REWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL
DIVISION
Arpit saxena1, Rahul sharma2
Civil Engineering Department, Radharaman engineering college, Bhopal, Madhya Pradesh, India
---------------------------------------------------------------------***---------------------------------------------------------------------
Abstract - Cost and schedule overruns are common in construction projects. Overruns are exacerbated by rework. Reducing
field rework is usually viewed as a good strategy to boost construction productivity, cost, schedule, quality, and safety. While
there are current rework reduction programmes and a lot of literature on the subject, there is always a need for more research
and ongoing enhancement of rework reduction approaches to improve project performance.Thegoalofthisstudyistoidentify,
rank, and assess rework elements in construction projects,as wellastodetermineoverallreworkcosts. Anonsitequestionnaire
survey was conducted to rank these rework factors, and the data obtained was analysed using multi-criteria decision and
relative importancemethodstodeterminetherelativesignificanceofthesevariables,afterwhichthereworkcostwascalculated.
In thisstudy, wediscovered that the most responsible factorsinconstructionprojectsbytheglobalmatrixarepoorconstruction
technique, scope, and design change. The entire cost of rework is about 15-20% of the total project cost.
Keywords— rework, cost management, project management, cost, analytical hirarchy process
1. Introduction -
India is still a developing country. India's building industry is rapidly expanding. There are a lot of multibillion-dollar
development projects in India where a halt or cessation of operations for any reason is insufficient. Many rework factors
emerge in this rapidly evolving construction business, affecting the success of building projects. Rework is a factor that was
incorrectly implimented at the first time or activity that was done more then once.The fundamental difference between the
two, according to "Determination of cross-functional collaboration in the project implementation process" is that the second
definition combines the" perception of success as a win metric." Whether the owner, planner, expert, contractual worker, or
administrator, success on an initiative meansthatparticularwishesfora certainmemberwererealised."Successmodelling:An
introduction," .Project success was characterised as "having everything come out as desired, anticipating all project
requirements, and having enough resources to resolve challenges in a timely manner" by a strategy for developing a winning
project team. "Rework success criteria for building projects," . However, these expectations may differ for each member, and
research on rework success factors frequently seenasone ofthemostimportantwaystoimproveprojectdelivery quality. "The
Rework uccess Factors Affecting Construction Industry Performance" A successful project is one that is delivered onschedule
and within budget. Quality, money, and time have all been identified as "three constraints" or essential variables in project
successConstruction sectors are becoming increasingly convoluted and problematic these days. The industry is undergoing
significant changes. The investigation of rework factors is thought to be a method of increasing the project'ssufficiency.Inany
event, project success has remained roughly defined in the minds of development specialists.
Hwang et al. This investigation aims to identify Rework Factors in relationtothevariousproject partiesandtheirobjectivesin
Singapore's construction sector. To achieve this goal, 32 rework variables were initially discovered and classified into four
categories: contractual arrangements, project participation, project features,andinteractiveprocesses.Theanalytichierarchy
process (AHP) approach was used to create a hierarchy model of the components' relative importance at that time.
Peter E.d. love 2018 A successful project is one that is completed on schedule and within budget, quality, cost, and time
constraints. For his calculations, he employed SPSS, person's correlation, and regression analysis, and the most important
aspects in their investigation were time, cost, quality, environmental effect, and conflicts. All six rework factors studied are
rework, providing experimental support for recognising themasvariablesinfluencing thesuccessofpublicsectorconstruction
businesses.
2. objective-
A.ranking of rework factors and find most responsible rework factors in construction projects
B. calculate rework cost for most responsible factors.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 06 | Jun 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 792
3. Responsible rework factors in construction projects-
TABLE 3.1 REWORK FACTORS
SR
NO.
MAIN GROUP
FACTORS
SUB GROUP FACTORS
1 Contractor field
management
1. Poor construction technique
2. Lack of advanced equipment’s
3. poor construction material
4. Poor supervision of material and equipment
5.Lack of use of construction management standard
2 Projectmanagement
related factors
1. Improper communication
2. Decision making effectiveness
3. Construction method
4. Project monitoring
5. Client satisfaction
3 Clientrelated factors
1. Client emphasis on low construction cost
2. New request by the client to improve standard during construction
3. Client emphasis of quick construction
4. Lack of client involvement
5. Dispute B/w client & construction team
4 Design management
factors
1. Poor coordination between design team members
2. Design error due to many design tasks
3. Lack of attention to detail
4. Scope and design changes
5. Insufficient data collection and survey before design
5 External and
Environmentrelated
factors
1. Poor site conditions
2. Shortage of construction materials/equipment’s
3. Effect of social and cultural factors
4. Climate condition
5. Change in government regulation
4. Methodology-
4.1 Rework factor ranking-
AHP METHOD is used to rank the rework factors. The relative relevance of each of the primary components and cofactors
determines the analytical hierarchy process.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 06 | Jun 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 793
4.2 rework cost calculation-
The likelihood of rework in any construction project has an impact on the cost and schedule of project activities. Because the
rework has the same cost and schedule impact on the project. This cost impact should be calculated, as it will help project
managers reduce project costs that may be impacted by rework.
REWORK COST=REWORK AMOUNT*PROJECT COST
5. RESULT ANALYSIS-
5.1Ranking of factors-
In this reserch for rework factors ranking the total rework factors categorised in five group each group have 5 factors . in all
five group take one factor whose most responsibe for rework for relevent group . then with the help of global matrix ranking
these five factors and calculte these prioroty with the help of AHP method.
global weightage matrix
Category Priority Rank
1 Poor construction technique 29.5% 1
2 Client satisfaction 21.1% 3
3 Dispute B/w client & construction team 16.2% 4
4 Scope and design changes 27.3% 2
5 .Change in government regulation 5.9% 5
5.2 Result analysis by probabilistic approach
In this research study Calculate the rework amount and rework cost, take an example for calculation of rework amount and
rework cost . activity A,B,C,D,E and there duration and normal cost are show in example. And the network diagram of these
activity are also shown
F,70
15,500
A,140 B,30 C,50 D,60
15000 1500 20000 2400
E,30
4600
1 2
3
4 5
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 06 | Jun 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 794
Table 5.1 budget for activity A
SR. TIME
DAYS
AMOUNT PRIORITY*PERCENTAGE
REWORK
REWORK
AMOUNT %
COST
FOR
REWORK
Poor construction
technique.
DAYS
140
15000
.295*.180 5.31 2250
Scope and design changes .273*.180 4.91 736.50
Client satisfaction .211*.180 3.79 568.5
Dispute B/w client &
construction team
.162*.180 2.91 436.5
Change in government
regulation
.059*.180 1.06 159
Rework for this activity 4149/-
Table 5.2 budget for activity B
SR. TIME
DAYS
AMOUNT PRIORITY*PERCENT-GE
REWORK
REWORK
AMOUNT %
COST
FORREWORK
Poor construction
technique.
DAYS
30
1500
.295*.180 5.31 225
Scope and design
changes
.273*.180 4.91 73.650
Client satisfaction .211*.180 3.79 56.85
Dispute B/w client &
construction team
.162*.180 2.91 43.65
Change in
government
regulation
.059*.180 1.06 15.9
Rework for this activity 412/-
By this rework cost calculation mechanism the rework cost for all activity respectivily-
Activity A- 4149/-
Activity B- 412/-
Activity C- 3596/-
Activity D- 428/-
Activity E- 824/
Activity F- 2786/-
THE TOTAL REWORK COST FOR ALL ACTIVITY IS 12195/- OF TOTAL PROJECT COST 59000/-
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 06 | Jun 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 795
6. CONCLUSION-
In this case study we have find that the rework is most responsible factor in construction project . in this study we have find
that the most responsible factor in construction project by the global matrix so the most responsible factor respectively are
poor construction technique, scope and design changes ,Clint satisfaction, dispute between Clint and construction team and
change in government regulation.
According this study poor construction technique, scope and design changesand Clint satisfactionincreasedtotal construction
cost is 15% and all these five factors increased total construction cost is 15%-20%. With the help of these factors the
construction cost is decreased 15-20% of total project cost.
7. REFERENCES-
 Love, P. E. D., Li, H. and Mandal, P. (1999a). ―Rework: A symptom of a dysfunctional supply-chain‖, European Journal of
Purchasing and Supply Management, Vol.5, No.(1), pp. 1–11
 Love, P. E. D., Irani, Z., and Edwards, D. J. 2004. “A rework reduction model for construction projects.” IEEE Trans. Eng.
Manage., 514, 426–440.
 Love, P. E. D., and Edwards, D. 2005. “Calculating total rework costsinAustralianconstructionprojects.”Civ.Eng.Environ.
Syst., 221, 11– 27.
 Aman sen ,A.k. dwivedi,M.K. trivedi(2018) Evaluation of Rework Factors Affecting Cost and Schedule Performance in
Construction Projects International Research Journal of EngineeringandTechnology(IRJET)e-ISSN:2395-0056Volume:
05 Issue: 08 | Aug 2018 www.irjet.net p-ISSN: 2395-0072.
 Love, P. E. D., and Smith, J. 2003. “Bench-marking, bench-action and bench-learning: Rework mitigation in projects.” J.
Manage. Eng., 194, 147–159
 Love, P. E. D., Edwards, D. J., Irani, Z., and Walker, D. H. T. 2009. “Project pathogens: The anatomy of omission errors in
construction and resource engineering projects.” IEEE Trans. Eng. Manage., 563, 425–435.
 Nuria Forcada ,Angela P. Alvarez,Peter E. D. Love, and David J. Edwards (2017) “ Rework in Urban Renewal Projects in
Colombia” j. Infrastruct., 2017, 23(2):04016034
 Aman sen ,M.K. trivedi, A.k. dwivedi (2018) Evaluation of Factors Causing Rework inConstructionProjects.International
Journal for Research in Engineering Application & Management (IJREAM) ISSN : 2454-9150 Vol-04, Issue-03, June 2018.
 NuriyaForcada, FartnaGanggolells, Miquel Casals(2017) “factors affecting rework cost in construction.” J. Constr. Eng.
Manage., 2017, 143(8): 04017032
 Aman sen (2022) International Research Journal Of Modernization In Engineering Technology And Scien ce (IRJMETS),
Volume 4, Issue 06, June 2022.
 Oyewobi L. O., Ibironke O. T., Ganiyu B. O. and Ola-AwoA. W. (2011),―Evaluatingrework cost-Astudyofselected building
projects in Niger State, Nigeria‘‘,Journal of Geography and Regional Planning Vol.4 No.(3), pp. 147-151.
 Richard, F., and Anita, L. (2008). Research Methods for Construction. United Kingdom:Blackwell Publishing Ltd.
 Rogge, D.F., Cogliser, C., Alaman, H., and McCormack, S. (2001), “An investigation into field rework in industrial
construction. Report No.RR153-11, CII, Austin, Texas.
 Wasfy, M. A. (2010), ―Severity and impact of rework, A case studyofa residential commercial towerprojectinthe eastern
province-KSA‖, Master Thesis. Dhahran, Saudi Arabia: King Fahd university of petroleum and minerals.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 06 | Jun 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 796
BIOGRAPHIES
Arpit saxena
(arpit.saxena2704@gmail.com)
Department of civil engg
REC BHOPAL
Prof. Rahul sharma
(rahulvds15@gmail.com)
Department of civil engg.
REC BHOPAL

More Related Content

Similar to REWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISION

Time, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsTime, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsIRJET Journal
 
IRJET- Review on Study of Factors Affecting Quality of Construction Project
IRJET- Review on Study of Factors Affecting Quality of Construction ProjectIRJET- Review on Study of Factors Affecting Quality of Construction Project
IRJET- Review on Study of Factors Affecting Quality of Construction ProjectIRJET Journal
 
IRJET- Quality Assurance & Project Scheduling for Residential Building
IRJET-  	  Quality Assurance & Project Scheduling for Residential BuildingIRJET-  	  Quality Assurance & Project Scheduling for Residential Building
IRJET- Quality Assurance & Project Scheduling for Residential BuildingIRJET Journal
 
IRJET- Study to Reduce Cost Price of Wood Products Manufacturing by Value Eng...
IRJET- Study to Reduce Cost Price of Wood Products Manufacturing by Value Eng...IRJET- Study to Reduce Cost Price of Wood Products Manufacturing by Value Eng...
IRJET- Study to Reduce Cost Price of Wood Products Manufacturing by Value Eng...IRJET Journal
 
IRJET- Study on Buildability Factors Affecting Formwork Labour Productivity i...
IRJET- Study on Buildability Factors Affecting Formwork Labour Productivity i...IRJET- Study on Buildability Factors Affecting Formwork Labour Productivity i...
IRJET- Study on Buildability Factors Affecting Formwork Labour Productivity i...IRJET Journal
 
IRJET- Prediction Model of Factors Causing Increase in Overhead Cost in C...
IRJET-  	  Prediction Model of Factors Causing Increase in Overhead Cost in C...IRJET-  	  Prediction Model of Factors Causing Increase in Overhead Cost in C...
IRJET- Prediction Model of Factors Causing Increase in Overhead Cost in C...IRJET Journal
 
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET Journal
 
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...IRJET Journal
 
IRJET-Survey on Effects of Productivity of Equipment in Construction Projects
IRJET-Survey on Effects of Productivity of Equipment in Construction ProjectsIRJET-Survey on Effects of Productivity of Equipment in Construction Projects
IRJET-Survey on Effects of Productivity of Equipment in Construction ProjectsIRJET Journal
 
Impact of delayness on construction projects
Impact of delayness on construction projectsImpact of delayness on construction projects
Impact of delayness on construction projectsIRJET Journal
 
IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET - Forecasting and Management of Triple Constraints in Construction proj...IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET - Forecasting and Management of Triple Constraints in Construction proj...IRJET Journal
 
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSPCOMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSPIRJET Journal
 
IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...
IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...
IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...IRJET Journal
 
IIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction ProjectIIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction ProjectIRJET Journal
 
Critical Study, Analysis and Suggestion for Labor Productivity Improvement in...
Critical Study, Analysis and Suggestion for Labor Productivity Improvement in...Critical Study, Analysis and Suggestion for Labor Productivity Improvement in...
Critical Study, Analysis and Suggestion for Labor Productivity Improvement in...IRJET Journal
 
Integrating Project Management Information System and BIM for Inspecting and ...
Integrating Project Management Information System and BIM for Inspecting and ...Integrating Project Management Information System and BIM for Inspecting and ...
Integrating Project Management Information System and BIM for Inspecting and ...IRJET Journal
 
IRJET- Optimization in Construction Management
IRJET-  	  Optimization in Construction ManagementIRJET-  	  Optimization in Construction Management
IRJET- Optimization in Construction ManagementIRJET Journal
 
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET Journal
 
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...IRJET Journal
 
IRJET- Identification of Constraints and there Impact on Construction Pro...
IRJET-  	  Identification of Constraints and there Impact on Construction Pro...IRJET-  	  Identification of Constraints and there Impact on Construction Pro...
IRJET- Identification of Constraints and there Impact on Construction Pro...IRJET Journal
 

Similar to REWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISION (20)

Time, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsTime, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction Projects
 
IRJET- Review on Study of Factors Affecting Quality of Construction Project
IRJET- Review on Study of Factors Affecting Quality of Construction ProjectIRJET- Review on Study of Factors Affecting Quality of Construction Project
IRJET- Review on Study of Factors Affecting Quality of Construction Project
 
IRJET- Quality Assurance & Project Scheduling for Residential Building
IRJET-  	  Quality Assurance & Project Scheduling for Residential BuildingIRJET-  	  Quality Assurance & Project Scheduling for Residential Building
IRJET- Quality Assurance & Project Scheduling for Residential Building
 
IRJET- Study to Reduce Cost Price of Wood Products Manufacturing by Value Eng...
IRJET- Study to Reduce Cost Price of Wood Products Manufacturing by Value Eng...IRJET- Study to Reduce Cost Price of Wood Products Manufacturing by Value Eng...
IRJET- Study to Reduce Cost Price of Wood Products Manufacturing by Value Eng...
 
IRJET- Study on Buildability Factors Affecting Formwork Labour Productivity i...
IRJET- Study on Buildability Factors Affecting Formwork Labour Productivity i...IRJET- Study on Buildability Factors Affecting Formwork Labour Productivity i...
IRJET- Study on Buildability Factors Affecting Formwork Labour Productivity i...
 
IRJET- Prediction Model of Factors Causing Increase in Overhead Cost in C...
IRJET-  	  Prediction Model of Factors Causing Increase in Overhead Cost in C...IRJET-  	  Prediction Model of Factors Causing Increase in Overhead Cost in C...
IRJET- Prediction Model of Factors Causing Increase in Overhead Cost in C...
 
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay AnalysisIRJET - Fuzzy Logic Approach in Construction Delay Analysis
IRJET - Fuzzy Logic Approach in Construction Delay Analysis
 
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
 
IRJET-Survey on Effects of Productivity of Equipment in Construction Projects
IRJET-Survey on Effects of Productivity of Equipment in Construction ProjectsIRJET-Survey on Effects of Productivity of Equipment in Construction Projects
IRJET-Survey on Effects of Productivity of Equipment in Construction Projects
 
Impact of delayness on construction projects
Impact of delayness on construction projectsImpact of delayness on construction projects
Impact of delayness on construction projects
 
IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET - Forecasting and Management of Triple Constraints in Construction proj...IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET - Forecasting and Management of Triple Constraints in Construction proj...
 
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSPCOMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
 
IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...
IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...
IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...
 
IIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction ProjectIIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction Project
 
Critical Study, Analysis and Suggestion for Labor Productivity Improvement in...
Critical Study, Analysis and Suggestion for Labor Productivity Improvement in...Critical Study, Analysis and Suggestion for Labor Productivity Improvement in...
Critical Study, Analysis and Suggestion for Labor Productivity Improvement in...
 
Integrating Project Management Information System and BIM for Inspecting and ...
Integrating Project Management Information System and BIM for Inspecting and ...Integrating Project Management Information System and BIM for Inspecting and ...
Integrating Project Management Information System and BIM for Inspecting and ...
 
IRJET- Optimization in Construction Management
IRJET-  	  Optimization in Construction ManagementIRJET-  	  Optimization in Construction Management
IRJET- Optimization in Construction Management
 
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
 
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
 
IRJET- Identification of Constraints and there Impact on Construction Pro...
IRJET-  	  Identification of Constraints and there Impact on Construction Pro...IRJET-  	  Identification of Constraints and there Impact on Construction Pro...
IRJET- Identification of Constraints and there Impact on Construction Pro...
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 

Recently uploaded (20)

Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 

REWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISION

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 06 | Jun 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 791 REWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISION Arpit saxena1, Rahul sharma2 Civil Engineering Department, Radharaman engineering college, Bhopal, Madhya Pradesh, India ---------------------------------------------------------------------***--------------------------------------------------------------------- Abstract - Cost and schedule overruns are common in construction projects. Overruns are exacerbated by rework. Reducing field rework is usually viewed as a good strategy to boost construction productivity, cost, schedule, quality, and safety. While there are current rework reduction programmes and a lot of literature on the subject, there is always a need for more research and ongoing enhancement of rework reduction approaches to improve project performance.Thegoalofthisstudyistoidentify, rank, and assess rework elements in construction projects,as wellastodetermineoverallreworkcosts. Anonsitequestionnaire survey was conducted to rank these rework factors, and the data obtained was analysed using multi-criteria decision and relative importancemethodstodeterminetherelativesignificanceofthesevariables,afterwhichthereworkcostwascalculated. In thisstudy, wediscovered that the most responsible factorsinconstructionprojectsbytheglobalmatrixarepoorconstruction technique, scope, and design change. The entire cost of rework is about 15-20% of the total project cost. Keywords— rework, cost management, project management, cost, analytical hirarchy process 1. Introduction - India is still a developing country. India's building industry is rapidly expanding. There are a lot of multibillion-dollar development projects in India where a halt or cessation of operations for any reason is insufficient. Many rework factors emerge in this rapidly evolving construction business, affecting the success of building projects. Rework is a factor that was incorrectly implimented at the first time or activity that was done more then once.The fundamental difference between the two, according to "Determination of cross-functional collaboration in the project implementation process" is that the second definition combines the" perception of success as a win metric." Whether the owner, planner, expert, contractual worker, or administrator, success on an initiative meansthatparticularwishesfora certainmemberwererealised."Successmodelling:An introduction," .Project success was characterised as "having everything come out as desired, anticipating all project requirements, and having enough resources to resolve challenges in a timely manner" by a strategy for developing a winning project team. "Rework success criteria for building projects," . However, these expectations may differ for each member, and research on rework success factors frequently seenasone ofthemostimportantwaystoimproveprojectdelivery quality. "The Rework uccess Factors Affecting Construction Industry Performance" A successful project is one that is delivered onschedule and within budget. Quality, money, and time have all been identified as "three constraints" or essential variables in project successConstruction sectors are becoming increasingly convoluted and problematic these days. The industry is undergoing significant changes. The investigation of rework factors is thought to be a method of increasing the project'ssufficiency.Inany event, project success has remained roughly defined in the minds of development specialists. Hwang et al. This investigation aims to identify Rework Factors in relationtothevariousproject partiesandtheirobjectivesin Singapore's construction sector. To achieve this goal, 32 rework variables were initially discovered and classified into four categories: contractual arrangements, project participation, project features,andinteractiveprocesses.Theanalytichierarchy process (AHP) approach was used to create a hierarchy model of the components' relative importance at that time. Peter E.d. love 2018 A successful project is one that is completed on schedule and within budget, quality, cost, and time constraints. For his calculations, he employed SPSS, person's correlation, and regression analysis, and the most important aspects in their investigation were time, cost, quality, environmental effect, and conflicts. All six rework factors studied are rework, providing experimental support for recognising themasvariablesinfluencing thesuccessofpublicsectorconstruction businesses. 2. objective- A.ranking of rework factors and find most responsible rework factors in construction projects B. calculate rework cost for most responsible factors.
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 06 | Jun 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 792 3. Responsible rework factors in construction projects- TABLE 3.1 REWORK FACTORS SR NO. MAIN GROUP FACTORS SUB GROUP FACTORS 1 Contractor field management 1. Poor construction technique 2. Lack of advanced equipment’s 3. poor construction material 4. Poor supervision of material and equipment 5.Lack of use of construction management standard 2 Projectmanagement related factors 1. Improper communication 2. Decision making effectiveness 3. Construction method 4. Project monitoring 5. Client satisfaction 3 Clientrelated factors 1. Client emphasis on low construction cost 2. New request by the client to improve standard during construction 3. Client emphasis of quick construction 4. Lack of client involvement 5. Dispute B/w client & construction team 4 Design management factors 1. Poor coordination between design team members 2. Design error due to many design tasks 3. Lack of attention to detail 4. Scope and design changes 5. Insufficient data collection and survey before design 5 External and Environmentrelated factors 1. Poor site conditions 2. Shortage of construction materials/equipment’s 3. Effect of social and cultural factors 4. Climate condition 5. Change in government regulation 4. Methodology- 4.1 Rework factor ranking- AHP METHOD is used to rank the rework factors. The relative relevance of each of the primary components and cofactors determines the analytical hierarchy process.
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 06 | Jun 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 793 4.2 rework cost calculation- The likelihood of rework in any construction project has an impact on the cost and schedule of project activities. Because the rework has the same cost and schedule impact on the project. This cost impact should be calculated, as it will help project managers reduce project costs that may be impacted by rework. REWORK COST=REWORK AMOUNT*PROJECT COST 5. RESULT ANALYSIS- 5.1Ranking of factors- In this reserch for rework factors ranking the total rework factors categorised in five group each group have 5 factors . in all five group take one factor whose most responsibe for rework for relevent group . then with the help of global matrix ranking these five factors and calculte these prioroty with the help of AHP method. global weightage matrix Category Priority Rank 1 Poor construction technique 29.5% 1 2 Client satisfaction 21.1% 3 3 Dispute B/w client & construction team 16.2% 4 4 Scope and design changes 27.3% 2 5 .Change in government regulation 5.9% 5 5.2 Result analysis by probabilistic approach In this research study Calculate the rework amount and rework cost, take an example for calculation of rework amount and rework cost . activity A,B,C,D,E and there duration and normal cost are show in example. And the network diagram of these activity are also shown F,70 15,500 A,140 B,30 C,50 D,60 15000 1500 20000 2400 E,30 4600 1 2 3 4 5
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 06 | Jun 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 794 Table 5.1 budget for activity A SR. TIME DAYS AMOUNT PRIORITY*PERCENTAGE REWORK REWORK AMOUNT % COST FOR REWORK Poor construction technique. DAYS 140 15000 .295*.180 5.31 2250 Scope and design changes .273*.180 4.91 736.50 Client satisfaction .211*.180 3.79 568.5 Dispute B/w client & construction team .162*.180 2.91 436.5 Change in government regulation .059*.180 1.06 159 Rework for this activity 4149/- Table 5.2 budget for activity B SR. TIME DAYS AMOUNT PRIORITY*PERCENT-GE REWORK REWORK AMOUNT % COST FORREWORK Poor construction technique. DAYS 30 1500 .295*.180 5.31 225 Scope and design changes .273*.180 4.91 73.650 Client satisfaction .211*.180 3.79 56.85 Dispute B/w client & construction team .162*.180 2.91 43.65 Change in government regulation .059*.180 1.06 15.9 Rework for this activity 412/- By this rework cost calculation mechanism the rework cost for all activity respectivily- Activity A- 4149/- Activity B- 412/- Activity C- 3596/- Activity D- 428/- Activity E- 824/ Activity F- 2786/- THE TOTAL REWORK COST FOR ALL ACTIVITY IS 12195/- OF TOTAL PROJECT COST 59000/-
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 06 | Jun 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 795 6. CONCLUSION- In this case study we have find that the rework is most responsible factor in construction project . in this study we have find that the most responsible factor in construction project by the global matrix so the most responsible factor respectively are poor construction technique, scope and design changes ,Clint satisfaction, dispute between Clint and construction team and change in government regulation. According this study poor construction technique, scope and design changesand Clint satisfactionincreasedtotal construction cost is 15% and all these five factors increased total construction cost is 15%-20%. With the help of these factors the construction cost is decreased 15-20% of total project cost. 7. REFERENCES-  Love, P. E. D., Li, H. and Mandal, P. (1999a). ―Rework: A symptom of a dysfunctional supply-chain‖, European Journal of Purchasing and Supply Management, Vol.5, No.(1), pp. 1–11  Love, P. E. D., Irani, Z., and Edwards, D. J. 2004. “A rework reduction model for construction projects.” IEEE Trans. Eng. Manage., 514, 426–440.  Love, P. E. D., and Edwards, D. 2005. “Calculating total rework costsinAustralianconstructionprojects.”Civ.Eng.Environ. Syst., 221, 11– 27.  Aman sen ,A.k. dwivedi,M.K. trivedi(2018) Evaluation of Rework Factors Affecting Cost and Schedule Performance in Construction Projects International Research Journal of EngineeringandTechnology(IRJET)e-ISSN:2395-0056Volume: 05 Issue: 08 | Aug 2018 www.irjet.net p-ISSN: 2395-0072.  Love, P. E. D., and Smith, J. 2003. “Bench-marking, bench-action and bench-learning: Rework mitigation in projects.” J. Manage. Eng., 194, 147–159  Love, P. E. D., Edwards, D. J., Irani, Z., and Walker, D. H. T. 2009. “Project pathogens: The anatomy of omission errors in construction and resource engineering projects.” IEEE Trans. Eng. Manage., 563, 425–435.  Nuria Forcada ,Angela P. Alvarez,Peter E. D. Love, and David J. Edwards (2017) “ Rework in Urban Renewal Projects in Colombia” j. Infrastruct., 2017, 23(2):04016034  Aman sen ,M.K. trivedi, A.k. dwivedi (2018) Evaluation of Factors Causing Rework inConstructionProjects.International Journal for Research in Engineering Application & Management (IJREAM) ISSN : 2454-9150 Vol-04, Issue-03, June 2018.  NuriyaForcada, FartnaGanggolells, Miquel Casals(2017) “factors affecting rework cost in construction.” J. Constr. Eng. Manage., 2017, 143(8): 04017032  Aman sen (2022) International Research Journal Of Modernization In Engineering Technology And Scien ce (IRJMETS), Volume 4, Issue 06, June 2022.  Oyewobi L. O., Ibironke O. T., Ganiyu B. O. and Ola-AwoA. W. (2011),―Evaluatingrework cost-Astudyofselected building projects in Niger State, Nigeria‘‘,Journal of Geography and Regional Planning Vol.4 No.(3), pp. 147-151.  Richard, F., and Anita, L. (2008). Research Methods for Construction. United Kingdom:Blackwell Publishing Ltd.  Rogge, D.F., Cogliser, C., Alaman, H., and McCormack, S. (2001), “An investigation into field rework in industrial construction. Report No.RR153-11, CII, Austin, Texas.  Wasfy, M. A. (2010), ―Severity and impact of rework, A case studyofa residential commercial towerprojectinthe eastern province-KSA‖, Master Thesis. Dhahran, Saudi Arabia: King Fahd university of petroleum and minerals.
  • 6. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 06 | Jun 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 796 BIOGRAPHIES Arpit saxena (arpit.saxena2704@gmail.com) Department of civil engg REC BHOPAL Prof. Rahul sharma (rahulvds15@gmail.com) Department of civil engg. REC BHOPAL