SlideShare a Scribd company logo
1 of 41
Download to read offline
Engineering Design Process 3rd Edition Haik SOLUTIONS MANUAL
Full download:
https://testbanklive.com/download/engineering-design-process-3rd-edition-haik-
solutions-manual/
Chapter 2
1. Table 2.3 breaks down the number of major jobs or activities involved in painting a two-
story house.
(a) Develop a CPM network.
(b) Determine the critical path of the network.
A-C-D-E-G-H-J-K
(c) Determine the expected project’s duration time period.
26 weeks
TABLE 2.3 Problem 1
Activity Identification Predecessor Duration
Contract signed A — 2
Purchase of material B A 2
Ladder and staging in site C A 2
Preparation of surface D C,B 5
Base coat complete E D 6
Base coat inspected F E 2
Trim coat complete G E 5
Trim coat inspected H G,F 2
Final inspection I H 2
Removal of staging J H 2
Final cleanup K I,J 2
2. Assume that the optimistic, most likely, and pessimistic activity times are as given in
Table 2.4.
(a) Complete the table.
Te =
Use s =
To + 4Tm +Tp
6
Tp -To
6
V =s 2
(b) Determine the probability of finishing the job in 32 weeks.
Z =
D -Te
=
32 -32.33
= -0.07
s 4.66
TABLE 2.4 Problem 2
Pessimistic Most Likely Optimistic Expected
Time
Variance
3 2 1 2 0.11
3 2 1 2 0.11
3 2 1 2 0.11
7 5 3 5 0.44
9 6 4 6.17 0.69
3 2 1 2 0.11
7 5 4 5.17 0.25
3 2 1 2 0.11
3 2 1 2 0.11
3 2 1 2 0.11
3 2 1 2 0.11
3. You should work on this activity during lab hours.
(a) Develop a CPM network and determine the critical path for the events defined in
the Gantt chart in Figure 2.1.
(b) Develop a Gantt chart for the events defined in Table 2.2.
1 2 3 4 5 6 7 8 9 10 11 12 13
Task A
Task B
Task C
Task D
Task E
Task F
Task G
Task H
(c) For the events defined in Table 2.5,
i. Complete the table.
ii. Draw the PERT network.
critical path 1-4-6-14-17-18-16-19-20
iii. Determine the probability of finishing the task on time if the design due date
is later than 95 days.
Z =
D -Te
=
95-90.17
= 0.59
s 8.17
Use the table below to calculate Te and Stdev for the critical path
TABLE 2.5 Problem 3
Predecessor Optimistic Most Likely Pessimistic Expected Stdev Variance
1 3 5 8 5.17 0.83 0.69
1 4 6 9 6.17 0.83 0.69
3 3 4 5 4.00 0.33 0.11
2 2 3 4 3.00 0.33 0.11
5 3 4 5 4.00 0.33 0.11
1 8 12 14 11.67 1.00 1.00
4 14 18 21 17.83 1.17 1.36
7 5 10 14 9.83 1.50 2.25
7 5 10 14 9.83 1.50 2.25
7 5 10 14 9.83 1.50 2.25
7 5 10 14 9.83 1.50 2.25
7 5 10 14 9.83 1.50 2.25
12 4 6 10 6.33 1.00 1.00
11 4 6 10 6.33 1.00 1.00
10 4 6 10 6.33 1.00 1.00
9 4 6 10 6.33 1.00 1.00
8 4 6 10 6.33 1.00 1.00
13 10 12 18 12.67 1.33 1.78
6 16 18 24 18.67 1.33 1.78
14 7 10 15 10.33 1.33 1.78
14 10 15 22 15.33 2.00 4.00
17 5 9 9 8.33 0.67 0.44
18 4 6 8 6.00 0.67 0.44
16 6 8 12 8.33 1.00 1.00
15 3 8 12 7.83 1.50 2.25
19 3 4 5 4.00 0.33 0.11
2.7.2 Individual Activities
4. Define the following terms:
(a) CPM (Critical Path Method): Management tool that assumes that activities durations
are known with certainty
(b) Gantt chart: A chart with series of blocks that account for activities in a project during
an assigned period.
(c) PERT (Program Evaluation Review Technique): Management tool that assumes activity
durations are random
5. Assume that an engineering course term project is broken down into a number of
major jobs or activities, as shown in Table 2.6.
(a) Draw a Gantt chart.
(b) Develop a CPM network.
(c) Determine the critical path of the network.
(d) Determine the project duration time period.
TABLE 2.6 Project
Activity
Description
Activity
Identification
Immediate
Predecessor
Activity Activity Duration (Days)
Literature
collection A — 7
Literature
review B A 4
Outline
preparation C B 1
Analysis D B 10
Report writing E C 5
Typing F E 3
Revision G E 4
Final draft H G 2
Assume that, for example, the optimistic, most likely, and pessimistic activity times are
as shown in Table 2.7. Calculate each activity’s expected time and variance along with
the probability of accomplishing the design project in 2.5 weeks. In addition, calculate
each event’s earliest and latest event times.
TABLE 2.7 Activity Time Estimates (Weeks)
© 2018 Cengage Learning®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in
part.
Pessimistic Most Likely Optimistic Expected Time Variance
4 2 1 2.16 0.25
3 2 1 2 0.11
4 2 1 2.16 0.25
8 5 3 5.16 0.7
5 4 2 3.83 0.25
7 4 3 4.33 0.44
5 3 2 3.17 0.25
5 3 2 3.17 0.25
9 6 3 6 1
10 4 2 4.17 0.69
17
© 2018 Cengage Learning®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in
part.
18
Engineering Design Process Haik/Sivaloganathan/Shahin
Engineering Design
Process
Chapter 2:
Essential
Transferable
Skills
Engineering Design Process Haik/Sivaloganathan/Shahin
2.1 – Objectives
1. Identify essential, prerequisite skills for design
process.
2. Appreciate importance and dynamics of working
in teams.
3. Develop a project schedule using existing tools.
4. Practice and improve research &
communications skills.
Engineering Design Process Haik/Sivaloganathan/Shahin
© 2018 Cengage Learning®. May not be scanned, copied or duplicated, or posted to a publicly accessible
website, in whole or in part.
3
2.2 – Working in Teams
• A team is a collection of individuals
• Whose work is interdependent and
• Who are collectively responsible for a performance
outcome
• Features of a team include
• Dynamic exchange of information & resources
• Coordinated task activities
• Continuous adjustment to team & task demands
• Shared authority & accountability for performance
Engineering Design Process Haik/Sivaloganathan/Shahin
© 2018 Cengage Learning®. May not be scanned, copied or duplicated, or posted to a publicly accessible
website, in whole or in part.
4
2.2 – Working in Teams
• Teams can be formed from various model. This
textbook uses the brain model.
• 2.2.1 – Forming a team
• The Hermann model is useful for classifying
individuals into 4 basic thinking styles.
• A team composed of members with all 4
thinking styles will be successful.
• The 4 styles are analytical/logical,
organized/planning, holistic/intuitive and
social/communicative.
Engineering Design Process Haik/Sivaloganathan/Shahin
© 2018 Cengage Learning®. May not be scanned, copied or duplicated, or posted to a publicly accessible
website, in whole or in part.
5
2.2 – Working in Teams
• 2.2.2 – Dynamics of a Team
• Teams evolve according to 4 stages:
1. Forming
2. Storming
3. Norming
4. Performing
• 4 behaviors are needed for effective team work
1. Communication team behavior
2. Decision making team behavior
3. Collaboration team behavior
4. Self management team behavior
Engineering Design Process Haik/Sivaloganathan/Shahin
© 2018 Cengage Learning®. May not be scanned, copied or duplicated, or posted to a publicly accessible
website, in whole or in part.
6
2.2 – Working in Teams
• 2.2.2 – Dynamics of a Team
• An effective 4-member team can organize into the
following distinct roles:
1. Captain – skilled in self-management team
behavior
2. Chief Engineer – skilled in decision making team
behavior
3. Human Resources person – skilled in collaboration
team behavior
4. Spokesperson – skilled in communication team
behavior
Engineering Design Process Haik/Sivaloganathan/Shahin
© 2018 Cengage Learning®. May not be scanned, copied or duplicated, or posted to a publicly accessible
website, in whole or in part.
7
2.3 – Scheduling
• 2.3.1 – Gantt Chart
• The Gannt chart is a form of bar chart and is
created as follows:
1. List all project events/milestones in an ordered list
2. Estimate the time required for each event
3. List the starting & end time for each event
4. Represent this information in a bar chart
Engineering Design Process Haik/Sivaloganathan/Shahin
2.3 – Scheduling
© 2018 Cengage Learning®. May not be scanned, copied or duplicated, or posted to a publicly accessible
website, in whole or in part.
8
Engineering Design Process Haik/Sivaloganathan/Shahin
© 2018 Cengage Learning®. May not be scanned, copied or duplicated, or posted to a publicly accessible
website, in whole or in part.
9
2.3 – Scheduling
• 2.3.2 – CPM/PERT
• CPM – Critical Path Method
• PERT- Program Evaluation & Review Technique
• CPM/PERT is used over 65% of time in US
manufacturing companies
• CPM/PERT projects have following characteristics:
1. Clearly defined activities/jobs in a project
2. Activities/jobs proceed uninterrupted once started
3. Activities/tasks are independent w.r.t starting,
stopping, and performed in a prescribed sequence
4. Activities/jobs are ordered in sequential manner
Engineering Design Process Haik/Sivaloganathan/Shahin
© 2018 Cengage Learning®. May not be scanned, copied or duplicated, or posted to a publicly accessible
website, in whole or in part.
10
2.3 – Scheduling
• 2.3.3 – CPM/PERT Definitions
1. Event (node) – represented by a circle and a
number, this stands for an event such as starting
or stopping of a stage
2. Activity – effort needed to carry out a portion of
project
3. Network paths – Paths needed/used to reach
event or project termination point
4. Critical path – Longest path (w.r.t time) through
the PERT/CPM network
5. Earliest Event Time (EET) – Earliest time at which
an event occurs if preceding events completed at
schedule
Engineering Design Process Haik/Sivaloganathan/Shahin
© 2018 Cengage Learning®. May not be scanned, copied or duplicated, or posted to a publicly accessible
website, in whole or in part.
11
2.3 – Scheduling
• 2.3.3 – CPM/PERT Definitions
6. Latest Event Time (LET) – Latest time at which an
event can be reached without delaying project
completion
7. Total float – Latest time of an event minus earliest
time of preceding event and duration time of in-
between activity
Engineering Design Process Haik/Sivaloganathan/Shahin
2.3 – Scheduling
Engineering Design Process Haik/Sivaloganathan/Shahin
2.3 – Scheduling
• 2.3.4 – CPM/PERT Network Development
• The steps to develop a CPM network are:
1. Break down design into individual activities.
2. Estimate required time for each activity.
3. Determine activity sequence.
4. Construct CPM network using defined symbols.
5. Determine critical path of the network.
Engineering Design Process Haik/Sivaloganathan/Shahin
2.3 – Scheduling
• 2.3.4 – CPM/PERT Network Development
• The steps to develop a PERT network are:
1. Break down design into individual activities.
2. Determine activity sequence.
3. Construct PERT network using defined symbols.
4. Obtain expected time to perform each activity
using the formula:
Te (x 4y  z) / 6
5. Determine the critical network path.
Engineering Design Process Haik/Sivaloganathan/Shahin
2
2.3 – Scheduling
• 2.3.4 – CPM/PERT Network Development
6. Compute variance associated with expected time
of each activity with the formula
2
s2 z x
6


7. Obtain probability of accomplishing design project
on the stated date using the formula
w
T TL
Scr
Engineering Design Process Haik/Sivaloganathan/Shahin
2.3 – Scheduling
Engineering Design Process Haik/Sivaloganathan/Shahin
2.4 – Research Skills
• In the design process, research is pursued at all
stages, but especially during customer
requirement collection and market analysis
stages.
• The Big6 method identifies 6 categories of research
skills:
1. Task definition
2. Information seeking strategies
3. Location and access
4. Use of information
5. Synthesis
6. Evaluation
Engineering Design Process Haik/Sivaloganathan/Shahin
2.5 – Technical Writing & Presentation
• The end of the design process often requires a
technical report, which is disseminated to a
diverse audience.
• Readers often assume that the quality of the
report reflects the quality of the design project.
• Therefore, effective report writing is essential to
market the design to stakeholders.
Engineering Design Process Haik/Sivaloganathan/Shahin
© 2018 Cengage Learning®. May not be scanned, copied or duplicated, or posted to a publicly accessible
website, in whole or in part.
19
2.5 – Technical Writing & Presentation
• The outline of a typical report format is:
1. Cover Page – Title, Address, Author name(s)
2. Summary – Intended for broad audience, including
executives. Should have a conclusion
3. Table of Contents
4. List of figures, list of tables
5. Introduction – provides background and possibly
market analysis
6. Design Process – provides details of procedures
followed in design process
Engineering Design Process Haik/Sivaloganathan/Shahin
2.5 – Technical Writing & Presentation
• The outline of a typical report format is:
7. Discussion – contains comprehensive examination
of results. Subsections may include technical
analysis, equipment used, details of mock-up
model, procedures, details of final results etc
8. Conclusion
9. References
10. Appendices – details deemed beyond the main
scope of the report. Can contain as many
subsections as necessary
Engineering Design Process Haik/Sivaloganathan/Shahin
2.5 – Technical Writing & Presentation
• 2.5.1 – Steps in Writing a Report
1. P : Plan the Writing
2. O : Outline the Report
3. W : Write
4. E : Edit
5. R : Rewrite
Engineering Design Process Haik/Sivaloganathan/Shahin
2.5 – Technical Writing & Presentation
• 2.5.1 – Steps in Writing a Report
• Some attributes of good report writing are:
1. Objective, concise and methodical writing.
2. Deliver written material on time.
3. Strive for clarity in writing.
4. Effectively answer readers’ questions as they
arise.
5. Give a good first impression and read coherently.
6. Contain effective introduction and summary.
7. Avoid vague and superfluous phrases.
Engineering Design Process Haik/Sivaloganathan/Shahin
2.5 – Technical Writing & Presentation
• 2.5.2 – Illustration Guidelines
• Some guidelines for preparing effective
visuals/illustrations are
1. Reference all illustrations in the text.
2. Reference data sources.
3. Specify all scales, axes, units etc., and provide a
caption/title for every illustration.
4. Carefully plan placement of visuals.
5. Avoid putting too much data in one visual.
6. Spell out words rather than use abbreviations.
7. Use a list of figures if more than 5 illustrations are
present in the report.
Engineering Design Process Haik/Sivaloganathan/Shahin
2.5 – Technical Writing & Presentation
• 2.5.3 – Mechanics of Writing
• Paragraph Structure – use a topic sentence; use a
single theme per paragraph
• Sentence Length – keep sentences as short as
possible, and convey one idea per sentence
• Pronouns – Use nouns instead of ‘it’, ‘this’, ‘that’.
Avoid using personal pronouns like ‘I’, ‘you’, ‘they’.
• Spelling and Punctuation – these errors are
inexcusable in the final draft of the report
• Tense – Use past tense to describe work done in the
past. Present tense should refer to ideas and items
in the report. Future tense is for making predictions
from data, or for results applicable in the future.
Engineering Design Process Haik/Sivaloganathan/Shahin
2.6 – Presentation Style
• 2.6.1 – Objective
• Every presentation must have a clearly focused
objective.
• If everything goes perfectly, what do I intend to
achieve?
• Determine your audience and their education
level.
• Practice presentations in advance through role
playing to evaluate if your objective is being
achieved in your presentation.
Engineering Design Process Haik/Sivaloganathan/Shahin
2.6 – Presentation Style
• 2.6.2 – Oral Presentation Obstacles
• Oral presentation requires lots of creativity.
• You have to be confident in your idea/design to
effectively sell it to others.
• People tend to resist change, and may raise
objections like:
We tried it before; its never been done before; the idea is
unrealistic etc.
• Only 70% of spoken word is initially understood –
repetition and redundancy help audience
understanding.
• People like simple explanations, and tend to see
things from their own perspective.
Engineering Design Process Haik/Sivaloganathan/Shahin
2.6 – Presentation Style
• 2.6.3 – Oral Presentation Do’s and Don’ts
• Know audience thoroughly, and make eye contact
with them majority of the time.
• Stay within the allotted time.
• Avoid technical jargon. Use jokes/anecdotes etc.,
but only if you can effectively deliver them.
• Practice repeatedly in advance.
• Understand your message clearly.
• The presentation should be presented in a logical
order of messages.
• Present the material in a clever way, but not in a
cheap, sensational way.
Engineering Design Process Haik/Sivaloganathan/Shahin
2.6 – Presentation Style
• 2.6.4 – Oral Presentation Techniques
• Visual aids convey information more effectively and
efficiently than text in most cases.
• Slides should be kept under 1 minute.
• Slides should contain a single idea generally.
• Never read directly from the slide.
• Use well labeled graphs to show variations, trends
etc.
• Include title, outline and summary slides in your
presentation.
• Color should enhance communication, not distract
from it.
Engineering Design Process Haik/Sivaloganathan/Shahin
2.6 – Presentation Style
• 2.6.5 – Question & Answer Session
• Allow the questioner to complete the question
before answering.
• Avoid being argumentative.
• Avoid making questioner feel the question is stupid.
• Adjourn meeting if questions slack off.
• Thank the audience one more time after the Q&A
session.
Engineering Design Process Haik/Sivaloganathan/Shahin
Engineering Design Process 3rd Edition Haik SOLUTIONS MANUAL
Full download:
https://testbanklive.com/download/engineering-design-process-3rd-edition-haik-solutions-
manual/
People also search:
engineering design process yousef haik pdf
engineering design process book pdf
engineering design process 2nd edition haik pdf
engineering design process pdf

More Related Content

What's hot

Innovative design thinking
Innovative design thinkingInnovative design thinking
Innovative design thinkingmarionkumar
 
How to Start a Project
How to Start a ProjectHow to Start a Project
How to Start a ProjectCraig Brown
 
Roads, Infrastructure and BIM
Roads, Infrastructure and BIMRoads, Infrastructure and BIM
Roads, Infrastructure and BIMCCT International
 
Brochure BIM
Brochure BIM Brochure BIM
Brochure BIM UTHM
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management FrameworkRahul Sudame
 
Top 20 Best Project Management Software
Top 20 Best Project Management SoftwareTop 20 Best Project Management Software
Top 20 Best Project Management SoftwareMopinion
 
Digital construction for DfMA
Digital construction for DfMADigital construction for DfMA
Digital construction for DfMAStephen Au
 
Designing for Possible Futures
Designing for Possible FuturesDesigning for Possible Futures
Designing for Possible Futures1508 A/S
 
Effective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryEffective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryPMI Chennai Chapter
 
Ai in civil engineering - webinar
Ai in civil engineering  - webinarAi in civil engineering  - webinar
Ai in civil engineering - webinaranilk1000
 
"Design Thinking for Business Growth!"
"Design Thinking for Business Growth!" "Design Thinking for Business Growth!"
"Design Thinking for Business Growth!" BizCamp NI
 
Visual Design and Architecture
Visual Design and ArchitectureVisual Design and Architecture
Visual Design and ArchitectureRuth Malan
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project ManagementKris Kimmerle
 
BIM for Interior Design
BIM for Interior DesignBIM for Interior Design
BIM for Interior DesignJeff Hong
 
Project Scope Change Management
Project Scope Change ManagementProject Scope Change Management
Project Scope Change ManagementAlex Iskandar
 

What's hot (20)

Innovative design thinking
Innovative design thinkingInnovative design thinking
Innovative design thinking
 
How to Start a Project
How to Start a ProjectHow to Start a Project
How to Start a Project
 
Roads, Infrastructure and BIM
Roads, Infrastructure and BIMRoads, Infrastructure and BIM
Roads, Infrastructure and BIM
 
COE
COECOE
COE
 
Design Thinking
Design Thinking Design Thinking
Design Thinking
 
Brochure BIM
Brochure BIM Brochure BIM
Brochure BIM
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
 
Top 20 Best Project Management Software
Top 20 Best Project Management SoftwareTop 20 Best Project Management Software
Top 20 Best Project Management Software
 
Digital construction for DfMA
Digital construction for DfMADigital construction for DfMA
Digital construction for DfMA
 
Revit architecture
Revit architectureRevit architecture
Revit architecture
 
Project management
Project managementProject management
Project management
 
Designing for Possible Futures
Designing for Possible FuturesDesigning for Possible Futures
Designing for Possible Futures
 
Effective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryEffective Engineering Management in EPC Industry
Effective Engineering Management in EPC Industry
 
The role of the project manager
The role of the project managerThe role of the project manager
The role of the project manager
 
Ai in civil engineering - webinar
Ai in civil engineering  - webinarAi in civil engineering  - webinar
Ai in civil engineering - webinar
 
"Design Thinking for Business Growth!"
"Design Thinking for Business Growth!" "Design Thinking for Business Growth!"
"Design Thinking for Business Growth!"
 
Visual Design and Architecture
Visual Design and ArchitectureVisual Design and Architecture
Visual Design and Architecture
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
 
BIM for Interior Design
BIM for Interior DesignBIM for Interior Design
BIM for Interior Design
 
Project Scope Change Management
Project Scope Change ManagementProject Scope Change Management
Project Scope Change Management
 

Similar to Engineering design process 3rd edition haik solutions manual

1.2 project management by bee 2
1.2 project management by bee 21.2 project management by bee 2
1.2 project management by bee 2Narayan Mane
 
Introduction to Project Management
Introduction to Project Management Introduction to Project Management
Introduction to Project Management Joshua Miranda
 
CCI PM Processes (within PMP Process Groups and Knowledge Areas)
CCI PM Processes (within PMP Process Groups and Knowledge Areas)CCI PM Processes (within PMP Process Groups and Knowledge Areas)
CCI PM Processes (within PMP Process Groups and Knowledge Areas)Pamela Garrett
 
PROJ 586 RANK Lessons in Excellence-- proj586rank.com
PROJ 586 RANK Lessons in Excellence-- proj586rank.comPROJ 586 RANK Lessons in Excellence-- proj586rank.com
PROJ 586 RANK Lessons in Excellence-- proj586rank.comRoelofMerwe131
 
PROJ 586 RANK Achievement Education / proj586rank.com
PROJ 586 RANK Achievement Education / proj586rank.comPROJ 586 RANK Achievement Education / proj586rank.com
PROJ 586 RANK Achievement Education / proj586rank.comagathachristie149
 
PROJ 586 RANK Education Counseling--proj586rank.com
PROJ 586 RANK Education Counseling--proj586rank.comPROJ 586 RANK Education Counseling--proj586rank.com
PROJ 586 RANK Education Counseling--proj586rank.comvenkat60045
 
Project planning-and-control
Project planning-and-controlProject planning-and-control
Project planning-and-controlJatindra Malik
 
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.pptTinotendaChivese
 
ABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning SlidesABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning SlidesYousef Abugosh, PMP, MA
 
Chapter 6 project management
Chapter 6 project managementChapter 6 project management
Chapter 6 project managementShadina Shah
 

Similar to Engineering design process 3rd edition haik solutions manual (20)

Ch3 proj.mgt
Ch3 proj.mgtCh3 proj.mgt
Ch3 proj.mgt
 
Chap003
Chap003Chap003
Chap003
 
Session 5 gdas pmp study group presentation
Session 5   gdas pmp study group presentationSession 5   gdas pmp study group presentation
Session 5 gdas pmp study group presentation
 
1.2 project management by bee 2
1.2 project management by bee 21.2 project management by bee 2
1.2 project management by bee 2
 
MGT-Ch07.ppt
MGT-Ch07.pptMGT-Ch07.ppt
MGT-Ch07.ppt
 
Introduction to Project Management
Introduction to Project Management Introduction to Project Management
Introduction to Project Management
 
Project management
Project managementProject management
Project management
 
PMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptxPMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptx
 
CCI PM Processes (within PMP Process Groups and Knowledge Areas)
CCI PM Processes (within PMP Process Groups and Knowledge Areas)CCI PM Processes (within PMP Process Groups and Knowledge Areas)
CCI PM Processes (within PMP Process Groups and Knowledge Areas)
 
PROJ 586 RANK Lessons in Excellence-- proj586rank.com
PROJ 586 RANK Lessons in Excellence-- proj586rank.comPROJ 586 RANK Lessons in Excellence-- proj586rank.com
PROJ 586 RANK Lessons in Excellence-- proj586rank.com
 
PROJ 586 RANK Achievement Education / proj586rank.com
PROJ 586 RANK Achievement Education / proj586rank.comPROJ 586 RANK Achievement Education / proj586rank.com
PROJ 586 RANK Achievement Education / proj586rank.com
 
PROJ 586 Entire Course NEW
PROJ 586 Entire Course NEWPROJ 586 Entire Course NEW
PROJ 586 Entire Course NEW
 
PROJ 586 RANK Education Counseling--proj586rank.com
PROJ 586 RANK Education Counseling--proj586rank.comPROJ 586 RANK Education Counseling--proj586rank.com
PROJ 586 RANK Education Counseling--proj586rank.com
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
Project planning-and-control
Project planning-and-controlProject planning-and-control
Project planning-and-control
 
Ms project training ver 01
Ms project training ver 01Ms project training ver 01
Ms project training ver 01
 
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
 
ABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning SlidesABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning Slides
 
Chapter 6 project management
Chapter 6 project managementChapter 6 project management
Chapter 6 project management
 

Recently uploaded

Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeThiyagu K
 
Micromeritics - Fundamental and Derived Properties of Powders
Micromeritics - Fundamental and Derived Properties of PowdersMicromeritics - Fundamental and Derived Properties of Powders
Micromeritics - Fundamental and Derived Properties of PowdersChitralekhaTherkar
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingTechSoup
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppCeline George
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsKarinaGenton
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxRoyAbrique
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfUmakantAnnand
 

Recently uploaded (20)

Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
Micromeritics - Fundamental and Derived Properties of Powders
Micromeritics - Fundamental and Derived Properties of PowdersMicromeritics - Fundamental and Derived Properties of Powders
Micromeritics - Fundamental and Derived Properties of Powders
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
Staff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSDStaff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSD
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website App
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its Characteristics
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.Compdf
 

Engineering design process 3rd edition haik solutions manual

  • 1. Engineering Design Process 3rd Edition Haik SOLUTIONS MANUAL Full download: https://testbanklive.com/download/engineering-design-process-3rd-edition-haik- solutions-manual/ Chapter 2 1. Table 2.3 breaks down the number of major jobs or activities involved in painting a two- story house. (a) Develop a CPM network. (b) Determine the critical path of the network. A-C-D-E-G-H-J-K (c) Determine the expected project’s duration time period. 26 weeks TABLE 2.3 Problem 1 Activity Identification Predecessor Duration Contract signed A — 2 Purchase of material B A 2 Ladder and staging in site C A 2 Preparation of surface D C,B 5
  • 2. Base coat complete E D 6 Base coat inspected F E 2
  • 3. Trim coat complete G E 5 Trim coat inspected H G,F 2 Final inspection I H 2 Removal of staging J H 2 Final cleanup K I,J 2 2. Assume that the optimistic, most likely, and pessimistic activity times are as given in Table 2.4. (a) Complete the table. Te = Use s = To + 4Tm +Tp 6 Tp -To 6 V =s 2 (b) Determine the probability of finishing the job in 32 weeks. Z = D -Te = 32 -32.33 = -0.07 s 4.66 TABLE 2.4 Problem 2 Pessimistic Most Likely Optimistic Expected Time Variance 3 2 1 2 0.11 3 2 1 2 0.11 3 2 1 2 0.11 7 5 3 5 0.44
  • 4. 9 6 4 6.17 0.69 3 2 1 2 0.11 7 5 4 5.17 0.25 3 2 1 2 0.11 3 2 1 2 0.11 3 2 1 2 0.11 3 2 1 2 0.11 3. You should work on this activity during lab hours. (a) Develop a CPM network and determine the critical path for the events defined in the Gantt chart in Figure 2.1.
  • 5. (b) Develop a Gantt chart for the events defined in Table 2.2. 1 2 3 4 5 6 7 8 9 10 11 12 13 Task A Task B Task C Task D Task E Task F Task G Task H (c) For the events defined in Table 2.5, i. Complete the table. ii. Draw the PERT network.
  • 6. critical path 1-4-6-14-17-18-16-19-20 iii. Determine the probability of finishing the task on time if the design due date is later than 95 days. Z = D -Te = 95-90.17 = 0.59 s 8.17 Use the table below to calculate Te and Stdev for the critical path TABLE 2.5 Problem 3 Predecessor Optimistic Most Likely Pessimistic Expected Stdev Variance 1 3 5 8 5.17 0.83 0.69 1 4 6 9 6.17 0.83 0.69 3 3 4 5 4.00 0.33 0.11 2 2 3 4 3.00 0.33 0.11 5 3 4 5 4.00 0.33 0.11 1 8 12 14 11.67 1.00 1.00 4 14 18 21 17.83 1.17 1.36 7 5 10 14 9.83 1.50 2.25 7 5 10 14 9.83 1.50 2.25 7 5 10 14 9.83 1.50 2.25 7 5 10 14 9.83 1.50 2.25
  • 7. 7 5 10 14 9.83 1.50 2.25 12 4 6 10 6.33 1.00 1.00 11 4 6 10 6.33 1.00 1.00 10 4 6 10 6.33 1.00 1.00 9 4 6 10 6.33 1.00 1.00 8 4 6 10 6.33 1.00 1.00 13 10 12 18 12.67 1.33 1.78 6 16 18 24 18.67 1.33 1.78 14 7 10 15 10.33 1.33 1.78 14 10 15 22 15.33 2.00 4.00 17 5 9 9 8.33 0.67 0.44 18 4 6 8 6.00 0.67 0.44 16 6 8 12 8.33 1.00 1.00 15 3 8 12 7.83 1.50 2.25 19 3 4 5 4.00 0.33 0.11 2.7.2 Individual Activities 4. Define the following terms: (a) CPM (Critical Path Method): Management tool that assumes that activities durations are known with certainty (b) Gantt chart: A chart with series of blocks that account for activities in a project during an assigned period. (c) PERT (Program Evaluation Review Technique): Management tool that assumes activity durations are random 5. Assume that an engineering course term project is broken down into a number of major jobs or activities, as shown in Table 2.6. (a) Draw a Gantt chart.
  • 8. (b) Develop a CPM network. (c) Determine the critical path of the network. (d) Determine the project duration time period.
  • 9. TABLE 2.6 Project Activity Description Activity Identification Immediate Predecessor Activity Activity Duration (Days) Literature collection A — 7 Literature review B A 4 Outline preparation C B 1 Analysis D B 10 Report writing E C 5 Typing F E 3 Revision G E 4 Final draft H G 2 Assume that, for example, the optimistic, most likely, and pessimistic activity times are as shown in Table 2.7. Calculate each activity’s expected time and variance along with the probability of accomplishing the design project in 2.5 weeks. In addition, calculate each event’s earliest and latest event times.
  • 10. TABLE 2.7 Activity Time Estimates (Weeks) © 2018 Cengage Learning®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part. Pessimistic Most Likely Optimistic Expected Time Variance 4 2 1 2.16 0.25 3 2 1 2 0.11 4 2 1 2.16 0.25 8 5 3 5.16 0.7 5 4 2 3.83 0.25 7 4 3 4.33 0.44 5 3 2 3.17 0.25 5 3 2 3.17 0.25 9 6 3 6 1 10 4 2 4.17 0.69 17
  • 11. © 2018 Cengage Learning®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part. 18
  • 12. Engineering Design Process Haik/Sivaloganathan/Shahin Engineering Design Process Chapter 2: Essential Transferable Skills
  • 13. Engineering Design Process Haik/Sivaloganathan/Shahin 2.1 – Objectives 1. Identify essential, prerequisite skills for design process. 2. Appreciate importance and dynamics of working in teams. 3. Develop a project schedule using existing tools. 4. Practice and improve research & communications skills.
  • 14. Engineering Design Process Haik/Sivaloganathan/Shahin © 2018 Cengage Learning®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part. 3 2.2 – Working in Teams • A team is a collection of individuals • Whose work is interdependent and • Who are collectively responsible for a performance outcome • Features of a team include • Dynamic exchange of information & resources • Coordinated task activities • Continuous adjustment to team & task demands • Shared authority & accountability for performance
  • 15. Engineering Design Process Haik/Sivaloganathan/Shahin © 2018 Cengage Learning®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part. 4 2.2 – Working in Teams • Teams can be formed from various model. This textbook uses the brain model. • 2.2.1 – Forming a team • The Hermann model is useful for classifying individuals into 4 basic thinking styles. • A team composed of members with all 4 thinking styles will be successful. • The 4 styles are analytical/logical, organized/planning, holistic/intuitive and social/communicative.
  • 16. Engineering Design Process Haik/Sivaloganathan/Shahin © 2018 Cengage Learning®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part. 5 2.2 – Working in Teams • 2.2.2 – Dynamics of a Team • Teams evolve according to 4 stages: 1. Forming 2. Storming 3. Norming 4. Performing • 4 behaviors are needed for effective team work 1. Communication team behavior 2. Decision making team behavior 3. Collaboration team behavior 4. Self management team behavior
  • 17. Engineering Design Process Haik/Sivaloganathan/Shahin © 2018 Cengage Learning®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part. 6 2.2 – Working in Teams • 2.2.2 – Dynamics of a Team • An effective 4-member team can organize into the following distinct roles: 1. Captain – skilled in self-management team behavior 2. Chief Engineer – skilled in decision making team behavior 3. Human Resources person – skilled in collaboration team behavior 4. Spokesperson – skilled in communication team behavior
  • 18. Engineering Design Process Haik/Sivaloganathan/Shahin © 2018 Cengage Learning®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part. 7 2.3 – Scheduling • 2.3.1 – Gantt Chart • The Gannt chart is a form of bar chart and is created as follows: 1. List all project events/milestones in an ordered list 2. Estimate the time required for each event 3. List the starting & end time for each event 4. Represent this information in a bar chart
  • 19. Engineering Design Process Haik/Sivaloganathan/Shahin 2.3 – Scheduling © 2018 Cengage Learning®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part. 8
  • 20. Engineering Design Process Haik/Sivaloganathan/Shahin © 2018 Cengage Learning®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part. 9 2.3 – Scheduling • 2.3.2 – CPM/PERT • CPM – Critical Path Method • PERT- Program Evaluation & Review Technique • CPM/PERT is used over 65% of time in US manufacturing companies • CPM/PERT projects have following characteristics: 1. Clearly defined activities/jobs in a project 2. Activities/jobs proceed uninterrupted once started 3. Activities/tasks are independent w.r.t starting, stopping, and performed in a prescribed sequence 4. Activities/jobs are ordered in sequential manner
  • 21. Engineering Design Process Haik/Sivaloganathan/Shahin © 2018 Cengage Learning®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part. 10 2.3 – Scheduling • 2.3.3 – CPM/PERT Definitions 1. Event (node) – represented by a circle and a number, this stands for an event such as starting or stopping of a stage 2. Activity – effort needed to carry out a portion of project 3. Network paths – Paths needed/used to reach event or project termination point 4. Critical path – Longest path (w.r.t time) through the PERT/CPM network 5. Earliest Event Time (EET) – Earliest time at which an event occurs if preceding events completed at schedule
  • 22. Engineering Design Process Haik/Sivaloganathan/Shahin © 2018 Cengage Learning®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part. 11 2.3 – Scheduling • 2.3.3 – CPM/PERT Definitions 6. Latest Event Time (LET) – Latest time at which an event can be reached without delaying project completion 7. Total float – Latest time of an event minus earliest time of preceding event and duration time of in- between activity
  • 23. Engineering Design Process Haik/Sivaloganathan/Shahin 2.3 – Scheduling
  • 24. Engineering Design Process Haik/Sivaloganathan/Shahin 2.3 – Scheduling • 2.3.4 – CPM/PERT Network Development • The steps to develop a CPM network are: 1. Break down design into individual activities. 2. Estimate required time for each activity. 3. Determine activity sequence. 4. Construct CPM network using defined symbols. 5. Determine critical path of the network.
  • 25. Engineering Design Process Haik/Sivaloganathan/Shahin 2.3 – Scheduling • 2.3.4 – CPM/PERT Network Development • The steps to develop a PERT network are: 1. Break down design into individual activities. 2. Determine activity sequence. 3. Construct PERT network using defined symbols. 4. Obtain expected time to perform each activity using the formula: Te (x 4y  z) / 6 5. Determine the critical network path.
  • 26. Engineering Design Process Haik/Sivaloganathan/Shahin 2 2.3 – Scheduling • 2.3.4 – CPM/PERT Network Development 6. Compute variance associated with expected time of each activity with the formula 2 s2 z x 6   7. Obtain probability of accomplishing design project on the stated date using the formula w T TL Scr
  • 27. Engineering Design Process Haik/Sivaloganathan/Shahin 2.3 – Scheduling
  • 28. Engineering Design Process Haik/Sivaloganathan/Shahin 2.4 – Research Skills • In the design process, research is pursued at all stages, but especially during customer requirement collection and market analysis stages. • The Big6 method identifies 6 categories of research skills: 1. Task definition 2. Information seeking strategies 3. Location and access 4. Use of information 5. Synthesis 6. Evaluation
  • 29. Engineering Design Process Haik/Sivaloganathan/Shahin 2.5 – Technical Writing & Presentation • The end of the design process often requires a technical report, which is disseminated to a diverse audience. • Readers often assume that the quality of the report reflects the quality of the design project. • Therefore, effective report writing is essential to market the design to stakeholders.
  • 30. Engineering Design Process Haik/Sivaloganathan/Shahin © 2018 Cengage Learning®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part. 19 2.5 – Technical Writing & Presentation • The outline of a typical report format is: 1. Cover Page – Title, Address, Author name(s) 2. Summary – Intended for broad audience, including executives. Should have a conclusion 3. Table of Contents 4. List of figures, list of tables 5. Introduction – provides background and possibly market analysis 6. Design Process – provides details of procedures followed in design process
  • 31. Engineering Design Process Haik/Sivaloganathan/Shahin 2.5 – Technical Writing & Presentation • The outline of a typical report format is: 7. Discussion – contains comprehensive examination of results. Subsections may include technical analysis, equipment used, details of mock-up model, procedures, details of final results etc 8. Conclusion 9. References 10. Appendices – details deemed beyond the main scope of the report. Can contain as many subsections as necessary
  • 32. Engineering Design Process Haik/Sivaloganathan/Shahin 2.5 – Technical Writing & Presentation • 2.5.1 – Steps in Writing a Report 1. P : Plan the Writing 2. O : Outline the Report 3. W : Write 4. E : Edit 5. R : Rewrite
  • 33. Engineering Design Process Haik/Sivaloganathan/Shahin 2.5 – Technical Writing & Presentation • 2.5.1 – Steps in Writing a Report • Some attributes of good report writing are: 1. Objective, concise and methodical writing. 2. Deliver written material on time. 3. Strive for clarity in writing. 4. Effectively answer readers’ questions as they arise. 5. Give a good first impression and read coherently. 6. Contain effective introduction and summary. 7. Avoid vague and superfluous phrases.
  • 34. Engineering Design Process Haik/Sivaloganathan/Shahin 2.5 – Technical Writing & Presentation • 2.5.2 – Illustration Guidelines • Some guidelines for preparing effective visuals/illustrations are 1. Reference all illustrations in the text. 2. Reference data sources. 3. Specify all scales, axes, units etc., and provide a caption/title for every illustration. 4. Carefully plan placement of visuals. 5. Avoid putting too much data in one visual. 6. Spell out words rather than use abbreviations. 7. Use a list of figures if more than 5 illustrations are present in the report.
  • 35. Engineering Design Process Haik/Sivaloganathan/Shahin 2.5 – Technical Writing & Presentation • 2.5.3 – Mechanics of Writing • Paragraph Structure – use a topic sentence; use a single theme per paragraph • Sentence Length – keep sentences as short as possible, and convey one idea per sentence • Pronouns – Use nouns instead of ‘it’, ‘this’, ‘that’. Avoid using personal pronouns like ‘I’, ‘you’, ‘they’. • Spelling and Punctuation – these errors are inexcusable in the final draft of the report • Tense – Use past tense to describe work done in the past. Present tense should refer to ideas and items in the report. Future tense is for making predictions from data, or for results applicable in the future.
  • 36. Engineering Design Process Haik/Sivaloganathan/Shahin 2.6 – Presentation Style • 2.6.1 – Objective • Every presentation must have a clearly focused objective. • If everything goes perfectly, what do I intend to achieve? • Determine your audience and their education level. • Practice presentations in advance through role playing to evaluate if your objective is being achieved in your presentation.
  • 37. Engineering Design Process Haik/Sivaloganathan/Shahin 2.6 – Presentation Style • 2.6.2 – Oral Presentation Obstacles • Oral presentation requires lots of creativity. • You have to be confident in your idea/design to effectively sell it to others. • People tend to resist change, and may raise objections like: We tried it before; its never been done before; the idea is unrealistic etc. • Only 70% of spoken word is initially understood – repetition and redundancy help audience understanding. • People like simple explanations, and tend to see things from their own perspective.
  • 38. Engineering Design Process Haik/Sivaloganathan/Shahin 2.6 – Presentation Style • 2.6.3 – Oral Presentation Do’s and Don’ts • Know audience thoroughly, and make eye contact with them majority of the time. • Stay within the allotted time. • Avoid technical jargon. Use jokes/anecdotes etc., but only if you can effectively deliver them. • Practice repeatedly in advance. • Understand your message clearly. • The presentation should be presented in a logical order of messages. • Present the material in a clever way, but not in a cheap, sensational way.
  • 39. Engineering Design Process Haik/Sivaloganathan/Shahin 2.6 – Presentation Style • 2.6.4 – Oral Presentation Techniques • Visual aids convey information more effectively and efficiently than text in most cases. • Slides should be kept under 1 minute. • Slides should contain a single idea generally. • Never read directly from the slide. • Use well labeled graphs to show variations, trends etc. • Include title, outline and summary slides in your presentation. • Color should enhance communication, not distract from it.
  • 40. Engineering Design Process Haik/Sivaloganathan/Shahin 2.6 – Presentation Style • 2.6.5 – Question & Answer Session • Allow the questioner to complete the question before answering. • Avoid being argumentative. • Avoid making questioner feel the question is stupid. • Adjourn meeting if questions slack off. • Thank the audience one more time after the Q&A session.
  • 41. Engineering Design Process Haik/Sivaloganathan/Shahin Engineering Design Process 3rd Edition Haik SOLUTIONS MANUAL Full download: https://testbanklive.com/download/engineering-design-process-3rd-edition-haik-solutions- manual/ People also search: engineering design process yousef haik pdf engineering design process book pdf engineering design process 2nd edition haik pdf engineering design process pdf