SlideShare a Scribd company logo
R
INTERNSHIP PRESENTATION ON
QUANTITY ESTIMATION OF BUILDING
Under the Guidance of Presented by
Shaik Vaheed M.Tech B.Aravind B151144
Assistant Professor
Dept. of Civil Engineerin P.Thirumalesh B151435
RGUKT Basar
B.Naresh B151372
RAJIV GANDHI UNIVERSITY OF KNOWLEDGE TECHNOLOGIES
R
1. What is Estimation?
2. Essential Qualities of Good Estimator.
3. Types of Estimates.
4. Methods of Detailed Estimates.
5. Description of Measurements for Common Items.
6. Estimation of Building, Plan , Foundation , Tabular forms..
7. Results.
8. Conclusion.
9. References.
CONTENT
R
Estimation
Estimation is the scientific way of working out the approximate cost of an engineering
project before execution of the work.
It is totally different from calculation of the exact cost after completion of the project.
Estimation requires a thorough Knowledge of the construction procedures and cost of
materials & labour in addition to the skill ,experience, foresight and good judgment
For a good estimate the, actual cost of the proposed work after completion should not
differ by more then 5 to 10 % from its approximate cost estimate, provided there are no
unusual, unforeseen circumstances.
R
1. It help to work out the approximate cost of the project in order to decide its
feasibility with respect to the cost and to ensure the financial resources, it the
proposal is approved.
2. Requirements of controlled materials, such as cement and steel can be estimated
for making applications to the controlling authorities.
3. It is used for framing the tenders for the work sand to check contractor’s work
during and after the its execution for the purpose of making payments to the
contractor.
4. From quantities of different items of work calculated in detailed estimation,
resources are allocated to different activities of the project and ultimately their
durations and whole planning and scheduling of the project is carried out.
NEED FOR ESTIMATE
R
ESSENTIAL QUALITIES OF A GOOD ESTIMATOR
Note the location of the proposed building.
Get all data available regarding the soil.
Make a sketch of the site showing all important details.
Obtain information concerning light, power, and water.
Secure information concerning banking facilities.
Note conditions of streets leading to railway yards and to material dealers, and
Investigate general efficiency of local workman.
R
1.To Explain the process of estimating the building cost for a Building.
2.To prepare a preliminary estimate of the cost of a residential Structure.
3.Generate a final estimate for a simple Structure.
4.To Estimate the quantities of a residential building by using long wall and short
wall method.
5. To know the approximate quantities of various material.
OBJECTIVIES
R
Purpose of Estimation
R
TYPES OF ESTIMATES
There are two main types of estimates:-
1 = Rough cost estimate.
2 = Detailed estimate.
Depending upon the purpose of estimate,
some types of detailed estimate are as
follows:-
a) Contractor's estimate
b) Engineer's estimate
c) Progress estimate
R
• Detailed estimates are prepared by carefully and separately calculating in detail
the costs of various items of the work.
• The mistakes, if any, in the rough cost estimate are eliminated in the detailed
estimate.
• Detailed estimates are submitted to the competent authorities for obtaining
technical sanction.
DETAILED ESTIMATE
R
The dimensions, length, breadth and height or depth are to
be taken out from the working drawings (plan, elevation
and section).
Junctions of walls, corners and the meeting points of walls
require special attention.
For symmetrical footings, which is the usual case, earthwork
in excavation in foundations, foundation concrete, brickwork
in foundation and plinth, and brickwork in superstructure
may be estimated by either of the two methods:
(1) SEPARATE OR INDIVIDUAL WALL METHOD
(2) CENTER LINE METHOD
METHODS OF DETAILED ESTIMATE
R
• The walls running in one direction are termed as "long walls” and the
walls running in the transverse direction, as "Short walls", without
keeping in mind which wall is lesser in length and which wall is greater
in length.
• Lengths of long walls are measured or found "Out-to out" and those of
short walls as "Into- in".
• Different quantities are calculated by multiplying the length by the
breadth and the height of the wall.
SEPARATE OR INDIVIDUAL WALLS METHOD
R
1.Site Clearance Works.
2.Excavation for Foundation Trenches.
3.Foundation Concrete.
4.Brick Work in Foundation up to Plinth.
5.Damp Proof Course.
6.Brick Work in Super Structure.
7. Roofing & R.C.C work.
8. Floor.
9.Plastering.
DESCRIPTION AND UNITS OF MEASUREMENT FOR COMMON ITEMS
R
Selected Building for Estimation
R
ESTIMATION OF A BUILDING : PLAN
R
FOUNDATIONS
R
SPECIFICATIONS
1.Clear Height of the Walls(Long & Short) = 3.96 m.
2.Plinth Level = 0.4 m.
3.Thickness of Roof Slab = 0.15 m.
4.Parapet wall Height = 1 m.
5.Parapet Wall Width = 0.1 m.
6.Lintels width & Height = 1.10 &0.15m
7.Damp proof Course = 2.5cm thickness of bitumen & polythene Sheet
8.Internal Finish = Three Coats of White Wash
9.External Finish= Three Coats of Weather Shield Paint
10.Door Dimensions = 1.98 m*1.1 m
11. Window Dimensions = 1.28m *1.22m
R
CENTRE TO CENTRE LENGTHS
S1 & S2 & S3 = (4.3+3.5)+(0.3)+(0.3/2)+(0.3/2) = 8.4 m
L1 & L2 & L3= (5.21)+(4.725)+(0.3)+(0.3/2)+(0.3/2) = 10.545 m
K = (4.3)+(0.3/2)+(0.3/2) = 4.6 m
R
Details of Measurement and Calculations of Building
Item
No. Particulars of Items No. Length Breadth Height or Depth Quantity
1 Earthwork in Excavation in
Foundation
Long Walls……
Short Walls…..
Kitchen Wall…..
3
3
1
10.535+0.6
8.4+0.6
4.6+0.6
0.6
0.6
0.6
0.7
0.7
0.7
14.03
11.34
2.184
Total = 27.6 m^3
2 Lime Concrete in
foundation
Long Walls….
Short Walls…
Kitchen Wall…
3
3
1
11.135
9.0
5.20
0.6
0.6
0.6
0.3
0.3
0.3
6.01
4.86
0.936
Total = 11.806 m^3
R
Item
No. Particular of Item No. Length Breadth Height or Depth Quantity
3 1st Class Brick Work in 1:6
cement mortar in
foundation and plinth
(i) Long Walls…
a) 1st Footing
b) Plinth
(ii) Short Walls….
a) 1st Footing
b) Plinth
Kitchen Wall…
a) 1st Footing
b) Plinth
3
3
3
3
1
1
10.935
10.835
8.8
8.7
5
4.9
0.4
0.3
0.4
0.3
0.4
0.3
0.3
0.60
0.20
0.60
0.4
0.3
2.62
1.95
2.112
4.691
0.4
0.882
Total = 12.662 m^3
4 Damp Proof Course
2.5 cm thick c.c
Long Walls….
Short Walls….
Kitchen Wall…
3
3
1
10.835
8.4
4.3
0.3
0.3
0.3
-
-
-
9.75
7.56
1.29
Total= 18.6 m^2
R
Item
No. Particulars of Item No. Length Breadth Height or Depth Quantity
5 1st Class Brick Work in
Lime Mortar in
Superstructure
Long Walls…
Short Walls…
Kitchen Wall….
Deduct
Door openings
Windows Opening
Lintels over Doors
Lintels over Windows
3
3
1
5
6
2
6
10.835
8.7
4.9
1.10
1.22
1.10
1.22
0.3
0.3
0.3
0.3
0.3
0.3
0.3
3.96
3.96
3.96
1.98
1.28
0.15
0.15
38.61
31.006
5.82
Total = 75.43 m^3
3.261
2.81
0.099
0.3294
Total = 6.49 m^3
Total = 75.43-6.49=68.92 m^3
6 Concrete in Slab 1 10.835 8.7 0.15 14.139 m^3
R
Item
No.
Particulars of Item No. Length Breadth Height or Depth Quantity
7 Plastering Of Super
Structure
Long Walls…
Short Walls..
Kitchen Wall…
Deduct
Door openings
Windows
3
3
1
5
6
10.835
8.7
4.3
1.10
1.22
-
-
-
-
-
3.96
3.96
3.96
1.98
1.28
128.71
103.356
17.025
TOTAL = 249.094 m^2
For both side of walls
249.094*2= 498.18 m^2
17.424
9.36
Total = 26.79 m^2
For both Sides
26.79*2=53.58 m^2
Plastering for Super
structure is
498.18-53.58=444.59 m^2
R
Details of Measurement and Calculations of Quantities of Compound Wall
Item
No. Particulars of Items No. Length Breadth Height or Depth Quantity
1 Earthwork in Excavation of
Compound Wall
Long Walls……
Short Walls…..
2
2
21.35+0.40
10.85+0.40
0.4
0.4
0.6
0.6
10.44
5.4
Total = 15.84 m^3
2 Lime Concrete in
foundation of Compound
Wall
Long Walls….
Short Walls…
2
2
21.35+0.40
10.85+0.40
0.4
0.4
0.2
0.2
3.48
1.8
Total = 5.28 m^3
R
Item
No. Particulars of Item No. Length Breadth Height or Depth Quantity
3 1st Class Brick Work
Compound Wall
Long Walls…
Short Walls…
Deduct
Gate openings
2
2
1
21.35+0.15
10.85+0.40
- 1.6
0.15
0.15
0.15
1.85
1.85
1.85
11.93
6.11
Total = 18.035 m^3
0.444 m^3
Total = 18.035-0.444=17.591 m^3
4 Plastering of Compound Wall
(Sides)
Long Walls….
Short Walls….
(Top)
Long Walls…..
Short Walls…..
Deduct
Gate Opening
2
2
2
2
1
21.5
11
21.5
11
1.6
-
-
0.15
0.15
1.55
1.55
-
-
1.85
66.65
34.1
6.45
3.3
Total= 110.5 m^2 *2= 221 m^2
2.96 m^2
Total = 221-2.96=218.2 m^2
R
Item
No. Particulars of Item No. Length Breadth Height or Depth Quantity
1 1st Class Brick Work in
Parapet Wall
Long Walls…
Short Walls…
Deduct
Parapet Wall opening
2
2
1
10.835
8.1
0.8
0.1
0.1
0.1
1
1
1
2.167
1.62
Total = 3.787 m^3
0.08 m^3
Total = 3.787-0.08=3.707 m^3
4 Plastering for Parapet Wall
(Sides)
Long Walls….
Short Walls….
(Top)
Long Walls…..
Short Walls…..
Deduct
Parapet Wall Opening(Side
Parapet Wall opening (top)
2
2
2
2
1
1
10.835
8.7
10.835
8.7
0.8
0.8
-
-
0.1
0.1
-
0.1
1
1
-
-
1
-
21.67
17.4
2.167
1.67
Total= 42.907 m^2 *2= 85.814 m^2
0.8*2=1.6 m^2
0.08*2=0.16 m^2 => 1.76 m^2
Total = 85.814-1.76= 84.054 m^2
R
Calculations For Staircase
R
Observations from Staircase
1. Height of Slab = 3.96 m.
2. Height to be acquired for on flight = 1.98 m.
3. Tread & Rise Lengths = 0.28 m & 0.16 m
4. Number of Risers = 12
5. Number of Treads = 11
6. Thickness of Waist Slab = 0.1524 m.
7. Length of Step = 0.9 m.
R
Calculations
1. Volume of Concrete for Steps
Volume of One Step = ½* Riser*Tread*Length of Step
= 0.21 m^3.
Volume for 12 steps = 12*0.21
= 2.42 m^3.
2. Volume of Concrete for Waist Slab
Volume of waist Slab = Inclined Length * Length of Slab * Width of Slab
= 3.9*0.9*0.15 = 0.54 m^3.
3. Volume of Concrete for First Flight
Total volume = Volume of waist Slab + Volume of Steps
= 0.54 + 2.42 = 2.96 m^3.
R
4. Volume of concrete for Landing of Staircase
Concrete volume for landing = Length * Width * Thickness of Landing
= 1.9 * 1 * 0.15
= 0.29 m^3.
5. Total Volume for Staircase
Volume = Volume of First Flight + Volume of Second Flight + Volume of Landing
= 2.96 + 2.96 + 0.29
= 6.21 m^3
R
Total Estimation of a Building
No. Particular of an Item Quantity( in m^3)
1 Earthwork in Excavation for Building and Compound Wall 27.6 + 15.84 = 43.33 m^3
2 Lime concrete in foundation of Building and Compound Wall 11.806 + 5.28 =
3 1st Class Brick Work in 1:6 cement mortar in foundation and plinth of
Building
12.67 m^3
4 Damp Proof Course 2.5 cm thick c.c of Building 18.6 m^3
5 1st Class Brick Work in Lime Mortar in Superstructure of Building ,
Compound Wall and Parapet Wall.
68.92 + 17.59 + 3.71 = 90.22 m^3
6 Plastering Of Super Structure of Building , Compound Wall and Parapet
Wall.
444.59 +218.2 + 84.05 = 746.84 m^2
7 Concrete in Slab 14.14 m^3
8 Total Volume of concrete of Staircase 6.21 m^3
R
Cost and time project estimate is a critical preparation in project management
process. Both of top-down and bottom-up approach is useful and applicable in
specific situations. Estimation as well as preparation for project, especially mission
critical ones, should be done so that it can reduce risks in implementing project,
control and assess this implementation process.
In this project we have estimated all the major items of works (Earth work
excavation, sand filling footings and columns, beams, slab total RCC Quantities and
brick work Quantities, plastering, painting, etc.) according to the drawings
CONCLUSION
R
• Akshay chaudhary and Payal Sachedeva and Maninderpal Singh; Design and
Estimation of a reinforced building: A Case study ISR journal of civil
Engineering.
• Estimation And Costing In Civil Engineering Theory And Practice Including
Specifications And Valuations B.N Dutta.
• Estimating, Costing, Specifications & Valuations in Civil Engineering By
Monojit Chakraborti (Book).
• Estimating in building construction By steven J.Peterson and Frank R.Dagostino.
REFERENCES
R
R

More Related Content

What's hot

Construction of residential building summer training ppt
 Construction of residential building summer training ppt Construction of residential building summer training ppt
Construction of residential building summer training ppt
Sumit Singh
 
Rate analysis in civil engineering
Rate analysis in civil engineeringRate analysis in civil engineering
Rate analysis in civil engineering
Kailash Chander
 
Retrofitting
RetrofittingRetrofitting
Retrofitting
Yash Kumar
 
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PPT
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PPTCTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PPT
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PPT
Shankar Ramasamy
 
Estimating and costing
Estimating and costingEstimating and costing
Estimating and costing
AyushHajare
 
Analysis and design of building
Analysis and design of buildingAnalysis and design of building
Analysis and design of building
Krishnagnr
 
G+3 APARTMENT BUILDING PROJECT REPORT
G+3 APARTMENT BUILDING  PROJECT  REPORTG+3 APARTMENT BUILDING  PROJECT  REPORT
G+3 APARTMENT BUILDING PROJECT REPORT
Fresher Thinking
 
Estimation and Costing
Estimation and Costing Estimation and Costing
Estimation and Costing
Vijay325
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
srinivas2036
 
Concrete Mix Design
Concrete Mix DesignConcrete Mix Design
Concrete Mix Design
GAURAV. H .TANDON
 
Long wall and short wall method 1
Long wall and short wall method 1Long wall and short wall method 1
Long wall and short wall method 1
Saiyyed Akbar
 
E.C.V detail estimate By centre line and Long wall short wall method
E.C.V detail estimate By centre line and Long wall short wall methodE.C.V detail estimate By centre line and Long wall short wall method
E.C.V detail estimate By centre line and Long wall short wall method
Yusuf Challawala
 
Earthwork and excavation
Earthwork  and  excavationEarthwork  and  excavation
Earthwork and excavation
Krishna Spoorthy Rachamalla
 
estimation,its types and methods
estimation,its types and methodsestimation,its types and methods
estimation,its types and methods
gayu pandian
 
Estimating and-costing
Estimating and-costingEstimating and-costing
Estimating and-costing
RANJIT KUMAR PANDA
 
minor project report on design of residential building
minor project report on design of residential buildingminor project report on design of residential building
minor project report on design of residential buildingtushar garg
 
Preparation of bill sandeep
Preparation of bill sandeepPreparation of bill sandeep
Preparation of bill sandeep
Sandeep Yadav
 
Non-Destructive Testing of Concrete In Structures
Non-Destructive Testing of Concrete In StructuresNon-Destructive Testing of Concrete In Structures
Non-Destructive Testing of Concrete In Structures26032015
 
Estimation (power point)
Estimation (power point)Estimation (power point)
Estimation (power point)Waqas Aslam
 

What's hot (20)

Construction of residential building summer training ppt
 Construction of residential building summer training ppt Construction of residential building summer training ppt
Construction of residential building summer training ppt
 
Rate analysis in civil engineering
Rate analysis in civil engineeringRate analysis in civil engineering
Rate analysis in civil engineering
 
Retrofitting
RetrofittingRetrofitting
Retrofitting
 
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PPT
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PPTCTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PPT
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PPT
 
Estimating and costing
Estimating and costingEstimating and costing
Estimating and costing
 
Estimation
EstimationEstimation
Estimation
 
Analysis and design of building
Analysis and design of buildingAnalysis and design of building
Analysis and design of building
 
G+3 APARTMENT BUILDING PROJECT REPORT
G+3 APARTMENT BUILDING  PROJECT  REPORTG+3 APARTMENT BUILDING  PROJECT  REPORT
G+3 APARTMENT BUILDING PROJECT REPORT
 
Estimation and Costing
Estimation and Costing Estimation and Costing
Estimation and Costing
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
 
Concrete Mix Design
Concrete Mix DesignConcrete Mix Design
Concrete Mix Design
 
Long wall and short wall method 1
Long wall and short wall method 1Long wall and short wall method 1
Long wall and short wall method 1
 
E.C.V detail estimate By centre line and Long wall short wall method
E.C.V detail estimate By centre line and Long wall short wall methodE.C.V detail estimate By centre line and Long wall short wall method
E.C.V detail estimate By centre line and Long wall short wall method
 
Earthwork and excavation
Earthwork  and  excavationEarthwork  and  excavation
Earthwork and excavation
 
estimation,its types and methods
estimation,its types and methodsestimation,its types and methods
estimation,its types and methods
 
Estimating and-costing
Estimating and-costingEstimating and-costing
Estimating and-costing
 
minor project report on design of residential building
minor project report on design of residential buildingminor project report on design of residential building
minor project report on design of residential building
 
Preparation of bill sandeep
Preparation of bill sandeepPreparation of bill sandeep
Preparation of bill sandeep
 
Non-Destructive Testing of Concrete In Structures
Non-Destructive Testing of Concrete In StructuresNon-Destructive Testing of Concrete In Structures
Non-Destructive Testing of Concrete In Structures
 
Estimation (power point)
Estimation (power point)Estimation (power point)
Estimation (power point)
 

Similar to Cost estimation of a Building

Estimation & costing guide
Estimation & costing guideEstimation & costing guide
Estimation & costing guide
Hiren Thakkar
 
B.arch Estimation and Costing
B.arch  Estimation and CostingB.arch  Estimation and Costing
B.arch Estimation and Costing
SamreenFatima29
 
Lec 9 center line method
Lec 9 center line methodLec 9 center line method
Lec 9 center line method
malang1214
 
Cost estimation
Cost estimationCost estimation
Cost estimation
Satyam Singh
 
Ce1402 estimationandquantitysurveying (1)
Ce1402 estimationandquantitysurveying (1)Ce1402 estimationandquantitysurveying (1)
Ce1402 estimationandquantitysurveying (1)
hlksd
 
estimation of a g+5 structure
estimation of a g+5 structureestimation of a g+5 structure
estimation of a g+5 structure
Sharan_63
 
estimation,costingandvaluation.pdf
estimation,costingandvaluation.pdfestimation,costingandvaluation.pdf
estimation,costingandvaluation.pdf
Ictsol
 
A Course Material On Estimation And Quantity Surveying
A Course Material On Estimation And Quantity SurveyingA Course Material On Estimation And Quantity Surveying
A Course Material On Estimation And Quantity Surveying
Claire Webber
 
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
DougDos
 
final praveen.pptx
final praveen.pptxfinal praveen.pptx
final praveen.pptx
RajeshKumar25548
 
Estimating-Costing-civil.pdf
Estimating-Costing-civil.pdfEstimating-Costing-civil.pdf
Estimating-Costing-civil.pdf
DivyaTadepalli1
 
Construction practices aphb
Construction practices aphbConstruction practices aphb
Construction practices aphbhlksd
 
Lec.3 General rules in quantitative survey. Quantity measuring. Rate analysis
Lec.3  General rules in quantitative survey. Quantity measuring. Rate analysisLec.3  General rules in quantitative survey. Quantity measuring. Rate analysis
Lec.3 General rules in quantitative survey. Quantity measuring. Rate analysis
Muthanna Abbu
 
Design of 16 storied apartment using TEKLA STRUCTURAL DESIGNER
Design of 16 storied apartment using TEKLA STRUCTURAL DESIGNERDesign of 16 storied apartment using TEKLA STRUCTURAL DESIGNER
Design of 16 storied apartment using TEKLA STRUCTURAL DESIGNER
zafrin mohamed
 
188.pptx
188.pptx188.pptx
188.pptx
19188BikashSah
 
EC Unit 002 new (1).pdf
EC  Unit 002 new (1).pdfEC  Unit 002 new (1).pdf
EC Unit 002 new (1).pdf
mohsin mohammad
 
Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)
Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)
Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)
AMIT PAYAL
 
INTERNSHIP (5).pptx
 INTERNSHIP (5).pptx INTERNSHIP (5).pptx
INTERNSHIP (5).pptx
kartik395517
 
EstimationandCosting.ppt
EstimationandCosting.pptEstimationandCosting.ppt
EstimationandCosting.ppt
SOUMITRAMUDI
 

Similar to Cost estimation of a Building (20)

Estimation & costing guide
Estimation & costing guideEstimation & costing guide
Estimation & costing guide
 
B.arch Estimation and Costing
B.arch  Estimation and CostingB.arch  Estimation and Costing
B.arch Estimation and Costing
 
Lec 9 center line method
Lec 9 center line methodLec 9 center line method
Lec 9 center line method
 
Cost estimation
Cost estimationCost estimation
Cost estimation
 
Seminar
SeminarSeminar
Seminar
 
Ce1402 estimationandquantitysurveying (1)
Ce1402 estimationandquantitysurveying (1)Ce1402 estimationandquantitysurveying (1)
Ce1402 estimationandquantitysurveying (1)
 
estimation of a g+5 structure
estimation of a g+5 structureestimation of a g+5 structure
estimation of a g+5 structure
 
estimation,costingandvaluation.pdf
estimation,costingandvaluation.pdfestimation,costingandvaluation.pdf
estimation,costingandvaluation.pdf
 
A Course Material On Estimation And Quantity Surveying
A Course Material On Estimation And Quantity SurveyingA Course Material On Estimation And Quantity Surveying
A Course Material On Estimation And Quantity Surveying
 
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
 
final praveen.pptx
final praveen.pptxfinal praveen.pptx
final praveen.pptx
 
Estimating-Costing-civil.pdf
Estimating-Costing-civil.pdfEstimating-Costing-civil.pdf
Estimating-Costing-civil.pdf
 
Construction practices aphb
Construction practices aphbConstruction practices aphb
Construction practices aphb
 
Lec.3 General rules in quantitative survey. Quantity measuring. Rate analysis
Lec.3  General rules in quantitative survey. Quantity measuring. Rate analysisLec.3  General rules in quantitative survey. Quantity measuring. Rate analysis
Lec.3 General rules in quantitative survey. Quantity measuring. Rate analysis
 
Design of 16 storied apartment using TEKLA STRUCTURAL DESIGNER
Design of 16 storied apartment using TEKLA STRUCTURAL DESIGNERDesign of 16 storied apartment using TEKLA STRUCTURAL DESIGNER
Design of 16 storied apartment using TEKLA STRUCTURAL DESIGNER
 
188.pptx
188.pptx188.pptx
188.pptx
 
EC Unit 002 new (1).pdf
EC  Unit 002 new (1).pdfEC  Unit 002 new (1).pdf
EC Unit 002 new (1).pdf
 
Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)
Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)
Whatisworkofcivilengineeronconstructionsite 190827025839 (9 files merged)
 
INTERNSHIP (5).pptx
 INTERNSHIP (5).pptx INTERNSHIP (5).pptx
INTERNSHIP (5).pptx
 
EstimationandCosting.ppt
EstimationandCosting.pptEstimationandCosting.ppt
EstimationandCosting.ppt
 

Recently uploaded

Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
SupreethSP4
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 

Recently uploaded (20)

Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 

Cost estimation of a Building

  • 1. R INTERNSHIP PRESENTATION ON QUANTITY ESTIMATION OF BUILDING Under the Guidance of Presented by Shaik Vaheed M.Tech B.Aravind B151144 Assistant Professor Dept. of Civil Engineerin P.Thirumalesh B151435 RGUKT Basar B.Naresh B151372 RAJIV GANDHI UNIVERSITY OF KNOWLEDGE TECHNOLOGIES
  • 2. R 1. What is Estimation? 2. Essential Qualities of Good Estimator. 3. Types of Estimates. 4. Methods of Detailed Estimates. 5. Description of Measurements for Common Items. 6. Estimation of Building, Plan , Foundation , Tabular forms.. 7. Results. 8. Conclusion. 9. References. CONTENT
  • 3. R Estimation Estimation is the scientific way of working out the approximate cost of an engineering project before execution of the work. It is totally different from calculation of the exact cost after completion of the project. Estimation requires a thorough Knowledge of the construction procedures and cost of materials & labour in addition to the skill ,experience, foresight and good judgment For a good estimate the, actual cost of the proposed work after completion should not differ by more then 5 to 10 % from its approximate cost estimate, provided there are no unusual, unforeseen circumstances.
  • 4. R 1. It help to work out the approximate cost of the project in order to decide its feasibility with respect to the cost and to ensure the financial resources, it the proposal is approved. 2. Requirements of controlled materials, such as cement and steel can be estimated for making applications to the controlling authorities. 3. It is used for framing the tenders for the work sand to check contractor’s work during and after the its execution for the purpose of making payments to the contractor. 4. From quantities of different items of work calculated in detailed estimation, resources are allocated to different activities of the project and ultimately their durations and whole planning and scheduling of the project is carried out. NEED FOR ESTIMATE
  • 5. R ESSENTIAL QUALITIES OF A GOOD ESTIMATOR Note the location of the proposed building. Get all data available regarding the soil. Make a sketch of the site showing all important details. Obtain information concerning light, power, and water. Secure information concerning banking facilities. Note conditions of streets leading to railway yards and to material dealers, and Investigate general efficiency of local workman.
  • 6. R 1.To Explain the process of estimating the building cost for a Building. 2.To prepare a preliminary estimate of the cost of a residential Structure. 3.Generate a final estimate for a simple Structure. 4.To Estimate the quantities of a residential building by using long wall and short wall method. 5. To know the approximate quantities of various material. OBJECTIVIES
  • 8. R TYPES OF ESTIMATES There are two main types of estimates:- 1 = Rough cost estimate. 2 = Detailed estimate. Depending upon the purpose of estimate, some types of detailed estimate are as follows:- a) Contractor's estimate b) Engineer's estimate c) Progress estimate
  • 9. R • Detailed estimates are prepared by carefully and separately calculating in detail the costs of various items of the work. • The mistakes, if any, in the rough cost estimate are eliminated in the detailed estimate. • Detailed estimates are submitted to the competent authorities for obtaining technical sanction. DETAILED ESTIMATE
  • 10. R The dimensions, length, breadth and height or depth are to be taken out from the working drawings (plan, elevation and section). Junctions of walls, corners and the meeting points of walls require special attention. For symmetrical footings, which is the usual case, earthwork in excavation in foundations, foundation concrete, brickwork in foundation and plinth, and brickwork in superstructure may be estimated by either of the two methods: (1) SEPARATE OR INDIVIDUAL WALL METHOD (2) CENTER LINE METHOD METHODS OF DETAILED ESTIMATE
  • 11. R • The walls running in one direction are termed as "long walls” and the walls running in the transverse direction, as "Short walls", without keeping in mind which wall is lesser in length and which wall is greater in length. • Lengths of long walls are measured or found "Out-to out" and those of short walls as "Into- in". • Different quantities are calculated by multiplying the length by the breadth and the height of the wall. SEPARATE OR INDIVIDUAL WALLS METHOD
  • 12. R 1.Site Clearance Works. 2.Excavation for Foundation Trenches. 3.Foundation Concrete. 4.Brick Work in Foundation up to Plinth. 5.Damp Proof Course. 6.Brick Work in Super Structure. 7. Roofing & R.C.C work. 8. Floor. 9.Plastering. DESCRIPTION AND UNITS OF MEASUREMENT FOR COMMON ITEMS
  • 14. R ESTIMATION OF A BUILDING : PLAN
  • 16. R SPECIFICATIONS 1.Clear Height of the Walls(Long & Short) = 3.96 m. 2.Plinth Level = 0.4 m. 3.Thickness of Roof Slab = 0.15 m. 4.Parapet wall Height = 1 m. 5.Parapet Wall Width = 0.1 m. 6.Lintels width & Height = 1.10 &0.15m 7.Damp proof Course = 2.5cm thickness of bitumen & polythene Sheet 8.Internal Finish = Three Coats of White Wash 9.External Finish= Three Coats of Weather Shield Paint 10.Door Dimensions = 1.98 m*1.1 m 11. Window Dimensions = 1.28m *1.22m
  • 17. R CENTRE TO CENTRE LENGTHS S1 & S2 & S3 = (4.3+3.5)+(0.3)+(0.3/2)+(0.3/2) = 8.4 m L1 & L2 & L3= (5.21)+(4.725)+(0.3)+(0.3/2)+(0.3/2) = 10.545 m K = (4.3)+(0.3/2)+(0.3/2) = 4.6 m
  • 18. R Details of Measurement and Calculations of Building Item No. Particulars of Items No. Length Breadth Height or Depth Quantity 1 Earthwork in Excavation in Foundation Long Walls…… Short Walls….. Kitchen Wall….. 3 3 1 10.535+0.6 8.4+0.6 4.6+0.6 0.6 0.6 0.6 0.7 0.7 0.7 14.03 11.34 2.184 Total = 27.6 m^3 2 Lime Concrete in foundation Long Walls…. Short Walls… Kitchen Wall… 3 3 1 11.135 9.0 5.20 0.6 0.6 0.6 0.3 0.3 0.3 6.01 4.86 0.936 Total = 11.806 m^3
  • 19. R Item No. Particular of Item No. Length Breadth Height or Depth Quantity 3 1st Class Brick Work in 1:6 cement mortar in foundation and plinth (i) Long Walls… a) 1st Footing b) Plinth (ii) Short Walls…. a) 1st Footing b) Plinth Kitchen Wall… a) 1st Footing b) Plinth 3 3 3 3 1 1 10.935 10.835 8.8 8.7 5 4.9 0.4 0.3 0.4 0.3 0.4 0.3 0.3 0.60 0.20 0.60 0.4 0.3 2.62 1.95 2.112 4.691 0.4 0.882 Total = 12.662 m^3 4 Damp Proof Course 2.5 cm thick c.c Long Walls…. Short Walls…. Kitchen Wall… 3 3 1 10.835 8.4 4.3 0.3 0.3 0.3 - - - 9.75 7.56 1.29 Total= 18.6 m^2
  • 20. R Item No. Particulars of Item No. Length Breadth Height or Depth Quantity 5 1st Class Brick Work in Lime Mortar in Superstructure Long Walls… Short Walls… Kitchen Wall…. Deduct Door openings Windows Opening Lintels over Doors Lintels over Windows 3 3 1 5 6 2 6 10.835 8.7 4.9 1.10 1.22 1.10 1.22 0.3 0.3 0.3 0.3 0.3 0.3 0.3 3.96 3.96 3.96 1.98 1.28 0.15 0.15 38.61 31.006 5.82 Total = 75.43 m^3 3.261 2.81 0.099 0.3294 Total = 6.49 m^3 Total = 75.43-6.49=68.92 m^3 6 Concrete in Slab 1 10.835 8.7 0.15 14.139 m^3
  • 21. R Item No. Particulars of Item No. Length Breadth Height or Depth Quantity 7 Plastering Of Super Structure Long Walls… Short Walls.. Kitchen Wall… Deduct Door openings Windows 3 3 1 5 6 10.835 8.7 4.3 1.10 1.22 - - - - - 3.96 3.96 3.96 1.98 1.28 128.71 103.356 17.025 TOTAL = 249.094 m^2 For both side of walls 249.094*2= 498.18 m^2 17.424 9.36 Total = 26.79 m^2 For both Sides 26.79*2=53.58 m^2 Plastering for Super structure is 498.18-53.58=444.59 m^2
  • 22. R Details of Measurement and Calculations of Quantities of Compound Wall Item No. Particulars of Items No. Length Breadth Height or Depth Quantity 1 Earthwork in Excavation of Compound Wall Long Walls…… Short Walls….. 2 2 21.35+0.40 10.85+0.40 0.4 0.4 0.6 0.6 10.44 5.4 Total = 15.84 m^3 2 Lime Concrete in foundation of Compound Wall Long Walls…. Short Walls… 2 2 21.35+0.40 10.85+0.40 0.4 0.4 0.2 0.2 3.48 1.8 Total = 5.28 m^3
  • 23. R Item No. Particulars of Item No. Length Breadth Height or Depth Quantity 3 1st Class Brick Work Compound Wall Long Walls… Short Walls… Deduct Gate openings 2 2 1 21.35+0.15 10.85+0.40 - 1.6 0.15 0.15 0.15 1.85 1.85 1.85 11.93 6.11 Total = 18.035 m^3 0.444 m^3 Total = 18.035-0.444=17.591 m^3 4 Plastering of Compound Wall (Sides) Long Walls…. Short Walls…. (Top) Long Walls….. Short Walls….. Deduct Gate Opening 2 2 2 2 1 21.5 11 21.5 11 1.6 - - 0.15 0.15 1.55 1.55 - - 1.85 66.65 34.1 6.45 3.3 Total= 110.5 m^2 *2= 221 m^2 2.96 m^2 Total = 221-2.96=218.2 m^2
  • 24. R Item No. Particulars of Item No. Length Breadth Height or Depth Quantity 1 1st Class Brick Work in Parapet Wall Long Walls… Short Walls… Deduct Parapet Wall opening 2 2 1 10.835 8.1 0.8 0.1 0.1 0.1 1 1 1 2.167 1.62 Total = 3.787 m^3 0.08 m^3 Total = 3.787-0.08=3.707 m^3 4 Plastering for Parapet Wall (Sides) Long Walls…. Short Walls…. (Top) Long Walls….. Short Walls….. Deduct Parapet Wall Opening(Side Parapet Wall opening (top) 2 2 2 2 1 1 10.835 8.7 10.835 8.7 0.8 0.8 - - 0.1 0.1 - 0.1 1 1 - - 1 - 21.67 17.4 2.167 1.67 Total= 42.907 m^2 *2= 85.814 m^2 0.8*2=1.6 m^2 0.08*2=0.16 m^2 => 1.76 m^2 Total = 85.814-1.76= 84.054 m^2
  • 26. R Observations from Staircase 1. Height of Slab = 3.96 m. 2. Height to be acquired for on flight = 1.98 m. 3. Tread & Rise Lengths = 0.28 m & 0.16 m 4. Number of Risers = 12 5. Number of Treads = 11 6. Thickness of Waist Slab = 0.1524 m. 7. Length of Step = 0.9 m.
  • 27. R Calculations 1. Volume of Concrete for Steps Volume of One Step = ½* Riser*Tread*Length of Step = 0.21 m^3. Volume for 12 steps = 12*0.21 = 2.42 m^3. 2. Volume of Concrete for Waist Slab Volume of waist Slab = Inclined Length * Length of Slab * Width of Slab = 3.9*0.9*0.15 = 0.54 m^3. 3. Volume of Concrete for First Flight Total volume = Volume of waist Slab + Volume of Steps = 0.54 + 2.42 = 2.96 m^3.
  • 28. R 4. Volume of concrete for Landing of Staircase Concrete volume for landing = Length * Width * Thickness of Landing = 1.9 * 1 * 0.15 = 0.29 m^3. 5. Total Volume for Staircase Volume = Volume of First Flight + Volume of Second Flight + Volume of Landing = 2.96 + 2.96 + 0.29 = 6.21 m^3
  • 29. R Total Estimation of a Building No. Particular of an Item Quantity( in m^3) 1 Earthwork in Excavation for Building and Compound Wall 27.6 + 15.84 = 43.33 m^3 2 Lime concrete in foundation of Building and Compound Wall 11.806 + 5.28 = 3 1st Class Brick Work in 1:6 cement mortar in foundation and plinth of Building 12.67 m^3 4 Damp Proof Course 2.5 cm thick c.c of Building 18.6 m^3 5 1st Class Brick Work in Lime Mortar in Superstructure of Building , Compound Wall and Parapet Wall. 68.92 + 17.59 + 3.71 = 90.22 m^3 6 Plastering Of Super Structure of Building , Compound Wall and Parapet Wall. 444.59 +218.2 + 84.05 = 746.84 m^2 7 Concrete in Slab 14.14 m^3 8 Total Volume of concrete of Staircase 6.21 m^3
  • 30. R Cost and time project estimate is a critical preparation in project management process. Both of top-down and bottom-up approach is useful and applicable in specific situations. Estimation as well as preparation for project, especially mission critical ones, should be done so that it can reduce risks in implementing project, control and assess this implementation process. In this project we have estimated all the major items of works (Earth work excavation, sand filling footings and columns, beams, slab total RCC Quantities and brick work Quantities, plastering, painting, etc.) according to the drawings CONCLUSION
  • 31. R • Akshay chaudhary and Payal Sachedeva and Maninderpal Singh; Design and Estimation of a reinforced building: A Case study ISR journal of civil Engineering. • Estimation And Costing In Civil Engineering Theory And Practice Including Specifications And Valuations B.N Dutta. • Estimating, Costing, Specifications & Valuations in Civil Engineering By Monojit Chakraborti (Book). • Estimating in building construction By steven J.Peterson and Frank R.Dagostino. REFERENCES
  • 32. R
  • 33. R