EFFECTS OF PROJECT COST ANALYSIS AND FACTORS AFFECTING
INFLATION
Avinash R. Yadav1, R.M. SWAMY2
1student, Civil Department, SSJCET, Maharashtra, India
2Assistant professor, Civil Department, SSJCET, Maharashtra, India
--------------------------------------------------------------------***-----------------------------------------------------------------------
Abstract;- Construction projects in India are experiencing widespread delays. The purpose is to test whether the project as
specified will be economically viable or whether it will generate good value for money. Leaving such feasibilitystudiesuntilaftera
project has started, may mean that potential problems are not revealed in time to influence project planning. Due to a dramatic
shift in the capacity and volume of the Indian construction sector over the last decade, the need of a systematic analysis of the
reasons of delays and developing a clear understanding among the industry professionalsarehighlycrucial. Usingaselected setof
attributes, this research first identified the key factors impacting delay in Indian construction industry and then established the
relationship between the critical attributes for developing prediction models for assessing the impacts of these factors on delay
Delays caused by contractors can generally be attributes to poor managerial skills. Lack of planning and a poor understandingof
accounting and financial principles have led to many a contractor’s downfall.
Key Words: Cost Saving, Excess, Overrun
1. INTRODUCTION
The construction industry is one of the main sectors that provide important ingredients for the development of an
economy. The construction industry is the tool through which society achieves its goals of urban and rural development.
However, it is becoming more complex because of the sophistication of the construction process itselfandthelarge numberof
parties involved in the constructionprocess,i.e.,clients,users,designers, regulators,contractors,suppliers,subcontractors,and
consultants. Modern construction projects are characterized by new standards, advanced technologies, multiparty
participation, and frequent owner-desired changes. Coupled with this state are inherent uncertainties and complexitiesinthe
physical, financial, and economic environment in which most projects are performed. Such conditions have made completing
projects on schedule and on budget difficult task to accomplish often leading to claims on cost compensations and time
extensions. This eventually leads to overrun in the completion of the project. Overrun could be defined as the time overrun
either beyond completion date specified in a contract or beyond the date that the parties agreeuponfordeliveryof a project.It
is slipping over its planned schedule and is considered as common problem in construction projects. Overrun in construction
project is considered one of the most common problems causing a multitude negativeeffectontheprojectanditsparticipating
parties.
Therefore, it is essential to identify the actual causes of overrun in order to minimize andavoidtheoverrunsandtheir
corresponding expenses. Overruns in construction can cause a number of changes in a project such as late completion, lost
productivity, acceleration, increased costs, and contract termination. The party experiencing damages and the parties
responsible for them are in turn responsible to recover time and cost. However, in general overrun situations are complex in
nature. A overrun in an activity may not result in the same amount of project overrun. A delay caused by a party may or may
not affect the project completion date and may or may not cause damagetoanotherparty.Adelaymayoccurconcurrentlywith
other delays and all of them may impact the project completion date.
2. LITERATURE REVIEW
Olabosipo, Fag Olabosipo, Et. Al., 2018.
The growing need at maintaining steady cost projection of construction projects has been an issue of seriousconcern
to both the clients and the construction practitioners on sites. This study therefore examinedthefactorsthatareconsideredto
be affecting the cost management practice of constructionfirmsinthesouthwesternNigeria andalsoprofferedpossiblewaysof
ameliorating the factors. It was concluded that extra focus should be placed on the identified factors with a view to reducing
cost of construction, enhancing construction performance and building confidence within the construction industry in the
study area.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 02 | Feb 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 2255
Ghulam Abbas Niazi and Noel Painting, (2017)
This research aims to identify the significant factorsthatlead toconstructioncostoverrunsinAfghanistan.Thefinding
of the research is that the key critical causes that potentiallyresult inconstructioncostoverrunsinAfghanistanare: corruption,
delay in progress payment by owner, difficulties in financing project by contractors, security, change the order by the owner
during construction and market inflation.
Olav Torp, Alemu Moges Belay, et. al. (2016).
The research aim is threefold: firstly, to identify the critical factors of cost development in the planning phase.
Secondly, to investigate empirically a dyadic relationship of cost deviation over time and quantitatively chart their
developments. Thirdly, to analyze the construction cost data, discuss their cost developments and identify critical projects
based on their actual financial impacts.Theresearchconsiders110projectsandanalyzethemusingqualitativeandquantitative
research methods. The results showed higher cost escalation in the planning phase. The research identified critical factorsfor
cost escalations at the planning phase. The average cost escalation of 110 projects (<5%) seems good, but some projects
showed large cost deviations with lower financial impacts and vice versa.
3. RESEARCH GAP
Overrun is one of the biggest problems offer experienced on construction project sites. Overrun in sites gets negative
effect such as increased cost loss of productivity and revenue may low suits between owners and contractors and contract
termination The study until now was carried out on the causes of overrun and inflation of project cost. Many researchers
defined different methods for optimizing cost of project after overrun. This study will continue with framing a relationship
between overrun and profitability of the project facing overrun problem.
4. CAUSES IN OVERRUN IN CONSTRUCTION
The study identified ten most important causes of delayfroma listof69differentcauses.Tenmostimportantcauses ofoverrun
were:
 Contractor’s improper planning
 Contractor’s poor site management
 Inadequate contractor experience
 Inadequate client’s finance and payments for completed work
 Problems with subcontractors
 Shortage in material
 Labor supply
 Equipment availability and failure
 Lack of communication between parties
 Mistakes during the construction stage
The survey showed that all three groups generally agree on the ranking of individual overrun factors. The factors were
categorized into nine major groups and were ranked. The nine groups were material, manpower, equipment, financing,
changes, government relations, scheduling and controlling, environment, and contractual relationships. Based on the
contractors surveyed, the most important overrun factors were:
 Preparation and approval of shop
 drawings
 Delays in contractor’s progress
 Payment by owners and
 Design changes
From the view of architects and engineers, the cashproblemsduringconstruction,therelationship betweensubcontractors
and the slow decision-making progress of the owner were the main causes of overrun. However, the owners agreed that the
design errors, labor shortages andinadequatelaborskillswereimportantoverrunfactors.Bothownersandconsultantsspecify
labor and contractor related causes as the severe and important sources of overrun while, contractors indicate that the
important sources of overrun in construction projects are owners and consultant.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 02 | Feb 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 2256
5. CASE STUDY
In this case study, Excess Amount required to complete the work with its reasons Construction of Multipurpose
Building along with Community Centre at plot No. 24 Sec- 5 Kopar-Khairne project is studied for project overruns Average
percentage is calculated by sum of all item’s excess percentage.
Estimated amount is calculated by multiplying rate with estimated quantity and anticipated amount is calculated by
multiplying rate with anticipated quantity. Excess amountiscalculatedbysubtractestimatedamountfromanticipatedamount
and excess quantity is calculated by estimated quantity subtract from anticipated quantity. Excess percentage is calculatedby
estimated amount subtract from excess amount. Average percentage is calculated by sum of all item’s excess percentage.
Figure No. 1.1: Excess Amount, Estimated Amount and Anticipated Amount
In the graph for case study 1 observed excess amount, estimated amount and anticipatedamount.Thebarsareshown
estimated amount in dark blue colour and excess amount in green colour. The area graph shows the anticipated cost shownin
grey colour on backside of bars. The excess amountismaximumfortotal ofpartVIIplasteringandmaximum estimatedamount
is for total of part XII miscellaneous. In the graph X-axis shows the items and Y-axis shows the cost in Rs
Figure No. 1.2: Saving amount and saving quantity
Saving amount and saving quantity is calculated. Estimated amount is calculated by multiplying rate with estimated
quantity and anticipated amount is calculated by multiplying rate with anticipated quantity. Saving amount is calculated by
subtract anticipated amount from estimated amount and saving quantity is calculated by subtract anticipated quantity from
estimated quantity. Saving percentage is calculated by anticipatedamountsubtractfromsavingamount.Average percentageis
calculated by sum of all items saving percentage.
In the graph observed saving amount, estimated amount and anticipated amount. The bars are shown anticipated
amount in dark blue colour and saving amount in green colour. The area graph shows the estimated amount in grey colour on
backside of bars. The saving amount is maximum for total ofpartXIImiscellaneousandmaximum estimatedamountisfortotal
of part III R.C.C. In the graph X-axis shows the items and Y-axis shows the cost in Rs.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 02 | Feb 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 2257
6. RESULT AND DISCUSSION
Project Causes of overrun Due to Contractor Affecting Profitability of Project Contractor mainly affects the processof
working and indirectly is responsible for overrun of project. Ineffective planning of contractor leads to shortage of material
labour resources on site due to which the overrun in project is seen mainly the overrun due to contractor is due to improper
planning of resources to be used on site.
It is observed that in the table 1.1 Responsible Authority and Person is Contractor. The 20 causesofoverrun arehere.
Addition of total respondents and frequencies of respondentsisgiveninthetable.Thepercentageof eachcauseiscalculatedby
RII method, the highest percentage is 68.00% for cause lack of sub-contractor skills and lowestpercentageis56.67%fordelay
in reviewing the design documents.
Figure No. 1.3: Frequencies of Rating for Contractor
It is observed that in the graph are frequencies of rating for client. The frequencies of rating for 20 causes of overrun
are here. On X-axis causes of overrun is plotted and on Y-axis frequency is plotted. In this graph 5 frequencies show of 30
respondents. The rating of frequency no 1 is show in blue color is high and frequency no 5 show in red color is low.
Figure No. 1.4: RII Ranking for Contractor
It is observed that in the graph is RII ranking for client. The frequencies of rating for 20 causes of overrun are here. On X-
axis causes of overrun is plotted and on Y-axis cumulative ranking is plotted. In this graph total response and RII ranking are
plotted.
EVM Calculation & Scheduling in MSP
Observed in the above figure shows the table of MSP (Microsoft office Project) scheduling with EVM (Earned Value
Method) for case study 1. In the Microsoft Project all the work means task added in task columninGanttChartwithduration in
day or hours then add the resources in resources sheet with cost per day or per hour. When apply in table earned value then
columns like Planned value (PV), Earned value (EV), Actual cost (AC), Schedule Variance (SV), Cost Variance (CV), Estimate at
Completion (EAC), Budget at Completion(BAC)andVarianceatCompletion(VAC)columnsareseenandSchedulePerformance
Index (SPI) & Cost Performance Index (CPI) columns are added by insert column in table
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 02 | Feb 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 2258
The scheduling of work is observed in above figure1.2. The blue bars seen in the figure are indicating the duration of
work and one work is complete then another work is start. In the MSP (Microsoft Project) we set the calendar for number of
days of work, number of working hours, weekly holiday, national holidays, etc.Theblack lineinthe blue barisindicatethe how
much work is completed in percentage. If work is 100% complete then black line on whole blue bar.
Sr.
No.
Cause of Overrun Responsible
Authority and
Person
RII %
1 Poor coordination and communication b/t
contractor and other parties
Contractor 0.55 55.33
2 Financial difficulties by contractors Contractor 0.57 57.33
3 Delay in site mobilization Contractor 0.61 60.67
4 Often changing sub-contractors Contractor 0.52 52.00
5 Mistakes during construction by contractors Contractor 0.51 50.67
6 Poor contractors experience Contractor 0.58 58.00
7 Ineffective planning and scheduling Contractor 0.50 50.00
8 Ineffective coordination between contractors
and other parties
Contractor 0.55 54.67
9 Lack of sub-contractor skills Contractor 0.68 68.00
10 Poor site management by contractors Contractor 0.56 56.00
11 Lack of sufficient experience of consultants Contractor 0.61 60.67
12 Delay in reviewing the design documents Contractor 0.52 52.00
13 Poor inspection plan by consultants Contractor 0.57 56.67
14 Project design complexity Contractor 0.53 52.67
15 Mistakes and discrepancies in design documents Contractor 0.57 56.67
16 Poor coordination/communication between
consultant & parties
Contractor 0.51 51.33
17 Slowness in giving instruction Contractor 0.55 55.33
18 Inadequate quality assurance and quality
control plans
Contractor 0.49 56.67
19 Conflicts amongst consultant with other parties Contractor 0.51 51.33
20 Delay in reporting the progress of works done Contractor 0.51 51.33
Table No. 1.1: Causes of Overrun Affecting to Contractor
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 02 | Feb 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 2259
Table No. 1.2:Causes of Overrun Ranking for Contractor
Sr.
No.
Cause of Overrun Responsible Authority and
Person
RII Ranking
9 Lack of sub-contractor skills Contractor 0.68 1
3 Delay in site mobilization Contractor 0.61 2
11 Lack of sufficient experience of consultants Contractor 0.61 3
6 Poor contractors experience Contractor 0.58 4
2 Financial difficulties by contractors Contractor 0.57 5
13 Poor inspection plan by consultants Contractor 0.57 6
15 Mistakes and discrepancies in design documents Contractor 0.57 7
10 Poor site management by contractors Contractor 0.56 8
1 Poor coordination and communication b/t contractor and
other parties
Contractor 0.55 9
17 Slowness in giving instruction Contractor 0.55 10
8 Ineffective coordination between contractors and other parties Contractor 0.55 11
14 Project design complexity Contractor 0.53 12
4 Often changing sub-contractors Contractor 0.52 13
12 Delay in reviewing the design documents Contractor 0.52 14
16 Poor coordination/communication between consultant &
parties
Contractor 0.51 15
19 Conflicts amongst consultant with other parties Contractor 0.51 16
20 Delay in reporting the progress of works done Contractor 0.51 17
5 Mistakes during construction by contractors Contractor 0.51 18
7 Ineffective planning and scheduling Contractor 0.50 19
18 Inadequate quality assurance and quality control plans Contractor 0.49 20
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 02 | Feb 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 2260
Figure No.1. 5: MSP Calculations
Figure No. 1.6: Calculation MSP Scheduling
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 02 | Feb 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 2261
Figure No. 1.7: Earned Value over Time Report
7. CONCLUSIONS
The Overruns in cost and time is a never-ending threat to a construction manager and is being faced in all types of
projects which include infrastructureprojects,heavyconstructionprojects,residential orcommercial construction projectsetc.
By studying various literature review from all across world and considering three working local sites as case study on which
various attributes of reducing cost overrun is analyses. The following are result from the sets of projects considered which
showed large cost deviation.
• The first three factors ranked by RII method first is conflict between labour, second lack of sub-contractor
skills and third is poor financial control mechanism. The first one conflict between labour in the category of
labour its RII is 0.70, second one lack of sub-contractor skills in the category of contractor its RII is 0.68 and
third one poor financial control mechanism in the category is client its RII is 0.63.
• Te severity index and frequency index of the factors are, for conflict between labour is 70.00, for lack of sub-
contractor skills is 68.00 and for poor financial control mechanism is 63.33.
• The average of percentage excess for case study 1 is 1.02 and percentage saving is 1.10. The average of
percentage excess for case study 2 is 2.71 and percentage saving is 4.39. Theaverageof percentageexcessfor
case study 3 is 1.90 and percentage saving is 0.15.
• The average percentage cost growth rate for all three case studies is 98.62% and average actual cost
percentage change for all three case studies is 97.20%.
8. REFERENCES
1. Ahmed Senouci, Alaa Ismail & Neil Eldin, “Time Delay and Cost Overrun in Qatari Public Construction Projects”,
Procedia Engineering, Vol.164, Pp. No.368 – 375, (2016).
2. Ali Touran and Ramon Lopez, “Modeling Cost Escalation In Large Infrastructure Projects”,J. Constr. Eng. Manage.,
Vol.132, Pp. No.853-860, (2006).
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 02 | Feb 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 2262
3. Anna Wasiluk, “Pro-Innovative Prerequisites for Establishing The Cooperation Between Companies”, Procedia
Engineering, Vol.182, Pp. No. 755 – 762, (2017).
4. Artur Czech & Jerzy Lewczuk, “Statistical Assessment of The Development of The Transportation System in Chosen
Countries – An International Approach”, Procedia Engineering, Vol.182, Pp. No.112 – 119, (2017).
5. Alfredo Serpell, José Ignacio Díaz, “Linking Central Business Processes of Construction Companies Within the
Performance of Construction Operations: A Preliminary Exploration”, CreativeConstructionConference,Vol.-164,Pp.
No. 25-28, 2016.
6. Berrak Bahadir, Olena Mykhaylova, “Housing Market Dynamics with Delays in The Construction Sector”, Journal of
Housing Economics, Vol.- 26 Pp. No. 94–108, 2014.
7. Divya. R, S. Ramya, “Causes, Effects and Minimization of Delays in Construction Projects”, National Conference on
Research Advances in Communication, Computation, Electrical Science and Structures (2015).
8. Dr. Shabbab Al Hammadi & M. Sadique Nawab, “Project Time Overruns in Saudi Arabian Con-Struction Industry”,
International Journal of Scientific & Engineering Research, Vol.7, (2016).
9. David Arditi , Shruti Nayak , Atilla Damci, “Effect Of Organizational Culture On Delay In Construction”, International
Journal of Project Management, Vol.- 35 Pp. No. 136–147, 2017.
10. Garry D. Creedy, Martin Skitmore and Johnny K. W. Wong, “Evaluation of Risk Factors Leading to Cost Overrun in
Delivery of Highway Construction Projects”, J. Constr. Eng. Manage, Vol.136, Pp. No.528-537, (2010).
11. Ghulam Abbas Niazi & Noel Painting, “Significant Factors Causing Cost Overruns in The Construction Industry in
Afghanistan”, Procedia Eng, Vol.182, Pp. No.510 – 517, (2017).
12. Gul Polat, Ferzan Okay & Ekin Eray, “Factors Affecting Cost Overruns in Micro-Scaled Construction Companies”,
Procedia Eng, Vol.85, Pp. No. 428-435, (2014).
13. G. Sweis, R. Sweis, A. Abu Hammad, A. Shboul, “Delays in construction projects: The case of Jordan”, International
Journal of Project Management, Vol.- 26, Pp. No. 665–674, (2008).
14. Hemanta Doloi & Anil Sawhney, et. al., “Analysing Factors Affecting Delays in Indian Construction Projects”,
International Journal of Project Management, Vol.30, Pp. No.479–489, (2012).
15. Jennifer S. Shane, A.M. ASCE & KEITH R. MOLENAAR, ET. AL., “ConstructionProjectCostEscalationFactors”,J.Manage.
Eng., Vol.25, Pp. No.221-229, (2009).
16. Jesus M. De La Garza and John W. Melin, “Prepayment Ability to Offset Inflation”, J. Constr. Eng. Manage., Vol.112, Pp.
No.514-529, 1986.
17. Krystyna Araszkiewicz, “Application of Critical Chain Management in Construction Projects Schedules In A Multi-
Project Environment: A Case Study”, Procedia Engineering, Vol.182, Pp. No. 33 – 41, (2017).
18. Majed Alzara, Jacob Kashiwagi, Dean Kashiwagi, Abdulrahman Al-Tassan, “Using PIPS to Minimize Causes OfDelayIn
Saudi Arabian Construction Projects: University Case Study”, Procedia Eng, Vol.- 145 Pp. No. 932 – 939, 2016.
19. N. Hamzah, M.A. Khoiry, I. Arshad, N. M. Tawil and A. I. Che Ani, “Cause of Construction Delay – Theoretical
Framework”, Procedia Eng, Vol.- 20, Pp. No. 490 – 495, 2011
20. Olabosipo, Fagbenle, Opeyemi, Joshua, Et. Al., “Cost Management Practice of Construction Firms and Its Influencing
Factors: Lessons from Southwestern Nigeria”, Construction Research Congress 2018.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 02 | Feb 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 2263
21. Olav Torp, Alemu Moges Belay, et. al. “Cost Development Over-Time At Construction Planning Phase: Empirical
Evidence From Norwegian Construction Projects”, Procedia Engineering, Vol.145, Pp. No.1177 – 1184, (2016).
22. Peter E. D. Love & Xiangyu Wang, “Determining the Probability of Project Cost Overruns”, J. Constr. Eng. Manage.,
Vol.139, Pp. No.321-330, (2013).
23. Prakash Kumar & Piush Raj, “Delay Analysis ofProjects andEffectsofDelaysinTheMining/ManufacturingIndustries”,
Vol. 12, PP. 61-71, (2015).
24. Romualdas Ginevičius, Dainora Gedvilaitė & Andrius Stasiukynas, “Assessment of The Interrelations Between
Economic and Ecological Development in Regions of Lithuania”, Procedia Engineering, Vol.182, Pp. No.213 – 221,
(2017).
25. Sadi A. Assaf & Sadiq Al-Hejji, “Causes of Delay In Large Construction Projects”, International Journal of Project
Management, Vol. 24, Pp. No. 349–357, (2006).

More Related Content

What's hot

IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET Journal
 
A Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project ManagementA Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project Managementijsrd.com
 
Analysis of Cost Over Run in Construction Projects
Analysis of Cost Over Run in Construction ProjectsAnalysis of Cost Over Run in Construction Projects
Analysis of Cost Over Run in Construction ProjectsIRJET Journal
 
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...IJMER
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET Journal
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...iosrjce
 
causes and implication of delay in construction
causes and implication of delay in constructioncauses and implication of delay in construction
causes and implication of delay in constructionsudinak
 
Project delay and_cost_overrun-libre
Project delay and_cost_overrun-libreProject delay and_cost_overrun-libre
Project delay and_cost_overrun-libreUTHM
 
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...IRJET Journal
 
IRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in ConstructionIRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in ConstructionIRJET Journal
 
A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...
A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...
A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...IRJET Journal
 
IRJET- Review on Study of Factors Affecting Quality of Construction Project
IRJET- Review on Study of Factors Affecting Quality of Construction ProjectIRJET- Review on Study of Factors Affecting Quality of Construction Project
IRJET- Review on Study of Factors Affecting Quality of Construction ProjectIRJET Journal
 
Risk analysis and managements large epc projects
Risk analysis and managements  large epc projectsRisk analysis and managements  large epc projects
Risk analysis and managements large epc projectsPALLA NARASIMHUDU
 
IRJET- Study on Scope Variances in Construction Projects
IRJET- Study on Scope Variances in Construction ProjectsIRJET- Study on Scope Variances in Construction Projects
IRJET- Study on Scope Variances in Construction ProjectsIRJET Journal
 
7. article azojete vol 11 77 88 alhassan
7. article azojete vol 11 77 88 alhassan7. article azojete vol 11 77 88 alhassan
7. article azojete vol 11 77 88 alhassanOyeniyi Samuel
 
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET Journal
 
IRJET- Study & Analysis of Subcontracting Practices in Infrastructure Project
IRJET- Study & Analysis of Subcontracting Practices in Infrastructure ProjectIRJET- Study & Analysis of Subcontracting Practices in Infrastructure Project
IRJET- Study & Analysis of Subcontracting Practices in Infrastructure ProjectIRJET Journal
 
construction project managment_civileng
construction project managment_civilengconstruction project managment_civileng
construction project managment_civilengsulaiman khan
 
Cost and time overruns in indian construction industry
Cost and time overruns in indian construction industryCost and time overruns in indian construction industry
Cost and time overruns in indian construction industryAngad Partap Singh Bali
 

What's hot (20)

IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
 
A Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project ManagementA Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project Management
 
Analysis of Cost Over Run in Construction Projects
Analysis of Cost Over Run in Construction ProjectsAnalysis of Cost Over Run in Construction Projects
Analysis of Cost Over Run in Construction Projects
 
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
 
Risk management
Risk managementRisk management
Risk management
 
causes and implication of delay in construction
causes and implication of delay in constructioncauses and implication of delay in construction
causes and implication of delay in construction
 
Project delay and_cost_overrun-libre
Project delay and_cost_overrun-libreProject delay and_cost_overrun-libre
Project delay and_cost_overrun-libre
 
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
 
IRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in ConstructionIRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in Construction
 
A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...
A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...
A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...
 
IRJET- Review on Study of Factors Affecting Quality of Construction Project
IRJET- Review on Study of Factors Affecting Quality of Construction ProjectIRJET- Review on Study of Factors Affecting Quality of Construction Project
IRJET- Review on Study of Factors Affecting Quality of Construction Project
 
Risk analysis and managements large epc projects
Risk analysis and managements  large epc projectsRisk analysis and managements  large epc projects
Risk analysis and managements large epc projects
 
IRJET- Study on Scope Variances in Construction Projects
IRJET- Study on Scope Variances in Construction ProjectsIRJET- Study on Scope Variances in Construction Projects
IRJET- Study on Scope Variances in Construction Projects
 
7. article azojete vol 11 77 88 alhassan
7. article azojete vol 11 77 88 alhassan7. article azojete vol 11 77 88 alhassan
7. article azojete vol 11 77 88 alhassan
 
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
 
IRJET- Study & Analysis of Subcontracting Practices in Infrastructure Project
IRJET- Study & Analysis of Subcontracting Practices in Infrastructure ProjectIRJET- Study & Analysis of Subcontracting Practices in Infrastructure Project
IRJET- Study & Analysis of Subcontracting Practices in Infrastructure Project
 
construction project managment_civileng
construction project managment_civilengconstruction project managment_civileng
construction project managment_civileng
 
Cost and time overruns in indian construction industry
Cost and time overruns in indian construction industryCost and time overruns in indian construction industry
Cost and time overruns in indian construction industry
 

Similar to IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation

REWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISION
REWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISIONREWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISION
REWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISIONIRJET Journal
 
IRJET- The Study on Evaluation of Cost Escalation in Infrastructure Proje...
IRJET-  	  The Study on Evaluation of Cost Escalation in Infrastructure Proje...IRJET-  	  The Study on Evaluation of Cost Escalation in Infrastructure Proje...
IRJET- The Study on Evaluation of Cost Escalation in Infrastructure Proje...IRJET Journal
 
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET Journal
 
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECTHOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECTIRJET Journal
 
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...IRJET Journal
 
A Critical Review of the Causes of Cost Overrun in Construction Industries in...
A Critical Review of the Causes of Cost Overrun in Construction Industries in...A Critical Review of the Causes of Cost Overrun in Construction Industries in...
A Critical Review of the Causes of Cost Overrun in Construction Industries in...IRJET Journal
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...IRJET Journal
 
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time ManagementIRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time ManagementIRJET Journal
 
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...IRJET Journal
 
Element of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewElement of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewIRJET Journal
 
IRJET- Factor Analysis of the Significant Drivers Causing Cost Variation in B...
IRJET- Factor Analysis of the Significant Drivers Causing Cost Variation in B...IRJET- Factor Analysis of the Significant Drivers Causing Cost Variation in B...
IRJET- Factor Analysis of the Significant Drivers Causing Cost Variation in B...IRJET Journal
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction ProjectIRJET Journal
 
IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...
IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...
IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...IRJET Journal
 
IRJET- Study and Analysis of Risk Management Strategies in Construction P...
IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...
IRJET- Study and Analysis of Risk Management Strategies in Construction P...IRJET Journal
 
IRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET Journal
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsDr. Amarjeet Singh
 
cost control analysis as effective tools in construction industry in nigeria
cost control analysis as effective tools in construction industry in nigeriacost control analysis as effective tools in construction industry in nigeria
cost control analysis as effective tools in construction industry in nigeriaNewman Jonathan
 
journalsresaim,+IJRESM_V3_I7_70.pdf
journalsresaim,+IJRESM_V3_I7_70.pdfjournalsresaim,+IJRESM_V3_I7_70.pdf
journalsresaim,+IJRESM_V3_I7_70.pdfKarthikeyanP288430
 

Similar to IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation (20)

REWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISION
REWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISIONREWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISION
REWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISION
 
IRJET- The Study on Evaluation of Cost Escalation in Infrastructure Proje...
IRJET-  	  The Study on Evaluation of Cost Escalation in Infrastructure Proje...IRJET-  	  The Study on Evaluation of Cost Escalation in Infrastructure Proje...
IRJET- The Study on Evaluation of Cost Escalation in Infrastructure Proje...
 
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
 
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECTHOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
 
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
 
A Critical Review of the Causes of Cost Overrun in Construction Industries in...
A Critical Review of the Causes of Cost Overrun in Construction Industries in...A Critical Review of the Causes of Cost Overrun in Construction Industries in...
A Critical Review of the Causes of Cost Overrun in Construction Industries in...
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...
 
I012646171
I012646171I012646171
I012646171
 
I012646171
I012646171I012646171
I012646171
 
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time ManagementIRJET- Effect of Pre-Planning in High Rise Building for Time Management
IRJET- Effect of Pre-Planning in High Rise Building for Time Management
 
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
 
Element of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewElement of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A Review
 
IRJET- Factor Analysis of the Significant Drivers Causing Cost Variation in B...
IRJET- Factor Analysis of the Significant Drivers Causing Cost Variation in B...IRJET- Factor Analysis of the Significant Drivers Causing Cost Variation in B...
IRJET- Factor Analysis of the Significant Drivers Causing Cost Variation in B...
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
 
IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...
IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...
IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...
 
IRJET- Study and Analysis of Risk Management Strategies in Construction P...
IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...
IRJET- Study and Analysis of Risk Management Strategies in Construction P...
 
IRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building Project
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure Projects
 
cost control analysis as effective tools in construction industry in nigeria
cost control analysis as effective tools in construction industry in nigeriacost control analysis as effective tools in construction industry in nigeria
cost control analysis as effective tools in construction industry in nigeria
 
journalsresaim,+IJRESM_V3_I7_70.pdf
journalsresaim,+IJRESM_V3_I7_70.pdfjournalsresaim,+IJRESM_V3_I7_70.pdf
journalsresaim,+IJRESM_V3_I7_70.pdf
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 

Recently uploaded (20)

complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 

IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 02 | Feb 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 2254 EFFECTS OF PROJECT COST ANALYSIS AND FACTORS AFFECTING INFLATION Avinash R. Yadav1, R.M. SWAMY2 1student, Civil Department, SSJCET, Maharashtra, India 2Assistant professor, Civil Department, SSJCET, Maharashtra, India --------------------------------------------------------------------***----------------------------------------------------------------------- Abstract;- Construction projects in India are experiencing widespread delays. The purpose is to test whether the project as specified will be economically viable or whether it will generate good value for money. Leaving such feasibilitystudiesuntilaftera project has started, may mean that potential problems are not revealed in time to influence project planning. Due to a dramatic shift in the capacity and volume of the Indian construction sector over the last decade, the need of a systematic analysis of the reasons of delays and developing a clear understanding among the industry professionalsarehighlycrucial. Usingaselected setof attributes, this research first identified the key factors impacting delay in Indian construction industry and then established the relationship between the critical attributes for developing prediction models for assessing the impacts of these factors on delay Delays caused by contractors can generally be attributes to poor managerial skills. Lack of planning and a poor understandingof accounting and financial principles have led to many a contractor’s downfall. Key Words: Cost Saving, Excess, Overrun 1. INTRODUCTION The construction industry is one of the main sectors that provide important ingredients for the development of an economy. The construction industry is the tool through which society achieves its goals of urban and rural development. However, it is becoming more complex because of the sophistication of the construction process itselfandthelarge numberof parties involved in the constructionprocess,i.e.,clients,users,designers, regulators,contractors,suppliers,subcontractors,and consultants. Modern construction projects are characterized by new standards, advanced technologies, multiparty participation, and frequent owner-desired changes. Coupled with this state are inherent uncertainties and complexitiesinthe physical, financial, and economic environment in which most projects are performed. Such conditions have made completing projects on schedule and on budget difficult task to accomplish often leading to claims on cost compensations and time extensions. This eventually leads to overrun in the completion of the project. Overrun could be defined as the time overrun either beyond completion date specified in a contract or beyond the date that the parties agreeuponfordeliveryof a project.It is slipping over its planned schedule and is considered as common problem in construction projects. Overrun in construction project is considered one of the most common problems causing a multitude negativeeffectontheprojectanditsparticipating parties. Therefore, it is essential to identify the actual causes of overrun in order to minimize andavoidtheoverrunsandtheir corresponding expenses. Overruns in construction can cause a number of changes in a project such as late completion, lost productivity, acceleration, increased costs, and contract termination. The party experiencing damages and the parties responsible for them are in turn responsible to recover time and cost. However, in general overrun situations are complex in nature. A overrun in an activity may not result in the same amount of project overrun. A delay caused by a party may or may not affect the project completion date and may or may not cause damagetoanotherparty.Adelaymayoccurconcurrentlywith other delays and all of them may impact the project completion date. 2. LITERATURE REVIEW Olabosipo, Fag Olabosipo, Et. Al., 2018. The growing need at maintaining steady cost projection of construction projects has been an issue of seriousconcern to both the clients and the construction practitioners on sites. This study therefore examinedthefactorsthatareconsideredto be affecting the cost management practice of constructionfirmsinthesouthwesternNigeria andalsoprofferedpossiblewaysof ameliorating the factors. It was concluded that extra focus should be placed on the identified factors with a view to reducing cost of construction, enhancing construction performance and building confidence within the construction industry in the study area.
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 02 | Feb 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 2255 Ghulam Abbas Niazi and Noel Painting, (2017) This research aims to identify the significant factorsthatlead toconstructioncostoverrunsinAfghanistan.Thefinding of the research is that the key critical causes that potentiallyresult inconstructioncostoverrunsinAfghanistanare: corruption, delay in progress payment by owner, difficulties in financing project by contractors, security, change the order by the owner during construction and market inflation. Olav Torp, Alemu Moges Belay, et. al. (2016). The research aim is threefold: firstly, to identify the critical factors of cost development in the planning phase. Secondly, to investigate empirically a dyadic relationship of cost deviation over time and quantitatively chart their developments. Thirdly, to analyze the construction cost data, discuss their cost developments and identify critical projects based on their actual financial impacts.Theresearchconsiders110projectsandanalyzethemusingqualitativeandquantitative research methods. The results showed higher cost escalation in the planning phase. The research identified critical factorsfor cost escalations at the planning phase. The average cost escalation of 110 projects (<5%) seems good, but some projects showed large cost deviations with lower financial impacts and vice versa. 3. RESEARCH GAP Overrun is one of the biggest problems offer experienced on construction project sites. Overrun in sites gets negative effect such as increased cost loss of productivity and revenue may low suits between owners and contractors and contract termination The study until now was carried out on the causes of overrun and inflation of project cost. Many researchers defined different methods for optimizing cost of project after overrun. This study will continue with framing a relationship between overrun and profitability of the project facing overrun problem. 4. CAUSES IN OVERRUN IN CONSTRUCTION The study identified ten most important causes of delayfroma listof69differentcauses.Tenmostimportantcauses ofoverrun were:  Contractor’s improper planning  Contractor’s poor site management  Inadequate contractor experience  Inadequate client’s finance and payments for completed work  Problems with subcontractors  Shortage in material  Labor supply  Equipment availability and failure  Lack of communication between parties  Mistakes during the construction stage The survey showed that all three groups generally agree on the ranking of individual overrun factors. The factors were categorized into nine major groups and were ranked. The nine groups were material, manpower, equipment, financing, changes, government relations, scheduling and controlling, environment, and contractual relationships. Based on the contractors surveyed, the most important overrun factors were:  Preparation and approval of shop  drawings  Delays in contractor’s progress  Payment by owners and  Design changes From the view of architects and engineers, the cashproblemsduringconstruction,therelationship betweensubcontractors and the slow decision-making progress of the owner were the main causes of overrun. However, the owners agreed that the design errors, labor shortages andinadequatelaborskillswereimportantoverrunfactors.Bothownersandconsultantsspecify labor and contractor related causes as the severe and important sources of overrun while, contractors indicate that the important sources of overrun in construction projects are owners and consultant.
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 02 | Feb 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 2256 5. CASE STUDY In this case study, Excess Amount required to complete the work with its reasons Construction of Multipurpose Building along with Community Centre at plot No. 24 Sec- 5 Kopar-Khairne project is studied for project overruns Average percentage is calculated by sum of all item’s excess percentage. Estimated amount is calculated by multiplying rate with estimated quantity and anticipated amount is calculated by multiplying rate with anticipated quantity. Excess amountiscalculatedbysubtractestimatedamountfromanticipatedamount and excess quantity is calculated by estimated quantity subtract from anticipated quantity. Excess percentage is calculatedby estimated amount subtract from excess amount. Average percentage is calculated by sum of all item’s excess percentage. Figure No. 1.1: Excess Amount, Estimated Amount and Anticipated Amount In the graph for case study 1 observed excess amount, estimated amount and anticipatedamount.Thebarsareshown estimated amount in dark blue colour and excess amount in green colour. The area graph shows the anticipated cost shownin grey colour on backside of bars. The excess amountismaximumfortotal ofpartVIIplasteringandmaximum estimatedamount is for total of part XII miscellaneous. In the graph X-axis shows the items and Y-axis shows the cost in Rs Figure No. 1.2: Saving amount and saving quantity Saving amount and saving quantity is calculated. Estimated amount is calculated by multiplying rate with estimated quantity and anticipated amount is calculated by multiplying rate with anticipated quantity. Saving amount is calculated by subtract anticipated amount from estimated amount and saving quantity is calculated by subtract anticipated quantity from estimated quantity. Saving percentage is calculated by anticipatedamountsubtractfromsavingamount.Average percentageis calculated by sum of all items saving percentage. In the graph observed saving amount, estimated amount and anticipated amount. The bars are shown anticipated amount in dark blue colour and saving amount in green colour. The area graph shows the estimated amount in grey colour on backside of bars. The saving amount is maximum for total ofpartXIImiscellaneousandmaximum estimatedamountisfortotal of part III R.C.C. In the graph X-axis shows the items and Y-axis shows the cost in Rs.
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 02 | Feb 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 2257 6. RESULT AND DISCUSSION Project Causes of overrun Due to Contractor Affecting Profitability of Project Contractor mainly affects the processof working and indirectly is responsible for overrun of project. Ineffective planning of contractor leads to shortage of material labour resources on site due to which the overrun in project is seen mainly the overrun due to contractor is due to improper planning of resources to be used on site. It is observed that in the table 1.1 Responsible Authority and Person is Contractor. The 20 causesofoverrun arehere. Addition of total respondents and frequencies of respondentsisgiveninthetable.Thepercentageof eachcauseiscalculatedby RII method, the highest percentage is 68.00% for cause lack of sub-contractor skills and lowestpercentageis56.67%fordelay in reviewing the design documents. Figure No. 1.3: Frequencies of Rating for Contractor It is observed that in the graph are frequencies of rating for client. The frequencies of rating for 20 causes of overrun are here. On X-axis causes of overrun is plotted and on Y-axis frequency is plotted. In this graph 5 frequencies show of 30 respondents. The rating of frequency no 1 is show in blue color is high and frequency no 5 show in red color is low. Figure No. 1.4: RII Ranking for Contractor It is observed that in the graph is RII ranking for client. The frequencies of rating for 20 causes of overrun are here. On X- axis causes of overrun is plotted and on Y-axis cumulative ranking is plotted. In this graph total response and RII ranking are plotted. EVM Calculation & Scheduling in MSP Observed in the above figure shows the table of MSP (Microsoft office Project) scheduling with EVM (Earned Value Method) for case study 1. In the Microsoft Project all the work means task added in task columninGanttChartwithduration in day or hours then add the resources in resources sheet with cost per day or per hour. When apply in table earned value then columns like Planned value (PV), Earned value (EV), Actual cost (AC), Schedule Variance (SV), Cost Variance (CV), Estimate at Completion (EAC), Budget at Completion(BAC)andVarianceatCompletion(VAC)columnsareseenandSchedulePerformance Index (SPI) & Cost Performance Index (CPI) columns are added by insert column in table
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 02 | Feb 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 2258 The scheduling of work is observed in above figure1.2. The blue bars seen in the figure are indicating the duration of work and one work is complete then another work is start. In the MSP (Microsoft Project) we set the calendar for number of days of work, number of working hours, weekly holiday, national holidays, etc.Theblack lineinthe blue barisindicatethe how much work is completed in percentage. If work is 100% complete then black line on whole blue bar. Sr. No. Cause of Overrun Responsible Authority and Person RII % 1 Poor coordination and communication b/t contractor and other parties Contractor 0.55 55.33 2 Financial difficulties by contractors Contractor 0.57 57.33 3 Delay in site mobilization Contractor 0.61 60.67 4 Often changing sub-contractors Contractor 0.52 52.00 5 Mistakes during construction by contractors Contractor 0.51 50.67 6 Poor contractors experience Contractor 0.58 58.00 7 Ineffective planning and scheduling Contractor 0.50 50.00 8 Ineffective coordination between contractors and other parties Contractor 0.55 54.67 9 Lack of sub-contractor skills Contractor 0.68 68.00 10 Poor site management by contractors Contractor 0.56 56.00 11 Lack of sufficient experience of consultants Contractor 0.61 60.67 12 Delay in reviewing the design documents Contractor 0.52 52.00 13 Poor inspection plan by consultants Contractor 0.57 56.67 14 Project design complexity Contractor 0.53 52.67 15 Mistakes and discrepancies in design documents Contractor 0.57 56.67 16 Poor coordination/communication between consultant & parties Contractor 0.51 51.33 17 Slowness in giving instruction Contractor 0.55 55.33 18 Inadequate quality assurance and quality control plans Contractor 0.49 56.67 19 Conflicts amongst consultant with other parties Contractor 0.51 51.33 20 Delay in reporting the progress of works done Contractor 0.51 51.33 Table No. 1.1: Causes of Overrun Affecting to Contractor
  • 6. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 02 | Feb 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 2259 Table No. 1.2:Causes of Overrun Ranking for Contractor Sr. No. Cause of Overrun Responsible Authority and Person RII Ranking 9 Lack of sub-contractor skills Contractor 0.68 1 3 Delay in site mobilization Contractor 0.61 2 11 Lack of sufficient experience of consultants Contractor 0.61 3 6 Poor contractors experience Contractor 0.58 4 2 Financial difficulties by contractors Contractor 0.57 5 13 Poor inspection plan by consultants Contractor 0.57 6 15 Mistakes and discrepancies in design documents Contractor 0.57 7 10 Poor site management by contractors Contractor 0.56 8 1 Poor coordination and communication b/t contractor and other parties Contractor 0.55 9 17 Slowness in giving instruction Contractor 0.55 10 8 Ineffective coordination between contractors and other parties Contractor 0.55 11 14 Project design complexity Contractor 0.53 12 4 Often changing sub-contractors Contractor 0.52 13 12 Delay in reviewing the design documents Contractor 0.52 14 16 Poor coordination/communication between consultant & parties Contractor 0.51 15 19 Conflicts amongst consultant with other parties Contractor 0.51 16 20 Delay in reporting the progress of works done Contractor 0.51 17 5 Mistakes during construction by contractors Contractor 0.51 18 7 Ineffective planning and scheduling Contractor 0.50 19 18 Inadequate quality assurance and quality control plans Contractor 0.49 20
  • 7. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 02 | Feb 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 2260 Figure No.1. 5: MSP Calculations Figure No. 1.6: Calculation MSP Scheduling
  • 8. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 02 | Feb 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 2261 Figure No. 1.7: Earned Value over Time Report 7. CONCLUSIONS The Overruns in cost and time is a never-ending threat to a construction manager and is being faced in all types of projects which include infrastructureprojects,heavyconstructionprojects,residential orcommercial construction projectsetc. By studying various literature review from all across world and considering three working local sites as case study on which various attributes of reducing cost overrun is analyses. The following are result from the sets of projects considered which showed large cost deviation. • The first three factors ranked by RII method first is conflict between labour, second lack of sub-contractor skills and third is poor financial control mechanism. The first one conflict between labour in the category of labour its RII is 0.70, second one lack of sub-contractor skills in the category of contractor its RII is 0.68 and third one poor financial control mechanism in the category is client its RII is 0.63. • Te severity index and frequency index of the factors are, for conflict between labour is 70.00, for lack of sub- contractor skills is 68.00 and for poor financial control mechanism is 63.33. • The average of percentage excess for case study 1 is 1.02 and percentage saving is 1.10. The average of percentage excess for case study 2 is 2.71 and percentage saving is 4.39. Theaverageof percentageexcessfor case study 3 is 1.90 and percentage saving is 0.15. • The average percentage cost growth rate for all three case studies is 98.62% and average actual cost percentage change for all three case studies is 97.20%. 8. REFERENCES 1. Ahmed Senouci, Alaa Ismail & Neil Eldin, “Time Delay and Cost Overrun in Qatari Public Construction Projects”, Procedia Engineering, Vol.164, Pp. No.368 – 375, (2016). 2. Ali Touran and Ramon Lopez, “Modeling Cost Escalation In Large Infrastructure Projects”,J. Constr. Eng. Manage., Vol.132, Pp. No.853-860, (2006).
  • 9. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 02 | Feb 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 2262 3. Anna Wasiluk, “Pro-Innovative Prerequisites for Establishing The Cooperation Between Companies”, Procedia Engineering, Vol.182, Pp. No. 755 – 762, (2017). 4. Artur Czech & Jerzy Lewczuk, “Statistical Assessment of The Development of The Transportation System in Chosen Countries – An International Approach”, Procedia Engineering, Vol.182, Pp. No.112 – 119, (2017). 5. Alfredo Serpell, José Ignacio Díaz, “Linking Central Business Processes of Construction Companies Within the Performance of Construction Operations: A Preliminary Exploration”, CreativeConstructionConference,Vol.-164,Pp. No. 25-28, 2016. 6. Berrak Bahadir, Olena Mykhaylova, “Housing Market Dynamics with Delays in The Construction Sector”, Journal of Housing Economics, Vol.- 26 Pp. No. 94–108, 2014. 7. Divya. R, S. Ramya, “Causes, Effects and Minimization of Delays in Construction Projects”, National Conference on Research Advances in Communication, Computation, Electrical Science and Structures (2015). 8. Dr. Shabbab Al Hammadi & M. Sadique Nawab, “Project Time Overruns in Saudi Arabian Con-Struction Industry”, International Journal of Scientific & Engineering Research, Vol.7, (2016). 9. David Arditi , Shruti Nayak , Atilla Damci, “Effect Of Organizational Culture On Delay In Construction”, International Journal of Project Management, Vol.- 35 Pp. No. 136–147, 2017. 10. Garry D. Creedy, Martin Skitmore and Johnny K. W. Wong, “Evaluation of Risk Factors Leading to Cost Overrun in Delivery of Highway Construction Projects”, J. Constr. Eng. Manage, Vol.136, Pp. No.528-537, (2010). 11. Ghulam Abbas Niazi & Noel Painting, “Significant Factors Causing Cost Overruns in The Construction Industry in Afghanistan”, Procedia Eng, Vol.182, Pp. No.510 – 517, (2017). 12. Gul Polat, Ferzan Okay & Ekin Eray, “Factors Affecting Cost Overruns in Micro-Scaled Construction Companies”, Procedia Eng, Vol.85, Pp. No. 428-435, (2014). 13. G. Sweis, R. Sweis, A. Abu Hammad, A. Shboul, “Delays in construction projects: The case of Jordan”, International Journal of Project Management, Vol.- 26, Pp. No. 665–674, (2008). 14. Hemanta Doloi & Anil Sawhney, et. al., “Analysing Factors Affecting Delays in Indian Construction Projects”, International Journal of Project Management, Vol.30, Pp. No.479–489, (2012). 15. Jennifer S. Shane, A.M. ASCE & KEITH R. MOLENAAR, ET. AL., “ConstructionProjectCostEscalationFactors”,J.Manage. Eng., Vol.25, Pp. No.221-229, (2009). 16. Jesus M. De La Garza and John W. Melin, “Prepayment Ability to Offset Inflation”, J. Constr. Eng. Manage., Vol.112, Pp. No.514-529, 1986. 17. Krystyna Araszkiewicz, “Application of Critical Chain Management in Construction Projects Schedules In A Multi- Project Environment: A Case Study”, Procedia Engineering, Vol.182, Pp. No. 33 – 41, (2017). 18. Majed Alzara, Jacob Kashiwagi, Dean Kashiwagi, Abdulrahman Al-Tassan, “Using PIPS to Minimize Causes OfDelayIn Saudi Arabian Construction Projects: University Case Study”, Procedia Eng, Vol.- 145 Pp. No. 932 – 939, 2016. 19. N. Hamzah, M.A. Khoiry, I. Arshad, N. M. Tawil and A. I. Che Ani, “Cause of Construction Delay – Theoretical Framework”, Procedia Eng, Vol.- 20, Pp. No. 490 – 495, 2011 20. Olabosipo, Fagbenle, Opeyemi, Joshua, Et. Al., “Cost Management Practice of Construction Firms and Its Influencing Factors: Lessons from Southwestern Nigeria”, Construction Research Congress 2018.
  • 10. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 02 | Feb 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 2263 21. Olav Torp, Alemu Moges Belay, et. al. “Cost Development Over-Time At Construction Planning Phase: Empirical Evidence From Norwegian Construction Projects”, Procedia Engineering, Vol.145, Pp. No.1177 – 1184, (2016). 22. Peter E. D. Love & Xiangyu Wang, “Determining the Probability of Project Cost Overruns”, J. Constr. Eng. Manage., Vol.139, Pp. No.321-330, (2013). 23. Prakash Kumar & Piush Raj, “Delay Analysis ofProjects andEffectsofDelaysinTheMining/ManufacturingIndustries”, Vol. 12, PP. 61-71, (2015). 24. Romualdas Ginevičius, Dainora Gedvilaitė & Andrius Stasiukynas, “Assessment of The Interrelations Between Economic and Ecological Development in Regions of Lithuania”, Procedia Engineering, Vol.182, Pp. No.213 – 221, (2017). 25. Sadi A. Assaf & Sadiq Al-Hejji, “Causes of Delay In Large Construction Projects”, International Journal of Project Management, Vol. 24, Pp. No. 349–357, (2006).