SlideShare a Scribd company logo
1 of 43
Estimate is required to know the
QUANTITY OF MATERIAL and COST
OF WORK.
It is defined as the process of working
out the APPROXIMATE QUANTITY
of a work.
It is prepared by-
1. Working out Quantities.
2. Calculating the cost at suitable rates.
It is defined as the process of
determining the ACTUAL COST of the
work before starting the work.
Costing is done by use of-
1. Measurement sheets
2. Abstract Sheets.
To know Approximate Cost.
To know quantities of Materials &labors.
For getting Technical Sanction.
For inviting Tenders.
To get Time of Completion.
To know Actual Cost.
To do Financial Planning.
Alterations in plans can be done if
costing goes beyond the capacity.
1. Approximate Estimate: It gives us an
Approximate amount needed for the project.
2. Detailed Estimate: It gives us a Detailed
amount which is very near to the actual
amount needed for the project.
a) Service Unit Method
b) Plinth Area Method
c) Cubical Content Method
d) Typical Bay Method
e) Approximate Quantity Method
a) Revised Estimate
b) Supplementary Estimate
c) Revised & Supplementary Estimate
d) Repair & Maintenance Estimate
e) Renovation Estimate
It is a type of detailed estimate which is
prepared if in the project work there is
change in design and planning.
Also when actual cost of construction
increases by 5 to 10%.
Even if there are material changes from
original proposal, still Revised estimate is made.
It is a type of detailed estimate which is prepared
when there is additional work in the project.
E.g. If in a bedroom, attach toilet is not provided in
original estimate & later it is decided to construct
the toilet block, Supplementary Estimate is
necessary.
It is a type of detailed estimate which
is prepared if it is
combine Revised
necessary to
Estimate &
Supplementary Estimate.
It is a type of detailed estimate which is
prepared whenever it is necessary to repair
and maintain any structure in its working
condition.
Buildings- White washing, Color washing, Minor
Repairs etc.
Roads- Patch Work, Repairs of Bridges,
culverts etc.
It is a type of detailed estimate which
is prepared to do the Renovation of
Buildings, Bungalow, Flats etc. after
some years of use.
It is defined as the formal acceptance
of a proposal by competent authority.
It is prepared by Engineering
Department.
Proposal Contains- Approximate
Estimate and Preliminary Plans.
Competent Authorities- PWD Minister,
Chief Engineer, Superintending
Engineer etc.
It is defined as the sanction of
Detailed Estimate, Design calculations,
Quantities of work, Rates and Costs of
work by Competent Authority.
After Tech. Sanction, construction
work is started.
Authority Power
Chief Engineer (CE) Full Powers
Superintending Engineer (SE) Upto 1 Crore
Executive Engineer (EE) Upto 30 Lakhs
Assistant Executive Engineer
(AEE)
Upto 10 thousands
A report is prepared in which total cost
required for execution of project is
mentioned.
According to 5-years plan, finance is
sanctioned after administrative approval
of the project is Budget Provision.
1. To prepare checklist of items as per
drawings.
2. Prepare Centre-line plan of the structure.
3. Calculate quantities of items of work.
4. Express all quantities in correct units of
measurements.
5. Prepare Estimate as per Drawings &
Specifications.
6. Prepare Measurement Sheet & Abstract
Sheet.
Items of work Unit/ Mode
1. Earthwork Cu.m
2. PCC for foundation Cu.m
3. RCC Cu.m
4. Brickwork Cu.m
5. Stone Masonry Cu.m
6. Concrete Cu.m
7. Door & Window Shutters Sq.m
8. Door & Window Frames Cu.m
9. DPC Sq.m
10. Plastering & Pointing Sq.m
Items of work
Unit/ Mode of
Measurement
11. Flooring Sq.m
12. Skirting RMT
13. Centering & Shuttering Sq.m
14. Dado Sq.m
15. Painting/Coloring Sq.m
16. Barbed Wire Fencing RMT
17. Tiled Roofing, G.I. Sheets Sq.m
18. Railing RMT
19. Pipe RMT
20. Wash Basin Numbers
Items of work
Unit/ Mode of
Measurement
21. Site Clearance Lump sum
22. Electric Wiring Points
23. Steel Reinforcement Kg/ Tonne
24. Sand Filling Cu.m
25. 10 cm thick Brickwall Sq.m
26. Nut bolts Kg
27. Laying of sewer pipe RMT
28. False Ceiling Sq.m
29. Cutting of big trees with disposal Numbers
30. Valves Numbers
1. Site Clearance
2. Earthwork in excavation
3. PCC Bed in Foundation
4. RCC in Footing
5. Plinth Beam
6. Column
7. Floor Beams
8. Slab
9. Staircase
10. Plinth Filling
11. BBM for superstructure
12. Flooring
13. Internal Plaster
14. External Plaster
15. Internal Painting
16. External Painting
1. Site Clearance
2. Earthwork in excavation
3. PCC Bed in Foundation
4. UCR Masonry in Foundation
5. DPC in CM (1:3)
6. Brick Masonry in CM (1:6)
7. Plinth Filling
8. Flooring
9. Internal Plaster
10. External Plaster
11. Internal Painting
12. External Painting
Printed Booklet having rates of different
works.
List of different items of work.
Serves as a guide in deciding rates of
various items of work.
If rates of contractor differs much from
DSR rates, his tender may be rejected.
Lengths shall be measured to the
nearest 0.01m.
Areas shall be measured to the nearest
0.01m2.
Volumes shall be measured to the
nearest 0.01m3.
(A) PCC 1:4:8 for Foundation Concrete:
1. Cement:
a) OPC
b) Fresh Stock
c) If stored for more than 60 days,
test before using
(A) PCC 1:4:8 for Foundation Concrete:
2. Coarse Aggregate:
a) Of hard broken stones (about 40mm)
b) Free from dust, organic materials
c) Well graded
d) Lesser voids
(A) PCC 1:4:8 for Foundation Concrete:
3. Fine Aggregate:
a) Of coarse sand (about 4.75 mm)
b) Free from dust, organic materials
c) Hard, sharp, angular
d) In dry condition
(A) PCC 1:4:8 for Foundation Concrete:
4. Water:
a) Clean & Potable
b) Free from acidic and alkaline matters
c) Free from other impurities
(A) PCC 1:4:8 for Foundation Concrete:
5. Proportion:
a) Must be measured using a Box
b) Volume of Box must be equal to volume of 1
bag of cement
c) Take 1 bag cement; 4 boxes Fine Aggregate
and 8 boxes of Coarse Aggregate
(A) PCC 1:4:8 for Foundation Concrete:
6. a. Machine Mixing:
a) First put Coarse agg. fine agg cement in hopper.
b) Let this dry mixture be mixed for at least 4 turns of
hopper
c) Then add water slowly
d) Mix this mixture for at least 2 minutes
e) Get a uniform colored and consistent mixture
(A) PCC 1:4:8 for Foundation Concrete:
6. b. Hand Mixing:
a) First dry mix Coarse agg., fine agg., and cement on
a smooth platform.
b) Slowly add water and mix again.
c) Mix shall be turned 3 times in dry condition and 3
times in wet condition.
d) It gives you a consistent and workable mixture.
(A) PCC 1:4:8 for Foundation Concrete:
7. Laying and Compacting:
a) Before laying concrete in trench, sprinkle some water
b) Concrete is laid slowly in layers not more than 20 cm
and compacted before putting another layer
c) Before 2nd layer is laid, make top surface of 1st layer
rough
d) All this process should be free from dust, leaves, earth
etc.
(A) PCC 1:4:8 for Foundation Concrete:
8. Curing:
a) Concrete must be kept wet for at
least 7 days
b) Curing using Gunny Bags or sprinkling
water at regular intervals
(A) PCC 1:4:8 for Foundation Concrete:
9. Measurements:
a) Measurement shall be taken in cu.m
for finished concrete
b) Measurements (Length, Breadth and
Depth) shall be accurate up to 0.01m.
Lengths shall be measured to the
nearest 0.01m
Areas shall be measured to the nearest
0.01m2
Volumes shall be measured to the
nearest 0.01m3
No deduction is made for following:
Opening each up to 1000sq cm 0.1 square meter
Ends of beams, post, rafters, etc. up to 500 sq.cm
or 0.05 sq.m in section.
Bed plate, wall plate, bearing of balcony (chajja)
and the like up to 10 cm depth. bearing of floor and
roof slabs are not deducted from masonry.
Deductions for Rectangular Opening:
Full deduction is made for rectangular
openings in masonry walls
Deductions = L x H x thickness of wall
Item
No.
Description
of Item
No. Length Breadth
Height
or
Depth
Quantity Remarks
Item
No.
Description
of Item
Quantity Unit Rate Unit of Rate Amount
 Fundamentals of Estimating and Costing

More Related Content

What's hot

Estimating and costing
Estimating and costingEstimating and costing
Estimating and costingAyushHajare
 
Rate analysis road work in Estimation & Rate Analyisis
Rate analysis road work in Estimation & Rate AnalyisisRate analysis road work in Estimation & Rate Analyisis
Rate analysis road work in Estimation & Rate AnalyisisJaptyesh Singh
 
District schedule rates (DSR), specification of items of work as per PWD
District schedule rates (DSR), specification of items of work as per PWDDistrict schedule rates (DSR), specification of items of work as per PWD
District schedule rates (DSR), specification of items of work as per PWDAshwiniChaudhari13
 
Estimation and costing of a commercial building
Estimation and costing of a commercial buildingEstimation and costing of a commercial building
Estimation and costing of a commercial buildinglckr117
 
Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works  Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works ALI HYDER GADHI
 
Concrete- types, testing & properties
Concrete- types, testing & propertiesConcrete- types, testing & properties
Concrete- types, testing & propertieslalitha moorthy
 
estimation,its types and methods
estimation,its types and methodsestimation,its types and methods
estimation,its types and methodsgayu pandian
 
Building construction ppt
Building construction pptBuilding construction ppt
Building construction pptgyan singh
 
Long wall and short wall method 1
Long wall and short wall method 1Long wall and short wall method 1
Long wall and short wall method 1Saiyyed Akbar
 
Mode of measurement, rules for deduction of plastering & brickwork
Mode of measurement, rules for deduction of plastering & brickworkMode of measurement, rules for deduction of plastering & brickwork
Mode of measurement, rules for deduction of plastering & brickworkAshwiniChaudhari13
 
Types of estimates, checklist of items of work, role of estimator
Types of estimates, checklist of items of work, role of estimatorTypes of estimates, checklist of items of work, role of estimator
Types of estimates, checklist of items of work, role of estimatorAshwiniChaudhari13
 
Workability of Concrete
Workability  of ConcreteWorkability  of Concrete
Workability of ConcreteGulraizArshad1
 
Well foundations
Well foundationsWell foundations
Well foundationsganesh6561
 

What's hot (20)

Estimating and costing
Estimating and costingEstimating and costing
Estimating and costing
 
Rate analysis road work in Estimation & Rate Analyisis
Rate analysis road work in Estimation & Rate AnalyisisRate analysis road work in Estimation & Rate Analyisis
Rate analysis road work in Estimation & Rate Analyisis
 
District schedule rates (DSR), specification of items of work as per PWD
District schedule rates (DSR), specification of items of work as per PWDDistrict schedule rates (DSR), specification of items of work as per PWD
District schedule rates (DSR), specification of items of work as per PWD
 
Estimation and costing of a commercial building
Estimation and costing of a commercial buildingEstimation and costing of a commercial building
Estimation and costing of a commercial building
 
Estimating & Costing - I
Estimating & Costing - IEstimating & Costing - I
Estimating & Costing - I
 
Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works  Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works
 
Earthwork
EarthworkEarthwork
Earthwork
 
Concrete- types, testing & properties
Concrete- types, testing & propertiesConcrete- types, testing & properties
Concrete- types, testing & properties
 
estimation,its types and methods
estimation,its types and methodsestimation,its types and methods
estimation,its types and methods
 
Building construction ppt
Building construction pptBuilding construction ppt
Building construction ppt
 
ESTIMATING AND COSTING
ESTIMATING AND COSTINGESTIMATING AND COSTING
ESTIMATING AND COSTING
 
Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
 
Long wall and short wall method 1
Long wall and short wall method 1Long wall and short wall method 1
Long wall and short wall method 1
 
Mode of measurement, rules for deduction of plastering & brickwork
Mode of measurement, rules for deduction of plastering & brickworkMode of measurement, rules for deduction of plastering & brickwork
Mode of measurement, rules for deduction of plastering & brickwork
 
Types of estimates, checklist of items of work, role of estimator
Types of estimates, checklist of items of work, role of estimatorTypes of estimates, checklist of items of work, role of estimator
Types of estimates, checklist of items of work, role of estimator
 
Types of estimates
Types of estimatesTypes of estimates
Types of estimates
 
Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
 
Workability of Concrete
Workability  of ConcreteWorkability  of Concrete
Workability of Concrete
 
Well foundations
Well foundationsWell foundations
Well foundations
 
Floors
FloorsFloors
Floors
 

Similar to Fundamentals of Estimating and Costing

Ppt summer presentation on finishing Of Police Station Construction Site
Ppt summer presentation on finishing Of Police Station Construction SitePpt summer presentation on finishing Of Police Station Construction Site
Ppt summer presentation on finishing Of Police Station Construction SiteAlok Mishra
 
Ce1402 estimationandquantitysurveying (1)
Ce1402 estimationandquantitysurveying (1)Ce1402 estimationandquantitysurveying (1)
Ce1402 estimationandquantitysurveying (1)hlksd
 
estimation and quantity surveying
estimation and quantity surveyingestimation and quantity surveying
estimation and quantity surveyingsooricivil
 
Introduction to Quantity Surveying .pptx
Introduction to Quantity Surveying .pptxIntroduction to Quantity Surveying .pptx
Introduction to Quantity Surveying .pptxNSHYAMANANDASINGH
 
Estimating-Costing-civil.pdf
Estimating-Costing-civil.pdfEstimating-Costing-civil.pdf
Estimating-Costing-civil.pdfDivyaTadepalli1
 
A valuable journey proposal
A valuable journey proposalA valuable journey proposal
A valuable journey proposalkjanand
 
Construction basic SIP
Construction basic SIPConstruction basic SIP
Construction basic SIPMkh Nantu
 
Eqs unit 3 final
Eqs unit 3 finalEqs unit 3 final
Eqs unit 3 finaldhanapal143
 
Notes on Estimation.ppt
Notes on Estimation.pptNotes on Estimation.ppt
Notes on Estimation.pptashoklalwani6
 
EstimationandCosting.ppt
EstimationandCosting.pptEstimationandCosting.ppt
EstimationandCosting.pptSOUMITRAMUDI
 
Presentation [AP14015]
Presentation [AP14015]Presentation [AP14015]
Presentation [AP14015]Rahul Dasgupta
 
estimating and costing introduction ppt.pptx
estimating and costing  introduction ppt.pptxestimating and costing  introduction ppt.pptx
estimating and costing introduction ppt.pptxAshishJadhav655553
 
estimation,costingandvaluation.pdf
estimation,costingandvaluation.pdfestimation,costingandvaluation.pdf
estimation,costingandvaluation.pdfIctsol
 
Estimating and costing complete note
Estimating and costing complete noteEstimating and costing complete note
Estimating and costing complete noteMani Das
 
Estimation & costing guide
Estimation & costing guideEstimation & costing guide
Estimation & costing guideHiren Thakkar
 
Amit pandit presentaion gautambuddha university
Amit pandit presentaion gautambuddha universityAmit pandit presentaion gautambuddha university
Amit pandit presentaion gautambuddha universityAman Jain
 

Similar to Fundamentals of Estimating and Costing (20)

Ppt summer presentation on finishing Of Police Station Construction Site
Ppt summer presentation on finishing Of Police Station Construction SitePpt summer presentation on finishing Of Police Station Construction Site
Ppt summer presentation on finishing Of Police Station Construction Site
 
Ce1402 estimationandquantitysurveying (1)
Ce1402 estimationandquantitysurveying (1)Ce1402 estimationandquantitysurveying (1)
Ce1402 estimationandquantitysurveying (1)
 
estimation and quantity surveying
estimation and quantity surveyingestimation and quantity surveying
estimation and quantity surveying
 
Introduction to Quantity Surveying .pptx
Introduction to Quantity Surveying .pptxIntroduction to Quantity Surveying .pptx
Introduction to Quantity Surveying .pptx
 
Estimating-Costing-civil.pdf
Estimating-Costing-civil.pdfEstimating-Costing-civil.pdf
Estimating-Costing-civil.pdf
 
EQS - RATE ANALYSIS.pdf
EQS -  RATE ANALYSIS.pdfEQS -  RATE ANALYSIS.pdf
EQS - RATE ANALYSIS.pdf
 
A valuable journey proposal
A valuable journey proposalA valuable journey proposal
A valuable journey proposal
 
Construction basic SIP
Construction basic SIPConstruction basic SIP
Construction basic SIP
 
Eqs unit 3 final
Eqs unit 3 finalEqs unit 3 final
Eqs unit 3 final
 
Notes on Estimation.ppt
Notes on Estimation.pptNotes on Estimation.ppt
Notes on Estimation.ppt
 
EstimationandCosting.ppt
EstimationandCosting.pptEstimationandCosting.ppt
EstimationandCosting.ppt
 
Estimation_and_Costing.ppt
Estimation_and_Costing.pptEstimation_and_Costing.ppt
Estimation_and_Costing.ppt
 
ECV All Chapters
ECV All ChaptersECV All Chapters
ECV All Chapters
 
Presentation [AP14015]
Presentation [AP14015]Presentation [AP14015]
Presentation [AP14015]
 
estimating and costing introduction ppt.pptx
estimating and costing  introduction ppt.pptxestimating and costing  introduction ppt.pptx
estimating and costing introduction ppt.pptx
 
estimation,costingandvaluation.pdf
estimation,costingandvaluation.pdfestimation,costingandvaluation.pdf
estimation,costingandvaluation.pdf
 
Module_3.pdf.pdf
Module_3.pdf.pdfModule_3.pdf.pdf
Module_3.pdf.pdf
 
Estimating and costing complete note
Estimating and costing complete noteEstimating and costing complete note
Estimating and costing complete note
 
Estimation & costing guide
Estimation & costing guideEstimation & costing guide
Estimation & costing guide
 
Amit pandit presentaion gautambuddha university
Amit pandit presentaion gautambuddha universityAmit pandit presentaion gautambuddha university
Amit pandit presentaion gautambuddha university
 

Recently uploaded

Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 

Recently uploaded (20)

Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 

Fundamentals of Estimating and Costing

  • 1.
  • 2. Estimate is required to know the QUANTITY OF MATERIAL and COST OF WORK.
  • 3. It is defined as the process of working out the APPROXIMATE QUANTITY of a work. It is prepared by- 1. Working out Quantities. 2. Calculating the cost at suitable rates.
  • 4. It is defined as the process of determining the ACTUAL COST of the work before starting the work. Costing is done by use of- 1. Measurement sheets 2. Abstract Sheets.
  • 5. To know Approximate Cost. To know quantities of Materials &labors. For getting Technical Sanction. For inviting Tenders. To get Time of Completion.
  • 6. To know Actual Cost. To do Financial Planning. Alterations in plans can be done if costing goes beyond the capacity.
  • 7. 1. Approximate Estimate: It gives us an Approximate amount needed for the project. 2. Detailed Estimate: It gives us a Detailed amount which is very near to the actual amount needed for the project.
  • 8. a) Service Unit Method b) Plinth Area Method c) Cubical Content Method d) Typical Bay Method e) Approximate Quantity Method
  • 9. a) Revised Estimate b) Supplementary Estimate c) Revised & Supplementary Estimate d) Repair & Maintenance Estimate e) Renovation Estimate
  • 10. It is a type of detailed estimate which is prepared if in the project work there is change in design and planning. Also when actual cost of construction increases by 5 to 10%. Even if there are material changes from original proposal, still Revised estimate is made.
  • 11. It is a type of detailed estimate which is prepared when there is additional work in the project. E.g. If in a bedroom, attach toilet is not provided in original estimate & later it is decided to construct the toilet block, Supplementary Estimate is necessary.
  • 12. It is a type of detailed estimate which is prepared if it is combine Revised necessary to Estimate & Supplementary Estimate.
  • 13. It is a type of detailed estimate which is prepared whenever it is necessary to repair and maintain any structure in its working condition. Buildings- White washing, Color washing, Minor Repairs etc. Roads- Patch Work, Repairs of Bridges, culverts etc.
  • 14. It is a type of detailed estimate which is prepared to do the Renovation of Buildings, Bungalow, Flats etc. after some years of use.
  • 15. It is defined as the formal acceptance of a proposal by competent authority. It is prepared by Engineering Department.
  • 16. Proposal Contains- Approximate Estimate and Preliminary Plans. Competent Authorities- PWD Minister, Chief Engineer, Superintending Engineer etc.
  • 17. It is defined as the sanction of Detailed Estimate, Design calculations, Quantities of work, Rates and Costs of work by Competent Authority. After Tech. Sanction, construction work is started.
  • 18. Authority Power Chief Engineer (CE) Full Powers Superintending Engineer (SE) Upto 1 Crore Executive Engineer (EE) Upto 30 Lakhs Assistant Executive Engineer (AEE) Upto 10 thousands
  • 19. A report is prepared in which total cost required for execution of project is mentioned. According to 5-years plan, finance is sanctioned after administrative approval of the project is Budget Provision.
  • 20. 1. To prepare checklist of items as per drawings. 2. Prepare Centre-line plan of the structure. 3. Calculate quantities of items of work. 4. Express all quantities in correct units of measurements. 5. Prepare Estimate as per Drawings & Specifications. 6. Prepare Measurement Sheet & Abstract Sheet.
  • 21. Items of work Unit/ Mode 1. Earthwork Cu.m 2. PCC for foundation Cu.m 3. RCC Cu.m 4. Brickwork Cu.m 5. Stone Masonry Cu.m 6. Concrete Cu.m 7. Door & Window Shutters Sq.m 8. Door & Window Frames Cu.m 9. DPC Sq.m 10. Plastering & Pointing Sq.m
  • 22. Items of work Unit/ Mode of Measurement 11. Flooring Sq.m 12. Skirting RMT 13. Centering & Shuttering Sq.m 14. Dado Sq.m 15. Painting/Coloring Sq.m 16. Barbed Wire Fencing RMT 17. Tiled Roofing, G.I. Sheets Sq.m 18. Railing RMT 19. Pipe RMT 20. Wash Basin Numbers
  • 23. Items of work Unit/ Mode of Measurement 21. Site Clearance Lump sum 22. Electric Wiring Points 23. Steel Reinforcement Kg/ Tonne 24. Sand Filling Cu.m 25. 10 cm thick Brickwall Sq.m 26. Nut bolts Kg 27. Laying of sewer pipe RMT 28. False Ceiling Sq.m 29. Cutting of big trees with disposal Numbers 30. Valves Numbers
  • 24. 1. Site Clearance 2. Earthwork in excavation 3. PCC Bed in Foundation 4. RCC in Footing 5. Plinth Beam 6. Column 7. Floor Beams 8. Slab 9. Staircase 10. Plinth Filling 11. BBM for superstructure 12. Flooring 13. Internal Plaster 14. External Plaster 15. Internal Painting 16. External Painting
  • 25. 1. Site Clearance 2. Earthwork in excavation 3. PCC Bed in Foundation 4. UCR Masonry in Foundation 5. DPC in CM (1:3) 6. Brick Masonry in CM (1:6) 7. Plinth Filling 8. Flooring 9. Internal Plaster 10. External Plaster 11. Internal Painting 12. External Painting
  • 26. Printed Booklet having rates of different works. List of different items of work. Serves as a guide in deciding rates of various items of work. If rates of contractor differs much from DSR rates, his tender may be rejected.
  • 27. Lengths shall be measured to the nearest 0.01m. Areas shall be measured to the nearest 0.01m2. Volumes shall be measured to the nearest 0.01m3.
  • 28. (A) PCC 1:4:8 for Foundation Concrete: 1. Cement: a) OPC b) Fresh Stock c) If stored for more than 60 days, test before using
  • 29. (A) PCC 1:4:8 for Foundation Concrete: 2. Coarse Aggregate: a) Of hard broken stones (about 40mm) b) Free from dust, organic materials c) Well graded d) Lesser voids
  • 30. (A) PCC 1:4:8 for Foundation Concrete: 3. Fine Aggregate: a) Of coarse sand (about 4.75 mm) b) Free from dust, organic materials c) Hard, sharp, angular d) In dry condition
  • 31. (A) PCC 1:4:8 for Foundation Concrete: 4. Water: a) Clean & Potable b) Free from acidic and alkaline matters c) Free from other impurities
  • 32. (A) PCC 1:4:8 for Foundation Concrete: 5. Proportion: a) Must be measured using a Box b) Volume of Box must be equal to volume of 1 bag of cement c) Take 1 bag cement; 4 boxes Fine Aggregate and 8 boxes of Coarse Aggregate
  • 33. (A) PCC 1:4:8 for Foundation Concrete: 6. a. Machine Mixing: a) First put Coarse agg. fine agg cement in hopper. b) Let this dry mixture be mixed for at least 4 turns of hopper c) Then add water slowly d) Mix this mixture for at least 2 minutes e) Get a uniform colored and consistent mixture
  • 34. (A) PCC 1:4:8 for Foundation Concrete: 6. b. Hand Mixing: a) First dry mix Coarse agg., fine agg., and cement on a smooth platform. b) Slowly add water and mix again. c) Mix shall be turned 3 times in dry condition and 3 times in wet condition. d) It gives you a consistent and workable mixture.
  • 35. (A) PCC 1:4:8 for Foundation Concrete: 7. Laying and Compacting: a) Before laying concrete in trench, sprinkle some water b) Concrete is laid slowly in layers not more than 20 cm and compacted before putting another layer c) Before 2nd layer is laid, make top surface of 1st layer rough d) All this process should be free from dust, leaves, earth etc.
  • 36. (A) PCC 1:4:8 for Foundation Concrete: 8. Curing: a) Concrete must be kept wet for at least 7 days b) Curing using Gunny Bags or sprinkling water at regular intervals
  • 37. (A) PCC 1:4:8 for Foundation Concrete: 9. Measurements: a) Measurement shall be taken in cu.m for finished concrete b) Measurements (Length, Breadth and Depth) shall be accurate up to 0.01m.
  • 38. Lengths shall be measured to the nearest 0.01m Areas shall be measured to the nearest 0.01m2 Volumes shall be measured to the nearest 0.01m3
  • 39. No deduction is made for following: Opening each up to 1000sq cm 0.1 square meter Ends of beams, post, rafters, etc. up to 500 sq.cm or 0.05 sq.m in section. Bed plate, wall plate, bearing of balcony (chajja) and the like up to 10 cm depth. bearing of floor and roof slabs are not deducted from masonry.
  • 40. Deductions for Rectangular Opening: Full deduction is made for rectangular openings in masonry walls Deductions = L x H x thickness of wall
  • 41. Item No. Description of Item No. Length Breadth Height or Depth Quantity Remarks
  • 42. Item No. Description of Item Quantity Unit Rate Unit of Rate Amount