SlideShare a Scribd company logo
1 of 6
Download to read offline
SCHOOL OF ARCHITECTURE, BUILDING AND DESIGN
BACHELOR IN QUANTITY SURVEYING (HONOURS)
AUGUST 2018
QSB 4223 DEVELOPMENT ECONOMICS ASSIGNMENT
ASSIGNMENT BRIEF
A property Developer intends to develop a piece of freehold land measuring 10 acres 1 rood
10 pole in Rawang, Selangor. The land was purchased three years ago at RM15.00 per sq. ft.
with a RM6,500,000.00 bank loan. During this period, the Developer had applied for land
conversion, subdivision, planning and building plans approval.
The proposed development shall be of mixed residential and commercial units comprising of
26’ x 80’ double storey shop/office lots, 22’ x 75’ double storey Terrace houses and 20’ x 60’
double storey Low Cost houses. Thirty percent (30%) of the development must be of low cost
houses. The Developer intends to have fifteen percent (15%) of the total units to be double
storey shop/office.
Development Order has now been granted and construction is ready to proceed. Construction
shall take two years to complete. As the cost consultant engaged for the proposed project,
prepare the following based on the project information available as attached.
Group Assignment
1) An analysis of the number of units for each type of houses that can be built for the
proposed development project.
2) A financial appraisal of the project using the Residue Method of Valuation.
3) A Cash Flow for the project based on ‘Sell-then-Build’ concept comprising of:
i) Monthly Cash Inflow taking into consideration the required sales projection:
* Note: Tabulation should indicate monthly total, net monthly cumulative total
and also quarterly inflow. Table should be in A4 size.
ii) Monthly Cash Outflow taking into consideration the contractual requirements;
* Note: Tabulation should indicate monthly total, net monthly cumulative total
and also quarterly inflow. Table should be in A4 size. This table will only reflect
construction costs. Administration expenses should be reflected in the quarter-
yearly cash flow as below.
iii) Quarter-Yearly Cash Flow based on the above Cash Inflow and Cash Outflow
and to include Project financing if required. For Project financing, to assume
that a one lump sum repayment for the land to be made upon completion of
construction. (For the purpose of this assignment, it is assumed no repayment is
made for construction cost).
4) With a twelve percent (12%) cost of capital, tabulate and calculate the NPV of the
project on a quarter-yearly basis. Give an overall analysis and comment on the
viability of the project.
5) Comment on the cash flow and viability of the project if it is based on a ‘Build-then-
Sell’ concept. (Assume 100% sales on completion of construction).
Instructions to students:
i) The assignment should be properly typed in A4/A3 sized paper with 12 point font size
and one-and-a-half spacing. Only one side of each sheet should be used. The margin at
the binding edge shall 40mm and other margins 25mm. The assignment must use
comb-binder and bound with the assessment form in front.
ii) All sources of information used should be acknowledged and referenced using an
appropriate referencing method.
iii) State the assignment topic, course and year, submission date and the names of all group
members and their respective ID on the front page of the assignment.
iv) You are to prepare minutes of meeting (in a format of your choice) to record what
transpired during your group discussion, attendees of the meeting, action to be taken by
respective individuals, progress of individual members & group as a whole and
deadlines set to achieve tasks in order to meet the assignment submission deadline. The
minutes of meetings are to be submitted as part of the assignment. ( 5 marks)
v) In order to also assess each student’s individual effort, please state your name for the
section/s of work/s that was prepared by you for the assignment.
vi) Please note that at the end of the assignment, a copy of peer evaluation form will be
given to all students for valuation of their team members’ contribution and efforts in the
project assignment.
vii) Submission date is on the 21st
November 2018.
-END-
PROJECT TITLE
PROPOSED DEVELOPMENT OF 26' X 80' D/S SHOP/OFFICE LOTS, 22’ X 75’ D/S TERRACE
HOUSES AND 20’ X 60’ D/S LOW COST HOUSES IN PUCHONG, SELANGOR.
PROJECT INFORMATION
Land Purchased @ RM15.00/fs : January 2010
Commencement of construction : January 2013
Scheduled Completion : End December 2014
Planning Constraints / Restrictions
 Effective development area : 60% of Land area
 Restrictions:
- Shop/Office Lots : maximum 10 units / block
- Terrace Houses : maximum 12 units / block
- Low Cost Houses : maximum 15 units / block
 Low Cost quota : 30%
 Bumiputra reservation : 30%
 Bumiputra discount : 7%
Development Composition:
Type Build-up Area Selling Price Construction Cost
Double Storey Shop/Office :
1. D/S Shop/Office 3,600 fs RM850,000.00 RM70.00 per fs
2. Corner unit 6,500 fs RM1,600,000.00 RM80.00 per fs
3. End unit 3,600 fs RM1,000,000.00 RM80.00 per fs
Double Storey Terrace :
4. D/S Terrace 1,500 fs RM400,000.00 RM75.00 per fs
5. Corner unit 1,500 fs RM650,000.00 RM85.00 per fs
6. End unit 1,500 fs RM500,000.00 RM85.00 per fs
Double-Storey Low Cost :
7. D/S Low Cost 900 fs RM45,000.00 RM35.00 per fs
8. Corner/End units 900 fs RM45,000.00 RM40.00 per fs
Development/Construction Costs
i. Land cost purchased at : RM15.00 per fs in January 2010
ii. Professional Fees : 9% of construction costs.
iii. Administrative Fees : 2% of GDV
iv. Plan Fees : RM2,000.00 per unit.
v. Contributions & Fees : 2% of construction costs
vi. Advertisement & Marketing : 1% of GDV
vii. Conversion premium -commercial : 20% of land value of commercial lots
-residential : 15% of land value of residential lots
viii. Subdivision : RM1,500.00 per unit
ix. Legal Fees : RM2,500.00 per unit
x. Contingencies : 5% of construction costs
xi. Earth Works : 5% of building costs
xii. Infrastructure costs : 10% of building costs
Assume:
 Item (ii) is payable 60% on commencement of construction and balance payable in two equal
yearly payments;
 Items (iv), (v), (vii) (viii) & (ix) are payable on commencement of construction;
 Items (iii), (vi) & (x) are payable equally throughout construction period.
Financing Costs
 Cost of Finance : 5.5% p.a.+ BLR
 Interest on Loan for Purchase of Land : 2.5% p.a. + BLR
(BLR assumed @ 6.5%)
Contractual Requirements
 Payment to contractor : 30 days Stage payment with 10% retention, limit 5%
On completion of : Foundation : 10%
RC Framework : 25%
Walls, Doors & Wdw Frame : 15%
Roofing, Elec Wiring & Plumbing : 15%
Internal & External Plastering : 15%
Sewerage Works : 5%
Drainage Works : 5%
Road Works : 10%
 Final Certificate : 18 months from completion of construction.
Sales Information
 Sales Launch : January 2013
 Sales Projection Shop/Office Terrace Low Cost
- on launching : 10% 30%
- end 2nd
Q. 2013 : 20% 50%
- end 3rd
Q. 2013 : 30% 70% 50%
- end 4th
Q. 2013 : 40% 80%
- end 1st
Q. 2014 : 50% 100% 100%
- end 2nd
Q. 2014 : 70%
- end 3rd
Q. 2014 : 100%
- end 4th
Q. 2014 :
 Collection from Purchasers : Stage Payment Third Schedule of SALE AND
PURCHASE AGREEMENT (LAND AND BUILDING)
Schedule G of HOUSING DEVELOPMENT (CONTROL
AND LICENSING) ACT 1966
Assume 100% collection 30 days after payment is due.
(ignore differences of billing period, notice period and
grace period)
Assume applicable for both commercial and residential
properties.
 Vacant Possession : Assume immediately upon completion of construction
PROPOSED DEVELOPMENT OF 26' X 80' D/S SHOP/OFFICE LOTS, 22’ X 75’ D/S TERRACE HOUSES AND 20’ X 60’ D/S LOW COST HOUSES IN PUCHONG,
SELANGOR.
Date of Commencement :
Date of Completion :
2013 2014
ITEM DESCRIPTION OF WORKS Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
1 EARTHWORKS
2 FOUNDATION
3 R.C. FRAMEWORK
4 WALLS, DOORS & WINDOW FRAME
5 ROOFING, ELEC WIRING & PLUMBING
6 INTERNAL & EXTERNAL PLASTERING
7 SEWERAGE WORKS
8 DRAINAGE WORKS
9 ROADWORKS
10 INFRASTRUCTURE WORKS
01 January 2013
31 December 2014CONSTRUCTION WORK PROGRAMME

More Related Content

What's hot

Piawai_Rekabentuk_Pencawang.pdf
Piawai_Rekabentuk_Pencawang.pdfPiawai_Rekabentuk_Pencawang.pdf
Piawai_Rekabentuk_Pencawang.pdfkhairulsalleh10
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2ahmong4
 
HOW CONSERVATION WORKS TAKE PLACE IN MALAYSIA
HOW CONSERVATION WORKS TAKE PLACE IN MALAYSIAHOW CONSERVATION WORKS TAKE PLACE IN MALAYSIA
HOW CONSERVATION WORKS TAKE PLACE IN MALAYSIAFakhrul Afifi
 
M3 Lecture 11 provisional sum prime cost sum
M3 Lecture 11 provisional sum  prime cost sumM3 Lecture 11 provisional sum  prime cost sum
M3 Lecture 11 provisional sum prime cost sumEst
 
Construction technology assignment 1
Construction technology assignment 1Construction technology assignment 1
Construction technology assignment 1Doreen Yeo
 
PP1 assignment
PP1 assignment PP1 assignment
PP1 assignment Enoch Wong
 
Measurement 4 Tender Document
Measurement 4 Tender Document Measurement 4 Tender Document
Measurement 4 Tender Document xingxin_GOh
 
Traditional procurement method
Traditional procurement methodTraditional procurement method
Traditional procurement methodhiewliming
 
Payments in the construction industry
Payments in the construction industryPayments in the construction industry
Payments in the construction industryKheng Hoe Advocates
 
Project Management (Group)
Project Management (Group)Project Management (Group)
Project Management (Group)FabienFoo
 
Determination of building_contracts
Determination of building_contractsDetermination of building_contracts
Determination of building_contractsHafizul Mukhlis
 
Form G1 G21(Bm)
Form G1 G21(Bm)Form G1 G21(Bm)
Form G1 G21(Bm)hadypower
 
Project management (1)
Project management (1)Project management (1)
Project management (1)aarenneoone
 
Guide for Construction Contract Administrators
Guide for Construction Contract AdministratorsGuide for Construction Contract Administrators
Guide for Construction Contract AdministratorsSarah Fox
 

What's hot (20)

Piawai_Rekabentuk_Pencawang.pdf
Piawai_Rekabentuk_Pencawang.pdfPiawai_Rekabentuk_Pencawang.pdf
Piawai_Rekabentuk_Pencawang.pdf
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 
BS course bldg diagnostic
BS course bldg diagnosticBS course bldg diagnostic
BS course bldg diagnostic
 
HOW CONSERVATION WORKS TAKE PLACE IN MALAYSIA
HOW CONSERVATION WORKS TAKE PLACE IN MALAYSIAHOW CONSERVATION WORKS TAKE PLACE IN MALAYSIA
HOW CONSERVATION WORKS TAKE PLACE IN MALAYSIA
 
M3 Lecture 11 provisional sum prime cost sum
M3 Lecture 11 provisional sum  prime cost sumM3 Lecture 11 provisional sum  prime cost sum
M3 Lecture 11 provisional sum prime cost sum
 
Construction technology assignment 1
Construction technology assignment 1Construction technology assignment 1
Construction technology assignment 1
 
PP2 - Assignment
PP2 - Assignment PP2 - Assignment
PP2 - Assignment
 
PP1 assignment
PP1 assignment PP1 assignment
PP1 assignment
 
PP2 COMPILCATION
PP2 COMPILCATIONPP2 COMPILCATION
PP2 COMPILCATION
 
Measurement 4 Tender Document
Measurement 4 Tender Document Measurement 4 Tender Document
Measurement 4 Tender Document
 
Traditional procurement method
Traditional procurement methodTraditional procurement method
Traditional procurement method
 
bs:copbs101
bs:copbs101bs:copbs101
bs:copbs101
 
Pp1 seminar
Pp1 seminarPp1 seminar
Pp1 seminar
 
Payments in the construction industry
Payments in the construction industryPayments in the construction industry
Payments in the construction industry
 
Project Management (Group)
Project Management (Group)Project Management (Group)
Project Management (Group)
 
Determination of building_contracts
Determination of building_contractsDetermination of building_contracts
Determination of building_contracts
 
Form G1 G21(Bm)
Form G1 G21(Bm)Form G1 G21(Bm)
Form G1 G21(Bm)
 
Project management (1)
Project management (1)Project management (1)
Project management (1)
 
Site possession
Site possessionSite possession
Site possession
 
Guide for Construction Contract Administrators
Guide for Construction Contract AdministratorsGuide for Construction Contract Administrators
Guide for Construction Contract Administrators
 

Similar to Assignment - Financial Appraisal

Development Economics (Group Assignment) - Financial appraisal
Development Economics (Group Assignment) - Financial appraisalDevelopment Economics (Group Assignment) - Financial appraisal
Development Economics (Group Assignment) - Financial appraisalYee Len Wan
 
Regulatory Requisites & Development Cost Analysis in Bangalore
Regulatory Requisites & Development Cost Analysis in BangaloreRegulatory Requisites & Development Cost Analysis in Bangalore
Regulatory Requisites & Development Cost Analysis in Bangalorepiasi sinha
 
Development Economics (Group Assignment) - Financial appraisal presentation
Development Economics (Group Assignment) - Financial appraisal presentationDevelopment Economics (Group Assignment) - Financial appraisal presentation
Development Economics (Group Assignment) - Financial appraisal presentationYee Len Wan
 
PPT4 RIBA Plan of Work 2013 Power point slide
PPT4 RIBA Plan of Work 2013 Power point slidePPT4 RIBA Plan of Work 2013 Power point slide
PPT4 RIBA Plan of Work 2013 Power point slideSithick Mohamed .
 
Project management-project life cycle-pdf
Project management-project life cycle-pdfProject management-project life cycle-pdf
Project management-project life cycle-pdfAditi Garg
 
Circus_Residence_Brochure_July_29th_2015
Circus_Residence_Brochure_July_29th_2015Circus_Residence_Brochure_July_29th_2015
Circus_Residence_Brochure_July_29th_2015SAINBAYAR Beejin
 
How to prepare your Standard Operating Procedures (SOP) for Property Developm...
How to prepare your Standard Operating Procedures (SOP) for Property Developm...How to prepare your Standard Operating Procedures (SOP) for Property Developm...
How to prepare your Standard Operating Procedures (SOP) for Property Developm...REDceo.net
 
MCE Learning and Teaching Version 2.0 Page 1 of 6 Cour
MCE  Learning and Teaching Version 2.0  Page 1 of 6 CourMCE  Learning and Teaching Version 2.0  Page 1 of 6 Cour
MCE Learning and Teaching Version 2.0 Page 1 of 6 CourAbramMartino96
 
Document 1
Document 1Document 1
Document 1Erik Ong
 
body Intern Anteneh.pdf
body Intern Anteneh.pdfbody Intern Anteneh.pdf
body Intern Anteneh.pdfAntenehTibebu1
 
Ravindra Raichur
Ravindra RaichurRavindra Raichur
Ravindra Raichurraichur456
 
Ravindra raichur retail
Ravindra raichur retailRavindra raichur retail
Ravindra raichur retailraichur456
 
Qs(ici&itd) (1)
Qs(ici&itd) (1)Qs(ici&itd) (1)
Qs(ici&itd) (1)Js Cheok
 
Qs(ici&itd)
Qs(ici&itd)Qs(ici&itd)
Qs(ici&itd)Jy Chong
 
Pm x de compilation
Pm x de compilationPm x de compilation
Pm x de compilationYong Sy
 

Similar to Assignment - Financial Appraisal (20)

Development Economics (Group Assignment) - Financial appraisal
Development Economics (Group Assignment) - Financial appraisalDevelopment Economics (Group Assignment) - Financial appraisal
Development Economics (Group Assignment) - Financial appraisal
 
Regulatory Requisites & Development Cost Analysis in Bangalore
Regulatory Requisites & Development Cost Analysis in BangaloreRegulatory Requisites & Development Cost Analysis in Bangalore
Regulatory Requisites & Development Cost Analysis in Bangalore
 
Development Economics (Group Assignment) - Financial appraisal presentation
Development Economics (Group Assignment) - Financial appraisal presentationDevelopment Economics (Group Assignment) - Financial appraisal presentation
Development Economics (Group Assignment) - Financial appraisal presentation
 
PPT4 RIBA Plan of Work 2013 Power point slide
PPT4 RIBA Plan of Work 2013 Power point slidePPT4 RIBA Plan of Work 2013 Power point slide
PPT4 RIBA Plan of Work 2013 Power point slide
 
Project management-project life cycle-pdf
Project management-project life cycle-pdfProject management-project life cycle-pdf
Project management-project life cycle-pdf
 
Circus_Residence_Brochure_July_29th_2015
Circus_Residence_Brochure_July_29th_2015Circus_Residence_Brochure_July_29th_2015
Circus_Residence_Brochure_July_29th_2015
 
RIBA - PLAN OF WORK
RIBA - PLAN OF WORKRIBA - PLAN OF WORK
RIBA - PLAN OF WORK
 
Senior Architect
Senior ArchitectSenior Architect
Senior Architect
 
How to prepare your Standard Operating Procedures (SOP) for Property Developm...
How to prepare your Standard Operating Procedures (SOP) for Property Developm...How to prepare your Standard Operating Procedures (SOP) for Property Developm...
How to prepare your Standard Operating Procedures (SOP) for Property Developm...
 
MCE Learning and Teaching Version 2.0 Page 1 of 6 Cour
MCE  Learning and Teaching Version 2.0  Page 1 of 6 CourMCE  Learning and Teaching Version 2.0  Page 1 of 6 Cour
MCE Learning and Teaching Version 2.0 Page 1 of 6 Cour
 
Document 1
Document 1Document 1
Document 1
 
body Intern Anteneh.pdf
body Intern Anteneh.pdfbody Intern Anteneh.pdf
body Intern Anteneh.pdf
 
Ravindra Raichur
Ravindra RaichurRavindra Raichur
Ravindra Raichur
 
Ravindra raichur retail
Ravindra raichur retailRavindra raichur retail
Ravindra raichur retail
 
QSS
QSSQSS
QSS
 
Qs(ici&itd) (1)
Qs(ici&itd) (1)Qs(ici&itd) (1)
Qs(ici&itd) (1)
 
Qs(ici&itd)
Qs(ici&itd)Qs(ici&itd)
Qs(ici&itd)
 
RIBA Revit.pdf
RIBA Revit.pdfRIBA Revit.pdf
RIBA Revit.pdf
 
De assignment compile
De assignment compileDe assignment compile
De assignment compile
 
Pm x de compilation
Pm x de compilationPm x de compilation
Pm x de compilation
 

More from Kai Yun Pang

Assignment 2 - Resort Proposal at Pulau Langkawi
Assignment 2 - Resort Proposal at Pulau LangkawiAssignment 2 - Resort Proposal at Pulau Langkawi
Assignment 2 - Resort Proposal at Pulau LangkawiKai Yun Pang
 
Assignment 2 - Report
Assignment 2 - ReportAssignment 2 - Report
Assignment 2 - ReportKai Yun Pang
 
Assignment 1 - Water Pump Station
Assignment 1 - Water Pump StationAssignment 1 - Water Pump Station
Assignment 1 - Water Pump StationKai Yun Pang
 
Assignment 1 - Microsoft Project
Assignment 1 - Microsoft ProjectAssignment 1 - Microsoft Project
Assignment 1 - Microsoft ProjectKai Yun Pang
 
Assignment - Financial Appraisal
Assignment - Financial AppraisalAssignment - Financial Appraisal
Assignment - Financial AppraisalKai Yun Pang
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC ContractKai Yun Pang
 
Assignment - Report
Assignment - ReportAssignment - Report
Assignment - ReportKai Yun Pang
 
Seminar - CIPAA 2012
Seminar - CIPAA 2012Seminar - CIPAA 2012
Seminar - CIPAA 2012Kai Yun Pang
 
Assignment - S Hotel (Presentation Slide)
Assignment - S Hotel (Presentation Slide)Assignment - S Hotel (Presentation Slide)
Assignment - S Hotel (Presentation Slide)Kai Yun Pang
 
Assignment - S Hotel
Assignment - S HotelAssignment - S Hotel
Assignment - S HotelKai Yun Pang
 
Assignment - Case Study Report
Assignment - Case Study ReportAssignment - Case Study Report
Assignment - Case Study ReportKai Yun Pang
 
Assignment - Journal
Assignment - JournalAssignment - Journal
Assignment - JournalKai Yun Pang
 
Assignment - Community Service
Assignment - Community Service Assignment - Community Service
Assignment - Community Service Kai Yun Pang
 
Assignment - Final Account
Assignment - Final AccountAssignment - Final Account
Assignment - Final AccountKai Yun Pang
 
Assignment - Report
Assignment - ReportAssignment - Report
Assignment - ReportKai Yun Pang
 
Seminar - Partial Possession by Employer
Seminar - Partial Possession by EmployerSeminar - Partial Possession by Employer
Seminar - Partial Possession by EmployerKai Yun Pang
 
Seminar - Question
Seminar - QuestionSeminar - Question
Seminar - QuestionKai Yun Pang
 
Assignment - MK Land
Assignment - MK LandAssignment - MK Land
Assignment - MK LandKai Yun Pang
 
Assignment - Financial Analysis
Assignment - Financial AnalysisAssignment - Financial Analysis
Assignment - Financial AnalysisKai Yun Pang
 
Assignment - Preliminary Cost Appraisal (Presentation Slide)
Assignment - Preliminary Cost Appraisal (Presentation Slide)Assignment - Preliminary Cost Appraisal (Presentation Slide)
Assignment - Preliminary Cost Appraisal (Presentation Slide)Kai Yun Pang
 

More from Kai Yun Pang (20)

Assignment 2 - Resort Proposal at Pulau Langkawi
Assignment 2 - Resort Proposal at Pulau LangkawiAssignment 2 - Resort Proposal at Pulau Langkawi
Assignment 2 - Resort Proposal at Pulau Langkawi
 
Assignment 2 - Report
Assignment 2 - ReportAssignment 2 - Report
Assignment 2 - Report
 
Assignment 1 - Water Pump Station
Assignment 1 - Water Pump StationAssignment 1 - Water Pump Station
Assignment 1 - Water Pump Station
 
Assignment 1 - Microsoft Project
Assignment 1 - Microsoft ProjectAssignment 1 - Microsoft Project
Assignment 1 - Microsoft Project
 
Assignment - Financial Appraisal
Assignment - Financial AppraisalAssignment - Financial Appraisal
Assignment - Financial Appraisal
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC Contract
 
Assignment - Report
Assignment - ReportAssignment - Report
Assignment - Report
 
Seminar - CIPAA 2012
Seminar - CIPAA 2012Seminar - CIPAA 2012
Seminar - CIPAA 2012
 
Assignment - S Hotel (Presentation Slide)
Assignment - S Hotel (Presentation Slide)Assignment - S Hotel (Presentation Slide)
Assignment - S Hotel (Presentation Slide)
 
Assignment - S Hotel
Assignment - S HotelAssignment - S Hotel
Assignment - S Hotel
 
Assignment - Case Study Report
Assignment - Case Study ReportAssignment - Case Study Report
Assignment - Case Study Report
 
Assignment - Journal
Assignment - JournalAssignment - Journal
Assignment - Journal
 
Assignment - Community Service
Assignment - Community Service Assignment - Community Service
Assignment - Community Service
 
Assignment - Final Account
Assignment - Final AccountAssignment - Final Account
Assignment - Final Account
 
Assignment - Report
Assignment - ReportAssignment - Report
Assignment - Report
 
Seminar - Partial Possession by Employer
Seminar - Partial Possession by EmployerSeminar - Partial Possession by Employer
Seminar - Partial Possession by Employer
 
Seminar - Question
Seminar - QuestionSeminar - Question
Seminar - Question
 
Assignment - MK Land
Assignment - MK LandAssignment - MK Land
Assignment - MK Land
 
Assignment - Financial Analysis
Assignment - Financial AnalysisAssignment - Financial Analysis
Assignment - Financial Analysis
 
Assignment - Preliminary Cost Appraisal (Presentation Slide)
Assignment - Preliminary Cost Appraisal (Presentation Slide)Assignment - Preliminary Cost Appraisal (Presentation Slide)
Assignment - Preliminary Cost Appraisal (Presentation Slide)
 

Recently uploaded

microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesFatimaKhan178732
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfSumit Tiwari
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxRoyAbrique
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppCeline George
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting DataJhengPantaleon
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docxPoojaSen20
 

Recently uploaded (20)

microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and Actinides
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website App
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docx
 

Assignment - Financial Appraisal

  • 1. SCHOOL OF ARCHITECTURE, BUILDING AND DESIGN BACHELOR IN QUANTITY SURVEYING (HONOURS) AUGUST 2018 QSB 4223 DEVELOPMENT ECONOMICS ASSIGNMENT ASSIGNMENT BRIEF A property Developer intends to develop a piece of freehold land measuring 10 acres 1 rood 10 pole in Rawang, Selangor. The land was purchased three years ago at RM15.00 per sq. ft. with a RM6,500,000.00 bank loan. During this period, the Developer had applied for land conversion, subdivision, planning and building plans approval. The proposed development shall be of mixed residential and commercial units comprising of 26’ x 80’ double storey shop/office lots, 22’ x 75’ double storey Terrace houses and 20’ x 60’ double storey Low Cost houses. Thirty percent (30%) of the development must be of low cost houses. The Developer intends to have fifteen percent (15%) of the total units to be double storey shop/office. Development Order has now been granted and construction is ready to proceed. Construction shall take two years to complete. As the cost consultant engaged for the proposed project, prepare the following based on the project information available as attached. Group Assignment 1) An analysis of the number of units for each type of houses that can be built for the proposed development project. 2) A financial appraisal of the project using the Residue Method of Valuation. 3) A Cash Flow for the project based on ‘Sell-then-Build’ concept comprising of: i) Monthly Cash Inflow taking into consideration the required sales projection: * Note: Tabulation should indicate monthly total, net monthly cumulative total and also quarterly inflow. Table should be in A4 size. ii) Monthly Cash Outflow taking into consideration the contractual requirements; * Note: Tabulation should indicate monthly total, net monthly cumulative total and also quarterly inflow. Table should be in A4 size. This table will only reflect construction costs. Administration expenses should be reflected in the quarter- yearly cash flow as below. iii) Quarter-Yearly Cash Flow based on the above Cash Inflow and Cash Outflow and to include Project financing if required. For Project financing, to assume
  • 2. that a one lump sum repayment for the land to be made upon completion of construction. (For the purpose of this assignment, it is assumed no repayment is made for construction cost). 4) With a twelve percent (12%) cost of capital, tabulate and calculate the NPV of the project on a quarter-yearly basis. Give an overall analysis and comment on the viability of the project. 5) Comment on the cash flow and viability of the project if it is based on a ‘Build-then- Sell’ concept. (Assume 100% sales on completion of construction). Instructions to students: i) The assignment should be properly typed in A4/A3 sized paper with 12 point font size and one-and-a-half spacing. Only one side of each sheet should be used. The margin at the binding edge shall 40mm and other margins 25mm. The assignment must use comb-binder and bound with the assessment form in front. ii) All sources of information used should be acknowledged and referenced using an appropriate referencing method. iii) State the assignment topic, course and year, submission date and the names of all group members and their respective ID on the front page of the assignment. iv) You are to prepare minutes of meeting (in a format of your choice) to record what transpired during your group discussion, attendees of the meeting, action to be taken by respective individuals, progress of individual members & group as a whole and deadlines set to achieve tasks in order to meet the assignment submission deadline. The minutes of meetings are to be submitted as part of the assignment. ( 5 marks) v) In order to also assess each student’s individual effort, please state your name for the section/s of work/s that was prepared by you for the assignment. vi) Please note that at the end of the assignment, a copy of peer evaluation form will be given to all students for valuation of their team members’ contribution and efforts in the project assignment. vii) Submission date is on the 21st November 2018. -END-
  • 3. PROJECT TITLE PROPOSED DEVELOPMENT OF 26' X 80' D/S SHOP/OFFICE LOTS, 22’ X 75’ D/S TERRACE HOUSES AND 20’ X 60’ D/S LOW COST HOUSES IN PUCHONG, SELANGOR. PROJECT INFORMATION Land Purchased @ RM15.00/fs : January 2010 Commencement of construction : January 2013 Scheduled Completion : End December 2014 Planning Constraints / Restrictions  Effective development area : 60% of Land area  Restrictions: - Shop/Office Lots : maximum 10 units / block - Terrace Houses : maximum 12 units / block - Low Cost Houses : maximum 15 units / block  Low Cost quota : 30%  Bumiputra reservation : 30%  Bumiputra discount : 7% Development Composition: Type Build-up Area Selling Price Construction Cost Double Storey Shop/Office : 1. D/S Shop/Office 3,600 fs RM850,000.00 RM70.00 per fs 2. Corner unit 6,500 fs RM1,600,000.00 RM80.00 per fs 3. End unit 3,600 fs RM1,000,000.00 RM80.00 per fs Double Storey Terrace : 4. D/S Terrace 1,500 fs RM400,000.00 RM75.00 per fs 5. Corner unit 1,500 fs RM650,000.00 RM85.00 per fs 6. End unit 1,500 fs RM500,000.00 RM85.00 per fs Double-Storey Low Cost : 7. D/S Low Cost 900 fs RM45,000.00 RM35.00 per fs 8. Corner/End units 900 fs RM45,000.00 RM40.00 per fs Development/Construction Costs i. Land cost purchased at : RM15.00 per fs in January 2010 ii. Professional Fees : 9% of construction costs. iii. Administrative Fees : 2% of GDV iv. Plan Fees : RM2,000.00 per unit. v. Contributions & Fees : 2% of construction costs vi. Advertisement & Marketing : 1% of GDV vii. Conversion premium -commercial : 20% of land value of commercial lots -residential : 15% of land value of residential lots viii. Subdivision : RM1,500.00 per unit ix. Legal Fees : RM2,500.00 per unit x. Contingencies : 5% of construction costs xi. Earth Works : 5% of building costs xii. Infrastructure costs : 10% of building costs Assume:
  • 4.  Item (ii) is payable 60% on commencement of construction and balance payable in two equal yearly payments;  Items (iv), (v), (vii) (viii) & (ix) are payable on commencement of construction;  Items (iii), (vi) & (x) are payable equally throughout construction period.
  • 5. Financing Costs  Cost of Finance : 5.5% p.a.+ BLR  Interest on Loan for Purchase of Land : 2.5% p.a. + BLR (BLR assumed @ 6.5%) Contractual Requirements  Payment to contractor : 30 days Stage payment with 10% retention, limit 5% On completion of : Foundation : 10% RC Framework : 25% Walls, Doors & Wdw Frame : 15% Roofing, Elec Wiring & Plumbing : 15% Internal & External Plastering : 15% Sewerage Works : 5% Drainage Works : 5% Road Works : 10%  Final Certificate : 18 months from completion of construction. Sales Information  Sales Launch : January 2013  Sales Projection Shop/Office Terrace Low Cost - on launching : 10% 30% - end 2nd Q. 2013 : 20% 50% - end 3rd Q. 2013 : 30% 70% 50% - end 4th Q. 2013 : 40% 80% - end 1st Q. 2014 : 50% 100% 100% - end 2nd Q. 2014 : 70% - end 3rd Q. 2014 : 100% - end 4th Q. 2014 :  Collection from Purchasers : Stage Payment Third Schedule of SALE AND PURCHASE AGREEMENT (LAND AND BUILDING) Schedule G of HOUSING DEVELOPMENT (CONTROL AND LICENSING) ACT 1966 Assume 100% collection 30 days after payment is due. (ignore differences of billing period, notice period and grace period) Assume applicable for both commercial and residential properties.  Vacant Possession : Assume immediately upon completion of construction
  • 6. PROPOSED DEVELOPMENT OF 26' X 80' D/S SHOP/OFFICE LOTS, 22’ X 75’ D/S TERRACE HOUSES AND 20’ X 60’ D/S LOW COST HOUSES IN PUCHONG, SELANGOR. Date of Commencement : Date of Completion : 2013 2014 ITEM DESCRIPTION OF WORKS Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 1 EARTHWORKS 2 FOUNDATION 3 R.C. FRAMEWORK 4 WALLS, DOORS & WINDOW FRAME 5 ROOFING, ELEC WIRING & PLUMBING 6 INTERNAL & EXTERNAL PLASTERING 7 SEWERAGE WORKS 8 DRAINAGE WORKS 9 ROADWORKS 10 INFRASTRUCTURE WORKS 01 January 2013 31 December 2014CONSTRUCTION WORK PROGRAMME