SlideShare a Scribd company logo
1 of 9
Download to read offline
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 08 | Aug 2018 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 489
Evaluation of Rework Factors Affecting Cost and Schedule Performance
in Construction Projects.
Aman Sen, A.K. Dwivedi, Dr. M.K. Trivedi
Civil Engineering Department, MITS, Gwalior, Madhya Pradesh, India.
---------------------------------------------------------------------***----------------------------------------------------------------
Abstract: - Rework is a tenable problem in construction industry. The additional cost and duration due to rework can have
effect on overall project performance work. The research represented in this paper aims to identify the rework factors and
calculate the total rework cost in construction projects. Using a questionnaire survey, the data was analyzed from various
infrastructure projects and from the past researches the four main factors and their sub factors are selected which is most
responsible for rework in construction projects. The ranking of rework factors is done by the analytical hierarchy process
and rework cost can be calculated by the probabilistic approach.
Author Keywords: - project management, rework cost, AHP, critical path, schedule overruns.
1. Introduction: -
Rework is an ordinary situation in construction projects and has been identified as the factors that can increase construction
project cost, project duration and reduce the construction project performance. Abandon defects, errors, poor management
and non-conformance may result into cost growth and schedule growth in construction projects. Rework is defined as the
activity that was improperly performed at the first time in construction.
The main factors can affect the project performance is lack of use of information technology, client involvement, unclear
working procedure, changes made by the client PETER E.D. LOVE (2010). The direct cost of rework is 12.4% of total
construction cost BURATI et al (1992). And the rework cost is 11% of the contract value in construction project NURIA
FORCADA (2017). The awarded budget is approximately 17% of the corrected budget.
This condition of rework in construction is occurred due to the insufficiency in details analysis of construction work and
during the design process lack of use of technology in construction work NURIA FORCADA AND ANGELA P (2017). The
rework schedule overrun is 38.26% of the total construction project duration and approximately 10 % cost overrun of the
total construction project cost L.O. OYEWOBI, A.A. OKE (2011).
The main object of this research is to identify the rework factors and classify the rework factors according to there weightage
which is most responsible for rework in construction industry and calculate the total rework cost in construction projects.
2. OBJECTIVE: -
1. To identify rework factors and ranking of the rework factors.
2. Calculate the total rework cost in construction project.
3. SOURCES OF REWORK: -
Total 20 factors of rework are taken in study and these rework factors are classified into 4 main groups as shown in table.
3.1.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 08 | Aug 2018 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 490
Table-3.1: lists of factors causes rework in construction projects.
Sr
no.
Group Factors
1 design related factors Poor used of advanced engineering
Inadequate details collection before preparing design
Poor communication between members of design team
Design mistake due to numerous design
Insufficiency of attention on design details
2 Client related factors Money and time spent on preparation of work
Poor coordination with design consultants
Insufficiency of experience and understanding of design
Shortage of funding for site investigation
Lack of client participation
3 Contractor related factors Imperfect construction technique
Unsuitable construction methods procedure
Low quality of construction materials
Imperfect observation of acceptance
material/equipment’s
Insufficiency of mechanical equipment’s
4 Extraneous environment
factors
Changes rules and regulation by the government
Construction work affected by social and cultural factors
Improper site condition
Improve standard by the end users
Dangerous natural climate and atmosphere
The table 3.1 will be used for analyzing the data to find the rank of rework alternatives and relative importance of the rework
alternatives by analytical hierarchy process.
4. Research Methodology: -
The goal of this research is done by two strategies first is the relative importance of 4 main factors and there sub factors is
evaluated by the analytical hierarchy process and total rework cost is calculated by the probabilistic approach.
4.1 Analytical hierarchy process: - AHP is a multi-criteria decision making tool used for designate the alternatives by pair
wise comparison of each criteria’s which is accomplished by comparing pair wise alternatives this is done by following
steps:-
1. Construct the model of decision matrix.
2. Evaluate the priorities of each criteria’s.
3. Evaluate the priorities of sub criteria’s.
4. Evaluate the alternatives with highest priorities or weightage, by evaluating consistency index followed by consistency
ratio which should be less than 10%.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 08 | Aug 2018 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 491
Table 4.1.1
This analysis is used for evaluating rework cost as shown in Table-4.1.1
4.2 Rework Cost Mechanism: - the method generated for calculating rework amount and rework cost
Where,
= this is the critical activity duration.
= the weightage of rework activities, which is obtained by evaluating the priorities weightage of each criteria’s which
is maximum of all.
= total cost which is associated with each critical activity.
=the amount of rework which is related to the cost of rework, as the rework increases, cost of project increases hence
result in increasing in rework cost.
The critical activity is the one which significantly affect the project cost, hence the above methodology is adopted for critical
activities.
5. Data analysis:-
5.1Data analysis by analytical hierarchy process
The relative importance of main group and there sub groups is determined by analytical hierarchy process.
= *
=
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 08 | Aug 2018 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 492
Table-5.1.1 Main Group ranking
Factors weight Rank
Design related factors .085 4
Client related factors .512 1
Contractor related factors .292 2
Extraneous environment factors .111 3
The ranking of the main group is s hown in table 5.1.1
Table-5.1.2 Ranking of design related factors
Factors weight Rank
Poor used of advanced
engineering
.260 2
Inadequate details collection
before preparing design
.077 5
Poor communication between
members of design team
.172 3
Design mistake due to
numerous design
.099 4
Insufficiency of attention on
design details
.393 1
The ranking of the factors under the influence of design related factors is shown in 5.1.2
Table-5.1.3 Ranking of client related factors
The ranking of the factors under the influence of extraneous environment factors is shown in 5.1.3 Table-5.1.4
Ranking of contractor related factors
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 08 | Aug 2018 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 493
The ranking of the factors under the influence of contractor related factors is shown in 5.1.4
Table-5.1.5 Ranking Of Extraneous Environment Factors
The ranking of the factors under the influence of extraneous environment factors is shown in 5.1.5
Table-5.1.6 Global Ranking
The ranking of the factors under the influence of client related factors is shown in 5.1.6
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 08 | Aug 2018 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 494
5.2 Rework cost calculation: -
In this research study Calculate the rework amount and rework cost, take an example for calculation of rework amount and
rework cost. activity A,B,C,D,E,F and there duration and normal cost are show in example. And the network diagram of these
activity is also shown,
Activity Duration (days) Normal cost (₹)
A 120 12,000/-
B 20 1,800/-
C 40 16,000/-
D 30 1,400/-
E 40 3,600/-
F 60 13,500/-
FIG. 1 ACTIVITY NETWORK DIAG.
Table 5.2.1 cost calculation for critical activity B
FACTORS DURATION
(DAYS)
COST WEIGHTAGE REWORK
AMOUNT
REWOK
COST (₹)
Lack of experience and knowledge
of design and construction process.
20 DAYS 1800
.288 5.76 103.68
Poor quality of construction
technique
.266 5.32 95.76
Poor use of advanced engineering .133 2.66 47.88
Adverse natural condition .111 2.22 39.96
Lack of use of advanced mechanical
equipment’s
.100 2 36.00
The total rework cost for activity B is shown in table 5.2.1
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 08 | Aug 2018 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 495
Table 5.2.2 cost calculation for critical activity C
FACTORS DURATION
(DAYS)
COST WEIGHTAGE REWORK
AMOUNT
REWORK
COST (₹)
Lack of experience and knowledge
of design and construction process.
40 DAYS 16000
.288 11.52 1843.2
Poor quality of
construction technique
.266 10.64 1702
Poor use of advanced engineering .133 5.32 851.40
Adverse natural condition .111 4.44 710.40
Lack of use of advanced
mechanical equipment's
.100 4.0 640
The total rework cost for activity C is shown in table 5.2.2
Table 5.2.3 cost calculation for critical activity D
FACTORS DURATION
(DAYS)
COST WEIGHTAGE REWORK
AMOUNT
REWORK
COST (₹)
Lack of experience and knowledge
of design and construction process.
30 DAYS 1400
.288 8.63 120.96
Poor quality of
construction technique
.266 7.98 110.46
Poor use of advanced engineering .133 3.99 55.86
Adverse natural condition .111 3.33 46.62
Lack of use of advanced
mechanical equipment's
.100 3.00 42.00
The total rework cost for activity D is shown in table 5.2.3
Table 5.2.4 cost calculation for critical activity E
FACTORS DURATION
(DAYS)
COST WEIGHTAGE REWORK
AMOUNT
REWORK
COST (₹)
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 08 | Aug 2018 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 496
Lack of experience and
knowledge of design and
construction process.
40 DAYS 3600
.288 11.52 414,72
Poor quality of construction
technique
.266 10.64 383.04
Poor use of advanced
engineering
.133 5.32 191.52
Adverse natural condition .111 4.44 159.84
Lack of use of advanced
mechanical equipment's
.100 4.0 144.00
The total rework cost for activity E is shown in table 5.2.4
The total rework cost for critical path B-C-D-E IS 7740/- and the total project cost for overall project is 48300/- according
to these data the total rework cost is 18.40% of the total project cost in construction industry.
Conclusion:-
The important conclusion withdraw from this research study is the client and contractor related factors are most responsible
for rework in construction projects. And the ranking of four main groups respectively are client related factors, contractor
related factors, extraneous environment factors and design related factors.
Lack of experience and knowledge of design and construction process, poor quality of construction technique and poor used
of advanced engineering are more responsible for rework in construction process.
The total rework cost is approximately 15-20% of the total project cost in construction work based on the probabilistic
approach.
REFERENCES:-
1. Love, P. E. D., Edwards, D. J., Irani, Z., and Walker, D. H. T. 2009. “Project pathogens: The anatomy of omission errors
in construction and resource engineering projects.” IEEE Trans. Eng. Manage., 563, 425–435.
2. Zhang, D. (2010). “Analysis of a construction small-projects rework reduction program for a capital facility.”J. Constr.
Eng. Manage., 2012, 138(12):1377-1385
3. Blacud, N. A., Bogus, S. M., Diekmann, J. E., and Molenaar, K. R. (2009). “Sensitivity of construction activities under
design uncertainty.” J. Constr. Eng. Manage., 10.1061/(ASCE)0733-9364(2009)135:3(199), 199–206
4. Love, P. E. D., Irani, Z., and Edwards, D. J. 2004. “A rework reduction model for construction projects.” IEEE Trans.
Eng. Manage., 514, 426–440.
5. Reza Dehghan and Janaka Y. Ruwnapura (2014). “model of trade-off between overlapping and rework of design
activities.” J. Constr. Eng. Manage., 2014, 140(2): 04013043
6. Love, P. E. D., and Edwards, D. 2005. “Calculating total rework costs in Australian construction projects.” Civ. Eng.
Environ. Syst., 221, 11– 27.
7. Nuria Forcada ,Angela P. Alvarez,Peter E. D. Love, and David J. Edwards (2017) “ Rework in Urban Renewal Projects
in Colombia” j. Infrastruct., 2017, 23(2):04016034
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 08 | Aug 2018 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 497
8. Love, P. E. D., and Edwards, D. 2005. “Calculating total rework costs in Australian construction projects.” Civ. Eng.
Environ. Syst., 221, 11– 27.
9. Gui ye, Zhigang Jin, Bo Xia (2015) “analyzing causes for reworks in construction projects in china.” J. Manage. Eng.,
2015, 31(6): 04014097
10. Nuriya Forcada, Fartna Ganggolells, Miquel Casals(2017) “factors affecting rework cost in construction.” J. Constr.
Eng. Manage., 2017, 143(8): 04017032
11. Love, P. E. D., and Smith, J. 2003. “Bench-marking, bench-action and bench-learning: Rework mitigation in projects.”
J. Manage. Eng., 194, 147–159

More Related Content

What's hot

IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting InflationIRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting InflationIRJET Journal
 
IRJET- Last Planner System
IRJET- Last Planner SystemIRJET- Last Planner System
IRJET- Last Planner SystemIRJET Journal
 
IRJET- Maintenance Management of Construction Equipment on Construction P...
IRJET-  	  Maintenance Management of Construction Equipment on Construction P...IRJET-  	  Maintenance Management of Construction Equipment on Construction P...
IRJET- Maintenance Management of Construction Equipment on Construction P...IRJET Journal
 
IRJET- Real Time Construction and Analyze of School Building at Nagapattinam
IRJET- Real Time Construction and Analyze of School Building at NagapattinamIRJET- Real Time Construction and Analyze of School Building at Nagapattinam
IRJET- Real Time Construction and Analyze of School Building at NagapattinamIRJET Journal
 
IRJET- Productivity Improvement in Construction Industry using Automation Tec...
IRJET- Productivity Improvement in Construction Industry using Automation Tec...IRJET- Productivity Improvement in Construction Industry using Automation Tec...
IRJET- Productivity Improvement in Construction Industry using Automation Tec...IRJET Journal
 
IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET - Forecasting and Management of Triple Constraints in Construction proj...IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET - Forecasting and Management of Triple Constraints in Construction proj...IRJET Journal
 
IRJET- Assessment of Role of Material Management in Construction Projects
IRJET- 	  Assessment of Role of Material Management in Construction ProjectsIRJET- 	  Assessment of Role of Material Management in Construction Projects
IRJET- Assessment of Role of Material Management in Construction ProjectsIRJET Journal
 
Impact of delayness on construction projects
Impact of delayness on construction projectsImpact of delayness on construction projects
Impact of delayness on construction projectsIRJET Journal
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET Journal
 
IRJET- Multiple Project Execution System for a Construction Contracting Organ...
IRJET- Multiple Project Execution System for a Construction Contracting Organ...IRJET- Multiple Project Execution System for a Construction Contracting Organ...
IRJET- Multiple Project Execution System for a Construction Contracting Organ...IRJET Journal
 
IRJET- Review on Study of Factors Affecting Quality of Construction Project
IRJET- Review on Study of Factors Affecting Quality of Construction ProjectIRJET- Review on Study of Factors Affecting Quality of Construction Project
IRJET- Review on Study of Factors Affecting Quality of Construction ProjectIRJET Journal
 
Lean Waste Assessment and Blue Print for Elimination of Waste Through Lean Di...
Lean Waste Assessment and Blue Print for Elimination of Waste Through Lean Di...Lean Waste Assessment and Blue Print for Elimination of Waste Through Lean Di...
Lean Waste Assessment and Blue Print for Elimination of Waste Through Lean Di...IRJET Journal
 
IRJET- Analysis of Change Order in Road Construction Projects
IRJET-  	  Analysis of Change Order in Road Construction ProjectsIRJET-  	  Analysis of Change Order in Road Construction Projects
IRJET- Analysis of Change Order in Road Construction ProjectsIRJET Journal
 
Factor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road projectFactor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road projectIRJET Journal
 
Success factors enhancing business performance of engineering procurement c...
Success factors enhancing business performance of  engineering procurement  c...Success factors enhancing business performance of  engineering procurement  c...
Success factors enhancing business performance of engineering procurement c...IAEME Publication
 
Success factors enhancing business performance of engineering procurement
Success factors enhancing business performance of engineering procurementSuccess factors enhancing business performance of engineering procurement
Success factors enhancing business performance of engineering procurementIAEME Publication
 
IRJET- Identification of Crucial Factor Affecting to Sustainable Construc...
IRJET-  	  Identification of Crucial Factor Affecting to Sustainable Construc...IRJET-  	  Identification of Crucial Factor Affecting to Sustainable Construc...
IRJET- Identification of Crucial Factor Affecting to Sustainable Construc...IRJET Journal
 
IRJET- Study on Scope Variances in Construction Projects
IRJET- Study on Scope Variances in Construction ProjectsIRJET- Study on Scope Variances in Construction Projects
IRJET- Study on Scope Variances in Construction ProjectsIRJET Journal
 
The Study of Measurement of Over-Engineering in Construction Project
The Study of Measurement of Over-Engineering in Construction ProjectThe Study of Measurement of Over-Engineering in Construction Project
The Study of Measurement of Over-Engineering in Construction ProjectIRJET Journal
 

What's hot (20)

IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting InflationIRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
 
IRJET- Last Planner System
IRJET- Last Planner SystemIRJET- Last Planner System
IRJET- Last Planner System
 
IRJET- Maintenance Management of Construction Equipment on Construction P...
IRJET-  	  Maintenance Management of Construction Equipment on Construction P...IRJET-  	  Maintenance Management of Construction Equipment on Construction P...
IRJET- Maintenance Management of Construction Equipment on Construction P...
 
IRJET- Real Time Construction and Analyze of School Building at Nagapattinam
IRJET- Real Time Construction and Analyze of School Building at NagapattinamIRJET- Real Time Construction and Analyze of School Building at Nagapattinam
IRJET- Real Time Construction and Analyze of School Building at Nagapattinam
 
IRJET- Productivity Improvement in Construction Industry using Automation Tec...
IRJET- Productivity Improvement in Construction Industry using Automation Tec...IRJET- Productivity Improvement in Construction Industry using Automation Tec...
IRJET- Productivity Improvement in Construction Industry using Automation Tec...
 
IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET - Forecasting and Management of Triple Constraints in Construction proj...IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET - Forecasting and Management of Triple Constraints in Construction proj...
 
IRJET- Assessment of Role of Material Management in Construction Projects
IRJET- 	  Assessment of Role of Material Management in Construction ProjectsIRJET- 	  Assessment of Role of Material Management in Construction Projects
IRJET- Assessment of Role of Material Management in Construction Projects
 
Impact of delayness on construction projects
Impact of delayness on construction projectsImpact of delayness on construction projects
Impact of delayness on construction projects
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
 
IRJET- Multiple Project Execution System for a Construction Contracting Organ...
IRJET- Multiple Project Execution System for a Construction Contracting Organ...IRJET- Multiple Project Execution System for a Construction Contracting Organ...
IRJET- Multiple Project Execution System for a Construction Contracting Organ...
 
IRJET- Review on Study of Factors Affecting Quality of Construction Project
IRJET- Review on Study of Factors Affecting Quality of Construction ProjectIRJET- Review on Study of Factors Affecting Quality of Construction Project
IRJET- Review on Study of Factors Affecting Quality of Construction Project
 
Lean Waste Assessment and Blue Print for Elimination of Waste Through Lean Di...
Lean Waste Assessment and Blue Print for Elimination of Waste Through Lean Di...Lean Waste Assessment and Blue Print for Elimination of Waste Through Lean Di...
Lean Waste Assessment and Blue Print for Elimination of Waste Through Lean Di...
 
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
 
IRJET- Analysis of Change Order in Road Construction Projects
IRJET-  	  Analysis of Change Order in Road Construction ProjectsIRJET-  	  Analysis of Change Order in Road Construction Projects
IRJET- Analysis of Change Order in Road Construction Projects
 
Factor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road projectFactor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road project
 
Success factors enhancing business performance of engineering procurement c...
Success factors enhancing business performance of  engineering procurement  c...Success factors enhancing business performance of  engineering procurement  c...
Success factors enhancing business performance of engineering procurement c...
 
Success factors enhancing business performance of engineering procurement
Success factors enhancing business performance of engineering procurementSuccess factors enhancing business performance of engineering procurement
Success factors enhancing business performance of engineering procurement
 
IRJET- Identification of Crucial Factor Affecting to Sustainable Construc...
IRJET-  	  Identification of Crucial Factor Affecting to Sustainable Construc...IRJET-  	  Identification of Crucial Factor Affecting to Sustainable Construc...
IRJET- Identification of Crucial Factor Affecting to Sustainable Construc...
 
IRJET- Study on Scope Variances in Construction Projects
IRJET- Study on Scope Variances in Construction ProjectsIRJET- Study on Scope Variances in Construction Projects
IRJET- Study on Scope Variances in Construction Projects
 
The Study of Measurement of Over-Engineering in Construction Project
The Study of Measurement of Over-Engineering in Construction ProjectThe Study of Measurement of Over-Engineering in Construction Project
The Study of Measurement of Over-Engineering in Construction Project
 

Similar to IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance in Construction Projects

REWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISION
REWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISIONREWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISION
REWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISIONIRJET Journal
 
IRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in ConstructionIRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in ConstructionIRJET Journal
 
IRJET- Quality Assurance & Project Scheduling for Residential Building
IRJET-  	  Quality Assurance & Project Scheduling for Residential BuildingIRJET-  	  Quality Assurance & Project Scheduling for Residential Building
IRJET- Quality Assurance & Project Scheduling for Residential BuildingIRJET Journal
 
OPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECT
OPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECTOPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECT
OPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECTIRJET Journal
 
IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...
IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...
IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...IRJET Journal
 
IRJET- Study to Reduce Cost Price of Wood Products Manufacturing by Value Eng...
IRJET- Study to Reduce Cost Price of Wood Products Manufacturing by Value Eng...IRJET- Study to Reduce Cost Price of Wood Products Manufacturing by Value Eng...
IRJET- Study to Reduce Cost Price of Wood Products Manufacturing by Value Eng...IRJET Journal
 
RII & IMPI: Effective Techniques for Finding Delay in Construction Project
RII & IMPI: Effective Techniques for Finding Delay in Construction ProjectRII & IMPI: Effective Techniques for Finding Delay in Construction Project
RII & IMPI: Effective Techniques for Finding Delay in Construction ProjectIRJET Journal
 
IRJET- Study to Condense Expenditure through Engineering Management of Wood P...
IRJET- Study to Condense Expenditure through Engineering Management of Wood P...IRJET- Study to Condense Expenditure through Engineering Management of Wood P...
IRJET- Study to Condense Expenditure through Engineering Management of Wood P...IRJET Journal
 
Integrating Project Management Information System and BIM for Inspecting and ...
Integrating Project Management Information System and BIM for Inspecting and ...Integrating Project Management Information System and BIM for Inspecting and ...
Integrating Project Management Information System and BIM for Inspecting and ...IRJET Journal
 
IRJET- The Evaluation of Payback period for Formwork system
IRJET-  	  The Evaluation of Payback period for Formwork systemIRJET-  	  The Evaluation of Payback period for Formwork system
IRJET- The Evaluation of Payback period for Formwork systemIRJET Journal
 
CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...
CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...
CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...IRJET Journal
 
IRJET-Survey on Effects of Productivity of Equipment in Construction Projects
IRJET-Survey on Effects of Productivity of Equipment in Construction ProjectsIRJET-Survey on Effects of Productivity of Equipment in Construction Projects
IRJET-Survey on Effects of Productivity of Equipment in Construction ProjectsIRJET Journal
 
IRJET- Impact of Demonetisation and Gst on Construction Industry
IRJET- Impact of Demonetisation and Gst on Construction IndustryIRJET- Impact of Demonetisation and Gst on Construction Industry
IRJET- Impact of Demonetisation and Gst on Construction IndustryIRJET Journal
 
USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...
USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...
USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...IRJET Journal
 
IIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction ProjectIIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction ProjectIRJET Journal
 
Review Application of value engineering in construction project.
Review Application of value engineering in construction project.Review Application of value engineering in construction project.
Review Application of value engineering in construction project.IRJET Journal
 
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...IRJET Journal
 
IRJET- The Study on Evaluation of Cost Escalation in Infrastructure Proje...
IRJET-  	  The Study on Evaluation of Cost Escalation in Infrastructure Proje...IRJET-  	  The Study on Evaluation of Cost Escalation in Infrastructure Proje...
IRJET- The Study on Evaluation of Cost Escalation in Infrastructure Proje...IRJET Journal
 
Resource Optimization in Mivan Construction Project
Resource Optimization in Mivan Construction ProjectResource Optimization in Mivan Construction Project
Resource Optimization in Mivan Construction ProjectIRJET Journal
 
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...IRJET Journal
 

Similar to IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance in Construction Projects (20)

REWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISION
REWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISIONREWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISION
REWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISION
 
IRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in ConstructionIRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in Construction
 
IRJET- Quality Assurance & Project Scheduling for Residential Building
IRJET-  	  Quality Assurance & Project Scheduling for Residential BuildingIRJET-  	  Quality Assurance & Project Scheduling for Residential Building
IRJET- Quality Assurance & Project Scheduling for Residential Building
 
OPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECT
OPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECTOPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECT
OPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECT
 
IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...
IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...
IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...
 
IRJET- Study to Reduce Cost Price of Wood Products Manufacturing by Value Eng...
IRJET- Study to Reduce Cost Price of Wood Products Manufacturing by Value Eng...IRJET- Study to Reduce Cost Price of Wood Products Manufacturing by Value Eng...
IRJET- Study to Reduce Cost Price of Wood Products Manufacturing by Value Eng...
 
RII & IMPI: Effective Techniques for Finding Delay in Construction Project
RII & IMPI: Effective Techniques for Finding Delay in Construction ProjectRII & IMPI: Effective Techniques for Finding Delay in Construction Project
RII & IMPI: Effective Techniques for Finding Delay in Construction Project
 
IRJET- Study to Condense Expenditure through Engineering Management of Wood P...
IRJET- Study to Condense Expenditure through Engineering Management of Wood P...IRJET- Study to Condense Expenditure through Engineering Management of Wood P...
IRJET- Study to Condense Expenditure through Engineering Management of Wood P...
 
Integrating Project Management Information System and BIM for Inspecting and ...
Integrating Project Management Information System and BIM for Inspecting and ...Integrating Project Management Information System and BIM for Inspecting and ...
Integrating Project Management Information System and BIM for Inspecting and ...
 
IRJET- The Evaluation of Payback period for Formwork system
IRJET-  	  The Evaluation of Payback period for Formwork systemIRJET-  	  The Evaluation of Payback period for Formwork system
IRJET- The Evaluation of Payback period for Formwork system
 
CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...
CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...
CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...
 
IRJET-Survey on Effects of Productivity of Equipment in Construction Projects
IRJET-Survey on Effects of Productivity of Equipment in Construction ProjectsIRJET-Survey on Effects of Productivity of Equipment in Construction Projects
IRJET-Survey on Effects of Productivity of Equipment in Construction Projects
 
IRJET- Impact of Demonetisation and Gst on Construction Industry
IRJET- Impact of Demonetisation and Gst on Construction IndustryIRJET- Impact of Demonetisation and Gst on Construction Industry
IRJET- Impact of Demonetisation and Gst on Construction Industry
 
USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...
USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...
USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...
 
IIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction ProjectIIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction Project
 
Review Application of value engineering in construction project.
Review Application of value engineering in construction project.Review Application of value engineering in construction project.
Review Application of value engineering in construction project.
 
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
 
IRJET- The Study on Evaluation of Cost Escalation in Infrastructure Proje...
IRJET-  	  The Study on Evaluation of Cost Escalation in Infrastructure Proje...IRJET-  	  The Study on Evaluation of Cost Escalation in Infrastructure Proje...
IRJET- The Study on Evaluation of Cost Escalation in Infrastructure Proje...
 
Resource Optimization in Mivan Construction Project
Resource Optimization in Mivan Construction ProjectResource Optimization in Mivan Construction Project
Resource Optimization in Mivan Construction Project
 
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 

Recently uploaded (20)

(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 

IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance in Construction Projects

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 08 | Aug 2018 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 489 Evaluation of Rework Factors Affecting Cost and Schedule Performance in Construction Projects. Aman Sen, A.K. Dwivedi, Dr. M.K. Trivedi Civil Engineering Department, MITS, Gwalior, Madhya Pradesh, India. ---------------------------------------------------------------------***---------------------------------------------------------------- Abstract: - Rework is a tenable problem in construction industry. The additional cost and duration due to rework can have effect on overall project performance work. The research represented in this paper aims to identify the rework factors and calculate the total rework cost in construction projects. Using a questionnaire survey, the data was analyzed from various infrastructure projects and from the past researches the four main factors and their sub factors are selected which is most responsible for rework in construction projects. The ranking of rework factors is done by the analytical hierarchy process and rework cost can be calculated by the probabilistic approach. Author Keywords: - project management, rework cost, AHP, critical path, schedule overruns. 1. Introduction: - Rework is an ordinary situation in construction projects and has been identified as the factors that can increase construction project cost, project duration and reduce the construction project performance. Abandon defects, errors, poor management and non-conformance may result into cost growth and schedule growth in construction projects. Rework is defined as the activity that was improperly performed at the first time in construction. The main factors can affect the project performance is lack of use of information technology, client involvement, unclear working procedure, changes made by the client PETER E.D. LOVE (2010). The direct cost of rework is 12.4% of total construction cost BURATI et al (1992). And the rework cost is 11% of the contract value in construction project NURIA FORCADA (2017). The awarded budget is approximately 17% of the corrected budget. This condition of rework in construction is occurred due to the insufficiency in details analysis of construction work and during the design process lack of use of technology in construction work NURIA FORCADA AND ANGELA P (2017). The rework schedule overrun is 38.26% of the total construction project duration and approximately 10 % cost overrun of the total construction project cost L.O. OYEWOBI, A.A. OKE (2011). The main object of this research is to identify the rework factors and classify the rework factors according to there weightage which is most responsible for rework in construction industry and calculate the total rework cost in construction projects. 2. OBJECTIVE: - 1. To identify rework factors and ranking of the rework factors. 2. Calculate the total rework cost in construction project. 3. SOURCES OF REWORK: - Total 20 factors of rework are taken in study and these rework factors are classified into 4 main groups as shown in table. 3.1.
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 08 | Aug 2018 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 490 Table-3.1: lists of factors causes rework in construction projects. Sr no. Group Factors 1 design related factors Poor used of advanced engineering Inadequate details collection before preparing design Poor communication between members of design team Design mistake due to numerous design Insufficiency of attention on design details 2 Client related factors Money and time spent on preparation of work Poor coordination with design consultants Insufficiency of experience and understanding of design Shortage of funding for site investigation Lack of client participation 3 Contractor related factors Imperfect construction technique Unsuitable construction methods procedure Low quality of construction materials Imperfect observation of acceptance material/equipment’s Insufficiency of mechanical equipment’s 4 Extraneous environment factors Changes rules and regulation by the government Construction work affected by social and cultural factors Improper site condition Improve standard by the end users Dangerous natural climate and atmosphere The table 3.1 will be used for analyzing the data to find the rank of rework alternatives and relative importance of the rework alternatives by analytical hierarchy process. 4. Research Methodology: - The goal of this research is done by two strategies first is the relative importance of 4 main factors and there sub factors is evaluated by the analytical hierarchy process and total rework cost is calculated by the probabilistic approach. 4.1 Analytical hierarchy process: - AHP is a multi-criteria decision making tool used for designate the alternatives by pair wise comparison of each criteria’s which is accomplished by comparing pair wise alternatives this is done by following steps:- 1. Construct the model of decision matrix. 2. Evaluate the priorities of each criteria’s. 3. Evaluate the priorities of sub criteria’s. 4. Evaluate the alternatives with highest priorities or weightage, by evaluating consistency index followed by consistency ratio which should be less than 10%.
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 08 | Aug 2018 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 491 Table 4.1.1 This analysis is used for evaluating rework cost as shown in Table-4.1.1 4.2 Rework Cost Mechanism: - the method generated for calculating rework amount and rework cost Where, = this is the critical activity duration. = the weightage of rework activities, which is obtained by evaluating the priorities weightage of each criteria’s which is maximum of all. = total cost which is associated with each critical activity. =the amount of rework which is related to the cost of rework, as the rework increases, cost of project increases hence result in increasing in rework cost. The critical activity is the one which significantly affect the project cost, hence the above methodology is adopted for critical activities. 5. Data analysis:- 5.1Data analysis by analytical hierarchy process The relative importance of main group and there sub groups is determined by analytical hierarchy process. = * =
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 08 | Aug 2018 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 492 Table-5.1.1 Main Group ranking Factors weight Rank Design related factors .085 4 Client related factors .512 1 Contractor related factors .292 2 Extraneous environment factors .111 3 The ranking of the main group is s hown in table 5.1.1 Table-5.1.2 Ranking of design related factors Factors weight Rank Poor used of advanced engineering .260 2 Inadequate details collection before preparing design .077 5 Poor communication between members of design team .172 3 Design mistake due to numerous design .099 4 Insufficiency of attention on design details .393 1 The ranking of the factors under the influence of design related factors is shown in 5.1.2 Table-5.1.3 Ranking of client related factors The ranking of the factors under the influence of extraneous environment factors is shown in 5.1.3 Table-5.1.4 Ranking of contractor related factors
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 08 | Aug 2018 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 493 The ranking of the factors under the influence of contractor related factors is shown in 5.1.4 Table-5.1.5 Ranking Of Extraneous Environment Factors The ranking of the factors under the influence of extraneous environment factors is shown in 5.1.5 Table-5.1.6 Global Ranking The ranking of the factors under the influence of client related factors is shown in 5.1.6
  • 6. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 08 | Aug 2018 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 494 5.2 Rework cost calculation: - In this research study Calculate the rework amount and rework cost, take an example for calculation of rework amount and rework cost. activity A,B,C,D,E,F and there duration and normal cost are show in example. And the network diagram of these activity is also shown, Activity Duration (days) Normal cost (₹) A 120 12,000/- B 20 1,800/- C 40 16,000/- D 30 1,400/- E 40 3,600/- F 60 13,500/- FIG. 1 ACTIVITY NETWORK DIAG. Table 5.2.1 cost calculation for critical activity B FACTORS DURATION (DAYS) COST WEIGHTAGE REWORK AMOUNT REWOK COST (₹) Lack of experience and knowledge of design and construction process. 20 DAYS 1800 .288 5.76 103.68 Poor quality of construction technique .266 5.32 95.76 Poor use of advanced engineering .133 2.66 47.88 Adverse natural condition .111 2.22 39.96 Lack of use of advanced mechanical equipment’s .100 2 36.00 The total rework cost for activity B is shown in table 5.2.1
  • 7. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 08 | Aug 2018 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 495 Table 5.2.2 cost calculation for critical activity C FACTORS DURATION (DAYS) COST WEIGHTAGE REWORK AMOUNT REWORK COST (₹) Lack of experience and knowledge of design and construction process. 40 DAYS 16000 .288 11.52 1843.2 Poor quality of construction technique .266 10.64 1702 Poor use of advanced engineering .133 5.32 851.40 Adverse natural condition .111 4.44 710.40 Lack of use of advanced mechanical equipment's .100 4.0 640 The total rework cost for activity C is shown in table 5.2.2 Table 5.2.3 cost calculation for critical activity D FACTORS DURATION (DAYS) COST WEIGHTAGE REWORK AMOUNT REWORK COST (₹) Lack of experience and knowledge of design and construction process. 30 DAYS 1400 .288 8.63 120.96 Poor quality of construction technique .266 7.98 110.46 Poor use of advanced engineering .133 3.99 55.86 Adverse natural condition .111 3.33 46.62 Lack of use of advanced mechanical equipment's .100 3.00 42.00 The total rework cost for activity D is shown in table 5.2.3 Table 5.2.4 cost calculation for critical activity E FACTORS DURATION (DAYS) COST WEIGHTAGE REWORK AMOUNT REWORK COST (₹)
  • 8. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 08 | Aug 2018 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 496 Lack of experience and knowledge of design and construction process. 40 DAYS 3600 .288 11.52 414,72 Poor quality of construction technique .266 10.64 383.04 Poor use of advanced engineering .133 5.32 191.52 Adverse natural condition .111 4.44 159.84 Lack of use of advanced mechanical equipment's .100 4.0 144.00 The total rework cost for activity E is shown in table 5.2.4 The total rework cost for critical path B-C-D-E IS 7740/- and the total project cost for overall project is 48300/- according to these data the total rework cost is 18.40% of the total project cost in construction industry. Conclusion:- The important conclusion withdraw from this research study is the client and contractor related factors are most responsible for rework in construction projects. And the ranking of four main groups respectively are client related factors, contractor related factors, extraneous environment factors and design related factors. Lack of experience and knowledge of design and construction process, poor quality of construction technique and poor used of advanced engineering are more responsible for rework in construction process. The total rework cost is approximately 15-20% of the total project cost in construction work based on the probabilistic approach. REFERENCES:- 1. Love, P. E. D., Edwards, D. J., Irani, Z., and Walker, D. H. T. 2009. “Project pathogens: The anatomy of omission errors in construction and resource engineering projects.” IEEE Trans. Eng. Manage., 563, 425–435. 2. Zhang, D. (2010). “Analysis of a construction small-projects rework reduction program for a capital facility.”J. Constr. Eng. Manage., 2012, 138(12):1377-1385 3. Blacud, N. A., Bogus, S. M., Diekmann, J. E., and Molenaar, K. R. (2009). “Sensitivity of construction activities under design uncertainty.” J. Constr. Eng. Manage., 10.1061/(ASCE)0733-9364(2009)135:3(199), 199–206 4. Love, P. E. D., Irani, Z., and Edwards, D. J. 2004. “A rework reduction model for construction projects.” IEEE Trans. Eng. Manage., 514, 426–440. 5. Reza Dehghan and Janaka Y. Ruwnapura (2014). “model of trade-off between overlapping and rework of design activities.” J. Constr. Eng. Manage., 2014, 140(2): 04013043 6. Love, P. E. D., and Edwards, D. 2005. “Calculating total rework costs in Australian construction projects.” Civ. Eng. Environ. Syst., 221, 11– 27. 7. Nuria Forcada ,Angela P. Alvarez,Peter E. D. Love, and David J. Edwards (2017) “ Rework in Urban Renewal Projects in Colombia” j. Infrastruct., 2017, 23(2):04016034
  • 9. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 08 | Aug 2018 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 497 8. Love, P. E. D., and Edwards, D. 2005. “Calculating total rework costs in Australian construction projects.” Civ. Eng. Environ. Syst., 221, 11– 27. 9. Gui ye, Zhigang Jin, Bo Xia (2015) “analyzing causes for reworks in construction projects in china.” J. Manage. Eng., 2015, 31(6): 04014097 10. Nuriya Forcada, Fartna Ganggolells, Miquel Casals(2017) “factors affecting rework cost in construction.” J. Constr. Eng. Manage., 2017, 143(8): 04017032 11. Love, P. E. D., and Smith, J. 2003. “Bench-marking, bench-action and bench-learning: Rework mitigation in projects.” J. Manage. Eng., 194, 147–159