SlideShare a Scribd company logo
LECTURE # 09
COST
ESTIMATION
Estimation For 02 Room Office
D4’x7’
Footing Details
2’’ 2’’
P.L
G.LG.L
P.L
G.L
Floor Details
4) 1-1/2’’ thick brick tiles joined and
pointed in cement sand mortar (1:3)
3) 1’’ thick mud plaster
2) 4’’ thick earth filling
1) Roof insulation comprising of 2
coats of hot bitumen
Roof Details
 SPECIFICATIONS
 P.C.C
 Damp Proof Coarse (D.P.C) = 1:2:4
 Floors = 1:4:8, 1:3:6, 1:2:4
 R.C.C
 Roof Slab, Lintel, and Sun Shades = 1:2:4
 C/S Mortar
 Brickwork in foundation = 1:6
 Brickwork in superstructure = 1:4
 Brick tiles on roof = 1:3
 Plaster Work
 ½” thick 1:3 C/S Plaster
Estimation For 02 Room Office
 SPECIFICATIONS
 Clear height of rooms :12’
 Clear height of Verandah : 12’
 Plinth level : 1’-6”
 Thickness of roof slab : 4”
 Thickness of RCC shade : 3”
 Depth of RCC Beams in Verandah : 1’-6” below verandah slab
 Parapet wall : 1’-0”
 Ventilators (4 No.) : 2’-6” x 1’-6”
 RCC lintel : 6” in depth
 Damp proof coarse : 1 ½”thick PCC (1:2:4) + 2 coats of
hot bitumen +polythene sheet
 Internal finishes : 03 coats of white wash/ distemper
paint
 External finishes : 03 coats of Weather shield paint
 Lintels extend : 6” on each side
Estimation For 02 Room Office
 This item is described in detail but the price of this item is usually
indicated as lump sum (LS).
 The cost of this item is provided in the estimate by judgment,
according to the description of the item and is indicated as Lump
sum (L.S).
 Estimator must determine
 Depth of soil to be removed
 Equipment to be used
 STEP 1: Clearing and Grubbing
 Topsoil is generally removed from all building, walk, roadway, and
parking areas.
 The volume of topsoil is figured in cubic yards.
 A clearance around the entire basic plan must also be left to allow
for the slope required for the general excavation; usually about 5
feet is allowed on each side of a building and 1 to 2 feet for walks,
roadways, and parking areas.
 STEP 1: Clearing and Grubbing
Plot Area = 28’ x 28‘ = 784 Sq. ft.
Efficiency of Dozer = 437 cu. ft. / hr.
Rate = PRs 4000/ hr. (if more than 12,000 cu. ft.)
Rate = PRs 8000/ hr. (if less than 12,000 cu. ft.)
Let us assume 3 in. depth
Quantity = 784 * (3/12) = 784 * 0.25 = 196 cu. ft.
Equipment hours = 196 cu. ft / 437 cu. ft /hr = 0.45 hours
Equipment cost = 0.45 hours * 8000 per hour = Rs. 3600
Equipment cost = Rs. 3600
 STEP 1: Clearing and Grubbing
 For symmetrical footings, which is the usual case, earthwork in
excavation in foundations, foundation concrete, brickwork in
foundation and plinth, and brickwork in superstructure may be
estimated by either of the two methods:
(1) Separate or Individual Wall Method
(2) Center Line Method
Methods Of Detailed Estimate
 In this method, total length of center lines of walls, long and short,
has to be found out
 Find the total length of center lines of walls of same type, having
same type of foundations and footings and then find the quantities
by multiplying the total center length by the respective breadth and
the height
 In this method, the length will remain the same for excavation in
foundations, for concrete in foundations, for all footings, and for
superstructure (with slight difference when there are cross walls or
number of junctions)
 This method is quicker but requires special attention and
considerations at the junctions, meeting points of partition or cross
walls
Center Line Method
 For rectangular, circular polygonal (hexagonal, octagonal etc.)
buildings having no inter or cross walls, this method is quite simple
 For buildings having cross or partition walls, for every junction, half
breadth of the respective item or footing is to be deducted from the
total center length
 Thus in the case of a building with one partition wall or cross wall
having two junctions, deduct one breadth of the respective item of
work from the total center length
Center Line Method
Centre to Centre Distance
 (4.5” = 0.37’)
 (9” =0.75’)
 H-1= H-2= H-3=10’+12’+0.37’
+0.37’+0.37’
=23.11’
 S-1= S-2= S-5=12’+0.37’+0.37’
= 12.74’
 S-3= S-4= 7.25’+0.37’+0.37’
= 8’
S-1 S-2 S-5
H-1
H-2
H-3
S-3
S-4
STEP 2: Excavation
 Earthwork in excavation for foundation trenches is calculated by
taking the dimensions of each trench as length x breadth x depth.
 It is measured in cubic ft, cubic yard or cubic meter, according to
the prevailing practice.
 The payment for this item is generally done as Rs. per hundred
cubic ft.
 Filling in trenches after the construction of foundation masonry is
ordinary neglected. If the trench filling is, also taken in account, it
may be calculated by deducing the volume of masonry in trenches
from that of the volume of excavation
STEP 2: Excavation
 To determine the amount of excavation, it is necessary to determine
the following:
1. The size of building (building dimensions).
2. The distance the footing will project beyond the wall.
3. The amount of working space required between the edge of the
footing and the beginning of excavation.
4. The elevation of the existing land, by checking the existing contour
lines on the plot (site) plan.
Continuous footing section
STEP 2: Excavation
6. The type of soil that will be encountered. This is determined by first
checking the soil borings (on the drawings), but must also be checked
during the site investigation.
7. Whether the excavation will be sloped or shored.
8. The depth of the excavation. This is done by determining the bottom
elevation of the cut to be made. Then take the existing elevation, deduct
any topsoil removed, and subtract the bottom elevation of the cut to
determine the depth of excavation.
STEP 2: Excavation
When calculating the amount of excavation to be done for a project, the
estimator must be certain that the dimensions used are the
measurements of the outside face of the footings and not those of the
outside of the building. The footings usually project beyond the wall.
Also, an extra 6 inches to 1 foot is added to all sides of the footing to
allow the workers to install and remove forms. The estimator must also
allow for the sloping of the banks to prevent a cave in. The amount of
slope required must be determined by the estimator who considers the
depth of excavation, type of soil, and possible water conditions.
Excavation Plan
Let Sa = S-1 + S-3
Sb = S-4 + S-5
 L1 = H-1 + Sa + H-3 + Sb
 L2 = S-2 – (Overlap)
= S-2 – ½(Width) – ½(Width)
= S-2 – Width
 L3 = H-2 - (Overlap)
= H-2 - ½(Width) – ½(Width)
= H-2 – Width
Using Center Line Method
S-1 S-2 S-5
H-1
H-2
H-3
S-3
S-4
STEP 2: Excavation
Footing Details
2’’ 2’’
P.L
G.LG.L
P.L
G.L
Floor Details
Let Sa = S-1 + S-3
Sb = S-4 + S-5
(As width of excavation is 2’-6”)
 L1 = H-1 + Sa + H-3 + Sb
 L2 = S-2 – ½(Width) – ½(Width)
= S-2 – Width
= S-2 – 2’-6”
 L3 = H-2 - ½(Width) – ½(Width)
= H-2 – Width
= H-2 – 2’-6”
S-2
H-1
H-2
H-3
Sa Sb
STEP 2: Excavation
S No Description N
Measurement
Quantity
(cu. ft.)
Total
Quantity
(cu. ft.)
Remarks
L’ B’ D’
1 L1 1 87.70 2.5 3.5 767.38 767.38
2 L2 1 10.2 2.1 3.5 75 75 L=12.74-2.5
3 L3 1 20.61 2.5 3.5 180.34 180.34 L=23.11-2.5
Total Quantity 1022.7
STEP 2: Excavation
Quantity = 1022.7 cu. ft.
Wage rate = Rs. 650/ day
Productivity rate = 0.0134 day / cu ft
Labour Hours = Productivity Rate * Quantity
Labour hours = 0.0134 day / cu ft *1023.88 = 13.65 days
Labour cost = Labour hours * Wage rate per hour
Labour cost = 13.65 days * Rs. 650/day
Labour cost = Rs. 8873
STEP 2: Excavation
P.C.C
 The type of concrete must be clearly mentioned. The mix proportions and
the type of cement, sand and coarse aggregate must be specified.
 This item is measured in cubic ft and the unit for measurement is,
generally Rs. per 100 cubic ft.
 When the soil is soft or weak, one layer of dry bricks or stone soling is
applied below the foundation concrete. The soling layer is computed in
sq.ft (length x breadth), specifying the thickness in description of item.
 In estimating quantities, the estimator makes no deductions for holes
smaller than 2 sf or for the space that reinforcing bars or other
miscellaneous accessories take up.
 Waste ranges from 5 percent for footings, columns, and beams to 8
percent for slabs.
Procedure for calculating concrete
1. Review the specifications to determine the requirements for each
area in which concrete is used separately (such as footings, floor
slabs, and walkways) and list the following:
(a) Type of concrete
(b) Strength of concrete
(c) Color of concrete
(d) Any special curing or testing
2. Review the drawings to be certain that all concrete items shown on
the drawings are covered in the specifications. If not, a call will have
to be made to the architect-engineer so that an addendum can be
issued.
3. List each of the concrete items required on the project.
4. Determine the quantities required from the working drawings.
Footing sizes are checked on the wall sections and foundation plans.
Watch for different size footings under different walls.
Let Sa = S-1 + S-3
Sb = S-4 + S-5
 L1= H-1 + Sa + H-3 + Sb
 L2 = S-2 – ½(Width) – ½(Width)
= S-2 – Width
 L3 = H-2 - ½(Width) – ½(Width)
= H-2 – Width
S-2
H-1
H-2
H-3
Sa Sb
STEP 3: P.C.C (1:4:8)
G.L
G.L
S No Description N
Measurement
Quantity
(cu. ft.)
Total
Quantity
(cu. ft.)
Remarks
L’ B’ D’
1 L1 1 87.70 2.5 0.5 109.63 109.63
2 L2 1 10.24 2.125 0.5 10.88 10.88 L=12.74-2.5
3 L3 1 20.61 2.5 0.5 25.76 25.76 L=23.11-2.5
Total Quantity 146.27
STEP 3: P.C.C (1:4:8)
Concrete in Foundations = 146.27 cu. ft.
Add 5% for waste
Concrete in Foundation = 146.27 + 5/100 * 146.27 = 153.58 cu. ft.
Thumb Rules
Dry material for 100 cu. ft. of cement concrete = 154 cu. ft.
Volume of cement bag = 1.25 cu. ft.
Materials
Concrete = 153.58 cu. ft *1.54 = 236.51 cu. ft.
Cement
= 1/13 * 236.51
= 18.19/1.25
= 18.19 cu. ft.
= 14.55 = 15 Bags
Sand = 4/13*236.51 = 72.77 cu. ft.
Aggregate = 8/13*236.51 = 145.54 cu. ft.
STEP 3: P.C.C (1:4:8)
 Care must be taken, while taking dimensions from the drawings in the
bill of quantities because the walls in this part of the structure are in
the form of steps with changing dimensions.
 This item is calculated in cft and the unit for payment is Rs. per 100
cft.
 In the description of work, the quality of bricks and mortar ratio must
be specified. For example, "Brickwork in foundation and plinth using
first class bricks laid in (1:4) or (1:6) cement-sand (c/s) mortar———
————“
STEP 4: Brickwork up to Plinth Level
with 1:6 (C/S)
 Wastage for masonry = 5%
 Wastage for mortar = 40%
STEP 4: Brickwork up to Plinth Level
with 1:6 (C/S)
Let Sa = S-1 + S-3
Sb = S-4 + S-5
 L1= H-1 + Sa + H-3 + Sb
 L2 = S-2 – ½(Width) – ½(Width)
= S-2 – Width
 L3 = H-2 - ½(Width) – ½(Width)
= H-2 – Width
S-2
H-1
H-2
H-3
Sa Sb
STEP 4: Brickwork up to Plinth Level
with (1:6 C/S)
G.L
Floor Details
Description N
Measurement Quantity
(cu. ft.)
Total
Quantity
(cu. ft.)
Remarks
L’ B’ D’
L1 = H-1 + Sa + H-3 + Sb
Step-1 1 87.70 1.5 0.5 65.78 65.78
Step-2 1 87.70 1.125 0.5 49.33 49.33
Step-3 up
to plinth 1 87.70 0.75 3.37 221.66 221.66 D = 2+1.5 – 0.13
Total Quantity 336.77
STEP 4: Brickwork up to Plinth Level
with 1:6 (C/S)
Description N
Measurement Quantity
(cu. ft.)
Total
Quantity
(cu. ft.)
Remarks
L’ B’ D’
L2 = S-2 – Width
Step-1 1 11.24 1.125 0.5 6.32 6.32 L=12.74-1.5
Step-2 1 11.62 0.75 0.5 4.36 4.36 L=12.74-1.125
Step-3 up
to plinth 1 11.99 0.38 3.37 15.35 15.35
L = 12.74 – 0.75
D = 2+1.5 –0.13
Total Quantity 26.03
STEP 4: Brickwork up to Plinth Level
with 1:6 (C/S)
Description N
Measurement Quantity
(cu. ft.)
Total
Quantity
(cu. ft.)
Remarks
L’ B’ D’
L3 = H-2 - Width
Step-1 1 21.61 1.5 0.5 16.20 16.20 L=23.11 –1.5
Step-2 1 21.985 1.125 0.5 12.36 12.36 L=23.11 –1.125
Step-3 up
to plinth 1 22.36 0.75 3.37 56.51 56.51
L=23.11 -0.75
D=2+1.5 –0.13
Total Quantity 85.07
STEP 4: Brickwork up to Plinth Level
with 1:6 (C/S)
Total Quantity = 336.77 + 26.03 + 85.07 = 447.87 cu. ft.
 Thumb Rules
Bricks for 100 cu. ft. of brick work = 1350 Nos.
Dry mortar for 100 cu. ft. of brick work = 30 cu. ft.
 Material
Bricks = 1350 / 100 * 447.87 = 6046 Bricks
Add 5% for wastage
Total bricks = 6046 + 5/100 * 6046 = 6349 Bricks
Mortar = 30 / 100 * 447.87 = 134.361
Add 40% for wastage
Total mortar = 134.361 + 134.361 * 40/100 = 188.10
STEP 4: Brickwork up to Plinth Level
with 1:6 /(C/S)
Cement
= 1 / 7 * 188.10
= 26.87 / 1.25 = 21.5
= 26.87
= 22 Bags
Sand = 6 / 7 * 188.10 = 161.22 cu. ft.
STEP 4: Brickwork up to Plinth Level
with 1:6 (C/S)
STEP 5: Steps in Front of Verandah with
1:6 (C/S)
Description N
Measurement
Quantity
(cu. ft.)
Total
Quantity
(cu. ft.)
Remarks
L’ B’ D’
Length of steps = 0.75 + 10 + 0.37 + 12 + 0.75 = 23.87’
Step-1 1 23.87 1 0.5 11.94 11.94
Step-2 1 23.87 2 0.5 23.87 23.87
Total Quantity 35.81
STEP 5: Steps in Front of Verandah with
1:6 (C/S)
 Thumb Rules
Bricks for 100 cu. ft. of brick work = 1350 Nos.
Mortar for 100 cu. ft. of brick work = 30 cu. ft.
 Materials
Bricks = 1350 / 100 * 35.81 = 483.44 = 484 Bricks
Add 5% for wastage
Total Bricks = 484 * 1.05 = 509 Bricks
Mortar = 30/100 * 35.81 = 10.74 cu. ft
Add 40% for wastage
Total Mortar = 10.74 * 1.40 = 15.04 cu. ft
STEP 5: Steps in Front of Verandah with
1:6 (C/S)
Total Mortar = 10.74 * 1.40 = 15.04 cu. ft
Cement = 1 / 7 * 15.04 = 2.14 cu. ft
= 2.14 / 1.25 = 1. 71 = 2 Bag
Sand = 6 / 7 * 15.04 = 12.89 cu. ft
STEP 5: Steps in Front of Verandah with
1:6 (C/S)
 Horizontal D.P.C. shall extend the full width of the super structure
walls, however, it shall not be provided across doorways and veranda
openings. It is also provided in roof and floors.
 Vertical D.P.C. is provided in external walls, especially, in the
walls of basements.
 The quantity of D.P.C. is estimated in square ft.(on area basis) and
standard unit for payment is Rs. per 100 sft
STEP 6: 1-1/2” DPC (1:2:4)
& 02 coats of hot bitumen
S-1 S-2 S-5
H-1
H-2
STEP 6: 1-1/2” DPC (1:2:4) & 02 coats of
hot bitumen
 (4.5” = 0.37’)
 (9” =0.75’)
 H-1= H-2= H-3=10’+12’+0.37’
+0.37’+0.37’
=23.11’
 S-1= S-2= S-5=12’+0.37’+0.37’
= 12.74’
TakingArea
Description N Measurement Quantity
(sq. ft.)
Total
Quantity
(sq. ft.)
Remarks
L’ B’ D’
L1 1 71.70 0.75 - 53.78 53.78
L= H-1 + S-1 + H-2
+ S-5
L2 1 12 0.37 - 4.44 4.44
L = 12.74 - 0.37 –
0.37
Columns 3 0.75 0.75 - 0.56 1.69
Total Quantity 59.91
STEP 6: 1-1/2” DPC (1:2:4) & 02 coats of
hot bitumen
Description N Measurement Quantity
(sq. ft.)
Total
Quantity
(sq. ft.)
Remarks
L’ B’ D’
Total
Area - - - - 59.16 59.91
Deductions
Doors 4 0.75 - 3.00 3.00
4 0.37 - 1.50 1.50
Total Quantity 55.41
STEP 6: 1-1/2” DPC (1:2:4) & 02 coats of
hot bitumen
Concrete Volume = 55.41 x 0.125 = 6.93 cu. ft.
Add 5% for wastage
Total concrete volume = 6.93 * 1.05 = 7.28 cu. ft
 Thumb Rules
Dry material for 100 cu. ft. of cement concrete = 154 cu. ft.
Bitumen for 100 sq. ft. of DPC (first coat) = 15 Kg
Bitumen for 100 sq. ft. of DPC (second coat) = 10 Kg
 Materials
Dry Concrete = 7.28 x 1.54 = 11.21 cu. ft.
STEP 6: 1-1/2” DPC (1:2:4) & 02 coats of
hot bitumen
Cement = 1/7 x 11.21 = 1.60 /1.25 = 1.28 = 2 Bags
Sand = 2/7 x 11.21 = 3.20 cu. ft.
Coarse aggregate = 4/7 x 11.21 = 6.4 cu. ft.
Bitumen = 25/100 x 55.41 = 13.85 Kg
STEP 6: 1-1/2” DPC (1:2:4) & 02 coats of
hot bitumen
Important considerations are:
1. Measurements of walls shall be taken in the same order and in the
same manner as for brickwork in foundations and plinth.
2. In the first measurements, all openings such as doors, windows,
veranda openings etc. shall be neglected. However, deductions shall
be made for all openings in the walls, at the end of the item.
3. In the description of the work, the quality of bricks and mortar
ratio have to be specified.
4. Masonry for arches shall be paid separately, at a different rate.
STEP 7: Brick work in super structure
5. The height of super structure is very important. Generally the
quantities are worked out for each storey separately and rates
would be different for different storeis because of additional
labor work, scaffolding and shuttering.
6. The item is worked out in cft and the standard unit for payment is
Rs. Per 100 cft.
STEP 7: Brick work in super structure
S-1 S-2 S-5
H-1
H-2
STEP 7: Brick work in super structure using
first class bricks in (1:4) cement sandmortar
 (4.5” = 0.37’)
 (9” =0.75’)
 H-1= H-2= H-3=10’+12’+0.37’
+0.37’+0.37’
=23.11’
 S-1= S-2= S-5=12’+0.37’+0.37’
= 12.74’
4) 1-1/2’’ thick brick tiles joined and
pointed in cement sand mortar (1:3)
3) 1’’ thick mud plaster
2) 4’’ thick earth filling
1) Roof insulation comprising of 2
coats of hot bitumen
STEP 7: Brick work in super structure
Description N
Measurement Quantity
(cu. ft.)
Total
Quantity
(cu. ft.)
Remarks
L’ B’ D’
L1 1 71.70 0.75 12 645.3 645.3
L= H-1 + S-1 + H-
2
+ S-5
L2 1 12 0.37 12 53.28 53.28
L = 12.74 - 0.37 –
0.37
Columns 3 0.75 0.75 10.5 5.9 17.71
716.29
STEP 7: Brick work in super structure
H-2
 H-1= H-2= H-3=10’+12’+0.37’
+0.37’+0.37’
=23.11’
Sa = Sb = 12’.74 + 8’
= 20.74’
Sa Sb
STEP 7: Brick work in super structure
parapet wall
Description N
Measurement
Quantity
(cu. ft.)
Total
Quantity
(cu. ft.)
Remarks
L’ B’ D’
Total
Volume 716.29
Parapet
Wall 1 87.7 0.75 1.541 101.35 101.35
L= H-1 + Sa + H-2
+ Sb
Total Volume 817.64
STEP 7: Brick work in super structure
Description N
Measurement
Quantity
(cu. ft.)
Total
Quantity
(cu. ft.)
RemarksL’ B’ D’
Doors
1 4 0.75 7 21 21
1 4 0.37 7 10.5 10.5
Windows 3 4 0.75 4 12 36
Ventilators 4 2.5 0.75 1.5 2.81 11.25
Shelves 2 4 0.5 5 10 20
RCC Lintels
Doors
1 5 0.75 0.5 1.87 1.87
1 5 0.37 0.5 0.93 0.93
Windows 3 5 0.75 0.5 1.87 5.62
Ventilators 4 3.5 0.75 0.5 1.31 5.25
Shelves 2 5 0.75 0.5 1.87 3.75
116.18
Net Total = (817.64-116.18) 701.46
STEP 7: Brick work in super structure
(Deductions)
Volume = 701.46 cu. ft.
 Thumbs Rules
Bricks for 100 cu. ft. of brick work = 1350 Nos.
Dry mortar for 100 cu. ft. of brick work = 30 cu. ft.
 Materials
Bricks = 1350 / 100 * 701.46 = 9469.71 = 9470 Bricks
Add 5% for wastage
Bricks = 9470 * 1.05 = 9944 Bricks
Mortar = 701.46 * 30/100 = 210.44 cu.ft
Add 40% for wastage
Total Mortar = 210.44 * 1.40 = 294.61 cu.ft
STEP 7: Brick work in super structure using
first class bricks in (1:4) cement sandmortar
Cement = 1 / 5 * 294.61 = 58.92
= 58.92/ 1.25 = 47.13 = 48 Bags
Sand = 4 / 5 * 294.61 = 235.69 cu. ft.
STEP 7: Brick work in super structure using
first class bricks in (1:4) cement sandmortar
 For R.C.C. Roof slabs and beams, the total quantities of concrete and
steel are estimated, separately.
 The quantity of plain concrete is estimated in cft and the standard
unit for payment of concrete is Rs. per 100 cft.
 Volume of Reinforcing Steel is not deducted , while estimating the
volume of plain concrete for payment.
 R.C.C. lintels over wall openings such as doors and windows are
also included in R.C.C. work.
STEP 8: Reinforced Cement Concrete
(4.5” = 0.37’)
(9” = 0.75’)
 L = 10’+12’+0.37’+0.75+0.75
= 23.87’
 B = 12’+0.75+0.75+8
= 21.5’
L
B
STEP 8: Reinforced Cement Concrete
(1:2:4)(Slab, Lintels & Beams)
Description N Measurement Quantity
(cu. ft.)
Total
Quantity
(cu. ft.)
Remarks
L’ B’ D’
Roof Slab 23.87 21.5 0.33 169.43 169.43
Verandah
Long Beam 1 23.87 0.75 1.5 26.86 26.86
Verandah
Short Beam 2 7.25 0.75 1.5 8.156 16.31
Total Quantity 212.60
STEP 8: Reinforced Cement Concrete
(1:2:4)(Slab, Lintels & Beams)
Description N Measurement Quantity
(cu. ft.)
Total
Quantity
(cu. ft.)
Remarks
L’ B’ D’
Volume 212.60
Lintels
Doors
1 5 0.75 0.5 1.87 1.87
1 5 0.37 0.5 0.93 0.93
Windows 3 5 0.75 0.5 1.87 5.62
Ventilators 4 3.5 0.75 0.5 1.31 5.25
Shelves 2 5 0.75 0.5 1.87 3.75
Shades 2 5 1.5 0.25 1.87 3.75
Total Quantity 233.77
STEP 8: Reinforced Cement Concrete
(1:2:4)(Slab, Lintels & Beams)
STEP 8: Reinforcement Steel / General
Steel Work
 Steel is provided separately from R.C.C. per ton, per Kg, or per cwt
(standard weight also called Quintal or century weight equal to 112
Ibs = 50Kg).
 Quantity of steel can either be worked out by rules of thumb practice
or by intensive calculations taking the length and diameter of steel
bars from the working drawings showing reinforcement details and
bar-bending schedules. In taking length of bars, due margin of
hooks, bends and overlapping is given.
 As a Rule Of Thumb Practice, for ordinary beams and slabs for
residences, assume 6.75 Ibs of steel per cft of R.C.C. work.
However, for R.C.C. columns, it varies from 8 to 10 Ibs per cft.
normally, we use 2% of steel in columns.
 Percentage of steel means, area of steel divided by total area of the
column multiplied by 100 and 1% of steel in columns corresponds to
a quantity of 4.5 Ibs/cft.
 Wastage for slab is 8% while wastage for other member 10%
(including laps)
Description N Measurement
Quantity
(lbs)
Total
Quantity
(lbs)
Remarks
6.75 Ibs. of steel per cu. ft. of R.C.C. work
Steel 6.75 64.34 434.30 434.30
233.77-169.43
=64.34
Total Weight 434.30
STEP 8: Mild Steel Round Bars as in
Reinforcement
 Thumbs Rules
Dry material for 100 cu. ft. of cement concrete = 154 cu. ft.
6.75 Ibs. of steel per cu. ft. of R.C.C. work
 Materials
Concrete for slab = 169.43 cu. ft
Add 8% for wastage in slab
Total Concrete for slab = 160.43 * 1.08 = 183 cu. ft
Concrete for other R.C.C members = 233.77 – 169.43 = 64.34 cu.ft
Add 5% for wastage
Total Concrete for other R.C.C members = 64.34 * 1.05 = 67.55 cu.ft
STEP 8: Reinforced Cement Concrete
(1:2:4)(Slab, Lintels & Beams)
Total Concrete for R.C.C members = 183 + 67.55 = 250.55 cu.ft
Dry Concrete = 250.55 x 1.54 = 385.85 cu. ft.
Cement = 1/7 x 385.85 = 55.07/1.25 = 44.06 = 45 Bags
Sand = 2/7 x 385.85 = 110.24 cu. ft.
Coarse aggregate= 4/7 x 385.85 = 220.28 cu.ft
Mild steel round bars= 434.30 lbs
Add 10% for wastage
Total mild steel = 434.30 * 1.1 = 477.72 lbs
Slab steel = 2682.41 lbs (From Lecture 10)
Total steel = 2682.41 + 477.72 = 3160.13 lbs
STEP 8: Reinforced Cement Concrete
(1:2:4)(Slab, Lintels & Beams)
Steel = 3160.13/ 2000
Steel = 1.58 tons
 Roof consisting of beams, battens, and tiles or wooden planks is
estimated for each part, separately
 Steel beam is estimated by weight, whereas, wooden beam is
measured in cft. Battens are estimated by numbers indicating there
size and lengths. Tiles are also estimated by size and numbers.
 Roof finishing may consist of bitumen coating and/or Polythene
sheets (water proofing) , earth filling (heat proofing) and brick tiles,
etc.
 Dimensions are taken from inner face to inner face of parapet walls.
 This item is estimated in sft and a composite rate for payment is
taken as Rs. per 100 sft of the roof area.
Roofing
 L = 10’+12’+0.37’ = 22.37’
 B = 12’+0.75+8-0.75 = 20’
Description N Measurement
Quantity
(sq. ft.)
Total
Quantity
(sq. ft.)
Remarks
Taking Area
Area 22.37 20 447.4 447.4
Total Area 447.4
STEP 9: Roof Insulation (02 coats of hot bitumen, 4”
thick earth filling, 1” thick mud plaster and 1-1/2” thick brick tiles
jointed and pointed in cement sand mortar (1:3))
 Thumbs Rules
100 sq. ft. surface area using bricks on bed= 360 Nos.
Dry mortar for 100 sft = 9.00 cft
Bitumen for 100 sq. ft. (first coat) = 15 Kg
Bitumen for 100 sq. ft. (second coat) = 10 Kg
 Materials
Brick Tiles = 360/100 x 447.4 = 1610.6 = 1611 No.
Add 5% for wastage
Total brick tiles = 1161 * 1.05 = 1220 No.
Mortar = 447.4 * 9 / 100 = 40.27 cu.ft
Add 40% for wastage
Total mortar = 40.27 * 1.4 = 56.38 cu.ft
STEP 9: Roof Insulation (02 coats of hot bitumen, 4”
thick earth filling, 1” thick mud plaster and 1-1/2” thick brick tiles
jointed and pointed in cement sand mortar (1:3))
Cement = 1/4 x 56.38 = 14.09 / 1.25 = 11.25 = 12 Bags
Sand = 3/4 x 56.38 = 42.27 cu. ft.
Mud/ Earth Filling = 447.4 x 0.42 = 188 cu. ft.
Bitumen= 25/100 x 447.4 = 111.9 kg
Polythene Sheet = 447.4 sq. ft.
STEP 9: Roof Insulation (02 coats of hot bitumen, 4”
thick earth filling, 1” thick mud plaster and 1-1/2” thick brick tiles
jointed and pointed in cement sand mortar (1:3))
 Cement concrete floors, mosaic floors, and brick floors are most
commonly used.
 Payments are made separately for different layers, like, topping, lean
concrete, sand filling, earth filling, etc.
 Earth filling, sand filling and lean concrete are paid by volume,
whereas, topping is paid on area basis, mentioning thickness in
the description.
 Standard unit for payment of topping is, usually, Rs. per 100 sft.
 The skirting is estimated in running ft.
Flooring
G.L
Verandah Length = 10’+12’+0.37’
= 22.37’
B = 8’ – 0.75’ = 7.25’
L
B
STEP 10: Flooring (sand under floor)
(4.5” = 0.37’)
(9” = 0.75’)
Description N
Measurement
Quantity
(cu. ft.)
Total
Quantity
(cu. ft.)
Remarks
L’ B’ D’
Room 1 1 12 10 0.5 60 60
Room 2 1 12 12 0.5 72 72
Verandah 1 22.37 7.25 0.5 81.11 81.11
Total Quantity 213.11
STEP 10: Flooring (sand under floor)
 4” thick P.C.C = 0.33’
L
B
(4.5” = 0.37’)
(9” = 0.75’)
STEP 10: Flooring (Cement concrete
(1:4:8) as under layer of floors)
Description N
Measurement Quantity
(cu. ft.)
Total
Quantity
(cu. ft.)
Remarks
L’ B’ D’
Room 1 1 12 10 0.33 40 40
Room 2 1 12 12 0.33 48 48
Verandah 1 22.37 7.25 0.33 54.07 54.07
Total Quantity 142.07
STEP 10: Flooring (Cement concrete
(1:4:8) as under layer of floors)
Concrete = 142.07 cu. ft.
Add 5% for wastage
Total concrete =142.07 * 1.05 = 149.17 cu.ft
 Thumbs Rules
Dry material for 100 cu. ft. of cement concrete = 154 cu. ft.
 Materials
Dry Concrete = 149.17 x 1.54 = 229.73 cu. ft.
Cement = 1/13 x 229.73 = 17.67/1.25 = 14.13 = 15 Bags
Sand = 4/13 x 229.73 = 70.69 cu. ft.
Coarse aggregate = 8/13 x 229.73 = 141.37 cu. ft.
STEP 10: Flooring (Cement concrete
(1:4:8) as under layer of floors)
TakingArea
Description N
Measurement
Quantity
(sq. ft.)
Total
Quantity
(sq. ft.)
RemarksL’ B’ D’
Room 1 1 12 10 - 120 120
Room 2 1 12 12 - 144 144
Verandah 1 23.87 8 - 191 191
L = 12+ 10
+0.37+0.75+0.75
Door Sill 1 1 4 0.75 - 3 3
Door Sill 2 1 4 0.37 - 1.5 1.5
Deductions
Columns 3 0.75 0.75 - 0.56 1.68
Total Quantity 457.80
STEP 10: Flooring (1-1/2” P.C.C (1:2:4) as
top layer of floor, finished smooth)
Concrete Volume = 457.8 x 0.125 = 57.23 cu. ft.
Add 5% for wastage
Total concrete = 57.23 * 1.05 = 60.09 cu.ft
 Thumbs Rules
Dry material for 100 cu. ft. of cement concrete = 154 cu. ft.
 Materials
Dry Concrete = 60.09 x 1.54 = 92.54 cu. ft.
Cement = 1/7 x 92.54 = 13.22/1.25 = 10.576 = 11 Bags
Sand = 2/7 x 92.54 = 26.44 cu. ft.
Coarse aggregate = 4/7 x 92.54 = 52.88 cu. ft.
STEP 10: Flooring (1-1/2” P.C.C (1:2:4) as
top layer of floor, finished smooth)
 Materials
Total Cement bags = 15 + 11 = 26 Bags
Total Sand = 213.11 + 70.69 + 26.44 = 310.24 cu. ft.
Total Coarse aggregate = 141.13 + 52.88 = 194.01 cu. ft.
STEP 10: Flooring (Cement concrete
(1:4:8) as under layer of floors)
 The type of plaster, proportioning of materials and minimum
thickness of plaster have to be specified.
 The quantity is calculated for total wall surface without deduction for
openings such as doors windows, ventilators, etc. However, if the
wall is being plastered on both the faces, the deductions for opening
areas are made from one side only.
 Standard unit for payment is Rs. per 100 sft.
 Height is also specified for plastering because, for greater heights,
labor cost increases. The rate varies according to the number of the
storey
Plastering
STEP 11: ½” thick (1:3) C/S plaster to
walls finished smooth
(4.5” = 0.37’)
(9” = 0.75’)
 Inner Height = 12’
 Outer Height =
TakingArea
Description N
Measurement
Quantity
(sq. ft.)
Total
Quantity
(sq. ft.)
Remarks
L’ B’ D’
INNER SIDE
Room 1
(Long Wall) 2 12 - 12 144 288
Room 1
(Short Wall) 2 10 - 12 120 240
Room 1
(Ceiling) 1 10 12 - 120 120
Room 2
(Long Wall) 2 12 - 12 144 288
Room 2
(Short Wall) 2 12 - 12 144 288
STEP 11: ½” thick (1:3) C/S plaster to
walls finished smooth
Description N
Measurement
Quantity
(sq. ft.)
Total
Quantity
(sq. ft.)
Remarks
L’ B’ D’
INNER SIDE
Room 2
(Ceiling) 1 12 12 - 144 288
Verandah
Wall 1 23.87 - 12 286.56 286.56
Verandah
Ceiling 1 22.37 7.25 - 162.18 162.18
Columns 3 3 - 10.5 31.5 94.5
L= 0.75 + 0.75 +
0.75 + 0.75
Long Beam
(Internal) 1 22.37 - 1.5 33.55 33.55
STEP 11: ½” thick (1:3) C/S plaster to
walls finished smooth
Description N
Measurement
Quantity
(sq. ft.)
Total
Quantity
(sq. ft.)
RemarksL’ B’ D’
INNER SIDE
Long Beam
(Soffit) 1 21.62 - 0.75 8.10 8.10
L= 23.87 – 0.75 -
0.75 -0.75
Short Beam
(Internal) 2 7.25 - 1.5 10.875 10.875
Short Beam
(Soffit) 2 7.25 - 0.75 5.43 10.87
OUTER SIDE
Rear Wall 1 23.87 - 15.33 365.92 365.92 L =1.5+12+0.33+1.5
STEP 11: ½” thick (1:3) C/S plaster to
walls finished smooth
Description N
Measurement
Quantity
(sq. ft.)
Total
Quantity
(sq. ft.)
Remarks
L’ B’ D’
Left & Right
Side
2 13.5 - 15.33 206.95 413.91
Front Side
(above
verandah)
1 23.87 - 3.33 79.4 79.4 L = 1.5 + 1.5 + 0.33
Left & Right
Side
(above
verandah)
2 8 - 3.33 26.64 53.28
L = 1.5+0.125
+12+0.33+1.5
Verandah
sides
(lower area)
2 8 - 1.5 12 24
Parapet Wall
Inner side 1 84.74 - 1 84.74 84.74
L = 22.37 + 22.37 +
20 + 20
Top side 1 87.7 - 0.75 65.77 65.77 Center to center
Outer side
Already calculated
above
STEP 11: ½” thick (1:3) C/S plaster to
walls finished smooth
Description N
Measurement
Quantity
(sq. ft.)
Total
Quantity
(sq. ft.)
Remarks
L’ B’ D’
Verandah Steps
Tread 2 23.87 - 1 23.87 47.74
Riser 3 23.87 - 0.5 11.93 35.80
Sides
2 2 - 0.5 1.00 2.00
2 1 - 0.5 0.5 1.00
Misc
Door Jambs
2 7 0.75 - 5.25 10.50
2 7 0.37 - 2.63 5.25
1 4 0.75 - 3.0 1.50
1 4 0.37 - 1.50 3.00
STEP 11: ½” thick (1:3) C/S plaster to
walls finished smooth
Description N
Measurement
Quantity
(sq. ft.)
Total
Quantity
(sq. ft.)
Remarks
L’ B’ D’
Window
Jambs
6 0.75 - 4 3.00 18.00
6 0.75 4 - 3.00 18.00
Ventilator
Jambs
8 0.75 2.5 - 1.88 15.00
8 0.75 - 1.5 1.19 9.00
Shelves 4 0.5 - 5 2.5 10.00
Total Area = 3211.42
DEDUCTION
Doors 2 4 - 7 28.00 56.00
Windows 3 4 - 4 16.00 48.00
Ventilators 4 2.5 - 1.5 3.75 15.00
STEP 11: ½” thick (1:3) C/S plaster to
walls finished smooth
Net Area = 3211.42 – 119 = 3281.2
 Thumbs Rules
Dry mortar for 100 sq. ft. of ½” thick cement plaster = 6 cu. ft.
or
100 cu. ft. wet mortar = 128 cu. ft. dry mortar
 Materials
Volume = 3294.7 x (0.5/12) = 137.28 cu. ft.
Add 40% for wastage
Total volume = 137.28 * 1.4 = 192.19 cu. ft.
Dry volume = 192.19 * 1.28 = 246 cu. ft
Cement = 1 /4 * 246 = 61.5
Sand
= 61.5/ 1.25
= 3 / 4 * 246
= 49.2 = 50 Bags
= 184.5 cu. ft.
STEP 11: ½” thick (1:3) C/S plaster to
walls finished smooth
 The type of material used and the quantity of finish required should
be clearly indicated in the description of the item.
 The rate for any type of woodwork includes cutting of timber to
required sizes, joinery work, fittings and fastenings, three coats of oil
paints or varnish, bolts, locks, handles, etc.
 The measurements are taken for the overall area of doors, windows,
etc. If volume of timber required for these items is to be find out, the
computed area is multiplied with the nominal thickness and an
allowance of 25% is made for wastage of timber.
 Rectangular wooden beams, vertical columns, trusses, etc., are
measured in cft.
 Wooden stairs are measured in number of steps and description of the
item includes the riser, tread, and width of the steps.
 Wooden shelves are measured in running ft (RFT).
Wood work / Carpentry
Description N
Measurement
Quantity
(sq. ft.)
Total
Quantity
(sq. ft.)
Remarks
L’ B’ D’
1 ½” Thick
Wooden
Doors with
Chowkat
2 4 - 7 28 56
Windows
and
Ventilators
3 4 - 4 16 48
4 2.5 - 1.5 3.75 15
Three Coats
of
Painting to
Doors
2 - - - 56 112 Already calculated
STEP 12: Door, Windows & Ventilators
Frames
 Thumbs Rules
Timber for 100 sq. ft. of Panelled Doors = 13 cu. ft.
Timber for 100 sq. ft. of Glazed windows and Ventilators = 8 cu. ft.
 Materials
Timber for doors = 13 / 100 x 56 = 7.28 cu. ft.
Timber for windows and Ventilators = 8 / 100 x 63 = 5.04 cu. ft.
Total = 13.32 cu. ft.
Add 25% for wastage
Total wood required = 13.32 * 1.25 = 16.65 cu. ft
STEP 12: Door, Windows & Ventilators
Frames
Description N
Measurement
Quantity
(sq. ft.)
Total
Quantity
(sq. ft.)
Remarks
L’ B’ D’
Room No.1
(Long wall) 2 12 - 12 144 288
Room No.1
(Short wall) 2 10 - 12 120 240
Room No.1
(Ceiling) 1 10 12 - 120 120
Room No.2
(Long wall) 2 12 - 12 144 288
Room No.2
(Short wall) 2 12 - 12 144 288
Room No.2
(Ceiling) 1 12 12 - 144 144
Verandah wall 1 23.875 - 12 286.5 286.5
Verandah
Ceiling 1 22.375 - 7.25 162.26 162.26
STEP 13: Three coats of distempering/
white washing to walls (Internal Side)
Description N
Measurement
Quantity
(sq. ft.)
Total
Quantity
(sq. ft.)
Remarks
L’ B’ D’
Columns 3 3 - 10.5 25.50 76.50
Long beam
(inner side)
1 22.375 - 1.5 33.55 33.55
Long beam
(soffit)
1 21.62 - 0.75 16.21 16.21
Short beam
(sides)
2 7.25 - 1.5 10.87 21.74
Short beam
(soffit)
2 7.25 - 0.75 5.43 10.87
Door Jambs
2 0.75 - 7 5.25 10.50
2 0.375 - 7 2.63 5.25
1 0.75 - 4 3 1.50
1 0.375 - 4 1.50 3.00
STEP 13: Three coats of distempering/
white washing to walls (Internal Side)
Description N
Measurement
Quantity
(sq. ft.)
Total
Quantity
(sq. ft.)
Remarks
L’ B’ D’
Window
Jambs
6 0.75 - 4 3 18
6 0.75 - 4 3 18
Ventilator
Jambs
8 0.75 - 2.5 1.88 15
8 0.75 - 1.5 1.19 9
Shelves
4 0.5 - 5 2.5 10
4 0.5 - 4 2.0 10
DEDUCTION
Doors 4 4 - 7 28 112
Windows 4 4 - 4 16 64
Ventilators 6 2.5 - 1.5 3 22.50
Net Total Area 1877.38
STEP 13: Three coats of distempering/
white washing to walls (Internal Side)
 Thumbs Rules
Lime for 100 sq. ft. of white wash (one coat) = 1.00 Kg
 Materials
Lime for three coats=1/100 x 3 x 1877.3 = 56.3 Kg
STEP 13: Three coats of distempering/
white washing to walls (Internal Side)
Description N
Measurement
Quantity
(sq. ft.)
Total
Quantity
(sq. ft.)
Remarks
L’ B’ D’
Rear wall 1 23.875 - 15.375 367.07 367.07
Left & Right
side wall 2 13.5 - 15.375 207.5 415.13
Front side
(above
verandah
roof)
1 23.875 - 3.33 79.50 79.50
Sides (above
verandah
roof)
2 8 - 3.33 26.64 53.28
Left & Right
side wall of
verandah
2 8 - 1.5 12 24
STEP 14: Three coats of Weather shield
paint to walls. (External side)
Description N
Measurement
Quantity
(sq. ft.)
Total
Quantity
(sq. ft.)
Remarks
L’ B’ D’
PARAPET WALL
Top of
parapet
wall
1 87.7 - 0.75 65.775 65.775
Parapet
wall
(inside)
2 20 - 1 20 40
2 22.37 - 1 22.37 44.74
DEDUCTION
Windows 2 4 - 4 16.00 32.00
Ventilators 2 2.5 - 1.5 3.75 7.50
Net Total 1049.99
STEP 14: Three coats of Weather shield
paint to walls. (External side)
Market Rates
Sr. No Item Rate (Rupees)
1 Cement 550 / bag
2 Sand 2000 / 100 cu.ft
3 Aggregate 4500 / 100 cu.ft
4 Bricks 10 / each
5 Steel 92,000 / ton
6 Bitumen 105 / kg
7 Weather Shield 30 / sft
8 Distemper 15 / sft
9 Brick Tile 12 / each
10 Framic tile or face tile 18 / each
Market Rates
Sr. No Item Rate (Rupees)
11 Wood (Deodar) 4500 / cft
12 Lime 10 / kg
13 Earth Filling 3 / cft
14 Polythene sheet 2 / sft
Cost Summary
Sr.
No
Description Item Unit Quantity
Unit Rate
(Rs.)
Amount
(Rs.)
1 Top soil (3’’ depth) 3600
2
Excavate
foundation trenches
(3’6’’ depth)
8873
3
Foundation
concrete (1:4:8)
Cement
Sand
Aggregate
Bags
Cu.ft
Cu.ft
15
73
146
550
20
45
8250
1460
6570
4
Foundation walls
(1:6 C/S)
Bricks
Cement
Sand
No.
Bags
Cu.ft
6349
22
162
10
550
20
63490
12100
3240
5
Brick steps in front
of verandah
(1:6 C/S)
Bricks
Cement
Sand
No.
Bags
Cu.ft
484
2
13
10
550
20
4840
1100
260
Sr.
No
Description Item Unit Quantity
Unit Rate
(Rs.)
Amount
(Rs.)
6
1/2’’ D.P.C (1:2:4)
&
2 coats of bitumen
Cement
Sand
Aggregate
Bitumen
Bags
Cu.ft
Cu.ft
kg
2
3
6
14
550
20
45
105
1100
60
270
1470
7
Brick work in
superstructure
(1:4 C/S)
Bricks
Cement
Sand
No.
Bags
Cu.ft
9944
48
236
10
550
20
99440
26400
4720
8
R.C.C
slab, beams, lintels
(1:2:4)
Cement
Sand
Aggregate
Steel
Bags
Cu.ft
Cu.ft
Tons
45
110
220
1.58
550
20
45
92000
24750
2200
9900
145360
9
Roof insulation
1-1/2’’ tiles
1:3 C/S
Earth filling 5’’
2 coats of hot
bitumen
Polythene sheet
Brick tiles
Cement
Sand
Mud
Bitumen
Sheet
No.
Bags
Cu.ft
Cu.ft
Kg
sft
1220
12
42
188
112
447
12
550
20
3
105
2
14640
6600
840
564
11760
894
Sr.
No
Description Item Unit Quantity
Unit Rate
(Rs.)
Amount
(Rs.)
10
Flooring
Sand cushion 6’’
4’’ P.C.C (1:4:8)
1-1/2’’ P.C.C (1:2:4)
Cement
Sand
Aggregate
Bags
Cu.ft
Cu.ft
26 bags
310 cu.ft
194 cu.ft
550
20
45
14300
6200
8730
11
Plastering
1-1/2’’ thick (1:3)
C/S
Cement
Sand
Bags
Cu.ft
50 bags
185 cu.ft
550
20
27500
3700
12
Wood work
Door, windows,
ventilators & frames
Wood Cu.ft 17 cu.ft 4500 76,500
13
3 coat distempering/
white wash
Lime
Distemper
kg
sft
56 kg
1877 sft
10
15
560
56310
14
3 coat of weather
shield paint
Weather
shield
sft 1050 sft 30 31500
Total Cost 690,051
Cost per square foot
 Total cost = Rs. 690,051
 Plot covered area = 23.87’ x 21.5’ = 513.205 sft
 Cost per sft = Total cost / Covered Area
 Cost per sft = 690,051 / 513.205 = Rs. 1345 / sf t
Instructions for Term Project
 For slab assume suitable bars and calculate steel using new
method.
 Perform quantity take by assuming slab as a single RCC
member of 6’’- 8’’ depth instead of using roof layers.
 Add wastage for each item of work.
 Use market rates provided above for calculating material cost.
 Develop a BoQ/Cost summary.
 Divide total cost with your buildings covered area to calculate
cost per square foot.

More Related Content

What's hot

Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
Ganesh Tatikonda
 
Construction equipments
Construction equipmentsConstruction equipments
Construction equipmentsAshish Parihar
 
Foundation types
Foundation typesFoundation types
Foundation types
Ashwini Ingale
 
Chapter 3 shallow foundations
Chapter 3 shallow foundationsChapter 3 shallow foundations
Chapter 3 shallow foundations
KHUSHBU SHAH
 
5#rate analysis problems
5#rate analysis   problems5#rate analysis   problems
5#rate analysis problems
LIJI A
 
Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works  Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works ALI HYDER GADHI
 
Soil exploration part i
Soil exploration part  iSoil exploration part  i
Soil exploration part i
Avinash Kumar Gupta
 
Cracks in Buildings
Cracks in BuildingsCracks in Buildings
Cracks in Buildings
Aravind Samala
 
Retaining walls
Retaining wallsRetaining walls
Retaining walls
Penchala Vineeth
 
Earthwork
EarthworkEarthwork
Earthwork
Rajiva Gupta
 
Chapter 4 repair, rehabilitation & retrofiiting
Chapter 4 repair, rehabilitation & retrofiitingChapter 4 repair, rehabilitation & retrofiiting
Chapter 4 repair, rehabilitation & retrofiiting
Ankit Patel
 
hot and cold weather concreting
hot and cold weather concretinghot and cold weather concreting
hot and cold weather concreting
Construction Tech. and Mgmt., VNIT Nagpur
 
Estimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provisionEstimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provision
AshwiniChaudhari13
 
Repair and Rehabilitation
Repair and RehabilitationRepair and Rehabilitation
Repair and Rehabilitation
GAURAV. H .TANDON
 
DESTRUCTIVE AND NON-DESTRUCTIVE TEST OF CONCRETE
DESTRUCTIVE AND NON-DESTRUCTIVE TEST OF CONCRETEDESTRUCTIVE AND NON-DESTRUCTIVE TEST OF CONCRETE
DESTRUCTIVE AND NON-DESTRUCTIVE TEST OF CONCRETE
Karan Patel
 
Plate load test ppt
Plate load test pptPlate load test ppt
Plate load test ppt
sayan sarkar
 
estimation,its types and methods
estimation,its types and methodsestimation,its types and methods
estimation,its types and methods
gayu pandian
 
Concrete Mix Design
Concrete Mix DesignConcrete Mix Design
Concrete Mix Design
GAURAV. H .TANDON
 
Cost estimation of a Building
Cost  estimation of a BuildingCost  estimation of a Building
Cost estimation of a Building
ARAVINDBORRA1
 
BUILDING ESTIMATION (Details Estimate For G+2 Storied Building presentation ...
BUILDING ESTIMATION (Details Estimate For G+2  Storied Building presentation ...BUILDING ESTIMATION (Details Estimate For G+2  Storied Building presentation ...
BUILDING ESTIMATION (Details Estimate For G+2 Storied Building presentation ...
Manoranjan Roy
 

What's hot (20)

Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
 
Construction equipments
Construction equipmentsConstruction equipments
Construction equipments
 
Foundation types
Foundation typesFoundation types
Foundation types
 
Chapter 3 shallow foundations
Chapter 3 shallow foundationsChapter 3 shallow foundations
Chapter 3 shallow foundations
 
5#rate analysis problems
5#rate analysis   problems5#rate analysis   problems
5#rate analysis problems
 
Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works  Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works
 
Soil exploration part i
Soil exploration part  iSoil exploration part  i
Soil exploration part i
 
Cracks in Buildings
Cracks in BuildingsCracks in Buildings
Cracks in Buildings
 
Retaining walls
Retaining wallsRetaining walls
Retaining walls
 
Earthwork
EarthworkEarthwork
Earthwork
 
Chapter 4 repair, rehabilitation & retrofiiting
Chapter 4 repair, rehabilitation & retrofiitingChapter 4 repair, rehabilitation & retrofiiting
Chapter 4 repair, rehabilitation & retrofiiting
 
hot and cold weather concreting
hot and cold weather concretinghot and cold weather concreting
hot and cold weather concreting
 
Estimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provisionEstimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provision
 
Repair and Rehabilitation
Repair and RehabilitationRepair and Rehabilitation
Repair and Rehabilitation
 
DESTRUCTIVE AND NON-DESTRUCTIVE TEST OF CONCRETE
DESTRUCTIVE AND NON-DESTRUCTIVE TEST OF CONCRETEDESTRUCTIVE AND NON-DESTRUCTIVE TEST OF CONCRETE
DESTRUCTIVE AND NON-DESTRUCTIVE TEST OF CONCRETE
 
Plate load test ppt
Plate load test pptPlate load test ppt
Plate load test ppt
 
estimation,its types and methods
estimation,its types and methodsestimation,its types and methods
estimation,its types and methods
 
Concrete Mix Design
Concrete Mix DesignConcrete Mix Design
Concrete Mix Design
 
Cost estimation of a Building
Cost  estimation of a BuildingCost  estimation of a Building
Cost estimation of a Building
 
BUILDING ESTIMATION (Details Estimate For G+2 Storied Building presentation ...
BUILDING ESTIMATION (Details Estimate For G+2  Storied Building presentation ...BUILDING ESTIMATION (Details Estimate For G+2  Storied Building presentation ...
BUILDING ESTIMATION (Details Estimate For G+2 Storied Building presentation ...
 

Similar to Lec 9 center line method

Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)
Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)
Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)
AMIT PAYAL
 
Estimation & costing guide
Estimation & costing guideEstimation & costing guide
Estimation & costing guide
Hiren Thakkar
 
B.arch Estimation and Costing
B.arch  Estimation and CostingB.arch  Estimation and Costing
B.arch Estimation and Costing
SamreenFatima29
 
Trapezium Rule Practical Substructure And Excavation Presentation1
Trapezium Rule Practical  Substructure And Excavation Presentation1Trapezium Rule Practical  Substructure And Excavation Presentation1
Trapezium Rule Practical Substructure And Excavation Presentation1
Daniel Ross
 
EC Unit 002 new (1).pdf
EC  Unit 002 new (1).pdfEC  Unit 002 new (1).pdf
EC Unit 002 new (1).pdf
mohsin mohammad
 
Quantity Surveying/longwall shortwall method/Earthwork- Civil Engineering
Quantity Surveying/longwall shortwall method/Earthwork- Civil EngineeringQuantity Surveying/longwall shortwall method/Earthwork- Civil Engineering
Quantity Surveying/longwall shortwall method/Earthwork- Civil Engineering
Aabid Ansar
 
Analysis and design of building
Analysis and design of buildingAnalysis and design of building
Analysis and design of building
Krishnagnr
 
Project 3 - Costing
Project 3 - CostingProject 3 - Costing
Project 3 - Costing
Kai Yun Pang
 
SPT and VST- By Daanyal Umar.pptx
SPT and VST- By Daanyal Umar.pptxSPT and VST- By Daanyal Umar.pptx
SPT and VST- By Daanyal Umar.pptx
MuhammadSafdar803531
 
Ce1402 estimationandquantitysurveying (1)
Ce1402 estimationandquantitysurveying (1)Ce1402 estimationandquantitysurveying (1)
Ce1402 estimationandquantitysurveying (1)
hlksd
 
Module_3.pdf.pdf
Module_3.pdf.pdfModule_3.pdf.pdf
Module_3.pdf.pdf
AlyssaSison3
 
GEOTECHNICAL-ENGINEERING-2 module 1 module 2 module 3
GEOTECHNICAL-ENGINEERING-2  module 1 module 2 module 3GEOTECHNICAL-ENGINEERING-2  module 1 module 2 module 3
GEOTECHNICAL-ENGINEERING-2 module 1 module 2 module 3
Akshayshinde504303
 
216586577-QUS-201-Building-Measurement-Specification-Theory-Practical.pdf
216586577-QUS-201-Building-Measurement-Specification-Theory-Practical.pdf216586577-QUS-201-Building-Measurement-Specification-Theory-Practical.pdf
216586577-QUS-201-Building-Measurement-Specification-Theory-Practical.pdf
Raj Bakhtani
 
Civil Works Site Construction Guidelines for Haris & Co Civil Team.pdf
Civil Works Site Construction Guidelines for  Haris & Co Civil Team.pdfCivil Works Site Construction Guidelines for  Haris & Co Civil Team.pdf
Civil Works Site Construction Guidelines for Haris & Co Civil Team.pdf
usamazahoor159
 
Basics of Foundation Engineering هندسة الأساسات & Eng. Ahmed S. Al-Agha
Basics of Foundation Engineering هندسة الأساسات & Eng. Ahmed S. Al-AghaBasics of Foundation Engineering هندسة الأساسات & Eng. Ahmed S. Al-Agha
Basics of Foundation Engineering هندسة الأساسات & Eng. Ahmed S. Al-Agha
Hossam Shafiq II
 
Fundamentals of Estimating and Costing
 Fundamentals of Estimating and Costing Fundamentals of Estimating and Costing
Fundamentals of Estimating and Costing
Ganesh Tatikonda
 
chapter1-210122051628.pdf
chapter1-210122051628.pdfchapter1-210122051628.pdf
chapter1-210122051628.pdf
Deepak37004
 
Lec- 3.ppt domabd gerhjddj gedawquun bhajk
Lec- 3.ppt domabd gerhjddj gedawquun bhajkLec- 3.ppt domabd gerhjddj gedawquun bhajk
Lec- 3.ppt domabd gerhjddj gedawquun bhajk
2cd
 
Double Storeyed Building Estimation and Costing by Nafisa Nazneen Choudhury (...
Double Storeyed Building Estimation and Costing by Nafisa Nazneen Choudhury (...Double Storeyed Building Estimation and Costing by Nafisa Nazneen Choudhury (...
Double Storeyed Building Estimation and Costing by Nafisa Nazneen Choudhury (...
Nafisa Nazneen Choudhury
 
INTERNSHIP (5).pptx
 INTERNSHIP (5).pptx INTERNSHIP (5).pptx
INTERNSHIP (5).pptx
kartik395517
 

Similar to Lec 9 center line method (20)

Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)
Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)
Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)
 
Estimation & costing guide
Estimation & costing guideEstimation & costing guide
Estimation & costing guide
 
B.arch Estimation and Costing
B.arch  Estimation and CostingB.arch  Estimation and Costing
B.arch Estimation and Costing
 
Trapezium Rule Practical Substructure And Excavation Presentation1
Trapezium Rule Practical  Substructure And Excavation Presentation1Trapezium Rule Practical  Substructure And Excavation Presentation1
Trapezium Rule Practical Substructure And Excavation Presentation1
 
EC Unit 002 new (1).pdf
EC  Unit 002 new (1).pdfEC  Unit 002 new (1).pdf
EC Unit 002 new (1).pdf
 
Quantity Surveying/longwall shortwall method/Earthwork- Civil Engineering
Quantity Surveying/longwall shortwall method/Earthwork- Civil EngineeringQuantity Surveying/longwall shortwall method/Earthwork- Civil Engineering
Quantity Surveying/longwall shortwall method/Earthwork- Civil Engineering
 
Analysis and design of building
Analysis and design of buildingAnalysis and design of building
Analysis and design of building
 
Project 3 - Costing
Project 3 - CostingProject 3 - Costing
Project 3 - Costing
 
SPT and VST- By Daanyal Umar.pptx
SPT and VST- By Daanyal Umar.pptxSPT and VST- By Daanyal Umar.pptx
SPT and VST- By Daanyal Umar.pptx
 
Ce1402 estimationandquantitysurveying (1)
Ce1402 estimationandquantitysurveying (1)Ce1402 estimationandquantitysurveying (1)
Ce1402 estimationandquantitysurveying (1)
 
Module_3.pdf.pdf
Module_3.pdf.pdfModule_3.pdf.pdf
Module_3.pdf.pdf
 
GEOTECHNICAL-ENGINEERING-2 module 1 module 2 module 3
GEOTECHNICAL-ENGINEERING-2  module 1 module 2 module 3GEOTECHNICAL-ENGINEERING-2  module 1 module 2 module 3
GEOTECHNICAL-ENGINEERING-2 module 1 module 2 module 3
 
216586577-QUS-201-Building-Measurement-Specification-Theory-Practical.pdf
216586577-QUS-201-Building-Measurement-Specification-Theory-Practical.pdf216586577-QUS-201-Building-Measurement-Specification-Theory-Practical.pdf
216586577-QUS-201-Building-Measurement-Specification-Theory-Practical.pdf
 
Civil Works Site Construction Guidelines for Haris & Co Civil Team.pdf
Civil Works Site Construction Guidelines for  Haris & Co Civil Team.pdfCivil Works Site Construction Guidelines for  Haris & Co Civil Team.pdf
Civil Works Site Construction Guidelines for Haris & Co Civil Team.pdf
 
Basics of Foundation Engineering هندسة الأساسات & Eng. Ahmed S. Al-Agha
Basics of Foundation Engineering هندسة الأساسات & Eng. Ahmed S. Al-AghaBasics of Foundation Engineering هندسة الأساسات & Eng. Ahmed S. Al-Agha
Basics of Foundation Engineering هندسة الأساسات & Eng. Ahmed S. Al-Agha
 
Fundamentals of Estimating and Costing
 Fundamentals of Estimating and Costing Fundamentals of Estimating and Costing
Fundamentals of Estimating and Costing
 
chapter1-210122051628.pdf
chapter1-210122051628.pdfchapter1-210122051628.pdf
chapter1-210122051628.pdf
 
Lec- 3.ppt domabd gerhjddj gedawquun bhajk
Lec- 3.ppt domabd gerhjddj gedawquun bhajkLec- 3.ppt domabd gerhjddj gedawquun bhajk
Lec- 3.ppt domabd gerhjddj gedawquun bhajk
 
Double Storeyed Building Estimation and Costing by Nafisa Nazneen Choudhury (...
Double Storeyed Building Estimation and Costing by Nafisa Nazneen Choudhury (...Double Storeyed Building Estimation and Costing by Nafisa Nazneen Choudhury (...
Double Storeyed Building Estimation and Costing by Nafisa Nazneen Choudhury (...
 
INTERNSHIP (5).pptx
 INTERNSHIP (5).pptx INTERNSHIP (5).pptx
INTERNSHIP (5).pptx
 

Recently uploaded

Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
DuvanRamosGarzon1
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
Kamal Acharya
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
Kamal Acharya
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
Kamal Acharya
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 

Recently uploaded (20)

Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 

Lec 9 center line method

  • 2. Estimation For 02 Room Office D4’x7’
  • 5. 4) 1-1/2’’ thick brick tiles joined and pointed in cement sand mortar (1:3) 3) 1’’ thick mud plaster 2) 4’’ thick earth filling 1) Roof insulation comprising of 2 coats of hot bitumen Roof Details
  • 6.  SPECIFICATIONS  P.C.C  Damp Proof Coarse (D.P.C) = 1:2:4  Floors = 1:4:8, 1:3:6, 1:2:4  R.C.C  Roof Slab, Lintel, and Sun Shades = 1:2:4  C/S Mortar  Brickwork in foundation = 1:6  Brickwork in superstructure = 1:4  Brick tiles on roof = 1:3  Plaster Work  ½” thick 1:3 C/S Plaster Estimation For 02 Room Office
  • 7.  SPECIFICATIONS  Clear height of rooms :12’  Clear height of Verandah : 12’  Plinth level : 1’-6”  Thickness of roof slab : 4”  Thickness of RCC shade : 3”  Depth of RCC Beams in Verandah : 1’-6” below verandah slab  Parapet wall : 1’-0”  Ventilators (4 No.) : 2’-6” x 1’-6”  RCC lintel : 6” in depth  Damp proof coarse : 1 ½”thick PCC (1:2:4) + 2 coats of hot bitumen +polythene sheet  Internal finishes : 03 coats of white wash/ distemper paint  External finishes : 03 coats of Weather shield paint  Lintels extend : 6” on each side Estimation For 02 Room Office
  • 8.  This item is described in detail but the price of this item is usually indicated as lump sum (LS).  The cost of this item is provided in the estimate by judgment, according to the description of the item and is indicated as Lump sum (L.S).  Estimator must determine  Depth of soil to be removed  Equipment to be used  STEP 1: Clearing and Grubbing
  • 9.  Topsoil is generally removed from all building, walk, roadway, and parking areas.  The volume of topsoil is figured in cubic yards.  A clearance around the entire basic plan must also be left to allow for the slope required for the general excavation; usually about 5 feet is allowed on each side of a building and 1 to 2 feet for walks, roadways, and parking areas.  STEP 1: Clearing and Grubbing
  • 10. Plot Area = 28’ x 28‘ = 784 Sq. ft. Efficiency of Dozer = 437 cu. ft. / hr. Rate = PRs 4000/ hr. (if more than 12,000 cu. ft.) Rate = PRs 8000/ hr. (if less than 12,000 cu. ft.) Let us assume 3 in. depth Quantity = 784 * (3/12) = 784 * 0.25 = 196 cu. ft. Equipment hours = 196 cu. ft / 437 cu. ft /hr = 0.45 hours Equipment cost = 0.45 hours * 8000 per hour = Rs. 3600 Equipment cost = Rs. 3600  STEP 1: Clearing and Grubbing
  • 11.  For symmetrical footings, which is the usual case, earthwork in excavation in foundations, foundation concrete, brickwork in foundation and plinth, and brickwork in superstructure may be estimated by either of the two methods: (1) Separate or Individual Wall Method (2) Center Line Method Methods Of Detailed Estimate
  • 12.  In this method, total length of center lines of walls, long and short, has to be found out  Find the total length of center lines of walls of same type, having same type of foundations and footings and then find the quantities by multiplying the total center length by the respective breadth and the height  In this method, the length will remain the same for excavation in foundations, for concrete in foundations, for all footings, and for superstructure (with slight difference when there are cross walls or number of junctions)  This method is quicker but requires special attention and considerations at the junctions, meeting points of partition or cross walls Center Line Method
  • 13.  For rectangular, circular polygonal (hexagonal, octagonal etc.) buildings having no inter or cross walls, this method is quite simple  For buildings having cross or partition walls, for every junction, half breadth of the respective item or footing is to be deducted from the total center length  Thus in the case of a building with one partition wall or cross wall having two junctions, deduct one breadth of the respective item of work from the total center length Center Line Method
  • 14. Centre to Centre Distance  (4.5” = 0.37’)  (9” =0.75’)  H-1= H-2= H-3=10’+12’+0.37’ +0.37’+0.37’ =23.11’  S-1= S-2= S-5=12’+0.37’+0.37’ = 12.74’  S-3= S-4= 7.25’+0.37’+0.37’ = 8’ S-1 S-2 S-5 H-1 H-2 H-3 S-3 S-4
  • 15. STEP 2: Excavation  Earthwork in excavation for foundation trenches is calculated by taking the dimensions of each trench as length x breadth x depth.  It is measured in cubic ft, cubic yard or cubic meter, according to the prevailing practice.  The payment for this item is generally done as Rs. per hundred cubic ft.  Filling in trenches after the construction of foundation masonry is ordinary neglected. If the trench filling is, also taken in account, it may be calculated by deducing the volume of masonry in trenches from that of the volume of excavation
  • 16. STEP 2: Excavation  To determine the amount of excavation, it is necessary to determine the following: 1. The size of building (building dimensions). 2. The distance the footing will project beyond the wall. 3. The amount of working space required between the edge of the footing and the beginning of excavation. 4. The elevation of the existing land, by checking the existing contour lines on the plot (site) plan. Continuous footing section
  • 17. STEP 2: Excavation 6. The type of soil that will be encountered. This is determined by first checking the soil borings (on the drawings), but must also be checked during the site investigation. 7. Whether the excavation will be sloped or shored. 8. The depth of the excavation. This is done by determining the bottom elevation of the cut to be made. Then take the existing elevation, deduct any topsoil removed, and subtract the bottom elevation of the cut to determine the depth of excavation.
  • 18. STEP 2: Excavation When calculating the amount of excavation to be done for a project, the estimator must be certain that the dimensions used are the measurements of the outside face of the footings and not those of the outside of the building. The footings usually project beyond the wall. Also, an extra 6 inches to 1 foot is added to all sides of the footing to allow the workers to install and remove forms. The estimator must also allow for the sloping of the banks to prevent a cave in. The amount of slope required must be determined by the estimator who considers the depth of excavation, type of soil, and possible water conditions.
  • 19. Excavation Plan Let Sa = S-1 + S-3 Sb = S-4 + S-5  L1 = H-1 + Sa + H-3 + Sb  L2 = S-2 – (Overlap) = S-2 – ½(Width) – ½(Width) = S-2 – Width  L3 = H-2 - (Overlap) = H-2 - ½(Width) – ½(Width) = H-2 – Width Using Center Line Method S-1 S-2 S-5 H-1 H-2 H-3 S-3 S-4 STEP 2: Excavation
  • 22. Let Sa = S-1 + S-3 Sb = S-4 + S-5 (As width of excavation is 2’-6”)  L1 = H-1 + Sa + H-3 + Sb  L2 = S-2 – ½(Width) – ½(Width) = S-2 – Width = S-2 – 2’-6”  L3 = H-2 - ½(Width) – ½(Width) = H-2 – Width = H-2 – 2’-6” S-2 H-1 H-2 H-3 Sa Sb STEP 2: Excavation
  • 23. S No Description N Measurement Quantity (cu. ft.) Total Quantity (cu. ft.) Remarks L’ B’ D’ 1 L1 1 87.70 2.5 3.5 767.38 767.38 2 L2 1 10.2 2.1 3.5 75 75 L=12.74-2.5 3 L3 1 20.61 2.5 3.5 180.34 180.34 L=23.11-2.5 Total Quantity 1022.7 STEP 2: Excavation
  • 24. Quantity = 1022.7 cu. ft. Wage rate = Rs. 650/ day Productivity rate = 0.0134 day / cu ft Labour Hours = Productivity Rate * Quantity Labour hours = 0.0134 day / cu ft *1023.88 = 13.65 days Labour cost = Labour hours * Wage rate per hour Labour cost = 13.65 days * Rs. 650/day Labour cost = Rs. 8873 STEP 2: Excavation
  • 25. P.C.C  The type of concrete must be clearly mentioned. The mix proportions and the type of cement, sand and coarse aggregate must be specified.  This item is measured in cubic ft and the unit for measurement is, generally Rs. per 100 cubic ft.  When the soil is soft or weak, one layer of dry bricks or stone soling is applied below the foundation concrete. The soling layer is computed in sq.ft (length x breadth), specifying the thickness in description of item.  In estimating quantities, the estimator makes no deductions for holes smaller than 2 sf or for the space that reinforcing bars or other miscellaneous accessories take up.  Waste ranges from 5 percent for footings, columns, and beams to 8 percent for slabs.
  • 26. Procedure for calculating concrete 1. Review the specifications to determine the requirements for each area in which concrete is used separately (such as footings, floor slabs, and walkways) and list the following: (a) Type of concrete (b) Strength of concrete (c) Color of concrete (d) Any special curing or testing 2. Review the drawings to be certain that all concrete items shown on the drawings are covered in the specifications. If not, a call will have to be made to the architect-engineer so that an addendum can be issued. 3. List each of the concrete items required on the project. 4. Determine the quantities required from the working drawings. Footing sizes are checked on the wall sections and foundation plans. Watch for different size footings under different walls.
  • 27. Let Sa = S-1 + S-3 Sb = S-4 + S-5  L1= H-1 + Sa + H-3 + Sb  L2 = S-2 – ½(Width) – ½(Width) = S-2 – Width  L3 = H-2 - ½(Width) – ½(Width) = H-2 – Width S-2 H-1 H-2 H-3 Sa Sb STEP 3: P.C.C (1:4:8)
  • 29. S No Description N Measurement Quantity (cu. ft.) Total Quantity (cu. ft.) Remarks L’ B’ D’ 1 L1 1 87.70 2.5 0.5 109.63 109.63 2 L2 1 10.24 2.125 0.5 10.88 10.88 L=12.74-2.5 3 L3 1 20.61 2.5 0.5 25.76 25.76 L=23.11-2.5 Total Quantity 146.27 STEP 3: P.C.C (1:4:8)
  • 30. Concrete in Foundations = 146.27 cu. ft. Add 5% for waste Concrete in Foundation = 146.27 + 5/100 * 146.27 = 153.58 cu. ft. Thumb Rules Dry material for 100 cu. ft. of cement concrete = 154 cu. ft. Volume of cement bag = 1.25 cu. ft. Materials Concrete = 153.58 cu. ft *1.54 = 236.51 cu. ft. Cement = 1/13 * 236.51 = 18.19/1.25 = 18.19 cu. ft. = 14.55 = 15 Bags Sand = 4/13*236.51 = 72.77 cu. ft. Aggregate = 8/13*236.51 = 145.54 cu. ft. STEP 3: P.C.C (1:4:8)
  • 31.  Care must be taken, while taking dimensions from the drawings in the bill of quantities because the walls in this part of the structure are in the form of steps with changing dimensions.  This item is calculated in cft and the unit for payment is Rs. per 100 cft.  In the description of work, the quality of bricks and mortar ratio must be specified. For example, "Brickwork in foundation and plinth using first class bricks laid in (1:4) or (1:6) cement-sand (c/s) mortar——— ————“ STEP 4: Brickwork up to Plinth Level with 1:6 (C/S)
  • 32.  Wastage for masonry = 5%  Wastage for mortar = 40% STEP 4: Brickwork up to Plinth Level with 1:6 (C/S)
  • 33. Let Sa = S-1 + S-3 Sb = S-4 + S-5  L1= H-1 + Sa + H-3 + Sb  L2 = S-2 – ½(Width) – ½(Width) = S-2 – Width  L3 = H-2 - ½(Width) – ½(Width) = H-2 – Width S-2 H-1 H-2 H-3 Sa Sb STEP 4: Brickwork up to Plinth Level with (1:6 C/S)
  • 35. Description N Measurement Quantity (cu. ft.) Total Quantity (cu. ft.) Remarks L’ B’ D’ L1 = H-1 + Sa + H-3 + Sb Step-1 1 87.70 1.5 0.5 65.78 65.78 Step-2 1 87.70 1.125 0.5 49.33 49.33 Step-3 up to plinth 1 87.70 0.75 3.37 221.66 221.66 D = 2+1.5 – 0.13 Total Quantity 336.77 STEP 4: Brickwork up to Plinth Level with 1:6 (C/S)
  • 36. Description N Measurement Quantity (cu. ft.) Total Quantity (cu. ft.) Remarks L’ B’ D’ L2 = S-2 – Width Step-1 1 11.24 1.125 0.5 6.32 6.32 L=12.74-1.5 Step-2 1 11.62 0.75 0.5 4.36 4.36 L=12.74-1.125 Step-3 up to plinth 1 11.99 0.38 3.37 15.35 15.35 L = 12.74 – 0.75 D = 2+1.5 –0.13 Total Quantity 26.03 STEP 4: Brickwork up to Plinth Level with 1:6 (C/S)
  • 37. Description N Measurement Quantity (cu. ft.) Total Quantity (cu. ft.) Remarks L’ B’ D’ L3 = H-2 - Width Step-1 1 21.61 1.5 0.5 16.20 16.20 L=23.11 –1.5 Step-2 1 21.985 1.125 0.5 12.36 12.36 L=23.11 –1.125 Step-3 up to plinth 1 22.36 0.75 3.37 56.51 56.51 L=23.11 -0.75 D=2+1.5 –0.13 Total Quantity 85.07 STEP 4: Brickwork up to Plinth Level with 1:6 (C/S)
  • 38. Total Quantity = 336.77 + 26.03 + 85.07 = 447.87 cu. ft.  Thumb Rules Bricks for 100 cu. ft. of brick work = 1350 Nos. Dry mortar for 100 cu. ft. of brick work = 30 cu. ft.  Material Bricks = 1350 / 100 * 447.87 = 6046 Bricks Add 5% for wastage Total bricks = 6046 + 5/100 * 6046 = 6349 Bricks Mortar = 30 / 100 * 447.87 = 134.361 Add 40% for wastage Total mortar = 134.361 + 134.361 * 40/100 = 188.10 STEP 4: Brickwork up to Plinth Level with 1:6 /(C/S)
  • 39. Cement = 1 / 7 * 188.10 = 26.87 / 1.25 = 21.5 = 26.87 = 22 Bags Sand = 6 / 7 * 188.10 = 161.22 cu. ft. STEP 4: Brickwork up to Plinth Level with 1:6 (C/S)
  • 40. STEP 5: Steps in Front of Verandah with 1:6 (C/S)
  • 41. Description N Measurement Quantity (cu. ft.) Total Quantity (cu. ft.) Remarks L’ B’ D’ Length of steps = 0.75 + 10 + 0.37 + 12 + 0.75 = 23.87’ Step-1 1 23.87 1 0.5 11.94 11.94 Step-2 1 23.87 2 0.5 23.87 23.87 Total Quantity 35.81 STEP 5: Steps in Front of Verandah with 1:6 (C/S)
  • 42.  Thumb Rules Bricks for 100 cu. ft. of brick work = 1350 Nos. Mortar for 100 cu. ft. of brick work = 30 cu. ft.  Materials Bricks = 1350 / 100 * 35.81 = 483.44 = 484 Bricks Add 5% for wastage Total Bricks = 484 * 1.05 = 509 Bricks Mortar = 30/100 * 35.81 = 10.74 cu. ft Add 40% for wastage Total Mortar = 10.74 * 1.40 = 15.04 cu. ft STEP 5: Steps in Front of Verandah with 1:6 (C/S)
  • 43. Total Mortar = 10.74 * 1.40 = 15.04 cu. ft Cement = 1 / 7 * 15.04 = 2.14 cu. ft = 2.14 / 1.25 = 1. 71 = 2 Bag Sand = 6 / 7 * 15.04 = 12.89 cu. ft STEP 5: Steps in Front of Verandah with 1:6 (C/S)
  • 44.  Horizontal D.P.C. shall extend the full width of the super structure walls, however, it shall not be provided across doorways and veranda openings. It is also provided in roof and floors.  Vertical D.P.C. is provided in external walls, especially, in the walls of basements.  The quantity of D.P.C. is estimated in square ft.(on area basis) and standard unit for payment is Rs. per 100 sft STEP 6: 1-1/2” DPC (1:2:4) & 02 coats of hot bitumen
  • 45. S-1 S-2 S-5 H-1 H-2 STEP 6: 1-1/2” DPC (1:2:4) & 02 coats of hot bitumen  (4.5” = 0.37’)  (9” =0.75’)  H-1= H-2= H-3=10’+12’+0.37’ +0.37’+0.37’ =23.11’  S-1= S-2= S-5=12’+0.37’+0.37’ = 12.74’
  • 46. TakingArea Description N Measurement Quantity (sq. ft.) Total Quantity (sq. ft.) Remarks L’ B’ D’ L1 1 71.70 0.75 - 53.78 53.78 L= H-1 + S-1 + H-2 + S-5 L2 1 12 0.37 - 4.44 4.44 L = 12.74 - 0.37 – 0.37 Columns 3 0.75 0.75 - 0.56 1.69 Total Quantity 59.91 STEP 6: 1-1/2” DPC (1:2:4) & 02 coats of hot bitumen
  • 47. Description N Measurement Quantity (sq. ft.) Total Quantity (sq. ft.) Remarks L’ B’ D’ Total Area - - - - 59.16 59.91 Deductions Doors 4 0.75 - 3.00 3.00 4 0.37 - 1.50 1.50 Total Quantity 55.41 STEP 6: 1-1/2” DPC (1:2:4) & 02 coats of hot bitumen
  • 48. Concrete Volume = 55.41 x 0.125 = 6.93 cu. ft. Add 5% for wastage Total concrete volume = 6.93 * 1.05 = 7.28 cu. ft  Thumb Rules Dry material for 100 cu. ft. of cement concrete = 154 cu. ft. Bitumen for 100 sq. ft. of DPC (first coat) = 15 Kg Bitumen for 100 sq. ft. of DPC (second coat) = 10 Kg  Materials Dry Concrete = 7.28 x 1.54 = 11.21 cu. ft. STEP 6: 1-1/2” DPC (1:2:4) & 02 coats of hot bitumen
  • 49. Cement = 1/7 x 11.21 = 1.60 /1.25 = 1.28 = 2 Bags Sand = 2/7 x 11.21 = 3.20 cu. ft. Coarse aggregate = 4/7 x 11.21 = 6.4 cu. ft. Bitumen = 25/100 x 55.41 = 13.85 Kg STEP 6: 1-1/2” DPC (1:2:4) & 02 coats of hot bitumen
  • 50. Important considerations are: 1. Measurements of walls shall be taken in the same order and in the same manner as for brickwork in foundations and plinth. 2. In the first measurements, all openings such as doors, windows, veranda openings etc. shall be neglected. However, deductions shall be made for all openings in the walls, at the end of the item. 3. In the description of the work, the quality of bricks and mortar ratio have to be specified. 4. Masonry for arches shall be paid separately, at a different rate. STEP 7: Brick work in super structure
  • 51. 5. The height of super structure is very important. Generally the quantities are worked out for each storey separately and rates would be different for different storeis because of additional labor work, scaffolding and shuttering. 6. The item is worked out in cft and the standard unit for payment is Rs. Per 100 cft. STEP 7: Brick work in super structure
  • 52. S-1 S-2 S-5 H-1 H-2 STEP 7: Brick work in super structure using first class bricks in (1:4) cement sandmortar  (4.5” = 0.37’)  (9” =0.75’)  H-1= H-2= H-3=10’+12’+0.37’ +0.37’+0.37’ =23.11’  S-1= S-2= S-5=12’+0.37’+0.37’ = 12.74’
  • 53.
  • 54. 4) 1-1/2’’ thick brick tiles joined and pointed in cement sand mortar (1:3) 3) 1’’ thick mud plaster 2) 4’’ thick earth filling 1) Roof insulation comprising of 2 coats of hot bitumen STEP 7: Brick work in super structure
  • 55. Description N Measurement Quantity (cu. ft.) Total Quantity (cu. ft.) Remarks L’ B’ D’ L1 1 71.70 0.75 12 645.3 645.3 L= H-1 + S-1 + H- 2 + S-5 L2 1 12 0.37 12 53.28 53.28 L = 12.74 - 0.37 – 0.37 Columns 3 0.75 0.75 10.5 5.9 17.71 716.29 STEP 7: Brick work in super structure
  • 56. H-2  H-1= H-2= H-3=10’+12’+0.37’ +0.37’+0.37’ =23.11’ Sa = Sb = 12’.74 + 8’ = 20.74’ Sa Sb STEP 7: Brick work in super structure parapet wall
  • 57. Description N Measurement Quantity (cu. ft.) Total Quantity (cu. ft.) Remarks L’ B’ D’ Total Volume 716.29 Parapet Wall 1 87.7 0.75 1.541 101.35 101.35 L= H-1 + Sa + H-2 + Sb Total Volume 817.64 STEP 7: Brick work in super structure
  • 58. Description N Measurement Quantity (cu. ft.) Total Quantity (cu. ft.) RemarksL’ B’ D’ Doors 1 4 0.75 7 21 21 1 4 0.37 7 10.5 10.5 Windows 3 4 0.75 4 12 36 Ventilators 4 2.5 0.75 1.5 2.81 11.25 Shelves 2 4 0.5 5 10 20 RCC Lintels Doors 1 5 0.75 0.5 1.87 1.87 1 5 0.37 0.5 0.93 0.93 Windows 3 5 0.75 0.5 1.87 5.62 Ventilators 4 3.5 0.75 0.5 1.31 5.25 Shelves 2 5 0.75 0.5 1.87 3.75 116.18 Net Total = (817.64-116.18) 701.46 STEP 7: Brick work in super structure (Deductions)
  • 59. Volume = 701.46 cu. ft.  Thumbs Rules Bricks for 100 cu. ft. of brick work = 1350 Nos. Dry mortar for 100 cu. ft. of brick work = 30 cu. ft.  Materials Bricks = 1350 / 100 * 701.46 = 9469.71 = 9470 Bricks Add 5% for wastage Bricks = 9470 * 1.05 = 9944 Bricks Mortar = 701.46 * 30/100 = 210.44 cu.ft Add 40% for wastage Total Mortar = 210.44 * 1.40 = 294.61 cu.ft STEP 7: Brick work in super structure using first class bricks in (1:4) cement sandmortar
  • 60. Cement = 1 / 5 * 294.61 = 58.92 = 58.92/ 1.25 = 47.13 = 48 Bags Sand = 4 / 5 * 294.61 = 235.69 cu. ft. STEP 7: Brick work in super structure using first class bricks in (1:4) cement sandmortar
  • 61.  For R.C.C. Roof slabs and beams, the total quantities of concrete and steel are estimated, separately.  The quantity of plain concrete is estimated in cft and the standard unit for payment of concrete is Rs. per 100 cft.  Volume of Reinforcing Steel is not deducted , while estimating the volume of plain concrete for payment.  R.C.C. lintels over wall openings such as doors and windows are also included in R.C.C. work. STEP 8: Reinforced Cement Concrete
  • 62. (4.5” = 0.37’) (9” = 0.75’)  L = 10’+12’+0.37’+0.75+0.75 = 23.87’  B = 12’+0.75+0.75+8 = 21.5’ L B STEP 8: Reinforced Cement Concrete (1:2:4)(Slab, Lintels & Beams)
  • 63.
  • 64.
  • 65. Description N Measurement Quantity (cu. ft.) Total Quantity (cu. ft.) Remarks L’ B’ D’ Roof Slab 23.87 21.5 0.33 169.43 169.43 Verandah Long Beam 1 23.87 0.75 1.5 26.86 26.86 Verandah Short Beam 2 7.25 0.75 1.5 8.156 16.31 Total Quantity 212.60 STEP 8: Reinforced Cement Concrete (1:2:4)(Slab, Lintels & Beams)
  • 66. Description N Measurement Quantity (cu. ft.) Total Quantity (cu. ft.) Remarks L’ B’ D’ Volume 212.60 Lintels Doors 1 5 0.75 0.5 1.87 1.87 1 5 0.37 0.5 0.93 0.93 Windows 3 5 0.75 0.5 1.87 5.62 Ventilators 4 3.5 0.75 0.5 1.31 5.25 Shelves 2 5 0.75 0.5 1.87 3.75 Shades 2 5 1.5 0.25 1.87 3.75 Total Quantity 233.77 STEP 8: Reinforced Cement Concrete (1:2:4)(Slab, Lintels & Beams)
  • 67. STEP 8: Reinforcement Steel / General Steel Work  Steel is provided separately from R.C.C. per ton, per Kg, or per cwt (standard weight also called Quintal or century weight equal to 112 Ibs = 50Kg).  Quantity of steel can either be worked out by rules of thumb practice or by intensive calculations taking the length and diameter of steel bars from the working drawings showing reinforcement details and bar-bending schedules. In taking length of bars, due margin of hooks, bends and overlapping is given.  As a Rule Of Thumb Practice, for ordinary beams and slabs for residences, assume 6.75 Ibs of steel per cft of R.C.C. work. However, for R.C.C. columns, it varies from 8 to 10 Ibs per cft. normally, we use 2% of steel in columns.  Percentage of steel means, area of steel divided by total area of the column multiplied by 100 and 1% of steel in columns corresponds to a quantity of 4.5 Ibs/cft.  Wastage for slab is 8% while wastage for other member 10% (including laps)
  • 68. Description N Measurement Quantity (lbs) Total Quantity (lbs) Remarks 6.75 Ibs. of steel per cu. ft. of R.C.C. work Steel 6.75 64.34 434.30 434.30 233.77-169.43 =64.34 Total Weight 434.30 STEP 8: Mild Steel Round Bars as in Reinforcement
  • 69.  Thumbs Rules Dry material for 100 cu. ft. of cement concrete = 154 cu. ft. 6.75 Ibs. of steel per cu. ft. of R.C.C. work  Materials Concrete for slab = 169.43 cu. ft Add 8% for wastage in slab Total Concrete for slab = 160.43 * 1.08 = 183 cu. ft Concrete for other R.C.C members = 233.77 – 169.43 = 64.34 cu.ft Add 5% for wastage Total Concrete for other R.C.C members = 64.34 * 1.05 = 67.55 cu.ft STEP 8: Reinforced Cement Concrete (1:2:4)(Slab, Lintels & Beams)
  • 70. Total Concrete for R.C.C members = 183 + 67.55 = 250.55 cu.ft Dry Concrete = 250.55 x 1.54 = 385.85 cu. ft. Cement = 1/7 x 385.85 = 55.07/1.25 = 44.06 = 45 Bags Sand = 2/7 x 385.85 = 110.24 cu. ft. Coarse aggregate= 4/7 x 385.85 = 220.28 cu.ft Mild steel round bars= 434.30 lbs Add 10% for wastage Total mild steel = 434.30 * 1.1 = 477.72 lbs Slab steel = 2682.41 lbs (From Lecture 10) Total steel = 2682.41 + 477.72 = 3160.13 lbs STEP 8: Reinforced Cement Concrete (1:2:4)(Slab, Lintels & Beams) Steel = 3160.13/ 2000 Steel = 1.58 tons
  • 71.  Roof consisting of beams, battens, and tiles or wooden planks is estimated for each part, separately  Steel beam is estimated by weight, whereas, wooden beam is measured in cft. Battens are estimated by numbers indicating there size and lengths. Tiles are also estimated by size and numbers.  Roof finishing may consist of bitumen coating and/or Polythene sheets (water proofing) , earth filling (heat proofing) and brick tiles, etc.  Dimensions are taken from inner face to inner face of parapet walls.  This item is estimated in sft and a composite rate for payment is taken as Rs. per 100 sft of the roof area. Roofing
  • 72.  L = 10’+12’+0.37’ = 22.37’  B = 12’+0.75+8-0.75 = 20’ Description N Measurement Quantity (sq. ft.) Total Quantity (sq. ft.) Remarks Taking Area Area 22.37 20 447.4 447.4 Total Area 447.4 STEP 9: Roof Insulation (02 coats of hot bitumen, 4” thick earth filling, 1” thick mud plaster and 1-1/2” thick brick tiles jointed and pointed in cement sand mortar (1:3))
  • 73.  Thumbs Rules 100 sq. ft. surface area using bricks on bed= 360 Nos. Dry mortar for 100 sft = 9.00 cft Bitumen for 100 sq. ft. (first coat) = 15 Kg Bitumen for 100 sq. ft. (second coat) = 10 Kg  Materials Brick Tiles = 360/100 x 447.4 = 1610.6 = 1611 No. Add 5% for wastage Total brick tiles = 1161 * 1.05 = 1220 No. Mortar = 447.4 * 9 / 100 = 40.27 cu.ft Add 40% for wastage Total mortar = 40.27 * 1.4 = 56.38 cu.ft STEP 9: Roof Insulation (02 coats of hot bitumen, 4” thick earth filling, 1” thick mud plaster and 1-1/2” thick brick tiles jointed and pointed in cement sand mortar (1:3))
  • 74. Cement = 1/4 x 56.38 = 14.09 / 1.25 = 11.25 = 12 Bags Sand = 3/4 x 56.38 = 42.27 cu. ft. Mud/ Earth Filling = 447.4 x 0.42 = 188 cu. ft. Bitumen= 25/100 x 447.4 = 111.9 kg Polythene Sheet = 447.4 sq. ft. STEP 9: Roof Insulation (02 coats of hot bitumen, 4” thick earth filling, 1” thick mud plaster and 1-1/2” thick brick tiles jointed and pointed in cement sand mortar (1:3))
  • 75.  Cement concrete floors, mosaic floors, and brick floors are most commonly used.  Payments are made separately for different layers, like, topping, lean concrete, sand filling, earth filling, etc.  Earth filling, sand filling and lean concrete are paid by volume, whereas, topping is paid on area basis, mentioning thickness in the description.  Standard unit for payment of topping is, usually, Rs. per 100 sft.  The skirting is estimated in running ft. Flooring
  • 76. G.L
  • 77. Verandah Length = 10’+12’+0.37’ = 22.37’ B = 8’ – 0.75’ = 7.25’ L B STEP 10: Flooring (sand under floor) (4.5” = 0.37’) (9” = 0.75’)
  • 78. Description N Measurement Quantity (cu. ft.) Total Quantity (cu. ft.) Remarks L’ B’ D’ Room 1 1 12 10 0.5 60 60 Room 2 1 12 12 0.5 72 72 Verandah 1 22.37 7.25 0.5 81.11 81.11 Total Quantity 213.11 STEP 10: Flooring (sand under floor)
  • 79.  4” thick P.C.C = 0.33’ L B (4.5” = 0.37’) (9” = 0.75’) STEP 10: Flooring (Cement concrete (1:4:8) as under layer of floors)
  • 80. Description N Measurement Quantity (cu. ft.) Total Quantity (cu. ft.) Remarks L’ B’ D’ Room 1 1 12 10 0.33 40 40 Room 2 1 12 12 0.33 48 48 Verandah 1 22.37 7.25 0.33 54.07 54.07 Total Quantity 142.07 STEP 10: Flooring (Cement concrete (1:4:8) as under layer of floors)
  • 81. Concrete = 142.07 cu. ft. Add 5% for wastage Total concrete =142.07 * 1.05 = 149.17 cu.ft  Thumbs Rules Dry material for 100 cu. ft. of cement concrete = 154 cu. ft.  Materials Dry Concrete = 149.17 x 1.54 = 229.73 cu. ft. Cement = 1/13 x 229.73 = 17.67/1.25 = 14.13 = 15 Bags Sand = 4/13 x 229.73 = 70.69 cu. ft. Coarse aggregate = 8/13 x 229.73 = 141.37 cu. ft. STEP 10: Flooring (Cement concrete (1:4:8) as under layer of floors)
  • 82. TakingArea Description N Measurement Quantity (sq. ft.) Total Quantity (sq. ft.) RemarksL’ B’ D’ Room 1 1 12 10 - 120 120 Room 2 1 12 12 - 144 144 Verandah 1 23.87 8 - 191 191 L = 12+ 10 +0.37+0.75+0.75 Door Sill 1 1 4 0.75 - 3 3 Door Sill 2 1 4 0.37 - 1.5 1.5 Deductions Columns 3 0.75 0.75 - 0.56 1.68 Total Quantity 457.80 STEP 10: Flooring (1-1/2” P.C.C (1:2:4) as top layer of floor, finished smooth)
  • 83. Concrete Volume = 457.8 x 0.125 = 57.23 cu. ft. Add 5% for wastage Total concrete = 57.23 * 1.05 = 60.09 cu.ft  Thumbs Rules Dry material for 100 cu. ft. of cement concrete = 154 cu. ft.  Materials Dry Concrete = 60.09 x 1.54 = 92.54 cu. ft. Cement = 1/7 x 92.54 = 13.22/1.25 = 10.576 = 11 Bags Sand = 2/7 x 92.54 = 26.44 cu. ft. Coarse aggregate = 4/7 x 92.54 = 52.88 cu. ft. STEP 10: Flooring (1-1/2” P.C.C (1:2:4) as top layer of floor, finished smooth)
  • 84.  Materials Total Cement bags = 15 + 11 = 26 Bags Total Sand = 213.11 + 70.69 + 26.44 = 310.24 cu. ft. Total Coarse aggregate = 141.13 + 52.88 = 194.01 cu. ft. STEP 10: Flooring (Cement concrete (1:4:8) as under layer of floors)
  • 85.  The type of plaster, proportioning of materials and minimum thickness of plaster have to be specified.  The quantity is calculated for total wall surface without deduction for openings such as doors windows, ventilators, etc. However, if the wall is being plastered on both the faces, the deductions for opening areas are made from one side only.  Standard unit for payment is Rs. per 100 sft.  Height is also specified for plastering because, for greater heights, labor cost increases. The rate varies according to the number of the storey Plastering
  • 86. STEP 11: ½” thick (1:3) C/S plaster to walls finished smooth (4.5” = 0.37’) (9” = 0.75’)  Inner Height = 12’  Outer Height =
  • 87. TakingArea Description N Measurement Quantity (sq. ft.) Total Quantity (sq. ft.) Remarks L’ B’ D’ INNER SIDE Room 1 (Long Wall) 2 12 - 12 144 288 Room 1 (Short Wall) 2 10 - 12 120 240 Room 1 (Ceiling) 1 10 12 - 120 120 Room 2 (Long Wall) 2 12 - 12 144 288 Room 2 (Short Wall) 2 12 - 12 144 288 STEP 11: ½” thick (1:3) C/S plaster to walls finished smooth
  • 88. Description N Measurement Quantity (sq. ft.) Total Quantity (sq. ft.) Remarks L’ B’ D’ INNER SIDE Room 2 (Ceiling) 1 12 12 - 144 288 Verandah Wall 1 23.87 - 12 286.56 286.56 Verandah Ceiling 1 22.37 7.25 - 162.18 162.18 Columns 3 3 - 10.5 31.5 94.5 L= 0.75 + 0.75 + 0.75 + 0.75 Long Beam (Internal) 1 22.37 - 1.5 33.55 33.55 STEP 11: ½” thick (1:3) C/S plaster to walls finished smooth
  • 89. Description N Measurement Quantity (sq. ft.) Total Quantity (sq. ft.) RemarksL’ B’ D’ INNER SIDE Long Beam (Soffit) 1 21.62 - 0.75 8.10 8.10 L= 23.87 – 0.75 - 0.75 -0.75 Short Beam (Internal) 2 7.25 - 1.5 10.875 10.875 Short Beam (Soffit) 2 7.25 - 0.75 5.43 10.87 OUTER SIDE Rear Wall 1 23.87 - 15.33 365.92 365.92 L =1.5+12+0.33+1.5 STEP 11: ½” thick (1:3) C/S plaster to walls finished smooth
  • 90. Description N Measurement Quantity (sq. ft.) Total Quantity (sq. ft.) Remarks L’ B’ D’ Left & Right Side 2 13.5 - 15.33 206.95 413.91 Front Side (above verandah) 1 23.87 - 3.33 79.4 79.4 L = 1.5 + 1.5 + 0.33 Left & Right Side (above verandah) 2 8 - 3.33 26.64 53.28 L = 1.5+0.125 +12+0.33+1.5 Verandah sides (lower area) 2 8 - 1.5 12 24 Parapet Wall Inner side 1 84.74 - 1 84.74 84.74 L = 22.37 + 22.37 + 20 + 20 Top side 1 87.7 - 0.75 65.77 65.77 Center to center Outer side Already calculated above STEP 11: ½” thick (1:3) C/S plaster to walls finished smooth
  • 91. Description N Measurement Quantity (sq. ft.) Total Quantity (sq. ft.) Remarks L’ B’ D’ Verandah Steps Tread 2 23.87 - 1 23.87 47.74 Riser 3 23.87 - 0.5 11.93 35.80 Sides 2 2 - 0.5 1.00 2.00 2 1 - 0.5 0.5 1.00 Misc Door Jambs 2 7 0.75 - 5.25 10.50 2 7 0.37 - 2.63 5.25 1 4 0.75 - 3.0 1.50 1 4 0.37 - 1.50 3.00 STEP 11: ½” thick (1:3) C/S plaster to walls finished smooth
  • 92. Description N Measurement Quantity (sq. ft.) Total Quantity (sq. ft.) Remarks L’ B’ D’ Window Jambs 6 0.75 - 4 3.00 18.00 6 0.75 4 - 3.00 18.00 Ventilator Jambs 8 0.75 2.5 - 1.88 15.00 8 0.75 - 1.5 1.19 9.00 Shelves 4 0.5 - 5 2.5 10.00 Total Area = 3211.42 DEDUCTION Doors 2 4 - 7 28.00 56.00 Windows 3 4 - 4 16.00 48.00 Ventilators 4 2.5 - 1.5 3.75 15.00 STEP 11: ½” thick (1:3) C/S plaster to walls finished smooth Net Area = 3211.42 – 119 = 3281.2
  • 93.  Thumbs Rules Dry mortar for 100 sq. ft. of ½” thick cement plaster = 6 cu. ft. or 100 cu. ft. wet mortar = 128 cu. ft. dry mortar  Materials Volume = 3294.7 x (0.5/12) = 137.28 cu. ft. Add 40% for wastage Total volume = 137.28 * 1.4 = 192.19 cu. ft. Dry volume = 192.19 * 1.28 = 246 cu. ft Cement = 1 /4 * 246 = 61.5 Sand = 61.5/ 1.25 = 3 / 4 * 246 = 49.2 = 50 Bags = 184.5 cu. ft. STEP 11: ½” thick (1:3) C/S plaster to walls finished smooth
  • 94.  The type of material used and the quantity of finish required should be clearly indicated in the description of the item.  The rate for any type of woodwork includes cutting of timber to required sizes, joinery work, fittings and fastenings, three coats of oil paints or varnish, bolts, locks, handles, etc.  The measurements are taken for the overall area of doors, windows, etc. If volume of timber required for these items is to be find out, the computed area is multiplied with the nominal thickness and an allowance of 25% is made for wastage of timber.  Rectangular wooden beams, vertical columns, trusses, etc., are measured in cft.  Wooden stairs are measured in number of steps and description of the item includes the riser, tread, and width of the steps.  Wooden shelves are measured in running ft (RFT). Wood work / Carpentry
  • 95. Description N Measurement Quantity (sq. ft.) Total Quantity (sq. ft.) Remarks L’ B’ D’ 1 ½” Thick Wooden Doors with Chowkat 2 4 - 7 28 56 Windows and Ventilators 3 4 - 4 16 48 4 2.5 - 1.5 3.75 15 Three Coats of Painting to Doors 2 - - - 56 112 Already calculated STEP 12: Door, Windows & Ventilators Frames
  • 96.  Thumbs Rules Timber for 100 sq. ft. of Panelled Doors = 13 cu. ft. Timber for 100 sq. ft. of Glazed windows and Ventilators = 8 cu. ft.  Materials Timber for doors = 13 / 100 x 56 = 7.28 cu. ft. Timber for windows and Ventilators = 8 / 100 x 63 = 5.04 cu. ft. Total = 13.32 cu. ft. Add 25% for wastage Total wood required = 13.32 * 1.25 = 16.65 cu. ft STEP 12: Door, Windows & Ventilators Frames
  • 97. Description N Measurement Quantity (sq. ft.) Total Quantity (sq. ft.) Remarks L’ B’ D’ Room No.1 (Long wall) 2 12 - 12 144 288 Room No.1 (Short wall) 2 10 - 12 120 240 Room No.1 (Ceiling) 1 10 12 - 120 120 Room No.2 (Long wall) 2 12 - 12 144 288 Room No.2 (Short wall) 2 12 - 12 144 288 Room No.2 (Ceiling) 1 12 12 - 144 144 Verandah wall 1 23.875 - 12 286.5 286.5 Verandah Ceiling 1 22.375 - 7.25 162.26 162.26 STEP 13: Three coats of distempering/ white washing to walls (Internal Side)
  • 98. Description N Measurement Quantity (sq. ft.) Total Quantity (sq. ft.) Remarks L’ B’ D’ Columns 3 3 - 10.5 25.50 76.50 Long beam (inner side) 1 22.375 - 1.5 33.55 33.55 Long beam (soffit) 1 21.62 - 0.75 16.21 16.21 Short beam (sides) 2 7.25 - 1.5 10.87 21.74 Short beam (soffit) 2 7.25 - 0.75 5.43 10.87 Door Jambs 2 0.75 - 7 5.25 10.50 2 0.375 - 7 2.63 5.25 1 0.75 - 4 3 1.50 1 0.375 - 4 1.50 3.00 STEP 13: Three coats of distempering/ white washing to walls (Internal Side)
  • 99. Description N Measurement Quantity (sq. ft.) Total Quantity (sq. ft.) Remarks L’ B’ D’ Window Jambs 6 0.75 - 4 3 18 6 0.75 - 4 3 18 Ventilator Jambs 8 0.75 - 2.5 1.88 15 8 0.75 - 1.5 1.19 9 Shelves 4 0.5 - 5 2.5 10 4 0.5 - 4 2.0 10 DEDUCTION Doors 4 4 - 7 28 112 Windows 4 4 - 4 16 64 Ventilators 6 2.5 - 1.5 3 22.50 Net Total Area 1877.38 STEP 13: Three coats of distempering/ white washing to walls (Internal Side)
  • 100.  Thumbs Rules Lime for 100 sq. ft. of white wash (one coat) = 1.00 Kg  Materials Lime for three coats=1/100 x 3 x 1877.3 = 56.3 Kg STEP 13: Three coats of distempering/ white washing to walls (Internal Side)
  • 101. Description N Measurement Quantity (sq. ft.) Total Quantity (sq. ft.) Remarks L’ B’ D’ Rear wall 1 23.875 - 15.375 367.07 367.07 Left & Right side wall 2 13.5 - 15.375 207.5 415.13 Front side (above verandah roof) 1 23.875 - 3.33 79.50 79.50 Sides (above verandah roof) 2 8 - 3.33 26.64 53.28 Left & Right side wall of verandah 2 8 - 1.5 12 24 STEP 14: Three coats of Weather shield paint to walls. (External side)
  • 102. Description N Measurement Quantity (sq. ft.) Total Quantity (sq. ft.) Remarks L’ B’ D’ PARAPET WALL Top of parapet wall 1 87.7 - 0.75 65.775 65.775 Parapet wall (inside) 2 20 - 1 20 40 2 22.37 - 1 22.37 44.74 DEDUCTION Windows 2 4 - 4 16.00 32.00 Ventilators 2 2.5 - 1.5 3.75 7.50 Net Total 1049.99 STEP 14: Three coats of Weather shield paint to walls. (External side)
  • 103. Market Rates Sr. No Item Rate (Rupees) 1 Cement 550 / bag 2 Sand 2000 / 100 cu.ft 3 Aggregate 4500 / 100 cu.ft 4 Bricks 10 / each 5 Steel 92,000 / ton 6 Bitumen 105 / kg 7 Weather Shield 30 / sft 8 Distemper 15 / sft 9 Brick Tile 12 / each 10 Framic tile or face tile 18 / each
  • 104. Market Rates Sr. No Item Rate (Rupees) 11 Wood (Deodar) 4500 / cft 12 Lime 10 / kg 13 Earth Filling 3 / cft 14 Polythene sheet 2 / sft
  • 105. Cost Summary Sr. No Description Item Unit Quantity Unit Rate (Rs.) Amount (Rs.) 1 Top soil (3’’ depth) 3600 2 Excavate foundation trenches (3’6’’ depth) 8873 3 Foundation concrete (1:4:8) Cement Sand Aggregate Bags Cu.ft Cu.ft 15 73 146 550 20 45 8250 1460 6570 4 Foundation walls (1:6 C/S) Bricks Cement Sand No. Bags Cu.ft 6349 22 162 10 550 20 63490 12100 3240 5 Brick steps in front of verandah (1:6 C/S) Bricks Cement Sand No. Bags Cu.ft 484 2 13 10 550 20 4840 1100 260
  • 106. Sr. No Description Item Unit Quantity Unit Rate (Rs.) Amount (Rs.) 6 1/2’’ D.P.C (1:2:4) & 2 coats of bitumen Cement Sand Aggregate Bitumen Bags Cu.ft Cu.ft kg 2 3 6 14 550 20 45 105 1100 60 270 1470 7 Brick work in superstructure (1:4 C/S) Bricks Cement Sand No. Bags Cu.ft 9944 48 236 10 550 20 99440 26400 4720 8 R.C.C slab, beams, lintels (1:2:4) Cement Sand Aggregate Steel Bags Cu.ft Cu.ft Tons 45 110 220 1.58 550 20 45 92000 24750 2200 9900 145360 9 Roof insulation 1-1/2’’ tiles 1:3 C/S Earth filling 5’’ 2 coats of hot bitumen Polythene sheet Brick tiles Cement Sand Mud Bitumen Sheet No. Bags Cu.ft Cu.ft Kg sft 1220 12 42 188 112 447 12 550 20 3 105 2 14640 6600 840 564 11760 894
  • 107. Sr. No Description Item Unit Quantity Unit Rate (Rs.) Amount (Rs.) 10 Flooring Sand cushion 6’’ 4’’ P.C.C (1:4:8) 1-1/2’’ P.C.C (1:2:4) Cement Sand Aggregate Bags Cu.ft Cu.ft 26 bags 310 cu.ft 194 cu.ft 550 20 45 14300 6200 8730 11 Plastering 1-1/2’’ thick (1:3) C/S Cement Sand Bags Cu.ft 50 bags 185 cu.ft 550 20 27500 3700 12 Wood work Door, windows, ventilators & frames Wood Cu.ft 17 cu.ft 4500 76,500 13 3 coat distempering/ white wash Lime Distemper kg sft 56 kg 1877 sft 10 15 560 56310 14 3 coat of weather shield paint Weather shield sft 1050 sft 30 31500 Total Cost 690,051
  • 108. Cost per square foot  Total cost = Rs. 690,051  Plot covered area = 23.87’ x 21.5’ = 513.205 sft  Cost per sft = Total cost / Covered Area  Cost per sft = 690,051 / 513.205 = Rs. 1345 / sf t
  • 109. Instructions for Term Project  For slab assume suitable bars and calculate steel using new method.  Perform quantity take by assuming slab as a single RCC member of 6’’- 8’’ depth instead of using roof layers.  Add wastage for each item of work.  Use market rates provided above for calculating material cost.  Develop a BoQ/Cost summary.  Divide total cost with your buildings covered area to calculate cost per square foot.