SCHOOL OF ARCHITECTURE, BUILDING AND DESIGN
BACHELOR OF QUANTITY SURVEYING (HONOURS)
MGT60704 PROJECT MANAGEMENT
AUGUST 2018 SEMESTER
INDIVIDUAL ASSIGNMENT
NAME : PANG KAI YUN
STUDENT ID : 0319802
LECTURER : MR LEONG BOON TIK
SUBMISSION DATE : 27 NOVEMBER 2018
Assumption:
1. Working days excluding Saturday and Sunday.
2. Clear and grub the site before installing temporary electrical
connections and plumbing facilities. It takes 1 working day to complete.
3. Driving sheet piles is able to prevent any soil collapse and water
seepage. No additional support system is needed.
4. Before laying down the concrete of the mat foundation and the inverse
slab, the formwork and reinforcement bar is erect and placed within 12
days. After the concrete is poured, it is left for dry for 7 days. The
formwork of the foundation will take 8 days to dismantle.
5. The formwork of heavy wall will be dismantle within 2 days after the
concrete is cure.
* Assumption is highlighted in PURPLE in Gantt Chart
ID Task Mode Activity
ID
Task Name Duration
1 0 Water Pump Station 279 days
2 1000 Apply for Permits 27 days
3 1001 Secure city permit 5 days
4 1002 Secure building permit 21 days
5 1010 Site Work 6 days
6 1011 Clear and grub site 1 day
7 1012 Install temporary electrical connections 5 days
8 1013 Install plumbing utilities 5 days
9 1020 Geotechnical Investigation 4 days
10 1021 Subsurface exploration 4 days
11 2000 Piling 23 days
12 2001 Mobilize equipment and personnel 5 days
13 2002 Driving sheet piles 18 days
14 2010 Excavation 90 days
15 2011 Excavation & Tieback 90 days
16 2020 Foundation 68 days
17 2021 Formwork and reinforcement bar mat
foundation and inverse slab
10 days
18 2022 Pour Concrete mat foundation and inverse
slab
43 days
19 2023 Cure mat foundation and inverse slab 7 days
20 2024 Dismantle formwork 8 days
21 2030 Heavy wall (EL72 ro EL95) 28 days
22 2031 Construct wet well floor 4 days
23 2032 Formwork and Reinforcing stell Placement
(FRP) of heavy wall
5 days
24 2033 Pour concrete for heavy wall 8 days
25 2034 Cure heavy wall 7 days
26 2035 Dismantle formwork 2 days
27 2036 PVC waterproofing membrane 3 days
28 2037 Backfill up to EL95 with soil 3 days
B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B
March April May June July August September October November December January February March April
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Critical
Critical Split
Progress
Manual Progress
Page 1
Project: 0319802 PANG KAI YU
Date: Tue 27/11/18
Secure building permit
Start: Tue 19/3/19ID: 4
Finish: Tue 16/4/19Dur: 21 days
Res:
Install plumbing utilities
Start: Tue 12/3/19ID: 8
Finish: Mon 18/3/19Dur: 5 days
Res:
Subsurface exploration
Start: Wed 17/4/19ID: 10
Finish: Mon 22/4/19Dur: 4 days
Res:
Mobilize equipment and personnel
Start: Mon 17/6/19ID: 12
Finish: Fri 21/6/19 Dur: 5 days
Res:
Driving sheet piles
Start: Mon 24/6/19ID: 13
Finish: Wed 17/7/19Dur: 18 days
Res:
Excavation & Tieback
Start: Thu 18/7/19ID: 15
Finish: Wed 20/11/19Dur: 90 days
Res:
Formwork and reinforcement bar mat foundation and inverse slab
Start: Thu 21/11/19ID: 17
Finish: Wed 4/12/19Dur: 10 days
Res:
Pour Concrete mat foundation and inverse slab
Start: Thu 5/12/19ID: 18
Finish: Mon 3/2/20Dur: 43 days
Res:
Cure mat foundation and inverse slab
Start: Tue 4/2/20 ID: 19
Finish: Wed 12/2/20Dur: 7 days
Res:
Dismantle formwork
Start: Thu 13/2/20ID: 20
Finish: Mon 24/2/20Dur: 8 days
Res:
Construct wet well floor
Start: Tue 25/2/20ID: 22
Finish: Fri 28/2/20 Dur: 4 days
Res:
Pour concrete for heavy wall
Start: Tue 3/3/20 ID: 24
Finish: Thu 12/3/20Dur: 8 days
Res:
Cure heavy wall
Start: Fri 13/3/20 ID: 25
Finish: Mon 23/3/20Dur: 7 days
Res:
Dismantle formwork
Start: Tue 24/3/20ID: 26
Finish: Wed 25/3/20Dur: 2 days
Res:
PVC waterproofing membrane
Start: Thu 26/3/20ID: 27
Finish: Mon 30/3/20Dur: 3 days
Res:
Backfill up to EL95 with soil
Start: Tue 31/3/20ID: 28
Finish: Thu 2/4/20 Dur: 3 days
Res:
Formwork and Reinforcing stell Placement (FRP) of heavy wall
Start: Tue 25/2/20ID: 23
Finish: Mon 2/3/20Dur: 5 days
Res:
Install temporary electrical connections
Start: Tue 12/3/19ID: 7
Finish: Mon 18/3/19Dur: 5 days
Res:
Clear and grub site
Start: Mon 11/3/19ID: 6
Finish: Mon 11/3/19Dur: 1 day
Res:
Secure city permit
Start: Mon 11/3/19ID: 3
Finish: Fri 15/3/19 Dur: 5 days
Res:
Page 1
Critical Noncritical Critical Milestone Milestone Critical Summary Summary Critical Inserted Inserted Critical Marked Marked Critical External External Project Summary Highlighted Critical Highlighted Noncritical
Page 2
Project: 0319802 PANG KAI YU
Date: Tue 27/11/18

Assignment 1 - Water Pump Station

  • 1.
    SCHOOL OF ARCHITECTURE,BUILDING AND DESIGN BACHELOR OF QUANTITY SURVEYING (HONOURS) MGT60704 PROJECT MANAGEMENT AUGUST 2018 SEMESTER INDIVIDUAL ASSIGNMENT NAME : PANG KAI YUN STUDENT ID : 0319802 LECTURER : MR LEONG BOON TIK SUBMISSION DATE : 27 NOVEMBER 2018
  • 2.
    Assumption: 1. Working daysexcluding Saturday and Sunday. 2. Clear and grub the site before installing temporary electrical connections and plumbing facilities. It takes 1 working day to complete. 3. Driving sheet piles is able to prevent any soil collapse and water seepage. No additional support system is needed. 4. Before laying down the concrete of the mat foundation and the inverse slab, the formwork and reinforcement bar is erect and placed within 12 days. After the concrete is poured, it is left for dry for 7 days. The formwork of the foundation will take 8 days to dismantle. 5. The formwork of heavy wall will be dismantle within 2 days after the concrete is cure. * Assumption is highlighted in PURPLE in Gantt Chart
  • 3.
    ID Task ModeActivity ID Task Name Duration 1 0 Water Pump Station 279 days 2 1000 Apply for Permits 27 days 3 1001 Secure city permit 5 days 4 1002 Secure building permit 21 days 5 1010 Site Work 6 days 6 1011 Clear and grub site 1 day 7 1012 Install temporary electrical connections 5 days 8 1013 Install plumbing utilities 5 days 9 1020 Geotechnical Investigation 4 days 10 1021 Subsurface exploration 4 days 11 2000 Piling 23 days 12 2001 Mobilize equipment and personnel 5 days 13 2002 Driving sheet piles 18 days 14 2010 Excavation 90 days 15 2011 Excavation & Tieback 90 days 16 2020 Foundation 68 days 17 2021 Formwork and reinforcement bar mat foundation and inverse slab 10 days 18 2022 Pour Concrete mat foundation and inverse slab 43 days 19 2023 Cure mat foundation and inverse slab 7 days 20 2024 Dismantle formwork 8 days 21 2030 Heavy wall (EL72 ro EL95) 28 days 22 2031 Construct wet well floor 4 days 23 2032 Formwork and Reinforcing stell Placement (FRP) of heavy wall 5 days 24 2033 Pour concrete for heavy wall 8 days 25 2034 Cure heavy wall 7 days 26 2035 Dismantle formwork 2 days 27 2036 PVC waterproofing membrane 3 days 28 2037 Backfill up to EL95 with soil 3 days B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B March April May June July August September October November December January February March April Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Critical Critical Split Progress Manual Progress Page 1 Project: 0319802 PANG KAI YU Date: Tue 27/11/18
  • 4.
    Secure building permit Start:Tue 19/3/19ID: 4 Finish: Tue 16/4/19Dur: 21 days Res: Install plumbing utilities Start: Tue 12/3/19ID: 8 Finish: Mon 18/3/19Dur: 5 days Res: Subsurface exploration Start: Wed 17/4/19ID: 10 Finish: Mon 22/4/19Dur: 4 days Res: Mobilize equipment and personnel Start: Mon 17/6/19ID: 12 Finish: Fri 21/6/19 Dur: 5 days Res: Driving sheet piles Start: Mon 24/6/19ID: 13 Finish: Wed 17/7/19Dur: 18 days Res: Excavation & Tieback Start: Thu 18/7/19ID: 15 Finish: Wed 20/11/19Dur: 90 days Res: Formwork and reinforcement bar mat foundation and inverse slab Start: Thu 21/11/19ID: 17 Finish: Wed 4/12/19Dur: 10 days Res: Pour Concrete mat foundation and inverse slab Start: Thu 5/12/19ID: 18 Finish: Mon 3/2/20Dur: 43 days Res: Cure mat foundation and inverse slab Start: Tue 4/2/20 ID: 19 Finish: Wed 12/2/20Dur: 7 days Res: Dismantle formwork Start: Thu 13/2/20ID: 20 Finish: Mon 24/2/20Dur: 8 days Res: Construct wet well floor Start: Tue 25/2/20ID: 22 Finish: Fri 28/2/20 Dur: 4 days Res: Pour concrete for heavy wall Start: Tue 3/3/20 ID: 24 Finish: Thu 12/3/20Dur: 8 days Res: Cure heavy wall Start: Fri 13/3/20 ID: 25 Finish: Mon 23/3/20Dur: 7 days Res: Dismantle formwork Start: Tue 24/3/20ID: 26 Finish: Wed 25/3/20Dur: 2 days Res: PVC waterproofing membrane Start: Thu 26/3/20ID: 27 Finish: Mon 30/3/20Dur: 3 days Res: Backfill up to EL95 with soil Start: Tue 31/3/20ID: 28 Finish: Thu 2/4/20 Dur: 3 days Res: Formwork and Reinforcing stell Placement (FRP) of heavy wall Start: Tue 25/2/20ID: 23 Finish: Mon 2/3/20Dur: 5 days Res: Install temporary electrical connections Start: Tue 12/3/19ID: 7 Finish: Mon 18/3/19Dur: 5 days Res: Clear and grub site Start: Mon 11/3/19ID: 6 Finish: Mon 11/3/19Dur: 1 day Res: Secure city permit Start: Mon 11/3/19ID: 3 Finish: Fri 15/3/19 Dur: 5 days Res: Page 1
  • 5.
    Critical Noncritical CriticalMilestone Milestone Critical Summary Summary Critical Inserted Inserted Critical Marked Marked Critical External External Project Summary Highlighted Critical Highlighted Noncritical Page 2 Project: 0319802 PANG KAI YU Date: Tue 27/11/18