Methodology of Project Progress
Reporting
Presented by :
Amit Kumar Senapati
Types
A. Earned Value (Physical % Complete)
B. Duration % Complete
C. Unit % Complete
D. Activity WeightageD. Activity Weightage
Purpose of Reporting
• Tracking progress
• Tracking internal resources cost and progress.
• Track cost.• Track cost.
• Tracking external resources cost and progress.
• Tracking both internal and external resources cost
and progress.
A. Earned Value
To enable reporting on Earned Value , the following
must be in place :-
a) Resources required for the project is identified.
b) Resource unit rate should be known.b) Resource unit rate should be known.
c) The Project Cost Centre of the project should be
available and used.
d) Earning rules are identified for the various
activities and are linked.
e) The project should be resource loaded.
Example of Earned Value Calculation – Step 1
The Activity Steps should be
checked to enable Earning Rules
development.
The Earning rules should be
finalized after discussion with
the team.
Earned Value Calculation – Step 2
• Assign the Earning rules to the project activities.
• Change the % Completion type to “Physical”.
• Assign Resources to the activity.
N.B : 1. Before finalizing the Activity Duration , make sure the correct calendar is selected . If not there will be
changes to the start and finish dates.
2. Ensure that the resource rates are first changed and then they are assigned to the activities.
If the duration of the
project is long, then ensure
that the effective date for
the Unit & Prices is filled in.
Earned Value Calculation – Step 3
In the first Instance the Budgeted
Unit for M18 is 40 hours as we have
In the second Instance the Budgeted Unit for
M18 is 16 hours as we have considered that the
resource will be working based on the resource
Unit for M18 is 40 hours as we have
considered that the resource will be
working full time on the project.
NB : The Budgeted Units can also be put in manually in discussion with the Engineers.
resource will be working based on the resource
calendar on the project. i.e. Working only on
Wednesday’s and Thursday.
Earned Value Calculation – Step 4
• Baseline the schedule.
• An anchor point for measuring performance.
• Aplanned cost and expected schedule against which actual cost and
schedule are measured..
• A basis for cash flows and awarding progress paymentsA basis for cash flows and awarding progress payments
• A summation of time-phased budgets(cost accounts as summed
work packages)along a project timeline.
• Receipt of Actual Cost from Finance.
• Receipt of Progress Update from PEM/Engineers.
• Data date for doing the Progress Update.
Understanding of Earned Value Calculation - Situation 1
In the above instance , we see that the Performance % Completion is 12.91%.
It is calculated as all the activity steps are completed and
Activity Budgeted Cost / Total Budgeted Cost = 12.91%.
The CPI and SPI is displaying as ZERO as the data date is a past date and the Actual is
ZERO.
Understanding of Earned Value Calculation - Situation 2
Here we see the CPI is equal to 2.84. i.e. R31,600(EVC) /R11,116.67(AC)
Here we see the SPI as 1.84. i.e. R31,600(EVC)/R17,174(PC)
Planned Cost(PC) is calculated based on the data date, Planned Value = (Planned %
Complete) X (BAC) , i.e. 7.03%(Planned % Complete) X R244,800(BAC) = R17,174(PC)
Here the Curve we have chosen is “Linear” which means the cost is uniformly
distributed throughout the activity duration.
Earned Value Report
Physical % Complete
When Physical % Complete is used, we must adjust the Remaining Duration as this is not
calculated by Primavera P6. You must enter a Remaining Duration manually, or set an
Expected Finish date on the activity.
We can use the Expected Finish
date option to help control the
remaining duration of Physical %
Complete activities. Adding a date
in the Expected Finish date field
locks down the end date of the
activity and forces P6 to calculate
the Remaining Duration.
B. Duration % Complete
• Team is required to report on the work completion.
• When we do not have resources in our schedule.
• There is no need to track the actual cost of the project.
• There is no earning rules in the schedule.
In case there is a requirement of Weightage to the various• In case there is a requirement of Weightage to the various
packages then MS-Excel or appropriate spreadsheet can be
used in conjunction with Primavera to calculate the Overall
% Completion.
NB : If we need to report on Duration % Completion , the % Completion Type must be changed to ‘Duration’.
Duration % Complete
This option is used to calculate progress from the planned and remaining duration values. For
example, if you enter 6 days of remaining duration for a 10 day duration activity, Primavera
P6 will calculate 40% complete. Transversely, if you enter 40% in the Activity % Complete
field, P6 will calculate a remaining duration of 6 days.
This percent complete type is best used for more level of effort type activities
where measurable deliverables are not expected and the percent complete
represents elapsed time more than deliverables completed.
Duration % Completion Reporting
Duration % Completion Report
Units % Complete
• Unit % Completion can be used in areas like amount of Concrete poured , length of
pipe laid down , number of light bulbs installed , no. Of weld build up , hours spent
on welding activity etc.
• Units % Complete doesn’t calculate the remaining duration for activities, so you
will need to use either the Remaining Duration field or an Expected Finish date to
manually control the calculated end date for your activity.
• The only drawback of this method is that hours expended doesn’t necessarily• The only drawback of this method is that hours expended doesn’t necessarily
equate to progress achieved, so this method is not very discrete.
Understanding Units % Complete
In scenario 1, of the total
Budgeted units of 24
hours , 6 hours has been
In scenario 2, of the total Budgeted
units of 24 hours , 50 hours has been
used, but the work is still not completehours , 6 hours has been
completed hence the Unit
% Complete is 25%
used, but the work is still not complete
but the Unit % Complete is 100%
Activity Weightage
Activity Weightage % Complete
NB : In activity Weightage % complete, the team cannot report on cost performance.
Conclusion
• The projects can be reported based on the
availability of information.
• Different project may require different project
reporting , based on requirement.reporting , based on requirement.
Thank You

More Related Content

What's hot

Project planning and Scheduling
Project planning and SchedulingProject planning and Scheduling
Project planning and Scheduling
saurabmi2
 
Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011
Jamal Nelson, CCM
 

What's hot (20)

construction project planing
 construction project planing construction project planing
construction project planing
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
Project management process_Infrastructure Engineering and Management (2170611...
Project management process_Infrastructure Engineering and Management (2170611...Project management process_Infrastructure Engineering and Management (2170611...
Project management process_Infrastructure Engineering and Management (2170611...
 
Baseline schedule review and analysis
Baseline schedule review and analysisBaseline schedule review and analysis
Baseline schedule review and analysis
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management
 
Extension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed IbarhimExtension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed Ibarhim
 
Primavera p6 advanced project planning
Primavera p6 advanced project planningPrimavera p6 advanced project planning
Primavera p6 advanced project planning
 
Introduction To Primavera (P6)
Introduction To Primavera (P6)Introduction To Primavera (P6)
Introduction To Primavera (P6)
 
Project management in construction.
Project management in construction.Project management in construction.
Project management in construction.
 
Project planning and Scheduling
Project planning and SchedulingProject planning and Scheduling
Project planning and Scheduling
 
Primavera - Tutorial
Primavera - TutorialPrimavera - Tutorial
Primavera - Tutorial
 
Primavera P6 manual
Primavera P6 manual Primavera P6 manual
Primavera P6 manual
 
Project Management Office Roles Functions And Benefits
Project Management Office Roles Functions And BenefitsProject Management Office Roles Functions And Benefits
Project Management Office Roles Functions And Benefits
 
Project Management Process and Its Phases
Project Management Process and Its PhasesProject Management Process and Its Phases
Project Management Process and Its Phases
 
Eot claims hr__may2012
Eot claims hr__may2012Eot claims hr__may2012
Eot claims hr__may2012
 
Project audit & closure
Project audit & closureProject audit & closure
Project audit & closure
 
Introduction to construction project management
Introduction to construction project managementIntroduction to construction project management
Introduction to construction project management
 
Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011
 
Project Control- Overview Presentation Tafseer
Project Control- Overview Presentation   TafseerProject Control- Overview Presentation   Tafseer
Project Control- Overview Presentation Tafseer
 

Similar to Methodologies of Project Progress Measurement

Chapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptxChapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptx
ssusercf695b
 

Similar to Methodologies of Project Progress Measurement (20)

A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
 
ATCO Engineering - Process Evaluation
ATCO Engineering - Process EvaluationATCO Engineering - Process Evaluation
ATCO Engineering - Process Evaluation
 
Chapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptxChapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptx
 
Topic 10 - Project Performance Management.pdf
Topic 10 - Project Performance Management.pdfTopic 10 - Project Performance Management.pdf
Topic 10 - Project Performance Management.pdf
 
CCM821S _ Contract Management _ 8. Monitoring Project Performance.pptx
CCM821S _ Contract Management _ 8. Monitoring Project Performance.pptxCCM821S _ Contract Management _ 8. Monitoring Project Performance.pptx
CCM821S _ Contract Management _ 8. Monitoring Project Performance.pptx
 
7 cost managmenet
7 cost managmenet7 cost managmenet
7 cost managmenet
 
EEEC pdf.pdf
EEEC pdf.pdfEEEC pdf.pdf
EEEC pdf.pdf
 
Monitor and control process group part two
Monitor and control process group part twoMonitor and control process group part two
Monitor and control process group part two
 
Project Management
Project ManagementProject Management
Project Management
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagement
 
Progress in Projects
Progress in ProjectsProgress in Projects
Progress in Projects
 
Topic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdfTopic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdf
 
PMP Exam Preparation Course: 06 Project Cost Management
PMP Exam Preparation Course: 06 Project Cost ManagementPMP Exam Preparation Course: 06 Project Cost Management
PMP Exam Preparation Course: 06 Project Cost Management
 
Chap05_Project Monitoring and Control.pdf
Chap05_Project Monitoring and Control.pdfChap05_Project Monitoring and Control.pdf
Chap05_Project Monitoring and Control.pdf
 
Project Management Day 4 Cost ٌ R02.pdf
Project Management Day 4 Cost ٌ R02.pdfProject Management Day 4 Cost ٌ R02.pdf
Project Management Day 4 Cost ٌ R02.pdf
 
Agile Metrics
Agile MetricsAgile Metrics
Agile Metrics
 
Project Accounting.pptx
Project Accounting.pptxProject Accounting.pptx
Project Accounting.pptx
 
Preparing cost estimation
Preparing cost estimationPreparing cost estimation
Preparing cost estimation
 
Tools and Techniques of Capital Expenditure Control
Tools and Techniques of Capital Expenditure ControlTools and Techniques of Capital Expenditure Control
Tools and Techniques of Capital Expenditure Control
 
MandC.pdf
MandC.pdfMandC.pdf
MandC.pdf
 

More from Amit Kumar Senapati, PMP®

More from Amit Kumar Senapati, PMP® (16)

Six Sigma implementation in Projects.pptx
Six Sigma implementation in Projects.pptxSix Sigma implementation in Projects.pptx
Six Sigma implementation in Projects.pptx
 
Starting up a project. Things to do.pptx
Starting up a project. Things to do.pptxStarting up a project. Things to do.pptx
Starting up a project. Things to do.pptx
 
Project Management - 5D without a ful fledged BIM.pptx
Project Management - 5D without a ful fledged BIM.pptxProject Management - 5D without a ful fledged BIM.pptx
Project Management - 5D without a ful fledged BIM.pptx
 
Agile project management
Agile project managementAgile project management
Agile project management
 
Productivity practioner
Productivity practionerProductivity practioner
Productivity practioner
 
Cost management basics for Construction Engineers
Cost management basics for Construction EngineersCost management basics for Construction Engineers
Cost management basics for Construction Engineers
 
Dashboard reporting
Dashboard reporting Dashboard reporting
Dashboard reporting
 
Electrical concepts
Electrical conceptsElectrical concepts
Electrical concepts
 
Energy saving in electrical motors and speed control
Energy saving in electrical motors and speed controlEnergy saving in electrical motors and speed control
Energy saving in electrical motors and speed control
 
Compressed air system
Compressed air systemCompressed air system
Compressed air system
 
Introduction to energy auditing
Introduction to energy auditingIntroduction to energy auditing
Introduction to energy auditing
 
Use of forward pass and backward pass in primavera
Use of forward pass and backward pass in primaveraUse of forward pass and backward pass in primavera
Use of forward pass and backward pass in primavera
 
Energy audit tata power solar
Energy audit   tata power solarEnergy audit   tata power solar
Energy audit tata power solar
 
Outage planning
Outage planningOutage planning
Outage planning
 
Earned value understanding
Earned value understandingEarned value understanding
Earned value understanding
 
Cover letter amit
Cover letter   amitCover letter   amit
Cover letter amit
 

Recently uploaded

Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
dollysharma2066
 
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 

Recently uploaded (20)

Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086
 
Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdf
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 

Methodologies of Project Progress Measurement

  • 1. Methodology of Project Progress Reporting Presented by : Amit Kumar Senapati
  • 2. Types A. Earned Value (Physical % Complete) B. Duration % Complete C. Unit % Complete D. Activity WeightageD. Activity Weightage
  • 3. Purpose of Reporting • Tracking progress • Tracking internal resources cost and progress. • Track cost.• Track cost. • Tracking external resources cost and progress. • Tracking both internal and external resources cost and progress.
  • 4. A. Earned Value To enable reporting on Earned Value , the following must be in place :- a) Resources required for the project is identified. b) Resource unit rate should be known.b) Resource unit rate should be known. c) The Project Cost Centre of the project should be available and used. d) Earning rules are identified for the various activities and are linked. e) The project should be resource loaded.
  • 5. Example of Earned Value Calculation – Step 1 The Activity Steps should be checked to enable Earning Rules development. The Earning rules should be finalized after discussion with the team.
  • 6. Earned Value Calculation – Step 2 • Assign the Earning rules to the project activities. • Change the % Completion type to “Physical”. • Assign Resources to the activity. N.B : 1. Before finalizing the Activity Duration , make sure the correct calendar is selected . If not there will be changes to the start and finish dates. 2. Ensure that the resource rates are first changed and then they are assigned to the activities. If the duration of the project is long, then ensure that the effective date for the Unit & Prices is filled in.
  • 7. Earned Value Calculation – Step 3 In the first Instance the Budgeted Unit for M18 is 40 hours as we have In the second Instance the Budgeted Unit for M18 is 16 hours as we have considered that the resource will be working based on the resource Unit for M18 is 40 hours as we have considered that the resource will be working full time on the project. NB : The Budgeted Units can also be put in manually in discussion with the Engineers. resource will be working based on the resource calendar on the project. i.e. Working only on Wednesday’s and Thursday.
  • 8. Earned Value Calculation – Step 4 • Baseline the schedule. • An anchor point for measuring performance. • Aplanned cost and expected schedule against which actual cost and schedule are measured.. • A basis for cash flows and awarding progress paymentsA basis for cash flows and awarding progress payments • A summation of time-phased budgets(cost accounts as summed work packages)along a project timeline. • Receipt of Actual Cost from Finance. • Receipt of Progress Update from PEM/Engineers. • Data date for doing the Progress Update.
  • 9. Understanding of Earned Value Calculation - Situation 1 In the above instance , we see that the Performance % Completion is 12.91%. It is calculated as all the activity steps are completed and Activity Budgeted Cost / Total Budgeted Cost = 12.91%. The CPI and SPI is displaying as ZERO as the data date is a past date and the Actual is ZERO.
  • 10. Understanding of Earned Value Calculation - Situation 2 Here we see the CPI is equal to 2.84. i.e. R31,600(EVC) /R11,116.67(AC) Here we see the SPI as 1.84. i.e. R31,600(EVC)/R17,174(PC) Planned Cost(PC) is calculated based on the data date, Planned Value = (Planned % Complete) X (BAC) , i.e. 7.03%(Planned % Complete) X R244,800(BAC) = R17,174(PC) Here the Curve we have chosen is “Linear” which means the cost is uniformly distributed throughout the activity duration.
  • 12. Physical % Complete When Physical % Complete is used, we must adjust the Remaining Duration as this is not calculated by Primavera P6. You must enter a Remaining Duration manually, or set an Expected Finish date on the activity. We can use the Expected Finish date option to help control the remaining duration of Physical % Complete activities. Adding a date in the Expected Finish date field locks down the end date of the activity and forces P6 to calculate the Remaining Duration.
  • 13. B. Duration % Complete • Team is required to report on the work completion. • When we do not have resources in our schedule. • There is no need to track the actual cost of the project. • There is no earning rules in the schedule. In case there is a requirement of Weightage to the various• In case there is a requirement of Weightage to the various packages then MS-Excel or appropriate spreadsheet can be used in conjunction with Primavera to calculate the Overall % Completion. NB : If we need to report on Duration % Completion , the % Completion Type must be changed to ‘Duration’.
  • 14. Duration % Complete This option is used to calculate progress from the planned and remaining duration values. For example, if you enter 6 days of remaining duration for a 10 day duration activity, Primavera P6 will calculate 40% complete. Transversely, if you enter 40% in the Activity % Complete field, P6 will calculate a remaining duration of 6 days. This percent complete type is best used for more level of effort type activities where measurable deliverables are not expected and the percent complete represents elapsed time more than deliverables completed.
  • 17. Units % Complete • Unit % Completion can be used in areas like amount of Concrete poured , length of pipe laid down , number of light bulbs installed , no. Of weld build up , hours spent on welding activity etc. • Units % Complete doesn’t calculate the remaining duration for activities, so you will need to use either the Remaining Duration field or an Expected Finish date to manually control the calculated end date for your activity. • The only drawback of this method is that hours expended doesn’t necessarily• The only drawback of this method is that hours expended doesn’t necessarily equate to progress achieved, so this method is not very discrete.
  • 18. Understanding Units % Complete In scenario 1, of the total Budgeted units of 24 hours , 6 hours has been In scenario 2, of the total Budgeted units of 24 hours , 50 hours has been used, but the work is still not completehours , 6 hours has been completed hence the Unit % Complete is 25% used, but the work is still not complete but the Unit % Complete is 100%
  • 20. Activity Weightage % Complete NB : In activity Weightage % complete, the team cannot report on cost performance.
  • 21. Conclusion • The projects can be reported based on the availability of information. • Different project may require different project reporting , based on requirement.reporting , based on requirement.