SlideShare a Scribd company logo
LANDSCAPE-Quantity Take-off & Costing 
Presented by: 
Sr. Loo Seong King 
BSc.QS, MRISM, MRICS, Reg. QS
LANDSCAPE-Quantity Take-off & Costing 
1)Introduction 
2)Estimating Techniques 
3)Scope of Work 
4)Quantity Takeoff List 
5)Unit of Measurement 
6)Unit Pricing 
7)Example
Introduction 
“ How much does it cost?” 
All owners have at least one thing in common: For them, financial considerations drive decisions. 
In fact, it sometimes is the most important factor on which to base their judgment. 
It is common for designer to hear from the owner, “It looks great, but tell me how much it costs; then I ‘ll tell you if I like it.” 
So its important that designer should has some knowledge of costing so as to be able to advise the employer of the likely cost of the project.
Introduction 
Once the owner is aware of the project cost and is satisfied that it is within his budget he will then be willing to talk about design concepts without always linking decisions back to dollars. 
The budget will also serve as means of cost control for the landscape architect while proposing for the project. 
It is also commonly required that landscape architect amend his or her design documents to bring the project within budget.
Estimating Techniques 
1. Cost per square meter of landscaped area of similar completed projects 
•Not accurate. Does not reflect the actual scope of work required 
•Suitable for budgeting purposes only. 
2. Approximate Quantities estimate 
•Most commonly applied technique 
•Based on quantification of works and multiplying them with the appropriate unit price. 
•Fairly accurate depending on the level of information available.
Scope of Work 
•Site work including site clearance and earthwork. 
•Softscape including trees by various sizes and categories, shrubs, groundcovers, grasses, etc. 
•Hardscape including pavement, planter wall, fencing, gazebo, trellis, water features, site furnishing, site lighting, site signs, etc. 
•Irrigation system 
•Maintenance 
•Preliminary 
•Contingency
Quantity Takeoff List 
First prepare a list of items for quantification by study of the drawing. 
•Quantity Takeoff List: 
A. Site Preparation/Earthwork 
1. Site clearance 
2. Excavation oversite 
3.Earth filling/import 
4.Earthwork-cut & fill
Quantity Takeoff List 
•Quantity Take-off List 
B.Softscape 
1.Trees 
2.Shrubs 
3.Groundcovers 
4.Grasses 
5.Pit excavation 
6.Soil mixture 
7.Mulching 
8.Tree stakes and ties 
9.Maintenance
Quantity Takeoff List 
•Quantity Take-off List 
C. Hardscape 
1. Pavement 
2. Planter wall 
3. Fencing 
4. Trellis 
5.Gazebo 
6.Water feature
Unit of Measurement 
A. Site Preparation/Earthwork 
1. Site clearance Square metre (m²) 
2. Excavation oversite Square metre (m² 
3.Earth filling/import Cubic metre (m³) 
4.Excavate generally Cubic metre (m³) 
5.Earth moulding Cubic metre (m³)
Unit of Measurement 
B. Softscape 
1.Tree Number (no.) 
2.Shrub Number (no.) 
3.Groundcover Number (no.) 
4.Grass Square metre (m²) 
5.Mulch Square metre (m²) 
6.Pit excavation Number (no.) 
7.Soil mixture Cubic metre (m³) 
8.Tree stakes and ties Number (no.) 
9.Maintenance Month (mth)
Unit of Measurement 
C. Hardscape 
1. Pavement Square metre (m²) 
2. Planter wall Square metre (m²) 
3. Fencing Linear metre (m) 
4. Trellis Square metre (m²) 
5.Gazebo Number (no.) 
6.Water feature Number (no.)
Unit Pricing 
•Once the quantities in the list have been established, you will then need to put a unit price to each of them to arrive at your total estimated cost of the project. 
•Sources of unit price 
1. Cost data of past projects 
2.Quotations from contractors 
3.From nurseries-requires an experienced estimator to build up the unit price
Unit Pricing 
A. Site Preparation/Earthwork 
1. Site clearance RM10/m² 
2.Excavation oversite; 
100mm thick RM10/m² 
3.Earth filling/import RM100/m³ 
4.Excavate generally RM50/m³ 
5.Earth moulding RM50/m³
Unit pricing 
B. Softscape 
1.Tree RM300/no. 
2.Shrub RM50/no. 
3.Groundcover RM20/no. 
4.Grass RM30/m² 
5.Mulch RM10/m² 
6.Pit excavation-Tree RM50/no - Shrub RM20/no. 
7.Soil mixture RM100/m³ 
8.Tree stakes and ties RM50/no. 
9.Maintenance RM1,500/mth
Unit Pricing 
C. Hardscape 
1.Pavement- 
-Granite/stone/timber RM350/m² 
-Tiles RM250/m² 
-Precast concrete RM100/m² 
-Concrete paver RM150/m² 
2. Planter wall-Brickwall RM150/m² 
3. Fencing- 1.80m high RM350/m 
4. Trellis-wood RM250/m² 
5.Gazebo RM5,000/no. 
6.Water feature RM20,000/no.
Preliminaries 
•This is for ancillary cost involved in the Contract which are not directly related to the actual cost of the items of construction works. 
•This includes the provision for the contractor’s shed, insurances, tools, equipment, safety measures, cleanliness of site, etc. 
•Generally, based on an allowance of 5% of the cost of construction cost.
Contingency 
•Contingency is an allowance to be used for works unforeseen at the planning and design stage. 
•Landscape architects must plan and budget for events which are hard to predict or unforeseen. Contingency must be built into all estimates. 
•A greater contingency must be built into design that has less certainty. For example those projects in the early stages of design and planning should consider upwards of 15% as a contingency to budget. 
•Projects with more certainty, for example those in later phases of design and documentation where more specific quantities are known, need only budget for 5 percent for contingency.
Updates 
•Cost estimates are typically updated at successive design/documentation phases from schematic design to design development, or design development to construction documents. 
•As estimates are updated with successive developments of the document, the estimates become more accurate. Estimates are also updated: 
•When significant changes occur to project progress 
•Significant project element re-quantifying occurs 
•Updated unit prices are received
Example 
.
PLAN VIEW
TREES LAYOUT ON PLAN VIEW 
Shade Tree 
Shade Tree 
Small trees 
Small trees
SHRUBS LAYOUT ON PLAN VIEW
GROUNDCOVER LAYOUT ON PLAN VIEW
ISOMETRIC DRAWING OF PLAN VIEW
PLAN VIEW 
Fence-49m 
Timber deck-47m² 
Cut stone paver-42m² 
Trellis- 21m² 
Brick edging-96m 
Precast concrete 
slab-11m² 
Precast concrete slab 800 x 300mm x 10 no.
SOFT & HARD LANDSCAPE WORKS 
ITEM 
DESCRIPTION 
UNIT 
QTY 
RATE (RM) 
AMOUNT (RM) 
A 
SITE PREPARATION 
1 
Clear site generally 
m² 
500 
10.00 
5,000.00 
2 
Excavate oversite 100mm thick 
m² 
500 
10.00 
5,000.00 
3 
Filling with imported earth 
m³ 
50 
100.00 
5,000.00 
Sub-total carried to Summary 
15,000.00
SOFT & HARD LANDSCAPE WORKS 
ITEM 
DESCRIPTION 
UNIT 
QTY 
RATE(RM) 
AMOUNT(RM) 
B 
SOFTSCAPE 
1 
Trees 
no. 
16 
300.00 
4,800.00 
2 
Shrubs 
no. 
103 
50.00 
18,000.00 
3 
Groundcovers 
no. 
1500 
20.00 
15,000.00 
4 
Taiwan grass 
m² 
300 
30.00 
9,000.00 
5 
Hole excavation 
i. 
Tree 1.0 x 1.0 x1.0m deep 
no. 
16 
50.00 
800.00 
ii. 
Shrub 0.45 x 0.45 x 0.45 deep 
no. 
103 
20.00 
2,060.00 
6 
Soil Mixture (Tree & shrub) 
m³ 
25 
100.00 
2,500.00 
7 
Mulching (Tree, Palm, Shrub & Groundcover) 
m² 
200 
10.00 
2,000.00 
8 
Staking & Ties (Tree) 
no. 
16 
50.00 
800.00 
9 
Maintenance 
mth. 
12 
1,500.00 
18,000.00 
Sub-total carried to Summary 
72,960.00
SOFT & HARD LANDSCAPE WORKS 
ITEM 
DESCRIPTION 
UNIT 
QTY 
RATE(RM) 
AMOUNT(RM) 
C 
HARDSCAPE 
1 
Cut stone slab 
m² 
42 
350.00 
14,700.00 
2 
Precast concrete slab 
m² 
11 
100.00 
1,100.00 
3 
PC slab 800 x 300mm 
no. 
10 
25.00 
250.00 
3 
Timber deck 
m² 
47 
350.00 
16.450.00 
4 
Brick edging 
m 
96 
20.00 
1,920.00 
5 
Fencing 
m 
49 
350 .00 
17,150.00 
6 
Trellis 
m² 
21 
250.00 
5,250.00 
7 
Irrigation-standpipe 
no. 
3 
1,200.00 
3,600.00 
Sub-total Carried to Summary 
60,420 .00
SOFT & HARD LANDSCAPE WORKS 
ITEM 
DESCRIPTION 
UNIT 
QTY 
RATE(RM) 
AMOUNT(RM) 
SUMMARY 
A 
SITE PREPARATION 
15.000.00 
B 
SOFTSCAPE 
72,960.00 
C 
HARDSCAPE 
60,420.00 
148,380.00 
D 
PRELIMINARIES (5%) 
7,419.00 
E 
CONTINGENCY (10%) 
15,579.90 
TOTAL 
171,378.90 
Say: 
171,000.00
Maintenance 
•The following are some typical maintenance tasks: 
•Watering 
•Fertilizing 
•Pest and disease control (herbicide spraying) 
•Weeding 
•Pruning and trimming 
•Grass cutting 
•Replacing dead plants 
•Stake repairs
Maintenance 
Maintenance cost RM/Mth 
•Labour cost 
1.1 laborers @ RM 50/day x 4 times a month 200 
2.1 supervisor @RM70/day x 4 times a month 280 
3.Transport-1 lorry @ RM100/day x 4 times a month 400 
•Material cost 
1.Fertiliser; once a month 100 
2.Pest control, once a month 100 
3. Replacing dead plants say 100 
Total 1180 
•Add Profit & overhead 20% 236 
1416 
Say RM 1,500/month

More Related Content

What's hot

Value Management Assignment (Report)
Value Management Assignment (Report)Value Management Assignment (Report)
Value Management Assignment (Report)
Pang Khai Shuen
 
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMAnep Botak
 
Measurement 4 Tender Document
Measurement 4 Tender Document Measurement 4 Tender Document
Measurement 4 Tender Document
xingxin_GOh
 
Elemental cost analysis
Elemental cost analysisElemental cost analysis
Elemental cost analysis
fareezsham
 
PP2 - Assignment
PP2 - Assignment PP2 - Assignment
PP2 - Assignment
lucaschinsheng
 
Intelligent building
Intelligent buildingIntelligent building
Intelligent building
Mohd. Ikhwan
 
Professional practice 1 (QS)
Professional practice 1 (QS)Professional practice 1 (QS)
Professional practice 1 (QS)
Hasif Alias
 
Project Management Project 1 Report: Defining & Documenting A Project
Project Management Project 1 Report: Defining & Documenting A ProjectProject Management Project 1 Report: Defining & Documenting A Project
Project Management Project 1 Report: Defining & Documenting A Project
Nekumi Kida
 
Professional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentProfessional Practice 1 Group Assignment
Professional Practice 1 Group Assignment
Haziq1511
 
Final submission be 2.0
Final submission be 2.0Final submission be 2.0
Final submission be 2.0
ahmong4
 
CL Final Assignment Report Part B
CL Final Assignment Report Part BCL Final Assignment Report Part B
CL Final Assignment Report Part B
Pang Shuen
 
SMM7 Bill of Quantities
SMM7 Bill of QuantitiesSMM7 Bill of Quantities
SMM7 Bill of QuantitiesNatalie Reid
 
Wblff (1)
Wblff (1)Wblff (1)
Wblff (1)
ahmong4
 
Pwd 203 a rev2007
Pwd 203 a rev2007Pwd 203 a rev2007
Pwd 203 a rev2007shimz2287
 
Sem 2 bs1 telecommunication r1
Sem 2 bs1 telecommunication r1Sem 2 bs1 telecommunication r1
Sem 2 bs1 telecommunication r1
Est
 
ECA presentation
ECA presentationECA presentation
ECA presentation
Shze Hwa Lee
 
Tender calling procedure
Tender calling procedureTender calling procedure
Tender calling procedure
Shourya Puri
 
The architect as contract administrator a legal perspective - presentation ...
The architect as contract administrator   a legal perspective - presentation ...The architect as contract administrator   a legal perspective - presentation ...
The architect as contract administrator a legal perspective - presentation ...Zainab Zainordin
 
Eca presentation-compile
Eca presentation-compileEca presentation-compile
Eca presentation-compile
Timun Loh
 
Tender
TenderTender

What's hot (20)

Value Management Assignment (Report)
Value Management Assignment (Report)Value Management Assignment (Report)
Value Management Assignment (Report)
 
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
 
Measurement 4 Tender Document
Measurement 4 Tender Document Measurement 4 Tender Document
Measurement 4 Tender Document
 
Elemental cost analysis
Elemental cost analysisElemental cost analysis
Elemental cost analysis
 
PP2 - Assignment
PP2 - Assignment PP2 - Assignment
PP2 - Assignment
 
Intelligent building
Intelligent buildingIntelligent building
Intelligent building
 
Professional practice 1 (QS)
Professional practice 1 (QS)Professional practice 1 (QS)
Professional practice 1 (QS)
 
Project Management Project 1 Report: Defining & Documenting A Project
Project Management Project 1 Report: Defining & Documenting A ProjectProject Management Project 1 Report: Defining & Documenting A Project
Project Management Project 1 Report: Defining & Documenting A Project
 
Professional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentProfessional Practice 1 Group Assignment
Professional Practice 1 Group Assignment
 
Final submission be 2.0
Final submission be 2.0Final submission be 2.0
Final submission be 2.0
 
CL Final Assignment Report Part B
CL Final Assignment Report Part BCL Final Assignment Report Part B
CL Final Assignment Report Part B
 
SMM7 Bill of Quantities
SMM7 Bill of QuantitiesSMM7 Bill of Quantities
SMM7 Bill of Quantities
 
Wblff (1)
Wblff (1)Wblff (1)
Wblff (1)
 
Pwd 203 a rev2007
Pwd 203 a rev2007Pwd 203 a rev2007
Pwd 203 a rev2007
 
Sem 2 bs1 telecommunication r1
Sem 2 bs1 telecommunication r1Sem 2 bs1 telecommunication r1
Sem 2 bs1 telecommunication r1
 
ECA presentation
ECA presentationECA presentation
ECA presentation
 
Tender calling procedure
Tender calling procedureTender calling procedure
Tender calling procedure
 
The architect as contract administrator a legal perspective - presentation ...
The architect as contract administrator   a legal perspective - presentation ...The architect as contract administrator   a legal perspective - presentation ...
The architect as contract administrator a legal perspective - presentation ...
 
Eca presentation-compile
Eca presentation-compileEca presentation-compile
Eca presentation-compile
 
Tender
TenderTender
Tender
 

Viewers also liked

Preliminary powerpoint structure
Preliminary powerpoint  structurePreliminary powerpoint  structure
Preliminary powerpoint structureannietagoe
 
Sgp4813 measurement of quantities
Sgp4813 measurement of quantitiesSgp4813 measurement of quantities
Sgp4813 measurement of quantitiesalanchong88
 
Sgp4813 measurement of quantities
Sgp4813 measurement of quantitiesSgp4813 measurement of quantities
Sgp4813 measurement of quantities
alanchong88
 
Sgp4813 measurement of quantities
Sgp4813 measurement of quantitiesSgp4813 measurement of quantities
Sgp4813 measurement of quantitiesalanchong88
 
Lecture slides4; Construction Project Planning
Lecture slides4; Construction Project PlanningLecture slides4; Construction Project Planning
Lecture slides4; Construction Project Planning
JB Nartey
 
QUANTITY SURVEYING
QUANTITY SURVEYINGQUANTITY SURVEYING
QUANTITY SURVEYING
lizwi nyandu
 
50451783 taking-off-quantity
50451783 taking-off-quantity50451783 taking-off-quantity
50451783 taking-off-quantity
hlksd
 

Viewers also liked (8)

Preliminary powerpoint structure
Preliminary powerpoint  structurePreliminary powerpoint  structure
Preliminary powerpoint structure
 
Sgp4813 measurement of quantities
Sgp4813 measurement of quantitiesSgp4813 measurement of quantities
Sgp4813 measurement of quantities
 
Sgp4813 measurement of quantities
Sgp4813 measurement of quantitiesSgp4813 measurement of quantities
Sgp4813 measurement of quantities
 
Sgp4813 measurement of quantities
Sgp4813 measurement of quantitiesSgp4813 measurement of quantities
Sgp4813 measurement of quantities
 
Lecture slides4; Construction Project Planning
Lecture slides4; Construction Project PlanningLecture slides4; Construction Project Planning
Lecture slides4; Construction Project Planning
 
QUANTITY SURVEYING
QUANTITY SURVEYINGQUANTITY SURVEYING
QUANTITY SURVEYING
 
50451783 taking-off-quantity
50451783 taking-off-quantity50451783 taking-off-quantity
50451783 taking-off-quantity
 
Boq sample
Boq sampleBoq sample
Boq sample
 

Similar to Project 3 - Costing

Civil Works Site Construction Guidelines for Haris & Co Civil Team.pdf
Civil Works Site Construction Guidelines for  Haris & Co Civil Team.pdfCivil Works Site Construction Guidelines for  Haris & Co Civil Team.pdf
Civil Works Site Construction Guidelines for Haris & Co Civil Team.pdf
usamazahoor159
 
Cost estimation
Cost estimationCost estimation
Cost estimation
Satyam Singh
 
Lec 9 center line method
Lec 9 center line methodLec 9 center line method
Lec 9 center line method
malang1214
 
013 5-design-techniques-review
013 5-design-techniques-review013 5-design-techniques-review
013 5-design-techniques-reviewMary Palmer Dargan
 
A PPT.pptx
A PPT.pptxA PPT.pptx
A PPT.pptx
RajeshKumar25548
 
Estimation
EstimationEstimation
Estimation
LipikaPandey
 
Fundamentals of Estimating and Costing
 Fundamentals of Estimating and Costing Fundamentals of Estimating and Costing
Fundamentals of Estimating and Costing
Ganesh Tatikonda
 
chapter1-210122051628.pdf
chapter1-210122051628.pdfchapter1-210122051628.pdf
chapter1-210122051628.pdf
Deepak37004
 
Cost estimation of a Building
Cost  estimation of a BuildingCost  estimation of a Building
Cost estimation of a Building
ARAVINDBORRA1
 
Construction practices aphb
Construction practices aphbConstruction practices aphb
Construction practices aphbhlksd
 
Module_3.pdf.pdf
Module_3.pdf.pdfModule_3.pdf.pdf
Module_3.pdf.pdf
AlyssaSison3
 
Construction basic SIP
Construction basic SIPConstruction basic SIP
Construction basic SIP
Mkh Nantu
 
deva batch FINAL PPT.pptx
deva batch FINAL PPT.pptxdeva batch FINAL PPT.pptx
deva batch FINAL PPT.pptx
RajeshKumar25548
 
SPM.pptx
SPM.pptxSPM.pptx
Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)
Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)
Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)
AMIT PAYAL
 
Graded unit Civil engineering Presentation
Graded unit Civil engineering PresentationGraded unit Civil engineering Presentation
Graded unit Civil engineering Presentation
Tehmas Saeed
 
Lowcost prefebrication and infrastructure services
Lowcost prefebrication and infrastructure servicesLowcost prefebrication and infrastructure services
Lowcost prefebrication and infrastructure services
Ar Jitendra
 
Amit pandit presentaion gautambuddha university
Amit pandit presentaion gautambuddha universityAmit pandit presentaion gautambuddha university
Amit pandit presentaion gautambuddha university
Aman Jain
 
Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)AJAY SHAHU
 
2022-07-13.pptx
2022-07-13.pptx2022-07-13.pptx
2022-07-13.pptx
AshrafulHaqueTushar1
 

Similar to Project 3 - Costing (20)

Civil Works Site Construction Guidelines for Haris & Co Civil Team.pdf
Civil Works Site Construction Guidelines for  Haris & Co Civil Team.pdfCivil Works Site Construction Guidelines for  Haris & Co Civil Team.pdf
Civil Works Site Construction Guidelines for Haris & Co Civil Team.pdf
 
Cost estimation
Cost estimationCost estimation
Cost estimation
 
Lec 9 center line method
Lec 9 center line methodLec 9 center line method
Lec 9 center line method
 
013 5-design-techniques-review
013 5-design-techniques-review013 5-design-techniques-review
013 5-design-techniques-review
 
A PPT.pptx
A PPT.pptxA PPT.pptx
A PPT.pptx
 
Estimation
EstimationEstimation
Estimation
 
Fundamentals of Estimating and Costing
 Fundamentals of Estimating and Costing Fundamentals of Estimating and Costing
Fundamentals of Estimating and Costing
 
chapter1-210122051628.pdf
chapter1-210122051628.pdfchapter1-210122051628.pdf
chapter1-210122051628.pdf
 
Cost estimation of a Building
Cost  estimation of a BuildingCost  estimation of a Building
Cost estimation of a Building
 
Construction practices aphb
Construction practices aphbConstruction practices aphb
Construction practices aphb
 
Module_3.pdf.pdf
Module_3.pdf.pdfModule_3.pdf.pdf
Module_3.pdf.pdf
 
Construction basic SIP
Construction basic SIPConstruction basic SIP
Construction basic SIP
 
deva batch FINAL PPT.pptx
deva batch FINAL PPT.pptxdeva batch FINAL PPT.pptx
deva batch FINAL PPT.pptx
 
SPM.pptx
SPM.pptxSPM.pptx
SPM.pptx
 
Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)
Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)
Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)
 
Graded unit Civil engineering Presentation
Graded unit Civil engineering PresentationGraded unit Civil engineering Presentation
Graded unit Civil engineering Presentation
 
Lowcost prefebrication and infrastructure services
Lowcost prefebrication and infrastructure servicesLowcost prefebrication and infrastructure services
Lowcost prefebrication and infrastructure services
 
Amit pandit presentaion gautambuddha university
Amit pandit presentaion gautambuddha universityAmit pandit presentaion gautambuddha university
Amit pandit presentaion gautambuddha university
 
Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)
 
2022-07-13.pptx
2022-07-13.pptx2022-07-13.pptx
2022-07-13.pptx
 

More from Kai Yun Pang

Assignment 2 - Resort Proposal at Pulau Langkawi
Assignment 2 - Resort Proposal at Pulau LangkawiAssignment 2 - Resort Proposal at Pulau Langkawi
Assignment 2 - Resort Proposal at Pulau Langkawi
Kai Yun Pang
 
Assignment 2 - Report
Assignment 2 - ReportAssignment 2 - Report
Assignment 2 - Report
Kai Yun Pang
 
Assignment 1 - Water Pump Station
Assignment 1 - Water Pump StationAssignment 1 - Water Pump Station
Assignment 1 - Water Pump Station
Kai Yun Pang
 
Assignment 1 - Microsoft Project
Assignment 1 - Microsoft ProjectAssignment 1 - Microsoft Project
Assignment 1 - Microsoft Project
Kai Yun Pang
 
Assignment - Financial Appraisal
Assignment - Financial AppraisalAssignment - Financial Appraisal
Assignment - Financial Appraisal
Kai Yun Pang
 
Assignment - Financial Appraisal
Assignment - Financial Appraisal Assignment - Financial Appraisal
Assignment - Financial Appraisal
Kai Yun Pang
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC Contract
Kai Yun Pang
 
Assignment - Report
Assignment - ReportAssignment - Report
Assignment - Report
Kai Yun Pang
 
Seminar - CIPAA 2012
Seminar - CIPAA 2012Seminar - CIPAA 2012
Seminar - CIPAA 2012
Kai Yun Pang
 
Assignment - S Hotel (Presentation Slide)
Assignment - S Hotel (Presentation Slide)Assignment - S Hotel (Presentation Slide)
Assignment - S Hotel (Presentation Slide)
Kai Yun Pang
 
Assignment - S Hotel
Assignment - S HotelAssignment - S Hotel
Assignment - S Hotel
Kai Yun Pang
 
Assignment - Case Study Report
Assignment - Case Study ReportAssignment - Case Study Report
Assignment - Case Study Report
Kai Yun Pang
 
Assignment - Journal
Assignment - JournalAssignment - Journal
Assignment - Journal
Kai Yun Pang
 
Assignment - Community Service
Assignment - Community Service Assignment - Community Service
Assignment - Community Service
Kai Yun Pang
 
Assignment - Final Account
Assignment - Final AccountAssignment - Final Account
Assignment - Final Account
Kai Yun Pang
 
Assignment - Report
Assignment - ReportAssignment - Report
Assignment - Report
Kai Yun Pang
 
Seminar - Partial Possession by Employer
Seminar - Partial Possession by EmployerSeminar - Partial Possession by Employer
Seminar - Partial Possession by Employer
Kai Yun Pang
 
Seminar - Question
Seminar - QuestionSeminar - Question
Seminar - Question
Kai Yun Pang
 
Assignment - MK Land
Assignment - MK LandAssignment - MK Land
Assignment - MK Land
Kai Yun Pang
 
Assignment - Financial Analysis
Assignment - Financial AnalysisAssignment - Financial Analysis
Assignment - Financial Analysis
Kai Yun Pang
 

More from Kai Yun Pang (20)

Assignment 2 - Resort Proposal at Pulau Langkawi
Assignment 2 - Resort Proposal at Pulau LangkawiAssignment 2 - Resort Proposal at Pulau Langkawi
Assignment 2 - Resort Proposal at Pulau Langkawi
 
Assignment 2 - Report
Assignment 2 - ReportAssignment 2 - Report
Assignment 2 - Report
 
Assignment 1 - Water Pump Station
Assignment 1 - Water Pump StationAssignment 1 - Water Pump Station
Assignment 1 - Water Pump Station
 
Assignment 1 - Microsoft Project
Assignment 1 - Microsoft ProjectAssignment 1 - Microsoft Project
Assignment 1 - Microsoft Project
 
Assignment - Financial Appraisal
Assignment - Financial AppraisalAssignment - Financial Appraisal
Assignment - Financial Appraisal
 
Assignment - Financial Appraisal
Assignment - Financial Appraisal Assignment - Financial Appraisal
Assignment - Financial Appraisal
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC Contract
 
Assignment - Report
Assignment - ReportAssignment - Report
Assignment - Report
 
Seminar - CIPAA 2012
Seminar - CIPAA 2012Seminar - CIPAA 2012
Seminar - CIPAA 2012
 
Assignment - S Hotel (Presentation Slide)
Assignment - S Hotel (Presentation Slide)Assignment - S Hotel (Presentation Slide)
Assignment - S Hotel (Presentation Slide)
 
Assignment - S Hotel
Assignment - S HotelAssignment - S Hotel
Assignment - S Hotel
 
Assignment - Case Study Report
Assignment - Case Study ReportAssignment - Case Study Report
Assignment - Case Study Report
 
Assignment - Journal
Assignment - JournalAssignment - Journal
Assignment - Journal
 
Assignment - Community Service
Assignment - Community Service Assignment - Community Service
Assignment - Community Service
 
Assignment - Final Account
Assignment - Final AccountAssignment - Final Account
Assignment - Final Account
 
Assignment - Report
Assignment - ReportAssignment - Report
Assignment - Report
 
Seminar - Partial Possession by Employer
Seminar - Partial Possession by EmployerSeminar - Partial Possession by Employer
Seminar - Partial Possession by Employer
 
Seminar - Question
Seminar - QuestionSeminar - Question
Seminar - Question
 
Assignment - MK Land
Assignment - MK LandAssignment - MK Land
Assignment - MK Land
 
Assignment - Financial Analysis
Assignment - Financial AnalysisAssignment - Financial Analysis
Assignment - Financial Analysis
 

Recently uploaded

Instructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptxInstructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptx
Jheel Barad
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
Jisc
 
How to Create Map Views in the Odoo 17 ERP
How to Create Map Views in the Odoo 17 ERPHow to Create Map Views in the Odoo 17 ERP
How to Create Map Views in the Odoo 17 ERP
Celine George
 
Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
AzmatAli747758
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
Celine George
 
Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
Jisc
 
The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
Delapenabediema
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
Tamralipta Mahavidyalaya
 
Fish and Chips - have they had their chips
Fish and Chips - have they had their chipsFish and Chips - have they had their chips
Fish and Chips - have they had their chips
GeoBlogs
 
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
Nguyen Thanh Tu Collection
 
Sectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdfSectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdf
Vivekanand Anglo Vedic Academy
 
Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
Atul Kumar Singh
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
TechSoup
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
siemaillard
 
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdfUnit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Thiyagu K
 
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXXPhrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
MIRIAMSALINAS13
 
The Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve ThomasonThe Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve Thomason
Steve Thomason
 
1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx
JosvitaDsouza2
 
How to Break the cycle of negative Thoughts
How to Break the cycle of negative ThoughtsHow to Break the cycle of negative Thoughts
How to Break the cycle of negative Thoughts
Col Mukteshwar Prasad
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
siemaillard
 

Recently uploaded (20)

Instructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptxInstructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptx
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
 
How to Create Map Views in the Odoo 17 ERP
How to Create Map Views in the Odoo 17 ERPHow to Create Map Views in the Odoo 17 ERP
How to Create Map Views in the Odoo 17 ERP
 
Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
 
Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
 
The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
 
Fish and Chips - have they had their chips
Fish and Chips - have they had their chipsFish and Chips - have they had their chips
Fish and Chips - have they had their chips
 
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
 
Sectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdfSectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdf
 
Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
 
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdfUnit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdf
 
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXXPhrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
 
The Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve ThomasonThe Art Pastor's Guide to Sabbath | Steve Thomason
The Art Pastor's Guide to Sabbath | Steve Thomason
 
1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx
 
How to Break the cycle of negative Thoughts
How to Break the cycle of negative ThoughtsHow to Break the cycle of negative Thoughts
How to Break the cycle of negative Thoughts
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
 

Project 3 - Costing

  • 1. LANDSCAPE-Quantity Take-off & Costing Presented by: Sr. Loo Seong King BSc.QS, MRISM, MRICS, Reg. QS
  • 2. LANDSCAPE-Quantity Take-off & Costing 1)Introduction 2)Estimating Techniques 3)Scope of Work 4)Quantity Takeoff List 5)Unit of Measurement 6)Unit Pricing 7)Example
  • 3. Introduction “ How much does it cost?” All owners have at least one thing in common: For them, financial considerations drive decisions. In fact, it sometimes is the most important factor on which to base their judgment. It is common for designer to hear from the owner, “It looks great, but tell me how much it costs; then I ‘ll tell you if I like it.” So its important that designer should has some knowledge of costing so as to be able to advise the employer of the likely cost of the project.
  • 4. Introduction Once the owner is aware of the project cost and is satisfied that it is within his budget he will then be willing to talk about design concepts without always linking decisions back to dollars. The budget will also serve as means of cost control for the landscape architect while proposing for the project. It is also commonly required that landscape architect amend his or her design documents to bring the project within budget.
  • 5. Estimating Techniques 1. Cost per square meter of landscaped area of similar completed projects •Not accurate. Does not reflect the actual scope of work required •Suitable for budgeting purposes only. 2. Approximate Quantities estimate •Most commonly applied technique •Based on quantification of works and multiplying them with the appropriate unit price. •Fairly accurate depending on the level of information available.
  • 6. Scope of Work •Site work including site clearance and earthwork. •Softscape including trees by various sizes and categories, shrubs, groundcovers, grasses, etc. •Hardscape including pavement, planter wall, fencing, gazebo, trellis, water features, site furnishing, site lighting, site signs, etc. •Irrigation system •Maintenance •Preliminary •Contingency
  • 7. Quantity Takeoff List First prepare a list of items for quantification by study of the drawing. •Quantity Takeoff List: A. Site Preparation/Earthwork 1. Site clearance 2. Excavation oversite 3.Earth filling/import 4.Earthwork-cut & fill
  • 8. Quantity Takeoff List •Quantity Take-off List B.Softscape 1.Trees 2.Shrubs 3.Groundcovers 4.Grasses 5.Pit excavation 6.Soil mixture 7.Mulching 8.Tree stakes and ties 9.Maintenance
  • 9. Quantity Takeoff List •Quantity Take-off List C. Hardscape 1. Pavement 2. Planter wall 3. Fencing 4. Trellis 5.Gazebo 6.Water feature
  • 10. Unit of Measurement A. Site Preparation/Earthwork 1. Site clearance Square metre (m²) 2. Excavation oversite Square metre (m² 3.Earth filling/import Cubic metre (m³) 4.Excavate generally Cubic metre (m³) 5.Earth moulding Cubic metre (m³)
  • 11. Unit of Measurement B. Softscape 1.Tree Number (no.) 2.Shrub Number (no.) 3.Groundcover Number (no.) 4.Grass Square metre (m²) 5.Mulch Square metre (m²) 6.Pit excavation Number (no.) 7.Soil mixture Cubic metre (m³) 8.Tree stakes and ties Number (no.) 9.Maintenance Month (mth)
  • 12. Unit of Measurement C. Hardscape 1. Pavement Square metre (m²) 2. Planter wall Square metre (m²) 3. Fencing Linear metre (m) 4. Trellis Square metre (m²) 5.Gazebo Number (no.) 6.Water feature Number (no.)
  • 13. Unit Pricing •Once the quantities in the list have been established, you will then need to put a unit price to each of them to arrive at your total estimated cost of the project. •Sources of unit price 1. Cost data of past projects 2.Quotations from contractors 3.From nurseries-requires an experienced estimator to build up the unit price
  • 14. Unit Pricing A. Site Preparation/Earthwork 1. Site clearance RM10/m² 2.Excavation oversite; 100mm thick RM10/m² 3.Earth filling/import RM100/m³ 4.Excavate generally RM50/m³ 5.Earth moulding RM50/m³
  • 15. Unit pricing B. Softscape 1.Tree RM300/no. 2.Shrub RM50/no. 3.Groundcover RM20/no. 4.Grass RM30/m² 5.Mulch RM10/m² 6.Pit excavation-Tree RM50/no - Shrub RM20/no. 7.Soil mixture RM100/m³ 8.Tree stakes and ties RM50/no. 9.Maintenance RM1,500/mth
  • 16. Unit Pricing C. Hardscape 1.Pavement- -Granite/stone/timber RM350/m² -Tiles RM250/m² -Precast concrete RM100/m² -Concrete paver RM150/m² 2. Planter wall-Brickwall RM150/m² 3. Fencing- 1.80m high RM350/m 4. Trellis-wood RM250/m² 5.Gazebo RM5,000/no. 6.Water feature RM20,000/no.
  • 17. Preliminaries •This is for ancillary cost involved in the Contract which are not directly related to the actual cost of the items of construction works. •This includes the provision for the contractor’s shed, insurances, tools, equipment, safety measures, cleanliness of site, etc. •Generally, based on an allowance of 5% of the cost of construction cost.
  • 18. Contingency •Contingency is an allowance to be used for works unforeseen at the planning and design stage. •Landscape architects must plan and budget for events which are hard to predict or unforeseen. Contingency must be built into all estimates. •A greater contingency must be built into design that has less certainty. For example those projects in the early stages of design and planning should consider upwards of 15% as a contingency to budget. •Projects with more certainty, for example those in later phases of design and documentation where more specific quantities are known, need only budget for 5 percent for contingency.
  • 19. Updates •Cost estimates are typically updated at successive design/documentation phases from schematic design to design development, or design development to construction documents. •As estimates are updated with successive developments of the document, the estimates become more accurate. Estimates are also updated: •When significant changes occur to project progress •Significant project element re-quantifying occurs •Updated unit prices are received
  • 21.
  • 23. TREES LAYOUT ON PLAN VIEW Shade Tree Shade Tree Small trees Small trees
  • 24. SHRUBS LAYOUT ON PLAN VIEW
  • 26. ISOMETRIC DRAWING OF PLAN VIEW
  • 27. PLAN VIEW Fence-49m Timber deck-47m² Cut stone paver-42m² Trellis- 21m² Brick edging-96m Precast concrete slab-11m² Precast concrete slab 800 x 300mm x 10 no.
  • 28. SOFT & HARD LANDSCAPE WORKS ITEM DESCRIPTION UNIT QTY RATE (RM) AMOUNT (RM) A SITE PREPARATION 1 Clear site generally m² 500 10.00 5,000.00 2 Excavate oversite 100mm thick m² 500 10.00 5,000.00 3 Filling with imported earth m³ 50 100.00 5,000.00 Sub-total carried to Summary 15,000.00
  • 29. SOFT & HARD LANDSCAPE WORKS ITEM DESCRIPTION UNIT QTY RATE(RM) AMOUNT(RM) B SOFTSCAPE 1 Trees no. 16 300.00 4,800.00 2 Shrubs no. 103 50.00 18,000.00 3 Groundcovers no. 1500 20.00 15,000.00 4 Taiwan grass m² 300 30.00 9,000.00 5 Hole excavation i. Tree 1.0 x 1.0 x1.0m deep no. 16 50.00 800.00 ii. Shrub 0.45 x 0.45 x 0.45 deep no. 103 20.00 2,060.00 6 Soil Mixture (Tree & shrub) m³ 25 100.00 2,500.00 7 Mulching (Tree, Palm, Shrub & Groundcover) m² 200 10.00 2,000.00 8 Staking & Ties (Tree) no. 16 50.00 800.00 9 Maintenance mth. 12 1,500.00 18,000.00 Sub-total carried to Summary 72,960.00
  • 30. SOFT & HARD LANDSCAPE WORKS ITEM DESCRIPTION UNIT QTY RATE(RM) AMOUNT(RM) C HARDSCAPE 1 Cut stone slab m² 42 350.00 14,700.00 2 Precast concrete slab m² 11 100.00 1,100.00 3 PC slab 800 x 300mm no. 10 25.00 250.00 3 Timber deck m² 47 350.00 16.450.00 4 Brick edging m 96 20.00 1,920.00 5 Fencing m 49 350 .00 17,150.00 6 Trellis m² 21 250.00 5,250.00 7 Irrigation-standpipe no. 3 1,200.00 3,600.00 Sub-total Carried to Summary 60,420 .00
  • 31. SOFT & HARD LANDSCAPE WORKS ITEM DESCRIPTION UNIT QTY RATE(RM) AMOUNT(RM) SUMMARY A SITE PREPARATION 15.000.00 B SOFTSCAPE 72,960.00 C HARDSCAPE 60,420.00 148,380.00 D PRELIMINARIES (5%) 7,419.00 E CONTINGENCY (10%) 15,579.90 TOTAL 171,378.90 Say: 171,000.00
  • 32. Maintenance •The following are some typical maintenance tasks: •Watering •Fertilizing •Pest and disease control (herbicide spraying) •Weeding •Pruning and trimming •Grass cutting •Replacing dead plants •Stake repairs
  • 33. Maintenance Maintenance cost RM/Mth •Labour cost 1.1 laborers @ RM 50/day x 4 times a month 200 2.1 supervisor @RM70/day x 4 times a month 280 3.Transport-1 lorry @ RM100/day x 4 times a month 400 •Material cost 1.Fertiliser; once a month 100 2.Pest control, once a month 100 3. Replacing dead plants say 100 Total 1180 •Add Profit & overhead 20% 236 1416 Say RM 1,500/month