Analysis of Change Order in Road Construction Projects
Prof. Shibi Varghese1, Roshini Parakkal2, Shreyas KK2, Smitha Treesa Babu2, Sreeraj
Anilkumar2
1Associate Professor, Dept. of Civil Engineering, MA College of Engineering, Kothamangalam, Kerala, India
2B Tech Degree Student, Dept. of Civil Engineering, MA College of Engineering, Kothamangalam, Kerala, India
---------------------------------------------------------------------***--------------------------------------------------------------------
Abstract -Construction contracts are complexbecausethey
involve many human and nonhuman factors and uncertain
conditions. Hence changes in plans, contract terms, designsor
specifications are very common and likely to occur at any
stage of the project. These changes have to be effectively
analyzed to reduce their unfavorable effectsonthecompletion
of the project which would require a comprehensive
understanding of the root causes. This project is aimed to
identify the vital causes of change orders and their effects in
road construction projects in Kerala and furthertoidentifythe
measures to mitigate their impacts in projectexecution.Global
causes and effects were obtained from literature study and
personal interviews were conducted to ascertain the factors
influencing in the local scenario. Using this questionnaire was
prepared and survey was conducted among government
officials, contractors, project managers and consultants of
road projects. The most influential causes and effects is
analyzed using IBM SPSS and they are ranked through
Relative Importance Index (RII) using weighted mean.
Relevant suggestions are proposed to improve the level of
project performance and to assist professionals to take
proactive measures for reducing change orders.
Key Words: Change, Weighted average, Questionnaire,
Reliability, Chronbach’s Alpha, Likert scale
1. INTRODUCTION
Change of planned design, construction procedure and
contract terms during execution of work leadsto the change
order. A change order is a written order to the contractor,
signed by the owner, and issued after execution of the
contract, authorizing a change in the work or an adjustment
in the contract sum or the contract time. Decisions are made
every day in construction processes based on incomplete
information, assumptions and the personalexperienceofthe
construction professionals that might lead to change or
rework. Both change and rework are done in the form of
either ‘adding’, ‘deleting’ or ‘replacement.Adegreeofchange
should be expected since it is difficult for the clients to
visualize the end product they requested. These changesare
commonly referred to as change orders
Critical change may cause consecutive delays in project
schedule, re-estimation of the work statement, and extra
demands of equipment, materials, labor, and overtime.
Changes, if not resolved through a formalized change
management process, can lead to big number of claims and
disputes.
1.1 Need For The Study
In Kerala, road construction projects undergo extensive
changes which often lead to deviation from the preplanned
construction methods. They are mostly unforeseen; hence it
is a serious issue and does not receive sufficient attention
from researchers. These changes have to be efficiently
managed through a formalized method for the successful
completion of project. This project is trying to open up the
area by identifying the major causes and effects and
suggesting certain remedies to minimize the impact of
change orders.
1.2 Scope
The aim of the study isto investigate the causes of change
orders on road construction projects, as well as to identify
the effectsof change orderson road construction projects in
Kerala. Evaluating and suggesting remedial measures to
overcome such problems.
1.3 Objective
This Study has the following four main objectives:
 To understand and evaluate various changes in road
construction projects.
 To identify causes of changes in construction projects.
 To determine effect of changesin construction projects.
 To suggest remedial control measures towards the
identified causes.
2. METHODOLOGY
Study of literature and understanding various concepts
Identify the area of interest
Preparation of questionnaire
Questionnaire survey
Analysing the surveyed data
Fig -1: Methodology chart
In the developing countries, there have been a lot of adverse
effectson ongoing projects as a result of constant changes in
the course of carrying out such projects. Questionnaire
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 03 | Mar-2018 www.irjet.net p-ISSN: 2395-0072
© 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 2672
survey is adopted as a methodology in accordance with the
fulfillment of the objective of the study. Detailedstudyonthe
causes and effects of road projects were done through
literature study.A draft wasprepared with111Globalcauses
and 27 effects of changesorders. Draftwasrevisedaccording
to prevailing conditions in Kerala through 6 Personal
Interview, Case study of a delayed project .The draft was
finalized to 21 causes and 11 Effects. The main causes of
change orders were divided mainly into four sections:
consultant and authority related causes, contractor related
causes, unforeseen causes and government related causes.
The questionnaire was structured in three sections(A,Band
C). The first section of questionnaire (A) provides data
regarding the personal information of the surveyed
respondents. The second section (B) consistsof21causesfor
change order. The section(C) consists of 11 major effects of
change orders. A seven point Likert scale was adopted to
mark the responses, the responses are 1. Stronglydisagree2.
Moderately disagree 3.Disagree 4.Neitheragreenordisagree
5. Agree 6.Moderately agree 7. Strongly agree
To check the reliability of questionnaire, pilot survey was
conducted among 15 respondents. The reliability check was
done using SPSS software. The reliability coefficient
Chronbach’salpha wasfound to be 0.883 whichismorethan
the minimum value. Hence the questionnaire was found to
be reliable.
Reliability Statistics
Cronbach's Alpha
Cronbach's Alpha
Based on
Standardized
Items N of Items
.883 .881 31
Fig -2: Reliability test output
To achieve the research objectives, surveywasconductedon
a selected sample of construction experts. The respondents
are divided into three groups: contractors, consultants and
clients. The response from the three groupsare showninpie
chart. Forty responseswere collected in totalwhichincludes
16 contractors, 9 consultants and 15 clients. It was noticed
that most of the respondentshad either experience between
10 and 20 years or more than 20 years which strengthens
the result obtained as their responses were based on
sufficient years of experience that allowed themtodigestthe
question well and give a precise answer.
Fig -3: Response Distribution
The questionnaire was statically analyzed using Statistical
Package for Social Science (SPSS). The most important
causes and effectsof change orderson construction projects
was ranked according to the weighted arithmetic mean.
3. RESULTS
From the obtained responses of all the category of
respondents, the causes and effects were ranked based on
the weighted average as shown in table A and table B.
Table -1: Causes ranked using weighted average
SL.NO. CAUSES
1
Difficulties faced in land acquisition by the
client/Delay in handover of site to contractor.
2
Misuse of democratic privileges (Increased
intervention by public, if any issue affects
them).
3 Delay in stage payments.
4
Restrictions regarding environmental
clearance, certain statutory requirements etc.
5
Unforeseen changes in grade of work,
Deviation from original scope of work during
extension.
6
Changes in government regulations and
policies
7
Troublesome procedures for safety especially
due to work in midst of traffic through
existing roads.
8 Unexpected ground conditions and terrain.
9 Prevailing political situations.
10
Insufficient coordination between various
departments in utility shifting and placing.
11
Delay made by authorities in making firm
decision.
12 Poor project management practices in
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 03 | Mar-2018 www.irjet.net p-ISSN: 2395-0072
© 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 2673
Departments.
13 Difficulties in financing project.
14
Delay in obtaining permits from local
authorities
15
Inefficient site study/ lack of clarity in scope
of work and incomplete bill of quantities
(BOQ).
16 Prevailing economic condition.
17
Incompetency of officials due to lack of
updation of technical knowhow, secured job
and other benefits received by them.
18
Lack of quality assurance of (low grade)
materials
19
Technical incompetency of contractor and his
team
20
Poor construction methods of contractor, lack
of sufficient machinery.
Table -2: Effects ranked using weighted average
SL.NO. EFFECTS
1 Cost overrun
2 Delay in completion schedule
3
Delays/ obstructs work in other areas or
in other projects
4 Delay in payment to contractor
5 Public discomfort & Traffic congestion
6 Increase in contractors overhead
7 Failure to meet utility
8
Legal dispute between owner and
contractor
9 Decrease in quality of work
10 Contract termination
11 Demolition and rework
The data analysis showed that each category of respondents
opined different causes of change order. From the
perspective of the contractor the major causes for the
generation of change orders are misuse of democratic
privileges, difficulties faced in land acquisition by the client,
delay in handover of site to the contractor, changes in
government regulations and policies.
According to consultant, the major causes for change orders
are difficulties faced in land acquisition by the client and
delay in handover of site to the contractor, unforeseen
changes in grade of work, deviation from original scope of
work during extension, unexpected ground conditions and
terrain.
The client of the project regarded insufficient coordination
between various departments in utility shifting and
troublesome proceduresfor safety especially due to workin
midst of traffic through existing roads as the major causes
for change orders.
4. CONCLUSIONS AND RECOMMENDATIONS
This research investigated the causes and effects of change
orders in road construction projects in Kerala. Through the
survey it is concluded that the most influencing causes for
the generation of change ordersare difficulties faced in land
acquisition by the client and delay in handover of site to the
contractor and misuse of democratic privilegesbythepublic.
The significant effects of change orders are cost overrun,
delay in completion schedule.
Based on the study, the following points are suggested to
minimize change orders.
1. Land acquisition and related procedures should be
completed prior to the commencement of project
2. Intervention by people other than department
should be minimized.
3. Proper investigation for study of site and terrain
conditions for DPR preparation
4. Detailed BOQ considering practical work has to be
made before tendering
5. Utility shifting should be made as part of the project
and executed by same contractor
6. EPC projects to be promoted
7. Fund allocation as per DPR requirement proper
management in execution.
REFERENCES
[1] R.U.Halwatura and N.P.N.P.Ranasinghe, “Causes of
Variation Orders in Road Construction Projects in Sri
Lanka”, Hindawi Publishing Corporation ISRN
Construction Engineering Volume2013,
ArticleID381670.
[2] Angelos Stasis, Jennifer Whyte, Ross Dentten, A Critical
Examination of Change Control Processes, 2nd
International Through-life Engineering Services
Conference, Procedia CIRP 11 ( 2013 ) 177 – 182.
[3] Murlidhar A. Lokhande, Farouk Saif Yahya Ahmed,
“Assessing Consequences of Change Request Impact in
Construction Industry of Yemen: An Explorative Likert-
Scale Based Survey Design,” Management 2015, 5(5):
141-147 DOI: 10.5923/j.mm.20150505.01.
[4] Ramos, Antonio A. González and Omar Molina,“Studyof
Change Orders in Design-Build-Maintain Projects of the
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 05 Issue: 03 | Mar-2018 www.irjet.net p-ISSN: 2395-0072
© 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 2674
XXI Century Schools in Puerto Rico”, Construction
Research Congress 2016.
[5] James Hartley, “Some thoughts on Likert-type scales”,
International Journal of Clinical and Health Psychology,
International Journal of Clinical and Health Psychology
(2013) 13, 83−86.
[6] Asish Ram, Dr. Pratheeba Paul, “Study on Construction
Sequence Delay for Road Infrastructure Projects”, IOSR
Journal of Mechanical and Civil Engineering (IOSR-
JMCE), e-ISSN: 2278-1684,p-ISSN: 2320-334X, Volume
12, Issue 2 Ver. VI (Mar - Apr. 2015), PP 15-21.

More Related Content

What's hot

Resume 2015updated doc
Resume 2015updated docResume 2015updated doc
Resume 2015updated doc
Mark Ikonen
 
CV Ramiz Siddiq 6.5
CV Ramiz Siddiq 6.5CV Ramiz Siddiq 6.5
CV Ramiz Siddiq 6.5
Ramiz Siddiq
 
Effective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryEffective Engineering Management in EPC Industry
Effective Engineering Management in EPC Industry
PMI Chennai Chapter
 
Facility Plant Mechanical Engineer Resume
Facility Plant Mechanical Engineer ResumeFacility Plant Mechanical Engineer Resume
Facility Plant Mechanical Engineer Resume
Boeing Douglas Han
 

What's hot (20)

IRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in ConstructionIRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in Construction
 
­­Construction Quality Auditing
­­Construction Quality Auditing­­Construction Quality Auditing
­­Construction Quality Auditing
 
Improving engineering productivity_loss_zhao-dungan
Improving engineering productivity_loss_zhao-dunganImproving engineering productivity_loss_zhao-dungan
Improving engineering productivity_loss_zhao-dungan
 
Bballard2000 dissertation
Bballard2000 dissertationBballard2000 dissertation
Bballard2000 dissertation
 
Resume 2015updated doc
Resume 2015updated docResume 2015updated doc
Resume 2015updated doc
 
COE
COECOE
COE
 
krishnajith_original
krishnajith_originalkrishnajith_original
krishnajith_original
 
A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...
A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...
A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...
 
asdfds
asdfdsasdfds
asdfds
 
IRJET- Achieving Total Quality Management in Construction Project using Six S...
IRJET- Achieving Total Quality Management in Construction Project using Six S...IRJET- Achieving Total Quality Management in Construction Project using Six S...
IRJET- Achieving Total Quality Management in Construction Project using Six S...
 
DIBIN C1
DIBIN C1DIBIN C1
DIBIN C1
 
CV Ramiz Siddiq 6.5
CV Ramiz Siddiq 6.5CV Ramiz Siddiq 6.5
CV Ramiz Siddiq 6.5
 
Bhattacharyya_Keya-Elec.Eng
Bhattacharyya_Keya-Elec.EngBhattacharyya_Keya-Elec.Eng
Bhattacharyya_Keya-Elec.Eng
 
Epc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promoEpc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promo
 
Effective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryEffective Engineering Management in EPC Industry
Effective Engineering Management in EPC Industry
 
Facility Plant Mechanical Engineer Resume
Facility Plant Mechanical Engineer ResumeFacility Plant Mechanical Engineer Resume
Facility Plant Mechanical Engineer Resume
 
A systematic study on site overhead costs in construction industry
A systematic study on site overhead costs in construction industryA systematic study on site overhead costs in construction industry
A systematic study on site overhead costs in construction industry
 
IRJET- Value Engineering-An Approach to Enhance Real Estate Industry
IRJET- Value Engineering-An Approach to Enhance Real Estate IndustryIRJET- Value Engineering-An Approach to Enhance Real Estate Industry
IRJET- Value Engineering-An Approach to Enhance Real Estate Industry
 
Enhancing the Software Effort Prediction Accuracy using Reduced Number of Cos...
Enhancing the Software Effort Prediction Accuracy using Reduced Number of Cos...Enhancing the Software Effort Prediction Accuracy using Reduced Number of Cos...
Enhancing the Software Effort Prediction Accuracy using Reduced Number of Cos...
 
Slqs pm spart2-blog
Slqs pm spart2-blogSlqs pm spart2-blog
Slqs pm spart2-blog
 

Similar to IRJET- Analysis of Change Order in Road Construction Projects

CE-545_Fall 2015_TPG_03_Final_Report
CE-545_Fall 2015_TPG_03_Final_ReportCE-545_Fall 2015_TPG_03_Final_Report
CE-545_Fall 2015_TPG_03_Final_Report
Muhammad Daniyal
 
Success factors enhancing business performance of engineering procurement c...
Success factors enhancing business performance of  engineering procurement  c...Success factors enhancing business performance of  engineering procurement  c...
Success factors enhancing business performance of engineering procurement c...
IAEME Publication
 

Similar to IRJET- Analysis of Change Order in Road Construction Projects (20)

IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
 
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
 
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting InflationIRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
 
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
 
Management For Construction Project:-Various Aspects Of Delay
Management For Construction Project:-Various Aspects Of DelayManagement For Construction Project:-Various Aspects Of Delay
Management For Construction Project:-Various Aspects Of Delay
 
IRJET- Review on Study of Factors Affecting Quality of Construction Project
IRJET- Review on Study of Factors Affecting Quality of Construction ProjectIRJET- Review on Study of Factors Affecting Quality of Construction Project
IRJET- Review on Study of Factors Affecting Quality of Construction Project
 
IRJET- Influence of Stakeholder Management on the Success Construction Pr...
IRJET-  	  Influence of Stakeholder Management on the Success Construction Pr...IRJET-  	  Influence of Stakeholder Management on the Success Construction Pr...
IRJET- Influence of Stakeholder Management on the Success Construction Pr...
 
Comparative Assessment of Delay Analysis Approaches in a Road Project: A Case...
Comparative Assessment of Delay Analysis Approaches in a Road Project: A Case...Comparative Assessment of Delay Analysis Approaches in a Road Project: A Case...
Comparative Assessment of Delay Analysis Approaches in a Road Project: A Case...
 
Impact of Sustainable Construction on Business Decisions
Impact of Sustainable Construction on Business DecisionsImpact of Sustainable Construction on Business Decisions
Impact of Sustainable Construction on Business Decisions
 
Factor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road projectFactor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road project
 
journalsresaim,+IJRESM_V3_I7_70.pdf
journalsresaim,+IJRESM_V3_I7_70.pdfjournalsresaim,+IJRESM_V3_I7_70.pdf
journalsresaim,+IJRESM_V3_I7_70.pdf
 
IRJET- Cost Control Methods used in Construction Projects
IRJET- Cost Control Methods used in Construction ProjectsIRJET- Cost Control Methods used in Construction Projects
IRJET- Cost Control Methods used in Construction Projects
 
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential ProjectsExploratory Study of Causes and Effects of Delay in Indian Residential Projects
Exploratory Study of Causes and Effects of Delay in Indian Residential Projects
 
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
 
IRJET- Importance of Construction Management Documentation in Planning and Co...
IRJET- Importance of Construction Management Documentation in Planning and Co...IRJET- Importance of Construction Management Documentation in Planning and Co...
IRJET- Importance of Construction Management Documentation in Planning and Co...
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure Projects
 
CE-545_Fall 2015_TPG_03_Final_Report
CE-545_Fall 2015_TPG_03_Final_ReportCE-545_Fall 2015_TPG_03_Final_Report
CE-545_Fall 2015_TPG_03_Final_Report
 
IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET - Forecasting and Management of Triple Constraints in Construction proj...IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET - Forecasting and Management of Triple Constraints in Construction proj...
 
IRJET - Investigating the Effectiveness of Construction Practices in Dela...
IRJET -  	  Investigating the Effectiveness of Construction Practices in Dela...IRJET -  	  Investigating the Effectiveness of Construction Practices in Dela...
IRJET - Investigating the Effectiveness of Construction Practices in Dela...
 
Success factors enhancing business performance of engineering procurement c...
Success factors enhancing business performance of  engineering procurement  c...Success factors enhancing business performance of  engineering procurement  c...
Success factors enhancing business performance of engineering procurement c...
 

More from IRJET Journal

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
ankushspencer015
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
rknatarajan
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Christo Ananth
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 

Recently uploaded (20)

ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 

IRJET- Analysis of Change Order in Road Construction Projects

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 03 | Mar-2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 2671 Analysis of Change Order in Road Construction Projects Prof. Shibi Varghese1, Roshini Parakkal2, Shreyas KK2, Smitha Treesa Babu2, Sreeraj Anilkumar2 1Associate Professor, Dept. of Civil Engineering, MA College of Engineering, Kothamangalam, Kerala, India 2B Tech Degree Student, Dept. of Civil Engineering, MA College of Engineering, Kothamangalam, Kerala, India ---------------------------------------------------------------------***-------------------------------------------------------------------- Abstract -Construction contracts are complexbecausethey involve many human and nonhuman factors and uncertain conditions. Hence changes in plans, contract terms, designsor specifications are very common and likely to occur at any stage of the project. These changes have to be effectively analyzed to reduce their unfavorable effectsonthecompletion of the project which would require a comprehensive understanding of the root causes. This project is aimed to identify the vital causes of change orders and their effects in road construction projects in Kerala and furthertoidentifythe measures to mitigate their impacts in projectexecution.Global causes and effects were obtained from literature study and personal interviews were conducted to ascertain the factors influencing in the local scenario. Using this questionnaire was prepared and survey was conducted among government officials, contractors, project managers and consultants of road projects. The most influential causes and effects is analyzed using IBM SPSS and they are ranked through Relative Importance Index (RII) using weighted mean. Relevant suggestions are proposed to improve the level of project performance and to assist professionals to take proactive measures for reducing change orders. Key Words: Change, Weighted average, Questionnaire, Reliability, Chronbach’s Alpha, Likert scale 1. INTRODUCTION Change of planned design, construction procedure and contract terms during execution of work leadsto the change order. A change order is a written order to the contractor, signed by the owner, and issued after execution of the contract, authorizing a change in the work or an adjustment in the contract sum or the contract time. Decisions are made every day in construction processes based on incomplete information, assumptions and the personalexperienceofthe construction professionals that might lead to change or rework. Both change and rework are done in the form of either ‘adding’, ‘deleting’ or ‘replacement.Adegreeofchange should be expected since it is difficult for the clients to visualize the end product they requested. These changesare commonly referred to as change orders Critical change may cause consecutive delays in project schedule, re-estimation of the work statement, and extra demands of equipment, materials, labor, and overtime. Changes, if not resolved through a formalized change management process, can lead to big number of claims and disputes. 1.1 Need For The Study In Kerala, road construction projects undergo extensive changes which often lead to deviation from the preplanned construction methods. They are mostly unforeseen; hence it is a serious issue and does not receive sufficient attention from researchers. These changes have to be efficiently managed through a formalized method for the successful completion of project. This project is trying to open up the area by identifying the major causes and effects and suggesting certain remedies to minimize the impact of change orders. 1.2 Scope The aim of the study isto investigate the causes of change orders on road construction projects, as well as to identify the effectsof change orderson road construction projects in Kerala. Evaluating and suggesting remedial measures to overcome such problems. 1.3 Objective This Study has the following four main objectives:  To understand and evaluate various changes in road construction projects.  To identify causes of changes in construction projects.  To determine effect of changesin construction projects.  To suggest remedial control measures towards the identified causes. 2. METHODOLOGY Study of literature and understanding various concepts Identify the area of interest Preparation of questionnaire Questionnaire survey Analysing the surveyed data Fig -1: Methodology chart In the developing countries, there have been a lot of adverse effectson ongoing projects as a result of constant changes in the course of carrying out such projects. Questionnaire
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 03 | Mar-2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 2672 survey is adopted as a methodology in accordance with the fulfillment of the objective of the study. Detailedstudyonthe causes and effects of road projects were done through literature study.A draft wasprepared with111Globalcauses and 27 effects of changesorders. Draftwasrevisedaccording to prevailing conditions in Kerala through 6 Personal Interview, Case study of a delayed project .The draft was finalized to 21 causes and 11 Effects. The main causes of change orders were divided mainly into four sections: consultant and authority related causes, contractor related causes, unforeseen causes and government related causes. The questionnaire was structured in three sections(A,Band C). The first section of questionnaire (A) provides data regarding the personal information of the surveyed respondents. The second section (B) consistsof21causesfor change order. The section(C) consists of 11 major effects of change orders. A seven point Likert scale was adopted to mark the responses, the responses are 1. Stronglydisagree2. Moderately disagree 3.Disagree 4.Neitheragreenordisagree 5. Agree 6.Moderately agree 7. Strongly agree To check the reliability of questionnaire, pilot survey was conducted among 15 respondents. The reliability check was done using SPSS software. The reliability coefficient Chronbach’salpha wasfound to be 0.883 whichismorethan the minimum value. Hence the questionnaire was found to be reliable. Reliability Statistics Cronbach's Alpha Cronbach's Alpha Based on Standardized Items N of Items .883 .881 31 Fig -2: Reliability test output To achieve the research objectives, surveywasconductedon a selected sample of construction experts. The respondents are divided into three groups: contractors, consultants and clients. The response from the three groupsare showninpie chart. Forty responseswere collected in totalwhichincludes 16 contractors, 9 consultants and 15 clients. It was noticed that most of the respondentshad either experience between 10 and 20 years or more than 20 years which strengthens the result obtained as their responses were based on sufficient years of experience that allowed themtodigestthe question well and give a precise answer. Fig -3: Response Distribution The questionnaire was statically analyzed using Statistical Package for Social Science (SPSS). The most important causes and effectsof change orderson construction projects was ranked according to the weighted arithmetic mean. 3. RESULTS From the obtained responses of all the category of respondents, the causes and effects were ranked based on the weighted average as shown in table A and table B. Table -1: Causes ranked using weighted average SL.NO. CAUSES 1 Difficulties faced in land acquisition by the client/Delay in handover of site to contractor. 2 Misuse of democratic privileges (Increased intervention by public, if any issue affects them). 3 Delay in stage payments. 4 Restrictions regarding environmental clearance, certain statutory requirements etc. 5 Unforeseen changes in grade of work, Deviation from original scope of work during extension. 6 Changes in government regulations and policies 7 Troublesome procedures for safety especially due to work in midst of traffic through existing roads. 8 Unexpected ground conditions and terrain. 9 Prevailing political situations. 10 Insufficient coordination between various departments in utility shifting and placing. 11 Delay made by authorities in making firm decision. 12 Poor project management practices in
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 03 | Mar-2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 2673 Departments. 13 Difficulties in financing project. 14 Delay in obtaining permits from local authorities 15 Inefficient site study/ lack of clarity in scope of work and incomplete bill of quantities (BOQ). 16 Prevailing economic condition. 17 Incompetency of officials due to lack of updation of technical knowhow, secured job and other benefits received by them. 18 Lack of quality assurance of (low grade) materials 19 Technical incompetency of contractor and his team 20 Poor construction methods of contractor, lack of sufficient machinery. Table -2: Effects ranked using weighted average SL.NO. EFFECTS 1 Cost overrun 2 Delay in completion schedule 3 Delays/ obstructs work in other areas or in other projects 4 Delay in payment to contractor 5 Public discomfort & Traffic congestion 6 Increase in contractors overhead 7 Failure to meet utility 8 Legal dispute between owner and contractor 9 Decrease in quality of work 10 Contract termination 11 Demolition and rework The data analysis showed that each category of respondents opined different causes of change order. From the perspective of the contractor the major causes for the generation of change orders are misuse of democratic privileges, difficulties faced in land acquisition by the client, delay in handover of site to the contractor, changes in government regulations and policies. According to consultant, the major causes for change orders are difficulties faced in land acquisition by the client and delay in handover of site to the contractor, unforeseen changes in grade of work, deviation from original scope of work during extension, unexpected ground conditions and terrain. The client of the project regarded insufficient coordination between various departments in utility shifting and troublesome proceduresfor safety especially due to workin midst of traffic through existing roads as the major causes for change orders. 4. CONCLUSIONS AND RECOMMENDATIONS This research investigated the causes and effects of change orders in road construction projects in Kerala. Through the survey it is concluded that the most influencing causes for the generation of change ordersare difficulties faced in land acquisition by the client and delay in handover of site to the contractor and misuse of democratic privilegesbythepublic. The significant effects of change orders are cost overrun, delay in completion schedule. Based on the study, the following points are suggested to minimize change orders. 1. Land acquisition and related procedures should be completed prior to the commencement of project 2. Intervention by people other than department should be minimized. 3. Proper investigation for study of site and terrain conditions for DPR preparation 4. Detailed BOQ considering practical work has to be made before tendering 5. Utility shifting should be made as part of the project and executed by same contractor 6. EPC projects to be promoted 7. Fund allocation as per DPR requirement proper management in execution. REFERENCES [1] R.U.Halwatura and N.P.N.P.Ranasinghe, “Causes of Variation Orders in Road Construction Projects in Sri Lanka”, Hindawi Publishing Corporation ISRN Construction Engineering Volume2013, ArticleID381670. [2] Angelos Stasis, Jennifer Whyte, Ross Dentten, A Critical Examination of Change Control Processes, 2nd International Through-life Engineering Services Conference, Procedia CIRP 11 ( 2013 ) 177 – 182. [3] Murlidhar A. Lokhande, Farouk Saif Yahya Ahmed, “Assessing Consequences of Change Request Impact in Construction Industry of Yemen: An Explorative Likert- Scale Based Survey Design,” Management 2015, 5(5): 141-147 DOI: 10.5923/j.mm.20150505.01. [4] Ramos, Antonio A. González and Omar Molina,“Studyof Change Orders in Design-Build-Maintain Projects of the
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 05 Issue: 03 | Mar-2018 www.irjet.net p-ISSN: 2395-0072 © 2018, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 2674 XXI Century Schools in Puerto Rico”, Construction Research Congress 2016. [5] James Hartley, “Some thoughts on Likert-type scales”, International Journal of Clinical and Health Psychology, International Journal of Clinical and Health Psychology (2013) 13, 83−86. [6] Asish Ram, Dr. Pratheeba Paul, “Study on Construction Sequence Delay for Road Infrastructure Projects”, IOSR Journal of Mechanical and Civil Engineering (IOSR- JMCE), e-ISSN: 2278-1684,p-ISSN: 2320-334X, Volume 12, Issue 2 Ver. VI (Mar - Apr. 2015), PP 15-21.