Study on Comparison of Precast and Cast In-Situ Construction of the
Structure based on Economic Category
Manbhawan Singh1, Jatin Mehta2, Kapil Soni3
1Department of Structural Engineering, Rabindranath Tagore University, Bhopal,
2Assistant Professor Department of Civil Engineering, Rabindranath Tagore University, Bhopal,
3HOD Department of Civil Engineering, Rabindranath Tagore University, Bhopal,
---------------------------------------------------------------------***---------------------------------------------------------------------
Abstract - India has been trying to transform from an
agricultural society to an industrial society. Fordecades, India
has invested a lot of money in education to develop its people
in fields that would make its transition to an industrial nation
much easier. As a result, labour costs have risen exponentially.
Like other Asian countries, India is now facing a rising labour
cost and a lack of both skilled and un-skilled workers. Many
developers and contractors in India also see this problem and
respond by using more prefabrication; this attracts many
investors from all over the world to invest more in the
prefabricated construction business. Currently, there are
several residential developers in India that use prefabrication
for their projects. In the near future, prefabricationisexpected
to play a major role in India construction, especially, in the
residential construction like in many European countries and
the United States.
In order to compare Cost and Time relationshipexistsbetween
Precast and Cast in-situ construction, G+2 storey building is
considered
Key Words: Prefab, cast in-situ construction,
comparison.
1.INTRODUCTION
Prefabrication plays an important role in the modern world
construction of every building today, it refers to the making
of parts in an offsite workshop or factory prior to the
installation at the site. “The primary purpose of
prefabrication is to produce building components in an
efficient work environment with accesses to specialized
skills and equipment in order to reduceoverall costandtime
expenditures on the site while enhancing quality and
consistency”. Most new construction will have to use more
and more prefabrication. From primary structures to small
architectural ornaments, prefabrication has becomea major
part of building construction.
Although prefabricationisa common methodofconstruction
in the U.S. and in many European countries, several
countries in Asia are still not familiar with this method.
Because those Asian countries have different social and
economic systems from the U.S., theytendtousemoreactual
manpower for constructions rather than prefabrication
methods. Construction methods that requirea lotofphysical
labour such as masonry, hand paintorcast-in-placeconcrete
are common in India. BecauseIndia isanagricultural society,
the labour wage for agricultural work in India is muchlower
than the labour wage for industrial work in the United
States. Furthermore, unlike the United States, a lot of
countries in Asia including India mayhavefewerconcerns in
many important aspects of building construction, such as
preciseness, on-site safety, energy saving and waste
management during a construction. All these issues can be
resolved by prefabrication methods.
1.1NEED OF STUDY
Urbanization is the rapid influx of people migrating to cities.
The UN has predicted that by 2050, 64.1% and 85.9% of the
developing and developed world respectively will be
urbanized. Withlimitedresourcesoflabour,timeandfinance,
slums around the world continue to grow in uninhabitable
conditions forhumans. Rapidurbanizationandavailabilityof
jobs in attracts thousands of people around the nation
seeking work opportunities. Perhaps, a dearth of residential
houses and rising prices has forcedmillionstoliveinslumsin
uninhabitable conditions. Which lead to the shortages of the
mass housing. In India rising urbanization has created an
imminent urban housing shortage of around 18.78 million
houses. The shortage is more prominent in the Economically
Weaker Section (EWS) / Lower Income Group (LIG)/Middle
Income Group (MIG), which comprises of 95.62% of the
housing shortage. Quite aptly, urban planners, real estate
players and the government have all been eyeing at the
development of the mass or affordable housing projects to
cater to the needs of the lower- or middle-income
households.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 06 | June 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 2176
2. METHODOLOGY
Study Literature review
Collecting data by
Survey Interviews
Study Demand and Supply for future requirement and
Present scenario of constructing structure in India
Precast construction Cast in-situ construction
Installed factory of Precast
Select suitable site
Calculate load (Number of elements
casting & labour working) on the factory
Compare Economic and Social factor
Result
3. PLAN PREPARATION
Plan preparation is done for the G+2 building toestimatethe
quantities of conventional and precast constructions. The
plan of the building is shown in fig.1
Fig-1 Typical plan of Ground, first and second floor
Table -1: Plan Details
STRUCTURE G+2
One Block Area 184.02 Sqm.
Number of Block 89
Number of Units in one Block 18
Number of dwelling units proposed 1602 Nos.
4. ESTIMATION OF QUANTITIES
Estimation is used to find out the requirement of the
materials for both the constructions. The details of the
materials which are used in the construction from the
companies were collected. By getting these details we can
estimate the quantities of the materials.
Table -2: Details of area used in Constructions
S No Description Area Unit Percentage
1 Total Land Area 45000 Sqm.
2 Total block area 16378 Sqm. 36.40
3 Area of Roads 11622 Sqm. 25.83
4 Amenities 17000 Sqm. 37.78
5 Total 100
4.1Cost Analysis
This is the main factor which is considered in the projectisto
find out the comparison of cost analysis of building for the
prefab construction and conventional construction. In this
analysis we want to consider the resources of labour,
material and machineries.
Table-3: Cost Analysis Cast in-situ Construction G+2
storey
Activity Cost in rupees
A) Foundation and plinth Beam 459317
B) Ground Floor 1211635
C) First Floor 1177846
D) Second Floor 1177846
Subtotal 4026644
Cost of the one block in-situ structure is Forty lac twenty-six
thousand six hundred forty-four (4026644)
Hence Cost of the one unit Two lacs twenty-four thousand
(224000)
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 06 | June 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 2177
Fig-2 Cast in-situ construction Cost
Table-4: Cost Analysis of Precast wall bearing
Construction
Activity Cost in rupees
A) Foundation and plinth Beam 459317
B) Ground Floor 1383051
C) First Floor 1351934
D) Second Floor 1351934
Subtotal 4546236
Cost of the one block in precast structure – Forty-five lacs
forty-six thousand two hundred thirty-six (4546236)
Hence cost of one unit Two lacs fifty-three thousand
(253000)
Fig-3 Precast wall bearing construction Cost
Fig-4 Relationship between Cast in-situ and Precast
construction Cost
4.2 PROJECT DURATION
Project duration of each construction was collected from the
site offices and compares the time of completion of gives the
project duration of precast and conventional construction of
the building.
G+2 CAST IN-SITU RCC FRAMED STRUCTURE- the Time
period of the one block having 18 units given below
Table-5: Time Analysis of Cast in-situ Construction
Activity Day Total days
A) Foundationand plinthBeam 30 30
B) Ground Floor 20 50
C) First Floor 20 70
D) Second Floor 20 90
Subtotal 90
Fig-5 Cast in-situ construction time
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 06 | June 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 2178
Table-6: Time Analysis of Precast Construction
Activity Day Total days
A) Foundation and plinth Beam 30 30
B) Ground Floor 7 37
C) First Floor 7 44
D) Second Floor 7 51
Sub total 51
Fig-6 Precast wall bearing construction Time
Fig-7 Relationship between Cast in-situ and Precast
construction Time
4.3 REPAIRING WORK
Repairing work of each construction was collected from the
housing and compares the repairing work for gives the
project of the precast and conventional construction of the
building.
Fig-8 Relationship between Cast in-situ and Precast
construction of repair work
5. CONCLUSIONS
We have study and analyzed the both methods cast in-situ
construction and precast construction. The initial cost of
precast construction is more than Cast in-situ construction
because in India cost of precast labour (skilled) is morethan
normal labour. And lack of knowledge about the precast
construction.
The cost of maintenance (repair cost) is more in cast in-situ
construction as compare to precast construction. But after
15-20-year precast construction is economical. And Time
saving in precast construction is 40-50% of the Cast in-situ
construction. At the end value of cast in-situ construction is
2% but at the end value of precast construction is 50%
because it can be easily recyclable.
More significant advantages, such as improved quality
control, reduction of construction time, construction waste,
dust and noise on-site, and less labour requirement on-site.
Fig-9 Relationship between Cast in-situ and Precast
construction of the Total Cost
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 06 | June 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 2179
REFERENCES
[1] N.Dineshkumar, P.Kathirvel “Comparative Study on
PrefabricationConstruction withCastIn-SituConstructionof
Residential Buildings” April 2015
[2] Wajiha Shahzad, Jasper Mbachu and Niluka Domingo
“Marginal Productivity Gained Through Prefabrication:Case
Studies of Building Projects in Auckland” February 2015
[3] Krish R. Villaitramani, Dhruv P. Hirani “prefabricated
construction for mass housing in mumbai” October 2014
[4] Wajiha Shahzad, Jasper Mbachu, and Niluka Domingo
“prefab content versus cost and time savings inconstruction
projects: a regression analysis” November 2014
[5] Xiaoling Zhang, Liyin Shen,Yuzhe Wu“Greenstrategy for
gaining competitive advantage in housing development: a
China study” August 2010
[6] Ying Chen, Gül E. Okudan , David R. Riley “Sustainable
performance criteria for construction method selection in
concrete buildings” October 2009
[7] http://www.precastindiainfrastructurespvt.ltd
[8] http://www.amrapaligrouppvt.ltd
[9] http://www.bbcInfrastructurespvt.ltd
[10] http://www.indianprecastfactory.com
BIOGRAPHIES
MANBHAWAN SINGH
Structural Engineering

More Related Content

What's hot

IRJET- Comparative Study of Multi-Storey Multi-Span G+4 Building by PEB and C...
IRJET- Comparative Study of Multi-Storey Multi-Span G+4 Building by PEB and C...IRJET- Comparative Study of Multi-Storey Multi-Span G+4 Building by PEB and C...
IRJET- Comparative Study of Multi-Storey Multi-Span G+4 Building by PEB and C...IRJET Journal
 
PRESENT APPLICATION OFRESOURCE MANAGEMENT IN PREFABRICATED AND IN-SITU CONSTR...
PRESENT APPLICATION OFRESOURCE MANAGEMENT IN PREFABRICATED AND IN-SITU CONSTR...PRESENT APPLICATION OFRESOURCE MANAGEMENT IN PREFABRICATED AND IN-SITU CONSTR...
PRESENT APPLICATION OFRESOURCE MANAGEMENT IN PREFABRICATED AND IN-SITU CONSTR...civej
 
IRJET- Analysis of Modular Housing Technique Perception and Identification it...
IRJET- Analysis of Modular Housing Technique Perception and Identification it...IRJET- Analysis of Modular Housing Technique Perception and Identification it...
IRJET- Analysis of Modular Housing Technique Perception and Identification it...IRJET Journal
 
IRJET- Equipment Planning and Management in Road Construction Project
IRJET- Equipment Planning and Management in Road Construction ProjectIRJET- Equipment Planning and Management in Road Construction Project
IRJET- Equipment Planning and Management in Road Construction ProjectIRJET Journal
 
Importance of industrial engineering department in rmg sector
Importance of industrial engineering department in rmg sectorImportance of industrial engineering department in rmg sector
Importance of industrial engineering department in rmg sectorMdMajharulIslam9
 
Estimation and Evaluation of G+3 Residential Building
Estimation and Evaluation of G+3 Residential BuildingEstimation and Evaluation of G+3 Residential Building
Estimation and Evaluation of G+3 Residential Buildingvivatechijri
 
IRJET- A Comparative Study on Precast Construction and Conventional Construction
IRJET- A Comparative Study on Precast Construction and Conventional ConstructionIRJET- A Comparative Study on Precast Construction and Conventional Construction
IRJET- A Comparative Study on Precast Construction and Conventional ConstructionIRJET Journal
 
IRJET- The Evaluation of Payback period for Formwork system
IRJET-  	  The Evaluation of Payback period for Formwork systemIRJET-  	  The Evaluation of Payback period for Formwork system
IRJET- The Evaluation of Payback period for Formwork systemIRJET Journal
 
Design of automobile front bumper for collision energy Attenuation
Design of automobile front bumper for collision energy AttenuationDesign of automobile front bumper for collision energy Attenuation
Design of automobile front bumper for collision energy AttenuationIRJET Journal
 
A Survey of Automated Process Planning Approaches in Machining
A Survey of Automated Process Planning Approaches in MachiningA Survey of Automated Process Planning Approaches in Machining
A Survey of Automated Process Planning Approaches in MachiningDr. Amarjeet Singh
 
WPI__Construction_s_Inflation__Note__26.11.14
WPI__Construction_s_Inflation__Note__26.11.14WPI__Construction_s_Inflation__Note__26.11.14
WPI__Construction_s_Inflation__Note__26.11.14Arun Soni
 
CSCM group project aug 2016
CSCM group project aug 2016CSCM group project aug 2016
CSCM group project aug 2016Est
 
The impact of ict in quantity surveying
The impact of ict in quantity surveyingThe impact of ict in quantity surveying
The impact of ict in quantity surveyingSolomon Rex Borchers
 
Engineering & Construction 4.0 – A Digital pathway to a more profitable future
Engineering & Construction 4.0 – A Digital pathway to a more profitable futureEngineering & Construction 4.0 – A Digital pathway to a more profitable future
Engineering & Construction 4.0 – A Digital pathway to a more profitable futureLaurianneSchillesDur
 
IRJET- Equipment Planning and Management in Road Construction Project
IRJET- Equipment Planning and Management in Road Construction ProjectIRJET- Equipment Planning and Management in Road Construction Project
IRJET- Equipment Planning and Management in Road Construction ProjectIRJET Journal
 
How CIDB could control and manage the construction contractors towards implem...
How CIDB could control and manage the construction contractors towards implem...How CIDB could control and manage the construction contractors towards implem...
How CIDB could control and manage the construction contractors towards implem...N.AIZA HASSAN
 
IRJET- Contour Crafting (A Management Tool for Swift Construction)
IRJET-  	  Contour Crafting (A Management Tool for Swift Construction)IRJET-  	  Contour Crafting (A Management Tool for Swift Construction)
IRJET- Contour Crafting (A Management Tool for Swift Construction)IRJET Journal
 
Knowledge and skill requirements in the installation of prefabricated members
Knowledge and skill requirements in the installation of prefabricated membersKnowledge and skill requirements in the installation of prefabricated members
Knowledge and skill requirements in the installation of prefabricated membersIAEME Publication
 
Executive Summary Of Federal State Climate Change Policy Rebates Grants
Executive Summary Of Federal State Climate Change Policy Rebates GrantsExecutive Summary Of Federal State Climate Change Policy Rebates Grants
Executive Summary Of Federal State Climate Change Policy Rebates GrantsDermotDuncan
 
Production management
Production managementProduction management
Production managementsmumbahelp
 

What's hot (20)

IRJET- Comparative Study of Multi-Storey Multi-Span G+4 Building by PEB and C...
IRJET- Comparative Study of Multi-Storey Multi-Span G+4 Building by PEB and C...IRJET- Comparative Study of Multi-Storey Multi-Span G+4 Building by PEB and C...
IRJET- Comparative Study of Multi-Storey Multi-Span G+4 Building by PEB and C...
 
PRESENT APPLICATION OFRESOURCE MANAGEMENT IN PREFABRICATED AND IN-SITU CONSTR...
PRESENT APPLICATION OFRESOURCE MANAGEMENT IN PREFABRICATED AND IN-SITU CONSTR...PRESENT APPLICATION OFRESOURCE MANAGEMENT IN PREFABRICATED AND IN-SITU CONSTR...
PRESENT APPLICATION OFRESOURCE MANAGEMENT IN PREFABRICATED AND IN-SITU CONSTR...
 
IRJET- Analysis of Modular Housing Technique Perception and Identification it...
IRJET- Analysis of Modular Housing Technique Perception and Identification it...IRJET- Analysis of Modular Housing Technique Perception and Identification it...
IRJET- Analysis of Modular Housing Technique Perception and Identification it...
 
IRJET- Equipment Planning and Management in Road Construction Project
IRJET- Equipment Planning and Management in Road Construction ProjectIRJET- Equipment Planning and Management in Road Construction Project
IRJET- Equipment Planning and Management in Road Construction Project
 
Importance of industrial engineering department in rmg sector
Importance of industrial engineering department in rmg sectorImportance of industrial engineering department in rmg sector
Importance of industrial engineering department in rmg sector
 
Estimation and Evaluation of G+3 Residential Building
Estimation and Evaluation of G+3 Residential BuildingEstimation and Evaluation of G+3 Residential Building
Estimation and Evaluation of G+3 Residential Building
 
IRJET- A Comparative Study on Precast Construction and Conventional Construction
IRJET- A Comparative Study on Precast Construction and Conventional ConstructionIRJET- A Comparative Study on Precast Construction and Conventional Construction
IRJET- A Comparative Study on Precast Construction and Conventional Construction
 
IRJET- The Evaluation of Payback period for Formwork system
IRJET-  	  The Evaluation of Payback period for Formwork systemIRJET-  	  The Evaluation of Payback period for Formwork system
IRJET- The Evaluation of Payback period for Formwork system
 
Design of automobile front bumper for collision energy Attenuation
Design of automobile front bumper for collision energy AttenuationDesign of automobile front bumper for collision energy Attenuation
Design of automobile front bumper for collision energy Attenuation
 
A Survey of Automated Process Planning Approaches in Machining
A Survey of Automated Process Planning Approaches in MachiningA Survey of Automated Process Planning Approaches in Machining
A Survey of Automated Process Planning Approaches in Machining
 
WPI__Construction_s_Inflation__Note__26.11.14
WPI__Construction_s_Inflation__Note__26.11.14WPI__Construction_s_Inflation__Note__26.11.14
WPI__Construction_s_Inflation__Note__26.11.14
 
CSCM group project aug 2016
CSCM group project aug 2016CSCM group project aug 2016
CSCM group project aug 2016
 
The impact of ict in quantity surveying
The impact of ict in quantity surveyingThe impact of ict in quantity surveying
The impact of ict in quantity surveying
 
Engineering & Construction 4.0 – A Digital pathway to a more profitable future
Engineering & Construction 4.0 – A Digital pathway to a more profitable futureEngineering & Construction 4.0 – A Digital pathway to a more profitable future
Engineering & Construction 4.0 – A Digital pathway to a more profitable future
 
IRJET- Equipment Planning and Management in Road Construction Project
IRJET- Equipment Planning and Management in Road Construction ProjectIRJET- Equipment Planning and Management in Road Construction Project
IRJET- Equipment Planning and Management in Road Construction Project
 
How CIDB could control and manage the construction contractors towards implem...
How CIDB could control and manage the construction contractors towards implem...How CIDB could control and manage the construction contractors towards implem...
How CIDB could control and manage the construction contractors towards implem...
 
IRJET- Contour Crafting (A Management Tool for Swift Construction)
IRJET-  	  Contour Crafting (A Management Tool for Swift Construction)IRJET-  	  Contour Crafting (A Management Tool for Swift Construction)
IRJET- Contour Crafting (A Management Tool for Swift Construction)
 
Knowledge and skill requirements in the installation of prefabricated members
Knowledge and skill requirements in the installation of prefabricated membersKnowledge and skill requirements in the installation of prefabricated members
Knowledge and skill requirements in the installation of prefabricated members
 
Executive Summary Of Federal State Climate Change Policy Rebates Grants
Executive Summary Of Federal State Climate Change Policy Rebates GrantsExecutive Summary Of Federal State Climate Change Policy Rebates Grants
Executive Summary Of Federal State Climate Change Policy Rebates Grants
 
Production management
Production managementProduction management
Production management
 

Similar to Precast vs Cast-In-Situ Construction Cost Comparison

IRJET- Quality Assurance & Project Scheduling for Residential Building
IRJET-  	  Quality Assurance & Project Scheduling for Residential BuildingIRJET-  	  Quality Assurance & Project Scheduling for Residential Building
IRJET- Quality Assurance & Project Scheduling for Residential BuildingIRJET Journal
 
IRJET- Study on Buildability Factors Affecting Formwork Labour Productivity i...
IRJET- Study on Buildability Factors Affecting Formwork Labour Productivity i...IRJET- Study on Buildability Factors Affecting Formwork Labour Productivity i...
IRJET- Study on Buildability Factors Affecting Formwork Labour Productivity i...IRJET Journal
 
OPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECT
OPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECTOPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECT
OPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECTIRJET Journal
 
REWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISION
REWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISIONREWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISION
REWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISIONIRJET Journal
 
IRJET- Study to Reduce Cost Price of Wood Products Manufacturing by Value Eng...
IRJET- Study to Reduce Cost Price of Wood Products Manufacturing by Value Eng...IRJET- Study to Reduce Cost Price of Wood Products Manufacturing by Value Eng...
IRJET- Study to Reduce Cost Price of Wood Products Manufacturing by Value Eng...IRJET Journal
 
IRJET- Cost Comparison on Industrialized Building System (IBS) and Convention...
IRJET- Cost Comparison on Industrialized Building System (IBS) and Convention...IRJET- Cost Comparison on Industrialized Building System (IBS) and Convention...
IRJET- Cost Comparison on Industrialized Building System (IBS) and Convention...IRJET Journal
 
IRJET- Analysis, Design and Estimation of Multi- Storied Residential Buil...
IRJET-  	  Analysis, Design and Estimation of Multi- Storied Residential Buil...IRJET-  	  Analysis, Design and Estimation of Multi- Storied Residential Buil...
IRJET- Analysis, Design and Estimation of Multi- Storied Residential Buil...IRJET Journal
 
PLANNING AND ANALYSIS OF MULTI-SPECIALITY HOSPITAL BUILDING
PLANNING AND ANALYSIS OF MULTI-SPECIALITY HOSPITAL BUILDINGPLANNING AND ANALYSIS OF MULTI-SPECIALITY HOSPITAL BUILDING
PLANNING AND ANALYSIS OF MULTI-SPECIALITY HOSPITAL BUILDINGIRJET Journal
 
A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...
A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...
A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...IRJET Journal
 
Analysis of Prefabricational Construction And Conventional Construction
Analysis of Prefabricational Construction And Conventional ConstructionAnalysis of Prefabricational Construction And Conventional Construction
Analysis of Prefabricational Construction And Conventional ConstructionIRJET Journal
 
CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...
CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...
CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...IRJET Journal
 
IRJET- An Investigation of Maintenance Management of Construction Equipment f...
IRJET- An Investigation of Maintenance Management of Construction Equipment f...IRJET- An Investigation of Maintenance Management of Construction Equipment f...
IRJET- An Investigation of Maintenance Management of Construction Equipment f...IRJET Journal
 
Study of Factors Affecting the Implementation of BIM: An Evaluation of Risk V...
Study of Factors Affecting the Implementation of BIM: An Evaluation of Risk V...Study of Factors Affecting the Implementation of BIM: An Evaluation of Risk V...
Study of Factors Affecting the Implementation of BIM: An Evaluation of Risk V...IRJET Journal
 
“Planning, Designing and Analysis of Net-Zero Residential Building with BIM I...
“Planning, Designing and Analysis of Net-Zero Residential Building with BIM I...“Planning, Designing and Analysis of Net-Zero Residential Building with BIM I...
“Planning, Designing and Analysis of Net-Zero Residential Building with BIM I...IRJET Journal
 
Challenges in High-Rise Building Projects for Parameters of Project Managemen...
Challenges in High-Rise Building Projects for Parameters of Project Managemen...Challenges in High-Rise Building Projects for Parameters of Project Managemen...
Challenges in High-Rise Building Projects for Parameters of Project Managemen...IRJET Journal
 
Analysis and Design of Commercial Building using ETABS
Analysis and Design of Commercial Building using ETABSAnalysis and Design of Commercial Building using ETABS
Analysis and Design of Commercial Building using ETABSIRJET Journal
 
“PLANNING AND SCHEDULING OF MULTI STOREY BUILDING USING BIM”
“PLANNING AND SCHEDULING OF MULTI STOREY BUILDING USING BIM”“PLANNING AND SCHEDULING OF MULTI STOREY BUILDING USING BIM”
“PLANNING AND SCHEDULING OF MULTI STOREY BUILDING USING BIM”IRJET Journal
 
IRJET- Study to Condense Expenditure through Engineering Management of Wood P...
IRJET- Study to Condense Expenditure through Engineering Management of Wood P...IRJET- Study to Condense Expenditure through Engineering Management of Wood P...
IRJET- Study to Condense Expenditure through Engineering Management of Wood P...IRJET Journal
 
IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...
IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...
IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...IRJET Journal
 
IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET - Forecasting and Management of Triple Constraints in Construction proj...IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET - Forecasting and Management of Triple Constraints in Construction proj...IRJET Journal
 

Similar to Precast vs Cast-In-Situ Construction Cost Comparison (20)

IRJET- Quality Assurance & Project Scheduling for Residential Building
IRJET-  	  Quality Assurance & Project Scheduling for Residential BuildingIRJET-  	  Quality Assurance & Project Scheduling for Residential Building
IRJET- Quality Assurance & Project Scheduling for Residential Building
 
IRJET- Study on Buildability Factors Affecting Formwork Labour Productivity i...
IRJET- Study on Buildability Factors Affecting Formwork Labour Productivity i...IRJET- Study on Buildability Factors Affecting Formwork Labour Productivity i...
IRJET- Study on Buildability Factors Affecting Formwork Labour Productivity i...
 
OPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECT
OPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECTOPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECT
OPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECT
 
REWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISION
REWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISIONREWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISION
REWORK FACTOR AFFECTING CONSTRUCTION PROJECT IN BHOPAL DIVISION
 
IRJET- Study to Reduce Cost Price of Wood Products Manufacturing by Value Eng...
IRJET- Study to Reduce Cost Price of Wood Products Manufacturing by Value Eng...IRJET- Study to Reduce Cost Price of Wood Products Manufacturing by Value Eng...
IRJET- Study to Reduce Cost Price of Wood Products Manufacturing by Value Eng...
 
IRJET- Cost Comparison on Industrialized Building System (IBS) and Convention...
IRJET- Cost Comparison on Industrialized Building System (IBS) and Convention...IRJET- Cost Comparison on Industrialized Building System (IBS) and Convention...
IRJET- Cost Comparison on Industrialized Building System (IBS) and Convention...
 
IRJET- Analysis, Design and Estimation of Multi- Storied Residential Buil...
IRJET-  	  Analysis, Design and Estimation of Multi- Storied Residential Buil...IRJET-  	  Analysis, Design and Estimation of Multi- Storied Residential Buil...
IRJET- Analysis, Design and Estimation of Multi- Storied Residential Buil...
 
PLANNING AND ANALYSIS OF MULTI-SPECIALITY HOSPITAL BUILDING
PLANNING AND ANALYSIS OF MULTI-SPECIALITY HOSPITAL BUILDINGPLANNING AND ANALYSIS OF MULTI-SPECIALITY HOSPITAL BUILDING
PLANNING AND ANALYSIS OF MULTI-SPECIALITY HOSPITAL BUILDING
 
A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...
A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...
A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...
 
Analysis of Prefabricational Construction And Conventional Construction
Analysis of Prefabricational Construction And Conventional ConstructionAnalysis of Prefabricational Construction And Conventional Construction
Analysis of Prefabricational Construction And Conventional Construction
 
CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...
CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...
CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...
 
IRJET- An Investigation of Maintenance Management of Construction Equipment f...
IRJET- An Investigation of Maintenance Management of Construction Equipment f...IRJET- An Investigation of Maintenance Management of Construction Equipment f...
IRJET- An Investigation of Maintenance Management of Construction Equipment f...
 
Study of Factors Affecting the Implementation of BIM: An Evaluation of Risk V...
Study of Factors Affecting the Implementation of BIM: An Evaluation of Risk V...Study of Factors Affecting the Implementation of BIM: An Evaluation of Risk V...
Study of Factors Affecting the Implementation of BIM: An Evaluation of Risk V...
 
“Planning, Designing and Analysis of Net-Zero Residential Building with BIM I...
“Planning, Designing and Analysis of Net-Zero Residential Building with BIM I...“Planning, Designing and Analysis of Net-Zero Residential Building with BIM I...
“Planning, Designing and Analysis of Net-Zero Residential Building with BIM I...
 
Challenges in High-Rise Building Projects for Parameters of Project Managemen...
Challenges in High-Rise Building Projects for Parameters of Project Managemen...Challenges in High-Rise Building Projects for Parameters of Project Managemen...
Challenges in High-Rise Building Projects for Parameters of Project Managemen...
 
Analysis and Design of Commercial Building using ETABS
Analysis and Design of Commercial Building using ETABSAnalysis and Design of Commercial Building using ETABS
Analysis and Design of Commercial Building using ETABS
 
“PLANNING AND SCHEDULING OF MULTI STOREY BUILDING USING BIM”
“PLANNING AND SCHEDULING OF MULTI STOREY BUILDING USING BIM”“PLANNING AND SCHEDULING OF MULTI STOREY BUILDING USING BIM”
“PLANNING AND SCHEDULING OF MULTI STOREY BUILDING USING BIM”
 
IRJET- Study to Condense Expenditure through Engineering Management of Wood P...
IRJET- Study to Condense Expenditure through Engineering Management of Wood P...IRJET- Study to Condense Expenditure through Engineering Management of Wood P...
IRJET- Study to Condense Expenditure through Engineering Management of Wood P...
 
IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...
IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...
IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...
 
IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET - Forecasting and Management of Triple Constraints in Construction proj...IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET - Forecasting and Management of Triple Constraints in Construction proj...
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 

Recently uploaded (20)

KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 

Precast vs Cast-In-Situ Construction Cost Comparison

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 06 | June 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 2175 Study on Comparison of Precast and Cast In-Situ Construction of the Structure based on Economic Category Manbhawan Singh1, Jatin Mehta2, Kapil Soni3 1Department of Structural Engineering, Rabindranath Tagore University, Bhopal, 2Assistant Professor Department of Civil Engineering, Rabindranath Tagore University, Bhopal, 3HOD Department of Civil Engineering, Rabindranath Tagore University, Bhopal, ---------------------------------------------------------------------***--------------------------------------------------------------------- Abstract - India has been trying to transform from an agricultural society to an industrial society. Fordecades, India has invested a lot of money in education to develop its people in fields that would make its transition to an industrial nation much easier. As a result, labour costs have risen exponentially. Like other Asian countries, India is now facing a rising labour cost and a lack of both skilled and un-skilled workers. Many developers and contractors in India also see this problem and respond by using more prefabrication; this attracts many investors from all over the world to invest more in the prefabricated construction business. Currently, there are several residential developers in India that use prefabrication for their projects. In the near future, prefabricationisexpected to play a major role in India construction, especially, in the residential construction like in many European countries and the United States. In order to compare Cost and Time relationshipexistsbetween Precast and Cast in-situ construction, G+2 storey building is considered Key Words: Prefab, cast in-situ construction, comparison. 1.INTRODUCTION Prefabrication plays an important role in the modern world construction of every building today, it refers to the making of parts in an offsite workshop or factory prior to the installation at the site. “The primary purpose of prefabrication is to produce building components in an efficient work environment with accesses to specialized skills and equipment in order to reduceoverall costandtime expenditures on the site while enhancing quality and consistency”. Most new construction will have to use more and more prefabrication. From primary structures to small architectural ornaments, prefabrication has becomea major part of building construction. Although prefabricationisa common methodofconstruction in the U.S. and in many European countries, several countries in Asia are still not familiar with this method. Because those Asian countries have different social and economic systems from the U.S., theytendtousemoreactual manpower for constructions rather than prefabrication methods. Construction methods that requirea lotofphysical labour such as masonry, hand paintorcast-in-placeconcrete are common in India. BecauseIndia isanagricultural society, the labour wage for agricultural work in India is muchlower than the labour wage for industrial work in the United States. Furthermore, unlike the United States, a lot of countries in Asia including India mayhavefewerconcerns in many important aspects of building construction, such as preciseness, on-site safety, energy saving and waste management during a construction. All these issues can be resolved by prefabrication methods. 1.1NEED OF STUDY Urbanization is the rapid influx of people migrating to cities. The UN has predicted that by 2050, 64.1% and 85.9% of the developing and developed world respectively will be urbanized. Withlimitedresourcesoflabour,timeandfinance, slums around the world continue to grow in uninhabitable conditions forhumans. Rapidurbanizationandavailabilityof jobs in attracts thousands of people around the nation seeking work opportunities. Perhaps, a dearth of residential houses and rising prices has forcedmillionstoliveinslumsin uninhabitable conditions. Which lead to the shortages of the mass housing. In India rising urbanization has created an imminent urban housing shortage of around 18.78 million houses. The shortage is more prominent in the Economically Weaker Section (EWS) / Lower Income Group (LIG)/Middle Income Group (MIG), which comprises of 95.62% of the housing shortage. Quite aptly, urban planners, real estate players and the government have all been eyeing at the development of the mass or affordable housing projects to cater to the needs of the lower- or middle-income households.
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 06 | June 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 2176 2. METHODOLOGY Study Literature review Collecting data by Survey Interviews Study Demand and Supply for future requirement and Present scenario of constructing structure in India Precast construction Cast in-situ construction Installed factory of Precast Select suitable site Calculate load (Number of elements casting & labour working) on the factory Compare Economic and Social factor Result 3. PLAN PREPARATION Plan preparation is done for the G+2 building toestimatethe quantities of conventional and precast constructions. The plan of the building is shown in fig.1 Fig-1 Typical plan of Ground, first and second floor Table -1: Plan Details STRUCTURE G+2 One Block Area 184.02 Sqm. Number of Block 89 Number of Units in one Block 18 Number of dwelling units proposed 1602 Nos. 4. ESTIMATION OF QUANTITIES Estimation is used to find out the requirement of the materials for both the constructions. The details of the materials which are used in the construction from the companies were collected. By getting these details we can estimate the quantities of the materials. Table -2: Details of area used in Constructions S No Description Area Unit Percentage 1 Total Land Area 45000 Sqm. 2 Total block area 16378 Sqm. 36.40 3 Area of Roads 11622 Sqm. 25.83 4 Amenities 17000 Sqm. 37.78 5 Total 100 4.1Cost Analysis This is the main factor which is considered in the projectisto find out the comparison of cost analysis of building for the prefab construction and conventional construction. In this analysis we want to consider the resources of labour, material and machineries. Table-3: Cost Analysis Cast in-situ Construction G+2 storey Activity Cost in rupees A) Foundation and plinth Beam 459317 B) Ground Floor 1211635 C) First Floor 1177846 D) Second Floor 1177846 Subtotal 4026644 Cost of the one block in-situ structure is Forty lac twenty-six thousand six hundred forty-four (4026644) Hence Cost of the one unit Two lacs twenty-four thousand (224000)
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 06 | June 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 2177 Fig-2 Cast in-situ construction Cost Table-4: Cost Analysis of Precast wall bearing Construction Activity Cost in rupees A) Foundation and plinth Beam 459317 B) Ground Floor 1383051 C) First Floor 1351934 D) Second Floor 1351934 Subtotal 4546236 Cost of the one block in precast structure – Forty-five lacs forty-six thousand two hundred thirty-six (4546236) Hence cost of one unit Two lacs fifty-three thousand (253000) Fig-3 Precast wall bearing construction Cost Fig-4 Relationship between Cast in-situ and Precast construction Cost 4.2 PROJECT DURATION Project duration of each construction was collected from the site offices and compares the time of completion of gives the project duration of precast and conventional construction of the building. G+2 CAST IN-SITU RCC FRAMED STRUCTURE- the Time period of the one block having 18 units given below Table-5: Time Analysis of Cast in-situ Construction Activity Day Total days A) Foundationand plinthBeam 30 30 B) Ground Floor 20 50 C) First Floor 20 70 D) Second Floor 20 90 Subtotal 90 Fig-5 Cast in-situ construction time
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 06 | June 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 2178 Table-6: Time Analysis of Precast Construction Activity Day Total days A) Foundation and plinth Beam 30 30 B) Ground Floor 7 37 C) First Floor 7 44 D) Second Floor 7 51 Sub total 51 Fig-6 Precast wall bearing construction Time Fig-7 Relationship between Cast in-situ and Precast construction Time 4.3 REPAIRING WORK Repairing work of each construction was collected from the housing and compares the repairing work for gives the project of the precast and conventional construction of the building. Fig-8 Relationship between Cast in-situ and Precast construction of repair work 5. CONCLUSIONS We have study and analyzed the both methods cast in-situ construction and precast construction. The initial cost of precast construction is more than Cast in-situ construction because in India cost of precast labour (skilled) is morethan normal labour. And lack of knowledge about the precast construction. The cost of maintenance (repair cost) is more in cast in-situ construction as compare to precast construction. But after 15-20-year precast construction is economical. And Time saving in precast construction is 40-50% of the Cast in-situ construction. At the end value of cast in-situ construction is 2% but at the end value of precast construction is 50% because it can be easily recyclable. More significant advantages, such as improved quality control, reduction of construction time, construction waste, dust and noise on-site, and less labour requirement on-site. Fig-9 Relationship between Cast in-situ and Precast construction of the Total Cost
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 06 | June 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 2179 REFERENCES [1] N.Dineshkumar, P.Kathirvel “Comparative Study on PrefabricationConstruction withCastIn-SituConstructionof Residential Buildings” April 2015 [2] Wajiha Shahzad, Jasper Mbachu and Niluka Domingo “Marginal Productivity Gained Through Prefabrication:Case Studies of Building Projects in Auckland” February 2015 [3] Krish R. Villaitramani, Dhruv P. Hirani “prefabricated construction for mass housing in mumbai” October 2014 [4] Wajiha Shahzad, Jasper Mbachu, and Niluka Domingo “prefab content versus cost and time savings inconstruction projects: a regression analysis” November 2014 [5] Xiaoling Zhang, Liyin Shen,Yuzhe Wu“Greenstrategy for gaining competitive advantage in housing development: a China study” August 2010 [6] Ying Chen, Gül E. Okudan , David R. Riley “Sustainable performance criteria for construction method selection in concrete buildings” October 2009 [7] http://www.precastindiainfrastructurespvt.ltd [8] http://www.amrapaligrouppvt.ltd [9] http://www.bbcInfrastructurespvt.ltd [10] http://www.indianprecastfactory.com BIOGRAPHIES MANBHAWAN SINGH Structural Engineering