SlideShare a Scribd company logo
DESIGN PROJECT
VII SEMESTER
SYNOPSIS
 INTRODUCTION
 PLANNING OF PROJECT
 AREA OF PROJECT
 DRAFTING
 ANALYSIS & DESIGNING
 ESTIMATION
INTRODUCTION
 This project mainly concerns on planning, analysis
& designing of framed structure
1) Planning of (G+2) hotel.
2) Analysis of the building by (STAAD PRO)
3) Detailed design by limit state method
4) Preparation of abstract estimation of the building
PLANNING OF PROJECT
 Selection of area and orientation of the building.
 Duration of time.
 Sequence of events.
 Requirements & General aspects.
 Sanitary installation.
 Water supply arrangement.
 Drainage & electrical installation.
AREA OF PROJECT
The project is proposed near pollachi
 Total area of site is 20000 sq.ft
 Total building area is 12500 sq.ft
 Plinth area is 10500 sq.ft
 Parking and Gardening area 7500 sq.ft
DRAFTING
 The plan is draft using auto cad 2010
 NBC-2005,IS 456,SP-16 are used in drafting and
designing
 Dining Hall ,Conference Hall and Kitchen Provided
separately on Ground Floor
PLAN VIEWS
 GROUND FLOOR
 FIRST FLOOR
 SECOND FLOOR
 ELEVATION
NO OF ROOMS
SUITE ROOM DOUBLE ROOM SINGLE ROOM
GROUND FLOOR 1 2 3
FIRST FLOOR 2 6 3
SECOND FLOOR NIL 8 3
 Analysis of beam and column is designed by using
STAAD.Pro V8i Software
 Our Structure contains
Total number of nodes : 858
Total number of members : 1431
Total number of supports : 84
ANALYSIS & DESIGNING
STRUCTURE & SUPPORT VIEW
DESIGN OF BEAM
BAR DETAILS FOR BEAM
 The size of the beam is = 300*450
 The size of the bar is used in the beam = 12mm
 Number of the rod is required in beam = 8
DESIGN OF COLUMN
BAR DETAILS FOR COLUMN
 The size of the column is = 300*450
 The size of the bar is used in the
column=12mm
 Number of bar required in the column = 8
DESIGN OF SLAB
DETAILS OF SLAB
 One Way Slab With Size 2500x6725 mm
 For the main reinforcement 12mm diameter
rods @ 300mm c/c
 For the distributors 8mm diameter rods @
300mm c/c
DESIGN OF FOOTING
 Isolated Rectangular Footing
 Size of Footing 1.7 x 2.5m
 For the long span 16mm diameter rods @ 170mm
c/c
 For the short span 12mm diameter rods @
210mm c/c
SPECIFICATION OF STAIR CASE
 The stair case is provided per NBC – 2005
 Staircase width 1500mm
 Tread width 300mm
 Riser height 150mm
RAMP DESIGN
 Gradient of ramp is 1 in 12
 Handrails at 1000mm high
 Width of ramp is 1200mm
ESTIMATION
 Excavation & filling cost =5,92,500
 Flooring & Brick Work cost =82,87,500
 Concrete Work cost =1,41,58,700
 Floor Finishing Cost =1,26,22,000
 Miscellaneous &White Washing =39,25,000
 Other Work =86,09,140
 Total Project Cost =4,81,94,840
CONCLUSION
 This project work has offered us to learn and
expressing our ideas on the topics like
Planning, Analysis, Designing and
Estimating.
 Planning, Analysis and design of the hotel
building was completed.
THANK YOU

More Related Content

Similar to A PPT.pptx

Residential cum commercial.pptx
Residential cum commercial.pptxResidential cum commercial.pptx
Residential cum commercial.pptx
RajeshKumar25548
 
MAHI PPT.pptx
MAHI PPT.pptxMAHI PPT.pptx
MAHI PPT.pptx
RajeshKumar25548
 
sandy batch.pptx
sandy batch.pptxsandy batch.pptx
sandy batch.pptx
RajeshKumar25548
 
deva batch FINAL PPT.pptx
deva batch FINAL PPT.pptxdeva batch FINAL PPT.pptx
deva batch FINAL PPT.pptx
RajeshKumar25548
 
final praveen.pptx
final praveen.pptxfinal praveen.pptx
final praveen.pptx
RajeshKumar25548
 
Design of multistorey building
Design of multistorey buildingDesign of multistorey building
Design of multistorey building
Sivaji Djpk
 
Final report 85,91,109
Final report 85,91,109Final report 85,91,109
Final report 85,91,109
PavithranKarthickeya
 
LiamBaines_Construction_FACADES
LiamBaines_Construction_FACADESLiamBaines_Construction_FACADES
LiamBaines_Construction_FACADESLiam Baines
 
Madhu PPT.pptx
Madhu PPT.pptxMadhu PPT.pptx
Madhu PPT.pptx
RajeshKumar25548
 
Computer aided analysis and design of multi story building
Computer aided analysis and design of multi story buildingComputer aided analysis and design of multi story building
Computer aided analysis and design of multi story building
paras6904
 
2nd batch.pptx
2nd batch.pptx2nd batch.pptx
2nd batch.pptx
RajeshKumar25548
 
G+3 APARTMENT BUILDING PROJECT REPORT
G+3 APARTMENT BUILDING  PROJECT  REPORTG+3 APARTMENT BUILDING  PROJECT  REPORT
G+3 APARTMENT BUILDING PROJECT REPORT
Fresher Thinking
 
Design and planning of hostel building by vijayan
Design and planning of hostel building by vijayanDesign and planning of hostel building by vijayan
Design and planning of hostel building by vijayan
Vijayan S
 
Project 3 - Costing
Project 3 - CostingProject 3 - Costing
Project 3 - Costing
Kai Yun Pang
 
SELENDRA CONDOMINIUM CONSTRUCTION ORIENTATION
SELENDRA CONDOMINIUM CONSTRUCTION ORIENTATIONSELENDRA CONDOMINIUM CONSTRUCTION ORIENTATION
SELENDRA CONDOMINIUM CONSTRUCTION ORIENTATION
SELENDRA CONDOMINIUM BAGUIO CITY
 
Building technology 1 Project 1 Drawing compilation
Building technology 1 Project 1 Drawing compilationBuilding technology 1 Project 1 Drawing compilation
Building technology 1 Project 1 Drawing compilation
Tan Jaden
 
ECA Workshop - ECA Form
ECA Workshop - ECA FormECA Workshop - ECA Form
ECA Workshop - ECA Form
Kai Yun Pang
 
Long Span Building Construction
Long Span Building ConstructionLong Span Building Construction
Long Span Building Construction
Asz My
 
Design of Flyover Transverse Vertically by using Hydraulic Jack
Design of Flyover Transverse Vertically by using Hydraulic JackDesign of Flyover Transverse Vertically by using Hydraulic Jack
Design of Flyover Transverse Vertically by using Hydraulic Jack
IRJET Journal
 

Similar to A PPT.pptx (20)

Residential cum commercial.pptx
Residential cum commercial.pptxResidential cum commercial.pptx
Residential cum commercial.pptx
 
MAHI PPT.pptx
MAHI PPT.pptxMAHI PPT.pptx
MAHI PPT.pptx
 
sandy batch.pptx
sandy batch.pptxsandy batch.pptx
sandy batch.pptx
 
deva batch FINAL PPT.pptx
deva batch FINAL PPT.pptxdeva batch FINAL PPT.pptx
deva batch FINAL PPT.pptx
 
final praveen.pptx
final praveen.pptxfinal praveen.pptx
final praveen.pptx
 
Design of multistorey building
Design of multistorey buildingDesign of multistorey building
Design of multistorey building
 
Final report 85,91,109
Final report 85,91,109Final report 85,91,109
Final report 85,91,109
 
LiamBaines_Construction_FACADES
LiamBaines_Construction_FACADESLiamBaines_Construction_FACADES
LiamBaines_Construction_FACADES
 
Madhu PPT.pptx
Madhu PPT.pptxMadhu PPT.pptx
Madhu PPT.pptx
 
Computer aided analysis and design of multi story building
Computer aided analysis and design of multi story buildingComputer aided analysis and design of multi story building
Computer aided analysis and design of multi story building
 
2nd batch.pptx
2nd batch.pptx2nd batch.pptx
2nd batch.pptx
 
G+3 APARTMENT BUILDING PROJECT REPORT
G+3 APARTMENT BUILDING  PROJECT  REPORTG+3 APARTMENT BUILDING  PROJECT  REPORT
G+3 APARTMENT BUILDING PROJECT REPORT
 
Design and planning of hostel building by vijayan
Design and planning of hostel building by vijayanDesign and planning of hostel building by vijayan
Design and planning of hostel building by vijayan
 
5th batch.pptx
5th batch.pptx5th batch.pptx
5th batch.pptx
 
Project 3 - Costing
Project 3 - CostingProject 3 - Costing
Project 3 - Costing
 
SELENDRA CONDOMINIUM CONSTRUCTION ORIENTATION
SELENDRA CONDOMINIUM CONSTRUCTION ORIENTATIONSELENDRA CONDOMINIUM CONSTRUCTION ORIENTATION
SELENDRA CONDOMINIUM CONSTRUCTION ORIENTATION
 
Building technology 1 Project 1 Drawing compilation
Building technology 1 Project 1 Drawing compilationBuilding technology 1 Project 1 Drawing compilation
Building technology 1 Project 1 Drawing compilation
 
ECA Workshop - ECA Form
ECA Workshop - ECA FormECA Workshop - ECA Form
ECA Workshop - ECA Form
 
Long Span Building Construction
Long Span Building ConstructionLong Span Building Construction
Long Span Building Construction
 
Design of Flyover Transverse Vertically by using Hydraulic Jack
Design of Flyover Transverse Vertically by using Hydraulic JackDesign of Flyover Transverse Vertically by using Hydraulic Jack
Design of Flyover Transverse Vertically by using Hydraulic Jack
 

More from RajeshKumar25548

PPT Notes.pdf
PPT Notes.pdfPPT Notes.pdf
PPT Notes.pdf
RajeshKumar25548
 
pradeep.pptx
pradeep.pptxpradeep.pptx
pradeep.pptx
RajeshKumar25548
 
vishnu coir ppt.pptx
vishnu coir ppt.pptxvishnu coir ppt.pptx
vishnu coir ppt.pptx
RajeshKumar25548
 
UNIT 4 SUSTAINABILITY.pptx
UNIT 4 SUSTAINABILITY.pptxUNIT 4 SUSTAINABILITY.pptx
UNIT 4 SUSTAINABILITY.pptx
RajeshKumar25548
 
UNIT 4 Intro_to_Sustainability.ppt
UNIT 4  Intro_to_Sustainability.pptUNIT 4  Intro_to_Sustainability.ppt
UNIT 4 Intro_to_Sustainability.ppt
RajeshKumar25548
 
SELF COMPACTING CONCRETE. ppt.pptx
SELF COMPACTING CONCRETE. ppt.pptxSELF COMPACTING CONCRETE. ppt.pptx
SELF COMPACTING CONCRETE. ppt.pptx
RajeshKumar25548
 
Prestressed concrete structures –general.pptx
Prestressed  concrete structures –general.pptxPrestressed  concrete structures –general.pptx
Prestressed concrete structures –general.pptx
RajeshKumar25548
 
BACTERIAL CONCRETE ppt.pptx
BACTERIAL CONCRETE  ppt.pptxBACTERIAL CONCRETE  ppt.pptx
BACTERIAL CONCRETE ppt.pptx
RajeshKumar25548
 
Application of coir fiber in civil Engg.pptx
Application of coir fiber in civil Engg.pptxApplication of coir fiber in civil Engg.pptx
Application of coir fiber in civil Engg.pptx
RajeshKumar25548
 
PPT DGFH.pptx
PPT DGFH.pptxPPT DGFH.pptx
PPT DGFH.pptx
RajeshKumar25548
 
1600752000647_GREEN CONCRETE PPT.pptx
1600752000647_GREEN CONCRETE PPT.pptx1600752000647_GREEN CONCRETE PPT.pptx
1600752000647_GREEN CONCRETE PPT.pptx
RajeshKumar25548
 
Hospital Building(PPT).pptx
Hospital Building(PPT).pptxHospital Building(PPT).pptx
Hospital Building(PPT).pptx
RajeshKumar25548
 
bagasse_ash[1].pptx
bagasse_ash[1].pptxbagasse_ash[1].pptx
bagasse_ash[1].pptx
RajeshKumar25548
 
project ppt.pptx
project ppt.pptxproject ppt.pptx
project ppt.pptx
RajeshKumar25548
 
project ppt.pptx
project ppt.pptxproject ppt.pptx
project ppt.pptx
RajeshKumar25548
 
Prestressed Concrete Bridge.pptx
Prestressed Concrete Bridge.pptxPrestressed Concrete Bridge.pptx
Prestressed Concrete Bridge.pptx
RajeshKumar25548
 
Presentation1.pptx
Presentation1.pptxPresentation1.pptx
Presentation1.pptx
RajeshKumar25548
 
Presentation.pptx
Presentation.pptxPresentation.pptx
Presentation.pptx
RajeshKumar25548
 
PPT.pptx
PPT.pptxPPT.pptx
PLANNING,ANALYSIS,DESIGN AND ESTIMATION OF A SHOPPING COMPLEX.pptx
PLANNING,ANALYSIS,DESIGN AND ESTIMATION OF A SHOPPING COMPLEX.pptxPLANNING,ANALYSIS,DESIGN AND ESTIMATION OF A SHOPPING COMPLEX.pptx
PLANNING,ANALYSIS,DESIGN AND ESTIMATION OF A SHOPPING COMPLEX.pptx
RajeshKumar25548
 

More from RajeshKumar25548 (20)

PPT Notes.pdf
PPT Notes.pdfPPT Notes.pdf
PPT Notes.pdf
 
pradeep.pptx
pradeep.pptxpradeep.pptx
pradeep.pptx
 
vishnu coir ppt.pptx
vishnu coir ppt.pptxvishnu coir ppt.pptx
vishnu coir ppt.pptx
 
UNIT 4 SUSTAINABILITY.pptx
UNIT 4 SUSTAINABILITY.pptxUNIT 4 SUSTAINABILITY.pptx
UNIT 4 SUSTAINABILITY.pptx
 
UNIT 4 Intro_to_Sustainability.ppt
UNIT 4  Intro_to_Sustainability.pptUNIT 4  Intro_to_Sustainability.ppt
UNIT 4 Intro_to_Sustainability.ppt
 
SELF COMPACTING CONCRETE. ppt.pptx
SELF COMPACTING CONCRETE. ppt.pptxSELF COMPACTING CONCRETE. ppt.pptx
SELF COMPACTING CONCRETE. ppt.pptx
 
Prestressed concrete structures –general.pptx
Prestressed  concrete structures –general.pptxPrestressed  concrete structures –general.pptx
Prestressed concrete structures –general.pptx
 
BACTERIAL CONCRETE ppt.pptx
BACTERIAL CONCRETE  ppt.pptxBACTERIAL CONCRETE  ppt.pptx
BACTERIAL CONCRETE ppt.pptx
 
Application of coir fiber in civil Engg.pptx
Application of coir fiber in civil Engg.pptxApplication of coir fiber in civil Engg.pptx
Application of coir fiber in civil Engg.pptx
 
PPT DGFH.pptx
PPT DGFH.pptxPPT DGFH.pptx
PPT DGFH.pptx
 
1600752000647_GREEN CONCRETE PPT.pptx
1600752000647_GREEN CONCRETE PPT.pptx1600752000647_GREEN CONCRETE PPT.pptx
1600752000647_GREEN CONCRETE PPT.pptx
 
Hospital Building(PPT).pptx
Hospital Building(PPT).pptxHospital Building(PPT).pptx
Hospital Building(PPT).pptx
 
bagasse_ash[1].pptx
bagasse_ash[1].pptxbagasse_ash[1].pptx
bagasse_ash[1].pptx
 
project ppt.pptx
project ppt.pptxproject ppt.pptx
project ppt.pptx
 
project ppt.pptx
project ppt.pptxproject ppt.pptx
project ppt.pptx
 
Prestressed Concrete Bridge.pptx
Prestressed Concrete Bridge.pptxPrestressed Concrete Bridge.pptx
Prestressed Concrete Bridge.pptx
 
Presentation1.pptx
Presentation1.pptxPresentation1.pptx
Presentation1.pptx
 
Presentation.pptx
Presentation.pptxPresentation.pptx
Presentation.pptx
 
PPT.pptx
PPT.pptxPPT.pptx
PPT.pptx
 
PLANNING,ANALYSIS,DESIGN AND ESTIMATION OF A SHOPPING COMPLEX.pptx
PLANNING,ANALYSIS,DESIGN AND ESTIMATION OF A SHOPPING COMPLEX.pptxPLANNING,ANALYSIS,DESIGN AND ESTIMATION OF A SHOPPING COMPLEX.pptx
PLANNING,ANALYSIS,DESIGN AND ESTIMATION OF A SHOPPING COMPLEX.pptx
 

Recently uploaded

Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERSCW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
veerababupersonal22
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
ssuser7dcef0
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 

Recently uploaded (20)

Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERSCW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 

A PPT.pptx

  • 2. SYNOPSIS  INTRODUCTION  PLANNING OF PROJECT  AREA OF PROJECT  DRAFTING  ANALYSIS & DESIGNING  ESTIMATION
  • 3. INTRODUCTION  This project mainly concerns on planning, analysis & designing of framed structure 1) Planning of (G+2) hotel. 2) Analysis of the building by (STAAD PRO) 3) Detailed design by limit state method 4) Preparation of abstract estimation of the building
  • 4. PLANNING OF PROJECT  Selection of area and orientation of the building.  Duration of time.  Sequence of events.  Requirements & General aspects.  Sanitary installation.  Water supply arrangement.  Drainage & electrical installation.
  • 5. AREA OF PROJECT The project is proposed near pollachi  Total area of site is 20000 sq.ft  Total building area is 12500 sq.ft  Plinth area is 10500 sq.ft  Parking and Gardening area 7500 sq.ft
  • 6. DRAFTING  The plan is draft using auto cad 2010  NBC-2005,IS 456,SP-16 are used in drafting and designing  Dining Hall ,Conference Hall and Kitchen Provided separately on Ground Floor
  • 7. PLAN VIEWS  GROUND FLOOR  FIRST FLOOR  SECOND FLOOR  ELEVATION
  • 8. NO OF ROOMS SUITE ROOM DOUBLE ROOM SINGLE ROOM GROUND FLOOR 1 2 3 FIRST FLOOR 2 6 3 SECOND FLOOR NIL 8 3
  • 9.  Analysis of beam and column is designed by using STAAD.Pro V8i Software  Our Structure contains Total number of nodes : 858 Total number of members : 1431 Total number of supports : 84 ANALYSIS & DESIGNING
  • 12. BAR DETAILS FOR BEAM  The size of the beam is = 300*450  The size of the bar is used in the beam = 12mm  Number of the rod is required in beam = 8
  • 14. BAR DETAILS FOR COLUMN  The size of the column is = 300*450  The size of the bar is used in the column=12mm  Number of bar required in the column = 8
  • 16. DETAILS OF SLAB  One Way Slab With Size 2500x6725 mm  For the main reinforcement 12mm diameter rods @ 300mm c/c  For the distributors 8mm diameter rods @ 300mm c/c
  • 17. DESIGN OF FOOTING  Isolated Rectangular Footing  Size of Footing 1.7 x 2.5m  For the long span 16mm diameter rods @ 170mm c/c  For the short span 12mm diameter rods @ 210mm c/c
  • 18. SPECIFICATION OF STAIR CASE  The stair case is provided per NBC – 2005  Staircase width 1500mm  Tread width 300mm  Riser height 150mm
  • 19. RAMP DESIGN  Gradient of ramp is 1 in 12  Handrails at 1000mm high  Width of ramp is 1200mm
  • 20. ESTIMATION  Excavation & filling cost =5,92,500  Flooring & Brick Work cost =82,87,500  Concrete Work cost =1,41,58,700  Floor Finishing Cost =1,26,22,000  Miscellaneous &White Washing =39,25,000  Other Work =86,09,140  Total Project Cost =4,81,94,840
  • 21. CONCLUSION  This project work has offered us to learn and expressing our ideas on the topics like Planning, Analysis, Designing and Estimating.  Planning, Analysis and design of the hotel building was completed.