International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 10 Issue: 05 | May 2023 www.irjet.net p-ISSN: 2395-0072
© 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 1353
Planning, Scheduling and Allocation of Resources for Multi –
storiedStructure using Microsoft Project Software
Prof. H. S. Dikkar1, Samarth Pawar2, Lokesh Shastri2, Khemraj Somwanshi2, Ganesh Patil2
1 Assistant Professor, Sandip Institute of Engineering & Management Nashik, Maharashtra, India.
2 Student of Bachelor of Engineering, Department of Civil Engineering Sandip Institute of Engineering &
Management, Nashik, Maharashtra, India.
---------------------------------------------------------------------***---------------------------------------------------------------------
Abstract - The focus of this work is to study scheduling
methods and construction systems for multistorey buildings,
with the aim of applying Microsoft Project software to plan
and schedule a hypothetical RCC residential G+7 building
construction project. The study compares the traditional
approach used by architects, engineers, and contractors with
the modern software technique. Observations from the study
indicate that Microsoft Project software is an effective tool for
generating Gantt charts for construction project schedules.
The software also offers the ability to determine the minimum
duration of construction time through schedule crunching and
project crashing methods. Overall, the study provides valuable
information on the application of Microsoft Project software
for planning and scheduling building construction projects.
The use of this software can help to streamline the scheduling
process, increase efficiency, and reduce costs associated with
construction projects. It is important to note that while
technology can be helpful in project planning and
management, it is not a replacement for experienced
professionals in the field who can provide insights and make
informed decisions.
Key Words: Project, Time, Cost, Scheduling, Resource
Allocation, construction, Critical Path Method (CPM)
The construction industry faces various challenges related
to time management, cost control, and project delays. These
challenges can be minimized through proper project
planning, which involves detailing the strategy that should
be followed to complete the project within the defined time,
budget, and quality specifications. Effective project planning
facilitates communication among stakeholders, documents
planning assumptions and decisions, and develops approved
scope, cost, and schedule baselines.
Construction project management is the science and art of
managing all aspects of the project to achieve project
mission objectives, specific time, budget cost, and predefined
quality specifications. It involves working efficiently and
effectively in a changing project environment while ensuring
the safety and health of construction workers. The mission of
creating a construction facility or services is achieved
through predetermined performance objectives defined in
terms of quality specifications, completion time, budget cost,
and other specified constraints.
The presented work reviewed the concepts of activity
sequencing used in building construction, scheduling
techniques used in Microsoft Project Planner, and the
development of construction planning and scheduling. The
study provides information about the project from the start
to the end of construction, including what needs to be done
before starting the project, during the construction, and after
the completion of the project.
1.1 Microsoft Project:
Microsoft Project is a comprehensive project management
software solution that aids project managers in planning and
executing their projects. It provides the tools to create a
detailed project plan, including tasks, milestones, and
deliverables. Once the plan is created, resources can be
assigned to each task, and the progress of each task and the
overall project can be tracked. In addition, Microsoft Project
enables project managers to manage the project budget and
workload, ensuring that the project is on track and within
budget. The four primary functions of Microsoft Project are
developing a project plan, assigning resources to tasks,
tracking progress, and managing the project budget and
workload.
2. LITERATURE REVIEV
1] Shruti Singh, Shweta Is tape, Amruta Survey, Sahil
Pandey, Avinash Singh, Sangram More MGMCET, Kamothe,
University of Mumbai, Navi Mumbai, India Project
Management is the application of knowledge, tools,
techniques and skills to any project activities to meet the
requirements of the project. Usually, many construction
industries in India do not practice the use of project
management properly. Poorly managed projects usually
result in a huge amount to all stakeholders not just financially
but also psychologically and emotionally as well as it also
consumes a lot of time. This has greatly motivated us to carry
out the working and functioning of a project using modern
project management tool, one of which is MSP (Microsoft
Project). This paper consists of planning and scheduling of
various activities involved in a construction project using
MSP. The presented work clearly gives the difference
between carrying out the work using MSP and traditional
planning techniques.
2] Subraman i, T.M.Karthic k Managing Director,
Priyanka Associates (Civil Engineers and Valuers), Salem,
1. INTRODUCTION
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 10 Issue: 05 | May 2023 www.irjet.net p-ISSN: 2395-0072
© 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 1354
TamilNadu,India. Design Engineer, Indo Builders (Civil
Engineers and Valuers), Dharmapuri ,TamilNadu, India he
construction project under study aims to achieve a time-
certain program performance goal through excessive stake
endeavor. Without carefully planned and procured
resources, it is impossible to complete activities within a
predetermined timetable. Project managers face complex
decisions under exceptional scheduling demands and
uncertain conditions that sometimes extend beyond
project intervals. This project study focuses on resource
scheduling for a quick-track project with constrained
intervals.
3] Nikhil R. Mahajan and M. V. Bhogone (2017) The
methodology adapted by them was to compare Microsoft
Project and Traditional Method. Schedule was prepared for
both conventional and prefabrication method. A residential
building was taken for comparison. The software used was
MSP, the duration required for completion of project was
collected from respective company. The comparison was
made by comparing the total time required for completion by
using critical path method with MSP project. The result
shows that the total duration for both the conventional and
prefabrication method and prefab construction for individual
house and double story the required cost is 13% more than
conventional but it reduces the project duration by 63 days.
4] R. Prabhahar and G. Ravichandran (2014) analyzed
that; Construction planning is an important part of the overall
management process. The planning and management
includes organizing the work, executing the work, correlating
plan and progress information and controlling the work, the
three inter-related factors of time, money and quality need to
be managed in a proper way. Completion of many of the
projects nowadays is not in estimated duration. This will
direct to an increase in overheads as well as various other
factors. It will not only reduce the expected revenues but also
will affect the reputation of the contractor. Scheduling is one
of the vital functions in construction project to determine the
sequence of activities necessary to complete a project.
3. Model Applications
3.1 MS Project Interface
Fig 3.1. Microsoft Project 2021 shows blank project.
We can see here interface of MS Project and what kind of
options are available on MS Project. Here we can enter our
data and can do many activities such as creating Gantt
Chart, Resource Allocation, Scheduling, Estimation, Creating
Reports and many more.-
3.2 Scheduling Activities using network models
Fig 3.2. Scheduling of Activities
With the help of Microsoft Project, it’s easily to understand
and visualize the flow and network of the project. Users can
also visualize parallel activities, which are activities that can
be performed simultaneously, as well as slack or total float,
which is the amount of time an activity can be delayed
without affecting the overall project completion date.
Microsoft Project allows users to create network diagrams
that show the relationships between activities and help to
identify dependencies and potential bottlenecks in the project
schedule. By visualizing these relationships and
dependencies, project managers can make informed
decisions about scheduling and resource allocation, and can
take appropriate action to ensure that the project stays on
track.
3.3 Scheduling and Tracking Activities with Gantt
Charts
Fig 3.3. Gantt Chart
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 10 Issue: 05 | May 2023 www.irjet.net p-ISSN: 2395-0072
© 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 1355
Gantt charts are a key visualization tool used in project
management, and they are extensively used in Microsoft
Project (MSP). The left side of the Gantt chart in MSP
typically displays a sheet view, which shows information
about the tasks and their associated properties, such as
start and finish dates, durations, and dependencies. On the
right side of the Gantt chart, there is a bar graph that shows
the tasks along a timescale.
4. RESULTS AND DISCUSSION
Using this software we got result about G+10 building and this
resultisverysatisfactorysuchresultareasfollows.
4.1 Resource Overview
Fig 4.1. Resource Overview
Microsoft Project, resources are defined as people,
equipment, or materials required to complete a project task.
The Resource Overview provides an essential summary of
the resources assigned to a project, their availability, and
their workloads. It is a valuable tool for identifying resource
conflicts, balancing workloads, and ensuring the effective use
of resources in a project. Microsoft Project's Resource Sheet
view displays a table of resources, including their names,
types, and costs. This view can be customized by adding or
removing columns based on the project's requirements.
Additionally, the Resource Usage view provides a calendar-
based view of resource allocation over time.
4.2 Resource Cost Overview
Fig 4.2. Resource Cost Overview
In Microsoft Project's Resource Cost Overview summarizes the
costs associated with each resource in a project, including hourly
rates,total costs,andanyassignmentsorcompletedwork.
This feature is an effective tool for monitoring and managing
resource costs. It enables project managers to optimize resource
allocation, identify cost overruns, and ensure the effective and
efficient use of resources. Besides the Resource Cost Overview,
Microsoft Project offersa variety of resourcecostreports thathelp
project managers analyze and manage the costs associated with
their project's resources. Some of these reports include the
Resource Cost Summary, Resource Cost by Type, and Resource
CostbyAssignmentreports.
4.3 Cost Overview
Fig 4.3. Cost Overview
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 10 Issue: 05 | May 2023 www.irjet.net p-ISSN: 2395-0072
© 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 1356
The Cost Overview feature in Microsoft Project provides a
concise summary of the costs associated with each task
and resource in your project, which includes the total cost,
actual cost, remaining cost, and cost variance. It is an
invaluable tool for project managers to monitor and
manage the costs associated with their project's tasks and
resources. By using the Cost Overview, project managers
can efficiently optimize resource allocation, identify cost
overruns, and ensure effective use of resources.
4.4 Cost Overruns
Fig 4.4. Cost Overruns
A cost overrun happens when the actual cost of a project
surpasses its planned or budgeted cost. Cost overruns can
significantly affect a project's timeline, quality, and success.
In Microsoft Project, the Cost Overview and other cost-
related reports are valuable tools for project managers to
identify cost overruns and take appropriate steps to
address them.
4.5 Task cost overview
Fig 4.5. Task Cost Overview
The Task Cost Overview feature in Microsoft Project
provides a comprehensive summary of the costs associated
with each task in your project. It includes the total cost,
actual cost, remaining cost, and cost variance. This tool is
useful in tracking and managing task costs and ensuring
that the project remains within budget and on track.
Monitoring actual costs, analyzing variances, and adjusting
the project plan as needed are crucial steps in achieving this
goal.
4.6 Upcoming Tasks
Fig 4.6. Upcoming Tasks
Microsoft Project offers two views to visualize upcoming
tasks: the Timeline view and the Gantt Chart view. Once you
have identified the upcoming tasks in your project, you can
take essential steps to prepare for them. This may include
allocating resources, reviewing task dependencies, and
adjusting the project schedule as necessary
4.7 Network Diagram
Fig 4.7. Network Diagram
Microsoft Project offers the Network Diagram view feature,
which allows you to create a visual representation of the
project's tasks and their dependencies. This diagram can
help you identify the critical path of your project and any
scheduling conflicts. Utilizing the Network Diagram view in
Microsoft Project can provide you with a better
understanding of the interconnections between project
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 10 Issue: 05 | May 2023 www.irjet.net p-ISSN: 2395-0072
5. CONCLUSIONS
Microsoft Project helps for scheduling, planning. Using this
software we plan G+10 building, their schedule and their
allocating. Using this software we plan easily, it reduce less
time for planning, scheduling and allocation. We used this
software for reducing time and proper management of
labor, and all resources in time. We experienced that this
software is very useful for now days in construction field.
6. REFERENCES
[1] Shruti Singh, Shweta Istape, Amruta Surve, Sahil
Pandey, Avinash Singh, Sangram More MGMCET,
Kamothe, University of Mumbai, Navi Mumbai, India
“Comparative study of planning and scheduling of a
construction project using Microsoft project”
International Journal of Research in Engineering and
Technology (IJRET) 23- 05-2018 Mr. Dipesh
R.Wallecha, Prof. Manish D. Mata, Civil Engineering
Department SSGBCOE T, Bhusawal” A Review on
Application of Microsoft Project Software in Multi-
Storeyed Buildings” International Journal for Research
in Applied Science & Engineering Technology(IJRASET)
May 2020
[2] Shubham Laddha , Prerna Chanda and Sneha
Khedekar. Student (BE Civil, AISSMS COE, Pune, India).
Assistant Professor (AISSMS COE, Pune, India).”
PLANNIN G AND SCHEDU LING OF A PROJECT USING
MICROS OFT PROJECT(MSP)” International journal of
Advanced research (IJAR) June 2017
[3] Nikhil R. Mahajan and M. V. Bhogone (2017) The methodology
adapted by them was to compare Microsoft Project and
TraditionalMethod
BIOGRAPHIES
Mr. L.G SHASTRI.
Student Bachelor of Engineering
Department Of Civil Engineering,
Sandip Institute of Engineering &
Management, Nashik,
Maharashtra, India.
Mr. S.D. PAWAR.
Student Bachelor of Engineering
Department Of Civil Engineering,
Sandip Institute of Engineering &
Management, Nashik,
Maharashtra, India.
Mr. K.T. SOMWANSHI.
Student Bachelor of Engineering
Department Of Civil Engineering,
Sandip Institute of Engineering &
Management, Nashik,
Maharashtra, India.
Mr. G.D. PATIL.
Student Bachelor of Engineering
Department Of Civil Engineering,
Sandip Institute of Engineering &
Management, Nashik,
Maharashtra, India.
tasks and help you to identify any potential scheduling
issues, which in turn can enable you to make necessary
adjustments to your project plan and ensure that your
project remains on track.
[4] R. Prabhakar and G. Ravichandran (2014) analysed
that; Construction planning is an important part of the
overall management process.
Prof. H.S. DIKKAR
Assistant professor,
Department Of Civil Engineering,
Sandip Institute of Engineering &
Management, Nashik,
Maharashtra, India.
© 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 1357

More Related Content

Similar to Planning, Scheduling and Allocation of Resources for Multi – storiedStructure using Microsoft Project Software

76 s201905
76 s20190576 s201905
76 s201905IJRAT
 
Project management tools and techniques- tutorsindia.com
Project management tools and techniques- tutorsindia.comProject management tools and techniques- tutorsindia.com
Project management tools and techniques- tutorsindia.comTutors India
 
IRJET- Optimized Project Planning and Scheduling of Multistorey Building
IRJET-  	  Optimized Project Planning and Scheduling of Multistorey BuildingIRJET-  	  Optimized Project Planning and Scheduling of Multistorey Building
IRJET- Optimized Project Planning and Scheduling of Multistorey BuildingIRJET Journal
 
A study of the constraints affecting the proper utilization of computer appli...
A study of the constraints affecting the proper utilization of computer appli...A study of the constraints affecting the proper utilization of computer appli...
A study of the constraints affecting the proper utilization of computer appli...eSAT Journals
 
Project Planning and Scheduling
Project Planning and SchedulingProject Planning and Scheduling
Project Planning and Schedulingijtsrd
 
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...IRJET Journal
 
Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...
Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...
Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...IRJET Journal
 
IRJET- Planning, Scheduling, and Optimization of Labor Resources in the C...
IRJET-  	  Planning, Scheduling, and Optimization of Labor Resources in the C...IRJET-  	  Planning, Scheduling, and Optimization of Labor Resources in the C...
IRJET- Planning, Scheduling, and Optimization of Labor Resources in the C...IRJET Journal
 
Review on Planning and Scheduling of Construction Project by Management Tool ...
Review on Planning and Scheduling of Construction Project by Management Tool ...Review on Planning and Scheduling of Construction Project by Management Tool ...
Review on Planning and Scheduling of Construction Project by Management Tool ...ijtsrd
 
Planning and Optimization of Resource Constrained Project Scheduling by using...
Planning and Optimization of Resource Constrained Project Scheduling by using...Planning and Optimization of Resource Constrained Project Scheduling by using...
Planning and Optimization of Resource Constrained Project Scheduling by using...IRJET Journal
 
A REVIEW ON FACTORS INFLUENCING CONSTRUCTION PROJECT SCHEDULING
A REVIEW ON FACTORS INFLUENCING CONSTRUCTION PROJECT SCHEDULINGA REVIEW ON FACTORS INFLUENCING CONSTRUCTION PROJECT SCHEDULING
A REVIEW ON FACTORS INFLUENCING CONSTRUCTION PROJECT SCHEDULINGIAEME Publication
 
Material Management Practices of “Foundation Silver Spring” Residential Build...
Material Management Practices of “Foundation Silver Spring” Residential Build...Material Management Practices of “Foundation Silver Spring” Residential Build...
Material Management Practices of “Foundation Silver Spring” Residential Build...IRJET Journal
 
IRJET- Identification of Constraints and there Impact on Construction Pro...
IRJET-  	  Identification of Constraints and there Impact on Construction Pro...IRJET-  	  Identification of Constraints and there Impact on Construction Pro...
IRJET- Identification of Constraints and there Impact on Construction Pro...IRJET Journal
 
IRJET- Scheduling and Labour Management for Residential Building Project usin...
IRJET- Scheduling and Labour Management for Residential Building Project usin...IRJET- Scheduling and Labour Management for Residential Building Project usin...
IRJET- Scheduling and Labour Management for Residential Building Project usin...IRJET Journal
 
A Study on Project Planning Using the Deterministic and Probabilistic Models ...
A Study on Project Planning Using the Deterministic and Probabilistic Models ...A Study on Project Planning Using the Deterministic and Probabilistic Models ...
A Study on Project Planning Using the Deterministic and Probabilistic Models ...IJERA Editor
 
Resource Optimization in Construction of a Residential Apartment using Primav...
Resource Optimization in Construction of a Residential Apartment using Primav...Resource Optimization in Construction of a Residential Apartment using Primav...
Resource Optimization in Construction of a Residential Apartment using Primav...IRJET Journal
 
Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...
Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...
Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...IRJET Journal
 
IT project management-IT project management-Unit-2.pptx
IT project management-IT project management-Unit-2.pptxIT project management-IT project management-Unit-2.pptx
IT project management-IT project management-Unit-2.pptxMAHASREEM
 

Similar to Planning, Scheduling and Allocation of Resources for Multi – storiedStructure using Microsoft Project Software (20)

76 s201905
76 s20190576 s201905
76 s201905
 
Project management tools and techniques- tutorsindia.com
Project management tools and techniques- tutorsindia.comProject management tools and techniques- tutorsindia.com
Project management tools and techniques- tutorsindia.com
 
IRJET- Optimized Project Planning and Scheduling of Multistorey Building
IRJET-  	  Optimized Project Planning and Scheduling of Multistorey BuildingIRJET-  	  Optimized Project Planning and Scheduling of Multistorey Building
IRJET- Optimized Project Planning and Scheduling of Multistorey Building
 
A study of the constraints affecting the proper utilization of computer appli...
A study of the constraints affecting the proper utilization of computer appli...A study of the constraints affecting the proper utilization of computer appli...
A study of the constraints affecting the proper utilization of computer appli...
 
H1303024956
H1303024956H1303024956
H1303024956
 
Project Planning and Scheduling
Project Planning and SchedulingProject Planning and Scheduling
Project Planning and Scheduling
 
Ijciet 10 01_075
Ijciet 10 01_075Ijciet 10 01_075
Ijciet 10 01_075
 
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
 
Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...
Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...
Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...
 
IRJET- Planning, Scheduling, and Optimization of Labor Resources in the C...
IRJET-  	  Planning, Scheduling, and Optimization of Labor Resources in the C...IRJET-  	  Planning, Scheduling, and Optimization of Labor Resources in the C...
IRJET- Planning, Scheduling, and Optimization of Labor Resources in the C...
 
Review on Planning and Scheduling of Construction Project by Management Tool ...
Review on Planning and Scheduling of Construction Project by Management Tool ...Review on Planning and Scheduling of Construction Project by Management Tool ...
Review on Planning and Scheduling of Construction Project by Management Tool ...
 
Planning and Optimization of Resource Constrained Project Scheduling by using...
Planning and Optimization of Resource Constrained Project Scheduling by using...Planning and Optimization of Resource Constrained Project Scheduling by using...
Planning and Optimization of Resource Constrained Project Scheduling by using...
 
A REVIEW ON FACTORS INFLUENCING CONSTRUCTION PROJECT SCHEDULING
A REVIEW ON FACTORS INFLUENCING CONSTRUCTION PROJECT SCHEDULINGA REVIEW ON FACTORS INFLUENCING CONSTRUCTION PROJECT SCHEDULING
A REVIEW ON FACTORS INFLUENCING CONSTRUCTION PROJECT SCHEDULING
 
Material Management Practices of “Foundation Silver Spring” Residential Build...
Material Management Practices of “Foundation Silver Spring” Residential Build...Material Management Practices of “Foundation Silver Spring” Residential Build...
Material Management Practices of “Foundation Silver Spring” Residential Build...
 
IRJET- Identification of Constraints and there Impact on Construction Pro...
IRJET-  	  Identification of Constraints and there Impact on Construction Pro...IRJET-  	  Identification of Constraints and there Impact on Construction Pro...
IRJET- Identification of Constraints and there Impact on Construction Pro...
 
IRJET- Scheduling and Labour Management for Residential Building Project usin...
IRJET- Scheduling and Labour Management for Residential Building Project usin...IRJET- Scheduling and Labour Management for Residential Building Project usin...
IRJET- Scheduling and Labour Management for Residential Building Project usin...
 
A Study on Project Planning Using the Deterministic and Probabilistic Models ...
A Study on Project Planning Using the Deterministic and Probabilistic Models ...A Study on Project Planning Using the Deterministic and Probabilistic Models ...
A Study on Project Planning Using the Deterministic and Probabilistic Models ...
 
Resource Optimization in Construction of a Residential Apartment using Primav...
Resource Optimization in Construction of a Residential Apartment using Primav...Resource Optimization in Construction of a Residential Apartment using Primav...
Resource Optimization in Construction of a Residential Apartment using Primav...
 
Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...
Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...
Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...
 
IT project management-IT project management-Unit-2.pptx
IT project management-IT project management-Unit-2.pptxIT project management-IT project management-Unit-2.pptx
IT project management-IT project management-Unit-2.pptx
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 

Recently uploaded (20)

Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 

Planning, Scheduling and Allocation of Resources for Multi – storiedStructure using Microsoft Project Software

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 10 Issue: 05 | May 2023 www.irjet.net p-ISSN: 2395-0072 © 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 1353 Planning, Scheduling and Allocation of Resources for Multi – storiedStructure using Microsoft Project Software Prof. H. S. Dikkar1, Samarth Pawar2, Lokesh Shastri2, Khemraj Somwanshi2, Ganesh Patil2 1 Assistant Professor, Sandip Institute of Engineering & Management Nashik, Maharashtra, India. 2 Student of Bachelor of Engineering, Department of Civil Engineering Sandip Institute of Engineering & Management, Nashik, Maharashtra, India. ---------------------------------------------------------------------***--------------------------------------------------------------------- Abstract - The focus of this work is to study scheduling methods and construction systems for multistorey buildings, with the aim of applying Microsoft Project software to plan and schedule a hypothetical RCC residential G+7 building construction project. The study compares the traditional approach used by architects, engineers, and contractors with the modern software technique. Observations from the study indicate that Microsoft Project software is an effective tool for generating Gantt charts for construction project schedules. The software also offers the ability to determine the minimum duration of construction time through schedule crunching and project crashing methods. Overall, the study provides valuable information on the application of Microsoft Project software for planning and scheduling building construction projects. The use of this software can help to streamline the scheduling process, increase efficiency, and reduce costs associated with construction projects. It is important to note that while technology can be helpful in project planning and management, it is not a replacement for experienced professionals in the field who can provide insights and make informed decisions. Key Words: Project, Time, Cost, Scheduling, Resource Allocation, construction, Critical Path Method (CPM) The construction industry faces various challenges related to time management, cost control, and project delays. These challenges can be minimized through proper project planning, which involves detailing the strategy that should be followed to complete the project within the defined time, budget, and quality specifications. Effective project planning facilitates communication among stakeholders, documents planning assumptions and decisions, and develops approved scope, cost, and schedule baselines. Construction project management is the science and art of managing all aspects of the project to achieve project mission objectives, specific time, budget cost, and predefined quality specifications. It involves working efficiently and effectively in a changing project environment while ensuring the safety and health of construction workers. The mission of creating a construction facility or services is achieved through predetermined performance objectives defined in terms of quality specifications, completion time, budget cost, and other specified constraints. The presented work reviewed the concepts of activity sequencing used in building construction, scheduling techniques used in Microsoft Project Planner, and the development of construction planning and scheduling. The study provides information about the project from the start to the end of construction, including what needs to be done before starting the project, during the construction, and after the completion of the project. 1.1 Microsoft Project: Microsoft Project is a comprehensive project management software solution that aids project managers in planning and executing their projects. It provides the tools to create a detailed project plan, including tasks, milestones, and deliverables. Once the plan is created, resources can be assigned to each task, and the progress of each task and the overall project can be tracked. In addition, Microsoft Project enables project managers to manage the project budget and workload, ensuring that the project is on track and within budget. The four primary functions of Microsoft Project are developing a project plan, assigning resources to tasks, tracking progress, and managing the project budget and workload. 2. LITERATURE REVIEV 1] Shruti Singh, Shweta Is tape, Amruta Survey, Sahil Pandey, Avinash Singh, Sangram More MGMCET, Kamothe, University of Mumbai, Navi Mumbai, India Project Management is the application of knowledge, tools, techniques and skills to any project activities to meet the requirements of the project. Usually, many construction industries in India do not practice the use of project management properly. Poorly managed projects usually result in a huge amount to all stakeholders not just financially but also psychologically and emotionally as well as it also consumes a lot of time. This has greatly motivated us to carry out the working and functioning of a project using modern project management tool, one of which is MSP (Microsoft Project). This paper consists of planning and scheduling of various activities involved in a construction project using MSP. The presented work clearly gives the difference between carrying out the work using MSP and traditional planning techniques. 2] Subraman i, T.M.Karthic k Managing Director, Priyanka Associates (Civil Engineers and Valuers), Salem, 1. INTRODUCTION
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 10 Issue: 05 | May 2023 www.irjet.net p-ISSN: 2395-0072 © 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 1354 TamilNadu,India. Design Engineer, Indo Builders (Civil Engineers and Valuers), Dharmapuri ,TamilNadu, India he construction project under study aims to achieve a time- certain program performance goal through excessive stake endeavor. Without carefully planned and procured resources, it is impossible to complete activities within a predetermined timetable. Project managers face complex decisions under exceptional scheduling demands and uncertain conditions that sometimes extend beyond project intervals. This project study focuses on resource scheduling for a quick-track project with constrained intervals. 3] Nikhil R. Mahajan and M. V. Bhogone (2017) The methodology adapted by them was to compare Microsoft Project and Traditional Method. Schedule was prepared for both conventional and prefabrication method. A residential building was taken for comparison. The software used was MSP, the duration required for completion of project was collected from respective company. The comparison was made by comparing the total time required for completion by using critical path method with MSP project. The result shows that the total duration for both the conventional and prefabrication method and prefab construction for individual house and double story the required cost is 13% more than conventional but it reduces the project duration by 63 days. 4] R. Prabhahar and G. Ravichandran (2014) analyzed that; Construction planning is an important part of the overall management process. The planning and management includes organizing the work, executing the work, correlating plan and progress information and controlling the work, the three inter-related factors of time, money and quality need to be managed in a proper way. Completion of many of the projects nowadays is not in estimated duration. This will direct to an increase in overheads as well as various other factors. It will not only reduce the expected revenues but also will affect the reputation of the contractor. Scheduling is one of the vital functions in construction project to determine the sequence of activities necessary to complete a project. 3. Model Applications 3.1 MS Project Interface Fig 3.1. Microsoft Project 2021 shows blank project. We can see here interface of MS Project and what kind of options are available on MS Project. Here we can enter our data and can do many activities such as creating Gantt Chart, Resource Allocation, Scheduling, Estimation, Creating Reports and many more.- 3.2 Scheduling Activities using network models Fig 3.2. Scheduling of Activities With the help of Microsoft Project, it’s easily to understand and visualize the flow and network of the project. Users can also visualize parallel activities, which are activities that can be performed simultaneously, as well as slack or total float, which is the amount of time an activity can be delayed without affecting the overall project completion date. Microsoft Project allows users to create network diagrams that show the relationships between activities and help to identify dependencies and potential bottlenecks in the project schedule. By visualizing these relationships and dependencies, project managers can make informed decisions about scheduling and resource allocation, and can take appropriate action to ensure that the project stays on track. 3.3 Scheduling and Tracking Activities with Gantt Charts Fig 3.3. Gantt Chart
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 10 Issue: 05 | May 2023 www.irjet.net p-ISSN: 2395-0072 © 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 1355 Gantt charts are a key visualization tool used in project management, and they are extensively used in Microsoft Project (MSP). The left side of the Gantt chart in MSP typically displays a sheet view, which shows information about the tasks and their associated properties, such as start and finish dates, durations, and dependencies. On the right side of the Gantt chart, there is a bar graph that shows the tasks along a timescale. 4. RESULTS AND DISCUSSION Using this software we got result about G+10 building and this resultisverysatisfactorysuchresultareasfollows. 4.1 Resource Overview Fig 4.1. Resource Overview Microsoft Project, resources are defined as people, equipment, or materials required to complete a project task. The Resource Overview provides an essential summary of the resources assigned to a project, their availability, and their workloads. It is a valuable tool for identifying resource conflicts, balancing workloads, and ensuring the effective use of resources in a project. Microsoft Project's Resource Sheet view displays a table of resources, including their names, types, and costs. This view can be customized by adding or removing columns based on the project's requirements. Additionally, the Resource Usage view provides a calendar- based view of resource allocation over time. 4.2 Resource Cost Overview Fig 4.2. Resource Cost Overview In Microsoft Project's Resource Cost Overview summarizes the costs associated with each resource in a project, including hourly rates,total costs,andanyassignmentsorcompletedwork. This feature is an effective tool for monitoring and managing resource costs. It enables project managers to optimize resource allocation, identify cost overruns, and ensure the effective and efficient use of resources. Besides the Resource Cost Overview, Microsoft Project offersa variety of resourcecostreports thathelp project managers analyze and manage the costs associated with their project's resources. Some of these reports include the Resource Cost Summary, Resource Cost by Type, and Resource CostbyAssignmentreports. 4.3 Cost Overview Fig 4.3. Cost Overview
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 10 Issue: 05 | May 2023 www.irjet.net p-ISSN: 2395-0072 © 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 1356 The Cost Overview feature in Microsoft Project provides a concise summary of the costs associated with each task and resource in your project, which includes the total cost, actual cost, remaining cost, and cost variance. It is an invaluable tool for project managers to monitor and manage the costs associated with their project's tasks and resources. By using the Cost Overview, project managers can efficiently optimize resource allocation, identify cost overruns, and ensure effective use of resources. 4.4 Cost Overruns Fig 4.4. Cost Overruns A cost overrun happens when the actual cost of a project surpasses its planned or budgeted cost. Cost overruns can significantly affect a project's timeline, quality, and success. In Microsoft Project, the Cost Overview and other cost- related reports are valuable tools for project managers to identify cost overruns and take appropriate steps to address them. 4.5 Task cost overview Fig 4.5. Task Cost Overview The Task Cost Overview feature in Microsoft Project provides a comprehensive summary of the costs associated with each task in your project. It includes the total cost, actual cost, remaining cost, and cost variance. This tool is useful in tracking and managing task costs and ensuring that the project remains within budget and on track. Monitoring actual costs, analyzing variances, and adjusting the project plan as needed are crucial steps in achieving this goal. 4.6 Upcoming Tasks Fig 4.6. Upcoming Tasks Microsoft Project offers two views to visualize upcoming tasks: the Timeline view and the Gantt Chart view. Once you have identified the upcoming tasks in your project, you can take essential steps to prepare for them. This may include allocating resources, reviewing task dependencies, and adjusting the project schedule as necessary 4.7 Network Diagram Fig 4.7. Network Diagram Microsoft Project offers the Network Diagram view feature, which allows you to create a visual representation of the project's tasks and their dependencies. This diagram can help you identify the critical path of your project and any scheduling conflicts. Utilizing the Network Diagram view in Microsoft Project can provide you with a better understanding of the interconnections between project
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 10 Issue: 05 | May 2023 www.irjet.net p-ISSN: 2395-0072 5. CONCLUSIONS Microsoft Project helps for scheduling, planning. Using this software we plan G+10 building, their schedule and their allocating. Using this software we plan easily, it reduce less time for planning, scheduling and allocation. We used this software for reducing time and proper management of labor, and all resources in time. We experienced that this software is very useful for now days in construction field. 6. REFERENCES [1] Shruti Singh, Shweta Istape, Amruta Surve, Sahil Pandey, Avinash Singh, Sangram More MGMCET, Kamothe, University of Mumbai, Navi Mumbai, India “Comparative study of planning and scheduling of a construction project using Microsoft project” International Journal of Research in Engineering and Technology (IJRET) 23- 05-2018 Mr. Dipesh R.Wallecha, Prof. Manish D. Mata, Civil Engineering Department SSGBCOE T, Bhusawal” A Review on Application of Microsoft Project Software in Multi- Storeyed Buildings” International Journal for Research in Applied Science & Engineering Technology(IJRASET) May 2020 [2] Shubham Laddha , Prerna Chanda and Sneha Khedekar. Student (BE Civil, AISSMS COE, Pune, India). Assistant Professor (AISSMS COE, Pune, India).” PLANNIN G AND SCHEDU LING OF A PROJECT USING MICROS OFT PROJECT(MSP)” International journal of Advanced research (IJAR) June 2017 [3] Nikhil R. Mahajan and M. V. Bhogone (2017) The methodology adapted by them was to compare Microsoft Project and TraditionalMethod BIOGRAPHIES Mr. L.G SHASTRI. Student Bachelor of Engineering Department Of Civil Engineering, Sandip Institute of Engineering & Management, Nashik, Maharashtra, India. Mr. S.D. PAWAR. Student Bachelor of Engineering Department Of Civil Engineering, Sandip Institute of Engineering & Management, Nashik, Maharashtra, India. Mr. K.T. SOMWANSHI. Student Bachelor of Engineering Department Of Civil Engineering, Sandip Institute of Engineering & Management, Nashik, Maharashtra, India. Mr. G.D. PATIL. Student Bachelor of Engineering Department Of Civil Engineering, Sandip Institute of Engineering & Management, Nashik, Maharashtra, India. tasks and help you to identify any potential scheduling issues, which in turn can enable you to make necessary adjustments to your project plan and ensure that your project remains on track. [4] R. Prabhakar and G. Ravichandran (2014) analysed that; Construction planning is an important part of the overall management process. Prof. H.S. DIKKAR Assistant professor, Department Of Civil Engineering, Sandip Institute of Engineering & Management, Nashik, Maharashtra, India. © 2023, IRJET | Impact Factor value: 8.226 | ISO 9001:2008 Certified Journal | Page 1357