TRACKING AND MANAGEMENT OF CONSTRUCTION PROJECTS USING
PRIMAVERA
Suchithra L1, Anne Ligoria S2
1PG Student, Department of Civil Engineering, Jerusalem College of Engineering, Tamil Nadu, India
2Professor of Civil Engineering Department and Dean- Academics, Jerusalem College of Engineering, Tamil Nadu, India
----------------------------------------------------------------------------***--------------------------------------------------------------------------
Abstract: Construction industry is an integral component of a nation’s infrastructure and industrial growth. Eventhough
construction industry is the second largest industry in India, the growth of this industry has been differential across the nation.
Proper planning, scheduling, tracking and application are the major parameters in construction industry. This study involves
tracking of the ongoing construction and management of a new building using primavera. The tracking of the project during
construction is necessary to control the variance in the project and to know the forecasting cost of the project. Construction
planning and scheduling is one of the important tool in construction. In the present study the tracking and forecasting was done
by a method called Earned Value Management (EVM). The importance of construction management has been reviewed and the
tracking of ongoing residential building as well as the management of new construction of an apartment building has been done.
Key Words: Planning, Scheduling, Construction Management, Tracking, Primavera, EVM
1. INTRODUCTION
The construction industry has been developed rapidly from the early days. One of the development was planning and
scheduling using software. In construction industry, mostly used software for the planning and scheduling are MS Project and
Primavera. But in India the use of the Primavera is rare and most of the construction has been taken place without the use of
software which leads to extension of the duration and the cost of the project. In this study, the use and need of the project
management software has been explained considering residential building and apartment building. The tracking was done in
residential building and the management of the apartment building up to planning process using the project management
software Primavera P6.R8.2.
1.1. PROJECT MANAGEMENT
Planning is important for any work to reach its goal and Proper Planning leads to excellent result. The three basic things
needed for the planning of construction projects are scope, time and cost. The efficient planning in a construction project
involves project management plan, managing scope, collecting requirements, creating WBS, defining activities and their
relationships, sequencing the activities, duration of the activities and estimation. If any risk arises then steps are taken to
minimize or remove the risk.
1.2. EARNED VALUE MANAGEMENT
Earned Value Management is the most frequently used performance measurement method. EVA looks at schedule, cost and
scope performance measurements of a project together. To perform the earned value calculations, it is needed to determine
the following three parameters:
 Planned Value (PV)
 Earned Value (EV)
 Actual Cost (AC)
The planned value is the cost of the work that has been budgeted for an activity or for the project during a certain time period.
The estimations and budgets are established during Planning Process. The Actual Cost is the cost of the work including direct
and indirect costs. The Earned Value is the value of work that has been completed to date. The EVM is categorized as shown in
Fig.1
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 678
Fig-1: EVM Types
1.2.1. TRACKING:
Planning is important for the success of the project. To know the project has been executed according to the planning,
tracking has been takes place. Tracking helps to stick to the plan during execution. The tracking is the process of analyses the
updated schedule whether the cost and units of the project are beyond or ahead or equal of the planning. The tracking is done
by EVM (Earned Value Management).
Tracking is comes under the process of monitoring and controlling of the construction project. Tracking of the project can
be done after updating the project by monitoring. If the project is deviated from the schedule or cost it can easily be identified
and controlling can be done.
 SV = EV - PV
 CV = EV – AC
 SPI = EV / PV
 CPI = EV / AC
a. Schedule Variance Cases
Case 1: if SV = 0 ; as per schedule, SPI =1
Case 2: if SV = -ve ; behind schedule, SPI <1
Case 3: if SV = +ve ; ahead schedule, SPI >1
b. Cost Variance Cases
Case 1: if CV = 0 ; as per budget, CPI =1
Case 2: if CV = -ve ; budget at over run, CPI <1
Case 3: if CV = +ve ; budget at under run, CPI >1
1.2.2. FORECASTING OF THE PROJECT
The forecasting is also done under EVM which helps us to know the forecasting end date of the project. It determines the
estimation cost of the project during tracking and also the needed cost to complete the project till the end of the project. It
helps to know the future performance of a construction project.
EVM
Tracking
Schedule Variance (SV)
Cost Variance (CV)
Schedule Performance Index
(SPI)
Cost Performance Index (CPI)
Forecasting
Estimate to Complete (ETC)
Estimate at Completion (EAC)
Variance at Completion (VAC)
Budget At Completion (BAC)
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 679
Case 1: if variance is not going to continue
ETC = BAC – EV
EAC = AC + ETC
EAC = AC + [BAC – EV]
VAC = BAC – EAC
Case 2: if variance is going to continue but affects only cost
ETC = [BAC – EV] / CPI
EAC = AC + ETC
VAC = BAC – EAC
Case 3: if variance is going to continue but affects the cost and schedule
ETC = [BAC - EV] / [CPI * SPI]
EAC = AC + ETC
VAC = BAC – EAC
where, PV is Planned Value
EV is Earned Value
AC is Actual Cost
SPI is Schedule Performance Index
CPI is Cost Performance Index
SV is Schedule Variance
CV is Cost Variance
ETC is Estimate to Complete
EAC is Estimate to Completion
VAC is Variance at Completion
BAC is Budget at Completion
2. APPLICATION OF PRIMAVERA SOFTWARE
The study involves tracking of ongoing construction project and management of new construction project of residential and
apartment buildings respectively using the project management software Primavera.
2.1. TRACKING OF ONGOING CONSTRUCTION PROJECT
Tracking of the construction projects involves following steps:
 Getting Information of the Project from the Organisation
 Entering the Details of the Project in Primavera
 Monitoring the Execution of the Project
 Entering the Planned and the Actual Cost
 Tracking the Project
 Forecasting the Project
 Report and Conclusion
2.2. CONSTRUCTION MANAGEMENT OF NEW PROJECT
The management of the new construction project in Primavera software involves following steps:
 New Building Project
 Calendar Creation
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 680
 Work Breakdown Structure
 Define Activities
 Applying Durations
 Sequence of Activities
 Finding the Critical Path
 Creation of Resources
 Assigning the Resources into a task
 Analysing the Resources
 Levelling the Resources
 Creating Baseline
 Develop the Schedule
 Report Preparation
3. PROGRESS OF TRACKING OF A CONSTRUCTION PROJECT
The tracking of an ongoing project is located in Chennai. It is residential project. The plot area of the project is 2322 sq.ft
and the built up area is 1357sq.ft. It is a G+1 building. After the drawing designs the project started with the preparation of
documents on May 2nd 2016. The project contractor said the project would be finished in 9 months for the construction of the
building which starts in Sep 2nd 2016 and the cost of the project is Rs.55 Lakhs. But during the scheduling of the project using
management software Primavera the end date of the project was 24th Aug 2017 which is nearly to 1 year. The cost of the
project is Rs.5842311.52 excludes the indirect cost of the building. The tracking has been done in four months.
The Table.1 shows the EVM parameters of tracking in four months
Table – 1: EVM of the tracking of the ongoing project
EVM Parameter
Tracking 1
Jan 31st 2017
Tracking 2
Feb 28th 2017
Tracking 3
Mar 31st 2017
Tracking 4
April 30th 2017
Budget at Completion Rs.5842311.52 Rs.5842311.52 Rs.5842311.52 Rs.5842311.52
Planned value Rs.1200890.29 Rs.1501963 Rs.2641957 Rs.3238450
Earned Value Rs.1199770.29 Rs.1392929 Rs.1647009 Rs.2689678
Actual Cost Rs. 1225770.29 Rs.1442429 Rs.1702143 Rs.27779012
Schedule Variance Rs.1120 Rs. 109035 Rs.994948 Rs.548772
Cost Variance Rs.26000 Rs. 49500 Rs.551341 Rs.89334
Schedule Performance Index 1 0.93 0.92 0.83
Cost Performance Index 0.98 0.97 0.97 0.97
Estimate at Complete Rs.5869511.52 Rs. 5893012 Rs. 5893645 Rs.5932845
Estimate to Complete Rs.4643741.24 Rs. 4450582 Rs.4196503 Rs.3153833
Planned schedule % complete 51.61% 54.97% 63.32% 68.48%
Actual Schedule % complete 20.55% 24.39% 45.21% 55.42%
Forecasting end date
Oct 14th 2017
Oct 19th 2017 Oct 25th 2017 Nov 7th 2017
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 681
Fig-2: Updation of the Project
Fig-3: Tracking Cost of the Project
4. CONSTRUCTION MANAGEMENT OF NEW BUILDING
Managing the new construction project using the software of Primavera. The project has initiation and planning up to
scheduling and estimation of the project. The project has the plot area of 2460 sq. ft. and building area of 2130 sq. ft. The
project starts at August 7th 2017. The project has the Budgeted total cost of Rs.8072726. The projects finish date is Dec
5th 2019. It is G+2 building. It has car parking at ground floor and 3 flats in each floor. The building has been spacious and
it is 2BHK apartment.
The planning and scheduling has been done in Primavera. The baselines also created to know the deviation in the
project duration during execution. Then develop a schedule and report of the project.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 682
Fig-4: Scheduling of the apartment building
5. CONCLUSION
 Residential Project progress is 55.42% of the total work had been completed in the time period of 68.48% of
the total project duration.
 Schedule variance index of a residential project is -0.17 therefore the residential building is 17% behind
schedule.
 SPI is 0.83 says that the residential project is only 83% rate had been done as originally planned.
 CPI is 0.97 indicates that the project is only progressing at 97% of the originally planned rate.
 The original estimated completion of the project was 15 months but due to the natural calamities, shortage of
labour and fund the duration had been extended to 3 months which has 18 months to complete the project.
 The project has a cost variance of Rs.89334 and cost variance index is -.03. A negative value of CV means that
the project is over budget.
 Apartment building has a budgeted cost of Rs.8072726.
 The duration of the new management project is 22 months.
REFERNCES
[1] Mohd Khalil Bin Abdur kadir on “Construction Planning and Scheduling: A Case Study of Cadangan Membjna Dan
Menyiapkan Kejll1yyah Sains
Untuk Universiti Islam Antarabangsa Malaysia” Nov 2006.
[2] Rong-yau Huang and Kuo-Shun Sun on “Non-UnitBased Planning and Scheduling of Repetitive Construction Projects”.
Journal of Construction Engineering and Management in American Society of Civil Engineers, June 2006.
[3] Yong-Cheol Yang, Chan-Jung Park, Ju-Hyung Kim and Jae-Jun Kim on “Management of Daily Progress in a Construction
Project of Multiple Apartment Buildings”. Journal of Construction Engineering and Management, American Society of
Civil Engineers, March 2007.
[4] Weng HoonKwak, Frank T Anbari on “Analyzing Project Management Research: Perspective from Top Management
Journals”. International Journal of Project Management 27 (2009) 435–446, March 2008.
[5] Andrew Fernans Tom, Sachin Paul on “Project Monitoring and Control using Primavera” International Journal of
Innovative Research in Science, Engineering and Technology Vol. 2, Issue 3, March 2013 ISSN: 2319-8753.
[6] Subramani.T, Sarkunam.A, Jayalakshmi.J “Planning and Scheduling of High Rise Building Using Primavera”,
International Journal of Engineering Research and Applications, Volume. 4, Issue. 6 (Version 5), pp 134 - 144, 2014.

More Related Content

What's hot

Project controls
Project controlsProject controls
Project controlsAshok Kumar
 
Project scheduling and tracking
Project scheduling and trackingProject scheduling and tracking
Project scheduling and trackingyenohhoney
 
Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...Shabaz Khan
 
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...IRJET Journal
 
construction project managment_civileng
construction project managment_civilengconstruction project managment_civileng
construction project managment_civilengsulaiman khan
 
Project typed
Project typedProject typed
Project typedRahul
 
Introduction - organization
Introduction - organizationIntroduction - organization
Introduction - organizationSOPUGent
 
Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...
Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...
Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...Ahmed Fouad, MCIArb, PMP, SP, RMP
 
IRJET- Value Management
IRJET- Value ManagementIRJET- Value Management
IRJET- Value ManagementIRJET Journal
 
Approaches to project control
Approaches to project controlApproaches to project control
Approaches to project controlNITISH SADOTRA
 
Primavera p3 [compatibility mode]
Primavera p3 [compatibility mode]Primavera p3 [compatibility mode]
Primavera p3 [compatibility mode]Rahul
 
Introduction - organization
Introduction - organizationIntroduction - organization
Introduction - organizationJolien Coenraets
 
EVMS for Commercial projects
EVMS for Commercial projectsEVMS for Commercial projects
EVMS for Commercial projectsGlen Alleman
 
Understanding p6 dates
Understanding p6 datesUnderstanding p6 dates
Understanding p6 dateskrunalplanning
 
Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...ijtsrd
 

What's hot (20)

Project controls
Project controlsProject controls
Project controls
 
Project scheduling and tracking
Project scheduling and trackingProject scheduling and tracking
Project scheduling and tracking
 
ppt for primevera
ppt for primeverappt for primevera
ppt for primevera
 
20320130405009
2032013040500920320130405009
20320130405009
 
Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...
 
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
 
construction project managment_civileng
construction project managment_civilengconstruction project managment_civileng
construction project managment_civileng
 
Project typed
Project typedProject typed
Project typed
 
Introduction - organization
Introduction - organizationIntroduction - organization
Introduction - organization
 
Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...
Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...
Construction Risks for Qatar Stadiums for FIFA - Overviewing Cost & Project M...
 
IRJET- Value Management
IRJET- Value ManagementIRJET- Value Management
IRJET- Value Management
 
Approaches to project control
Approaches to project controlApproaches to project control
Approaches to project control
 
Primavera p3 [compatibility mode]
Primavera p3 [compatibility mode]Primavera p3 [compatibility mode]
Primavera p3 [compatibility mode]
 
H1303055462
H1303055462H1303055462
H1303055462
 
project monitoring and control
project monitoring and controlproject monitoring and control
project monitoring and control
 
Introduction - organization
Introduction - organizationIntroduction - organization
Introduction - organization
 
012 bussiness planning process
012 bussiness planning process012 bussiness planning process
012 bussiness planning process
 
EVMS for Commercial projects
EVMS for Commercial projectsEVMS for Commercial projects
EVMS for Commercial projects
 
Understanding p6 dates
Understanding p6 datesUnderstanding p6 dates
Understanding p6 dates
 
Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...
 

Similar to Tracking and managing construction projects

Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...IRJET Journal
 
Tracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value ManagementTracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value ManagementIRJET Journal
 
Project Scheduling of a High-rise Building using Primavera P6
Project Scheduling of a High-rise Building using Primavera P6Project Scheduling of a High-rise Building using Primavera P6
Project Scheduling of a High-rise Building using Primavera P6IRJET Journal
 
EVM Without Quality is Unsuitable for Software Project & Program Management
EVM Without Quality is Unsuitable for Software Project & Program ManagementEVM Without Quality is Unsuitable for Software Project & Program Management
EVM Without Quality is Unsuitable for Software Project & Program ManagementIRJET Journal
 
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-ProjectIRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-ProjectIRJET Journal
 
IRJET- Optimization of Time and Cost of Building Construction using Fast ...
IRJET-  	  Optimization of Time and Cost of Building Construction using Fast ...IRJET-  	  Optimization of Time and Cost of Building Construction using Fast ...
IRJET- Optimization of Time and Cost of Building Construction using Fast ...IRJET Journal
 
Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...
Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...
Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...IRJET Journal
 
IRJET- Optimized Project Planning and Scheduling of Multistorey Building
IRJET-  	  Optimized Project Planning and Scheduling of Multistorey BuildingIRJET-  	  Optimized Project Planning and Scheduling of Multistorey Building
IRJET- Optimized Project Planning and Scheduling of Multistorey BuildingIRJET Journal
 
Finance management in construction site
Finance management in construction siteFinance management in construction site
Finance management in construction siteSHAHIDBASHIRMALIK
 
IIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction ProjectIIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction ProjectIRJET Journal
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET Journal
 
IRJET- Planning, Scheduling, and Optimization of Labor Resources in the C...
IRJET-  	  Planning, Scheduling, and Optimization of Labor Resources in the C...IRJET-  	  Planning, Scheduling, and Optimization of Labor Resources in the C...
IRJET- Planning, Scheduling, and Optimization of Labor Resources in the C...IRJET Journal
 
Application of Building Information Modelling Software’s for Planning and Sch...
Application of Building Information Modelling Software’s for Planning and Sch...Application of Building Information Modelling Software’s for Planning and Sch...
Application of Building Information Modelling Software’s for Planning and Sch...IRJET Journal
 
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...IRJET Journal
 
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...IRJET Journal
 
iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...IRJET Journal
 
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...IRJET Journal
 
Study of Probability Distributions of Cpi and Spi in Earned Value Analysis
Study of Probability Distributions of Cpi and Spi in Earned Value AnalysisStudy of Probability Distributions of Cpi and Spi in Earned Value Analysis
Study of Probability Distributions of Cpi and Spi in Earned Value Analysistheijes
 
Earned Value Management for Design and Construction Project
Earned Value Management for Design and Construction ProjectEarned Value Management for Design and Construction Project
Earned Value Management for Design and Construction Projectijtsrd
 

Similar to Tracking and managing construction projects (20)

Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...
 
Tracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value ManagementTracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value Management
 
Project Scheduling of a High-rise Building using Primavera P6
Project Scheduling of a High-rise Building using Primavera P6Project Scheduling of a High-rise Building using Primavera P6
Project Scheduling of a High-rise Building using Primavera P6
 
EVM Without Quality is Unsuitable for Software Project & Program Management
EVM Without Quality is Unsuitable for Software Project & Program ManagementEVM Without Quality is Unsuitable for Software Project & Program Management
EVM Without Quality is Unsuitable for Software Project & Program Management
 
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-ProjectIRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
 
IRJET- Optimization of Time and Cost of Building Construction using Fast ...
IRJET-  	  Optimization of Time and Cost of Building Construction using Fast ...IRJET-  	  Optimization of Time and Cost of Building Construction using Fast ...
IRJET- Optimization of Time and Cost of Building Construction using Fast ...
 
Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...
Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...
Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...
 
IRJET- Optimized Project Planning and Scheduling of Multistorey Building
IRJET-  	  Optimized Project Planning and Scheduling of Multistorey BuildingIRJET-  	  Optimized Project Planning and Scheduling of Multistorey Building
IRJET- Optimized Project Planning and Scheduling of Multistorey Building
 
Finance management in construction site
Finance management in construction siteFinance management in construction site
Finance management in construction site
 
IIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction ProjectIIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction Project
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
 
IRJET- Planning, Scheduling, and Optimization of Labor Resources in the C...
IRJET-  	  Planning, Scheduling, and Optimization of Labor Resources in the C...IRJET-  	  Planning, Scheduling, and Optimization of Labor Resources in the C...
IRJET- Planning, Scheduling, and Optimization of Labor Resources in the C...
 
Application of Building Information Modelling Software’s for Planning and Sch...
Application of Building Information Modelling Software’s for Planning and Sch...Application of Building Information Modelling Software’s for Planning and Sch...
Application of Building Information Modelling Software’s for Planning and Sch...
 
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
 
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
 
COST CONTROL AND TRACKING OF A BUILDING BY EARNED VALUE METHOD
COST CONTROL AND TRACKING OF A BUILDING BY EARNED VALUE METHODCOST CONTROL AND TRACKING OF A BUILDING BY EARNED VALUE METHOD
COST CONTROL AND TRACKING OF A BUILDING BY EARNED VALUE METHOD
 
iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...
 
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
 
Study of Probability Distributions of Cpi and Spi in Earned Value Analysis
Study of Probability Distributions of Cpi and Spi in Earned Value AnalysisStudy of Probability Distributions of Cpi and Spi in Earned Value Analysis
Study of Probability Distributions of Cpi and Spi in Earned Value Analysis
 
Earned Value Management for Design and Construction Project
Earned Value Management for Design and Construction ProjectEarned Value Management for Design and Construction Project
Earned Value Management for Design and Construction Project
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 

Recently uploaded (20)

VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 

Tracking and managing construction projects

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 677 TRACKING AND MANAGEMENT OF CONSTRUCTION PROJECTS USING PRIMAVERA Suchithra L1, Anne Ligoria S2 1PG Student, Department of Civil Engineering, Jerusalem College of Engineering, Tamil Nadu, India 2Professor of Civil Engineering Department and Dean- Academics, Jerusalem College of Engineering, Tamil Nadu, India ----------------------------------------------------------------------------***-------------------------------------------------------------------------- Abstract: Construction industry is an integral component of a nation’s infrastructure and industrial growth. Eventhough construction industry is the second largest industry in India, the growth of this industry has been differential across the nation. Proper planning, scheduling, tracking and application are the major parameters in construction industry. This study involves tracking of the ongoing construction and management of a new building using primavera. The tracking of the project during construction is necessary to control the variance in the project and to know the forecasting cost of the project. Construction planning and scheduling is one of the important tool in construction. In the present study the tracking and forecasting was done by a method called Earned Value Management (EVM). The importance of construction management has been reviewed and the tracking of ongoing residential building as well as the management of new construction of an apartment building has been done. Key Words: Planning, Scheduling, Construction Management, Tracking, Primavera, EVM 1. INTRODUCTION The construction industry has been developed rapidly from the early days. One of the development was planning and scheduling using software. In construction industry, mostly used software for the planning and scheduling are MS Project and Primavera. But in India the use of the Primavera is rare and most of the construction has been taken place without the use of software which leads to extension of the duration and the cost of the project. In this study, the use and need of the project management software has been explained considering residential building and apartment building. The tracking was done in residential building and the management of the apartment building up to planning process using the project management software Primavera P6.R8.2. 1.1. PROJECT MANAGEMENT Planning is important for any work to reach its goal and Proper Planning leads to excellent result. The three basic things needed for the planning of construction projects are scope, time and cost. The efficient planning in a construction project involves project management plan, managing scope, collecting requirements, creating WBS, defining activities and their relationships, sequencing the activities, duration of the activities and estimation. If any risk arises then steps are taken to minimize or remove the risk. 1.2. EARNED VALUE MANAGEMENT Earned Value Management is the most frequently used performance measurement method. EVA looks at schedule, cost and scope performance measurements of a project together. To perform the earned value calculations, it is needed to determine the following three parameters:  Planned Value (PV)  Earned Value (EV)  Actual Cost (AC) The planned value is the cost of the work that has been budgeted for an activity or for the project during a certain time period. The estimations and budgets are established during Planning Process. The Actual Cost is the cost of the work including direct and indirect costs. The Earned Value is the value of work that has been completed to date. The EVM is categorized as shown in Fig.1
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 678 Fig-1: EVM Types 1.2.1. TRACKING: Planning is important for the success of the project. To know the project has been executed according to the planning, tracking has been takes place. Tracking helps to stick to the plan during execution. The tracking is the process of analyses the updated schedule whether the cost and units of the project are beyond or ahead or equal of the planning. The tracking is done by EVM (Earned Value Management). Tracking is comes under the process of monitoring and controlling of the construction project. Tracking of the project can be done after updating the project by monitoring. If the project is deviated from the schedule or cost it can easily be identified and controlling can be done.  SV = EV - PV  CV = EV – AC  SPI = EV / PV  CPI = EV / AC a. Schedule Variance Cases Case 1: if SV = 0 ; as per schedule, SPI =1 Case 2: if SV = -ve ; behind schedule, SPI <1 Case 3: if SV = +ve ; ahead schedule, SPI >1 b. Cost Variance Cases Case 1: if CV = 0 ; as per budget, CPI =1 Case 2: if CV = -ve ; budget at over run, CPI <1 Case 3: if CV = +ve ; budget at under run, CPI >1 1.2.2. FORECASTING OF THE PROJECT The forecasting is also done under EVM which helps us to know the forecasting end date of the project. It determines the estimation cost of the project during tracking and also the needed cost to complete the project till the end of the project. It helps to know the future performance of a construction project. EVM Tracking Schedule Variance (SV) Cost Variance (CV) Schedule Performance Index (SPI) Cost Performance Index (CPI) Forecasting Estimate to Complete (ETC) Estimate at Completion (EAC) Variance at Completion (VAC) Budget At Completion (BAC)
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 679 Case 1: if variance is not going to continue ETC = BAC – EV EAC = AC + ETC EAC = AC + [BAC – EV] VAC = BAC – EAC Case 2: if variance is going to continue but affects only cost ETC = [BAC – EV] / CPI EAC = AC + ETC VAC = BAC – EAC Case 3: if variance is going to continue but affects the cost and schedule ETC = [BAC - EV] / [CPI * SPI] EAC = AC + ETC VAC = BAC – EAC where, PV is Planned Value EV is Earned Value AC is Actual Cost SPI is Schedule Performance Index CPI is Cost Performance Index SV is Schedule Variance CV is Cost Variance ETC is Estimate to Complete EAC is Estimate to Completion VAC is Variance at Completion BAC is Budget at Completion 2. APPLICATION OF PRIMAVERA SOFTWARE The study involves tracking of ongoing construction project and management of new construction project of residential and apartment buildings respectively using the project management software Primavera. 2.1. TRACKING OF ONGOING CONSTRUCTION PROJECT Tracking of the construction projects involves following steps:  Getting Information of the Project from the Organisation  Entering the Details of the Project in Primavera  Monitoring the Execution of the Project  Entering the Planned and the Actual Cost  Tracking the Project  Forecasting the Project  Report and Conclusion 2.2. CONSTRUCTION MANAGEMENT OF NEW PROJECT The management of the new construction project in Primavera software involves following steps:  New Building Project  Calendar Creation
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 680  Work Breakdown Structure  Define Activities  Applying Durations  Sequence of Activities  Finding the Critical Path  Creation of Resources  Assigning the Resources into a task  Analysing the Resources  Levelling the Resources  Creating Baseline  Develop the Schedule  Report Preparation 3. PROGRESS OF TRACKING OF A CONSTRUCTION PROJECT The tracking of an ongoing project is located in Chennai. It is residential project. The plot area of the project is 2322 sq.ft and the built up area is 1357sq.ft. It is a G+1 building. After the drawing designs the project started with the preparation of documents on May 2nd 2016. The project contractor said the project would be finished in 9 months for the construction of the building which starts in Sep 2nd 2016 and the cost of the project is Rs.55 Lakhs. But during the scheduling of the project using management software Primavera the end date of the project was 24th Aug 2017 which is nearly to 1 year. The cost of the project is Rs.5842311.52 excludes the indirect cost of the building. The tracking has been done in four months. The Table.1 shows the EVM parameters of tracking in four months Table – 1: EVM of the tracking of the ongoing project EVM Parameter Tracking 1 Jan 31st 2017 Tracking 2 Feb 28th 2017 Tracking 3 Mar 31st 2017 Tracking 4 April 30th 2017 Budget at Completion Rs.5842311.52 Rs.5842311.52 Rs.5842311.52 Rs.5842311.52 Planned value Rs.1200890.29 Rs.1501963 Rs.2641957 Rs.3238450 Earned Value Rs.1199770.29 Rs.1392929 Rs.1647009 Rs.2689678 Actual Cost Rs. 1225770.29 Rs.1442429 Rs.1702143 Rs.27779012 Schedule Variance Rs.1120 Rs. 109035 Rs.994948 Rs.548772 Cost Variance Rs.26000 Rs. 49500 Rs.551341 Rs.89334 Schedule Performance Index 1 0.93 0.92 0.83 Cost Performance Index 0.98 0.97 0.97 0.97 Estimate at Complete Rs.5869511.52 Rs. 5893012 Rs. 5893645 Rs.5932845 Estimate to Complete Rs.4643741.24 Rs. 4450582 Rs.4196503 Rs.3153833 Planned schedule % complete 51.61% 54.97% 63.32% 68.48% Actual Schedule % complete 20.55% 24.39% 45.21% 55.42% Forecasting end date Oct 14th 2017 Oct 19th 2017 Oct 25th 2017 Nov 7th 2017
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 681 Fig-2: Updation of the Project Fig-3: Tracking Cost of the Project 4. CONSTRUCTION MANAGEMENT OF NEW BUILDING Managing the new construction project using the software of Primavera. The project has initiation and planning up to scheduling and estimation of the project. The project has the plot area of 2460 sq. ft. and building area of 2130 sq. ft. The project starts at August 7th 2017. The project has the Budgeted total cost of Rs.8072726. The projects finish date is Dec 5th 2019. It is G+2 building. It has car parking at ground floor and 3 flats in each floor. The building has been spacious and it is 2BHK apartment. The planning and scheduling has been done in Primavera. The baselines also created to know the deviation in the project duration during execution. Then develop a schedule and report of the project.
  • 6. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 07 | July -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 5.181 | ISO 9001:2008 Certified Journal | Page 682 Fig-4: Scheduling of the apartment building 5. CONCLUSION  Residential Project progress is 55.42% of the total work had been completed in the time period of 68.48% of the total project duration.  Schedule variance index of a residential project is -0.17 therefore the residential building is 17% behind schedule.  SPI is 0.83 says that the residential project is only 83% rate had been done as originally planned.  CPI is 0.97 indicates that the project is only progressing at 97% of the originally planned rate.  The original estimated completion of the project was 15 months but due to the natural calamities, shortage of labour and fund the duration had been extended to 3 months which has 18 months to complete the project.  The project has a cost variance of Rs.89334 and cost variance index is -.03. A negative value of CV means that the project is over budget.  Apartment building has a budgeted cost of Rs.8072726.  The duration of the new management project is 22 months. REFERNCES [1] Mohd Khalil Bin Abdur kadir on “Construction Planning and Scheduling: A Case Study of Cadangan Membjna Dan Menyiapkan Kejll1yyah Sains Untuk Universiti Islam Antarabangsa Malaysia” Nov 2006. [2] Rong-yau Huang and Kuo-Shun Sun on “Non-UnitBased Planning and Scheduling of Repetitive Construction Projects”. Journal of Construction Engineering and Management in American Society of Civil Engineers, June 2006. [3] Yong-Cheol Yang, Chan-Jung Park, Ju-Hyung Kim and Jae-Jun Kim on “Management of Daily Progress in a Construction Project of Multiple Apartment Buildings”. Journal of Construction Engineering and Management, American Society of Civil Engineers, March 2007. [4] Weng HoonKwak, Frank T Anbari on “Analyzing Project Management Research: Perspective from Top Management Journals”. International Journal of Project Management 27 (2009) 435–446, March 2008. [5] Andrew Fernans Tom, Sachin Paul on “Project Monitoring and Control using Primavera” International Journal of Innovative Research in Science, Engineering and Technology Vol. 2, Issue 3, March 2013 ISSN: 2319-8753. [6] Subramani.T, Sarkunam.A, Jayalakshmi.J “Planning and Scheduling of High Rise Building Using Primavera”, International Journal of Engineering Research and Applications, Volume. 4, Issue. 6 (Version 5), pp 134 - 144, 2014.