SlideShare a Scribd company logo
TAJUK
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
PWD 203A Standard Form of Contract (Ed.1983)

This form of contract contain no expressed provision that allows the Contractor to
suspend the works if his payment was unduly delayed or he is not getting his
payment at all.

In the PWD203A Form of Contract (2007), it is stipulated that the period for
honouring the certificate is 30 days from the date of the issuance of the certificate.
Clause 30.1 of the PAM Form of Contract (2006) stated that the period of honouring
certificate is within 21 days after the issuance of the certificate. Any payment made
later than the stipulated time frame can be considered as late or delayed payment

PAM Form of Contract 1998

There is no express provision that permits the Contractor to suspend his work when
he is not paid or his payment was not forthcoming in due time after receiving the
Interim Certificate. Clause 25(1) (ii) and Clause 23.4 state that the Contractor is to
proceed regularly and diligently and he is to use his best endeavours to prevent
delay. The clauses clearly demand the Contractor to show a good performance and
continue with the work to prevent disruption to the progress of the project.

PAM Form of Contract 2006

But the new PAM 2006 contains provision that give the Contractor to suspend the
progress of work if the Contractor is faced with problem of delayed or non payment
by the Employer. It is clearly stated in clause 30.7. But it requires the Contractor to
give a written a notice to Employer with reason to suspend the works until the
Employer has paid the amount due to the Contractor
THE DIFFERENCE BETWEEN JKR/PWD AND PAM CONTRACT

                  JKR/PWD                                              PAM

- Standard form of contract for government and   - Standard form of contract for private sector
public sector project.                           and traditional general contract

- JKR/PWD covered all building and engineering   - PAM covered building work only.
work.
                                                 - PAM contract not covered
- Standard form for JKR/PWD are :                    I. Engineering construction contract (other
    I.  203 (Rev 10/83) – without quantities            than building
   II.  203A (Rev 10/83) – with quantities          II. Package deal / Turnkey
  III.  203N (Rev 10/83) – for NSC                 III. Management type
                                                   IV.  Domestic subcontract
  IV.   203P (Rev 10/83) – for nominated
                                                    V.  Serial contract
        suppliers                                  VI.  Periodic /Term contract
   V.   PWP Form DB/T (2000 Edn) For Design       VII.  Continuation control
        And Build Turnkey Contracts              VIII.  Other miscellaneous contract

     Miscellaneous :                             - Standard form for PAM :
   I.   CIDB Form for building contracts 2000      (Building Works)
        Edn                                           I.  PAM 98 – with quantities
  II.   Modified JKR/PWD Forms, eg LPK, MHA          II.  PAM 98 – without quantities
        etc                                         III.  PAM NSC 98
ISSUES PERIOD OF   ISSUE OF                PERIOD OF   ISSUING             AMOUNT
          INTERIM     INTERIM                 HONOURING PERSON                TO BE
          CERTIFICATE CERTIFICATE             THE                             PAID
                      OF SITE                 CERTIFICATE
                      VALUATION

CONTRACT
FORM
PWD        One month        14 days after     30 days from     Superintending Value of
           [Clause 47(a)]   site              the              Officer (S.O)  Work
203A                        valuation         date of the                     Done +
                            [Clause 47 (b)]   issuance                        90%
                                              of the Interim                  Material On
                                              Certificate                     Site
                                              [Clause 47(d)]

PAM        One Month        Upon the          14 days from     Architect      Value of
           [Clause 30.2)    receipt of        the date                        Work Done
1998                        Contractors       of the                          + 90%
                            details           issuance of                     Material On
                            and particulars   Interim                         Site
                            [Clause 30.2]     Certificate
                                              [Clause 30.2]

More Related Content

What's hot

Eca presentation-compile
Eca presentation-compileEca presentation-compile
Eca presentation-compile
Timun Loh
 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment
마 이환
 
Assignment - Preliminary Cost Appraisal
Assignment - Preliminary Cost AppraisalAssignment - Preliminary Cost Appraisal
Assignment - Preliminary Cost Appraisal
Kai Yun Pang
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006
Melvin Lim
 
ECA form
ECA formECA form
ECA form
Arissa Loh
 
Sectional completion and partial possession by employer PP2 Coursework 1
Sectional completion and partial possession by employer PP2 Coursework 1Sectional completion and partial possession by employer PP2 Coursework 1
Sectional completion and partial possession by employer PP2 Coursework 1
Arissa Loh
 
Traditional procurement method
Traditional procurement methodTraditional procurement method
Traditional procurement method
hiewliming
 
Payments in the construction industry
Payments in the construction industryPayments in the construction industry
Payments in the construction industry
Kheng Hoe Advocates
 
Elemental Cost Analysis
Elemental Cost AnalysisElemental Cost Analysis
Elemental Cost Analysis
Pang Khai Shuen
 
Smm2 second edition
Smm2 second editionSmm2 second edition
Smm2 second editionBt Lee
 
Pwd 203 a rev2007
Pwd 203 a rev2007Pwd 203 a rev2007
Pwd 203 a rev2007shimz2287
 
Pp1 seminar
Pp1 seminarPp1 seminar
Pp1 seminar
wendyteosy
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
ahmong4
 
Provisional sum prime cost sum
Provisional sum  prime cost sumProvisional sum  prime cost sum
Provisional sum prime cost sum
Est
 
Wblff (1)
Wblff (1)Wblff (1)
Wblff (1)
ahmong4
 
Jenis kontraktor
Jenis kontraktorJenis kontraktor
Jenis kontraktor
sofyan fatimi
 
How CIDB could control and manage the construction contractors towards implem...
How CIDB could control and manage the construction contractors towards implem...How CIDB could control and manage the construction contractors towards implem...
How CIDB could control and manage the construction contractors towards implem...
N.AIZA HASSAN
 
Construction Law Assignment BQS Taylor's University
Construction Law Assignment BQS Taylor's UniversityConstruction Law Assignment BQS Taylor's University
Construction Law Assignment BQS Taylor's University
Pang Khai Shuen
 

What's hot (20)

Site Possession
Site PossessionSite Possession
Site Possession
 
Eca presentation-compile
Eca presentation-compileEca presentation-compile
Eca presentation-compile
 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment
 
Assignment - Preliminary Cost Appraisal
Assignment - Preliminary Cost AppraisalAssignment - Preliminary Cost Appraisal
Assignment - Preliminary Cost Appraisal
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006
 
ECA form
ECA formECA form
ECA form
 
Sectional completion and partial possession by employer PP2 Coursework 1
Sectional completion and partial possession by employer PP2 Coursework 1Sectional completion and partial possession by employer PP2 Coursework 1
Sectional completion and partial possession by employer PP2 Coursework 1
 
Traditional procurement method
Traditional procurement methodTraditional procurement method
Traditional procurement method
 
Payments in the construction industry
Payments in the construction industryPayments in the construction industry
Payments in the construction industry
 
Elemental Cost Analysis
Elemental Cost AnalysisElemental Cost Analysis
Elemental Cost Analysis
 
Pengurusan kontrak
Pengurusan kontrakPengurusan kontrak
Pengurusan kontrak
 
Smm2 second edition
Smm2 second editionSmm2 second edition
Smm2 second edition
 
Pwd 203 a rev2007
Pwd 203 a rev2007Pwd 203 a rev2007
Pwd 203 a rev2007
 
Pp1 seminar
Pp1 seminarPp1 seminar
Pp1 seminar
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 
Provisional sum prime cost sum
Provisional sum  prime cost sumProvisional sum  prime cost sum
Provisional sum prime cost sum
 
Wblff (1)
Wblff (1)Wblff (1)
Wblff (1)
 
Jenis kontraktor
Jenis kontraktorJenis kontraktor
Jenis kontraktor
 
How CIDB could control and manage the construction contractors towards implem...
How CIDB could control and manage the construction contractors towards implem...How CIDB could control and manage the construction contractors towards implem...
How CIDB could control and manage the construction contractors towards implem...
 
Construction Law Assignment BQS Taylor's University
Construction Law Assignment BQS Taylor's UniversityConstruction Law Assignment BQS Taylor's University
Construction Law Assignment BQS Taylor's University
 

Similar to DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM

MSP
MSPMSP
Cbb512 examination november_2011
Cbb512 examination november_2011Cbb512 examination november_2011
Cbb512 examination november_2011Maatla Moadi
 
GENERAL CONDITIONS FOR CONTRACTS OF CIVIL ENGINEERING WORKS
GENERAL CONDITIONS  FOR  CONTRACTS OF CIVIL ENGINEERING WORKS GENERAL CONDITIONS  FOR  CONTRACTS OF CIVIL ENGINEERING WORKS
GENERAL CONDITIONS FOR CONTRACTS OF CIVIL ENGINEERING WORKS
Bahzad5
 
Psscoc 2008 db contract
Psscoc 2008 db contractPsscoc 2008 db contract
Psscoc 2008 db contract
Vance Ang
 
Suspension and Termination by Contractor Presentation.pptx
Suspension and Termination by Contractor Presentation.pptxSuspension and Termination by Contractor Presentation.pptx
Suspension and Termination by Contractor Presentation.pptx
NathannielGonzales1
 
Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)
Yee Len Wan
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
Vj NiroSh
 
CONDITIONS OF CONTRACT FOR WORKS OF CIVIL ENGINEERING CONSTRUCTION
CONDITIONS OF CONTRACT  FOR WORKS OF CIVIL  ENGINEERING CONSTRUCTIONCONDITIONS OF CONTRACT  FOR WORKS OF CIVIL  ENGINEERING CONSTRUCTION
CONDITIONS OF CONTRACT FOR WORKS OF CIVIL ENGINEERING CONSTRUCTION
Bahzad5
 
5. international standard contract for construction
5. international standard contract for construction5. international standard contract for construction
5. international standard contract for construction
Hyoyoung Kim
 
(Interior const) instruction to bidders
(Interior const) instruction to bidders(Interior const) instruction to bidders
(Interior const) instruction to bidderspiyush1266
 
Pp2 group assignment
Pp2 group assignmentPp2 group assignment
Pp2 group assignment
lohwenjun
 
07 cl-assignment-syafiq-qy-macy-huiyong-deric
07 cl-assignment-syafiq-qy-macy-huiyong-deric07 cl-assignment-syafiq-qy-macy-huiyong-deric
07 cl-assignment-syafiq-qy-macy-huiyong-deric
Syafiq Zariful
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-final
ashleyyeap
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-final
ashleyyeap
 
Ppt by mr pr subramaniam
Ppt by  mr pr subramaniamPpt by  mr pr subramaniam
Ppt by mr pr subramaniammcci175
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7
Farah Sham
 
TE&A's Newsletter, April, 2019
TE&A's Newsletter, April, 2019TE&A's Newsletter, April, 2019
TE&A's Newsletter, April, 2019
Cerasela Angelescu
 
FIDIC Pakistan laws of construction 1992.pdf
FIDIC Pakistan laws of construction 1992.pdfFIDIC Pakistan laws of construction 1992.pdf
FIDIC Pakistan laws of construction 1992.pdf
MohammedBilal554495
 

Similar to DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM (20)

MSP
MSPMSP
MSP
 
Cbb512 examination november_2011
Cbb512 examination november_2011Cbb512 examination november_2011
Cbb512 examination november_2011
 
GENERAL CONDITIONS FOR CONTRACTS OF CIVIL ENGINEERING WORKS
GENERAL CONDITIONS  FOR  CONTRACTS OF CIVIL ENGINEERING WORKS GENERAL CONDITIONS  FOR  CONTRACTS OF CIVIL ENGINEERING WORKS
GENERAL CONDITIONS FOR CONTRACTS OF CIVIL ENGINEERING WORKS
 
Psscoc 2008 db contract
Psscoc 2008 db contractPsscoc 2008 db contract
Psscoc 2008 db contract
 
Cm mitemrate ver270206
Cm mitemrate ver270206Cm mitemrate ver270206
Cm mitemrate ver270206
 
Suspension and Termination by Contractor Presentation.pptx
Suspension and Termination by Contractor Presentation.pptxSuspension and Termination by Contractor Presentation.pptx
Suspension and Termination by Contractor Presentation.pptx
 
Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
 
CONDITIONS OF CONTRACT FOR WORKS OF CIVIL ENGINEERING CONSTRUCTION
CONDITIONS OF CONTRACT  FOR WORKS OF CIVIL  ENGINEERING CONSTRUCTIONCONDITIONS OF CONTRACT  FOR WORKS OF CIVIL  ENGINEERING CONSTRUCTION
CONDITIONS OF CONTRACT FOR WORKS OF CIVIL ENGINEERING CONSTRUCTION
 
Cl report final
Cl report finalCl report final
Cl report final
 
5. international standard contract for construction
5. international standard contract for construction5. international standard contract for construction
5. international standard contract for construction
 
(Interior const) instruction to bidders
(Interior const) instruction to bidders(Interior const) instruction to bidders
(Interior const) instruction to bidders
 
Pp2 group assignment
Pp2 group assignmentPp2 group assignment
Pp2 group assignment
 
07 cl-assignment-syafiq-qy-macy-huiyong-deric
07 cl-assignment-syafiq-qy-macy-huiyong-deric07 cl-assignment-syafiq-qy-macy-huiyong-deric
07 cl-assignment-syafiq-qy-macy-huiyong-deric
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-final
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-final
 
Ppt by mr pr subramaniam
Ppt by  mr pr subramaniamPpt by  mr pr subramaniam
Ppt by mr pr subramaniam
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7
 
TE&A's Newsletter, April, 2019
TE&A's Newsletter, April, 2019TE&A's Newsletter, April, 2019
TE&A's Newsletter, April, 2019
 
FIDIC Pakistan laws of construction 1992.pdf
FIDIC Pakistan laws of construction 1992.pdfFIDIC Pakistan laws of construction 1992.pdf
FIDIC Pakistan laws of construction 1992.pdf
 

Recently uploaded

CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptxCADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
fakeloginn69
 
Attending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learnersAttending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learners
Erika906060
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
Cynthia Clay
 
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
BBPMedia1
 
Exploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social DreamingExploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social Dreaming
Nicola Wreford-Howard
 
Global Interconnection Group Joint Venture[960] (1).pdf
Global Interconnection Group Joint Venture[960] (1).pdfGlobal Interconnection Group Joint Venture[960] (1).pdf
Global Interconnection Group Joint Venture[960] (1).pdf
Henry Tapper
 
Project File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdfProject File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdf
RajPriye
 
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-indiafalcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
Falcon Invoice Discounting
 
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdfMeas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
dylandmeas
 
Lookback Analysis
Lookback AnalysisLookback Analysis
Lookback Analysis
Safe PaaS
 
Brand Analysis for an artist named Struan
Brand Analysis for an artist named StruanBrand Analysis for an artist named Struan
Brand Analysis for an artist named Struan
sarahvanessa51503
 
Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...
dylandmeas
 
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n PrintAffordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Navpack & Print
 
Improving profitability for small business
Improving profitability for small businessImproving profitability for small business
Improving profitability for small business
Ben Wann
 
BeMetals Presentation_May_22_2024 .pdf
BeMetals Presentation_May_22_2024   .pdfBeMetals Presentation_May_22_2024   .pdf
BeMetals Presentation_May_22_2024 .pdf
DerekIwanaka1
 
5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer
ofm712785
 
Buy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star ReviewsBuy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star Reviews
usawebmarket
 
3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx
tanyjahb
 
Business Valuation Principles for Entrepreneurs
Business Valuation Principles for EntrepreneursBusiness Valuation Principles for Entrepreneurs
Business Valuation Principles for Entrepreneurs
Ben Wann
 
Memorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.pptMemorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.ppt
seri bangash
 

Recently uploaded (20)

CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptxCADAVER AS OUR FIRST TEACHER anatomt in your.pptx
CADAVER AS OUR FIRST TEACHER anatomt in your.pptx
 
Attending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learnersAttending a job Interview for B1 and B2 Englsih learners
Attending a job Interview for B1 and B2 Englsih learners
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
RMD24 | Debunking the non-endemic revenue myth Marvin Vacquier Droop | First ...
 
Exploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social DreamingExploring Patterns of Connection with Social Dreaming
Exploring Patterns of Connection with Social Dreaming
 
Global Interconnection Group Joint Venture[960] (1).pdf
Global Interconnection Group Joint Venture[960] (1).pdfGlobal Interconnection Group Joint Venture[960] (1).pdf
Global Interconnection Group Joint Venture[960] (1).pdf
 
Project File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdfProject File Report BBA 6th semester.pdf
Project File Report BBA 6th semester.pdf
 
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-indiafalcon-invoice-discounting-a-premier-platform-for-investors-in-india
falcon-invoice-discounting-a-premier-platform-for-investors-in-india
 
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdfMeas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
Meas_Dylan_DMBS_PB1_2024-05XX_Revised.pdf
 
Lookback Analysis
Lookback AnalysisLookback Analysis
Lookback Analysis
 
Brand Analysis for an artist named Struan
Brand Analysis for an artist named StruanBrand Analysis for an artist named Struan
Brand Analysis for an artist named Struan
 
Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...Discover the innovative and creative projects that highlight my journey throu...
Discover the innovative and creative projects that highlight my journey throu...
 
Affordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n PrintAffordable Stationery Printing Services in Jaipur | Navpack n Print
Affordable Stationery Printing Services in Jaipur | Navpack n Print
 
Improving profitability for small business
Improving profitability for small businessImproving profitability for small business
Improving profitability for small business
 
BeMetals Presentation_May_22_2024 .pdf
BeMetals Presentation_May_22_2024   .pdfBeMetals Presentation_May_22_2024   .pdf
BeMetals Presentation_May_22_2024 .pdf
 
5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer5 Things You Need To Know Before Hiring a Videographer
5 Things You Need To Know Before Hiring a Videographer
 
Buy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star ReviewsBuy Verified PayPal Account | Buy Google 5 Star Reviews
Buy Verified PayPal Account | Buy Google 5 Star Reviews
 
3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx3.0 Project 2_ Developing My Brand Identity Kit.pptx
3.0 Project 2_ Developing My Brand Identity Kit.pptx
 
Business Valuation Principles for Entrepreneurs
Business Valuation Principles for EntrepreneursBusiness Valuation Principles for Entrepreneurs
Business Valuation Principles for Entrepreneurs
 
Memorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.pptMemorandum Of Association Constitution of Company.ppt
Memorandum Of Association Constitution of Company.ppt
 

DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM

  • 1. TAJUK DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
  • 2. PWD 203A Standard Form of Contract (Ed.1983) This form of contract contain no expressed provision that allows the Contractor to suspend the works if his payment was unduly delayed or he is not getting his payment at all. In the PWD203A Form of Contract (2007), it is stipulated that the period for honouring the certificate is 30 days from the date of the issuance of the certificate. Clause 30.1 of the PAM Form of Contract (2006) stated that the period of honouring certificate is within 21 days after the issuance of the certificate. Any payment made later than the stipulated time frame can be considered as late or delayed payment PAM Form of Contract 1998 There is no express provision that permits the Contractor to suspend his work when he is not paid or his payment was not forthcoming in due time after receiving the Interim Certificate. Clause 25(1) (ii) and Clause 23.4 state that the Contractor is to proceed regularly and diligently and he is to use his best endeavours to prevent delay. The clauses clearly demand the Contractor to show a good performance and continue with the work to prevent disruption to the progress of the project. PAM Form of Contract 2006 But the new PAM 2006 contains provision that give the Contractor to suspend the progress of work if the Contractor is faced with problem of delayed or non payment by the Employer. It is clearly stated in clause 30.7. But it requires the Contractor to give a written a notice to Employer with reason to suspend the works until the Employer has paid the amount due to the Contractor
  • 3. THE DIFFERENCE BETWEEN JKR/PWD AND PAM CONTRACT JKR/PWD PAM - Standard form of contract for government and - Standard form of contract for private sector public sector project. and traditional general contract - JKR/PWD covered all building and engineering - PAM covered building work only. work. - PAM contract not covered - Standard form for JKR/PWD are : I. Engineering construction contract (other I. 203 (Rev 10/83) – without quantities than building II. 203A (Rev 10/83) – with quantities II. Package deal / Turnkey III. 203N (Rev 10/83) – for NSC III. Management type IV. Domestic subcontract IV. 203P (Rev 10/83) – for nominated V. Serial contract suppliers VI. Periodic /Term contract V. PWP Form DB/T (2000 Edn) For Design VII. Continuation control And Build Turnkey Contracts VIII. Other miscellaneous contract Miscellaneous : - Standard form for PAM : I. CIDB Form for building contracts 2000 (Building Works) Edn I. PAM 98 – with quantities II. Modified JKR/PWD Forms, eg LPK, MHA II. PAM 98 – without quantities etc III. PAM NSC 98
  • 4. ISSUES PERIOD OF ISSUE OF PERIOD OF ISSUING AMOUNT INTERIM INTERIM HONOURING PERSON TO BE CERTIFICATE CERTIFICATE THE PAID OF SITE CERTIFICATE VALUATION CONTRACT FORM PWD One month 14 days after 30 days from Superintending Value of [Clause 47(a)] site the Officer (S.O) Work 203A valuation date of the Done + [Clause 47 (b)] issuance 90% of the Interim Material On Certificate Site [Clause 47(d)] PAM One Month Upon the 14 days from Architect Value of [Clause 30.2) receipt of the date Work Done 1998 Contractors of the + 90% details issuance of Material On and particulars Interim Site [Clause 30.2] Certificate [Clause 30.2]