This slide show complements the Learner Guide NCV 4 Project Management Hands-On Training by Bert Eksteen, published by Future Managers. For more information visit our website www.futuremanagers.net
In this chapter, you will learn how to:
✔ Use the Backstage view to open and save Project files.
✔ Work with commands on different tabs of the ribbon interface, the major visual
change introduced in Project 2010.
✔ Use different views to see Project information presented in different ways.
In this chapter, you will learn how to:
✔ Use the Backstage view to open and save Project files.
✔ Work with commands on different tabs of the ribbon interface, the major visual
change introduced in Project 2010.
✔ Use different views to see Project information presented in different ways.
- Project time management start with planning by the project management team (not shown as a discrete process)
- Project Time Management provides a basis to activity definition, sequencing them in an order, Estimate Resource and Duration, Develop and control schedule.
Initiation Planning Execution Monitoring and Controlling Closing
Project Management Techniques ( CPM & PERT Techniques )
A revised PPT from other shared PPT available
Project management is a scientific way of planning, implementing, monitoring & controlling the various aspects of a project such as time, money, materials, manpower & other resources.
By,
Mr. AKARESH JOSE
Kerala Agricultural University
akareshjose@gmail.com
Control account, work and planning package - PMP/CAPM from PMIMudassir Iqbal
https://www.mudassiriqbal.net/project-management-terms-and-concepts
There are many concepts and definitions which require special attention by all PMP Aspirants as the terminologies are largely used interchangeably in the real world.
- Project time management start with planning by the project management team (not shown as a discrete process)
- Project Time Management provides a basis to activity definition, sequencing them in an order, Estimate Resource and Duration, Develop and control schedule.
Initiation Planning Execution Monitoring and Controlling Closing
Project Management Techniques ( CPM & PERT Techniques )
A revised PPT from other shared PPT available
Project management is a scientific way of planning, implementing, monitoring & controlling the various aspects of a project such as time, money, materials, manpower & other resources.
By,
Mr. AKARESH JOSE
Kerala Agricultural University
akareshjose@gmail.com
Control account, work and planning package - PMP/CAPM from PMIMudassir Iqbal
https://www.mudassiriqbal.net/project-management-terms-and-concepts
There are many concepts and definitions which require special attention by all PMP Aspirants as the terminologies are largely used interchangeably in the real world.
Project TimeIST4055Chapter 6Now that you have the Sc.docxbriancrawford30935
Project Time
IST4055
Chapter 6
Now that you have the Scope and Work Breakdown Structures done, we address the other 2 aspects of the triple constraint – time and money.
Focus here is looking at the entire project, sequence the steps, and then cost them.
1
Importance of Project Schedules
Managers often cite delivering projects on time as one of their biggest challenges
Average time overrun from 1995 CHAOS report was 222%; improved to 84% in 2004 study; 74% in 2012 study; down to 51% in 2016
Time is the most precarious element of the triple constraint:
Time has the least amount of flexibility; it passes no matter what!
Scope and cost can be adjusted; time goes on regardless of what you do or don’t do.
Traditionally IT project managers have underestimated the amount of time needed to complete the tasks – they are overly confident in their abilities to get the job done and sometimes are too simplistic in their approach. You must be realistic in the time constraint. Note also that it might take you 10 hours, but you also may be working on other projects or doing daily operations too…..so time is how long and over what period of time – 10 hours spread over 60 hours.
Schedule issues are the main reason for conflicts on projects, especially during the second half of projects. So where are we now with time overruns?
2
Attitudes toward deadlines
Cultures have different attitudes about time
Individual Work Styles and Cultural Differences Cause Schedule Conflicts
3
One dimension Meyers-Briggs Type Indicator focuses on peoples’ attitudes toward structure and deadlines
Some people prefer schedules and deadlines while others do not
Difference cultures and countries have different attitudes about schedules/time
3
Time Robbers
Task rework
Calls, texts, e-mail
Land mail
Incomplete work
Lack of needed authority
Inefficient change procedures
Waiting on people
Day-to-day administration
Too many levels of review
Casual office conversations
Poorly run meetings
Micromanagement
Those activities that at first seem to be short and unobtrusive but when they are all added together can completely fill an entire work day
It is important to realize that some time increments can lead to major time wasters. This slide covers some time robbers that occur in your everyday work life.
In addition to the ones listed on the slide you can add
Poorly motivated or educated customers
Vague goals and objectives
Poor time management
Ill defined project scope
Company politics
Working on under-funded projects
4
Project Time Management
Activity Definition
Activity Sequencing
Project Time Management describes the processes and methods required to create and manage appropriate schedules to complete the project:
Activity Definition – identifies the lowest level of work on the WBS, “work packages”, that needs to be performed to create the finished product deliverable; An activity or task is an element of work normally found on the work breakdown structure (WBS) tha.
POM 3 JUNE 2022 PROJECT MANAGEMENT QUESTION.pdfAlison Tutors
This document has questions on Project management asked in the paper 3 June 2022
The paper tested on the following concepts :
-steps involved in creating a feasibility study
-definition of project manager and project management
-responsibilities of a project manager
-project management methodology
-Work Breakdown Structure
-Net Present Value
Identifying Requirements, Creating the Work Breakdown structure, Developing the Project Schedule, Developing a Project Cost Estimate, Planning Quality, Organizing the Project Team, Planning for Potential Risks
NCV 4 Project Management Hands-On Support Slide Show - Module 2Future Managers
This slide show complements the Learner Guide NCV 4 Project Management Hands-On Training by Bert Eksteen, published by Future Managers. For more information visit our website www.futuremanagers.net
Do you know why numbers look like they do? Someone, at some point in time, had to create their shapes and meaning.
Watch this short presentation and then you will know how our Arabic numbers were originally created a very long time ago and what logic the people that created them used to determine their shapes. It is really very simple and quite creative.
You have to admire the intelligence of a person or people that created something so simple and perfect that it has lasted thousands and thousands of years and will probably never change.
When the presentation gets to the number "seven" you will notice that the7 has a line through the middle of it. That was the way the Arabic 7 was originally written, and in Europe and certain other areas they still write the 7 that way. Also, in the military, they commonly write it that way. The nine has a kind of curly tail on it that has been reduced, for the most part nowadays, to a simple curve, but the logic involved still applies.
N4 Communication & Management Communication - Module 1 case studyFuture Managers
This PowerPoint presentation accompanies N4 Communication & Management Communication published by Future Managers Pty Ltd. Its content relates to page 23 of the above named book.
NCV 4 Personal Assistance Hands-On Support - Module 4Future Managers
This slide show accompanies the textbook NCV 4 Personal Assistance Hands-On Training - Module 4 published by Future Managers Pty Ltd. It is intended to be used for support material for lecturers teaching this subject. This module deals with liaising with a range of customers in a business.
NCV 4 Personal Assistance Hands-On Support - Module 3Future Managers
This slide show accompanies the textbook NCV 4 Personal Assistance Hands-On Training - Module 3 published by Future Managers Pty Ltd. It is intended to be used for support material for lecturers teaching this subject. This module deals with customer complaints.
NCV 4 Personal Assistance Hands-On Support - Module 7Future Managers
This slide show accompanies the textbook NCV 4 Personal Assistance Hands-On Training - Module 7 published by Future Managers Pty Ltd. It is intended to be used for support material for lecturers teaching this subject. This module deals with identifying expertise and resources.
NCV 4 Personal Assistance Hands-On Support - Module 1Future Managers
This slide show accompanies the textbook NCV 4 Personal Assistance Hands-On Training - Module 1 published by Future Managers Pty Ltd. It is intended to be used for support material for lecturers teaching this subject. This module deals with planning and conducting meetings.
NCV 4 Personal Assistance Hands-On Support - Module 2Future Managers
This slide show accompanies the textbook NCV 4 Personal Assistance Hands-On Training - Module 2 published by Future Managers Pty Ltd. It is intended to be used for support material for lecturers teaching this subject. This module deals with applying basic business principles.
NCV 4 Personal Assistance Hands-On Support - Module 6Future Managers
This slide show accompanies the textbook NCV 4 Personal Assistance Hands-On Training - Module 6 published by Future Managers Pty Ltd. It is intended to be used for support material for lecturers teaching this subject. This module deals with improving single factor productivity.
Mechanical Technology Grade 10 Chapter 10 Systems And ControlFuture Managers
This slide show accompanies the learner guide "Mechanical Technology Grade 10" by Charles Goodwin, Andre Lategan & Daniel Meyer, published by Future Managers Pty Ltd. For more information visit our website www.futuremanagers.net
This slide show accompanies the learner guide "Mechanical Technology Grade 10" by Charles Goodwin, Andre Lategan & Daniel Meyer, published by Future Managers Pty Ltd. For more information visit our website www.futuremanagers.net
This slide show accompanies the learner guide "Mechanical Technology Grade 10" by Charles Goodwin, Andre Lategan & Daniel Meyer, published by Future Managers Pty Ltd. For more information visit our website www.futuremanagers.net
Mechanical Technology Grade 12 Chapter 6 Terminology Of MachinesFuture Managers
This slide show accompanies the learner guide "Mechanical Technology Grade 10" by Charles Goodwin, Andre Lategan & Daniel Meyer, published by Future Managers Pty Ltd. For more information visit our website www.futuremanagers.net
This slide show accompanies the learner guide "Mechanical Technology Grade 10" by Charles Goodwin, Andre Lategan & Daniel Meyer, published by Future Managers Pty Ltd. For more information visit our website www.futuremanagers.net
2024.06.01 Introducing a competency framework for languag learning materials ...Sandy Millin
http://sandymillin.wordpress.com/iateflwebinar2024
Published classroom materials form the basis of syllabuses, drive teacher professional development, and have a potentially huge influence on learners, teachers and education systems. All teachers also create their own materials, whether a few sentences on a blackboard, a highly-structured fully-realised online course, or anything in between. Despite this, the knowledge and skills needed to create effective language learning materials are rarely part of teacher training, and are mostly learnt by trial and error.
Knowledge and skills frameworks, generally called competency frameworks, for ELT teachers, trainers and managers have existed for a few years now. However, until I created one for my MA dissertation, there wasn’t one drawing together what we need to know and do to be able to effectively produce language learning materials.
This webinar will introduce you to my framework, highlighting the key competencies I identified from my research. It will also show how anybody involved in language teaching (any language, not just English!), teacher training, managing schools or developing language learning materials can benefit from using the framework.
How to Create Map Views in the Odoo 17 ERPCeline George
The map views are useful for providing a geographical representation of data. They allow users to visualize and analyze the data in a more intuitive manner.
Ethnobotany and Ethnopharmacology:
Ethnobotany in herbal drug evaluation,
Impact of Ethnobotany in traditional medicine,
New development in herbals,
Bio-prospecting tools for drug discovery,
Role of Ethnopharmacology in drug evaluation,
Reverse Pharmacology.
Operation “Blue Star” is the only event in the history of Independent India where the state went into war with its own people. Even after about 40 years it is not clear if it was culmination of states anger over people of the region, a political game of power or start of dictatorial chapter in the democratic setup.
The people of Punjab felt alienated from main stream due to denial of their just demands during a long democratic struggle since independence. As it happen all over the word, it led to militant struggle with great loss of lives of military, police and civilian personnel. Killing of Indira Gandhi and massacre of innocent Sikhs in Delhi and other India cities was also associated with this movement.
Palestine last event orientationfvgnh .pptxRaedMohamed3
An EFL lesson about the current events in Palestine. It is intended to be for intermediate students who wish to increase their listening skills through a short lesson in power point.
Unit 8 - Information and Communication Technology (Paper I).pdfThiyagu K
This slides describes the basic concepts of ICT, basics of Email, Emerging Technology and Digital Initiatives in Education. This presentations aligns with the UGC Paper I syllabus.
The Roman Empire A Historical Colossus.pdfkaushalkr1407
The Roman Empire, a vast and enduring power, stands as one of history's most remarkable civilizations, leaving an indelible imprint on the world. It emerged from the Roman Republic, transitioning into an imperial powerhouse under the leadership of Augustus Caesar in 27 BCE. This transformation marked the beginning of an era defined by unprecedented territorial expansion, architectural marvels, and profound cultural influence.
The empire's roots lie in the city of Rome, founded, according to legend, by Romulus in 753 BCE. Over centuries, Rome evolved from a small settlement to a formidable republic, characterized by a complex political system with elected officials and checks on power. However, internal strife, class conflicts, and military ambitions paved the way for the end of the Republic. Julius Caesar’s dictatorship and subsequent assassination in 44 BCE created a power vacuum, leading to a civil war. Octavian, later Augustus, emerged victorious, heralding the Roman Empire’s birth.
Under Augustus, the empire experienced the Pax Romana, a 200-year period of relative peace and stability. Augustus reformed the military, established efficient administrative systems, and initiated grand construction projects. The empire's borders expanded, encompassing territories from Britain to Egypt and from Spain to the Euphrates. Roman legions, renowned for their discipline and engineering prowess, secured and maintained these vast territories, building roads, fortifications, and cities that facilitated control and integration.
The Roman Empire’s society was hierarchical, with a rigid class system. At the top were the patricians, wealthy elites who held significant political power. Below them were the plebeians, free citizens with limited political influence, and the vast numbers of slaves who formed the backbone of the economy. The family unit was central, governed by the paterfamilias, the male head who held absolute authority.
Culturally, the Romans were eclectic, absorbing and adapting elements from the civilizations they encountered, particularly the Greeks. Roman art, literature, and philosophy reflected this synthesis, creating a rich cultural tapestry. Latin, the Roman language, became the lingua franca of the Western world, influencing numerous modern languages.
Roman architecture and engineering achievements were monumental. They perfected the arch, vault, and dome, constructing enduring structures like the Colosseum, Pantheon, and aqueducts. These engineering marvels not only showcased Roman ingenuity but also served practical purposes, from public entertainment to water supply.
How to Make a Field invisible in Odoo 17Celine George
It is possible to hide or invisible some fields in odoo. Commonly using “invisible” attribute in the field definition to invisible the fields. This slide will show how to make a field invisible in odoo 17.
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptxEduSkills OECD
Andreas Schleicher presents at the OECD webinar ‘Digital devices in schools: detrimental distraction or secret to success?’ on 27 May 2024. The presentation was based on findings from PISA 2022 results and the webinar helped launch the PISA in Focus ‘Managing screen time: How to protect and equip students against distraction’ https://www.oecd-ilibrary.org/education/managing-screen-time_7c225af4-en and the OECD Education Policy Perspective ‘Students, digital devices and success’ can be found here - https://oe.cd/il/5yV
21. WBS as a horizontal presentation House project Civil Plumbing Security wall and gates Electrical Landscaping Foundations Walls and roof Piping Sewerage Wiring Appliances Garden outlay Water irrigation system
22. WBS as an organogram illustration House project Civil work Plumbing work Electrical work Security walls and gates Landscaping Foundations Walls and roof Piping Sewerage Wiring Appliances Garden outlay Water irrigation
23. House project R84 000 Civil work 1.1 R44 000 Plumbing work 1.2 R8 000 Electrical work 1.3 R11 000 Security walls and gates 1.4 R12 000 Landscaping 1.5 R9 000 Foundations 1.1.1 R15 000 Walls and roof 1.1.2 R29 000 Piping 1.2.1 R6000 Sewerage 1.2.2 R2 000 Wiring 1.3.1 R3 000 Appliances 1.3.2 R8 000 Garden outlay 1.5.1 R3 000 Water irrigation 1.5.2 R6 000