Submit Search
Upload
Tracking and managing construction projects
•
0 likes
•
93 views
AI-enhanced title
IRJET Journal
Follow
https://irjet.net/archives/V4/i7/IRJET-V4I7120.pdf
Read less
Read more
Engineering
Report
Share
Report
Share
1 of 6
Download now
Download to read offline
Recommended
IRJET- Scheduling and Labour Management for Residential Building Project usin...
IRJET- Scheduling and Labour Management for Residential Building Project usin...
IRJET Journal
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
IRJET Journal
Methodologies of Project Progress Measurement
Methodologies of Project Progress Measurement
Amit Kumar Senapati, PMP®
Use of forward pass and backward pass in primavera
Use of forward pass and backward pass in primavera
Amit Kumar Senapati, PMP®
Outage planning
Outage planning
Amit Kumar Senapati, PMP®
edSe275 ms project-assignment
edSe275 ms project-assignment
harinathinfotech
Project planning and scheduling
Project planning and scheduling
Muhammad Umar Farooq
Construction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential Building
SHAZEBALIKHAN1
Recommended
IRJET- Scheduling and Labour Management for Residential Building Project usin...
IRJET- Scheduling and Labour Management for Residential Building Project usin...
IRJET Journal
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
IRJET Journal
Methodologies of Project Progress Measurement
Methodologies of Project Progress Measurement
Amit Kumar Senapati, PMP®
Use of forward pass and backward pass in primavera
Use of forward pass and backward pass in primavera
Amit Kumar Senapati, PMP®
Outage planning
Outage planning
Amit Kumar Senapati, PMP®
edSe275 ms project-assignment
edSe275 ms project-assignment
harinathinfotech
Project planning and scheduling
Project planning and scheduling
Muhammad Umar Farooq
Construction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential Building
SHAZEBALIKHAN1
Project controls
Project controls
Ashok Kumar
Project scheduling and tracking
Project scheduling and tracking
yenohhoney
ppt for primevera
ppt for primevera
sneha saranya
20320130405009
20320130405009
IAEME Publication
Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...
Shabaz Khan
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
IRJET Journal
construction project managment_civileng
construction project managment_civileng
sulaiman khan
Project typed
Project typed
Rahul
Introduction - organization
Introduction - organization
SOPUGent
Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...
Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...
Ahmed Fouad, MCIArb, PMP, SP, RMP
IRJET- Value Management
IRJET- Value Management
IRJET Journal
Approaches to project control
Approaches to project control
NITISH SADOTRA
Primavera p3 [compatibility mode]
Primavera p3 [compatibility mode]
Rahul
H1303055462
H1303055462
IOSR Journals
project monitoring and control
project monitoring and control
ChandraShekhar Patel
Introduction - organization
Introduction - organization
Jolien Coenraets
012 bussiness planning process
012 bussiness planning process
Dr Fereidoun Dejahang
EVMS for Commercial projects
EVMS for Commercial projects
Glen Alleman
Understanding p6 dates
Understanding p6 dates
krunalplanning
Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...
ijtsrd
Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...
IRJET Journal
Tracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value Management
IRJET Journal
More Related Content
What's hot
Project controls
Project controls
Ashok Kumar
Project scheduling and tracking
Project scheduling and tracking
yenohhoney
ppt for primevera
ppt for primevera
sneha saranya
20320130405009
20320130405009
IAEME Publication
Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...
Shabaz Khan
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
IRJET Journal
construction project managment_civileng
construction project managment_civileng
sulaiman khan
Project typed
Project typed
Rahul
Introduction - organization
Introduction - organization
SOPUGent
Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...
Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...
Ahmed Fouad, MCIArb, PMP, SP, RMP
IRJET- Value Management
IRJET- Value Management
IRJET Journal
Approaches to project control
Approaches to project control
NITISH SADOTRA
Primavera p3 [compatibility mode]
Primavera p3 [compatibility mode]
Rahul
H1303055462
H1303055462
IOSR Journals
project monitoring and control
project monitoring and control
ChandraShekhar Patel
Introduction - organization
Introduction - organization
Jolien Coenraets
012 bussiness planning process
012 bussiness planning process
Dr Fereidoun Dejahang
EVMS for Commercial projects
EVMS for Commercial projects
Glen Alleman
Understanding p6 dates
Understanding p6 dates
krunalplanning
Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...
ijtsrd
What's hot
(20)
Project controls
Project controls
Project scheduling and tracking
Project scheduling and tracking
ppt for primevera
ppt for primevera
20320130405009
20320130405009
Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
construction project managment_civileng
construction project managment_civileng
Project typed
Project typed
Introduction - organization
Introduction - organization
Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...
Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...
IRJET- Value Management
IRJET- Value Management
Approaches to project control
Approaches to project control
Primavera p3 [compatibility mode]
Primavera p3 [compatibility mode]
H1303055462
H1303055462
project monitoring and control
project monitoring and control
Introduction - organization
Introduction - organization
012 bussiness planning process
012 bussiness planning process
EVMS for Commercial projects
EVMS for Commercial projects
Understanding p6 dates
Understanding p6 dates
Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...
Similar to Tracking and managing construction projects
Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...
IRJET Journal
Tracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value Management
IRJET Journal
Project Scheduling of a High-rise Building using Primavera P6
Project Scheduling of a High-rise Building using Primavera P6
IRJET Journal
EVM Without Quality is Unsuitable for Software Project & Program Management
EVM Without Quality is Unsuitable for Software Project & Program Management
IRJET Journal
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET Journal
IRJET- Optimization of Time and Cost of Building Construction using Fast ...
IRJET- Optimization of Time and Cost of Building Construction using Fast ...
IRJET Journal
Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...
Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...
IRJET Journal
IRJET- Optimized Project Planning and Scheduling of Multistorey Building
IRJET- Optimized Project Planning and Scheduling of Multistorey Building
IRJET Journal
Finance management in construction site
Finance management in construction site
SHAHIDBASHIRMALIK
IIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction Project
IRJET Journal
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET Journal
IRJET- Planning, Scheduling, and Optimization of Labor Resources in the C...
IRJET- Planning, Scheduling, and Optimization of Labor Resources in the C...
IRJET Journal
Application of Building Information Modelling Software’s for Planning and Sch...
Application of Building Information Modelling Software’s for Planning and Sch...
IRJET Journal
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET Journal
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET Journal
COST CONTROL AND TRACKING OF A BUILDING BY EARNED VALUE METHOD
COST CONTROL AND TRACKING OF A BUILDING BY EARNED VALUE METHOD
International Journal of Technical Research & Application
iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...
IRJET Journal
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
IRJET Journal
Study of Probability Distributions of Cpi and Spi in Earned Value Analysis
Study of Probability Distributions of Cpi and Spi in Earned Value Analysis
theijes
Earned Value Management for Design and Construction Project
Earned Value Management for Design and Construction Project
ijtsrd
Similar to Tracking and managing construction projects
(20)
Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...
Tracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value Management
Project Scheduling of a High-rise Building using Primavera P6
Project Scheduling of a High-rise Building using Primavera P6
EVM Without Quality is Unsuitable for Software Project & Program Management
EVM Without Quality is Unsuitable for Software Project & Program Management
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET- Optimization of Time and Cost of Building Construction using Fast ...
IRJET- Optimization of Time and Cost of Building Construction using Fast ...
Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...
Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...
IRJET- Optimized Project Planning and Scheduling of Multistorey Building
IRJET- Optimized Project Planning and Scheduling of Multistorey Building
Finance management in construction site
Finance management in construction site
IIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction Project
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning, Scheduling, and Optimization of Labor Resources in the C...
IRJET- Planning, Scheduling, and Optimization of Labor Resources in the C...
Application of Building Information Modelling Software’s for Planning and Sch...
Application of Building Information Modelling Software’s for Planning and Sch...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
COST CONTROL AND TRACKING OF A BUILDING BY EARNED VALUE METHOD
COST CONTROL AND TRACKING OF A BUILDING BY EARNED VALUE METHOD
iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
Study of Probability Distributions of Cpi and Spi in Earned Value Analysis
Study of Probability Distributions of Cpi and Spi in Earned Value Analysis
Earned Value Management for Design and Construction Project
Earned Value Management for Design and Construction Project
More from IRJET Journal
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
IRJET Journal
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
IRJET Journal
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
IRJET Journal
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
IRJET Journal
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
IRJET Journal
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
IRJET Journal
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
IRJET Journal
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
IRJET Journal
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
IRJET Journal
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
IRJET Journal
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
IRJET Journal
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
IRJET Journal
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
IRJET Journal
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
IRJET Journal
React based fullstack edtech web application
React based fullstack edtech web application
IRJET Journal
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
IRJET Journal
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
IRJET Journal
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
IRJET Journal
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
IRJET Journal
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
IRJET Journal
More from IRJET Journal
(20)
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
React based fullstack edtech web application
React based fullstack edtech web application
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Recently uploaded
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
Suhani Kapoor
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
KartikeyaDwivedi3
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
britheesh05
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
GDSCAESB
Internship report on mechanical engineering
Internship report on mechanical engineering
malavadedarshan25
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
roselinkalist12
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
misbanausheenparvam
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
9953056974 Low Rate Call Girls In Saket, Delhi NCR
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
hassan khalil
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
me23b1001
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ
power system scada applications and uses
power system scada applications and uses
DevarapalliHaritha
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
asadnawaz62
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
jennyeacort
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
RajaP95
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
Asst.prof M.Gokilavani
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
João Esperancinha
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
PoojaBan
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
Tsuyoshi Horigome
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
Asst.prof M.Gokilavani
Recently uploaded
(20)
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
Internship report on mechanical engineering
Internship report on mechanical engineering
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
power system scada applications and uses
power system scada applications and uses
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
Tracking and managing construction projects
1.
International Research Journal
of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 677 TRACKING AND MANAGEMENT OF CONSTRUCTION PROJECTS USING PRIMAVERA Suchithra L1, Anne Ligoria S2 1PG Student, Department of Civil Engineering, Jerusalem College of Engineering, Tamil Nadu, India 2Professor of Civil Engineering Department and Dean- Academics, Jerusalem College of Engineering, Tamil Nadu, India ----------------------------------------------------------------------------***-------------------------------------------------------------------------- Abstract: Construction industry is an integral component of a nation’s infrastructure and industrial growth. Eventhough construction industry is the second largest industry in India, the growth of this industry has been differential across the nation. Proper planning, scheduling, tracking and application are the major parameters in construction industry. This study involves tracking of the ongoing construction and management of a new building using primavera. The tracking of the project during construction is necessary to control the variance in the project and to know the forecasting cost of the project. Construction planning and scheduling is one of the important tool in construction. In the present study the tracking and forecasting was done by a method called Earned Value Management (EVM). The importance of construction management has been reviewed and the tracking of ongoing residential building as well as the management of new construction of an apartment building has been done. Key Words: Planning, Scheduling, Construction Management, Tracking, Primavera, EVM 1. INTRODUCTION The construction industry has been developed rapidly from the early days. One of the development was planning and scheduling using software. In construction industry, mostly used software for the planning and scheduling are MS Project and Primavera. But in India the use of the Primavera is rare and most of the construction has been taken place without the use of software which leads to extension of the duration and the cost of the project. In this study, the use and need of the project management software has been explained considering residential building and apartment building. The tracking was done in residential building and the management of the apartment building up to planning process using the project management software Primavera P6.R8.2. 1.1. PROJECT MANAGEMENT Planning is important for any work to reach its goal and Proper Planning leads to excellent result. The three basic things needed for the planning of construction projects are scope, time and cost. The efficient planning in a construction project involves project management plan, managing scope, collecting requirements, creating WBS, defining activities and their relationships, sequencing the activities, duration of the activities and estimation. If any risk arises then steps are taken to minimize or remove the risk. 1.2. EARNED VALUE MANAGEMENT Earned Value Management is the most frequently used performance measurement method. EVA looks at schedule, cost and scope performance measurements of a project together. To perform the earned value calculations, it is needed to determine the following three parameters: Planned Value (PV) Earned Value (EV) Actual Cost (AC) The planned value is the cost of the work that has been budgeted for an activity or for the project during a certain time period. The estimations and budgets are established during Planning Process. The Actual Cost is the cost of the work including direct and indirect costs. The Earned Value is the value of work that has been completed to date. The EVM is categorized as shown in Fig.1
2.
International Research Journal
of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 678 Fig-1: EVM Types 1.2.1. TRACKING: Planning is important for the success of the project. To know the project has been executed according to the planning, tracking has been takes place. Tracking helps to stick to the plan during execution. The tracking is the process of analyses the updated schedule whether the cost and units of the project are beyond or ahead or equal of the planning. The tracking is done by EVM (Earned Value Management). Tracking is comes under the process of monitoring and controlling of the construction project. Tracking of the project can be done after updating the project by monitoring. If the project is deviated from the schedule or cost it can easily be identified and controlling can be done. SV = EV - PV CV = EV – AC SPI = EV / PV CPI = EV / AC a. Schedule Variance Cases Case 1: if SV = 0 ; as per schedule, SPI =1 Case 2: if SV = -ve ; behind schedule, SPI <1 Case 3: if SV = +ve ; ahead schedule, SPI >1 b. Cost Variance Cases Case 1: if CV = 0 ; as per budget, CPI =1 Case 2: if CV = -ve ; budget at over run, CPI <1 Case 3: if CV = +ve ; budget at under run, CPI >1 1.2.2. FORECASTING OF THE PROJECT The forecasting is also done under EVM which helps us to know the forecasting end date of the project. It determines the estimation cost of the project during tracking and also the needed cost to complete the project till the end of the project. It helps to know the future performance of a construction project. EVM Tracking Schedule Variance (SV) Cost Variance (CV) Schedule Performance Index (SPI) Cost Performance Index (CPI) Forecasting Estimate to Complete (ETC) Estimate at Completion (EAC) Variance at Completion (VAC) Budget At Completion (BAC)
3.
International Research Journal
of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 679 Case 1: if variance is not going to continue ETC = BAC – EV EAC = AC + ETC EAC = AC + [BAC – EV] VAC = BAC – EAC Case 2: if variance is going to continue but affects only cost ETC = [BAC – EV] / CPI EAC = AC + ETC VAC = BAC – EAC Case 3: if variance is going to continue but affects the cost and schedule ETC = [BAC - EV] / [CPI * SPI] EAC = AC + ETC VAC = BAC – EAC where, PV is Planned Value EV is Earned Value AC is Actual Cost SPI is Schedule Performance Index CPI is Cost Performance Index SV is Schedule Variance CV is Cost Variance ETC is Estimate to Complete EAC is Estimate to Completion VAC is Variance at Completion BAC is Budget at Completion 2. APPLICATION OF PRIMAVERA SOFTWARE The study involves tracking of ongoing construction project and management of new construction project of residential and apartment buildings respectively using the project management software Primavera. 2.1. TRACKING OF ONGOING CONSTRUCTION PROJECT Tracking of the construction projects involves following steps: Getting Information of the Project from the Organisation Entering the Details of the Project in Primavera Monitoring the Execution of the Project Entering the Planned and the Actual Cost Tracking the Project Forecasting the Project Report and Conclusion 2.2. CONSTRUCTION MANAGEMENT OF NEW PROJECT The management of the new construction project in Primavera software involves following steps: New Building Project Calendar Creation
4.
International Research Journal
of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 680 Work Breakdown Structure Define Activities Applying Durations Sequence of Activities Finding the Critical Path Creation of Resources Assigning the Resources into a task Analysing the Resources Levelling the Resources Creating Baseline Develop the Schedule Report Preparation 3. PROGRESS OF TRACKING OF A CONSTRUCTION PROJECT The tracking of an ongoing project is located in Chennai. It is residential project. The plot area of the project is 2322 sq.ft and the built up area is 1357sq.ft. It is a G+1 building. After the drawing designs the project started with the preparation of documents on May 2nd 2016. The project contractor said the project would be finished in 9 months for the construction of the building which starts in Sep 2nd 2016 and the cost of the project is Rs.55 Lakhs. But during the scheduling of the project using management software Primavera the end date of the project was 24th Aug 2017 which is nearly to 1 year. The cost of the project is Rs.5842311.52 excludes the indirect cost of the building. The tracking has been done in four months. The Table.1 shows the EVM parameters of tracking in four months Table – 1: EVM of the tracking of the ongoing project EVM Parameter Tracking 1 Jan 31st 2017 Tracking 2 Feb 28th 2017 Tracking 3 Mar 31st 2017 Tracking 4 April 30th 2017 Budget at Completion Rs.5842311.52 Rs.5842311.52 Rs.5842311.52 Rs.5842311.52 Planned value Rs.1200890.29 Rs.1501963 Rs.2641957 Rs.3238450 Earned Value Rs.1199770.29 Rs.1392929 Rs.1647009 Rs.2689678 Actual Cost Rs. 1225770.29 Rs.1442429 Rs.1702143 Rs.27779012 Schedule Variance Rs.1120 Rs. 109035 Rs.994948 Rs.548772 Cost Variance Rs.26000 Rs. 49500 Rs.551341 Rs.89334 Schedule Performance Index 1 0.93 0.92 0.83 Cost Performance Index 0.98 0.97 0.97 0.97 Estimate at Complete Rs.5869511.52 Rs. 5893012 Rs. 5893645 Rs.5932845 Estimate to Complete Rs.4643741.24 Rs. 4450582 Rs.4196503 Rs.3153833 Planned schedule % complete 51.61% 54.97% 63.32% 68.48% Actual Schedule % complete 20.55% 24.39% 45.21% 55.42% Forecasting end date Oct 14th 2017 Oct 19th 2017 Oct 25th 2017 Nov 7th 2017
5.
International Research Journal
of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 681 Fig-2: Updation of the Project Fig-3: Tracking Cost of the Project 4. CONSTRUCTION MANAGEMENT OF NEW BUILDING Managing the new construction project using the software of Primavera. The project has initiation and planning up to scheduling and estimation of the project. The project has the plot area of 2460 sq. ft. and building area of 2130 sq. ft. The project starts at August 7th 2017. The project has the Budgeted total cost of Rs.8072726. The projects finish date is Dec 5th 2019. It is G+2 building. It has car parking at ground floor and 3 flats in each floor. The building has been spacious and it is 2BHK apartment. The planning and scheduling has been done in Primavera. The baselines also created to know the deviation in the project duration during execution. Then develop a schedule and report of the project.
6.
International Research Journal
of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 682 Fig-4: Scheduling of the apartment building 5. CONCLUSION Residential Project progress is 55.42% of the total work had been completed in the time period of 68.48% of the total project duration. Schedule variance index of a residential project is -0.17 therefore the residential building is 17% behind schedule. SPI is 0.83 says that the residential project is only 83% rate had been done as originally planned. CPI is 0.97 indicates that the project is only progressing at 97% of the originally planned rate. The original estimated completion of the project was 15 months but due to the natural calamities, shortage of labour and fund the duration had been extended to 3 months which has 18 months to complete the project. The project has a cost variance of Rs.89334 and cost variance index is -.03. A negative value of CV means that the project is over budget. Apartment building has a budgeted cost of Rs.8072726. The duration of the new management project is 22 months. REFERNCES [1] Mohd Khalil Bin Abdur kadir on “Construction Planning and Scheduling: A Case Study of Cadangan Membjna Dan Menyiapkan Kejll1yyah Sains Untuk Universiti Islam Antarabangsa Malaysia” Nov 2006. [2] Rong-yau Huang and Kuo-Shun Sun on “Non-UnitBased Planning and Scheduling of Repetitive Construction Projects”. Journal of Construction Engineering and Management in American Society of Civil Engineers, June 2006. [3] Yong-Cheol Yang, Chan-Jung Park, Ju-Hyung Kim and Jae-Jun Kim on “Management of Daily Progress in a Construction Project of Multiple Apartment Buildings”. Journal of Construction Engineering and Management, American Society of Civil Engineers, March 2007. [4] Weng HoonKwak, Frank T Anbari on “Analyzing Project Management Research: Perspective from Top Management Journals”. International Journal of Project Management 27 (2009) 435–446, March 2008. [5] Andrew Fernans Tom, Sachin Paul on “Project Monitoring and Control using Primavera” International Journal of Innovative Research in Science, Engineering and Technology Vol. 2, Issue 3, March 2013 ISSN: 2319-8753. [6] Subramani.T, Sarkunam.A, Jayalakshmi.J “Planning and Scheduling of High Rise Building Using Primavera”, International Journal of Engineering Research and Applications, Volume. 4, Issue. 6 (Version 5), pp 134 - 144, 2014.