O – K – J – C – A, Duration = 36 days
5th Path = Q – O – K – I – D – A, Duration = 42 days
6th Path = Q – M – L – J – C – A, Duration = 39 days
7th Path = Q – O – K – I – D – A, Duration = 45 days
RECOURSE PROFILE &
HISTOGRAMS
RESOURCE HISTOGRAM
 It is a graphical
representation of time on X-
axis and resources on Y-axis.
 It is a view of project data in
which resource requirements,
usage, and availabilities are
shown against a time scale.
The personnel, equipment,
materials, and services
needed to complete tasks in
a project are resources.
TYPES OF RESOURCE HISTOGRAM
1. Labor Resource Histogram
2. Material Resource Histogram
3. Equipment Resource
Histogram
4. Cost Histogram
In these resource histograms time
is taken on x axis and the resource
is taken on y axis. For a
construction project total resources
are mentioned according to that
particular time these histograms
also help us to calculate cost for a
particular resource of a project at a
particular time because resource
can be converted in terms of cost.
PROCEDURE FOR RESOURCE LEVELING
1. Plan and Schedule project activities.
2. Construct a Network for the project.
3. Mark Critical Path (CP).
4. Construct the Bar Chart for the Project.
5. For each working day show resources of each activity at
their respective duration on Bar Chart.
6. Sum up the total resources vertically for each working day.
7. Plot the histogram for the resource.
8. Mark the sudden drop or rise in resource histogram.
9. Utilize the total float available for non critical activity to
level the resources by hit & trial method.
10. Recheck the leveled histogram and prepare a new
schedule of work / execution.
Activity Duration Pred. Labour
(Per
Day)
Total Cost of
Activity
ES EF LS LF Float
A 6 None 4 PKR60,000 0 6 0 6 0
B 20 A 8 PKR400,000 6 26 15 35 9
C 5 A 12 PKR100,000 6 11 6 11 0
D 8 A 4 PKR240,000 6 14 17 25 11
E 10 D 10 PKR300,000 14 24 25 35 11
F 14 C 10 PKR280,000 11 35 11 35 0
G 8 C 3 PKR320,000 11 19 45 53 34
H 12 C 20 PKR360,000 11 23 31 43 20
I 6 B, F 9 PKR180,000 14 20 37 43 23
J 10 E, H 6 PKR400,000 23 33 43 53 20
K 18 G, I, J 4 PKR180,000 35 53 35 53 0
PKR 2,820,000
EXAMPLE-7: CONSTRUCTING COST & LABOR
HISTOGRAM
EXAMPLE-7: CONSTRUCTING COST & LABOR
HISTOGRAM
S-CURVE
29 November 2022 45
EXAMPLE-8: CONSTRUCT S-CURVE FOR
EXAMPLE NO. 7
CONSTRUCTING RESOURCE HISTOGRAM
EARNED VALUE MANAGEMENT SYSTEM
(EVMS)
52
• EVM is a project performance measurement
technique that integrates scope, time, and cost
data.
• Given a baseline (original plan plus approved
changes), you can determine how well the project is
meeting its goals.
• You must enter actual information periodically to
use EVM.
• More and more organizations around the world are
using EVM to help control project costs.
EARNED VALUE MANAGEMENT
SYSTEM (EVMS)
• It’s a Management Tool
– Used for project status: (1) previous work
accomplished and (2) where the project was
planned to be.
– Early warning system to detect deficient or
endangered progress.
EARNED VALUE MANAGEMENT SYSTEM
(EVMS)
Why Use EVMS?
• Ensures a clear definition of work prior to beginning that
work
• Presents a logical plan for accomplishing the work
• Provides an objective measure of accomplishments
• Early and accurate identification of trends and problems
• Accurate picture of contract status
– cost, schedule, and scope
• Basis for course correction
• Supports mutual goals of contractor and customer
– bring project in on schedule and cost
Earned Value Management System
(EVMS)
• Budgeted cost for work scheduled
• Amount /level of effort or apportioned effort
scheduled to be accomplished in a given
time period
Planned Value (PV)
BCWS
• Budgeted cost for work performed
• Budgeted for level of effort or apportioned
effort activity completed within a given time
period
• Sometimes referred to as “earned value.”
Earned Value (EV)
BCWP
• Actual cost for work performed
• Amount reported as actually expended in
completing the work accomplished within a
given time period
Actual Cost (AC)
ACWP
Core Concept of Terms
EVMS Indicators
Cost variance (CV):
CV = BCWP – ACWP = EV – AC
A negative variance indicates a cost-overrun condition.
Schedule variance (SV):
SV = BCWP – BCWS = EV – PV
A negative variance indicates a behind-schedule
condition.
Cost performance index (CPI) =
Schedule performance index (SPI) =
If CPI = 1.0, we have perfect performance, If CPI >
1.0, project is under budgeted. If CPI < 1.0, project
is over budgeted.
If SPI = 1.0, we have perfect performance, If SPI >
1.0, project is ahead of schedule. If SPI < 1.0,
project is behind Schedule.
The cost and schedule performance index is most
often used for trend analysis as shown the figure.
Three-month, four-mouth, or six-month may be used
to predict trends. Trend analysis provides an early
warning system and allows managers to take
corrective action.
Variance and Index
Earned Value Management System (EVMS)
Variance and Index
Earned Value Management System (EVMS)
Critical Ratio (CR):
This indicator combines both the cost performance index (CPI) and schedule
performance index (SPI) to represent the project status
Critical Ratio (CR) = SPI x CPI
Project Status (PS):
This indicator is the average of both the cost performance index (CPI) and schedule
performance index (SPI) to represent the project status
Project Status (PS) = (SPI + CPI)/2
Schedule Variance in Time (SV.t)
Variance in Schedule at a particular time on project timeline.
Schedule Variance in time (duration) = (SV x T) / BAC
Earned Schedule (ES)
The measure of work performed in terms of schedule as on status date
Earned Schedule (ES) = T - SV(t)
TIME
COST
SCHEDULE ANALYSIS BAC
Data Date
AC
EV
PV
Progress at end of 3rd Month:
Project Budget (BAC): 37.22 lakhs
Funds Used (AC): 16.40 lakhs
Utilization = 44.1 %
Additional EV Parameters:
Planned (PV): 19.82 lakhs
Earned (EV): 14.50 lakhs
Schedule Performance
Planned (PV): 19.82 lakhs
Earned (EV): 14.50 lakhs
Schedule Variance = EV-PV = -5.32
Schedule Performance Index = EV/PV = 0.73
SV
TIME
COST
Cost Analysis BAC
Data Date
AC
EV
PV
Progress at end of 3rd Month:
Project Budget (BAC): 37.22 lakhs
Funds Used (AC): 16.40 lakhs
Utilization = 44.1 %
Additional EV Parameters:
Planned (PV): 19.82 lakhs
Earned (EV): 14.50 lakhs
Cost Performance
Actual Cost (AC): 16.40 lakhs
Earned (EV): 14.50 lakhs
Cost Variance = EV-AC = -1.90
Cost Performance Index = EV/AC = 0.88
CV
TIME
COST
ESTIMATE AT COMPLETIONBAC
Data Date
AC
EV
PV
Progress at end of 3rd Month:
Project Budget (BAC): 37.22 lakhs
Funds Used (AC): 16.40 lakhs
Utilization = 44.1 %
Additional EV Parameters:
Planned (PV): 19.82 lakhs
Earned (EV): 14.50 lakhs
Estimate at Completion
Actual Cost (AC): 16.40 lakhs
Earned (EV): 14.50 lakhs
EAC = BAC/CPI = 42.3
Variance at Completion = BAC-EAC = -5.07
PROJECT STATUS AT MONTH 3
Progress at end of 3rd Month:
Project Budget (BAC): 37.22 lakhs
Funds Used (AC): 16.40 lakhs
Utilization = 44.1 %
Additional EV Parameters:
Planned (PV): 19.82 lakhs
Earned (EV): 14.50 lakhs
Sheet 1 of 1
Ac ti vi ty
I D
Ac ti vi ty
De s cri p ti o n
Ori g
Du r
Bu d ge t
(BAC)
P l a nn e d
(BCW S )
E a rne d
(BCW P )
Ac tua l
(ACW P )
R ural H ealth C linic
T o t a l 2 1 0 3 , 7 2 2 , 0 0 0 . 0 0 1 , 9 8 2 , 8 0 0 . 0 0 1 , 4 5 0 , 0 0 0 . 0 0 1 , 6 4 0 , 0 0 0 . 0 0
G ener al
S u b to t a l 2 1 0 0 . 0 0 0 . 0 0 0 . 0 0 0 . 0 0
1 0 0 0 P r o j e c t S t a rt 0 0 . 0 0 0 . 0 0 0 . 0 0 0 . 0 0
1 1 1 0 P r o j e c t C o m p l e t e 0 0 . 0 0 0 . 0 0 0 . 0 0 0 . 0 0
Foundation
S u b to t a l 5 4 8 5 0 ,0 0 0 . 0 0 8 5 0 ,0 0 0 . 0 0 8 5 0 ,0 0 0 . 0 0 9 5 0 ,0 0 0 . 0 0
1 0 1 0 E a r t h w o r k s 1 8 5 0 , 0 0 0 . 0 0 5 0 , 0 0 0 . 0 0 5 0 , 0 0 0 . 0 0 6 0 , 0 0 0 . 0 0
1 0 2 0 F o u n d a t i o n u p t o P li n t h 2 4 8 0 0 ,0 0 0 . 0 0 8 0 0 ,0 0 0 . 0 0 8 0 0 ,0 0 0 . 0 0 8 9 0 ,0 0 0 . 0 0
S tr uctur e W or k
S u b to t a l 5 1 1 , 5 3 6 , 0 0 0 . 0 0 1 , 1 3 2 , 8 0 0 . 0 0 6 0 0 ,0 0 0 . 0 0 6 9 0 ,0 0 0 . 0 0
1 0 3 0 S u p e r - s t r u c t u r e 5 0 1 , 4 4 0 , 0 0 0 . 0 0 1 , 0 3 6 , 8 0 0 . 0 0 5 0 4 ,0 0 0 . 0 0 5 8 4 ,0 0 0 . 0 0
1 0 4 0 B l o c k M a s o n r y 1 5 9 6 , 0 0 0 . 0 0 9 6 , 0 0 0 . 0 0 9 6 , 0 0 0 . 0 0 1 0 6 ,0 0 0 . 0 0
Finishes
S u b to t a l 1 0 5 1 , 3 3 6 , 0 0 0 . 0 0 0 . 0 0 0 . 0 0 0 . 0 0
1 0 5 0 P l a s t e r 4 0 1 9 2 ,0 0 0 . 0 0 0 . 0 0 0 . 0 0 0 . 0 0
1 1 0 0 P l u m b i n g 1 5 1 0 0 ,0 0 0 . 0 0 0 . 0 0 0 . 0 0 0 . 0 0
1 0 9 0 E l e c t r i c a l W o r k s 2 5 2 0 0 ,0 0 0 . 0 0 0 . 0 0 0 . 0 0 0 . 0 0
1 0 7 0 F l o o r i n g 4 5 3 0 0 ,0 0 0 . 0 0 0 . 0 0 0 . 0 0 0 . 0 0
1 0 6 0 P a i n t 4 0 1 4 4 ,0 0 0 . 0 0 0 . 0 0 0 . 0 0 0 . 0 0
1 0 8 0 W o o d W o r k 2 0 4 0 0 ,0 0 0 . 0 0 0 . 0 0 0 . 0 0 0 . 0 0
M o nth s
1 2 3 4 5 6 7 8 9 1 0
P ro j ec t S ta rt
P ro j ec t Co m p l e te
E a rthwo rk s
F o u nd a ti o n u p to P li n th
S u p er-s tru ctu re
Bl o ck M a s on ry
P l a ste r
P l u m b i n g
E l e ctri c a l W o rk s
F l o ori n g
P a i nt
W o od W o rk
R e s o u rc e / Co s t P ro fi l e L e g e n d
P l a n n e d v a l u e c u rv e
E a rn e d v a l u e c u rv e
C u rre n t e s t im a t e c u rv e
T o t a l e a rl y c o s t p e r M o n t h ( C u rre n t E s t i m a t e )
T o t a l o f A l l R e s o u rc e s D e t a i l s c a l e ( l e f t ) : X 1 0 0 0 0 0
C u m u l a t i v e s c a l e (ri g h t ) : X 1 0 0 0 0 0
1 2 3 4 5 6 7 8 9 1 0
M o nth s
1
2
3
4
5
6
7
8
9
1 0
4
8
1 2
1 6
2 0
2 4
2 8
3 2
3 6
4 0
x 1 0 0 0 0 0 x 1 0 0 0 0 0
Sheet 1 of 1
PV
EV
AC
EAC
BAC
EXAMPLE-7 EVMS
PROGRAMME EVALUATION AND
REVIEW TECHNIQUE (PERT)
PROGRAMME EVALUATION AND REVIEW
TECHNIQUE (PERT)
 PERT is an inherent planning technique forces the manager to
develop a comprehensive plan and allows realistic scheduling. The
procedure for monitoring, forecasting and simulating allows the
manager to respond quickly to unexpected changes in the project,
detect trouble areas early and evaluate proposed alternative
courses of action. PERT also helps to evaluate alternatives at any
time during projects duration by looking effect of each change on its
completion date. PERT also helps to simulate the project time &
cost and effects of alternate decisions.
 It is a planning & Control techniques that precuts statistical
information regarding the uncertainties associated with completing
the different activities associated to a project. Expected Value of
activity direction
DIFFERENCE BETWEEN PERT AND CPM
CPM PERT
CPM uses one time estimate that represents
the normal time.
PERT uses three time estimates (optimistic, most
likely, and pessimistic) to derive an expected time.
CPM is deterministic in nature. PERT is probabilistic in nature,
CPM is used for those projects where percent
complete can be determined with reasonable
accuracy such as construction.
PERT is used for R&D, where percent complete is
almost impossible to determine except a completed
milestones.
CPM is activity oriented and can be used as
an arrow diagram network.
PERT is event oriented rather than activity oriented
and can be used as an arrow diagram network.
CPM as a controlling device for the simple
reason that one must repeat the entire
evaluation of the project each time the
changes are introduced into the network
PERT serves a useful control device as it assist the
management in controlling a project by calling attention
through constant review to such delays in activities
which might lead to a delay in the project completion
date.
Cannot be used for risk analysis and
management
Can be used for risk analysis and management
CPM Gives Critical Path PERT gives probability in % to achieve critical path
May be used successfully for projects without
uncertainties and risks
May be used successfully for projects with
uncertainties and risks
a) Draw net work for PERT
b) Find Expected Time “te”
for all activities and “TE “
c) Find Variance “σ2” for all
activities
d) Find “Z” value, when Ts=
40 days
e) Find the probability to
complete the project in 40
days
f) Find the scheduled
duration (Ts) for project
completion with 80%
probability
EXAMPLE-6: PERT
Activity Duration Pred. Expected
Time
Variance
O M P te σ2
A 4 8 15 Nil
B 8 10 20 Nil
C 11 12 15 Nil
D 13 15 20 C
E 2 3 4 B
F 2 3 5 A
G 3 4 8 A
H 1 2 3 G
I 5 8 12 D,E,F
J 3 5 7 H,I
EXAMPLE-7: PERT
Activity Duration Pre
d.
Expect
ed
Time
Varianc
e
O M P te σ2
A 8 10 15 Nil
B 8 10 12 A
C 11 12 13 B
D 18 20 26 B
E 1 2 4 B
F 1 2 5 C
G 3 4 7 E
H 1 2 3 F
I 10 15 21 D
J 3 5 7 G
K 32 40 56 H,I,
J
L 4 8 13 K
(i)Draw net work for PERT
(ii)Find Expected Time “te” for all
activities
(iii)Find Variance “σ2” for all activities
(iv)Find “Z” value, when Ts= 103
(v)What is the probability that project
will finish in 104 days?
(vi)What is the probability that activity
“K” will start on 55th day of project
execution?
Calculations:
SOLUTION
Activity Duration Pred Expecte
d Time
Variance
O M P te σ2
A 8 10 15 Nil
B 8 10 12 A
C 11 12 13 B
D 18 20 26 B
E 1 2 4 B
F 1 2 5 C
G 3 4 7 E
H 1 2 3 F
I 10 15 21 D
J 3 5 7 G
K 32 40 56 H,I,J
L 4 8 13 K
= 10.5 days
= =
= 1.36
EARNED VALUE MANAGEMENT
SYSTEM (EVMS)
SOFTWARE BASED
SCHEDULING &
MONITORING OF PROJECTS
PLANNING, SCHEDULING AND CONTROL
• MS Project
• Primavera (P3, P6)
• Risky Project
• Pertmaster
• Cloud based
Software application
Process Overview
 Project  Management.pptx

More Related Content

What's hot

PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERSPLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
Hafiz JUNAID
 
Chapter 3 Construction Planning and Scheduling lect. 3.ppt
Chapter 3 Construction Planning and Scheduling lect. 3.pptChapter 3 Construction Planning and Scheduling lect. 3.ppt
Chapter 3 Construction Planning and Scheduling lect. 3.ppt
ssuserb4074f
 
Ms project training ver 01
Ms project training ver 01Ms project training ver 01
Ms project training ver 01
Isidro Sid Calayag
 
PRIMAVERA P6 manual.pptx
PRIMAVERA P6 manual.pptxPRIMAVERA P6 manual.pptx
PRIMAVERA P6 manual.pptx
GracePentinio1
 
Construction scheduling & Cost control
Construction scheduling & Cost controlConstruction scheduling & Cost control
Construction scheduling & Cost control
Guhan M
 
Primavara
PrimavaraPrimavara
Primavara
danabl
 
Primavera P6 manual
Primavera P6 manual Primavera P6 manual
Primavera P6 manual
Abbas Tahir
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
Baker Khader Abdallah, PMP
 
TILOS, Plan Linear Projects with Confidence
TILOS, Plan Linear Projects with ConfidenceTILOS, Plan Linear Projects with Confidence
TILOS, Plan Linear Projects with Confidence
M. Tuna
 
Project Time Management - PMBOK 5th Edition
Project  Time Management - PMBOK 5th EditionProject  Time Management - PMBOK 5th Edition
Project Time Management - PMBOK 5th Edition
pankajsh10
 
Primavera p6 advanced project planning
Primavera p6 advanced project planningPrimavera p6 advanced project planning
Primavera p6 advanced project planning
Amit Kumar Senapati, PMP®
 
3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project managementKabilan Kabi
 
Project Schedule Management
Project Schedule ManagementProject Schedule Management
Project Schedule Management
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Primavera training 02- Creating a new project
Primavera training  02- Creating a new projectPrimavera training  02- Creating a new project
Primavera training 02- Creating a new project
Civil Millennium Design Complex (CMDC)
 
Project Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP WorkgroupProject Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP Workgroup
Tùng Trần Thanh
 
CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptx
CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptxCONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptx
CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptx
surekha1287
 
6.3 Sequence Activities
6.3 Sequence Activities6.3 Sequence Activities
6.3 Sequence Activities
DavidMcLachlan1
 
Scheduling of a five story residential apartment project
Scheduling of a five story residential apartment project Scheduling of a five story residential apartment project
Scheduling of a five story residential apartment project
kaishwarya3
 
Project manager project-plan-template-cm
Project manager project-plan-template-cmProject manager project-plan-template-cm
Project manager project-plan-template-cm
Prasad Reddy
 

What's hot (20)

PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERSPLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
 
Chapter 3 Construction Planning and Scheduling lect. 3.ppt
Chapter 3 Construction Planning and Scheduling lect. 3.pptChapter 3 Construction Planning and Scheduling lect. 3.ppt
Chapter 3 Construction Planning and Scheduling lect. 3.ppt
 
Ms project training ver 01
Ms project training ver 01Ms project training ver 01
Ms project training ver 01
 
Project Planning Scheduling
Project Planning SchedulingProject Planning Scheduling
Project Planning Scheduling
 
PRIMAVERA P6 manual.pptx
PRIMAVERA P6 manual.pptxPRIMAVERA P6 manual.pptx
PRIMAVERA P6 manual.pptx
 
Construction scheduling & Cost control
Construction scheduling & Cost controlConstruction scheduling & Cost control
Construction scheduling & Cost control
 
Primavara
PrimavaraPrimavara
Primavara
 
Primavera P6 manual
Primavera P6 manual Primavera P6 manual
Primavera P6 manual
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
TILOS, Plan Linear Projects with Confidence
TILOS, Plan Linear Projects with ConfidenceTILOS, Plan Linear Projects with Confidence
TILOS, Plan Linear Projects with Confidence
 
Project Time Management - PMBOK 5th Edition
Project  Time Management - PMBOK 5th EditionProject  Time Management - PMBOK 5th Edition
Project Time Management - PMBOK 5th Edition
 
Primavera p6 advanced project planning
Primavera p6 advanced project planningPrimavera p6 advanced project planning
Primavera p6 advanced project planning
 
3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project management
 
Project Schedule Management
Project Schedule ManagementProject Schedule Management
Project Schedule Management
 
Primavera training 02- Creating a new project
Primavera training  02- Creating a new projectPrimavera training  02- Creating a new project
Primavera training 02- Creating a new project
 
Project Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP WorkgroupProject Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP Workgroup
 
CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptx
CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptxCONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptx
CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptx
 
6.3 Sequence Activities
6.3 Sequence Activities6.3 Sequence Activities
6.3 Sequence Activities
 
Scheduling of a five story residential apartment project
Scheduling of a five story residential apartment project Scheduling of a five story residential apartment project
Scheduling of a five story residential apartment project
 
Project manager project-plan-template-cm
Project manager project-plan-template-cmProject manager project-plan-template-cm
Project manager project-plan-template-cm
 

Similar to Project Management.pptx

project time management
 project time management project time management
project time management
Hira Atiq
 
Project-Management.pptx
Project-Management.pptxProject-Management.pptx
Project-Management.pptx
TecnicoItca
 
Presintation on Project constraint
Presintation on Project constraint Presintation on Project constraint
Presintation on Project constraint university(kust)
 
Project Implementation.pdf
Project Implementation.pdfProject Implementation.pdf
Project Implementation.pdf
ssuserc0e4e0
 
Project management
Project managementProject management
Project management
Satish Yadavalli
 
projectmanagement-130721095616-phpapp01-converted.pptx
projectmanagement-130721095616-phpapp01-converted.pptxprojectmanagement-130721095616-phpapp01-converted.pptx
projectmanagement-130721095616-phpapp01-converted.pptx
Chandrasen Sharma
 
bingsusu.pptx
bingsusu.pptxbingsusu.pptx
bingsusu.pptx
giahuy646563
 
06- PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx
06-  PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx06-  PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx
06- PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx
WajihAnsari7
 
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01
petch phanpha
 
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01
samansari22
 
Time management pressent
Time management pressentTime management pressent
Time management pressent
iklil fairuz
 
4) PTM & PCM .pptx
4) PTM & PCM .pptx4) PTM & PCM .pptx
4) PTM & PCM .pptx
MuhammadAmanAzam
 
CHAPTER 1.pptx
CHAPTER 1.pptxCHAPTER 1.pptx
CHAPTER 1.pptx
behailuzerihun1
 
CHAPTER 1.pptx
CHAPTER 1.pptxCHAPTER 1.pptx
CHAPTER 1.pptx
behailuzerihun1
 
PMP-Schedule Management area
PMP-Schedule Management areaPMP-Schedule Management area
PMP-Schedule Management area
Zaur Ahmadov, PMP
 
Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)
ShudipPal
 
schedule Management v4
 schedule Management v4 schedule Management v4
schedule Management v4
Qussay Karam
 
Episode 23 : PROJECT TIME MANAGEMENT
Episode 23 : PROJECT TIME MANAGEMENTEpisode 23 : PROJECT TIME MANAGEMENT
Episode 23 : PROJECT TIME MANAGEMENT
SAJJAD KHUDHUR ABBAS
 
Pm chapter 5...
Pm chapter 5...Pm chapter 5...
Pm chapter 5...
Golam Bitonsir
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
Golam Bitonsir
 

Similar to Project Management.pptx (20)

project time management
 project time management project time management
project time management
 
Project-Management.pptx
Project-Management.pptxProject-Management.pptx
Project-Management.pptx
 
Presintation on Project constraint
Presintation on Project constraint Presintation on Project constraint
Presintation on Project constraint
 
Project Implementation.pdf
Project Implementation.pdfProject Implementation.pdf
Project Implementation.pdf
 
Project management
Project managementProject management
Project management
 
projectmanagement-130721095616-phpapp01-converted.pptx
projectmanagement-130721095616-phpapp01-converted.pptxprojectmanagement-130721095616-phpapp01-converted.pptx
projectmanagement-130721095616-phpapp01-converted.pptx
 
bingsusu.pptx
bingsusu.pptxbingsusu.pptx
bingsusu.pptx
 
06- PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx
06-  PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx06-  PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx
06- PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx
 
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01
 
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01
 
Time management pressent
Time management pressentTime management pressent
Time management pressent
 
4) PTM & PCM .pptx
4) PTM & PCM .pptx4) PTM & PCM .pptx
4) PTM & PCM .pptx
 
CHAPTER 1.pptx
CHAPTER 1.pptxCHAPTER 1.pptx
CHAPTER 1.pptx
 
CHAPTER 1.pptx
CHAPTER 1.pptxCHAPTER 1.pptx
CHAPTER 1.pptx
 
PMP-Schedule Management area
PMP-Schedule Management areaPMP-Schedule Management area
PMP-Schedule Management area
 
Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)Software Engineering (Project Scheduling)
Software Engineering (Project Scheduling)
 
schedule Management v4
 schedule Management v4 schedule Management v4
schedule Management v4
 
Episode 23 : PROJECT TIME MANAGEMENT
Episode 23 : PROJECT TIME MANAGEMENTEpisode 23 : PROJECT TIME MANAGEMENT
Episode 23 : PROJECT TIME MANAGEMENT
 
Pm chapter 5...
Pm chapter 5...Pm chapter 5...
Pm chapter 5...
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 

Recently uploaded

Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111
zoyaansari11365
 
Attending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learnersAttending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learners
Erika906060
 
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-indiafalcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
Falcon Invoice Discounting
 
5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer
ofm712785
 
Improving profitability for small business
Improving profitability for small businessImproving profitability for small business
Improving profitability for small business
Ben Wann
 
The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...
awaisafdar
 
April 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products NewsletterApril 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products Newsletter
NathanBaughman3
 
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
BBPMedia1
 
Unveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdfUnveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdf
Sam H
 
Business Valuation Principles for Entrepreneurs
Business Valuation Principles for EntrepreneursBusiness Valuation Principles for Entrepreneurs
Business Valuation Principles for Entrepreneurs
Ben Wann
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
Cynthia Clay
 
What are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdfWhat are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdf
HumanResourceDimensi1
 
Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...
dylandmeas
 
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdfMeas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
dylandmeas
 
3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx
tanyjahb
 
The effects of customers service quality and online reviews on customer loyal...
The effects of customers service quality and online reviews on customer loyal...The effects of customers service quality and online reviews on customer loyal...
The effects of customers service quality and online reviews on customer loyal...
balatucanapplelovely
 
Sustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & EconomySustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & Economy
Operational Excellence Consulting
 
The-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic managementThe-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic management
Bojamma2
 
Skye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto AirportSkye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto Airport
marketingjdass
 
LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024
Lital Barkan
 

Recently uploaded (20)

Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111Introduction to Amazon company 111111111111
Introduction to Amazon company 111111111111
 
Attending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learnersAttending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learners
 
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-indiafalcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
 
5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer
 
Improving profitability for small business
Improving profitability for small businessImproving profitability for small business
Improving profitability for small business
 
The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...The Parable of the Pipeline a book every new businessman or business student ...
The Parable of the Pipeline a book every new businessman or business student ...
 
April 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products NewsletterApril 2024 Nostalgia Products Newsletter
April 2024 Nostalgia Products Newsletter
 
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
RMD24 | Retail media: hoe zet je dit in als je geen AH of Unilever bent? Heid...
 
Unveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdfUnveiling the Secrets How Does Generative AI Work.pdf
Unveiling the Secrets How Does Generative AI Work.pdf
 
Business Valuation Principles for Entrepreneurs
Business Valuation Principles for EntrepreneursBusiness Valuation Principles for Entrepreneurs
Business Valuation Principles for Entrepreneurs
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 
What are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdfWhat are the main advantages of using HR recruiter services.pdf
What are the main advantages of using HR recruiter services.pdf
 
Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...
 
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdfMeas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
 
3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx
 
The effects of customers service quality and online reviews on customer loyal...
The effects of customers service quality and online reviews on customer loyal...The effects of customers service quality and online reviews on customer loyal...
The effects of customers service quality and online reviews on customer loyal...
 
Sustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & EconomySustainability: Balancing the Environment, Equity & Economy
Sustainability: Balancing the Environment, Equity & Economy
 
The-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic managementThe-McKinsey-7S-Framework. strategic management
The-McKinsey-7S-Framework. strategic management
 
Skye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto AirportSkye Residences | Extended Stay Residences Near Toronto Airport
Skye Residences | Extended Stay Residences Near Toronto Airport
 
LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024LA HUG - Video Testimonials with Chynna Morgan - June 2024
LA HUG - Video Testimonials with Chynna Morgan - June 2024
 

Project Management.pptx

  • 1. PROJECT SCHEDULING & TIME MANAGEMENT LECTURE 4
  • 2. CONTENT OF PRESENTATION  WBS/ Activity Definition  Scheduling (Planning and Scheduling) o Objectives o Techniques o Critical Path Method (CPM)  Basic Definition of CPM  Activity  Activity Duration  Network Construction  Example 1 o Histogram  Resource Histogram  Constructing Resource histogram o Procedure for Resource Leveling o PERT o Example  Use of software for planning, scheduling & control of projects o Process overview o Software application o EVMS
  • 3. Work Breakdown Structure (WBS) • To be able to perform an accurate estimate of the project targets it is very pertinent to divide project into manageable sets of components or activities called as (WBS) of the project. • Patrick (2003) defines WBS as “a hierarchical system that represents the total project scope in increasing levels of detail to define, organise, and display the project work in measurable and manageable components” 3
  • 4. Work Breakdown Structure (WBS) PMI • The WBS is a hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables. Each descending level of the WBS represents an increasingly detailed definition of the project work. • The WBS is finalized by assigning each work package to a control account and establishing a unique identifier for that work package from a code of accounts. These identifiers provide a structure for hierarchical summation of costs, schedule, and resource information. 4
  • 7. Work Breakdown Structure (WBS) • The WBS consists of different levels where level one is the least detailed level often representing the entire project. The number of activities in the WBS grows quite rapidly and it is not unusual that a large construction project is broken down into several hundreds of activities. There is no specific rule about which level of detail a WBS should have but a low level of detail may result in insufficient detail for effective planning, whereas a too high level of detail may become unmanageable and increase planning costs. It is generally the case that the WBS is poorly detailed rather than too detailed. According to Jackson (2004) the level of detail should correlate with the control level desired, i.e. to have enough activities and just the right amount of detail so that the work-flow effectively can be monitored and managed. 7 A proposed WBS for an infrastructure project (multi-storey building project).
  • 8. Creating the Work Breakdown Structure (WBS) • A WBS is a deliverable-oriented grouping of the work involved in a project that defines the total scope of the project • WBS is a preliminary document that provides the basis for planning and managing project schedules, costs and resources • Decomposition is subdividing project deliverables into smaller pieces • A work package is a task at the lowest level of the WBS 8
  • 9. Sample Intranet WBS Organized by Phase 9
  • 10. Intranet WBS in Tabular Form 1.0 Concept 1.1 Evaluate current systems 1.2 Define Requirements 1.2.1 Define user requirements 1.2.2 Define content requirements 1.2.3 Define system requirements 1.2.4 Define server owner requirements 1.3 Define specific functionality 1.4 Define risks and risk management approach 1.5 Develop project plan 1.6 Brief Web development team 2.0 Web Site Design 3.0 Web Site Development 4.0 Roll Out 5.0 Support 10
  • 11. Intranet WBS and Gantt Chart in Microsoft Project 11
  • 12. Gantt Chart Organized by Project Management Deptt. 12
  • 14. Exercise: WBS Draw hierarchal WBS of a project “Establishment 1122 Emergency Response Centers” in all nine divisions and 36 districts of Punjab. The following scope of work was to be executed at each station. • Design and Construction Supervision of facility • Construction of Emergency Response Center • Procurement of all furniture, fixtures, CCTV, attendance record • Purchase and installation of one server, 20 computers and associated software & hardware including scanner and printers • Purchase and installation High quality telephone exchange • Networking of computers, connectivity, internet and intranet • Procurement of 4 Ambulances and associated medical equipment • Procurement of Firefighting vehicle, 2 cranes and other emergency response equipment • Recruitment and Training of staff
  • 16. PROJECT TIME MANAGEMENT 6.1 ACTIVITY DEFINITION 1. Inputs 1. Enterprise environmental factors . 2. Organizational process assets 3. Project scope statement 4. Work Breakdown structure 5. WBS Dictionary 6. Project management plan 2. Tools and Techniques 1. Decomposition 2. Templates 3. Rolling wave planning 4. Expert judgment 5. Planning component 3. Outputs 1. Activity list 2. Activity attributes 3. Milestone list 4. Requested changes 6.2 ACTIVITY SEQUENCING 1. Inputs .1 Project scope statement .2 Activity list .3 Activity attributes .4 Milestone List .5 Approved change requests 2 . Tools and Techniques .1 Precedence Diagramming Method (PDM) .2 Arrow Diagramming Method (ADM) .3 Schedule network templates .4 Dependency determination .5 Applying leads and lags 3. Outputs .1 Project schedule network diagrams .2 Activity list (updates) .3 Activity attributes (updates) .4 Requested changes 6.3 ACTIVITY RESOURCE ESTIMATING 1. Inputs .1 Enterprise environmental factors .2 Organizational process assets .3 Activity list .4 Activity attributes .5 Resource availability .6 Project management plan 2. Tools and Techniques .1 Expert judgment .2 Alternatives analysis .3 Published estimating data .4 Project management software .5 bottom-up-estimating 3. Outputs .1 Activity resource requirements .2 Activity attributes (updates) .3 Resource breakdown structure .4 Resource calendars (updates) .5 Requested changes Continue on next slide PMI Approach of Project Time Management (Cont..)
  • 17. PMI Approach of Project Time Management (Cont..) PROJECT TINE MANAGEMENT 6.4 ACTIVITY DURATION ESTIMATING 1. Inputs .1 Enterprise environmental factors .2 Organizational process assets .3 Project scope statement .4 Activity list .5 Activity attributes .6 Activity resource requirements .7 Resource calendars .8 Project Management plan . Risk register . Activity cost estimates 2. Tools and Techniques .1 Expert judgment .2 Analogous estimating .3 Parametric estimating .4 Three-point estimating .5 Reserve analysis 3. Outputs .1 Activity duration estimates .2 Activity attributes (updates) 6.5 SCHEDULE DEVELOPMENT 1. Inputs .1 Organizational process assets , .2 Project scope statement, .3 Activity list .4 Activity attributes, .5 Project schedule network diagrams, .6 Activity resource requirements, .7 Resource calendars .8 Activity duration estimates .9 Project management plan, 10. Risk register 2. Tools and Techniques .1 Schedule network analysis .2 Critical path method .3 Schedule compression .4 What-if scenario analysis .5 Resource leveling .6 Critical chain method .7 Project management software .8 Applying calendars .9 Adjusting leads & lags 10. Schedule model 3. Outputs .1 Project schedule .2 Schedule model data .3 Schedule baseline .4 resource requirements (Updates) .5 Activity attributes (updates) .6 Project calendars (updates) .7 Requested changes 6.6 SCHEDULE CONTROL 1. Inputs .1 Schedule management plan .2 Schedule baseline .3 Performance report .4 Approved change request 2. Tools and Techniques .1 Progress reporting .2 Schedule change control system .3 Performance measurement .4 Project management software .5 Variance analysis .6 Schedule comparison bar charts 3. Outputs .1 Schedule model data (updates) .2 Schedule baseline (updates) .3 Performance measurements .4 Requested changes .5 Recommended corrective actions .6 Organizational process assets (updates) .7 Activity list (updates) .8 Activity attributes (updates) .9 Project management plan (updates) Continu e on Previou s slide
  • 18. PROJECT SCHEDULING • Project Planning: Process of identifying all the activities necessary to successfully complete the project is called project planning. • Project Scheduling: Process of determining sequential order of planned activities, assigning realistic duration, to each activity and determining start and finish dates of each activity is called project scheduling. Project planning is prerequisite to project scheduling because there is no way to determine the sequential order of activities until they are identified. However, the terms planning and scheduling are often used synonymously because they are performed interactively. E.g. when some schedule is reviewed, it may be decided that additional activities may be added or rearranged in order to get the best schedule of events of projects.
  • 19.
  • 20. OBJECTIVES OF PROJECT SCHEDULING  Finish project on time.  Finish project within cost.  Continuous (uninterrupted) flow of work.  Reduced amount of rework.  Minimize confusion and misunderstanding.  Increased knowledge of status of project to every one (including management).  Knowledge of distribution of costs of project.  Accountability of people / defined responsibility and clear understanding of who does what, when and how much.  Optimum use of resources.
  • 21. TECHNIQUES FOR SCHEDULING Techniques used for scheduling depends upon the type, size, complexity, duration, personal and owner requirement. It is preferred to use a simpler technique which is simple to use and easily interpreted by all project participants. There are two general techniques which commonly used for planning and scheduling.  Bar Chart (Gantt Chart): It is the graphical representation of Time (X-axis) and Activities on Y- axis, so that the status of project may be visualized and controlled.  Net work analysis system (CPM and PERT): It is the schematic representation of various activities. This method calculates the minimum completion time for a project along with start and finish time of project activities.  Software application: (MS Project, Primavera, Pertmaster, Risky Project.
  • 22. BAR CHART  Bar Chart was developed by Henery L. Gantt in 1917, which is the most common planning tool even today, which provided basis for developing planning and scheduling software.  Bar Charts are the easiest and most widely used form of scheduling in project management. Even with other scheduling techniques, the eventual schedule is presented the form of a bar chart. The level of detail of the activities depends on the intended use of the schedule. The most commonly used bar chart for engineering works is called Gantt chart.  A Gantt chart is a type of bar chart that illustrates a project schedule, start and finish dates of the terminal elements and summary elements of civil engineering project. Terminal elements and summary elements comprise the work breakdown structure of the project. Some Gantt charts also show the dependency (i.e. precedence network) relationships between activities. Gantt charts can be used to show current schedule status using percent- complete shadings.  Gantt charts have become a common technique for representing the phases and activities of a project work breakdown (WBS), so they can be understood by a wide audience all over the world.
  • 23.
  • 24. CRITICAL PATH METHOD (CPM) The Critical Path Method is a method where activities are arranged based on interrelationship. It is a planning and control technique that provides an accurate, timely and easily understood picture of the project. Its purpose is to allows effective scheduling and controlling. One of the most important features of CPM is the logic diagram. The logic diagram graphically portrays the relationship between project activities.  Critical path in a network is a longest path in terms of time unit, which gives minimum overall duration to complete the project.  CPM calls attention which activities must be completed before other activities can begun. A B D F G E C H
  • 25. ACTIVITY A common technique used to understand and organize complex undertaking is to break the project into smaller pieces. This technique is used both planning and estimating. Each activity is a discrete task. Activities should be only be specified as per level of management. The number and detail of listed quality will vary from job to job and depend on the intended level of control. Usually for planning purposes activity doesn’t exceed from 25 days, if exceeds may be divided into further components. The activities must have four characteristics. 1. Time consumption: An activity must consume time. 2. Use of resources: An activity usually consumes Labour, Material or Equipment resources. 3. Definite Start and Finish time: An activity represents a definite scope of work i.e. Starting and Ending point in time. 4. Activities are measurable. The progress towards completion of activity’s scope of work must be measureable.
  • 26. ACTIVITY DURATION • One of the most important steps in planning a project is estimating the time required to complete each activity. The duration of each activity is a function of quantity of work and work production rate. Work production rates are based on planned composition of labor and equipment used to perform the task. Careless estimates of production rates may cause un economical use of personnel, materials, equipment and time. • When the project bid estimate is prepared, the estimator calculates the quantity of material that must be put in place and assumes a production rate to get the cost of each work, which is based construction method and technique. The bid preparation information can be served as the tool for calculating g an activity duration. • All Activities in a schedule should have same unit of time, which may be in months, weeks, days and hours.
  • 27. ESTIMATION: EXAMPLE-1 (a) a) In estimating a five storey office building, it was determined that 480 light fixtures would be installed on each floor. The production rate of Five fixtures per man hour may be used for installation. The company has five electrician. The normal working day will be 8 hours. What will be the duration (in days) to install all lights in the building. b) If the cost of one fixture is 1500 PKR and electrician takes around 1500 PKR per 8 hour working day. Then, considered 5% breakage of fixtures during installation, find the budget of the activity. SOLUTION: Production Rate: 5 fixture x 5 electrician = 25 fixtures per man hour 1-man hour Activity Duration = 480 fixture x 5 floors = 96 hours 25 Activity Duration = 96 hours = 12 day 8 hours
  • 28. ESTIMATION: EXAMPLE-1 (b) The following items of works were to be conducted in a project; 1. Excavation of 4768 cubic meter 2. Driving of RCC Piles (48 Nos.) Dia 2ft. 200 ft deep. Find Duration and Budget of Project. Assume missing data. SOLUTION:
  • 29. IMPORTANCE OF ACCURATE ESTIMATES 29  Inaccurate time estimates can result in unrealistic schedule  Inaccurate time estimates can result in inefficient use of resources and late delivery.  Inaccurate cost estimates can result in insufficient budget being allocated, or excess budget being set aside for the project when it could be used for other projects.  If the cost or benefits estimates are inaccurate this can lead to incorrect decisions about proceeding with the project being made.
  • 30. BASIC DEFINITIONS OF CPM TERMS • Activity:- The performance of a task required to complete the project e.g. foundation design, contract document, RCC form work, pouring of concrete. • Network:- A diagram to represents the relationship of activities to complete the project. • Duration:- The estimated time required to perform an activity. • Early Start (ES):- The earliest time an activity can be start. • Early Finish (EF):- The earliest time an activity can be finished. • Late Finish (LF):- The latest time an activity can be finished. • Late Start (LS):- The latest time an activity can be started without delaying the completion of project. (LS = LF – D) • Total Float (TF):- The amount of time an activity may be delayed without delaying the completion date of project. Mathematically, TF = LF – EF = LS – ES. • Critical Activity:- If total float for an activity is zero, activity is called critical activity. • Critical path is a longest path in terms of time unit in a network, which gives minimum overall duration to complete the project.
  • 31. NETWORK CONSTRUCTION The performance of a task required to complete the project. Activity must have a specific duration except the dummy activity, having zero duration. Each activity is represented as can arrow or node. Arrows are not drawn according to scale. The brief description about activity is written over arrow or node. Duration (hours, week, months) to complete that activity is written under the arrow, where 1 and 2 are the event. Which are written inside the circles or boxes. The starting event is masked at the tail and finish event at the head of the arrow. Rules: 1. Each activity should be represented by a separate arrow. 2. The arrow may be straight or inclined lines. 3. Dummy activity should be represented with dotted lines. 4. Critical path must be shown clearly with double line. 5. Intersection of activity is not allowed. 6. Boxes are provided for event times (ES, EF, LS, LF) 7. EST is some reference time, normally EST = 0 at the start of the project / work. EFT = EST + Duration. 8. Each activity is followed by a predecessor and successor except start and finish activities. Any starting activity must have predecessor none, or finish activity must have no successor.
  • 32.
  • 33. EXAMPLE 2. CPM Activity Duration (days) Preceding Activity (Predecessor) A 3 None B 5 A C 8 A D 10 B E 5 B F 7 C G 12 D H 8 E, F I 3 G,H 1. Construct AOA network 2. Find ES, EF, LS and LF of all activities 3. Find total float of all activities (days) 4. Find the project duration (days) 5. Mark critical path on the network
  • 35. EXAMPLE-4. CPM Activity Duration Predecessor Resource Early Start (ES) Early Finish (EF) Late Start (LS) Late Finish (LF) Total Float (TF) Remark O 8 None 10 N 3 O 2 M 13 N 5 L 7 O 15 K 12 O 8 J 3 K 4 I 10 L 3 H 8 L 10 G 6 H,M 8 F 20 I 4 E 16 I 6 D 8 J 4 C 4 G, E 20 B 5 F 6 A 3 B, C,D 3 1. Construct AOA network 2. Find ES, EF, LS and LF of all activities 4. Find the project duration (days) 5. Mark critical path on the network Find total float of all activities (days)
  • 36. EXAMPLE 5. CPM Activity Duration Predecessor Resource ES EF LS LF (TF) Remark Q 8 None 5 P 10 Q 6 O 7 Q 10 N 6 O 2 M 9 Q 5 L 5 M 15 K 4 O 8 J 7 L, K 4 I 9 L, K 3 H 20 P 10 G 12 H 8 F 9 N 4 E 20 N 6 D 11 I 4 C 7 E, J 20 B 7 G, F 6 A 3 B, C,D 3 1. Construct AON network 2. Find ES, EF, LS and LF of all activities Find total float of all activities (days) 4. Find the project duration (days) 5. Mark critical path on the network
  • 37. EXAMPLE-6: CRITICAL PATH Solution: Critical Path = Q – P – H – G – B – A, Project Duration = 60 days 2nd Path = Q – O – N – F – B – A, Duration = 40 days 3rd Path = Q – O – N – E – C – A, Duration = 51days 4th Path = Q – O – K – J – C – A, Duration = 36 days 5th Path = Q – O – K – I – D – A, Duration = 42 days 6th Path = Q – M – L – J – C – A, Duration = 39 days 7th Path = Q – O – K – I – D – A, Duration = 45 days
  • 39. RESOURCE HISTOGRAM  It is a graphical representation of time on X- axis and resources on Y-axis.  It is a view of project data in which resource requirements, usage, and availabilities are shown against a time scale. The personnel, equipment, materials, and services needed to complete tasks in a project are resources.
  • 40. TYPES OF RESOURCE HISTOGRAM 1. Labor Resource Histogram 2. Material Resource Histogram 3. Equipment Resource Histogram 4. Cost Histogram In these resource histograms time is taken on x axis and the resource is taken on y axis. For a construction project total resources are mentioned according to that particular time these histograms also help us to calculate cost for a particular resource of a project at a particular time because resource can be converted in terms of cost.
  • 41. PROCEDURE FOR RESOURCE LEVELING 1. Plan and Schedule project activities. 2. Construct a Network for the project. 3. Mark Critical Path (CP). 4. Construct the Bar Chart for the Project. 5. For each working day show resources of each activity at their respective duration on Bar Chart. 6. Sum up the total resources vertically for each working day. 7. Plot the histogram for the resource. 8. Mark the sudden drop or rise in resource histogram. 9. Utilize the total float available for non critical activity to level the resources by hit & trial method. 10. Recheck the leveled histogram and prepare a new schedule of work / execution.
  • 42. Activity Duration Pred. Labour (Per Day) Total Cost of Activity ES EF LS LF Float A 6 None 4 PKR60,000 0 6 0 6 0 B 20 A 8 PKR400,000 6 26 15 35 9 C 5 A 12 PKR100,000 6 11 6 11 0 D 8 A 4 PKR240,000 6 14 17 25 11 E 10 D 10 PKR300,000 14 24 25 35 11 F 14 C 10 PKR280,000 11 35 11 35 0 G 8 C 3 PKR320,000 11 19 45 53 34 H 12 C 20 PKR360,000 11 23 31 43 20 I 6 B, F 9 PKR180,000 14 20 37 43 23 J 10 E, H 6 PKR400,000 23 33 43 53 20 K 18 G, I, J 4 PKR180,000 35 53 35 53 0 PKR 2,820,000 EXAMPLE-7: CONSTRUCTING COST & LABOR HISTOGRAM
  • 43. EXAMPLE-7: CONSTRUCTING COST & LABOR HISTOGRAM
  • 46. EXAMPLE-8: CONSTRUCT S-CURVE FOR EXAMPLE NO. 7
  • 48.
  • 49.
  • 50.
  • 51.
  • 52. EARNED VALUE MANAGEMENT SYSTEM (EVMS) 52 • EVM is a project performance measurement technique that integrates scope, time, and cost data. • Given a baseline (original plan plus approved changes), you can determine how well the project is meeting its goals. • You must enter actual information periodically to use EVM. • More and more organizations around the world are using EVM to help control project costs.
  • 53. EARNED VALUE MANAGEMENT SYSTEM (EVMS) • It’s a Management Tool – Used for project status: (1) previous work accomplished and (2) where the project was planned to be. – Early warning system to detect deficient or endangered progress.
  • 54. EARNED VALUE MANAGEMENT SYSTEM (EVMS) Why Use EVMS? • Ensures a clear definition of work prior to beginning that work • Presents a logical plan for accomplishing the work • Provides an objective measure of accomplishments • Early and accurate identification of trends and problems • Accurate picture of contract status – cost, schedule, and scope • Basis for course correction • Supports mutual goals of contractor and customer – bring project in on schedule and cost
  • 55. Earned Value Management System (EVMS) • Budgeted cost for work scheduled • Amount /level of effort or apportioned effort scheduled to be accomplished in a given time period Planned Value (PV) BCWS • Budgeted cost for work performed • Budgeted for level of effort or apportioned effort activity completed within a given time period • Sometimes referred to as “earned value.” Earned Value (EV) BCWP • Actual cost for work performed • Amount reported as actually expended in completing the work accomplished within a given time period Actual Cost (AC) ACWP Core Concept of Terms
  • 57.
  • 58. Cost variance (CV): CV = BCWP – ACWP = EV – AC A negative variance indicates a cost-overrun condition. Schedule variance (SV): SV = BCWP – BCWS = EV – PV A negative variance indicates a behind-schedule condition. Cost performance index (CPI) = Schedule performance index (SPI) = If CPI = 1.0, we have perfect performance, If CPI > 1.0, project is under budgeted. If CPI < 1.0, project is over budgeted. If SPI = 1.0, we have perfect performance, If SPI > 1.0, project is ahead of schedule. If SPI < 1.0, project is behind Schedule. The cost and schedule performance index is most often used for trend analysis as shown the figure. Three-month, four-mouth, or six-month may be used to predict trends. Trend analysis provides an early warning system and allows managers to take corrective action. Variance and Index Earned Value Management System (EVMS)
  • 59. Variance and Index Earned Value Management System (EVMS) Critical Ratio (CR): This indicator combines both the cost performance index (CPI) and schedule performance index (SPI) to represent the project status Critical Ratio (CR) = SPI x CPI Project Status (PS): This indicator is the average of both the cost performance index (CPI) and schedule performance index (SPI) to represent the project status Project Status (PS) = (SPI + CPI)/2 Schedule Variance in Time (SV.t) Variance in Schedule at a particular time on project timeline. Schedule Variance in time (duration) = (SV x T) / BAC Earned Schedule (ES) The measure of work performed in terms of schedule as on status date Earned Schedule (ES) = T - SV(t)
  • 60. TIME COST SCHEDULE ANALYSIS BAC Data Date AC EV PV Progress at end of 3rd Month: Project Budget (BAC): 37.22 lakhs Funds Used (AC): 16.40 lakhs Utilization = 44.1 % Additional EV Parameters: Planned (PV): 19.82 lakhs Earned (EV): 14.50 lakhs Schedule Performance Planned (PV): 19.82 lakhs Earned (EV): 14.50 lakhs Schedule Variance = EV-PV = -5.32 Schedule Performance Index = EV/PV = 0.73 SV
  • 61. TIME COST Cost Analysis BAC Data Date AC EV PV Progress at end of 3rd Month: Project Budget (BAC): 37.22 lakhs Funds Used (AC): 16.40 lakhs Utilization = 44.1 % Additional EV Parameters: Planned (PV): 19.82 lakhs Earned (EV): 14.50 lakhs Cost Performance Actual Cost (AC): 16.40 lakhs Earned (EV): 14.50 lakhs Cost Variance = EV-AC = -1.90 Cost Performance Index = EV/AC = 0.88 CV
  • 62. TIME COST ESTIMATE AT COMPLETIONBAC Data Date AC EV PV Progress at end of 3rd Month: Project Budget (BAC): 37.22 lakhs Funds Used (AC): 16.40 lakhs Utilization = 44.1 % Additional EV Parameters: Planned (PV): 19.82 lakhs Earned (EV): 14.50 lakhs Estimate at Completion Actual Cost (AC): 16.40 lakhs Earned (EV): 14.50 lakhs EAC = BAC/CPI = 42.3 Variance at Completion = BAC-EAC = -5.07
  • 63. PROJECT STATUS AT MONTH 3 Progress at end of 3rd Month: Project Budget (BAC): 37.22 lakhs Funds Used (AC): 16.40 lakhs Utilization = 44.1 % Additional EV Parameters: Planned (PV): 19.82 lakhs Earned (EV): 14.50 lakhs Sheet 1 of 1 Ac ti vi ty I D Ac ti vi ty De s cri p ti o n Ori g Du r Bu d ge t (BAC) P l a nn e d (BCW S ) E a rne d (BCW P ) Ac tua l (ACW P ) R ural H ealth C linic T o t a l 2 1 0 3 , 7 2 2 , 0 0 0 . 0 0 1 , 9 8 2 , 8 0 0 . 0 0 1 , 4 5 0 , 0 0 0 . 0 0 1 , 6 4 0 , 0 0 0 . 0 0 G ener al S u b to t a l 2 1 0 0 . 0 0 0 . 0 0 0 . 0 0 0 . 0 0 1 0 0 0 P r o j e c t S t a rt 0 0 . 0 0 0 . 0 0 0 . 0 0 0 . 0 0 1 1 1 0 P r o j e c t C o m p l e t e 0 0 . 0 0 0 . 0 0 0 . 0 0 0 . 0 0 Foundation S u b to t a l 5 4 8 5 0 ,0 0 0 . 0 0 8 5 0 ,0 0 0 . 0 0 8 5 0 ,0 0 0 . 0 0 9 5 0 ,0 0 0 . 0 0 1 0 1 0 E a r t h w o r k s 1 8 5 0 , 0 0 0 . 0 0 5 0 , 0 0 0 . 0 0 5 0 , 0 0 0 . 0 0 6 0 , 0 0 0 . 0 0 1 0 2 0 F o u n d a t i o n u p t o P li n t h 2 4 8 0 0 ,0 0 0 . 0 0 8 0 0 ,0 0 0 . 0 0 8 0 0 ,0 0 0 . 0 0 8 9 0 ,0 0 0 . 0 0 S tr uctur e W or k S u b to t a l 5 1 1 , 5 3 6 , 0 0 0 . 0 0 1 , 1 3 2 , 8 0 0 . 0 0 6 0 0 ,0 0 0 . 0 0 6 9 0 ,0 0 0 . 0 0 1 0 3 0 S u p e r - s t r u c t u r e 5 0 1 , 4 4 0 , 0 0 0 . 0 0 1 , 0 3 6 , 8 0 0 . 0 0 5 0 4 ,0 0 0 . 0 0 5 8 4 ,0 0 0 . 0 0 1 0 4 0 B l o c k M a s o n r y 1 5 9 6 , 0 0 0 . 0 0 9 6 , 0 0 0 . 0 0 9 6 , 0 0 0 . 0 0 1 0 6 ,0 0 0 . 0 0 Finishes S u b to t a l 1 0 5 1 , 3 3 6 , 0 0 0 . 0 0 0 . 0 0 0 . 0 0 0 . 0 0 1 0 5 0 P l a s t e r 4 0 1 9 2 ,0 0 0 . 0 0 0 . 0 0 0 . 0 0 0 . 0 0 1 1 0 0 P l u m b i n g 1 5 1 0 0 ,0 0 0 . 0 0 0 . 0 0 0 . 0 0 0 . 0 0 1 0 9 0 E l e c t r i c a l W o r k s 2 5 2 0 0 ,0 0 0 . 0 0 0 . 0 0 0 . 0 0 0 . 0 0 1 0 7 0 F l o o r i n g 4 5 3 0 0 ,0 0 0 . 0 0 0 . 0 0 0 . 0 0 0 . 0 0 1 0 6 0 P a i n t 4 0 1 4 4 ,0 0 0 . 0 0 0 . 0 0 0 . 0 0 0 . 0 0 1 0 8 0 W o o d W o r k 2 0 4 0 0 ,0 0 0 . 0 0 0 . 0 0 0 . 0 0 0 . 0 0 M o nth s 1 2 3 4 5 6 7 8 9 1 0 P ro j ec t S ta rt P ro j ec t Co m p l e te E a rthwo rk s F o u nd a ti o n u p to P li n th S u p er-s tru ctu re Bl o ck M a s on ry P l a ste r P l u m b i n g E l e ctri c a l W o rk s F l o ori n g P a i nt W o od W o rk R e s o u rc e / Co s t P ro fi l e L e g e n d P l a n n e d v a l u e c u rv e E a rn e d v a l u e c u rv e C u rre n t e s t im a t e c u rv e T o t a l e a rl y c o s t p e r M o n t h ( C u rre n t E s t i m a t e ) T o t a l o f A l l R e s o u rc e s D e t a i l s c a l e ( l e f t ) : X 1 0 0 0 0 0 C u m u l a t i v e s c a l e (ri g h t ) : X 1 0 0 0 0 0 1 2 3 4 5 6 7 8 9 1 0 M o nth s 1 2 3 4 5 6 7 8 9 1 0 4 8 1 2 1 6 2 0 2 4 2 8 3 2 3 6 4 0 x 1 0 0 0 0 0 x 1 0 0 0 0 0 Sheet 1 of 1 PV EV AC EAC BAC
  • 66. PROGRAMME EVALUATION AND REVIEW TECHNIQUE (PERT)  PERT is an inherent planning technique forces the manager to develop a comprehensive plan and allows realistic scheduling. The procedure for monitoring, forecasting and simulating allows the manager to respond quickly to unexpected changes in the project, detect trouble areas early and evaluate proposed alternative courses of action. PERT also helps to evaluate alternatives at any time during projects duration by looking effect of each change on its completion date. PERT also helps to simulate the project time & cost and effects of alternate decisions.  It is a planning & Control techniques that precuts statistical information regarding the uncertainties associated with completing the different activities associated to a project. Expected Value of activity direction
  • 67. DIFFERENCE BETWEEN PERT AND CPM CPM PERT CPM uses one time estimate that represents the normal time. PERT uses three time estimates (optimistic, most likely, and pessimistic) to derive an expected time. CPM is deterministic in nature. PERT is probabilistic in nature, CPM is used for those projects where percent complete can be determined with reasonable accuracy such as construction. PERT is used for R&D, where percent complete is almost impossible to determine except a completed milestones. CPM is activity oriented and can be used as an arrow diagram network. PERT is event oriented rather than activity oriented and can be used as an arrow diagram network. CPM as a controlling device for the simple reason that one must repeat the entire evaluation of the project each time the changes are introduced into the network PERT serves a useful control device as it assist the management in controlling a project by calling attention through constant review to such delays in activities which might lead to a delay in the project completion date. Cannot be used for risk analysis and management Can be used for risk analysis and management CPM Gives Critical Path PERT gives probability in % to achieve critical path May be used successfully for projects without uncertainties and risks May be used successfully for projects with uncertainties and risks
  • 68. a) Draw net work for PERT b) Find Expected Time “te” for all activities and “TE “ c) Find Variance “σ2” for all activities d) Find “Z” value, when Ts= 40 days e) Find the probability to complete the project in 40 days f) Find the scheduled duration (Ts) for project completion with 80% probability EXAMPLE-6: PERT Activity Duration Pred. Expected Time Variance O M P te σ2 A 4 8 15 Nil B 8 10 20 Nil C 11 12 15 Nil D 13 15 20 C E 2 3 4 B F 2 3 5 A G 3 4 8 A H 1 2 3 G I 5 8 12 D,E,F J 3 5 7 H,I
  • 69. EXAMPLE-7: PERT Activity Duration Pre d. Expect ed Time Varianc e O M P te σ2 A 8 10 15 Nil B 8 10 12 A C 11 12 13 B D 18 20 26 B E 1 2 4 B F 1 2 5 C G 3 4 7 E H 1 2 3 F I 10 15 21 D J 3 5 7 G K 32 40 56 H,I, J L 4 8 13 K (i)Draw net work for PERT (ii)Find Expected Time “te” for all activities (iii)Find Variance “σ2” for all activities (iv)Find “Z” value, when Ts= 103 (v)What is the probability that project will finish in 104 days? (vi)What is the probability that activity “K” will start on 55th day of project execution? Calculations:
  • 70. SOLUTION Activity Duration Pred Expecte d Time Variance O M P te σ2 A 8 10 15 Nil B 8 10 12 A C 11 12 13 B D 18 20 26 B E 1 2 4 B F 1 2 5 C G 3 4 7 E H 1 2 3 F I 10 15 21 D J 3 5 7 G K 32 40 56 H,I,J L 4 8 13 K = 10.5 days = = = 1.36
  • 71.
  • 74. PLANNING, SCHEDULING AND CONTROL • MS Project • Primavera (P3, P6) • Risky Project • Pertmaster • Cloud based Software application