International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 03 | Mar 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 5008
OPTIMIZED PROJECT PLANNING AND SCHEDULING OF
MULTISTOREY BUILDING
B. Arun Kumar1, S. Santhosh2, G. Balaji3, T.G. Ram Kumar4
1,2,3UG Student, Department of Civil Engineering, Sethu Institute of Technology, Kariapatti-626 115, Virudhunagar,
Tamil Nadu, India.
4Assistant Professor in Civil Engineering, Sethu Institute of Technology, Kariapatti-626 115, Virudhunagar,
Tamil Nadu, India.
---------------------------------------------------------------------***----------------------------------------------------------------------
Abstract - Generally,intheConstructionProjects, itinvolves
many complexities in the Project such as maintaining the
Work flow, Resources and the Cost of the Project. To avoid or
to Reduce the complexities in the Project, The Project
Management Tools are used. The management Softwaretools
generally used are Microsoft Project and Primavera. In this
Project we adopt Microsoft Project for Planning and
Scheduling of the Multi-Storey Buildings. The building is of
G+16 in which Stilt Floor is used for Parking and the
remaining Sixteen floors are utilised for flats, These Sixteen
Floors are Typical. The building consists of Thirty-Two 3BHK
flats and Thirty-Two 4BHK flats. Entirely it consists of Sixty-
Four Flats.
Key Words: Scheduling, Microsoft Project, Scheduling of
Multi-storey Building, Estimation.
1. INTRODUCTION
Scheduling is the way to actually manage the project,
without scheduling the project gets delay. Scheduling
describes the guidance and pathway for a project to run it
defines certain milestone and deliverables which need to be
achieved on a timely basis for successful completion of
project. Monitoring the project schedule can provideanidea
of the impact the current problems on the project and
provide opportunities to reduce the scope of phase in the
project. Project scheduling is used to organize and complete
the project within a time and achieve the quality of the
project with the support of finance need, project scheduling
carefully. The effective projectschedulingplaysa crucial role
in ensuring project success to follow the project schedule on
track set the realistic time frame, assign resources
appropriately and manage the quality to reduce the costand
achieve the target within the project duration.
1.1 Project management
The way toward overseeing and bringing human and
material asset into a proficient method for working for the
duration of the life of an undertaking by utilizing current
administration advances to accomplishforeordainedtargets,
cost, extension, time and quality and individual fulfilment is
satisfied with project administration. The objectives are
settled up in the undertaking project management, which is
to be satisfied by executing a genuine arrangement of
activities subjected to asset requirements.
1.2 Project scheduling system
Scheduling is a process of needs to assign the resources
and time for assigning the jobs. It is one part of prediction
and one part of expectation management. The planning and
scheduling problems are in many cases such as a problem of
combinatorial optimization and to find the optimum
schedule. The scheduling problem frequently involves
various types of choices this choice couldbeorderingamong
the job’s dependency relation, choosing the available
resources that satisfies need of the job, selecting the proper
time for during the execution process.
1.3 Planning, scheduling and tracking
Construction planning is challenging and fundamental
task in execution and management of construction work. It
incorporates the determination of resources,themeaning of
the work action, the estimation of required resources and
span of an individual movement, and distinguish the
connection between various work exercises.
Scheduling is determining the timing of task in the project
that gives which and when the task will be performed.
Defining it in other words it is a reflection of a plan.
Scheduling can be also defined as a project with detail work
task with time.
Project performance values that is task and actual
duration of work is done by tracking the project in terms of
collecting, enteringandanalyzing.Secondimportantphaseis
tracking in project management. At start of actual work,
main thing to highlight in project planningiscommunicating
and developing the details of project plan.Whenactual work
has been started, the next phase of project management is
tracking progress.
1.4 Work breakdown structure
A work-breakdown structure (WBS) in project
management and systems engineering, is a deliverable-
oriented breakdown of a project into smaller components. A
work breakdown structure is a key project deliverable that
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 03 | Mar 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 5009
organizes the team's work into manageable sections. The
Project Management Body of Knowledge (PMBOK5)defines
the work-breakdown structure "A hierarchical
decomposition of the total scope of work to becarriedout by
the project team to accomplish the project objectives and
create the required deliverables."
A work-breakdown structure element may be a product,
data, service, or any combination thereof. A WBS also
provides the necessary framework for detailed cost
estimating and control along with providing guidance for
schedule development and control.
1.5 Microsoft Project
Microsoft Project is a project management software
product, developed and sold by Microsoft. It is designed to
assist a project manager in developing a schedule, assigning
resources to tasks, tracking progress, managing the budget,
and analyzing workloads.
Microsoft Project was the company's third Microsoft
Windows-based application. Within a few years after its
launch, it became the dominant PC-based project
management software. It is part of the Microsoft Office
family but has never been included inanyoftheOfficesuites.
It is available currently in two editions, Standard and
Professional. Microsoft Project's proprietary file format is
.mpp. Microsoft Project and Microsoft Project Serverarethe
cornerstones of the Microsoft Office enterprise project
management (EPM) product.
2. OBJECTIVES
 To minimize the duration of the project
 To minimize the cost of the project
 To maintain the work flow of the project
 To maintain the robustness of the project
 To facilitate quick evaluations using Gantt chart
 Coordinates different activities of departments
 Provides stability
 Helps to control activities
3. METHODOLOGY
3.1 Project Details
The proposed project for case study work is construction
of Residential Apartment of Appaswamy Real Estates Ltd.,
Chennai at Semmencherry.Theconstructionofthework isin
progress. Building has total site area 175 feet x 125 feet
(21875 ft2) The Built-up area is 10720 ft2. The Residential
Apartment project consists of G+16 floors which contains
3BHK and 4BHK Flats. The estimated cost is Rs.
89,05,96,000/-. The project started on 15/02/2019 whose
estimated completion date is 17/11/2020 (21 months).The
activity name, duration, predecessor and resources are
entered in the Microsoft Project software which give the
total duration of about 588 working days for the completion
of the project.
3.2 Research methodology
3.2.1 First Stage
This stage is known as pre data collection where it
consists of setting out the objectives, literature review, and
based on the area of research, the Residential Apartment is
taken as a case study.
3.2.2 Second Stage
3.2.2.1 Site Supervision
Working status and understandingtheworkingonthesite
is considered here. The work which are carried here should
be understood by every individual like organization of
structure, degree of quality used in work, safety aspects,
rules etc. Dimension, equal, alignment, cross section should
be with accordance to all work.
3.2.2.2 Drawing Details
In every planning task drawingisanimportant role.There
are various drawings which are observed during the
construction work like architectural drawingsand structural
drawings. According to the drawings all the tasks are
identified to reduce the sequential order.
3.2.2.3 Details Estimation
For all engineering work it is necessary to know
beforehand the cost of construction known as the estimated
cost. The subject of estimating is easy, nothing much to
understand, but the knowledge of drawings is very
important.
3.2.2.4 Material and Labour Calculation
The cost of quantities of materials, the costoflabours,and
other miscellaneous is determined by rate per unit of a
particular item work is known as analysis of rate.
3.2.3 Third Stage
This stage is also known as post data collection, whatever
data is collected is analysed in Microsoft project, where
planning, scheduling, and tracking of the project is done. A
working calendar represents theworkingdaysina week and
the working hours. The standard calendar which consists of
working hours from Monday to Friday 8AM to 5AM with
one-hour break.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 03 | Mar 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 5010
3.2.3.1 Selection of Task Mode and Inserting task
The Task mode gives an option whether a task is
scheduled automatically ormanually.Thetask isstepbystep
entered in manually schedule mode and the activities are in
auto scheduled mode in the Microsoft Project software.
3.2.3.2 Organizing Work Breakdown Structure
Work breakdown structure is created after a complete
planning of a project. Where work breakdown structure is
defined as to organize the project element with different
elements.
3.2.3.3 Scheduling the Project work
After all the task are entered along with their respective
duration, the data of activity dependencies is specified by
specifying predecessor of each of the task.
3.2.3.4 Assigning Materials and labours.
A material and labour can be explained as the quantity of
material and number of people that is required to finish the
task and is assigned to an activity.
3.2.3.5 Critical Path
The critical path through a scheduled network is a long-
time duration direction through the network.
3.2.3.6 Creation of Baseline
Baseline is a completeimageof a constructionprojectplan
that can be used to compare the current schedule to
calculate progress.
4. RESULTS AND DISCUSSION
4.1 Working Drawing
There were many corrections in drawings during and
after the work had started. The Architects made some
changes. As drawings play an important role for assigning
the task so it should be completed properly with a better
understanding.
’
4.2 Detailed Estimation, material and labour
calculation
The finalized drawing helps to calculate Study of Detailed
estimate contains the quantitiesofvariousitemsofactivities.
The estimation work was carried out in MS Excel. The
quantity of each item which is found during estimate helps
us to calculate material and labour quantity which is further
useful in our project. The total estimated cost of the project
is Rs. 89,05,96,000/-
From detailed estimation we have calculated the quantity
of each item now that quantity helps to find out the material
and labour quantity by rate analysis through MS Excel. The
rate of material according to market rate and labour rate
according to SR 2018-19.
4.3 Estimated Time and Cost Overrun
After adding actual changes in the site, it may be delay of
work due to material or labour, what will be the actual cost,
remaining cost, cost variance and durationiscomparedwith
planned cost and baseline duration. Belowfiguresshowsthe
above data.
5. CONCLUTION
Construction of building using Traditional way proves to
be uneconomical and consumes more time with many
complexity and enormous error which actual execution of
the Project. Traditional way of planning doesn’t sub divide
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 03 | Mar 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 5011
the main task which future gets the hurdle of over allocation
of resources, improper judgment of resources for particular
activities etc. Microsoft Project is the modern tool of Project
Management that aid to overcome the obstaclesfacedowing
to traditional way of Planning and Management. It helps for
the optimum and effective organization of activities which
helps to give the vision to complete the project in planned
duration and within the Economy. The estimated cost using
Microsoft Project is Rs. 89,05,96,000/-. The project started
on 15/02/2019 whose estimated completion date is
17/11/2020 (21 months)
REFERENCES
[1] Ch. Chowdeswari, D. Satish Chandra and S. S. Asadi,
“Optimal planningandschedulingofhighrisebuildings”,
International Journal of Civil Engineering and
Technology (IJCIET) Volume 8, Issue1,January2017, pp
312–324.
[2] Shubham Laddha, Prerna Chanda and Sneha Khedekar,
“Planning and scheduling of a project using Microsoft
Project (msp)” International Journal of Advance
Research ISSN: 2320-5407, pp.161-168.June 2017
[3] Mrs. Sangeetha H. M., Mr. Rajeeva S. J., Dr. G. Narayana,
“Planning, scheduling, tracking of residential building
using primavera software p6”, IJARIIE-ISSN(O)-2395-
4396, Vol-3 Issue-4 2017, pp. 2361-2368.
[4] J. Sharanya sreenivas, G. Gajalakshmi, K. Ravi theja,
“Project Planning, SchedulingandPreparationofQuality
Assurance Control Documents”, International Research
Journal of Engineering and Technology (IRJET) p-ISSN:
2395-0072, Volume: 04 Issue: 11, Nov -2017
[5] Ashish D. Joshi, Prof. Dr. S.D. Khandekar “Project
Management for Construction Projects: Improving
Project Performance “, International ResearchJournal of
EngineeringandTechnology (IRJET) p-ISSN:2395-0072,
Volume: 02 Issue: 03 | June-2015

More Related Content

What's hot

Construction Project Managment Techniques
Construction Project Managment TechniquesConstruction Project Managment Techniques
Construction Project Managment Techniquesguestc8140fe
 
Review on Planning and Scheduling of Construction Project by Management Tool ...
Review on Planning and Scheduling of Construction Project by Management Tool ...Review on Planning and Scheduling of Construction Project by Management Tool ...
Review on Planning and Scheduling of Construction Project by Management Tool ...ijtsrd
 
NCV 3 Project Management Hands-On Support Slide Show - Module 2
NCV 3 Project Management Hands-On Support Slide Show - Module 2NCV 3 Project Management Hands-On Support Slide Show - Module 2
NCV 3 Project Management Hands-On Support Slide Show - Module 2Future Managers
 
Planning and Optimization of Resource Constrained Project Scheduling by using...
Planning and Optimization of Resource Constrained Project Scheduling by using...Planning and Optimization of Resource Constrained Project Scheduling by using...
Planning and Optimization of Resource Constrained Project Scheduling by using...IRJET Journal
 
PROJECT PLANNINGMEASURES IN CMMI
PROJECT PLANNINGMEASURES IN CMMIPROJECT PLANNINGMEASURES IN CMMI
PROJECT PLANNINGMEASURES IN CMMIIJSEA
 
D0365030036
D0365030036D0365030036
D0365030036theijes
 
Project Management Techniques ( WBS & Critical Path Method )
Project Management Techniques ( WBS & Critical Path Method )Project Management Techniques ( WBS & Critical Path Method )
Project Management Techniques ( WBS & Critical Path Method )Surajkumar Sonar
 
My 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project ManagementMy 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project ManagementSHAZEBALIKHAN1
 
Construction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingConstruction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingSHAZEBALIKHAN1
 
Is5540 course review
Is5540 course reviewIs5540 course review
Is5540 course reviewAsa Chan
 
Enhancing planning and scheduling program by using benefits of bim based appl...
Enhancing planning and scheduling program by using benefits of bim based appl...Enhancing planning and scheduling program by using benefits of bim based appl...
Enhancing planning and scheduling program by using benefits of bim based appl...Alexander Decker
 
Report on Planning & scheduling of a Minor bridge
Report on Planning & scheduling of a Minor bridgeReport on Planning & scheduling of a Minor bridge
Report on Planning & scheduling of a Minor bridgeKundan Sanap
 
Project Management Individual Assignment
Project Management Individual AssignmentProject Management Individual Assignment
Project Management Individual AssignmentArissa Loh
 

What's hot (15)

Construction Project Managment Techniques
Construction Project Managment TechniquesConstruction Project Managment Techniques
Construction Project Managment Techniques
 
Review on Planning and Scheduling of Construction Project by Management Tool ...
Review on Planning and Scheduling of Construction Project by Management Tool ...Review on Planning and Scheduling of Construction Project by Management Tool ...
Review on Planning and Scheduling of Construction Project by Management Tool ...
 
Chapter 2
Chapter 2Chapter 2
Chapter 2
 
NCV 3 Project Management Hands-On Support Slide Show - Module 2
NCV 3 Project Management Hands-On Support Slide Show - Module 2NCV 3 Project Management Hands-On Support Slide Show - Module 2
NCV 3 Project Management Hands-On Support Slide Show - Module 2
 
Planning and Optimization of Resource Constrained Project Scheduling by using...
Planning and Optimization of Resource Constrained Project Scheduling by using...Planning and Optimization of Resource Constrained Project Scheduling by using...
Planning and Optimization of Resource Constrained Project Scheduling by using...
 
PROJECT PLANNINGMEASURES IN CMMI
PROJECT PLANNINGMEASURES IN CMMIPROJECT PLANNINGMEASURES IN CMMI
PROJECT PLANNINGMEASURES IN CMMI
 
4213ijsea08
4213ijsea084213ijsea08
4213ijsea08
 
D0365030036
D0365030036D0365030036
D0365030036
 
Project Management Techniques ( WBS & Critical Path Method )
Project Management Techniques ( WBS & Critical Path Method )Project Management Techniques ( WBS & Critical Path Method )
Project Management Techniques ( WBS & Critical Path Method )
 
My 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project ManagementMy 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project Management
 
Construction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingConstruction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential Building
 
Is5540 course review
Is5540 course reviewIs5540 course review
Is5540 course review
 
Enhancing planning and scheduling program by using benefits of bim based appl...
Enhancing planning and scheduling program by using benefits of bim based appl...Enhancing planning and scheduling program by using benefits of bim based appl...
Enhancing planning and scheduling program by using benefits of bim based appl...
 
Report on Planning & scheduling of a Minor bridge
Report on Planning & scheduling of a Minor bridgeReport on Planning & scheduling of a Minor bridge
Report on Planning & scheduling of a Minor bridge
 
Project Management Individual Assignment
Project Management Individual AssignmentProject Management Individual Assignment
Project Management Individual Assignment
 

Similar to IRJET- Optimized Project Planning and Scheduling of Multistorey Building

IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...IRJET Journal
 
IRJET- Identification of Constraints and there Impact on Construction Pro...
IRJET-  	  Identification of Constraints and there Impact on Construction Pro...IRJET-  	  Identification of Constraints and there Impact on Construction Pro...
IRJET- Identification of Constraints and there Impact on Construction Pro...IRJET Journal
 
76 s201905
76 s20190576 s201905
76 s201905IJRAT
 
IRJET- Optimization of Time and Cost of Building Construction using Fast ...
IRJET-  	  Optimization of Time and Cost of Building Construction using Fast ...IRJET-  	  Optimization of Time and Cost of Building Construction using Fast ...
IRJET- Optimization of Time and Cost of Building Construction using Fast ...IRJET Journal
 
IRJET- Scheduling and Labour Management for Residential Building Project usin...
IRJET- Scheduling and Labour Management for Residential Building Project usin...IRJET- Scheduling and Labour Management for Residential Building Project usin...
IRJET- Scheduling and Labour Management for Residential Building Project usin...IRJET Journal
 
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...IRJET Journal
 
Project Scheduling of a High-rise Building using Primavera P6
Project Scheduling of a High-rise Building using Primavera P6Project Scheduling of a High-rise Building using Primavera P6
Project Scheduling of a High-rise Building using Primavera P6IRJET Journal
 
Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...
Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...
Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...IRJET Journal
 
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...IRJET Journal
 
Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...
Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...
Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...IJSRD
 
Planning, Scheduling and Allocation of Resources for Multi – storiedStructure...
Planning, Scheduling and Allocation of Resources for Multi – storiedStructure...Planning, Scheduling and Allocation of Resources for Multi – storiedStructure...
Planning, Scheduling and Allocation of Resources for Multi – storiedStructure...IRJET Journal
 
Resource scheduling in Construction Project Using Microsoft Project
Resource scheduling in Construction Project Using Microsoft ProjectResource scheduling in Construction Project Using Microsoft Project
Resource scheduling in Construction Project Using Microsoft ProjectSagar Kaptan
 
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...IRJET Journal
 
The role of time, cost and quality in project management
The role of time, cost and quality in project managementThe role of time, cost and quality in project management
The role of time, cost and quality in project managementIRJET Journal
 
Construction Management Techniques to Complete the Project within Time Period...
Construction Management Techniques to Complete the Project within Time Period...Construction Management Techniques to Complete the Project within Time Period...
Construction Management Techniques to Complete the Project within Time Period...IRJET Journal
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800PRIYANSHU KUMAR
 
Enterprise Project Management using Primavera P6 EPPM
Enterprise Project Management using Primavera P6 EPPMEnterprise Project Management using Primavera P6 EPPM
Enterprise Project Management using Primavera P6 EPPMIRJET Journal
 
Delay Analysis for an On-Going Residential Project
Delay Analysis for an On-Going Residential ProjectDelay Analysis for an On-Going Residential Project
Delay Analysis for an On-Going Residential ProjectIRJET Journal
 
Project Planning and Scheduling
Project Planning and SchedulingProject Planning and Scheduling
Project Planning and Schedulingijtsrd
 

Similar to IRJET- Optimized Project Planning and Scheduling of Multistorey Building (20)

IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
 
IRJET- Identification of Constraints and there Impact on Construction Pro...
IRJET-  	  Identification of Constraints and there Impact on Construction Pro...IRJET-  	  Identification of Constraints and there Impact on Construction Pro...
IRJET- Identification of Constraints and there Impact on Construction Pro...
 
76 s201905
76 s20190576 s201905
76 s201905
 
IRJET- Optimization of Time and Cost of Building Construction using Fast ...
IRJET-  	  Optimization of Time and Cost of Building Construction using Fast ...IRJET-  	  Optimization of Time and Cost of Building Construction using Fast ...
IRJET- Optimization of Time and Cost of Building Construction using Fast ...
 
IRJET- Scheduling and Labour Management for Residential Building Project usin...
IRJET- Scheduling and Labour Management for Residential Building Project usin...IRJET- Scheduling and Labour Management for Residential Building Project usin...
IRJET- Scheduling and Labour Management for Residential Building Project usin...
 
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
 
Project Scheduling of a High-rise Building using Primavera P6
Project Scheduling of a High-rise Building using Primavera P6Project Scheduling of a High-rise Building using Primavera P6
Project Scheduling of a High-rise Building using Primavera P6
 
Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...
Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...
Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...
 
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...
 
Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...
Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...
Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...
 
Planning, Scheduling and Allocation of Resources for Multi – storiedStructure...
Planning, Scheduling and Allocation of Resources for Multi – storiedStructure...Planning, Scheduling and Allocation of Resources for Multi – storiedStructure...
Planning, Scheduling and Allocation of Resources for Multi – storiedStructure...
 
Resource scheduling in Construction Project Using Microsoft Project
Resource scheduling in Construction Project Using Microsoft ProjectResource scheduling in Construction Project Using Microsoft Project
Resource scheduling in Construction Project Using Microsoft Project
 
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
 
The role of time, cost and quality in project management
The role of time, cost and quality in project managementThe role of time, cost and quality in project management
The role of time, cost and quality in project management
 
Construction Management Techniques to Complete the Project within Time Period...
Construction Management Techniques to Complete the Project within Time Period...Construction Management Techniques to Complete the Project within Time Period...
Construction Management Techniques to Complete the Project within Time Period...
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800
 
Enterprise Project Management using Primavera P6 EPPM
Enterprise Project Management using Primavera P6 EPPMEnterprise Project Management using Primavera P6 EPPM
Enterprise Project Management using Primavera P6 EPPM
 
Delay Analysis for an On-Going Residential Project
Delay Analysis for an On-Going Residential ProjectDelay Analysis for an On-Going Residential Project
Delay Analysis for an On-Going Residential Project
 
Project Planning and Scheduling
Project Planning and SchedulingProject Planning and Scheduling
Project Planning and Scheduling
 
I012335763
I012335763I012335763
I012335763
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 

Recently uploaded (20)

Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 

IRJET- Optimized Project Planning and Scheduling of Multistorey Building

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 03 | Mar 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 5008 OPTIMIZED PROJECT PLANNING AND SCHEDULING OF MULTISTOREY BUILDING B. Arun Kumar1, S. Santhosh2, G. Balaji3, T.G. Ram Kumar4 1,2,3UG Student, Department of Civil Engineering, Sethu Institute of Technology, Kariapatti-626 115, Virudhunagar, Tamil Nadu, India. 4Assistant Professor in Civil Engineering, Sethu Institute of Technology, Kariapatti-626 115, Virudhunagar, Tamil Nadu, India. ---------------------------------------------------------------------***---------------------------------------------------------------------- Abstract - Generally,intheConstructionProjects, itinvolves many complexities in the Project such as maintaining the Work flow, Resources and the Cost of the Project. To avoid or to Reduce the complexities in the Project, The Project Management Tools are used. The management Softwaretools generally used are Microsoft Project and Primavera. In this Project we adopt Microsoft Project for Planning and Scheduling of the Multi-Storey Buildings. The building is of G+16 in which Stilt Floor is used for Parking and the remaining Sixteen floors are utilised for flats, These Sixteen Floors are Typical. The building consists of Thirty-Two 3BHK flats and Thirty-Two 4BHK flats. Entirely it consists of Sixty- Four Flats. Key Words: Scheduling, Microsoft Project, Scheduling of Multi-storey Building, Estimation. 1. INTRODUCTION Scheduling is the way to actually manage the project, without scheduling the project gets delay. Scheduling describes the guidance and pathway for a project to run it defines certain milestone and deliverables which need to be achieved on a timely basis for successful completion of project. Monitoring the project schedule can provideanidea of the impact the current problems on the project and provide opportunities to reduce the scope of phase in the project. Project scheduling is used to organize and complete the project within a time and achieve the quality of the project with the support of finance need, project scheduling carefully. The effective projectschedulingplaysa crucial role in ensuring project success to follow the project schedule on track set the realistic time frame, assign resources appropriately and manage the quality to reduce the costand achieve the target within the project duration. 1.1 Project management The way toward overseeing and bringing human and material asset into a proficient method for working for the duration of the life of an undertaking by utilizing current administration advances to accomplishforeordainedtargets, cost, extension, time and quality and individual fulfilment is satisfied with project administration. The objectives are settled up in the undertaking project management, which is to be satisfied by executing a genuine arrangement of activities subjected to asset requirements. 1.2 Project scheduling system Scheduling is a process of needs to assign the resources and time for assigning the jobs. It is one part of prediction and one part of expectation management. The planning and scheduling problems are in many cases such as a problem of combinatorial optimization and to find the optimum schedule. The scheduling problem frequently involves various types of choices this choice couldbeorderingamong the job’s dependency relation, choosing the available resources that satisfies need of the job, selecting the proper time for during the execution process. 1.3 Planning, scheduling and tracking Construction planning is challenging and fundamental task in execution and management of construction work. It incorporates the determination of resources,themeaning of the work action, the estimation of required resources and span of an individual movement, and distinguish the connection between various work exercises. Scheduling is determining the timing of task in the project that gives which and when the task will be performed. Defining it in other words it is a reflection of a plan. Scheduling can be also defined as a project with detail work task with time. Project performance values that is task and actual duration of work is done by tracking the project in terms of collecting, enteringandanalyzing.Secondimportantphaseis tracking in project management. At start of actual work, main thing to highlight in project planningiscommunicating and developing the details of project plan.Whenactual work has been started, the next phase of project management is tracking progress. 1.4 Work breakdown structure A work-breakdown structure (WBS) in project management and systems engineering, is a deliverable- oriented breakdown of a project into smaller components. A work breakdown structure is a key project deliverable that
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 03 | Mar 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 5009 organizes the team's work into manageable sections. The Project Management Body of Knowledge (PMBOK5)defines the work-breakdown structure "A hierarchical decomposition of the total scope of work to becarriedout by the project team to accomplish the project objectives and create the required deliverables." A work-breakdown structure element may be a product, data, service, or any combination thereof. A WBS also provides the necessary framework for detailed cost estimating and control along with providing guidance for schedule development and control. 1.5 Microsoft Project Microsoft Project is a project management software product, developed and sold by Microsoft. It is designed to assist a project manager in developing a schedule, assigning resources to tasks, tracking progress, managing the budget, and analyzing workloads. Microsoft Project was the company's third Microsoft Windows-based application. Within a few years after its launch, it became the dominant PC-based project management software. It is part of the Microsoft Office family but has never been included inanyoftheOfficesuites. It is available currently in two editions, Standard and Professional. Microsoft Project's proprietary file format is .mpp. Microsoft Project and Microsoft Project Serverarethe cornerstones of the Microsoft Office enterprise project management (EPM) product. 2. OBJECTIVES  To minimize the duration of the project  To minimize the cost of the project  To maintain the work flow of the project  To maintain the robustness of the project  To facilitate quick evaluations using Gantt chart  Coordinates different activities of departments  Provides stability  Helps to control activities 3. METHODOLOGY 3.1 Project Details The proposed project for case study work is construction of Residential Apartment of Appaswamy Real Estates Ltd., Chennai at Semmencherry.Theconstructionofthework isin progress. Building has total site area 175 feet x 125 feet (21875 ft2) The Built-up area is 10720 ft2. The Residential Apartment project consists of G+16 floors which contains 3BHK and 4BHK Flats. The estimated cost is Rs. 89,05,96,000/-. The project started on 15/02/2019 whose estimated completion date is 17/11/2020 (21 months).The activity name, duration, predecessor and resources are entered in the Microsoft Project software which give the total duration of about 588 working days for the completion of the project. 3.2 Research methodology 3.2.1 First Stage This stage is known as pre data collection where it consists of setting out the objectives, literature review, and based on the area of research, the Residential Apartment is taken as a case study. 3.2.2 Second Stage 3.2.2.1 Site Supervision Working status and understandingtheworkingonthesite is considered here. The work which are carried here should be understood by every individual like organization of structure, degree of quality used in work, safety aspects, rules etc. Dimension, equal, alignment, cross section should be with accordance to all work. 3.2.2.2 Drawing Details In every planning task drawingisanimportant role.There are various drawings which are observed during the construction work like architectural drawingsand structural drawings. According to the drawings all the tasks are identified to reduce the sequential order. 3.2.2.3 Details Estimation For all engineering work it is necessary to know beforehand the cost of construction known as the estimated cost. The subject of estimating is easy, nothing much to understand, but the knowledge of drawings is very important. 3.2.2.4 Material and Labour Calculation The cost of quantities of materials, the costoflabours,and other miscellaneous is determined by rate per unit of a particular item work is known as analysis of rate. 3.2.3 Third Stage This stage is also known as post data collection, whatever data is collected is analysed in Microsoft project, where planning, scheduling, and tracking of the project is done. A working calendar represents theworkingdaysina week and the working hours. The standard calendar which consists of working hours from Monday to Friday 8AM to 5AM with one-hour break.
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 03 | Mar 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 5010 3.2.3.1 Selection of Task Mode and Inserting task The Task mode gives an option whether a task is scheduled automatically ormanually.Thetask isstepbystep entered in manually schedule mode and the activities are in auto scheduled mode in the Microsoft Project software. 3.2.3.2 Organizing Work Breakdown Structure Work breakdown structure is created after a complete planning of a project. Where work breakdown structure is defined as to organize the project element with different elements. 3.2.3.3 Scheduling the Project work After all the task are entered along with their respective duration, the data of activity dependencies is specified by specifying predecessor of each of the task. 3.2.3.4 Assigning Materials and labours. A material and labour can be explained as the quantity of material and number of people that is required to finish the task and is assigned to an activity. 3.2.3.5 Critical Path The critical path through a scheduled network is a long- time duration direction through the network. 3.2.3.6 Creation of Baseline Baseline is a completeimageof a constructionprojectplan that can be used to compare the current schedule to calculate progress. 4. RESULTS AND DISCUSSION 4.1 Working Drawing There were many corrections in drawings during and after the work had started. The Architects made some changes. As drawings play an important role for assigning the task so it should be completed properly with a better understanding. ’ 4.2 Detailed Estimation, material and labour calculation The finalized drawing helps to calculate Study of Detailed estimate contains the quantitiesofvariousitemsofactivities. The estimation work was carried out in MS Excel. The quantity of each item which is found during estimate helps us to calculate material and labour quantity which is further useful in our project. The total estimated cost of the project is Rs. 89,05,96,000/- From detailed estimation we have calculated the quantity of each item now that quantity helps to find out the material and labour quantity by rate analysis through MS Excel. The rate of material according to market rate and labour rate according to SR 2018-19. 4.3 Estimated Time and Cost Overrun After adding actual changes in the site, it may be delay of work due to material or labour, what will be the actual cost, remaining cost, cost variance and durationiscomparedwith planned cost and baseline duration. Belowfiguresshowsthe above data. 5. CONCLUTION Construction of building using Traditional way proves to be uneconomical and consumes more time with many complexity and enormous error which actual execution of the Project. Traditional way of planning doesn’t sub divide
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 03 | Mar 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 5011 the main task which future gets the hurdle of over allocation of resources, improper judgment of resources for particular activities etc. Microsoft Project is the modern tool of Project Management that aid to overcome the obstaclesfacedowing to traditional way of Planning and Management. It helps for the optimum and effective organization of activities which helps to give the vision to complete the project in planned duration and within the Economy. The estimated cost using Microsoft Project is Rs. 89,05,96,000/-. The project started on 15/02/2019 whose estimated completion date is 17/11/2020 (21 months) REFERENCES [1] Ch. Chowdeswari, D. Satish Chandra and S. S. Asadi, “Optimal planningandschedulingofhighrisebuildings”, International Journal of Civil Engineering and Technology (IJCIET) Volume 8, Issue1,January2017, pp 312–324. [2] Shubham Laddha, Prerna Chanda and Sneha Khedekar, “Planning and scheduling of a project using Microsoft Project (msp)” International Journal of Advance Research ISSN: 2320-5407, pp.161-168.June 2017 [3] Mrs. Sangeetha H. M., Mr. Rajeeva S. J., Dr. G. Narayana, “Planning, scheduling, tracking of residential building using primavera software p6”, IJARIIE-ISSN(O)-2395- 4396, Vol-3 Issue-4 2017, pp. 2361-2368. [4] J. Sharanya sreenivas, G. Gajalakshmi, K. Ravi theja, “Project Planning, SchedulingandPreparationofQuality Assurance Control Documents”, International Research Journal of Engineering and Technology (IRJET) p-ISSN: 2395-0072, Volume: 04 Issue: 11, Nov -2017 [5] Ashish D. Joshi, Prof. Dr. S.D. Khandekar “Project Management for Construction Projects: Improving Project Performance “, International ResearchJournal of EngineeringandTechnology (IRJET) p-ISSN:2395-0072, Volume: 02 Issue: 03 | June-2015