Arid Zone Journal of Engineering, Technology and Environment. August, 2015; Vol. 11: 77-88
Copyright© Faculty of Engineering, University of Maiduguri, Nigeria.
Print ISSN: 1596-2490, Electronic ISSN: 2545-5818
www.azojete.com.ng
RISK FACTORS INFLUENCING CONSTRUCTION PROCUREMENT
PERFORMANCE IN NIGERIA
Alhassan Dahiru1
and Aminu Muhammad Bashir2
(Department of Quantity Surveying, Faculty of Earth & Environmental Sciences,
Bayero University, Kano, Nigeria.)
Phone - 08020793242
Abstract
One of the challenges facing construction procurement performance is the failure to determine the risk related
factors limiting its success. These risk factors can cause a significant increase in the procurement cost leading to an
increase in the overall project cost. The purpose of this study is to identify and evaluate the risk factors influencing
construction procurement performance with a view to achieve the overall project performance. The objectives are to
establish a relative significance index score for the most important risk factors limiting the procurement performance
of the projects. A self administered questionnaire was employed to the construction industry professionals for
responses. A total of 78 questionnaires were distributed to these professionals (architects, quantity surveyors,
engineers, and contractors) but 62 were returned and analyzed using influential index and later ranked in order of
importance. Results of the analysis indicate a disparity in terms of ranking of the factors influencing construction
procurement performance. Corruption related risk, conflict of interest, ineffective project technical feasibility, and
lack of commitment to transparency were found to be the most significant factors limiting construction procurement
performance. Communication barriers and unconfidential tender evaluation process were found to be the low
weighted risk factors. The findings can serve as a supportive mechanism for risks management in public
construction procurement management. Therefore, construction procurement personnel at all levels of government
may find this study relevant, while improving construction procurement performance in the country. It is
recommended that construction procurement system should be focused on risks related to corruption, conflict of
interest, and effective technical feasibility for improving the overall project performance.
Keywords: Construction project, procurement performance, risk factors, risk management.
1. Introduction
The pace of change in the construction procurement performance has imposed additional
demands on risk management. Risk management is a vital project procurement performance tool
for reducing uncertainty and improving decision making. Risk cannot be avoided but must be
recognized, assessed and manage for better procurement performance. The aim of this study is to
assess key risk factors affecting construction procurement performance from stakeholders‟
perspective. The study is concerned with performance risk as it is often argued that if
procurement planning procedure is adequately supported with a comprehensive strategy with
regard to the most significant risk factors affecting procurement performance will improve the
overall project performance (Tipili and Ilyasu, 2014). Construction procurement efficiency and
effectiveness largely depends on the identification of critical factors limiting its performance.
Risk is an uncertain event or set of circumstances that could occur, have an effect on the
achievement of the procurement planning objectives. Risk factors is inherent in every
construction procurement planning procedure and sometimes is impossible for these risks to be
avoided (Abba, 2008).
Alhassan and Aminu: Risk factors influencing construction procurement performance in Nigeria.
AZOJETE, 11: 77-88
78
Furthermore, during the procurement planning process of the project development, most of these
risk factors are not properly identified and assessed (Faruk et al., 2013). Fabi et al. (2015) has
also advocate that no procurement system is risk free. Therefore, it becomes imperatives to
identify and assess risk factors related to procurement planning procedures for improving the
overall procurement performance.
1.1 Risk Factors Influencing Construction Projects Generally
The Nigeria‟s construction industry is like other developing countries, is dramatically
experiencing a highly risk prone, due to the complex and dynamic environments (Tipili and
Ibrahim, 2015). Thus, such nature is creating an atmosphere of high uncertainty and risks. This
consequently affects the overall project performance. In an effort to identify and assess
construction risk factors, Tipili and Ibrahim (2015) have jointly identified and assessed 27 key
risk factors affecting public construction project from project stakeholder perspectives (clients,
contractors and consultants). The study reveals that these risk factors spread through the whole
project life cycle and many risks occur at more than one phase, with the construction stage with
risky phase. On the risk categories level all the stakeholders agreed on the finance category as
the main factor threatening project completion, and the labour and equipment category as having
the least impact. Furthermore, clients and consultants have different perception on the impact of
design category. Moreover, the study had elaborated the stakeholder role and responsibility on
the management of the 27 identified risks and include: seven (7) key risks related to clients such
as: tight project schedule; decision making process; payment for completion work; delay in site
mobilization; design modification; financing project by client; and excessive change order
ranked the least factor in order of priority. Tight project schedule was ranked as the most
significant risk factors among the seven identified factors related to clients, which infers that
formulating an appropriate schedule in the conceptual/feasibility phase is never more
constructive to the project delivery. The clients should prepare a practical schedule allowing
sufficient but not redundant time to accommodate all design and construction activities. As time
and cost are always closely correlated, a lengthy schedule will undoubtedly wreck the project
cost benefit.
Twelve (12) key risks related to contractors were evaluated and include: inadequate program
planning; material delivery; contractor experience; labour performance; material waste handling;
availability of material in the market; compliance of material to specification; design team
experience; complexity of project design; necessity of specific skill; labour and management
skill relation; and payment for completion work ranked the least risk factor. Thus, inadequate
construction program planning was ranked the most influential risk factor related to contractors.
This finding may result from inadequate program scheduling, innovative design or
contractors„lack of knowledge in planning construction programs. To reduce the negative
influence of the two risks, an informative program scheduling should be worked out in the design
phase, and the constructability of innovative design should be examined. More importantly, the
Arid Zone Journal of Engineering, Technology and Environment. August, 2015; Vol. 11: 77-88
79
abilities to manage construction programs and implement innovative design should be used as
key criteria in appointing contractors.
Eight (8) key risks related to consultants were also discovered by the researchers and these are:
design modification; unclear responsibility; compliance of material to specification; cost
estimation accuracy; delay in site mobilization; design modification; clarity of details in drawing;
excessive change order. The survey indicates that design modification was ranked the most
important factor related to consultants in limiting public construction projects. This popularly
arisen in the design phase of a project and may result from issues such as variations by the client
and defective designs. To avoid defective design, the design teams need not only to fully
understand what the clients want as defined in the project brief, but also to establish an efficient
communication scheme among the designers. Inadequate program scheduling often appears in
projects with a tight schedule when some programs need to be reduced to meet the project
timeline. Moreover, uncertainty surrounds most facets of construction projects, which makes it
impossible to accurately predict the time required for various programs. Choosing experienced
designers can help to minimize the difference between the proposed and practical program
schedules. Incomplete or inaccurate cost estimate is directly related to the designers/consultants„
knowledge and attitude towards work.
1.2 Risk Factors Limiting Construction Procurement Performances
Procurement performance refers to proper planning and scheduling of procurement procedures in
terms of efficiency and effectiveness for improving the overall project performance. Rrisk
identification is defined as the process of systematically and continuously identifying,
categorizing and assessing the initial significance of risk associated with construction
procurement performance (Odeyinka & Lowe, 2000). Managing changes has led to the
introduction of techniques for risk assessment as a major part of the planning process. Risk
assessment concentrates on quantifying identified risks by using statistical analysis, since the
identified risk in most cases can be either quantitively or subjectively assessed factors
(Augustine et al., 2013).
Risk factors appear to influence the objective performance of procurement process. If not
adequately identified and managed may affect the overall project success especially in terms of
achieving value for money. Risk identification is the first phase of risk management process,
which can be divided into four major phases: risk identification, risk analysis, risk response, and
risk monitoring and evaluation (Tipili & Ilyasu, 2014). According to Augustine et al. (2013) the
objectives of risk identification are as follows: to identify all significant types and sources of risk
and uncertainty associated with the objectives and their key parameters; to ascertain the causes of
each risk; to assess how risks are related to other risks and how risks should be classified and
grouped for evaluation.
Alhassan and Aminu: Risk factors influencing construction procurement performance in Nigeria.
AZOJETE, 11: 77-88
80
Risk identification is a beginning step of risk management. It yields types, sources, causes,
characteristics, and relations of risks associated with the problem considered, all of which will be
used to analyze and respond each risk in the subsequent phases. Tipili and Ibrahim (2015) had
defined risk identification as a process for uncovering any risks that could potentially affect a
process. This step is of considerable importance as other processes such as risk analysis and
response can only be undertaken on the potential risks that have been identified (Odeyinka &
Lowe, 2000). Risk identification is a simple but difficult task as there are no absolute procedures
that may be used to identify risks in a procurement planning procedure. Project managers often
rely heavily on their experience and on the insight of other key personnel involved in the process
(Odeyinka & Lowe, 2000). Depending on the process documentation available and the nature of
the process, a variety of considerations may prompt risk discovery. Regarding risk, Augustine et
al. (2013) noted that managers need to focus on the interface between the consultant and the
client, between departments of the client organization, between phases or tasks of a client
process, or between geographic areas. They further suggest that the procurement planning and
schedule should clearly show dependencies between tasks in order to help pinpoint risk-prone
areas. Alternatively, managers may use process maps that show interfaces between processes or
tasks. At the stage of risk identification it is important to identify the risk source and its effect.
Within the framework of risk management, there are four alternative strategies: risk avoidance,
risk reduction, risk transfer, and risk retention (Odeyinka & Lowe, 2000; Augustine et al., 2013).
Risk Avoidance: This method of mitigation involves the removal of the causes of the risk and
therefore the risk itself. The most simple form of risk avoidance is not to tender for a project.
Also risk avoidance may involve considering and adopting alternative courses of action or using
the exemption clauses in contracts. Risk avoidance approach should be addressed whenever the
level of risk is high enough to render a project unfeasible.
Risk Reduction: Risk reduction is another approach that might be used to mitigate risk. This
method is directed towards decreasing the contractor's potential exposure to risk by two ways:
reducing the probability of risk; and reducing the impact of a risk. Risk reduction methods may
sometimes require some initial investment which should then reduce the likelihood of the risk
occurring. Risk reduction should be addressed whenever the level of risk is unacceptable and
alternative action is available. Risk reduction invariably leads to greater confidence regarding the
project's outcome. However, risk reduction will result in an increase in the base cost but should
offer a significantly greater procurement performance leading to the reduction in the level of the
overall project cost.
Risk Transfer: Through negotiation, the contractor can transfer risk to other parties such as the
owner, subcontractors, or suppliers. Commonly this can be achieved through a provision in a
contracts or a new contract placement. Transference of risk comprises the passing of risks to
those who are more capable of maintaining control and influencing the outcome of the risk.
Arid Zone Journal of Engineering, Technology and Environment. August, 2015; Vol. 11: 77-88
81
It's worth mentioning that some texts view insurance as risk reduction whilst others consider it as
risk transfer. Both of the two views are considered correct. When some risk is transferred and
some is retained this is known as risk-sharing. This approach should be adopted when the risk
exposure is beyond the control of one party and it's important that each party acknowledges the
value of the portion of risk for which he is responsible.
Risk Retention: This method of risk retention should be used when all the avenues for other risk
mitigation strategies are blocked. In other words, this method should only be used for the
residual risks that cannot be mitigated by the previous three strategies. In this method, residual
risks undergo a detailed quantitative analysis in order to allocate an appropriate level of
procurement performance. This does not imply that these risks would by then be ignored and not
monitored throughout the cycle of the project. In fact, they should be under the eye and control
of management in order to ensure that they are contained within the procurement performance.
1.3 Construction Project Delivery and Procurement Performance
Construction projects are becoming increasingly complex thereby resulting in complex
procurement processes. In an effort to improve the procurement planning procedures capable for
improving procurement performance, several studies have indicated the key factors influencing
public construction procurement process and include: economy; value for money, ethical
standards, competition and transparency and accountability (OECD, 2005; Dahiru, 2014;
Babatunde et al., 2010). To obtain the best service and performance from the construction
procurement system, risk related factors should be identify at each process for realizing project‟s
success (Odeyinka & Lowe, 2000; Babatunde et al., 2010; Augustine et al., 2013). Successful
construction projects should result in project delivered on time, to cost, and to the desired quality
capable of performing the specific business function of the client (Bureau of Public Procurement
2007); Fabi et al., 2015). Procurement process in Nigeria involves a wide range of challenges
that stakeholders face on project delivery and according to Fabi et al., (2015) these include:
absence of internal management structure, lack of social drive, low technical and management
capacity as well as low multi stakeholder approach. These challenges have led to difficulty in
procuring public projects and are a major concern to all stakeholders because the Nigerian
construction industry is perceived as one engrossed with corruption and bureaucracy (Alfred,
2008).
2. Research Methodology
The study covers a systematic approach to review some literature on the nature and application
of construction procurement systems in Nigeria. This provided the foundation upon which the
study was premised. The constraints surrounding the application of construction procurement
systems was reviewed which also provides good basis for understanding where the problems
exist and the resultant gap in procurement performance. A quantitative approach using a well-
structured questionnaire survey was chosen for this research since a wide range of responses are
Alhassan and Aminu: Risk factors influencing construction procurement performance in Nigeria.
AZOJETE, 11: 77-88
82
required and in view of its ability to facilitate comparison of themes (Sambo, 2005). A vast
amount of information was collected using a semi-structured interview with construction
procurement practitioners in government sector, construction consultants and academics who
were in one way or the other involved in the delivery of construction projects in Nigeria.
Project participants in construction projects delivery (such as: contractors; architects; quantity
surveyors; and engineers) in the northern part of the country were considered for the study. Data
were specifically collected from Kano, Kaduna and Abuja. These places were selected because
of frequent construction activities that are carried out in these regions. Alongside with this, more
construction and consulting firms were commonly found available in these areas and this led to
have more experienced construction procurement stakeholders as been the respondents.
Questionnaire was designed and administered on 78 randomly selected construction
professionals involved in a nearly completed or recently completed construction projects in the
study area. The questionnaire was based on a rank scale of 1-5 to be ranked among the various
effects of risk factors that can occur to construction procurement performance. A total of seventy
eight (78) questionnaires were distributed but sixty two (62) (79%) of the data were retrieved as
shown in Table 1. Of these, 30 responses came from the private sector and 32 from the public
sector. All the respondents were either directors, principal partners or managers belonging to
either client‟s organisation, consultants or private financiers and developers. The data provided
by the questionnaire were analyzed using influence index.
The Questionnaire was developed on one hand using some key indicators from the literature
review and from information initially collected using a series of semi-structured interviews. A
total of 20 risk factors were included in the questionnaire and these factors were obtained from
the literature reviewed. The complete questionnaire comprises of three parts: questions about
respondent's academic and professional background, experience and questions on perceived risk
factors of construction procurement performances in Nigeria.
Table 1: Categorization of respondents found in the study area
Respondents Frequency Percentage % Cumulative %
Architects
Contractors
Engineers
Quantity Surveyors
Total
14
17
15
16
62
22.58
27.42
24.19
25.81
100
22.58
50.00
74.19
100
Finally, a survey based on a questionnaire was also done to solicit nationwide expert opinions on
the relative significance of risk factors limiting construction procurement performances in the
country. The results of this survey are presented in this paper. The survey was conducted
Arid Zone Journal of Engineering, Technology and Environment. August, 2015; Vol. 11: 77-88
83
amongst and within organisations, ministries, and private practitioners in various disciplines who
have been involved in construction projects delivery. Although many studies have shown that,
electronic survey elicits higher response rate from the respondents (Alfred, 2008), this research
did not find it expedient to conduct any online survey. The survey also adopted a convenient
sampling technique rather than random sampling because there is no database for organizations
involved in construction procurement system in Nigeria.
Background information on respondents‟ profile is provided in table 2. This table shows that
17.74% of the respondents have the qualification of PhD, while 20.97% have masters in their
respective field area of specialization. 25.81 have first degrees, 19.35% have either HND or ND
in their various fields of disciplines. This summarily shows that majority of the respondents have
high qualification in their field of endeavours. More importantly, 100% of the respondents are
corporate members of their respective professional bodies (Table 3). In addition, 70.97% of them
have an average of 12years of experience in the construction procurement systems (Table 4).
From the foregoing, it can be concluded that the respondents could be relied upon for the
information provided for this study for the purpose of analysis.
Table 2: Academic Qualification of respondents
Respondents Frequency Percentage % Cumulative %
PhD/M.Phil
MSc/M.Eng/M.Tech
BSc/B.Eng/B.Tech
HND/ND
Others
Total
11
13
16
12
10
62
17.74
20.97
25.81
19.35
16.13
100
17.74
38.71
64.52
83.87
100
Table 3: Professional Qualification of respondents
Respondents Frequency Percentage % Cumulative %
MNIA
MNIOB
MNSE
MNIQS
Total
12
15
17
18
62
19.35
24.20
27.42
29.03
100
19.35
43.55
70.97
100
Alhassan and Aminu: Risk factors influencing construction procurement performance in Nigeria.
AZOJETE, 11: 77-88
84
Table 4: Procurement Experience of respondents
Respondents Frequency Percentage % Cumulative %
1 – 5 years
6 – 10 years
11 – 15 years
16 – 20 years
Above 20 years
6
12
16
18
10
9.68
19.35
25.81
29.03
16.13
9.68
29.03
54.84
83.87
100
3. Survey Data Analysis and Results
The outcome of the data collected was critically analysed and summarised in order to determine
the strength of different opinions and their relative importance. The objective is to collect data on
the attitudes, opinion and behavioural disposition of the respondents. The relative importance of
20 risk factors identified from the literature review was explored by means of Likert rating scale.
This, according to Sambo (2005), is one of the acceptable methods of scale rating in construction
management research.
Based on all the gathered information, influence index was used as to find the most influential
risk factors limiting the procurement performance in Nigeria. Respondents were asked to rank
the influence of these factors over the procurement performance for which the relative
information have been provided on a five point scale (1 = very low; 2 = low; 3 = medium; 4 =
high; and 5 = very high). Thus the significance of adopting the influence index is to determine
the most influential risk factors limiting procurement performance. This method was previously
used by Arif et al (2010) in their effort to determined factors influencing the accuracy of cost
estimates of construction projects in Pakistan.
Hence, the influence index of each factor was calculated using the following formula:
Influence Index =
∑ (Influence score X Response frequency at that influence score)
Total Number of Responses
Arid Zone Journal of Engineering, Technology and Environment. August, 2015; Vol. 11: 77-88
85
Table 5: Ranking of Risk Factors Influencing Construction Procurement Performance
Risk Factors Influencing Construction Procurement Performance
Influential Factors
Influential Index
Architects Q/Surveyors Contractors C/Engineer Weighted
Average
Rank
Corruption related risks
Conflict of interest
Ineffective project
technical feasibility
Lack of commitment to
transparency
Discrimination of
tenderers
Unequal treatment of
tenders
Non early involvement
of consultants
Expertise level of
procurement personnel
Impact of contract type
Level of project team
integration
Lack of good
governance
Unavailability of
procurement structure
Unfavourable
procurement framework
Levels of project team
commitment
Inconsistency of
government policies
Inappropriate condition
of contract
Use of inappropriate
procurement strategy
Ineffective procurement
approach
Communication barriers
Unconfidential tender
evaluation process
6.9
6.7
6.7
6.6
6.5
6.4
6.2
6.2
6.1
6.1
5.9
6.0
5.7
5.2
5.2
5.3
5.3
5.2
5.0
5.0
6.9
6.8
6.6
6.5
6.3
6.3
6.3
6.1
6.0
5.7
5.6
5.5
5.5
5.6
5.6
5.2
5.2
5.0
5.1
4.9
6.8
6.7
6.6
6.5
6.5
6.3
6.2
6.0
6.0
5.8
5.8
5.7
5.6
5.8
5.3
5.5
5.0
5.1
5.0
4.8
6.8
6.8
6.7
6.7
6.7
6.6
6.6
6.5
6.5
6.5
6.4
6.2
6.1
6.0
5.8
5.6
5.6
5.2
5.2
5.1
6.85
6.75
6.65
6.58
6.50
6.40
6.33
6.20
6.15
6.03
5.93
5.85
5.73
5.65
5.48
5.40
5.28
5.13
5.08
4.95
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
Alhassan and Aminu: Risk factors influencing construction procurement performance in Nigeria.
AZOJETE, 11: 77-88
86
3.1 Ranking of Perceived Risk Factors Influencing Construction Procurement
Performance
From the analysis shown in table 5, the influence index values for the 20 different risk factors is
presented ranging from 6.85 to 4.95 (average weighted). It can be seen that factors, such as
corruption related risks ( with an average weighted influence value of 6.85), conflict of interest
(6.75), ineffective project technical feasibility (6.65), lack of commitment to transparency
(6.58), discrimination of tenderers (6.50), unequal treatment of tenders (6.40), non early
involvement of consultants (6.33), expertise level of procurement personnel (6.20), impact of
contract type (6.15), and level of project team integration (6.03) top the first ten (10) most
influential risk factors limiting construction procurement performance.
The top four (4) most risk factors influencing construction procurement performance were
corruption related risks, conflict of interest, ineffective project technical feasibility, and lack of
commitment to transparency. This shows that lack of contracting mind-set and distrust within the
public sector usually affect construction procurement performance. Although, there were no
official reports on cases about conflicting of interest in public procurement management, it is
however believed that issues such as lack of commitment to transparency and accountability as
well as influence of corruption are serious problems that can results to the lost of contracting
mindset and distrust between construction project parties. Therefore, unless government
commitment in the fight against corruption continues to yield positive results, there would be
limited genuine commitment and trust of the public and private parties in construction contract.
On issue has to do with ineffective project technical feasibility, it is important to note that
procuring construction projects required intensive study and analysis to be able to verify whether
it can deliver value for money or not. This is therefore more indicative of the apparent necessity
for government to be of adequately poised in providing an astute operational framework for such
deals.
Good Governance provides sound economic policies, administrative platform that promote
construction procurement performance (Babatunde et al., 2010 and Dahiru, 2014). This cannot
be achieved with corrupt officials within the public sector. Although it is important to note that
government had established an institution and a structure called the Bureau for Public
Procurement Act (BPP Act, 2007) to principally regulate procurement process and ensure
accountability and probity in the public sector contract award process, there is still an increasing
evidence that corruption is one of the problems which still confront project procurement process
in Nigeria (Alfred, 2008 and Dahiru, 2014). Today, the World Bank funding for services in
developing countries has become inadequate and ineffective due to effect of corruption (Akelere
and Gidado 2003).
Arid Zone Journal of Engineering, Technology and Environment. August, 2015; Vol. 11: 77-88
87
4. Conclusion
Construction procurement procedures has many challenges on performances and these
challenges are evident in risk factors associated with the procurement planning and scheduling
and consequent performance of the procurement process. The study had evaluated some
mechanisms limiting the performance of construction procurement management with a view to
improve integrity in the processes. Factors, such as corruption related risks, conflict of interest,
ineffective project technical feasibility, lack of commitment to transparency, discrimination of
tenderers, unequal treatment of tenders, non early involvement of consultants, expertise level of
procurement personnel, impact of contract type, and level of project team integration top the list
of the most influential factors limiting construction procurement performance in Nigeria.
Therefore the findings can serve as a supportive mechanism for risks management in public
construction procurement management in Nigeria. Hence, construction procurement personnel at
all levels of government may found this study relevant while improving construction
procurement performance in the country.
References
Abba, D. 2008. Assessment of contingency allowance at tender stage. Unpublished BSc thesis,
Department of Quantity Surveying, Ahmadu University Zaria.
Alfred, OO. 2008. Due Process and Contractor Selection for Public works in Nigeria.
Procurement of construction and reconstruction projects in the international context. University
of Newcastle, UK, pp 1-14
Arif, F., Lodi, SH. and Farooqui, RU. 2010. Accuracy of Cost Estimates of Construction Projects
in Pakistan. Paper presented at the 2nd
International conference on construction in Developing
countries held in Egypt.
Augustine, IE., Ajayi, JR., Ade, BA., and Edwin, AA. 2013. Assessment of risk management
practices in Nigerian construction industry: toward establishing risk management index. Int. J.
Pure Appl. Sci. Technol., 16(2), pp. 20-31
Babatunde, SO., Opawole, A., Ujaddughe, IC. 2010. Appraisal of Project Procurement Methods
in the Nigerian Construction Industry. Journal of Civil Engineering Dimension, Vol. 12, No. 1
March, 2010 pp. 1 – 7
Bureau of Public Procurement, BPP. 2007. Procurement Procedures Manual for Public
Procurement in Nigeria. The principal authority for establishing general policies and guidelines
relating to public sector procurement in Nigeria.
Dahiru, A. 2014. Conflict of interest in public procurement management in Nigeria. A paper
presented at the Nigerian Institute of Quantity Surveyors (NIQS) National Seminar under the
theme “Procurement of Construction Works and Services – Adapting to Contemporary
Challenges for Enhanced National Development” held at International Hotel, Gombe.
Alhassan and Aminu: Risk factors influencing construction procurement performance in Nigeria.
AZOJETE, 11: 77-88
88
Fabi, JK., Awolesi, JA., and Akinseinde, OA. 2015. An assessment of effect of procurement
process on construction project delivery In: Ogunsemi, D.R, Awodele, O.A, & Oke, A.E (Eds).
Proceedings of the 2nd Nigerian Institute of Quantity Surveyors Research Conference Federal
University of Technology, Akure (pp 519 - 529).
Faruk, A., Ibrahim, AD. and Ibrahim, YM. 2013. Investigating drivers and barriers for adopting
collaborative procurement strategies in the Nigerian construction industry. A paper presented at
the NIQS Annual Research Conference (AnReCon) held in Abuja.
Odeyinka, HA. and Lowe, JG. 2000. An Assessment of risk factors involved in modelling cash
flow forecast. Paper presented at the 16th
Annual Research Conference in Construction
Management held in Glasgow Caledonian University, UK.
OECD. 2005. Fighting corruption and promoting integrity in public procurement.
(http://wiki.bezkorupce.cz/_media/wiki/corrup_proc_oecdrapport- 2005-aase.pdf) Accessed on
the 13th
May, 2014.
Public Procurement Act, PPA. 2007. Fundamental Principles for Procurement. An Act enacted
by the National Assembly setting standards and developing the legal framework and
professional capacity for public procurement in Nigeria.
Sambo, AA. 2005. Research methods in education, Stirling-Horden Publishers (Nig.) Ltd.,
Ibadan Pp87-93.
Tipili, LG. and Ilyasu, SM. 2014. Evaluating the impact of risk factors on construction projects
cost in Nigeria. The International Journal of Engineering and sciences, vol. 3, issue 6, pp 10-15.
Tipili, LG., and Ibrahim, Y. 2015. Identification and assessment of key risk factors affecting
public construction projects in Nigeria: stakeholders‟ perspectives In: Ogunsemi, D.R, Awodele,
O.A, and Oke, A.E (Eds). Proceedings of the 2nd Nigerian Institute of Quantity Surveyors
Research Conference Federal University of Technology, Akure (pp 707 - 721).

More Related Content

What's hot

Construction project risk management
Construction project risk managementConstruction project risk management
Construction project risk managementIQPC
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentIJERD Editor
 
IRJET- Risk Management using Primavera Software for Residential Sector
IRJET-  	  Risk Management using Primavera Software for Residential SectorIRJET-  	  Risk Management using Primavera Software for Residential Sector
IRJET- Risk Management using Primavera Software for Residential SectorIRJET Journal
 
Establishing risk management factors for construction projects in iraq
Establishing risk management factors for construction projects in iraqEstablishing risk management factors for construction projects in iraq
Establishing risk management factors for construction projects in iraqIAEME Publication
 
RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIO
RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIORISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIO
RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIOIAEME Publication
 
IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...
IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...
IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...IRJET Journal
 
Risk Management in High Rise Construction Projects: A Review
Risk Management in High Rise Construction Projects: A ReviewRisk Management in High Rise Construction Projects: A Review
Risk Management in High Rise Construction Projects: A ReviewA Makwana
 
A REVIEW ON FACTORS INFLUENCING CONSTRUCTION PROJECT SCHEDULING
A REVIEW ON FACTORS INFLUENCING CONSTRUCTION PROJECT SCHEDULINGA REVIEW ON FACTORS INFLUENCING CONSTRUCTION PROJECT SCHEDULING
A REVIEW ON FACTORS INFLUENCING CONSTRUCTION PROJECT SCHEDULINGIAEME Publication
 
Project risk management
Project risk managementProject risk management
Project risk managementAndreea Usatenco
 
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTSEFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTSvivatechijri
 
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...IRJET Journal
 
A study of various factors affecting risk management techniques in constructi...
A study of various factors affecting risk management techniques in constructi...A study of various factors affecting risk management techniques in constructi...
A study of various factors affecting risk management techniques in constructi...eSAT Journals
 
risk management: a better approach
risk management: a better approachrisk management: a better approach
risk management: a better approachMadhumanti Samaddar
 
Risk Contingency Evaluation in International Construction Projects (Real Case...
Risk Contingency Evaluation in International Construction Projects (Real Case...Risk Contingency Evaluation in International Construction Projects (Real Case...
Risk Contingency Evaluation in International Construction Projects (Real Case...IJLT EMAS
 
IRJET- A Review Paper on Risk Management using Primavera for Residential ...
IRJET-  	  A Review Paper on Risk Management using Primavera for Residential ...IRJET-  	  A Review Paper on Risk Management using Primavera for Residential ...
IRJET- A Review Paper on Risk Management using Primavera for Residential ...IRJET Journal
 
Risk analysis and managements large epc projects
Risk analysis and managements  large epc projectsRisk analysis and managements  large epc projects
Risk analysis and managements large epc projectsPALLA NARASIMHUDU
 
Claims Management And Assessment Through Documentation
Claims Management And Assessment Through DocumentationClaims Management And Assessment Through Documentation
Claims Management And Assessment Through Documentationvivatechijri
 
A Study on Risk Assessment in Construction Projects
A Study on Risk Assessment in Construction ProjectsA Study on Risk Assessment in Construction Projects
A Study on Risk Assessment in Construction ProjectsIJMER
 

What's hot (20)

Construction project risk management
Construction project risk managementConstruction project risk management
Construction project risk management
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
 
IRJET- Risk Management using Primavera Software for Residential Sector
IRJET-  	  Risk Management using Primavera Software for Residential SectorIRJET-  	  Risk Management using Primavera Software for Residential Sector
IRJET- Risk Management using Primavera Software for Residential Sector
 
Establishing risk management factors for construction projects in iraq
Establishing risk management factors for construction projects in iraqEstablishing risk management factors for construction projects in iraq
Establishing risk management factors for construction projects in iraq
 
RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIO
RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIORISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIO
RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIO
 
IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...
IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...
IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...
 
Risk Management in High Rise Construction Projects: A Review
Risk Management in High Rise Construction Projects: A ReviewRisk Management in High Rise Construction Projects: A Review
Risk Management in High Rise Construction Projects: A Review
 
A REVIEW ON FACTORS INFLUENCING CONSTRUCTION PROJECT SCHEDULING
A REVIEW ON FACTORS INFLUENCING CONSTRUCTION PROJECT SCHEDULINGA REVIEW ON FACTORS INFLUENCING CONSTRUCTION PROJECT SCHEDULING
A REVIEW ON FACTORS INFLUENCING CONSTRUCTION PROJECT SCHEDULING
 
C1303032126
C1303032126C1303032126
C1303032126
 
Project risk management
Project risk managementProject risk management
Project risk management
 
Risk management
Risk managementRisk management
Risk management
 
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTSEFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
 
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...
 
A study of various factors affecting risk management techniques in constructi...
A study of various factors affecting risk management techniques in constructi...A study of various factors affecting risk management techniques in constructi...
A study of various factors affecting risk management techniques in constructi...
 
risk management: a better approach
risk management: a better approachrisk management: a better approach
risk management: a better approach
 
Risk Contingency Evaluation in International Construction Projects (Real Case...
Risk Contingency Evaluation in International Construction Projects (Real Case...Risk Contingency Evaluation in International Construction Projects (Real Case...
Risk Contingency Evaluation in International Construction Projects (Real Case...
 
IRJET- A Review Paper on Risk Management using Primavera for Residential ...
IRJET-  	  A Review Paper on Risk Management using Primavera for Residential ...IRJET-  	  A Review Paper on Risk Management using Primavera for Residential ...
IRJET- A Review Paper on Risk Management using Primavera for Residential ...
 
Risk analysis and managements large epc projects
Risk analysis and managements  large epc projectsRisk analysis and managements  large epc projects
Risk analysis and managements large epc projects
 
Claims Management And Assessment Through Documentation
Claims Management And Assessment Through DocumentationClaims Management And Assessment Through Documentation
Claims Management And Assessment Through Documentation
 
A Study on Risk Assessment in Construction Projects
A Study on Risk Assessment in Construction ProjectsA Study on Risk Assessment in Construction Projects
A Study on Risk Assessment in Construction Projects
 

Viewers also liked

20100224 foro ventas3 (2)
20100224 foro ventas3 (2)20100224 foro ventas3 (2)
20100224 foro ventas3 (2)PTF
 
äœœć“ç”š
äœœć“ç”šäœœć“ç”š
äœœć“ç”šSophie Chen
 
hermann perfil
hermann perfilhermann perfil
hermann perfilPTF
 
Blog-7-Self-Regulation
Blog-7-Self-RegulationBlog-7-Self-Regulation
Blog-7-Self-RegulationElya Steinberg
 
PMA Guillermo Sicardi 2014 24 material gestion_competencias_resumen
PMA Guillermo Sicardi 2014 24 material gestion_competencias_resumenPMA Guillermo Sicardi 2014 24 material gestion_competencias_resumen
PMA Guillermo Sicardi 2014 24 material gestion_competencias_resumenPTF
 
Modelo de negocio. Rodrigo Saa. TRS 2014
Modelo de negocio. Rodrigo Saa. TRS 2014Modelo de negocio. Rodrigo Saa. TRS 2014
Modelo de negocio. Rodrigo Saa. TRS 2014PTF
 
Trans-generational and Inter-generational Trauma Body in Relationship Congres...
Trans-generational and Inter-generational Trauma Body in Relationship Congres...Trans-generational and Inter-generational Trauma Body in Relationship Congres...
Trans-generational and Inter-generational Trauma Body in Relationship Congres...Elya Steinberg
 
Estudio base para diseño producto residencial ba 2000
Estudio base para diseño producto residencial ba 2000Estudio base para diseño producto residencial ba 2000
Estudio base para diseño producto residencial ba 2000PTF
 
Neurocuestionario
NeurocuestionarioNeurocuestionario
NeurocuestionarioPTF
 
Pgi miguel pato dia 01
Pgi miguel pato dia 01Pgi miguel pato dia 01
Pgi miguel pato dia 01PTF
 
Modelo de negocio transformadores - día 1 Rodrigo Saa
Modelo de negocio   transformadores - día 1 Rodrigo SaaModelo de negocio   transformadores - día 1 Rodrigo Saa
Modelo de negocio transformadores - día 1 Rodrigo SaaPTF
 
PPP - Eduardo SpĂłsito
PPP - Eduardo SpĂłsitoPPP - Eduardo SpĂłsito
PPP - Eduardo SpĂłsitoPTF
 
Neo marxism, neue marxismus, neuer marxismus, néo-marxisme
Neo marxism, neue marxismus, neuer marxismus, néo-marxismeNeo marxism, neue marxismus, neuer marxismus, néo-marxisme
Neo marxism, neue marxismus, neuer marxismus, néo-marxismeUNIVERSITY OF COIMBRA
 
Participantes PMA
Participantes PMAParticipantes PMA
Participantes PMAPTF
 
Exponegocios 2013
Exponegocios 2013Exponegocios 2013
Exponegocios 2013PTF
 
Relevamiento oferta 2000 ba
Relevamiento oferta 2000 baRelevamiento oferta 2000 ba
Relevamiento oferta 2000 baPTF
 
Pma 2013 no-hay-mktg-sin-personas_participantes_printable
Pma 2013 no-hay-mktg-sin-personas_participantes_printablePma 2013 no-hay-mktg-sin-personas_participantes_printable
Pma 2013 no-hay-mktg-sin-personas_participantes_printablePTF
 
Presentacion ds alumnos
Presentacion ds alumnosPresentacion ds alumnos
Presentacion ds alumnosPTF
 
Transformadores 2013 reflexiones print
Transformadores 2013 reflexiones printTransformadores 2013 reflexiones print
Transformadores 2013 reflexiones printPTF
 
Attending-to-the-Silence-Attending to the Silence_ The Birth and life of a Po...
Attending-to-the-Silence-Attending to the Silence_ The Birth and life of a Po...Attending-to-the-Silence-Attending to the Silence_ The Birth and life of a Po...
Attending-to-the-Silence-Attending to the Silence_ The Birth and life of a Po...Elya Steinberg
 

Viewers also liked (20)

20100224 foro ventas3 (2)
20100224 foro ventas3 (2)20100224 foro ventas3 (2)
20100224 foro ventas3 (2)
 
äœœć“ç”š
äœœć“ç”šäœœć“ç”š
äœœć“ç”š
 
hermann perfil
hermann perfilhermann perfil
hermann perfil
 
Blog-7-Self-Regulation
Blog-7-Self-RegulationBlog-7-Self-Regulation
Blog-7-Self-Regulation
 
PMA Guillermo Sicardi 2014 24 material gestion_competencias_resumen
PMA Guillermo Sicardi 2014 24 material gestion_competencias_resumenPMA Guillermo Sicardi 2014 24 material gestion_competencias_resumen
PMA Guillermo Sicardi 2014 24 material gestion_competencias_resumen
 
Modelo de negocio. Rodrigo Saa. TRS 2014
Modelo de negocio. Rodrigo Saa. TRS 2014Modelo de negocio. Rodrigo Saa. TRS 2014
Modelo de negocio. Rodrigo Saa. TRS 2014
 
Trans-generational and Inter-generational Trauma Body in Relationship Congres...
Trans-generational and Inter-generational Trauma Body in Relationship Congres...Trans-generational and Inter-generational Trauma Body in Relationship Congres...
Trans-generational and Inter-generational Trauma Body in Relationship Congres...
 
Estudio base para diseño producto residencial ba 2000
Estudio base para diseño producto residencial ba 2000Estudio base para diseño producto residencial ba 2000
Estudio base para diseño producto residencial ba 2000
 
Neurocuestionario
NeurocuestionarioNeurocuestionario
Neurocuestionario
 
Pgi miguel pato dia 01
Pgi miguel pato dia 01Pgi miguel pato dia 01
Pgi miguel pato dia 01
 
Modelo de negocio transformadores - día 1 Rodrigo Saa
Modelo de negocio   transformadores - día 1 Rodrigo SaaModelo de negocio   transformadores - día 1 Rodrigo Saa
Modelo de negocio transformadores - día 1 Rodrigo Saa
 
PPP - Eduardo SpĂłsito
PPP - Eduardo SpĂłsitoPPP - Eduardo SpĂłsito
PPP - Eduardo SpĂłsito
 
Neo marxism, neue marxismus, neuer marxismus, néo-marxisme
Neo marxism, neue marxismus, neuer marxismus, néo-marxismeNeo marxism, neue marxismus, neuer marxismus, néo-marxisme
Neo marxism, neue marxismus, neuer marxismus, néo-marxisme
 
Participantes PMA
Participantes PMAParticipantes PMA
Participantes PMA
 
Exponegocios 2013
Exponegocios 2013Exponegocios 2013
Exponegocios 2013
 
Relevamiento oferta 2000 ba
Relevamiento oferta 2000 baRelevamiento oferta 2000 ba
Relevamiento oferta 2000 ba
 
Pma 2013 no-hay-mktg-sin-personas_participantes_printable
Pma 2013 no-hay-mktg-sin-personas_participantes_printablePma 2013 no-hay-mktg-sin-personas_participantes_printable
Pma 2013 no-hay-mktg-sin-personas_participantes_printable
 
Presentacion ds alumnos
Presentacion ds alumnosPresentacion ds alumnos
Presentacion ds alumnos
 
Transformadores 2013 reflexiones print
Transformadores 2013 reflexiones printTransformadores 2013 reflexiones print
Transformadores 2013 reflexiones print
 
Attending-to-the-Silence-Attending to the Silence_ The Birth and life of a Po...
Attending-to-the-Silence-Attending to the Silence_ The Birth and life of a Po...Attending-to-the-Silence-Attending to the Silence_ The Birth and life of a Po...
Attending-to-the-Silence-Attending to the Silence_ The Birth and life of a Po...
 

Similar to 7. article azojete vol 11 77 88 alhassan

Literature Review - Final
Literature Review - FinalLiterature Review - Final
Literature Review - FinalRifan Fhazi
 
Evaluation of Risk Factors Affecting Cost Performance of Construction Project...
Evaluation of Risk Factors Affecting Cost Performance of Construction Project...Evaluation of Risk Factors Affecting Cost Performance of Construction Project...
Evaluation of Risk Factors Affecting Cost Performance of Construction Project...IJCMESJOURNAL
 
IRJET- Study and Analysis of Risk Management Strategies in Construction P...
IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...
IRJET- Study and Analysis of Risk Management Strategies in Construction P...IRJET Journal
 
IRJET- Risk Management in Residential Project by Primavera Software
IRJET- Risk Management in Residential Project by Primavera SoftwareIRJET- Risk Management in Residential Project by Primavera Software
IRJET- Risk Management in Residential Project by Primavera SoftwareIRJET Journal
 
IRJET- Risk Management in the Construction Project: Review
IRJET-  	  Risk Management in the Construction Project: ReviewIRJET-  	  Risk Management in the Construction Project: Review
IRJET- Risk Management in the Construction Project: ReviewIRJET Journal
 
Risk Management and Cost Overruns due to delays in Construction Project using...
Risk Management and Cost Overruns due to delays in Construction Project using...Risk Management and Cost Overruns due to delays in Construction Project using...
Risk Management and Cost Overruns due to delays in Construction Project using...IRJET Journal
 
Study and Need of Risk Management for Construction Projects
Study and Need of Risk Management for Construction ProjectsStudy and Need of Risk Management for Construction Projects
Study and Need of Risk Management for Construction ProjectsIRJET Journal
 
Risk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in ConstructionRisk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in ConstructionIRJET Journal
 
A Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project ManagementA Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project Managementijsrd.com
 
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSRISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSIRJET Journal
 
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSRISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSIRJET Journal
 
IRJET- Risk Management of Contracts in Construction Projects
IRJET- Risk Management of Contracts in Construction ProjectsIRJET- Risk Management of Contracts in Construction Projects
IRJET- Risk Management of Contracts in Construction ProjectsIRJET Journal
 
A Critical Review of the Causes of Cost Overrun in Construction Industries in...
A Critical Review of the Causes of Cost Overrun in Construction Industries in...A Critical Review of the Causes of Cost Overrun in Construction Industries in...
A Critical Review of the Causes of Cost Overrun in Construction Industries in...IRJET Journal
 
AN INTEGRATED PROJECT EVALUATION TOOL FOR PFI SEAPORT PROJECTS
AN INTEGRATED PROJECT EVALUATION TOOL FOR PFI SEAPORT PROJECTSAN INTEGRATED PROJECT EVALUATION TOOL FOR PFI SEAPORT PROJECTS
AN INTEGRATED PROJECT EVALUATION TOOL FOR PFI SEAPORT PROJECTSFredy Kurniawan
 
An Integrated Project Evaluation Tool for PFI Seaport Project
An Integrated Project Evaluation Tool for PFI Seaport ProjectAn Integrated Project Evaluation Tool for PFI Seaport Project
An Integrated Project Evaluation Tool for PFI Seaport ProjectFredy Kurniawan
 
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...IRJET Journal
 
EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...
EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...
EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...Sibo Kanyambari Aimable
 
The Identification of Risks and its Criticality in the Nigeria Construction I...
The Identification of Risks and its Criticality in the Nigeria Construction I...The Identification of Risks and its Criticality in the Nigeria Construction I...
The Identification of Risks and its Criticality in the Nigeria Construction I...Dr. Amarjeet Singh
 
Effect or Risk Management Methods on project performance in Rwandan Construct...
Effect or Risk Management Methods on project performance in Rwandan Construct...Effect or Risk Management Methods on project performance in Rwandan Construct...
Effect or Risk Management Methods on project performance in Rwandan Construct...Sibo Kanyambari Aimable
 

Similar to 7. article azojete vol 11 77 88 alhassan (20)

Literature Review - Final
Literature Review - FinalLiterature Review - Final
Literature Review - Final
 
Evaluation of Risk Factors Affecting Cost Performance of Construction Project...
Evaluation of Risk Factors Affecting Cost Performance of Construction Project...Evaluation of Risk Factors Affecting Cost Performance of Construction Project...
Evaluation of Risk Factors Affecting Cost Performance of Construction Project...
 
IRJET- Study and Analysis of Risk Management Strategies in Construction P...
IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...
IRJET- Study and Analysis of Risk Management Strategies in Construction P...
 
IRJET- Risk Management in Residential Project by Primavera Software
IRJET- Risk Management in Residential Project by Primavera SoftwareIRJET- Risk Management in Residential Project by Primavera Software
IRJET- Risk Management in Residential Project by Primavera Software
 
IRJET- Risk Management in the Construction Project: Review
IRJET-  	  Risk Management in the Construction Project: ReviewIRJET-  	  Risk Management in the Construction Project: Review
IRJET- Risk Management in the Construction Project: Review
 
Risk Management and Cost Overruns due to delays in Construction Project using...
Risk Management and Cost Overruns due to delays in Construction Project using...Risk Management and Cost Overruns due to delays in Construction Project using...
Risk Management and Cost Overruns due to delays in Construction Project using...
 
Study and Need of Risk Management for Construction Projects
Study and Need of Risk Management for Construction ProjectsStudy and Need of Risk Management for Construction Projects
Study and Need of Risk Management for Construction Projects
 
33 article text-127-1-10-20181005
33 article text-127-1-10-2018100533 article text-127-1-10-20181005
33 article text-127-1-10-20181005
 
Risk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in ConstructionRisk Analysis and Strategic Evaluation of Procurement Process in Construction
Risk Analysis and Strategic Evaluation of Procurement Process in Construction
 
A Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project ManagementA Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project Management
 
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSRISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
 
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSRISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
 
IRJET- Risk Management of Contracts in Construction Projects
IRJET- Risk Management of Contracts in Construction ProjectsIRJET- Risk Management of Contracts in Construction Projects
IRJET- Risk Management of Contracts in Construction Projects
 
A Critical Review of the Causes of Cost Overrun in Construction Industries in...
A Critical Review of the Causes of Cost Overrun in Construction Industries in...A Critical Review of the Causes of Cost Overrun in Construction Industries in...
A Critical Review of the Causes of Cost Overrun in Construction Industries in...
 
AN INTEGRATED PROJECT EVALUATION TOOL FOR PFI SEAPORT PROJECTS
AN INTEGRATED PROJECT EVALUATION TOOL FOR PFI SEAPORT PROJECTSAN INTEGRATED PROJECT EVALUATION TOOL FOR PFI SEAPORT PROJECTS
AN INTEGRATED PROJECT EVALUATION TOOL FOR PFI SEAPORT PROJECTS
 
An Integrated Project Evaluation Tool for PFI Seaport Project
An Integrated Project Evaluation Tool for PFI Seaport ProjectAn Integrated Project Evaluation Tool for PFI Seaport Project
An Integrated Project Evaluation Tool for PFI Seaport Project
 
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
 
EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...
EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...
EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...
 
The Identification of Risks and its Criticality in the Nigeria Construction I...
The Identification of Risks and its Criticality in the Nigeria Construction I...The Identification of Risks and its Criticality in the Nigeria Construction I...
The Identification of Risks and its Criticality in the Nigeria Construction I...
 
Effect or Risk Management Methods on project performance in Rwandan Construct...
Effect or Risk Management Methods on project performance in Rwandan Construct...Effect or Risk Management Methods on project performance in Rwandan Construct...
Effect or Risk Management Methods on project performance in Rwandan Construct...
 

More from Oyeniyi Samuel

Particle Swarm Optimization (PSO)-Based Distributed Power Control Algorithm f...
Particle Swarm Optimization (PSO)-Based Distributed Power Control Algorithm f...Particle Swarm Optimization (PSO)-Based Distributed Power Control Algorithm f...
Particle Swarm Optimization (PSO)-Based Distributed Power Control Algorithm f...Oyeniyi Samuel
 
Equilibrium and Kinetic Studies of Adsorption of Safranin-O from Aqueous Solu...
Equilibrium and Kinetic Studies of Adsorption of Safranin-O from Aqueous Solu...Equilibrium and Kinetic Studies of Adsorption of Safranin-O from Aqueous Solu...
Equilibrium and Kinetic Studies of Adsorption of Safranin-O from Aqueous Solu...Oyeniyi Samuel
 
Design Description of a Tentacle Based Scanning System
Design Description of a Tentacle Based Scanning SystemDesign Description of a Tentacle Based Scanning System
Design Description of a Tentacle Based Scanning SystemOyeniyi Samuel
 
Profiled Deck Composite Slab Strength Verification: A Review
Profiled Deck Composite Slab Strength Verification: A ReviewProfiled Deck Composite Slab Strength Verification: A Review
Profiled Deck Composite Slab Strength Verification: A ReviewOyeniyi Samuel
 
Optimization of Mechanical Expression of Castor Seeds Oil (Ricinus communis) ...
Optimization of Mechanical Expression of Castor Seeds Oil (Ricinus communis) ...Optimization of Mechanical Expression of Castor Seeds Oil (Ricinus communis) ...
Optimization of Mechanical Expression of Castor Seeds Oil (Ricinus communis) ...Oyeniyi Samuel
 
Inundation and Hazard Mapping on River Asa, using GIS
Inundation and Hazard Mapping on River Asa, using GISInundation and Hazard Mapping on River Asa, using GIS
Inundation and Hazard Mapping on River Asa, using GISOyeniyi Samuel
 
A Review of Smart Grids Deployment Issues in Developing Countries
A Review of Smart Grids Deployment Issues in Developing CountriesA Review of Smart Grids Deployment Issues in Developing Countries
A Review of Smart Grids Deployment Issues in Developing CountriesOyeniyi Samuel
 
NOx Emission in Iron and Steel Production: A Review of Control Measures for S...
NOx Emission in Iron and Steel Production: A Review of Control Measures for S...NOx Emission in Iron and Steel Production: A Review of Control Measures for S...
NOx Emission in Iron and Steel Production: A Review of Control Measures for S...Oyeniyi Samuel
 
Artificial Neural Network Modelling of the Energy Content of Municipal Solid ...
Artificial Neural Network Modelling of the Energy Content of Municipal Solid ...Artificial Neural Network Modelling of the Energy Content of Municipal Solid ...
Artificial Neural Network Modelling of the Energy Content of Municipal Solid ...Oyeniyi Samuel
 
Development of Inundation Map for Hypothetical Asa Dam Break using HEC-RAS an...
Development of Inundation Map for Hypothetical Asa Dam Break using HEC-RAS an...Development of Inundation Map for Hypothetical Asa Dam Break using HEC-RAS an...
Development of Inundation Map for Hypothetical Asa Dam Break using HEC-RAS an...Oyeniyi Samuel
 
Job Safety Assessment of Woodwork Industry in the South-western Nigeria
Job Safety Assessment of Woodwork Industry in the South-western NigeriaJob Safety Assessment of Woodwork Industry in the South-western Nigeria
Job Safety Assessment of Woodwork Industry in the South-western NigeriaOyeniyi Samuel
 
Anaerobicaly - Composted Environmental Wastes as Organic Fertilizer and Ident...
Anaerobicaly - Composted Environmental Wastes as Organic Fertilizer and Ident...Anaerobicaly - Composted Environmental Wastes as Organic Fertilizer and Ident...
Anaerobicaly - Composted Environmental Wastes as Organic Fertilizer and Ident...Oyeniyi Samuel
 
Security Architecture for Thin Client Network
Security Architecture for Thin Client NetworkSecurity Architecture for Thin Client Network
Security Architecture for Thin Client NetworkOyeniyi Samuel
 
Algorithm for the Dynamic Analysis of Plane Rectangular Rigid Frame Subjected...
Algorithm for the Dynamic Analysis of Plane Rectangular Rigid Frame Subjected...Algorithm for the Dynamic Analysis of Plane Rectangular Rigid Frame Subjected...
Algorithm for the Dynamic Analysis of Plane Rectangular Rigid Frame Subjected...Oyeniyi Samuel
 
Comparism of the Properties and Yield of Bioethanol from Mango and Orange Waste
Comparism of the Properties and Yield of Bioethanol from Mango and Orange WasteComparism of the Properties and Yield of Bioethanol from Mango and Orange Waste
Comparism of the Properties and Yield of Bioethanol from Mango and Orange WasteOyeniyi Samuel
 
Development of Farm Records Software
Development of Farm Records SoftwareDevelopment of Farm Records Software
Development of Farm Records SoftwareOyeniyi Samuel
 
Compressive Strength of Concrete made from Natural Fine Aggregate Sources in ...
Compressive Strength of Concrete made from Natural Fine Aggregate Sources in ...Compressive Strength of Concrete made from Natural Fine Aggregate Sources in ...
Compressive Strength of Concrete made from Natural Fine Aggregate Sources in ...Oyeniyi Samuel
 
Evaluation of Chemical and Physico-Mechanical Properties of Ado-Ekiti Natural...
Evaluation of Chemical and Physico-Mechanical Properties of Ado-Ekiti Natural...Evaluation of Chemical and Physico-Mechanical Properties of Ado-Ekiti Natural...
Evaluation of Chemical and Physico-Mechanical Properties of Ado-Ekiti Natural...Oyeniyi Samuel
 
Modeling and Simulation of Pyrolysis Process for a Beech Wood Material
Modeling and Simulation of Pyrolysis Process for a Beech Wood MaterialModeling and Simulation of Pyrolysis Process for a Beech Wood Material
Modeling and Simulation of Pyrolysis Process for a Beech Wood MaterialOyeniyi Samuel
 
An Investigation into the Effectiveness of Machine Learning Techniques for In...
An Investigation into the Effectiveness of Machine Learning Techniques for In...An Investigation into the Effectiveness of Machine Learning Techniques for In...
An Investigation into the Effectiveness of Machine Learning Techniques for In...Oyeniyi Samuel
 

More from Oyeniyi Samuel (20)

Particle Swarm Optimization (PSO)-Based Distributed Power Control Algorithm f...
Particle Swarm Optimization (PSO)-Based Distributed Power Control Algorithm f...Particle Swarm Optimization (PSO)-Based Distributed Power Control Algorithm f...
Particle Swarm Optimization (PSO)-Based Distributed Power Control Algorithm f...
 
Equilibrium and Kinetic Studies of Adsorption of Safranin-O from Aqueous Solu...
Equilibrium and Kinetic Studies of Adsorption of Safranin-O from Aqueous Solu...Equilibrium and Kinetic Studies of Adsorption of Safranin-O from Aqueous Solu...
Equilibrium and Kinetic Studies of Adsorption of Safranin-O from Aqueous Solu...
 
Design Description of a Tentacle Based Scanning System
Design Description of a Tentacle Based Scanning SystemDesign Description of a Tentacle Based Scanning System
Design Description of a Tentacle Based Scanning System
 
Profiled Deck Composite Slab Strength Verification: A Review
Profiled Deck Composite Slab Strength Verification: A ReviewProfiled Deck Composite Slab Strength Verification: A Review
Profiled Deck Composite Slab Strength Verification: A Review
 
Optimization of Mechanical Expression of Castor Seeds Oil (Ricinus communis) ...
Optimization of Mechanical Expression of Castor Seeds Oil (Ricinus communis) ...Optimization of Mechanical Expression of Castor Seeds Oil (Ricinus communis) ...
Optimization of Mechanical Expression of Castor Seeds Oil (Ricinus communis) ...
 
Inundation and Hazard Mapping on River Asa, using GIS
Inundation and Hazard Mapping on River Asa, using GISInundation and Hazard Mapping on River Asa, using GIS
Inundation and Hazard Mapping on River Asa, using GIS
 
A Review of Smart Grids Deployment Issues in Developing Countries
A Review of Smart Grids Deployment Issues in Developing CountriesA Review of Smart Grids Deployment Issues in Developing Countries
A Review of Smart Grids Deployment Issues in Developing Countries
 
NOx Emission in Iron and Steel Production: A Review of Control Measures for S...
NOx Emission in Iron and Steel Production: A Review of Control Measures for S...NOx Emission in Iron and Steel Production: A Review of Control Measures for S...
NOx Emission in Iron and Steel Production: A Review of Control Measures for S...
 
Artificial Neural Network Modelling of the Energy Content of Municipal Solid ...
Artificial Neural Network Modelling of the Energy Content of Municipal Solid ...Artificial Neural Network Modelling of the Energy Content of Municipal Solid ...
Artificial Neural Network Modelling of the Energy Content of Municipal Solid ...
 
Development of Inundation Map for Hypothetical Asa Dam Break using HEC-RAS an...
Development of Inundation Map for Hypothetical Asa Dam Break using HEC-RAS an...Development of Inundation Map for Hypothetical Asa Dam Break using HEC-RAS an...
Development of Inundation Map for Hypothetical Asa Dam Break using HEC-RAS an...
 
Job Safety Assessment of Woodwork Industry in the South-western Nigeria
Job Safety Assessment of Woodwork Industry in the South-western NigeriaJob Safety Assessment of Woodwork Industry in the South-western Nigeria
Job Safety Assessment of Woodwork Industry in the South-western Nigeria
 
Anaerobicaly - Composted Environmental Wastes as Organic Fertilizer and Ident...
Anaerobicaly - Composted Environmental Wastes as Organic Fertilizer and Ident...Anaerobicaly - Composted Environmental Wastes as Organic Fertilizer and Ident...
Anaerobicaly - Composted Environmental Wastes as Organic Fertilizer and Ident...
 
Security Architecture for Thin Client Network
Security Architecture for Thin Client NetworkSecurity Architecture for Thin Client Network
Security Architecture for Thin Client Network
 
Algorithm for the Dynamic Analysis of Plane Rectangular Rigid Frame Subjected...
Algorithm for the Dynamic Analysis of Plane Rectangular Rigid Frame Subjected...Algorithm for the Dynamic Analysis of Plane Rectangular Rigid Frame Subjected...
Algorithm for the Dynamic Analysis of Plane Rectangular Rigid Frame Subjected...
 
Comparism of the Properties and Yield of Bioethanol from Mango and Orange Waste
Comparism of the Properties and Yield of Bioethanol from Mango and Orange WasteComparism of the Properties and Yield of Bioethanol from Mango and Orange Waste
Comparism of the Properties and Yield of Bioethanol from Mango and Orange Waste
 
Development of Farm Records Software
Development of Farm Records SoftwareDevelopment of Farm Records Software
Development of Farm Records Software
 
Compressive Strength of Concrete made from Natural Fine Aggregate Sources in ...
Compressive Strength of Concrete made from Natural Fine Aggregate Sources in ...Compressive Strength of Concrete made from Natural Fine Aggregate Sources in ...
Compressive Strength of Concrete made from Natural Fine Aggregate Sources in ...
 
Evaluation of Chemical and Physico-Mechanical Properties of Ado-Ekiti Natural...
Evaluation of Chemical and Physico-Mechanical Properties of Ado-Ekiti Natural...Evaluation of Chemical and Physico-Mechanical Properties of Ado-Ekiti Natural...
Evaluation of Chemical and Physico-Mechanical Properties of Ado-Ekiti Natural...
 
Modeling and Simulation of Pyrolysis Process for a Beech Wood Material
Modeling and Simulation of Pyrolysis Process for a Beech Wood MaterialModeling and Simulation of Pyrolysis Process for a Beech Wood Material
Modeling and Simulation of Pyrolysis Process for a Beech Wood Material
 
An Investigation into the Effectiveness of Machine Learning Techniques for In...
An Investigation into the Effectiveness of Machine Learning Techniques for In...An Investigation into the Effectiveness of Machine Learning Techniques for In...
An Investigation into the Effectiveness of Machine Learning Techniques for In...
 

Recently uploaded

Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEslot gacor bisa pakai pulsa
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 

Recently uploaded (20)

Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 

7. article azojete vol 11 77 88 alhassan

  • 1. Arid Zone Journal of Engineering, Technology and Environment. August, 2015; Vol. 11: 77-88 Copyright© Faculty of Engineering, University of Maiduguri, Nigeria. Print ISSN: 1596-2490, Electronic ISSN: 2545-5818 www.azojete.com.ng RISK FACTORS INFLUENCING CONSTRUCTION PROCUREMENT PERFORMANCE IN NIGERIA Alhassan Dahiru1 and Aminu Muhammad Bashir2 (Department of Quantity Surveying, Faculty of Earth & Environmental Sciences, Bayero University, Kano, Nigeria.) Phone - 08020793242 Abstract One of the challenges facing construction procurement performance is the failure to determine the risk related factors limiting its success. These risk factors can cause a significant increase in the procurement cost leading to an increase in the overall project cost. The purpose of this study is to identify and evaluate the risk factors influencing construction procurement performance with a view to achieve the overall project performance. The objectives are to establish a relative significance index score for the most important risk factors limiting the procurement performance of the projects. A self administered questionnaire was employed to the construction industry professionals for responses. A total of 78 questionnaires were distributed to these professionals (architects, quantity surveyors, engineers, and contractors) but 62 were returned and analyzed using influential index and later ranked in order of importance. Results of the analysis indicate a disparity in terms of ranking of the factors influencing construction procurement performance. Corruption related risk, conflict of interest, ineffective project technical feasibility, and lack of commitment to transparency were found to be the most significant factors limiting construction procurement performance. Communication barriers and unconfidential tender evaluation process were found to be the low weighted risk factors. The findings can serve as a supportive mechanism for risks management in public construction procurement management. Therefore, construction procurement personnel at all levels of government may find this study relevant, while improving construction procurement performance in the country. It is recommended that construction procurement system should be focused on risks related to corruption, conflict of interest, and effective technical feasibility for improving the overall project performance. Keywords: Construction project, procurement performance, risk factors, risk management. 1. Introduction The pace of change in the construction procurement performance has imposed additional demands on risk management. Risk management is a vital project procurement performance tool for reducing uncertainty and improving decision making. Risk cannot be avoided but must be recognized, assessed and manage for better procurement performance. The aim of this study is to assess key risk factors affecting construction procurement performance from stakeholders‟ perspective. The study is concerned with performance risk as it is often argued that if procurement planning procedure is adequately supported with a comprehensive strategy with regard to the most significant risk factors affecting procurement performance will improve the overall project performance (Tipili and Ilyasu, 2014). Construction procurement efficiency and effectiveness largely depends on the identification of critical factors limiting its performance. Risk is an uncertain event or set of circumstances that could occur, have an effect on the achievement of the procurement planning objectives. Risk factors is inherent in every construction procurement planning procedure and sometimes is impossible for these risks to be avoided (Abba, 2008).
  • 2. Alhassan and Aminu: Risk factors influencing construction procurement performance in Nigeria. AZOJETE, 11: 77-88 78 Furthermore, during the procurement planning process of the project development, most of these risk factors are not properly identified and assessed (Faruk et al., 2013). Fabi et al. (2015) has also advocate that no procurement system is risk free. Therefore, it becomes imperatives to identify and assess risk factors related to procurement planning procedures for improving the overall procurement performance. 1.1 Risk Factors Influencing Construction Projects Generally The Nigeria‟s construction industry is like other developing countries, is dramatically experiencing a highly risk prone, due to the complex and dynamic environments (Tipili and Ibrahim, 2015). Thus, such nature is creating an atmosphere of high uncertainty and risks. This consequently affects the overall project performance. In an effort to identify and assess construction risk factors, Tipili and Ibrahim (2015) have jointly identified and assessed 27 key risk factors affecting public construction project from project stakeholder perspectives (clients, contractors and consultants). The study reveals that these risk factors spread through the whole project life cycle and many risks occur at more than one phase, with the construction stage with risky phase. On the risk categories level all the stakeholders agreed on the finance category as the main factor threatening project completion, and the labour and equipment category as having the least impact. Furthermore, clients and consultants have different perception on the impact of design category. Moreover, the study had elaborated the stakeholder role and responsibility on the management of the 27 identified risks and include: seven (7) key risks related to clients such as: tight project schedule; decision making process; payment for completion work; delay in site mobilization; design modification; financing project by client; and excessive change order ranked the least factor in order of priority. Tight project schedule was ranked as the most significant risk factors among the seven identified factors related to clients, which infers that formulating an appropriate schedule in the conceptual/feasibility phase is never more constructive to the project delivery. The clients should prepare a practical schedule allowing sufficient but not redundant time to accommodate all design and construction activities. As time and cost are always closely correlated, a lengthy schedule will undoubtedly wreck the project cost benefit. Twelve (12) key risks related to contractors were evaluated and include: inadequate program planning; material delivery; contractor experience; labour performance; material waste handling; availability of material in the market; compliance of material to specification; design team experience; complexity of project design; necessity of specific skill; labour and management skill relation; and payment for completion work ranked the least risk factor. Thus, inadequate construction program planning was ranked the most influential risk factor related to contractors. This finding may result from inadequate program scheduling, innovative design or contractors„lack of knowledge in planning construction programs. To reduce the negative influence of the two risks, an informative program scheduling should be worked out in the design phase, and the constructability of innovative design should be examined. More importantly, the
  • 3. Arid Zone Journal of Engineering, Technology and Environment. August, 2015; Vol. 11: 77-88 79 abilities to manage construction programs and implement innovative design should be used as key criteria in appointing contractors. Eight (8) key risks related to consultants were also discovered by the researchers and these are: design modification; unclear responsibility; compliance of material to specification; cost estimation accuracy; delay in site mobilization; design modification; clarity of details in drawing; excessive change order. The survey indicates that design modification was ranked the most important factor related to consultants in limiting public construction projects. This popularly arisen in the design phase of a project and may result from issues such as variations by the client and defective designs. To avoid defective design, the design teams need not only to fully understand what the clients want as defined in the project brief, but also to establish an efficient communication scheme among the designers. Inadequate program scheduling often appears in projects with a tight schedule when some programs need to be reduced to meet the project timeline. Moreover, uncertainty surrounds most facets of construction projects, which makes it impossible to accurately predict the time required for various programs. Choosing experienced designers can help to minimize the difference between the proposed and practical program schedules. Incomplete or inaccurate cost estimate is directly related to the designers/consultants„ knowledge and attitude towards work. 1.2 Risk Factors Limiting Construction Procurement Performances Procurement performance refers to proper planning and scheduling of procurement procedures in terms of efficiency and effectiveness for improving the overall project performance. Rrisk identification is defined as the process of systematically and continuously identifying, categorizing and assessing the initial significance of risk associated with construction procurement performance (Odeyinka & Lowe, 2000). Managing changes has led to the introduction of techniques for risk assessment as a major part of the planning process. Risk assessment concentrates on quantifying identified risks by using statistical analysis, since the identified risk in most cases can be either quantitively or subjectively assessed factors (Augustine et al., 2013). Risk factors appear to influence the objective performance of procurement process. If not adequately identified and managed may affect the overall project success especially in terms of achieving value for money. Risk identification is the first phase of risk management process, which can be divided into four major phases: risk identification, risk analysis, risk response, and risk monitoring and evaluation (Tipili & Ilyasu, 2014). According to Augustine et al. (2013) the objectives of risk identification are as follows: to identify all significant types and sources of risk and uncertainty associated with the objectives and their key parameters; to ascertain the causes of each risk; to assess how risks are related to other risks and how risks should be classified and grouped for evaluation.
  • 4. Alhassan and Aminu: Risk factors influencing construction procurement performance in Nigeria. AZOJETE, 11: 77-88 80 Risk identification is a beginning step of risk management. It yields types, sources, causes, characteristics, and relations of risks associated with the problem considered, all of which will be used to analyze and respond each risk in the subsequent phases. Tipili and Ibrahim (2015) had defined risk identification as a process for uncovering any risks that could potentially affect a process. This step is of considerable importance as other processes such as risk analysis and response can only be undertaken on the potential risks that have been identified (Odeyinka & Lowe, 2000). Risk identification is a simple but difficult task as there are no absolute procedures that may be used to identify risks in a procurement planning procedure. Project managers often rely heavily on their experience and on the insight of other key personnel involved in the process (Odeyinka & Lowe, 2000). Depending on the process documentation available and the nature of the process, a variety of considerations may prompt risk discovery. Regarding risk, Augustine et al. (2013) noted that managers need to focus on the interface between the consultant and the client, between departments of the client organization, between phases or tasks of a client process, or between geographic areas. They further suggest that the procurement planning and schedule should clearly show dependencies between tasks in order to help pinpoint risk-prone areas. Alternatively, managers may use process maps that show interfaces between processes or tasks. At the stage of risk identification it is important to identify the risk source and its effect. Within the framework of risk management, there are four alternative strategies: risk avoidance, risk reduction, risk transfer, and risk retention (Odeyinka & Lowe, 2000; Augustine et al., 2013). Risk Avoidance: This method of mitigation involves the removal of the causes of the risk and therefore the risk itself. The most simple form of risk avoidance is not to tender for a project. Also risk avoidance may involve considering and adopting alternative courses of action or using the exemption clauses in contracts. Risk avoidance approach should be addressed whenever the level of risk is high enough to render a project unfeasible. Risk Reduction: Risk reduction is another approach that might be used to mitigate risk. This method is directed towards decreasing the contractor's potential exposure to risk by two ways: reducing the probability of risk; and reducing the impact of a risk. Risk reduction methods may sometimes require some initial investment which should then reduce the likelihood of the risk occurring. Risk reduction should be addressed whenever the level of risk is unacceptable and alternative action is available. Risk reduction invariably leads to greater confidence regarding the project's outcome. However, risk reduction will result in an increase in the base cost but should offer a significantly greater procurement performance leading to the reduction in the level of the overall project cost. Risk Transfer: Through negotiation, the contractor can transfer risk to other parties such as the owner, subcontractors, or suppliers. Commonly this can be achieved through a provision in a contracts or a new contract placement. Transference of risk comprises the passing of risks to those who are more capable of maintaining control and influencing the outcome of the risk.
  • 5. Arid Zone Journal of Engineering, Technology and Environment. August, 2015; Vol. 11: 77-88 81 It's worth mentioning that some texts view insurance as risk reduction whilst others consider it as risk transfer. Both of the two views are considered correct. When some risk is transferred and some is retained this is known as risk-sharing. This approach should be adopted when the risk exposure is beyond the control of one party and it's important that each party acknowledges the value of the portion of risk for which he is responsible. Risk Retention: This method of risk retention should be used when all the avenues for other risk mitigation strategies are blocked. In other words, this method should only be used for the residual risks that cannot be mitigated by the previous three strategies. In this method, residual risks undergo a detailed quantitative analysis in order to allocate an appropriate level of procurement performance. This does not imply that these risks would by then be ignored and not monitored throughout the cycle of the project. In fact, they should be under the eye and control of management in order to ensure that they are contained within the procurement performance. 1.3 Construction Project Delivery and Procurement Performance Construction projects are becoming increasingly complex thereby resulting in complex procurement processes. In an effort to improve the procurement planning procedures capable for improving procurement performance, several studies have indicated the key factors influencing public construction procurement process and include: economy; value for money, ethical standards, competition and transparency and accountability (OECD, 2005; Dahiru, 2014; Babatunde et al., 2010). To obtain the best service and performance from the construction procurement system, risk related factors should be identify at each process for realizing project‟s success (Odeyinka & Lowe, 2000; Babatunde et al., 2010; Augustine et al., 2013). Successful construction projects should result in project delivered on time, to cost, and to the desired quality capable of performing the specific business function of the client (Bureau of Public Procurement 2007); Fabi et al., 2015). Procurement process in Nigeria involves a wide range of challenges that stakeholders face on project delivery and according to Fabi et al., (2015) these include: absence of internal management structure, lack of social drive, low technical and management capacity as well as low multi stakeholder approach. These challenges have led to difficulty in procuring public projects and are a major concern to all stakeholders because the Nigerian construction industry is perceived as one engrossed with corruption and bureaucracy (Alfred, 2008). 2. Research Methodology The study covers a systematic approach to review some literature on the nature and application of construction procurement systems in Nigeria. This provided the foundation upon which the study was premised. The constraints surrounding the application of construction procurement systems was reviewed which also provides good basis for understanding where the problems exist and the resultant gap in procurement performance. A quantitative approach using a well- structured questionnaire survey was chosen for this research since a wide range of responses are
  • 6. Alhassan and Aminu: Risk factors influencing construction procurement performance in Nigeria. AZOJETE, 11: 77-88 82 required and in view of its ability to facilitate comparison of themes (Sambo, 2005). A vast amount of information was collected using a semi-structured interview with construction procurement practitioners in government sector, construction consultants and academics who were in one way or the other involved in the delivery of construction projects in Nigeria. Project participants in construction projects delivery (such as: contractors; architects; quantity surveyors; and engineers) in the northern part of the country were considered for the study. Data were specifically collected from Kano, Kaduna and Abuja. These places were selected because of frequent construction activities that are carried out in these regions. Alongside with this, more construction and consulting firms were commonly found available in these areas and this led to have more experienced construction procurement stakeholders as been the respondents. Questionnaire was designed and administered on 78 randomly selected construction professionals involved in a nearly completed or recently completed construction projects in the study area. The questionnaire was based on a rank scale of 1-5 to be ranked among the various effects of risk factors that can occur to construction procurement performance. A total of seventy eight (78) questionnaires were distributed but sixty two (62) (79%) of the data were retrieved as shown in Table 1. Of these, 30 responses came from the private sector and 32 from the public sector. All the respondents were either directors, principal partners or managers belonging to either client‟s organisation, consultants or private financiers and developers. The data provided by the questionnaire were analyzed using influence index. The Questionnaire was developed on one hand using some key indicators from the literature review and from information initially collected using a series of semi-structured interviews. A total of 20 risk factors were included in the questionnaire and these factors were obtained from the literature reviewed. The complete questionnaire comprises of three parts: questions about respondent's academic and professional background, experience and questions on perceived risk factors of construction procurement performances in Nigeria. Table 1: Categorization of respondents found in the study area Respondents Frequency Percentage % Cumulative % Architects Contractors Engineers Quantity Surveyors Total 14 17 15 16 62 22.58 27.42 24.19 25.81 100 22.58 50.00 74.19 100 Finally, a survey based on a questionnaire was also done to solicit nationwide expert opinions on the relative significance of risk factors limiting construction procurement performances in the country. The results of this survey are presented in this paper. The survey was conducted
  • 7. Arid Zone Journal of Engineering, Technology and Environment. August, 2015; Vol. 11: 77-88 83 amongst and within organisations, ministries, and private practitioners in various disciplines who have been involved in construction projects delivery. Although many studies have shown that, electronic survey elicits higher response rate from the respondents (Alfred, 2008), this research did not find it expedient to conduct any online survey. The survey also adopted a convenient sampling technique rather than random sampling because there is no database for organizations involved in construction procurement system in Nigeria. Background information on respondents‟ profile is provided in table 2. This table shows that 17.74% of the respondents have the qualification of PhD, while 20.97% have masters in their respective field area of specialization. 25.81 have first degrees, 19.35% have either HND or ND in their various fields of disciplines. This summarily shows that majority of the respondents have high qualification in their field of endeavours. More importantly, 100% of the respondents are corporate members of their respective professional bodies (Table 3). In addition, 70.97% of them have an average of 12years of experience in the construction procurement systems (Table 4). From the foregoing, it can be concluded that the respondents could be relied upon for the information provided for this study for the purpose of analysis. Table 2: Academic Qualification of respondents Respondents Frequency Percentage % Cumulative % PhD/M.Phil MSc/M.Eng/M.Tech BSc/B.Eng/B.Tech HND/ND Others Total 11 13 16 12 10 62 17.74 20.97 25.81 19.35 16.13 100 17.74 38.71 64.52 83.87 100 Table 3: Professional Qualification of respondents Respondents Frequency Percentage % Cumulative % MNIA MNIOB MNSE MNIQS Total 12 15 17 18 62 19.35 24.20 27.42 29.03 100 19.35 43.55 70.97 100
  • 8. Alhassan and Aminu: Risk factors influencing construction procurement performance in Nigeria. AZOJETE, 11: 77-88 84 Table 4: Procurement Experience of respondents Respondents Frequency Percentage % Cumulative % 1 – 5 years 6 – 10 years 11 – 15 years 16 – 20 years Above 20 years 6 12 16 18 10 9.68 19.35 25.81 29.03 16.13 9.68 29.03 54.84 83.87 100 3. Survey Data Analysis and Results The outcome of the data collected was critically analysed and summarised in order to determine the strength of different opinions and their relative importance. The objective is to collect data on the attitudes, opinion and behavioural disposition of the respondents. The relative importance of 20 risk factors identified from the literature review was explored by means of Likert rating scale. This, according to Sambo (2005), is one of the acceptable methods of scale rating in construction management research. Based on all the gathered information, influence index was used as to find the most influential risk factors limiting the procurement performance in Nigeria. Respondents were asked to rank the influence of these factors over the procurement performance for which the relative information have been provided on a five point scale (1 = very low; 2 = low; 3 = medium; 4 = high; and 5 = very high). Thus the significance of adopting the influence index is to determine the most influential risk factors limiting procurement performance. This method was previously used by Arif et al (2010) in their effort to determined factors influencing the accuracy of cost estimates of construction projects in Pakistan. Hence, the influence index of each factor was calculated using the following formula: Influence Index = ∑ (Influence score X Response frequency at that influence score) Total Number of Responses
  • 9. Arid Zone Journal of Engineering, Technology and Environment. August, 2015; Vol. 11: 77-88 85 Table 5: Ranking of Risk Factors Influencing Construction Procurement Performance Risk Factors Influencing Construction Procurement Performance Influential Factors Influential Index Architects Q/Surveyors Contractors C/Engineer Weighted Average Rank Corruption related risks Conflict of interest Ineffective project technical feasibility Lack of commitment to transparency Discrimination of tenderers Unequal treatment of tenders Non early involvement of consultants Expertise level of procurement personnel Impact of contract type Level of project team integration Lack of good governance Unavailability of procurement structure Unfavourable procurement framework Levels of project team commitment Inconsistency of government policies Inappropriate condition of contract Use of inappropriate procurement strategy Ineffective procurement approach Communication barriers Unconfidential tender evaluation process 6.9 6.7 6.7 6.6 6.5 6.4 6.2 6.2 6.1 6.1 5.9 6.0 5.7 5.2 5.2 5.3 5.3 5.2 5.0 5.0 6.9 6.8 6.6 6.5 6.3 6.3 6.3 6.1 6.0 5.7 5.6 5.5 5.5 5.6 5.6 5.2 5.2 5.0 5.1 4.9 6.8 6.7 6.6 6.5 6.5 6.3 6.2 6.0 6.0 5.8 5.8 5.7 5.6 5.8 5.3 5.5 5.0 5.1 5.0 4.8 6.8 6.8 6.7 6.7 6.7 6.6 6.6 6.5 6.5 6.5 6.4 6.2 6.1 6.0 5.8 5.6 5.6 5.2 5.2 5.1 6.85 6.75 6.65 6.58 6.50 6.40 6.33 6.20 6.15 6.03 5.93 5.85 5.73 5.65 5.48 5.40 5.28 5.13 5.08 4.95 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
  • 10. Alhassan and Aminu: Risk factors influencing construction procurement performance in Nigeria. AZOJETE, 11: 77-88 86 3.1 Ranking of Perceived Risk Factors Influencing Construction Procurement Performance From the analysis shown in table 5, the influence index values for the 20 different risk factors is presented ranging from 6.85 to 4.95 (average weighted). It can be seen that factors, such as corruption related risks ( with an average weighted influence value of 6.85), conflict of interest (6.75), ineffective project technical feasibility (6.65), lack of commitment to transparency (6.58), discrimination of tenderers (6.50), unequal treatment of tenders (6.40), non early involvement of consultants (6.33), expertise level of procurement personnel (6.20), impact of contract type (6.15), and level of project team integration (6.03) top the first ten (10) most influential risk factors limiting construction procurement performance. The top four (4) most risk factors influencing construction procurement performance were corruption related risks, conflict of interest, ineffective project technical feasibility, and lack of commitment to transparency. This shows that lack of contracting mind-set and distrust within the public sector usually affect construction procurement performance. Although, there were no official reports on cases about conflicting of interest in public procurement management, it is however believed that issues such as lack of commitment to transparency and accountability as well as influence of corruption are serious problems that can results to the lost of contracting mindset and distrust between construction project parties. Therefore, unless government commitment in the fight against corruption continues to yield positive results, there would be limited genuine commitment and trust of the public and private parties in construction contract. On issue has to do with ineffective project technical feasibility, it is important to note that procuring construction projects required intensive study and analysis to be able to verify whether it can deliver value for money or not. This is therefore more indicative of the apparent necessity for government to be of adequately poised in providing an astute operational framework for such deals. Good Governance provides sound economic policies, administrative platform that promote construction procurement performance (Babatunde et al., 2010 and Dahiru, 2014). This cannot be achieved with corrupt officials within the public sector. Although it is important to note that government had established an institution and a structure called the Bureau for Public Procurement Act (BPP Act, 2007) to principally regulate procurement process and ensure accountability and probity in the public sector contract award process, there is still an increasing evidence that corruption is one of the problems which still confront project procurement process in Nigeria (Alfred, 2008 and Dahiru, 2014). Today, the World Bank funding for services in developing countries has become inadequate and ineffective due to effect of corruption (Akelere and Gidado 2003).
  • 11. Arid Zone Journal of Engineering, Technology and Environment. August, 2015; Vol. 11: 77-88 87 4. Conclusion Construction procurement procedures has many challenges on performances and these challenges are evident in risk factors associated with the procurement planning and scheduling and consequent performance of the procurement process. The study had evaluated some mechanisms limiting the performance of construction procurement management with a view to improve integrity in the processes. Factors, such as corruption related risks, conflict of interest, ineffective project technical feasibility, lack of commitment to transparency, discrimination of tenderers, unequal treatment of tenders, non early involvement of consultants, expertise level of procurement personnel, impact of contract type, and level of project team integration top the list of the most influential factors limiting construction procurement performance in Nigeria. Therefore the findings can serve as a supportive mechanism for risks management in public construction procurement management in Nigeria. Hence, construction procurement personnel at all levels of government may found this study relevant while improving construction procurement performance in the country. References Abba, D. 2008. Assessment of contingency allowance at tender stage. Unpublished BSc thesis, Department of Quantity Surveying, Ahmadu University Zaria. Alfred, OO. 2008. Due Process and Contractor Selection for Public works in Nigeria. Procurement of construction and reconstruction projects in the international context. University of Newcastle, UK, pp 1-14 Arif, F., Lodi, SH. and Farooqui, RU. 2010. Accuracy of Cost Estimates of Construction Projects in Pakistan. Paper presented at the 2nd International conference on construction in Developing countries held in Egypt. Augustine, IE., Ajayi, JR., Ade, BA., and Edwin, AA. 2013. Assessment of risk management practices in Nigerian construction industry: toward establishing risk management index. Int. J. Pure Appl. Sci. Technol., 16(2), pp. 20-31 Babatunde, SO., Opawole, A., Ujaddughe, IC. 2010. Appraisal of Project Procurement Methods in the Nigerian Construction Industry. Journal of Civil Engineering Dimension, Vol. 12, No. 1 March, 2010 pp. 1 – 7 Bureau of Public Procurement, BPP. 2007. Procurement Procedures Manual for Public Procurement in Nigeria. The principal authority for establishing general policies and guidelines relating to public sector procurement in Nigeria. Dahiru, A. 2014. Conflict of interest in public procurement management in Nigeria. A paper presented at the Nigerian Institute of Quantity Surveyors (NIQS) National Seminar under the theme “Procurement of Construction Works and Services – Adapting to Contemporary Challenges for Enhanced National Development” held at International Hotel, Gombe.
  • 12. Alhassan and Aminu: Risk factors influencing construction procurement performance in Nigeria. AZOJETE, 11: 77-88 88 Fabi, JK., Awolesi, JA., and Akinseinde, OA. 2015. An assessment of effect of procurement process on construction project delivery In: Ogunsemi, D.R, Awodele, O.A, & Oke, A.E (Eds). Proceedings of the 2nd Nigerian Institute of Quantity Surveyors Research Conference Federal University of Technology, Akure (pp 519 - 529). Faruk, A., Ibrahim, AD. and Ibrahim, YM. 2013. Investigating drivers and barriers for adopting collaborative procurement strategies in the Nigerian construction industry. A paper presented at the NIQS Annual Research Conference (AnReCon) held in Abuja. Odeyinka, HA. and Lowe, JG. 2000. An Assessment of risk factors involved in modelling cash flow forecast. Paper presented at the 16th Annual Research Conference in Construction Management held in Glasgow Caledonian University, UK. OECD. 2005. Fighting corruption and promoting integrity in public procurement. (http://wiki.bezkorupce.cz/_media/wiki/corrup_proc_oecdrapport- 2005-aase.pdf) Accessed on the 13th May, 2014. Public Procurement Act, PPA. 2007. Fundamental Principles for Procurement. An Act enacted by the National Assembly setting standards and developing the legal framework and professional capacity for public procurement in Nigeria. Sambo, AA. 2005. Research methods in education, Stirling-Horden Publishers (Nig.) Ltd., Ibadan Pp87-93. Tipili, LG. and Ilyasu, SM. 2014. Evaluating the impact of risk factors on construction projects cost in Nigeria. The International Journal of Engineering and sciences, vol. 3, issue 6, pp 10-15. Tipili, LG., and Ibrahim, Y. 2015. Identification and assessment of key risk factors affecting public construction projects in Nigeria: stakeholders‟ perspectives In: Ogunsemi, D.R, Awodele, O.A, and Oke, A.E (Eds). Proceedings of the 2nd Nigerian Institute of Quantity Surveyors Research Conference Federal University of Technology, Akure (pp 707 - 721).