International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 03 Issue: 01 | Jan-2016 www.irjet.net p-ISSN: 2395-0072
© 2016, IRJET | Impact Factor value: 4.45 | ISO 9001:2008 Certified Journal | Page 1173
RII & IMPI: EFFECTIVE TECHNIQUES FOR FINDING DELAY IN
CONSTRUCTION PROJECT
Mamata Rajgor 1 , Chauhan Paresh 2, Patel Dhruv 3 ,Panchal chirag 4 ,Bhavsar Dhrmesh5
1Assistant Professor. Civil Engg. Babaria institute of Technology, varnama, Gujarat, India
2345 Student of final year BE, Babaria institute of Technology ,varnama ,Gujarat
---------------------------------------------------------------------***---------------------------------------------------------------------
Abstract - Delays are unique one in every of the
largest issues construction companies are facing today.
The research presents the result of the questionnaires
survey conducted to identify and evaluate the relative
importance of the significant factors contributing to
delay in construction project. Construction projects are
heavily affected by causes of delay, if anybody doesn’t
knows which are the factors that causes delay then they
cannot be succeeded. The project investigated in this
study included residential building, office building
projects and high rise building .In this research the
project team members i.e. owner, contractor,
consultant, Engineers etc. are taken for questionnaire
survey to obtain the delay factors and research to
identify the main causes and effects of delay in
construction projects.
Key Words: Project management, Inventory, Cost
efficient, Survey, Relative important index (RII),
Importance index (IMPI)
1. INTODUCTION
In construction work delay is defined as time more
time consuming either beyond completion date of the
project which is given to the contractor and given to
the parties for delivery of it. Project delay is on over
its planned schedule and is considered as common
problem in construction projects. To the owner of the
project delay means loss of money through lack of
production facilities and rentable space. To the
contractor delay means higher overhead cost because
of longer time of project, higher material cost,
machinery and labour cost increase. The construction
process is subjected to various and unwanted factors
which result from many sources. These sources
include availability of resources, environmental
condition, performance of various parties,
involvement of other parties and contractual relations.
It is very rarely happen that project completed in the
specified time period. Delay means more activities are
pending which mentioned within the contract
duration of project. For various parties definition of
delay is different such as for owner delay means low
income in more time, for consultant delay means more
work remaining in less time period etc. so because of
delay project cost, material cost, government charges
and overall cost are increase. All these factors are
related to causes if delay so, we can find the causes of
delay in construction to increase the performance of
project. For any construction projects requirement of
work is very high so, owner needs planning at which
time and cost of project is satisfy. This can be listed
out by proper planning and by identification of causes
of delay.
2. 0BJECTIVES
To study the Factors affecting on Delay.
To identify the key factors affecting on different
Mega projects and their behavior.
To evaluate the critical factors affecting the Delay.
To identify the approaches for solving the
problems regarding delay.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 03 Issue: 01 | Jan-2016 www.irjet.net p-ISSN: 2395-0072
© 2016, IRJET | Impact Factor value: 4.45 | ISO 9001:2008 Certified Journal | Page 1174
To minimize the effect of delay in construction
project.
3. RESEARCH METHODOLOGY
The data collected to determine the most
influential factors on project management of the project
was done through a survey by explorative questionnaire to
the respondents involved in daily activities of construction
firms in various regions in the Gujarat region of India. The
questionnaire was designed so that respondents can give
the rank to their answers based on their opinions. The
analysis of these data was done by a method named
relative importance index (RII) method as well as
important index (IMPI).
4. DATA COLLECTION
The target population included civil engineering and
buildings construction firms of central Gujarat region of
India. The architects, contractors and developers of
various Vadodara and of various cities of Gujarat who
work in Vadodara were targeted for survey. The details of
various stakeholders and total numbers of were collected
through internet. These details were considered as size of
population to decide sample size of study.
We distributed over a 100 Questionnaires, out of which we
received 60 questionnaires. The analysis of these
questionnaires helped us calculate the Relative
Importance Index and Important index of each clause. We
received responses from a pretty diverse group of
professionals ie owners, contractors, builders, architects,
consultants, etc
A. Relative Importance Index Technique: It is used
determine the relative importance of the various
causes and effects of delays. The same method is going
to adopted in this study within various groups (i.e.
contractors, project engineers, owner and site
supervisor). The four-point scale ranged from 1 (vey
little degree affect) to 4 (very high degree affect) is
adopted and transformed to relative importance
indices (RII) for each factor as follows:
RII = ΣW / (A*N)
Where, W is the weighting given to each factor by the
respondents (ranging from 1 to 4), A is the highest
weight (i.e. 4 in this case), and N is the total number of
respondents. Higher the value of RII, more important
was the cause of delays.
B. Importance Index Technique -In this technique, for
each cause/factor two questions were asked: What is
the frequency of occurrence for this cause? And what is
the degree of severity of this cause on project delay?
Both frequency of occurrence and severity were
categorized on a four-point scale. Frequency of
occurrence is categorized as follows: always, often,
sometimes and rarely (on 4 to 1 point scale). Similarly,
degree of severity was categorized as follows: extreme,
great, moderate and little (on 4 to 1 point scale).
C. Frequency index: A formula is used to rank causes of
delay based on frequency of occurrence as identified by
the participants.
Frequency Index (F.I.) (%) = Σ a (n/N) * 100/4….(4)
Where, a is the constant expressing weighting given to
each response (ranges From 1 for rarely up to 4 for
always), n is the frequency of the responses, and N is
total number of responses.
D. Severity index: A formula is used to rank causes of
delay based on severity as indiacated by the
participants.
Severity Index (S.I.) (%) = Σ a (n/N) * 100/… (5)
Where a is the constant expressing weighting given to
each response (ranges from 1 for little up to 4 for
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 03 Issue: 01 | Jan-2016 www.irjet.net p-ISSN: 2395-0072
© 2016, IRJET | Impact Factor value: 4.45 | ISO 9001:2008 Certified Journal | Page 1175
severe), n is the frequency of the responses, and N is
total number of responses.
E. Importance index: The importance index of each cause
is calculated as function of both frequency and
severity indices, as follows:
Importance Index (IMPI) (%) = [F.I. * S.I.]/100… (6)
5. RESULTS
PART – 1 RII Results
Top 10 causes ranked by Relative Importance Index (RII)
technique
The relative importance index, RII, was computed for
each cause to identify the most significant causes. The
causes were ranked based on RII values. From the
ranking assigned to each cause of delays, it was possible
to identify the most important factors or causes of delays
in Indian construction industry.
Base on the ranking, the 10 most important causes of
material management by RII were:
Table -1: Critical Causes of delay by RII Method
No Critical Causes of delay RII
1 Shortage of labours (A) 0.84
2 Delay in material delivery(B) 0.83
3
Poor site management and supervision by
contractor (C )
0.82
4
Improper construction methods implemented by
contractor (D)
0.82
5 Rework due to errors during construction (E ) 0.81
6 Change orders by owner during construction (F) 0.81
7
Poor communication and coordination by owner
and other parties (G)
0.80
8 Slowness in decision making process by owner(H) 0.79
9
Poor communication& coordination by contractor
with other parties (I)
0.79
10 Original contract duration is too short (J) 0.78
Chart -1: Critical Causes of Delay by RII Method
PART-2 IMPI Results
Top 10 causes ranked by Importance Index (IMPI)
technique
Table -2: Critical Causes of delay by IMPI Method
No Critical Causes for delay
FI
(%)
SI
(%)
IMPI
(%)
1
Change orders by owner
during construction (A)
77 79 60.83
2
Original contract duration is
too short (B)
79 73 57.67
3
Poor communication and
coordination by owner and
other parties (C)
73.2 78.5 57.47
4
Slowness in decision making
process by owner (D)
73.2 78.5 57.47
5
Poor site management and
supervision by contractor (E)
73 76.5 55.85
6 Delay in material delivery (F) 75 71 53.25
7
Delay in progress payments
by owner (G)
69 77 53.13
8
Personal conflicts among
labours (H)
70 75.5 52.85
9
Delay in providing services
from utilities (such as water,
electricity) (I)
69.5 75.5 52.48
10
Improper construction
methods implemented by
contractor (J)
70 74.5 52.15
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 03 Issue: 01 | Jan-2016 www.irjet.net p-ISSN: 2395-0072
© 2016, IRJET | Impact Factor value: 4.45 | ISO 9001:2008 Certified Journal | Page 1176
Chart -2: Critical Causes of Delay by IMPI Method
6. CONCLUSION
Delays can be avoided or minimized when their causes
are clearly identified. The aim of this report was to
identify the delay factors in construction projects, since
delays are considered to be a serious problem in the
construction industry. The paper addressed the most
significant factors and groups to cause delays.
According to the findings above, following points can be
recommended in order to minimize and control delays in
construction projects:
1) Advance arrangement of equipment’s should be made
or equipment should purchase on rent.
2) The quality and experience of labor supply can have
major impact on the projects. Unexperienced labor may
lead to inefficient work and may cause accidents during
construction.
3) Site management and supervision should be made in a
correct manner. Administrative staff should be assigned to
make necessary arrangements to complete the project
within specified time while satisfying required quality and
estimated cost.
4) Approval of design documents should not be late, since
it could delay the progress of work. Progress payments
should be made on time to contractor to finance the work.
5) Finding out G.L. water pipe connection leakage and
quickly take appropriate action consulting with structural
engineer like (Pile foundation, providing impervious layer
etc.)
7. ACKNOWLEDGEMENT
The Authors thankfully acknowledge to Mr J.D.Patel,
Chairman, BITS edu Campus, Mr Dhruv.J.Patel, Vice
Chairman, BITS edu Campus, Dr. N.D.Shah, Principal,
Babaria Institute of Engineering College, Dr. L.S.Thakur,
Head and Professor, Civil Engineering Department,
Babaria Institute of Engineering College, for their
motivations and infrastructural support to carry out this
research.
8. REFERENCES
1. Aditi Dinakar “Delay Analysis in Construction Project”
(Volume 4, Issue 5, May 2014)
2. Ashish D. Joshi1, Prof. Dr. S.D. Khandekar, “Project
Management for Construction Projects: Improving
Project Performance”(volume02 Issue: 03 | June-2015)
3. Arditi R.D., Akan G.T., Gurdamar S. (1985). “Reasons for
Delays in Public Projects in Turkey”. Construction
Management and Economics. 3: 171-181.
4. Assaf, S.A., Al-Khalil, M. and A-Hazmi, M. (1995).
“Causes of Delay in Large Building Construction
Projects”. Journal of Management in Engineering. ASCE:
45-50.
5. Eckert Scott Grant, “Inventory Management and Its
Effects on Customer satisfaction”, Journal of Business
and Public Policy, Volume-1 Number-3, Summer 2007,
1936-9794
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056
Volume: 03 Issue: 01 | Jan-2016 www.irjet.net p-ISSN: 2395-0072
© 2016, IRJET | Impact Factor value: 4.45 | ISO 9001:2008 Certified Journal | Page 1177
6. Dennis Daina R. and Meredith Jack R., “An analysis of
Process Industry Production and Inventory
Management Systems”, Journal of Operations
Management, 18 (2000) 683-699.
7. Desai Megha, Dr Bhatt Rajiv “A Methodology for
Ranking of Causes of Delay for Residential Construction
Projects in Indian Context” (Volume 3, Issue 3, March
(2013)
8. Desai Megha, Rajiv Bhatt, “Critical Causes of Delay in
Residential Construction Projects: Case Study of
Central Gujarat Region of India “(Volume-4 Issue-4,
Year of Publication: 2013)
9. Kasim Narimah, Liwan Siti Radziah, Shamsuddin Alina,
Zainal Rozlin and Kamaruddin Naadira che, “Improving
on Site Material Tracking for Inventory Management in
Construction Projects”, Proceedings International
Conference of Technology Management, Business and
Entrepreneurship, 2012
10. Patil Ashwini R. and Pataskar Smita J., “Analysing
Material Management Techniques on Construction
Project”, International Journal of Engineering and
Innovative Technology, Volume-3 Issue-4, October
2013, 2277-3754
11. Patel Khyomesh V. and Prof. Chetna M.
Vyas,“Construction Material Management on Project
Site”, National Conference on Recent Trends in
Engineering & Technology, May-2011
12. Patel Hemish A, Jayeshkumar Pitroda and J. J.
Bhavsar, “A Review on Material Management
through Inventory Management “, Journal of
International Academic Research for Multidisciplinary,
Volume-2 Issue-12, January 2015, 2320-5083.
13. Sugiharto Alwi ,Keith Hampson “IDENTIFYING THE
IMPORTANT CAUSES OF DELAYS IN BUILDING
CONSTRUCTION PROJECTS “(2003)
14. N.Hamzah,M.A.Khoiry, I. Arshad, W.H.W.
Badaruzzaman, and N. M. Tawil “Identification of the
Causes of Construction Delay in Malaysia”
Environmental, structural, Construction and
Architectural Engineering Vol: 6, No: 12, 2012
15. Sahari Salawati, Tinggi Michael and Kadri
Norlina, “Inventory Management in Malaysian
Construction Firm: Impact on Performance”, SIU
Journal of Management, Volume-2 Number-1,
June 2012, 2229-0044
16. Sindhu S., Dr. K. Nirmalkumar and
Krishnamoorthy V., “Performance Analysis of
Inventory Management System in Construction
Industry in India”, International Journal of
Innovative Research in Science, Engineering and
Technology, Volume-3 Issue-4, April 2014, 2319-
8753
17. Songer, A. D., and Molenaar, K. R. ~1997.
„„Project characteristics for successful public-
sector design-build.‟‟ J. Constr. Eng. Manage,
123(1), 34–40.

More Related Content

What's hot

causes and implication of delay in construction
causes and implication of delay in constructioncauses and implication of delay in construction
causes and implication of delay in construction
sudinak
 
IT Services Management
IT Services ManagementIT Services Management
IT Services Management
Chetan Goenka
 
Leak d Detection feasibility study iFluids Engineering
Leak d Detection feasibility study iFluids EngineeringLeak d Detection feasibility study iFluids Engineering
Leak d Detection feasibility study iFluids Engineering
John Kingsley
 

What's hot (20)

IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...
IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...
IRJET- Evaluation of Rework Factors Affecting Cost and Schedule Performance i...
 
IRJET-A Study on Factors Affecting Labour Productivity by Application of Rela...
IRJET-A Study on Factors Affecting Labour Productivity by Application of Rela...IRJET-A Study on Factors Affecting Labour Productivity by Application of Rela...
IRJET-A Study on Factors Affecting Labour Productivity by Application of Rela...
 
Factor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road projectFactor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road project
 
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
To Minimize The Time And Cost Overrun Of Similar Buildings ( p6 primavera )
 
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsDELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
 
Project management
Project management Project management
Project management
 
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
 
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTSFACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
 
SRA_Vinit1
SRA_Vinit1SRA_Vinit1
SRA_Vinit1
 
causes and implication of delay in construction
causes and implication of delay in constructioncauses and implication of delay in construction
causes and implication of delay in construction
 
IT Services Management
IT Services ManagementIT Services Management
IT Services Management
 
Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...
 
SHAMSHAD QAQC RESUME
SHAMSHAD QAQC RESUMESHAMSHAD QAQC RESUME
SHAMSHAD QAQC RESUME
 
Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...
 
Construction KPIs & Dashboards
Construction KPIs & DashboardsConstruction KPIs & Dashboards
Construction KPIs & Dashboards
 
Leak d Detection feasibility study iFluids Engineering
Leak d Detection feasibility study iFluids EngineeringLeak d Detection feasibility study iFluids Engineering
Leak d Detection feasibility study iFluids Engineering
 
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
 
Primavera EPPM case study - Oracle Primavera P6 Collaborate 14
Primavera EPPM case study - Oracle Primavera P6 Collaborate 14Primavera EPPM case study - Oracle Primavera P6 Collaborate 14
Primavera EPPM case study - Oracle Primavera P6 Collaborate 14
 
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
 

Similar to RII & IMPI: Effective Techniques for Finding Delay in Construction Project

Success factors enhancing business performance of engineering procurement c...
Success factors enhancing business performance of  engineering procurement  c...Success factors enhancing business performance of  engineering procurement  c...
Success factors enhancing business performance of engineering procurement c...
IAEME Publication
 
Success factors enhancing business performance of engineering procurement
Success factors enhancing business performance of engineering procurementSuccess factors enhancing business performance of engineering procurement
Success factors enhancing business performance of engineering procurement
IAEME Publication
 

Similar to RII & IMPI: Effective Techniques for Finding Delay in Construction Project (20)

Impact of delayness on construction projects
Impact of delayness on construction projectsImpact of delayness on construction projects
Impact of delayness on construction projects
 
Ijciet 08 04_220
Ijciet 08 04_220Ijciet 08 04_220
Ijciet 08 04_220
 
Management For Construction Project:-Various Aspects Of Delay
Management For Construction Project:-Various Aspects Of DelayManagement For Construction Project:-Various Aspects Of Delay
Management For Construction Project:-Various Aspects Of Delay
 
IRJET- Identification of Crucial Factor Affecting to Sustainable Construc...
IRJET-  	  Identification of Crucial Factor Affecting to Sustainable Construc...IRJET-  	  Identification of Crucial Factor Affecting to Sustainable Construc...
IRJET- Identification of Crucial Factor Affecting to Sustainable Construc...
 
I012646171
I012646171I012646171
I012646171
 
I012646171
I012646171I012646171
I012646171
 
IRJET-Survey on Effects of Productivity of Equipment in Construction Projects
IRJET-Survey on Effects of Productivity of Equipment in Construction ProjectsIRJET-Survey on Effects of Productivity of Equipment in Construction Projects
IRJET-Survey on Effects of Productivity of Equipment in Construction Projects
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure Projects
 
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTINVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
 
­­Construction Quality Auditing
­­Construction Quality Auditing­­Construction Quality Auditing
­­Construction Quality Auditing
 
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential ProjectsExploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
 
Success factors enhancing business performance of engineering procurement c...
Success factors enhancing business performance of  engineering procurement  c...Success factors enhancing business performance of  engineering procurement  c...
Success factors enhancing business performance of engineering procurement c...
 
Success factors enhancing business performance of engineering procurement
Success factors enhancing business performance of engineering procurementSuccess factors enhancing business performance of engineering procurement
Success factors enhancing business performance of engineering procurement
 
Delay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index MethodDelay Analysis in Industrial Projects by using Relative Importance Index Method
Delay Analysis in Industrial Projects by using Relative Importance Index Method
 
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting InflationIRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
 
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
Evaluation of Factors Causing Conflicts & Dispute in Construction Projects by...
 
IRJET- Analysis of Change Order in Road Construction Projects
IRJET-  	  Analysis of Change Order in Road Construction ProjectsIRJET-  	  Analysis of Change Order in Road Construction Projects
IRJET- Analysis of Change Order in Road Construction Projects
 
Element of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewElement of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A Review
 
IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET - Forecasting and Management of Triple Constraints in Construction proj...IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET - Forecasting and Management of Triple Constraints in Construction proj...
 
Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis
 

More from IRJET Journal

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
ankushspencer015
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
ssuser89054b
 
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
dharasingh5698
 
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
amitlee9823
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 

Recently uploaded (20)

Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
 
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdf
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 

RII & IMPI: Effective Techniques for Finding Delay in Construction Project

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 03 Issue: 01 | Jan-2016 www.irjet.net p-ISSN: 2395-0072 © 2016, IRJET | Impact Factor value: 4.45 | ISO 9001:2008 Certified Journal | Page 1173 RII & IMPI: EFFECTIVE TECHNIQUES FOR FINDING DELAY IN CONSTRUCTION PROJECT Mamata Rajgor 1 , Chauhan Paresh 2, Patel Dhruv 3 ,Panchal chirag 4 ,Bhavsar Dhrmesh5 1Assistant Professor. Civil Engg. Babaria institute of Technology, varnama, Gujarat, India 2345 Student of final year BE, Babaria institute of Technology ,varnama ,Gujarat ---------------------------------------------------------------------***--------------------------------------------------------------------- Abstract - Delays are unique one in every of the largest issues construction companies are facing today. The research presents the result of the questionnaires survey conducted to identify and evaluate the relative importance of the significant factors contributing to delay in construction project. Construction projects are heavily affected by causes of delay, if anybody doesn’t knows which are the factors that causes delay then they cannot be succeeded. The project investigated in this study included residential building, office building projects and high rise building .In this research the project team members i.e. owner, contractor, consultant, Engineers etc. are taken for questionnaire survey to obtain the delay factors and research to identify the main causes and effects of delay in construction projects. Key Words: Project management, Inventory, Cost efficient, Survey, Relative important index (RII), Importance index (IMPI) 1. INTODUCTION In construction work delay is defined as time more time consuming either beyond completion date of the project which is given to the contractor and given to the parties for delivery of it. Project delay is on over its planned schedule and is considered as common problem in construction projects. To the owner of the project delay means loss of money through lack of production facilities and rentable space. To the contractor delay means higher overhead cost because of longer time of project, higher material cost, machinery and labour cost increase. The construction process is subjected to various and unwanted factors which result from many sources. These sources include availability of resources, environmental condition, performance of various parties, involvement of other parties and contractual relations. It is very rarely happen that project completed in the specified time period. Delay means more activities are pending which mentioned within the contract duration of project. For various parties definition of delay is different such as for owner delay means low income in more time, for consultant delay means more work remaining in less time period etc. so because of delay project cost, material cost, government charges and overall cost are increase. All these factors are related to causes if delay so, we can find the causes of delay in construction to increase the performance of project. For any construction projects requirement of work is very high so, owner needs planning at which time and cost of project is satisfy. This can be listed out by proper planning and by identification of causes of delay. 2. 0BJECTIVES To study the Factors affecting on Delay. To identify the key factors affecting on different Mega projects and their behavior. To evaluate the critical factors affecting the Delay. To identify the approaches for solving the problems regarding delay.
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 03 Issue: 01 | Jan-2016 www.irjet.net p-ISSN: 2395-0072 © 2016, IRJET | Impact Factor value: 4.45 | ISO 9001:2008 Certified Journal | Page 1174 To minimize the effect of delay in construction project. 3. RESEARCH METHODOLOGY The data collected to determine the most influential factors on project management of the project was done through a survey by explorative questionnaire to the respondents involved in daily activities of construction firms in various regions in the Gujarat region of India. The questionnaire was designed so that respondents can give the rank to their answers based on their opinions. The analysis of these data was done by a method named relative importance index (RII) method as well as important index (IMPI). 4. DATA COLLECTION The target population included civil engineering and buildings construction firms of central Gujarat region of India. The architects, contractors and developers of various Vadodara and of various cities of Gujarat who work in Vadodara were targeted for survey. The details of various stakeholders and total numbers of were collected through internet. These details were considered as size of population to decide sample size of study. We distributed over a 100 Questionnaires, out of which we received 60 questionnaires. The analysis of these questionnaires helped us calculate the Relative Importance Index and Important index of each clause. We received responses from a pretty diverse group of professionals ie owners, contractors, builders, architects, consultants, etc A. Relative Importance Index Technique: It is used determine the relative importance of the various causes and effects of delays. The same method is going to adopted in this study within various groups (i.e. contractors, project engineers, owner and site supervisor). The four-point scale ranged from 1 (vey little degree affect) to 4 (very high degree affect) is adopted and transformed to relative importance indices (RII) for each factor as follows: RII = ΣW / (A*N) Where, W is the weighting given to each factor by the respondents (ranging from 1 to 4), A is the highest weight (i.e. 4 in this case), and N is the total number of respondents. Higher the value of RII, more important was the cause of delays. B. Importance Index Technique -In this technique, for each cause/factor two questions were asked: What is the frequency of occurrence for this cause? And what is the degree of severity of this cause on project delay? Both frequency of occurrence and severity were categorized on a four-point scale. Frequency of occurrence is categorized as follows: always, often, sometimes and rarely (on 4 to 1 point scale). Similarly, degree of severity was categorized as follows: extreme, great, moderate and little (on 4 to 1 point scale). C. Frequency index: A formula is used to rank causes of delay based on frequency of occurrence as identified by the participants. Frequency Index (F.I.) (%) = Σ a (n/N) * 100/4….(4) Where, a is the constant expressing weighting given to each response (ranges From 1 for rarely up to 4 for always), n is the frequency of the responses, and N is total number of responses. D. Severity index: A formula is used to rank causes of delay based on severity as indiacated by the participants. Severity Index (S.I.) (%) = Σ a (n/N) * 100/… (5) Where a is the constant expressing weighting given to each response (ranges from 1 for little up to 4 for
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 03 Issue: 01 | Jan-2016 www.irjet.net p-ISSN: 2395-0072 © 2016, IRJET | Impact Factor value: 4.45 | ISO 9001:2008 Certified Journal | Page 1175 severe), n is the frequency of the responses, and N is total number of responses. E. Importance index: The importance index of each cause is calculated as function of both frequency and severity indices, as follows: Importance Index (IMPI) (%) = [F.I. * S.I.]/100… (6) 5. RESULTS PART – 1 RII Results Top 10 causes ranked by Relative Importance Index (RII) technique The relative importance index, RII, was computed for each cause to identify the most significant causes. The causes were ranked based on RII values. From the ranking assigned to each cause of delays, it was possible to identify the most important factors or causes of delays in Indian construction industry. Base on the ranking, the 10 most important causes of material management by RII were: Table -1: Critical Causes of delay by RII Method No Critical Causes of delay RII 1 Shortage of labours (A) 0.84 2 Delay in material delivery(B) 0.83 3 Poor site management and supervision by contractor (C ) 0.82 4 Improper construction methods implemented by contractor (D) 0.82 5 Rework due to errors during construction (E ) 0.81 6 Change orders by owner during construction (F) 0.81 7 Poor communication and coordination by owner and other parties (G) 0.80 8 Slowness in decision making process by owner(H) 0.79 9 Poor communication& coordination by contractor with other parties (I) 0.79 10 Original contract duration is too short (J) 0.78 Chart -1: Critical Causes of Delay by RII Method PART-2 IMPI Results Top 10 causes ranked by Importance Index (IMPI) technique Table -2: Critical Causes of delay by IMPI Method No Critical Causes for delay FI (%) SI (%) IMPI (%) 1 Change orders by owner during construction (A) 77 79 60.83 2 Original contract duration is too short (B) 79 73 57.67 3 Poor communication and coordination by owner and other parties (C) 73.2 78.5 57.47 4 Slowness in decision making process by owner (D) 73.2 78.5 57.47 5 Poor site management and supervision by contractor (E) 73 76.5 55.85 6 Delay in material delivery (F) 75 71 53.25 7 Delay in progress payments by owner (G) 69 77 53.13 8 Personal conflicts among labours (H) 70 75.5 52.85 9 Delay in providing services from utilities (such as water, electricity) (I) 69.5 75.5 52.48 10 Improper construction methods implemented by contractor (J) 70 74.5 52.15
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 03 Issue: 01 | Jan-2016 www.irjet.net p-ISSN: 2395-0072 © 2016, IRJET | Impact Factor value: 4.45 | ISO 9001:2008 Certified Journal | Page 1176 Chart -2: Critical Causes of Delay by IMPI Method 6. CONCLUSION Delays can be avoided or minimized when their causes are clearly identified. The aim of this report was to identify the delay factors in construction projects, since delays are considered to be a serious problem in the construction industry. The paper addressed the most significant factors and groups to cause delays. According to the findings above, following points can be recommended in order to minimize and control delays in construction projects: 1) Advance arrangement of equipment’s should be made or equipment should purchase on rent. 2) The quality and experience of labor supply can have major impact on the projects. Unexperienced labor may lead to inefficient work and may cause accidents during construction. 3) Site management and supervision should be made in a correct manner. Administrative staff should be assigned to make necessary arrangements to complete the project within specified time while satisfying required quality and estimated cost. 4) Approval of design documents should not be late, since it could delay the progress of work. Progress payments should be made on time to contractor to finance the work. 5) Finding out G.L. water pipe connection leakage and quickly take appropriate action consulting with structural engineer like (Pile foundation, providing impervious layer etc.) 7. ACKNOWLEDGEMENT The Authors thankfully acknowledge to Mr J.D.Patel, Chairman, BITS edu Campus, Mr Dhruv.J.Patel, Vice Chairman, BITS edu Campus, Dr. N.D.Shah, Principal, Babaria Institute of Engineering College, Dr. L.S.Thakur, Head and Professor, Civil Engineering Department, Babaria Institute of Engineering College, for their motivations and infrastructural support to carry out this research. 8. REFERENCES 1. Aditi Dinakar “Delay Analysis in Construction Project” (Volume 4, Issue 5, May 2014) 2. Ashish D. Joshi1, Prof. Dr. S.D. Khandekar, “Project Management for Construction Projects: Improving Project Performance”(volume02 Issue: 03 | June-2015) 3. Arditi R.D., Akan G.T., Gurdamar S. (1985). “Reasons for Delays in Public Projects in Turkey”. Construction Management and Economics. 3: 171-181. 4. Assaf, S.A., Al-Khalil, M. and A-Hazmi, M. (1995). “Causes of Delay in Large Building Construction Projects”. Journal of Management in Engineering. ASCE: 45-50. 5. Eckert Scott Grant, “Inventory Management and Its Effects on Customer satisfaction”, Journal of Business and Public Policy, Volume-1 Number-3, Summer 2007, 1936-9794
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395 -0056 Volume: 03 Issue: 01 | Jan-2016 www.irjet.net p-ISSN: 2395-0072 © 2016, IRJET | Impact Factor value: 4.45 | ISO 9001:2008 Certified Journal | Page 1177 6. Dennis Daina R. and Meredith Jack R., “An analysis of Process Industry Production and Inventory Management Systems”, Journal of Operations Management, 18 (2000) 683-699. 7. Desai Megha, Dr Bhatt Rajiv “A Methodology for Ranking of Causes of Delay for Residential Construction Projects in Indian Context” (Volume 3, Issue 3, March (2013) 8. Desai Megha, Rajiv Bhatt, “Critical Causes of Delay in Residential Construction Projects: Case Study of Central Gujarat Region of India “(Volume-4 Issue-4, Year of Publication: 2013) 9. Kasim Narimah, Liwan Siti Radziah, Shamsuddin Alina, Zainal Rozlin and Kamaruddin Naadira che, “Improving on Site Material Tracking for Inventory Management in Construction Projects”, Proceedings International Conference of Technology Management, Business and Entrepreneurship, 2012 10. Patil Ashwini R. and Pataskar Smita J., “Analysing Material Management Techniques on Construction Project”, International Journal of Engineering and Innovative Technology, Volume-3 Issue-4, October 2013, 2277-3754 11. Patel Khyomesh V. and Prof. Chetna M. Vyas,“Construction Material Management on Project Site”, National Conference on Recent Trends in Engineering & Technology, May-2011 12. Patel Hemish A, Jayeshkumar Pitroda and J. J. Bhavsar, “A Review on Material Management through Inventory Management “, Journal of International Academic Research for Multidisciplinary, Volume-2 Issue-12, January 2015, 2320-5083. 13. Sugiharto Alwi ,Keith Hampson “IDENTIFYING THE IMPORTANT CAUSES OF DELAYS IN BUILDING CONSTRUCTION PROJECTS “(2003) 14. N.Hamzah,M.A.Khoiry, I. Arshad, W.H.W. Badaruzzaman, and N. M. Tawil “Identification of the Causes of Construction Delay in Malaysia” Environmental, structural, Construction and Architectural Engineering Vol: 6, No: 12, 2012 15. Sahari Salawati, Tinggi Michael and Kadri Norlina, “Inventory Management in Malaysian Construction Firm: Impact on Performance”, SIU Journal of Management, Volume-2 Number-1, June 2012, 2229-0044 16. Sindhu S., Dr. K. Nirmalkumar and Krishnamoorthy V., “Performance Analysis of Inventory Management System in Construction Industry in India”, International Journal of Innovative Research in Science, Engineering and Technology, Volume-3 Issue-4, April 2014, 2319- 8753 17. Songer, A. D., and Molenaar, K. R. ~1997. „„Project characteristics for successful public- sector design-build.‟‟ J. Constr. Eng. Manage, 123(1), 34–40.