SlideShare a Scribd company logo
1 of 7
Download to read offline
Risk Analysis and Management- EPC Projects
Palla Narasimhudu , Larsen & toubro ltd.
The demand for scientific management in different types of projects is constantly increasing, especially for
project base organizations, Engineering, Procurement and Construction (EPC) projects have become one of the
more popular methods of project execution by both clients and contractors. Risk Management, one of the critical
concepts of project management is interesting to focus on because of its advantages and capabilities [1].
Utilization of Project Risk Management methodologies, especially in large EPC projects can lead to huge
advantages on all aspects of projects’ development. It can also be implemented as the main reference and basis
for bidding, tendering and execution (including cost, time, resource, and quality management).
By risk identification, assessment and control, probable gaps between estimated and real cost, time, and quality
of projects can be prevented or decreased. This approach also provides facilities to predict the final cost and end
dates of projects with a greater level of confidence [1].
Risk can be defined in many ways
Risk is a possibility of something that may occur in the future. It has its origins in uncertainty as on today and
has to be identified today [2]
“Risk is most commonly conceived as reflecting variation in the distribution of possible outcomes, their
likelihoods, and their subjective values” (March & Shapira 1987)[1].
Risk is defined as the possible variation in results and can be either positive or negative (Williams et al., 1998)[1]
Risk defines as the “effect of uncertainty on objectives” while “An effect is a deviation from the expected -
positive and/or negative. Objectives can have different aspects (such as financial, health and safety, and
environmental goals) and can apply at different levels (such as strategic, organization-wide, project, product and
process).Risk is often characterized by reference to potential events and consequences or a combination of these.
Risk is often expressed in terms of a combination of the consequences of an event (including changes in
circumstances) and the associated likelihood of occurrence.” - Joint Technical Committee OB-007 (Standards
Australia/Standards New Zealand, 2009)[1]
Considering the definitions above, a wide variety of risk descriptions can be found based on the circumstances
and applications. These definitions reveal two important aspects of the risk in general; uncertainty and
consequences. Therefore the occurrence probability of the risk and the severity of the effects are considered as
two major parameters of defining the risk [1]
All in all, risk is interpreted as a type of unknown event with unpleasant effects, although it can be a pleasant
happening with positive consequences which would normally be considered as an opportunity. Risk analysis
focuses on both pleasant and unpleasant aspects of the risk [2]
Profit/Loss
Problem
Situation
Risk
Uncertainty
Attributed to
Chakradhar Iyyunni, Ph.D
L&T IPM
Project Risk
According to the Project Management Body of Knowledge standard, PMBOK® Guide (PMI, 2008, p.275)
project risk “is an uncertain event or condition that, if it occurs, has an effect on at least one project objective. A
risk may have one or more causes and, if it occurs, it may have one or more impacts”. A cause can be considered
as an assumption, condition, constraint, or a requirement that makes the probability of positive or negative
results, and project objectives consist of cost, time, resource, scope and quality [1]. A project is a certain type of
service which gathers different products together in order to achieve an inclusive solution. From this perspective,
projects are generally considered to have greater risk than products. Project risk is categorized separately from
financial or technical risks.
According to Mulcahy (2003) Projects risk are divided into two parts:
Static: Static risks are those who keep their characteristics during the whole project life cycle.
Dynamic: Dynamic risks can change their occurrence probability and consequences severity in the project time
span [1].
Project Risk Management
Based on PMBOK® Guide (PMI, 2008, p.273), "Project Risk Management includes the processes of conducting
risk management planning, identification, analysis, response planning, and monitoring and control on a project.
The objectives of Project Risk:
Management are to increase the probability and impact of positive events, and decrease the probability and
impact of negative events in the project."[1]
“It is the art and science of identifying, analysing and responding to the risk factor throughout the life of project
and in the best interest of its objectives.”[2]
Inherent Project
Risk
Risks Specific to
the Owner
Execution Risk
Uncertainty Risk Problem Evolution
Project Risks Evolution
Project Risk = (Probability of Events) (Consequences of Events)
Attributed to
Krishnamurthy,
Ex- Dean, L&T IPM
Applying of risk management is managing the risk effectively rather eliminating all risks in projects. Benefits of
risk management involves,
1) Systematic decision making approach and implementation
2) Probable out comes of the project
3) Outcome plan or approach to mitigate
4) Considered as a threat or opportunity ,which affects quality, time ,cost and performance of the project
5) Express the organisation’s responsibility to the clients
6) Able to withstand the competition
7) Demonstrate and enhance the successful completion of organisation record
8) Explore the techovative thinking, while face off risks.
9) To facilitate good platform for further growth of individual as well as organisation.
10) To facilitate good plat form for leaders
EPC PROJECT
EPC stands for Engineering Procurement and Construction, In EPC contracts, the contractor is responsible for
engineering and designing the project, procurement of all materials, tools and equipment and fabrication or
construction of the project, either in house or by subcontracting some work packages or some phases of the
project.
In EPC projects, total interaction of multiple agencies and multiple people working concurrently towards
common goal and transference of sharing information.
Engineering procurement and construction enterprise seen as key element participation and is critical for
delivery of project. Quality does not need more cost, but its value needs to be recognised.
The approach involves the execution of engineering and procurement activities running concurrently with
required at site deliveries timed match the schedule for efficient construction and installation.
In EPC projects, working with issues such as deadlines, controls, mission statements and submissions
combinations, along with delivery (with defined cost, time and quality by considering risks in the domain of each
contract), all in all means management, although the management of an EPC contract must be committed for all
pre-defined responsibilities (Huse, 2002).
Risks involved in EPC projects
Because the dynamic and complex nature of projects, contractor carry the risk on behalf of the customer at large
extent and there is substantial amount of risk involved.
The procurement phase is allocated the highest risk in the cost distribution of an EPC project and, as such, it is
imperative to ensure accurate and correct collaborations between the engineering and procurement sectors
Ability to handle good frontline engineering, basic engineering is the key factor to optimise the cost. If it is not it
may be disaster.
EPC companies are not much value creator for shareholders, over the years it may be not attractive, if not come
up their expectations.
Owner 1. Lack of Customer Interaction
2. Failed to Financial Closure/ Crisis.
3. Change in Scope
Contractors 1. Inexperience Project Management Team
2. Lack of common practices (life cycle, planning, and so forth)
3. Ineffective project decomposition (Work Break down Structure) resulting inefficient
Plan Risk
Management
Identify Risks
Perform
Qualitative
Risk Analysis
Perform
Quantitative
Risk Analysis
Plan Risk
Responses
Monitor and
Control risks
work flow
4. Non availability of technical, skilled and semi-skilled manpower
5. Ineffective Communication and Coordination
6. Safety
7. Competition
8. Poor Documentation
9. Poor Quality
10. Poor Cash Flow Management
11. Higher Inventory
12. Higher Interest rates
13. Environmental Controls
Government 1. Regulatory Issues
2. Policy paralysis
3. Unstable Government
4. Ineffective Co-ordination between Central and State Departments
Climatic and
Geographic
Conditions
1. Unforeseen Occurrences like Rain, cyclones, earthquake
2. Excessive Heat during Summer
3. Unusual Soil Strata
Social and
Economic
1. Anti-Social elements involvement and unethical process
2. Recession
3. Fluctuation in Currency and commodities
Shareholders 1. Low wealth creation
Risk analysing & management
EPC Projects are large in nature; better data at bid stage would provide higher level of resource optimisation and
deliver better bids/bid decision. During the phases of project development by the owners/ clients and bidding by
EPC contractors, it is important to generate realistic budgets and to develop a sound execution strategy to meet
the completion requirements of the project. To understand the base cost of the project a careful bottom-up cost
estimate for procured items as well as for contracted services including various risks associated with the project
is required. Estimating project work is challenging, and most people are admitting also avoiding, probably most
significant problem of technical projects like EPC involves engineering, designing, procuring and constructing
requires interaction and integrating chain relation.
Key
Contributor
Unable to
Complete
Critical
Scope
SchedulePeople
Cost Organization
Causes Effect
Changes Need
Unavailable
Skills
New Technology
Requires
Unanticipated
Skills
Budget Cut
Task Queued Due
to Resource Limits
Reorganizatio
n
Layoffs
Inadequate
Notice and
Communication
Learning Curve too
High
Work Delayed, Leads
to Timing Conflict
Interruptio
n
Not Ready in Time
Lost Resource
Personality Conflict
Wrong
Skills
The best way of effort is the measurement made the same /similar work done erlier.Good estimates relies on:
1)Finding and using of historical data:- one’s go through the historical data, one can find out the project
analysis and lesion learnt, reference material s and engineering or other standards, published technical data and
the kind of risk level [3].
2) Experts and expert judgement: - Historical information need not be personal to be useful. Even when no
one on the project has relevant experience or data, there may be others who do, outside of project. One source
may be peers, managers, and technical talent elsewhere within organization. Another possibility is to seek out the
opinions of colleagues in professional societies who do similar work for other companies outside consultants in
technical or management fields may have useful information that they will share, for a fee. Even quotations and
proposals from service suppliers may contain useful data that you can use for estimating project work [3].
3) Delphi estimates: -Delphi is a ‘‘group intelligence’’ way to tap into subconscious historical data that would
otherwise be unavailable. It is also a collaborative team technique and contributes to group buy-in, ownership,
and motivation [3].
4) Further decomposition: -When you lack of historical data, begin by breaking the activity to be estimated into
even small pieces of work. Extrapolate from actual measurements of the portion of the work to estimate whole
activity [3].
Estimation Techniques [3]
Relevant Metrics Exist No Data Available
Prior Activity Experience  Retrospectives
 Databases
 Parametric Formulas,
Experiential Rules (“Size”
Methods)
 Life Cycle Norms
 Task Owner Input
 Peer Inputs
 Inspections
 Delphi Analysis
 Short Tasks (20 Day Max)
in WBS
 Further Decomposition
No Activity Experience  Published Information
 Vender Quotes
 Expert Consultation
 Guess
 Get Outside Help
 Use Older Technology
5) Activity sequencing: - Activity sequence requires determining the dependencies for each project activity, and
these linkages reveal many potential sources of project delay. Discovering risk arising from schedule
dependencies require all project activities to be linked both predecessor and successor activities. Critical path
method analysis is a useful technique for determining which schedule risk belonging on project risk list [90].
6) Planning horizon: -The uncertainty inherent in work planned more than a few months in the future is a
source of significant schedule risk on any lengthy project. Make specific note of any unusual, novel, or unstaffed
activities more than three months into the project. On a regular basis, include explicit activities in the project
plan to review estimates, risks, assumptions, and other project data. Risk management relies on periodic
recommendations for project plan adjustments based on the results of these reviews [96]
7) Planning procurement:-Starting before any work, specific risk permeates all aspects of the procurement
process. Procurement planning involves investigation of possible options, and requires a “make-or-buy” analysis
to determine the amount of risk involved. Determine what is most important of the project and ensure meet the
specifications that the project required and specific work on technical projects tends to evolve and change
quickly; it is challenge to evaluate potential suppliers to supply accordingly. After select a supplier, the next step
in the procurement process is to finalize the details of the work and finances. Once a selection is made, the
balance of power begins to shift from the purchaser to the supplier, which raises additional risks. When the work
begins, the project becomes dependent on the supplier for crucial, time-sensitive project deliverables. Since the
primary consideration on the supplier side is financial, the best tactic for risk management in negotiation is to
strongly align payments with achievement of specific results. Risk management also requires that at least one
member of the project team be involved with planning and contracting for outside services so that the interests of
Fishbone Diagram Analysis [3]
the project are represented throughout the procurement process. Before finalising request for proposal, one needs
gather information through other agencies; colleagues, internal business units and some other outsource to
determine the capabilities and risk taking abilities of the particular agency/out sourcing firm. Communication
throughout the process is also essential. Anything that one potential supplier finds unclear in the request for
proposal needs to be addressed [3]. In projects everything is possible, some highly influenced supplier is
definitely potential risk source for project, and management should definitely take a look. Despite best efforts,
results in terms that represent potential project problems, note these as risks. In extreme cases, may need to
reconsider selection decision
8) Engineering and Construction: - Ability to handle good frontline engineering, basic engineering is the key
factor to optimise the cost. If it is not it may be disaster. Engineering is the prime in control the project in the
scientific way. Person need not come from elite colleges, but person who having passion and dedication inside
organisation with bit training able to create great results. Early in the engineering phase a document delivery
schedule shall be developed which supports the project baseline schedule. This would enable manpower as well
as resources planning. In case the available in house resources are not sufficient to support the project execution,
utilisation of contracted resources shall be considered, as a compromise on project schedule due to resource
constraints would not be desirable. Major focus areas during engineering are speed and quality of engineering
deliverables. Hidden defects in engineering can prove extremely expensive to rectify if identified at a late stage
of the project. Delays in engineering shall be avoided by all means as this will have a knock-on-effect on the
further project execution schedule. Also, delay recovery in engineering can be easily handled compared to
recovery of delays in fabrication or construction. An established culture of fair reporting of problems, either
technical or relating to project schedules, within the EPC organisation enables the project manager to initiate
corrective actions right in time.
EPC companies needs to be concentrate. Finally construction, it is really the art of management to cope with
planning, time, schedule and cost more importantly Quality and Safety of the people because these are the only
land mark for future prospects. Project manager needs to accelerate his role to create interaction between his
team and multiple agencies for getting things done. Needs to conduct weekly, monthly and quarterly reviews and
meetings to track and monitor the progress and foreseen risks and appropriate plans to overcome. In construction
stage, whole package to brake at smallest level, tracking schedules, creating critical paths, Quality and Safety
plan develop and implementation, creating work front for resources utilisation, cost optimisation ,documentation
is the part of evidence and future controller risk and change management, managing stack holders ,legal and
regulatory issues, vertical ,horizontal and down level communication, for the coping with lack of skills
,identifying and upgrade by training ,skill training to work men for enhance the quality of product ,methodology
preparation for all activities along with risk and hazard identification and mitigation at planning and execution
stage, resource levelling, outsource resources is involving potential risk, decision making, interaction with
customers, methodology for delayed schedules ,monitoring the cost, inventory control , invoice and billing in
accordance with financial aspects, accounts receivable, accounts payable to vendors, cash inflow and out flow,
working capital management, cost control management, waste management, change management,
environmental harmony and unforeseen risk all are part of execution, every entity having potential source of risk,
inefficient risk management leads to damage the company ,human lives, machinery.
9) Project Management: An essential role during project execution is project management, which we would
foster into highlighting some important activities in the context of risk mitigation strategies. First and foremost
being the generation and freeze of the baseline schedule for which client approval shall be obtained. The baseline
schedule shall clearly define client obligations (what and when; e.g. handover of cleared site, provision of
utilities, etc.) and shall be supported by a schedule basis memorandum describing important assumptions made
for the generation of the schedule. The approved baseline schedule is not only a fundamental tool to steer the
project within the organisation of the EPC contractor but is also essential when consequences of changes have to
be evaluated. A change event in a project may lead to cost and/or schedule consequences and the latter can be
evaluated and substantiated only if the baseline schedule and regular schedule updates are available to EPC
contractor and client. In respect to changes to the project scope or schedule a frequently seen mistake during
project execution is the late notification of a change event and the late determination and documentation of its
impact on time and cost. A further important activity is the billing schedule which ideally targets a cash positive
or cash neutral project execution. As the approval of the billing schedule is often a precondition for submission
of first invoices, due attention should be given to this activity.
In the execution phase it is essential to be precise in crucial decisions and move forward to actualise the plans
rather than spending excessive time in exploring alternatives or going into R&D, as the EPC projects have
predefined boundaries of project time, cost, and quality.
A significant challenge for the project management in this phase is the coordination of the interfaces between
various engineering disciplines as well as between engineering, procurement and construction. In order to
manage this challenge the project manager shall have the full understanding of required workflows and processes
and has to align these with the schedule requirements. When the construction site nears completion the quality
and completion documentation become an issue in respect of timely generation at required quality. For an EPC
contractor it is highly recommended to keep the generation of test packs and other quality documents under tight
control or under own management.
However, with careful planning and risk management through all the phases of the project, from proposal to
completion and with due consideration of at least the described risk mitigation measures, the EPC contractors
shall be able to execute the projects within their budgets and time.
References:
[1] Amir Hassan Mohebbi, Ngadhnjim Bislimi, Project Risk Management: Methodology Development for
Engineering, Procurement and Construction Projects, Karlstads Universitet, Karlstad, Sweden, (2012), p.1,3,4
[2] Chakradhar Iyyunni, Ph.D, Risk Management to Opportunity Management, L&T Institute of Project
Management, Knowledge City, Vadodara
[3] Tom Kendrick, PMP, Identifying and Managing Project Risk, Second Edition, PHI Learning Private Limited,
Delhi, (2013) p.81, 82, 87, 90, 96, 178

More Related Content

What's hot

Lecture 1 introduction to construction procurement process.
Lecture 1   introduction to construction procurement process.Lecture 1   introduction to construction procurement process.
Lecture 1 introduction to construction procurement process.
Aszahari Aie
 
EPC_EPCM Business process modelling rendition
EPC_EPCM Business process modelling renditionEPC_EPCM Business process modelling rendition
EPC_EPCM Business process modelling rendition
Jaswin Sood
 
Epc issues and recommendations
Epc issues and recommendationsEpc issues and recommendations
Epc issues and recommendations
ubk1411
 

What's hot (20)

Epc overview
Epc  overviewEpc  overview
Epc overview
 
Why EPC
Why EPCWhy EPC
Why EPC
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Clause 14.2 Advance Payment-Understanding Clauses in FIDIC ‘Conditions of Con...
Clause 14.2 Advance Payment-Understanding Clauses in FIDIC ‘Conditions of Con...Clause 14.2 Advance Payment-Understanding Clauses in FIDIC ‘Conditions of Con...
Clause 14.2 Advance Payment-Understanding Clauses in FIDIC ‘Conditions of Con...
 
How to Choose a Project Delivery Method
How to Choose a Project Delivery MethodHow to Choose a Project Delivery Method
How to Choose a Project Delivery Method
 
CCP Technical Paper and Application
CCP Technical Paper and ApplicationCCP Technical Paper and Application
CCP Technical Paper and Application
 
Project risk management
Project risk managementProject risk management
Project risk management
 
Project risk management
Project risk managementProject risk management
Project risk management
 
Pmp risk chapter 11
Pmp risk chapter 11Pmp risk chapter 11
Pmp risk chapter 11
 
Lecture 1 introduction to construction procurement process.
Lecture 1   introduction to construction procurement process.Lecture 1   introduction to construction procurement process.
Lecture 1 introduction to construction procurement process.
 
Exploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project deliveryExploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project delivery
 
Pre bid meeting presentation
Pre bid meeting presentationPre bid meeting presentation
Pre bid meeting presentation
 
EPC_EPCM Business process modelling rendition
EPC_EPCM Business process modelling renditionEPC_EPCM Business process modelling rendition
EPC_EPCM Business process modelling rendition
 
Managing Cash Flows On Construction Projects
Managing Cash Flows On Construction ProjectsManaging Cash Flows On Construction Projects
Managing Cash Flows On Construction Projects
 
Tender Management
Tender ManagementTender Management
Tender Management
 
The pathway to documenting successful contract claims..
The pathway to documenting successful contract claims..The pathway to documenting successful contract claims..
The pathway to documenting successful contract claims..
 
Epc issues and recommendations
Epc issues and recommendationsEpc issues and recommendations
Epc issues and recommendations
 
Construction Management in Developing Countries, Lecture 5
Construction Management in Developing Countries, Lecture 5Construction Management in Developing Countries, Lecture 5
Construction Management in Developing Countries, Lecture 5
 
Pp1 seminar
Pp1 seminarPp1 seminar
Pp1 seminar
 
Mega Project Management In The Oil & Gas Industry
Mega Project Management In The Oil & Gas IndustryMega Project Management In The Oil & Gas Industry
Mega Project Management In The Oil & Gas Industry
 

Viewers also liked

Berezansky Vladimir Trade Sanctions Risk Mitigation Overview
Berezansky Vladimir Trade Sanctions Risk Mitigation OverviewBerezansky Vladimir Trade Sanctions Risk Mitigation Overview
Berezansky Vladimir Trade Sanctions Risk Mitigation Overview
Vladimir Berezansky
 
Assessment Of Risk Mitigation
Assessment Of Risk MitigationAssessment Of Risk Mitigation
Assessment Of Risk Mitigation
Eneni Oduwole
 
Claims Final (2)
Claims Final (2)Claims Final (2)
Claims Final (2)
vijay popat
 

Viewers also liked (20)

Risk management large epc projects
Risk management  large epc projectsRisk management  large epc projects
Risk management large epc projects
 
Constructability of ug stations
Constructability of ug stationsConstructability of ug stations
Constructability of ug stations
 
Tc iv submited paper risk analysis and managements large epc projects
Tc iv submited paper risk analysis and managements  large epc projectsTc iv submited paper risk analysis and managements  large epc projects
Tc iv submited paper risk analysis and managements large epc projects
 
EPC Contracts – Negotiation, Administration and Risk Management
EPC Contracts – Negotiation, Administration and Risk ManagementEPC Contracts – Negotiation, Administration and Risk Management
EPC Contracts – Negotiation, Administration and Risk Management
 
Berezansky Vladimir Trade Sanctions Risk Mitigation Overview
Berezansky Vladimir Trade Sanctions Risk Mitigation OverviewBerezansky Vladimir Trade Sanctions Risk Mitigation Overview
Berezansky Vladimir Trade Sanctions Risk Mitigation Overview
 
Assessing EPC Contract Risk by using integrated systems
Assessing EPC Contract Risk by using integrated systemsAssessing EPC Contract Risk by using integrated systems
Assessing EPC Contract Risk by using integrated systems
 
Assessment Of Risk Mitigation
Assessment Of Risk MitigationAssessment Of Risk Mitigation
Assessment Of Risk Mitigation
 
Project cost management
Project cost management Project cost management
Project cost management
 
Advanced program management risk mitigation and management
Advanced program management   risk mitigation and managementAdvanced program management   risk mitigation and management
Advanced program management risk mitigation and management
 
Political risk assessment
Political risk assessmentPolitical risk assessment
Political risk assessment
 
Insurance claims (RISK MANAGEMENT)
Insurance claims (RISK MANAGEMENT)Insurance claims (RISK MANAGEMENT)
Insurance claims (RISK MANAGEMENT)
 
International Financial Management Political Risk
International Financial Management Political RiskInternational Financial Management Political Risk
International Financial Management Political Risk
 
Political risks and management assesment
Political risks and management assesmentPolitical risks and management assesment
Political risks and management assesment
 
TYPES OF POLITICAL RISKS
TYPES OF POLITICAL RISKSTYPES OF POLITICAL RISKS
TYPES OF POLITICAL RISKS
 
Claims Final (2)
Claims Final (2)Claims Final (2)
Claims Final (2)
 
Criterium epc project risks (5.28.13)
Criterium epc project risks (5.28.13)Criterium epc project risks (5.28.13)
Criterium epc project risks (5.28.13)
 
Fundamentals of Claims Management
Fundamentals of Claims ManagementFundamentals of Claims Management
Fundamentals of Claims Management
 
Claim settlement
Claim settlementClaim settlement
Claim settlement
 
Iso 31000
Iso 31000Iso 31000
Iso 31000
 
Political Risk
Political RiskPolitical Risk
Political Risk
 

Similar to Risk analysis and managements large epc projects

Evaluation of Risk Factors Affecting Cost Performance of Construction Project...
Evaluation of Risk Factors Affecting Cost Performance of Construction Project...Evaluation of Risk Factors Affecting Cost Performance of Construction Project...
Evaluation of Risk Factors Affecting Cost Performance of Construction Project...
IJCMESJOURNAL
 
EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...
EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...
EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...
Sibo Kanyambari Aimable
 
Effect or Risk Management Methods on project performance in Rwandan Construct...
Effect or Risk Management Methods on project performance in Rwandan Construct...Effect or Risk Management Methods on project performance in Rwandan Construct...
Effect or Risk Management Methods on project performance in Rwandan Construct...
Sibo Kanyambari Aimable
 
PAPERS72 September 2009 ■ Project Management.docx
PAPERS72 September 2009 ■ Project Management.docxPAPERS72 September 2009 ■ Project Management.docx
PAPERS72 September 2009 ■ Project Management.docx
herbertwilson5999
 
Risk Management in Construction Project
Risk Management in Construction ProjectRisk Management in Construction Project
Risk Management in Construction Project
Dr. Amarjeet Singh
 

Similar to Risk analysis and managements large epc projects (20)

Evaluation of Risk Factors Affecting Cost Performance of Construction Project...
Evaluation of Risk Factors Affecting Cost Performance of Construction Project...Evaluation of Risk Factors Affecting Cost Performance of Construction Project...
Evaluation of Risk Factors Affecting Cost Performance of Construction Project...
 
RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIO
RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIORISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIO
RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIO
 
A Qualitative approach for analysing Causes and Effects of Construction Risks
A Qualitative approach for analysing Causes and Effects of Construction RisksA Qualitative approach for analysing Causes and Effects of Construction Risks
A Qualitative approach for analysing Causes and Effects of Construction Risks
 
EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...
EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...
EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...
 
Effect or Risk Management Methods on project performance in Rwandan Construct...
Effect or Risk Management Methods on project performance in Rwandan Construct...Effect or Risk Management Methods on project performance in Rwandan Construct...
Effect or Risk Management Methods on project performance in Rwandan Construct...
 
International Journal of Engineering and Science Invention (IJESI)
International Journal of Engineering and Science Invention (IJESI)International Journal of Engineering and Science Invention (IJESI)
International Journal of Engineering and Science Invention (IJESI)
 
IRJET- Projects in Constructions due to Inadequate Risk Management
IRJET-  	  Projects in Constructions due to Inadequate Risk ManagementIRJET-  	  Projects in Constructions due to Inadequate Risk Management
IRJET- Projects in Constructions due to Inadequate Risk Management
 
C1303032126
C1303032126C1303032126
C1303032126
 
7. article azojete vol 11 77 88 alhassan
7. article azojete vol 11 77 88 alhassan7. article azojete vol 11 77 88 alhassan
7. article azojete vol 11 77 88 alhassan
 
Risk Management and Cost Overruns due to delays in Construction Project using...
Risk Management and Cost Overruns due to delays in Construction Project using...Risk Management and Cost Overruns due to delays in Construction Project using...
Risk Management and Cost Overruns due to delays in Construction Project using...
 
PAPERS72 September 2009 ■ Project Management.docx
PAPERS72 September 2009 ■ Project Management.docxPAPERS72 September 2009 ■ Project Management.docx
PAPERS72 September 2009 ■ Project Management.docx
 
Project mngmnt risks3.2
Project mngmnt risks3.2Project mngmnt risks3.2
Project mngmnt risks3.2
 
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
 
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...
 
Integrated Analysis of Schedule and Cost Risk
Integrated Analysis of Schedule and Cost RiskIntegrated Analysis of Schedule and Cost Risk
Integrated Analysis of Schedule and Cost Risk
 
IRJET- Risk Management using Primavera Software for Residential Sector
IRJET-  	  Risk Management using Primavera Software for Residential SectorIRJET-  	  Risk Management using Primavera Software for Residential Sector
IRJET- Risk Management using Primavera Software for Residential Sector
 
Risk Management in Construction Project
Risk Management in Construction ProjectRisk Management in Construction Project
Risk Management in Construction Project
 
IRJET- Risk Management in the Construction Project: Review
IRJET-  	  Risk Management in the Construction Project: ReviewIRJET-  	  Risk Management in the Construction Project: Review
IRJET- Risk Management in the Construction Project: Review
 
IRJET- Risk Management in Residential Project by Primavera Software
IRJET- Risk Management in Residential Project by Primavera SoftwareIRJET- Risk Management in Residential Project by Primavera Software
IRJET- Risk Management in Residential Project by Primavera Software
 
IJET-V2I6P23
IJET-V2I6P23IJET-V2I6P23
IJET-V2I6P23
 

Recently uploaded

VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
ssuser89054b
 

Recently uploaded (20)

Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdf
 
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 

Risk analysis and managements large epc projects

  • 1. Risk Analysis and Management- EPC Projects Palla Narasimhudu , Larsen & toubro ltd. The demand for scientific management in different types of projects is constantly increasing, especially for project base organizations, Engineering, Procurement and Construction (EPC) projects have become one of the more popular methods of project execution by both clients and contractors. Risk Management, one of the critical concepts of project management is interesting to focus on because of its advantages and capabilities [1]. Utilization of Project Risk Management methodologies, especially in large EPC projects can lead to huge advantages on all aspects of projects’ development. It can also be implemented as the main reference and basis for bidding, tendering and execution (including cost, time, resource, and quality management). By risk identification, assessment and control, probable gaps between estimated and real cost, time, and quality of projects can be prevented or decreased. This approach also provides facilities to predict the final cost and end dates of projects with a greater level of confidence [1]. Risk can be defined in many ways Risk is a possibility of something that may occur in the future. It has its origins in uncertainty as on today and has to be identified today [2] “Risk is most commonly conceived as reflecting variation in the distribution of possible outcomes, their likelihoods, and their subjective values” (March & Shapira 1987)[1]. Risk is defined as the possible variation in results and can be either positive or negative (Williams et al., 1998)[1] Risk defines as the “effect of uncertainty on objectives” while “An effect is a deviation from the expected - positive and/or negative. Objectives can have different aspects (such as financial, health and safety, and environmental goals) and can apply at different levels (such as strategic, organization-wide, project, product and process).Risk is often characterized by reference to potential events and consequences or a combination of these. Risk is often expressed in terms of a combination of the consequences of an event (including changes in circumstances) and the associated likelihood of occurrence.” - Joint Technical Committee OB-007 (Standards Australia/Standards New Zealand, 2009)[1] Considering the definitions above, a wide variety of risk descriptions can be found based on the circumstances and applications. These definitions reveal two important aspects of the risk in general; uncertainty and consequences. Therefore the occurrence probability of the risk and the severity of the effects are considered as two major parameters of defining the risk [1] All in all, risk is interpreted as a type of unknown event with unpleasant effects, although it can be a pleasant happening with positive consequences which would normally be considered as an opportunity. Risk analysis focuses on both pleasant and unpleasant aspects of the risk [2] Profit/Loss Problem Situation Risk Uncertainty Attributed to Chakradhar Iyyunni, Ph.D L&T IPM
  • 2. Project Risk According to the Project Management Body of Knowledge standard, PMBOK® Guide (PMI, 2008, p.275) project risk “is an uncertain event or condition that, if it occurs, has an effect on at least one project objective. A risk may have one or more causes and, if it occurs, it may have one or more impacts”. A cause can be considered as an assumption, condition, constraint, or a requirement that makes the probability of positive or negative results, and project objectives consist of cost, time, resource, scope and quality [1]. A project is a certain type of service which gathers different products together in order to achieve an inclusive solution. From this perspective, projects are generally considered to have greater risk than products. Project risk is categorized separately from financial or technical risks. According to Mulcahy (2003) Projects risk are divided into two parts: Static: Static risks are those who keep their characteristics during the whole project life cycle. Dynamic: Dynamic risks can change their occurrence probability and consequences severity in the project time span [1]. Project Risk Management Based on PMBOK® Guide (PMI, 2008, p.273), "Project Risk Management includes the processes of conducting risk management planning, identification, analysis, response planning, and monitoring and control on a project. The objectives of Project Risk: Management are to increase the probability and impact of positive events, and decrease the probability and impact of negative events in the project."[1] “It is the art and science of identifying, analysing and responding to the risk factor throughout the life of project and in the best interest of its objectives.”[2] Inherent Project Risk Risks Specific to the Owner Execution Risk Uncertainty Risk Problem Evolution Project Risks Evolution Project Risk = (Probability of Events) (Consequences of Events) Attributed to Krishnamurthy, Ex- Dean, L&T IPM
  • 3. Applying of risk management is managing the risk effectively rather eliminating all risks in projects. Benefits of risk management involves, 1) Systematic decision making approach and implementation 2) Probable out comes of the project 3) Outcome plan or approach to mitigate 4) Considered as a threat or opportunity ,which affects quality, time ,cost and performance of the project 5) Express the organisation’s responsibility to the clients 6) Able to withstand the competition 7) Demonstrate and enhance the successful completion of organisation record 8) Explore the techovative thinking, while face off risks. 9) To facilitate good platform for further growth of individual as well as organisation. 10) To facilitate good plat form for leaders EPC PROJECT EPC stands for Engineering Procurement and Construction, In EPC contracts, the contractor is responsible for engineering and designing the project, procurement of all materials, tools and equipment and fabrication or construction of the project, either in house or by subcontracting some work packages or some phases of the project. In EPC projects, total interaction of multiple agencies and multiple people working concurrently towards common goal and transference of sharing information. Engineering procurement and construction enterprise seen as key element participation and is critical for delivery of project. Quality does not need more cost, but its value needs to be recognised. The approach involves the execution of engineering and procurement activities running concurrently with required at site deliveries timed match the schedule for efficient construction and installation. In EPC projects, working with issues such as deadlines, controls, mission statements and submissions combinations, along with delivery (with defined cost, time and quality by considering risks in the domain of each contract), all in all means management, although the management of an EPC contract must be committed for all pre-defined responsibilities (Huse, 2002). Risks involved in EPC projects Because the dynamic and complex nature of projects, contractor carry the risk on behalf of the customer at large extent and there is substantial amount of risk involved. The procurement phase is allocated the highest risk in the cost distribution of an EPC project and, as such, it is imperative to ensure accurate and correct collaborations between the engineering and procurement sectors Ability to handle good frontline engineering, basic engineering is the key factor to optimise the cost. If it is not it may be disaster. EPC companies are not much value creator for shareholders, over the years it may be not attractive, if not come up their expectations. Owner 1. Lack of Customer Interaction 2. Failed to Financial Closure/ Crisis. 3. Change in Scope Contractors 1. Inexperience Project Management Team 2. Lack of common practices (life cycle, planning, and so forth) 3. Ineffective project decomposition (Work Break down Structure) resulting inefficient Plan Risk Management Identify Risks Perform Qualitative Risk Analysis Perform Quantitative Risk Analysis Plan Risk Responses Monitor and Control risks
  • 4. work flow 4. Non availability of technical, skilled and semi-skilled manpower 5. Ineffective Communication and Coordination 6. Safety 7. Competition 8. Poor Documentation 9. Poor Quality 10. Poor Cash Flow Management 11. Higher Inventory 12. Higher Interest rates 13. Environmental Controls Government 1. Regulatory Issues 2. Policy paralysis 3. Unstable Government 4. Ineffective Co-ordination between Central and State Departments Climatic and Geographic Conditions 1. Unforeseen Occurrences like Rain, cyclones, earthquake 2. Excessive Heat during Summer 3. Unusual Soil Strata Social and Economic 1. Anti-Social elements involvement and unethical process 2. Recession 3. Fluctuation in Currency and commodities Shareholders 1. Low wealth creation Risk analysing & management EPC Projects are large in nature; better data at bid stage would provide higher level of resource optimisation and deliver better bids/bid decision. During the phases of project development by the owners/ clients and bidding by EPC contractors, it is important to generate realistic budgets and to develop a sound execution strategy to meet the completion requirements of the project. To understand the base cost of the project a careful bottom-up cost estimate for procured items as well as for contracted services including various risks associated with the project is required. Estimating project work is challenging, and most people are admitting also avoiding, probably most significant problem of technical projects like EPC involves engineering, designing, procuring and constructing requires interaction and integrating chain relation. Key Contributor Unable to Complete Critical Scope SchedulePeople Cost Organization Causes Effect Changes Need Unavailable Skills New Technology Requires Unanticipated Skills Budget Cut Task Queued Due to Resource Limits Reorganizatio n Layoffs Inadequate Notice and Communication Learning Curve too High Work Delayed, Leads to Timing Conflict Interruptio n Not Ready in Time Lost Resource Personality Conflict Wrong Skills
  • 5. The best way of effort is the measurement made the same /similar work done erlier.Good estimates relies on: 1)Finding and using of historical data:- one’s go through the historical data, one can find out the project analysis and lesion learnt, reference material s and engineering or other standards, published technical data and the kind of risk level [3]. 2) Experts and expert judgement: - Historical information need not be personal to be useful. Even when no one on the project has relevant experience or data, there may be others who do, outside of project. One source may be peers, managers, and technical talent elsewhere within organization. Another possibility is to seek out the opinions of colleagues in professional societies who do similar work for other companies outside consultants in technical or management fields may have useful information that they will share, for a fee. Even quotations and proposals from service suppliers may contain useful data that you can use for estimating project work [3]. 3) Delphi estimates: -Delphi is a ‘‘group intelligence’’ way to tap into subconscious historical data that would otherwise be unavailable. It is also a collaborative team technique and contributes to group buy-in, ownership, and motivation [3]. 4) Further decomposition: -When you lack of historical data, begin by breaking the activity to be estimated into even small pieces of work. Extrapolate from actual measurements of the portion of the work to estimate whole activity [3]. Estimation Techniques [3] Relevant Metrics Exist No Data Available Prior Activity Experience  Retrospectives  Databases  Parametric Formulas, Experiential Rules (“Size” Methods)  Life Cycle Norms  Task Owner Input  Peer Inputs  Inspections  Delphi Analysis  Short Tasks (20 Day Max) in WBS  Further Decomposition No Activity Experience  Published Information  Vender Quotes  Expert Consultation  Guess  Get Outside Help  Use Older Technology 5) Activity sequencing: - Activity sequence requires determining the dependencies for each project activity, and these linkages reveal many potential sources of project delay. Discovering risk arising from schedule dependencies require all project activities to be linked both predecessor and successor activities. Critical path method analysis is a useful technique for determining which schedule risk belonging on project risk list [90]. 6) Planning horizon: -The uncertainty inherent in work planned more than a few months in the future is a source of significant schedule risk on any lengthy project. Make specific note of any unusual, novel, or unstaffed activities more than three months into the project. On a regular basis, include explicit activities in the project plan to review estimates, risks, assumptions, and other project data. Risk management relies on periodic recommendations for project plan adjustments based on the results of these reviews [96] 7) Planning procurement:-Starting before any work, specific risk permeates all aspects of the procurement process. Procurement planning involves investigation of possible options, and requires a “make-or-buy” analysis to determine the amount of risk involved. Determine what is most important of the project and ensure meet the specifications that the project required and specific work on technical projects tends to evolve and change quickly; it is challenge to evaluate potential suppliers to supply accordingly. After select a supplier, the next step in the procurement process is to finalize the details of the work and finances. Once a selection is made, the balance of power begins to shift from the purchaser to the supplier, which raises additional risks. When the work begins, the project becomes dependent on the supplier for crucial, time-sensitive project deliverables. Since the primary consideration on the supplier side is financial, the best tactic for risk management in negotiation is to strongly align payments with achievement of specific results. Risk management also requires that at least one member of the project team be involved with planning and contracting for outside services so that the interests of Fishbone Diagram Analysis [3]
  • 6. the project are represented throughout the procurement process. Before finalising request for proposal, one needs gather information through other agencies; colleagues, internal business units and some other outsource to determine the capabilities and risk taking abilities of the particular agency/out sourcing firm. Communication throughout the process is also essential. Anything that one potential supplier finds unclear in the request for proposal needs to be addressed [3]. In projects everything is possible, some highly influenced supplier is definitely potential risk source for project, and management should definitely take a look. Despite best efforts, results in terms that represent potential project problems, note these as risks. In extreme cases, may need to reconsider selection decision 8) Engineering and Construction: - Ability to handle good frontline engineering, basic engineering is the key factor to optimise the cost. If it is not it may be disaster. Engineering is the prime in control the project in the scientific way. Person need not come from elite colleges, but person who having passion and dedication inside organisation with bit training able to create great results. Early in the engineering phase a document delivery schedule shall be developed which supports the project baseline schedule. This would enable manpower as well as resources planning. In case the available in house resources are not sufficient to support the project execution, utilisation of contracted resources shall be considered, as a compromise on project schedule due to resource constraints would not be desirable. Major focus areas during engineering are speed and quality of engineering deliverables. Hidden defects in engineering can prove extremely expensive to rectify if identified at a late stage of the project. Delays in engineering shall be avoided by all means as this will have a knock-on-effect on the further project execution schedule. Also, delay recovery in engineering can be easily handled compared to recovery of delays in fabrication or construction. An established culture of fair reporting of problems, either technical or relating to project schedules, within the EPC organisation enables the project manager to initiate corrective actions right in time. EPC companies needs to be concentrate. Finally construction, it is really the art of management to cope with planning, time, schedule and cost more importantly Quality and Safety of the people because these are the only land mark for future prospects. Project manager needs to accelerate his role to create interaction between his team and multiple agencies for getting things done. Needs to conduct weekly, monthly and quarterly reviews and meetings to track and monitor the progress and foreseen risks and appropriate plans to overcome. In construction stage, whole package to brake at smallest level, tracking schedules, creating critical paths, Quality and Safety plan develop and implementation, creating work front for resources utilisation, cost optimisation ,documentation is the part of evidence and future controller risk and change management, managing stack holders ,legal and regulatory issues, vertical ,horizontal and down level communication, for the coping with lack of skills ,identifying and upgrade by training ,skill training to work men for enhance the quality of product ,methodology preparation for all activities along with risk and hazard identification and mitigation at planning and execution stage, resource levelling, outsource resources is involving potential risk, decision making, interaction with customers, methodology for delayed schedules ,monitoring the cost, inventory control , invoice and billing in accordance with financial aspects, accounts receivable, accounts payable to vendors, cash inflow and out flow, working capital management, cost control management, waste management, change management, environmental harmony and unforeseen risk all are part of execution, every entity having potential source of risk, inefficient risk management leads to damage the company ,human lives, machinery. 9) Project Management: An essential role during project execution is project management, which we would foster into highlighting some important activities in the context of risk mitigation strategies. First and foremost being the generation and freeze of the baseline schedule for which client approval shall be obtained. The baseline schedule shall clearly define client obligations (what and when; e.g. handover of cleared site, provision of utilities, etc.) and shall be supported by a schedule basis memorandum describing important assumptions made for the generation of the schedule. The approved baseline schedule is not only a fundamental tool to steer the project within the organisation of the EPC contractor but is also essential when consequences of changes have to be evaluated. A change event in a project may lead to cost and/or schedule consequences and the latter can be evaluated and substantiated only if the baseline schedule and regular schedule updates are available to EPC contractor and client. In respect to changes to the project scope or schedule a frequently seen mistake during project execution is the late notification of a change event and the late determination and documentation of its impact on time and cost. A further important activity is the billing schedule which ideally targets a cash positive or cash neutral project execution. As the approval of the billing schedule is often a precondition for submission of first invoices, due attention should be given to this activity. In the execution phase it is essential to be precise in crucial decisions and move forward to actualise the plans rather than spending excessive time in exploring alternatives or going into R&D, as the EPC projects have predefined boundaries of project time, cost, and quality.
  • 7. A significant challenge for the project management in this phase is the coordination of the interfaces between various engineering disciplines as well as between engineering, procurement and construction. In order to manage this challenge the project manager shall have the full understanding of required workflows and processes and has to align these with the schedule requirements. When the construction site nears completion the quality and completion documentation become an issue in respect of timely generation at required quality. For an EPC contractor it is highly recommended to keep the generation of test packs and other quality documents under tight control or under own management. However, with careful planning and risk management through all the phases of the project, from proposal to completion and with due consideration of at least the described risk mitigation measures, the EPC contractors shall be able to execute the projects within their budgets and time. References: [1] Amir Hassan Mohebbi, Ngadhnjim Bislimi, Project Risk Management: Methodology Development for Engineering, Procurement and Construction Projects, Karlstads Universitet, Karlstad, Sweden, (2012), p.1,3,4 [2] Chakradhar Iyyunni, Ph.D, Risk Management to Opportunity Management, L&T Institute of Project Management, Knowledge City, Vadodara [3] Tom Kendrick, PMP, Identifying and Managing Project Risk, Second Edition, PHI Learning Private Limited, Delhi, (2013) p.81, 82, 87, 90, 96, 178