Analysis of Cost over run in construction Projects
Aishwarya Prashant Patil1
1 M-Tech final Year Student of construction Management , Department of Project and construction management ,
MIT Art Design And Technology University, Pune, Maharashtra , India.
-----------------------------------------------------------------------------***----------------------------------------------------------------------------
Abstract - Many projects experience cost overrun and there
for exceed initial contract amount. The purpose of this
research is to assess causes and effects of cost and time
overruns in construction projects. The main aim of this
paper is to identify the major reasons for cost overruns in
construction projects in India as well as the critical success
factors that are helping to avoid the cost overruns.Cost
overruns occur in every construction project and the
magnitude varies significantly from project to project. This
leads to severe need of addressing the acute issue of
construction cost overrun. The most common effects of cost
overrun identified by this research were delay, and
supplementary agreement or adversarial relations among
stakeholders, and budget shortfall of project owners This
paper describes the state of art of the research on cost
overrun factors in the construction projects.
Key Words: cost overrun, time, Construction projects,
cause, effect,
1. INTRODUCTION
The Indian construction industry is an integral
part of country’s economy and its growth and a conduit for
a substantial part of India’s development investment. The
industry plays a pivotal role in developing the country’s
infrastructure, a pre-requisite for high levels of economic
growth. Most construction projects experience cost
overrun and it put massive financial burden on the client
or owner.
As with construction industry anywhere in the
world, the Indian construction sector also face a lot of
challenges from land acquisition issues, adverse political
and structural changes, shortage of talent, design and
constructability issues, and rising material and labour
costs. As a result of the current levels of material and
labour cost inflation and the buoyant market conditions,
contractors are increasing their average margins by
between 6% and 9%. These increases are reflected in
higher tender prices, particularly on key landmark
developments, although on smaller projects contractors
are more likely to absorb the increased costs to remain
competitive Time and cost overruns have significant
impact on the national economy. He argues that, if the
completion of a project exceeds the planned schedule, the
people as well as the economy have to wait for the
provisions of public goods and services longer than is
necessary and hence delays limit the growth potential of
the economy. Similarly, cost overruns in public sector
projects seem to reduce competitiveness of the economy.
1.2 Cost overrun
It is the phenomenon in which the client has to spend
more money for the completion of project than the
originally estimated i.e. the project goes over the budget.
1.3 Schedule Overrun
It is the phenomenon in which the project gets delayed
beyond its expected completion time due to certain
difficulties i.e. more time is required to finish the project
than initially planned.
Before you begin to format your paper, first write and
save the content as a separate text file. Keep your text and
graphic files separate until after the text has been
formatted and styled. Do not use hard tabs, and limit use of
hard returns to only one return at the end of a paragraph.
Do not add any kind of pagination anywhere in the paper.
Do not number text heads-the template will do that for you.
2.1 Time Overrun and Cost Overrun
2.1.1 2.1 Causes of Time Overrun
Majority of infrastructure projects in India are affected
by time overruns. These overruns vary from few months
to as high as five or more years placing
1. The project viability at risk. Delays in land
acquisition and site handover is the primary
reason for time overruns in pre-execution phase
Delays in land acquisition are driven by several
factors.
2. Regulatory approvals from several agencies
leading to delay in Construction.
3. Poor program management resulting in
ineffective co-ordination with other projects and
schedule delay Insufficient management of Project
design/scope change is widely prevalent in the
infrastructure sector availability of resources for
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 11 | Nov -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 1235
infrastructure sector is limited plans ,
specifications, etc are not received by the
contractor in time.
2.2 Causes of Cost Overrun –
 Availability of raw materials, allocation of
sufficient time, cost of design phase, fraudulent
prevention, bulk material purchase and by
applying short term goals were marked as vital
factors to be considered to overcome cost
overrun.
 cost variation in owner originated project than
contractor or designer originated category. The
major factors are design changes, incorrect
evaluation of projects time and cost, risk and
uncertainty related with projects, non-
performance of subcontractors, conflict between
project parties, fluctuation of rates, low skilled
manpower, financing and payment.
 unstable interest rate, complexity of works, lack of
proper training and experience of project
manager, disagreement in contract
documentation, lack of appropriate software,
inflation of prices, contract and specification
interpretation disagreement, dependency on
imported materials, unpredictable weather
condition, projects fraud and corruption, weak
regulation and control and unstable
3. METHODS TO AVOID COST OVERRUN-
3.1 The proactive strategy
Measures were those which should be added in
planning stage of project. Planning strategy includes
1. Efficient planning of strategies and management
of site.
2. Proper supervision of project site.
3. Appropriate planning and arrangement of project
4. Organized inventory mechanism
3.2 organizational strategy
1. Appropriate prominence on previous experience
2. Regular coordination between associate parties.
3. Increase human resource in industry
4. Complete administration of contract and regular
meeting about development of project.
5. Employing Proficient subcontractor and suppliers
Attributing less weight to price and more weight to abilities
By using channel for perfect information and
communication is proactive and organizational strategy.
Utilization of latest technology is a proactive and reactive
strategy. Undertaking a preconstruction planning
regarding the procedure.
However all above factors are not similar to every project,
factors varies from project to project but though some are
conman in all projects so the study specific factors that lead
to either good or poor performance individually can give
more accurate results specially for small projects.
4. METHODOLOGY
For analysis of cost overrun I have done case study of MJM
hospital, Pune extension of construction work for 3 floor
above Existing building. As site was situated in crowed area
of city there are many problems faced by contractor.
following factors are factors with their nature which I have
observed while analysis.
1. Delay in Progress payment-
It frequently happens. When contractor get the wind of
financial crisis client is in, he may be induced to delay
the construction work deliberately.
2. Inaccurate planning and scheduling of project
by contractors –
Often fails to to draw up practicable and user friendly “
work programmer due to lack of knowledge in
construction management technique. Tends to work
programmer which is not accurate but jst satisfies the
requirements in condition of contracts.
3. Rainy whether
Prevails over longer periods of year. The planning
process (designing , estimating , sanctioning and
procurement work etc) starts after the provisional
budget get approved in march so much. So project may
starts in rainy season as half of year is spend on above.
4. Non availability of experienced technical staff of
contractor –
At the binding stage, contractor claims to be having
qualified staff. Do not employ adequate number of
skilled technical staff. Also projects are handled by
foreman not having adequate technical experience.
Due to current demand, retention of technical staff is
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 11 | Nov -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 1236
difficult. Create a communication gap between
consultant and contractor.
5. Excessive work in hand s of Contractors-
Frequently happens. too many contracts can be
awarded to same contractor by different client. As
contractor tends to bid for as many contracts as
possible, one may end up being awarded too many
projects. No central unit receives contract awarding
details.
6. Poor liquidity of contractors-
Contractor having poor liquidity problem may win
contract as financial status is not checked at tender
evaluation, only go by bid price. No payment of
mobilization advance makes matter worse. Delay in
payment of progress payment aggravates the problem
7. Shortage of labours-
Due to boom in construction industry demand has
exceeded the supply. The potential labour force is not
attracted to construction industry. Opportunities are
available for skilled workers oversea at a much higher
salary.
8. Delay in approving extra work and variation-
The majority of engineers and contractors do not
follow proper procedure and format for submission of
extra work and variation for approval. Authority for
approving extra work and variation is kept with the
clients. Non delegation of authority for approving has
made the process too long and tedious.
9. Poor site management and supervision of
contractors-
Many contractor are poor in planning , organizing ,
staffing, directing and controlling
10. Ineffective time management of contractor-
Most of the projects are under-staff and contractor
himself is handling planning, purchasing and
supervision etc. contractors may be heavily burdened
himself with internal and external communication
conflict resolution , meeting and report preparation.
5. CONCLUSIONS
The most significant factors causing time overrun
is identified in this research based on perception of all
three main parties to the contract namely client ,
consultant and contractor.
1. Delay in Progress payment.
2. Inaccurate planning and scheduling of project by
contractors.
3. Rainy weather.
4. Non availability of experienced technical staff of
contractor.
5. Excessive work in hand s of Contractors.
6. Poor liquidity of contractors.
7. Shortage of labours.
8. Delay in approving extra work and variation
9. Poor site management and supervision of
contractors-
10. Ineffective time management of contractor-
6 Recommendation
 Project planning should be properly done at
starting phase of project.
 Variation of material and labour rate must be
considered while finalizing budget.
 Proper study of all details of project should be
done before planning.
 Scope of project should be clear before Starting
any project to avoid future cost overrun
 Proper resource management should be done at
site to avoid Resources should be ideally available
on site
 Sourcing of material should be technically and
financially adequate..
 Increase the speed of construction
 Wastage of resource should be minimum
 Resources should be properly utilized.
 Proper Communication between all project
participant should be there.
.
REFERENCES
1. Azhar, N., Farooqui, R. U., & Ahmed, S. M. (2008).
Cost overrun factors in construction industry of
Pakistan. Proceedings from First International
Conference on Construction in Developing Countries.
Flyvbjerg, B., Holm, M. K. S., & Buhl, S. L. (2003).
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 11 | Nov -2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 1237
2. Koushki, P. A., & Kartam, N. (2004). Impact of
construction materials on project time and cost in
Kuwait. Engineering, Construction and Management.
Economics Journal, 11(2), 126-132.
3. Rahman, I. A., Memon, A. H., & Karim, A. T. A. (2013).
Significant factors causing cost overruns in large
construction projects in Malaysia. Journal of Applied
Sciences, 13(2), 286-293.
4. N.Hamezah ,M.A.Khoiry,I . Arshad, N.M.Tawil and A.I.
Che Ani (2011)―Causes of construction Delay
Theoretical framework
5. H. P. Moura, J. C. Teixeira, and B. Pires, ―Dealing
With Cost and Time in the Portuguese Construction
Industry,‖ in CIB World Building Congress, 2007
BIOGRAPHIES
Aishwarya Patil
Mtech Final Year Student, Project
and Construction Management
Department, MIT Art , Design and
Technology Universuty, Pune,
Maharashtra, India.

More Related Content

What's hot

IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting InflationIRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting InflationIRJET Journal
 
Project delay and_cost_overrun-libre
Project delay and_cost_overrun-libreProject delay and_cost_overrun-libre
Project delay and_cost_overrun-libreUTHM
 
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...IJMER
 
A Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project ManagementA Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project Managementijsrd.com
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...iosrjce
 
IRJET- Prediction Model of Factors Causing Increase in Overhead Cost in C...
IRJET-  	  Prediction Model of Factors Causing Increase in Overhead Cost in C...IRJET-  	  Prediction Model of Factors Causing Increase in Overhead Cost in C...
IRJET- Prediction Model of Factors Causing Increase in Overhead Cost in C...IRJET Journal
 
causes and implication of delay in construction
causes and implication of delay in constructioncauses and implication of delay in construction
causes and implication of delay in constructionsudinak
 
IRJET- Identification of Constraints and there Impact on Construction Pro...
IRJET-  	  Identification of Constraints and there Impact on Construction Pro...IRJET-  	  Identification of Constraints and there Impact on Construction Pro...
IRJET- Identification of Constraints and there Impact on Construction Pro...IRJET Journal
 
IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET - Forecasting and Management of Triple Constraints in Construction proj...IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET - Forecasting and Management of Triple Constraints in Construction proj...IRJET Journal
 
Effective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryEffective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryPMI Chennai Chapter
 
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...World-Academic Journal
 
Examining the Effect of Project Delays in Construction Field, A Case Study of...
Examining the Effect of Project Delays in Construction Field, A Case Study of...Examining the Effect of Project Delays in Construction Field, A Case Study of...
Examining the Effect of Project Delays in Construction Field, A Case Study of...Associate Professor in VSB Coimbatore
 
Claims Management, Extension of Time (EOT) and Delays Analysis
Claims Management, Extension of Time (EOT) and Delays AnalysisClaims Management, Extension of Time (EOT) and Delays Analysis
Claims Management, Extension of Time (EOT) and Delays AnalysisPlanning Engineer Est.
 
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...IRJET Journal
 
Delay Analysis for an On-Going Residential Project
Delay Analysis for an On-Going Residential ProjectDelay Analysis for an On-Going Residential Project
Delay Analysis for an On-Going Residential ProjectIRJET Journal
 
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsDELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsTwana Ahmad
 
Impact of delayness on construction projects
Impact of delayness on construction projectsImpact of delayness on construction projects
Impact of delayness on construction projectsIRJET Journal
 
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Sankalp Swarnkar
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction ProjectIRJET Journal
 
Literature review on_ extension of time
Literature review on_ extension of timeLiterature review on_ extension of time
Literature review on_ extension of timeJoseph Sangpang
 

What's hot (20)

IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting InflationIRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
IRJET- Effects of Project Cost Analysis and Factors Affecting Inflation
 
Project delay and_cost_overrun-libre
Project delay and_cost_overrun-libreProject delay and_cost_overrun-libre
Project delay and_cost_overrun-libre
 
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
 
A Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project ManagementA Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project Management
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
 
IRJET- Prediction Model of Factors Causing Increase in Overhead Cost in C...
IRJET-  	  Prediction Model of Factors Causing Increase in Overhead Cost in C...IRJET-  	  Prediction Model of Factors Causing Increase in Overhead Cost in C...
IRJET- Prediction Model of Factors Causing Increase in Overhead Cost in C...
 
causes and implication of delay in construction
causes and implication of delay in constructioncauses and implication of delay in construction
causes and implication of delay in construction
 
IRJET- Identification of Constraints and there Impact on Construction Pro...
IRJET-  	  Identification of Constraints and there Impact on Construction Pro...IRJET-  	  Identification of Constraints and there Impact on Construction Pro...
IRJET- Identification of Constraints and there Impact on Construction Pro...
 
IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET - Forecasting and Management of Triple Constraints in Construction proj...IRJET - Forecasting and Management of Triple Constraints in Construction proj...
IRJET - Forecasting and Management of Triple Constraints in Construction proj...
 
Effective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryEffective Engineering Management in EPC Industry
Effective Engineering Management in EPC Industry
 
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
 
Examining the Effect of Project Delays in Construction Field, A Case Study of...
Examining the Effect of Project Delays in Construction Field, A Case Study of...Examining the Effect of Project Delays in Construction Field, A Case Study of...
Examining the Effect of Project Delays in Construction Field, A Case Study of...
 
Claims Management, Extension of Time (EOT) and Delays Analysis
Claims Management, Extension of Time (EOT) and Delays AnalysisClaims Management, Extension of Time (EOT) and Delays Analysis
Claims Management, Extension of Time (EOT) and Delays Analysis
 
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
 
Delay Analysis for an On-Going Residential Project
Delay Analysis for an On-Going Residential ProjectDelay Analysis for an On-Going Residential Project
Delay Analysis for an On-Going Residential Project
 
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & FactorsDELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
DELAY IN GOVERNMENT CONSTRUCTION PROJECT , Types & Factors
 
Impact of delayness on construction projects
Impact of delayness on construction projectsImpact of delayness on construction projects
Impact of delayness on construction projects
 
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
 
Literature review on_ extension of time
Literature review on_ extension of timeLiterature review on_ extension of time
Literature review on_ extension of time
 

Similar to Analysis of Cost Over Run in Construction Projects

A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...IRJET Journal
 
Management For Construction Project:-Various Aspects Of Delay
Management For Construction Project:-Various Aspects Of DelayManagement For Construction Project:-Various Aspects Of Delay
Management For Construction Project:-Various Aspects Of DelayIRJET Journal
 
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECTHOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECTIRJET Journal
 
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...IRJET Journal
 
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...IRJET Journal
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET Journal
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...IRJET Journal
 
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...IRJET Journal
 
journalsresaim,+IJRESM_V3_I7_70.pdf
journalsresaim,+IJRESM_V3_I7_70.pdfjournalsresaim,+IJRESM_V3_I7_70.pdf
journalsresaim,+IJRESM_V3_I7_70.pdfKarthikeyanP288430
 
IRJET- The Study on Evaluation of Cost Escalation in Infrastructure Proje...
IRJET-  	  The Study on Evaluation of Cost Escalation in Infrastructure Proje...IRJET-  	  The Study on Evaluation of Cost Escalation in Infrastructure Proje...
IRJET- The Study on Evaluation of Cost Escalation in Infrastructure Proje...IRJET Journal
 
Infrastrcture project management
Infrastrcture project managementInfrastrcture project management
Infrastrcture project managementSanjeev Deshmukh
 
IRJET- Review on Study of Factors Affecting Quality of Construction Project
IRJET- Review on Study of Factors Affecting Quality of Construction ProjectIRJET- Review on Study of Factors Affecting Quality of Construction Project
IRJET- Review on Study of Factors Affecting Quality of Construction ProjectIRJET Journal
 
76 s201905
76 s20190576 s201905
76 s201905IJRAT
 
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET Journal
 
Introduction of Agile Project Management (APM) Methodology to a Railway and M...
Introduction of Agile Project Management (APM) Methodology to a Railway and M...Introduction of Agile Project Management (APM) Methodology to a Railway and M...
Introduction of Agile Project Management (APM) Methodology to a Railway and M...IRJET Journal
 
IRJET- Study & Analysis of Subcontracting Practices in Infrastructure Project
IRJET- Study & Analysis of Subcontracting Practices in Infrastructure ProjectIRJET- Study & Analysis of Subcontracting Practices in Infrastructure Project
IRJET- Study & Analysis of Subcontracting Practices in Infrastructure ProjectIRJET Journal
 
The role of time, cost and quality in project management
The role of time, cost and quality in project managementThe role of time, cost and quality in project management
The role of time, cost and quality in project managementIRJET Journal
 
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-ProjectIRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-ProjectIRJET Journal
 
IRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in ConstructionIRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in ConstructionIRJET Journal
 
A Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsA Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsRick Vogel
 

Similar to Analysis of Cost Over Run in Construction Projects (20)

A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...
 
Management For Construction Project:-Various Aspects Of Delay
Management For Construction Project:-Various Aspects Of DelayManagement For Construction Project:-Various Aspects Of Delay
Management For Construction Project:-Various Aspects Of Delay
 
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECTHOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
 
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
 
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...
 
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
 
journalsresaim,+IJRESM_V3_I7_70.pdf
journalsresaim,+IJRESM_V3_I7_70.pdfjournalsresaim,+IJRESM_V3_I7_70.pdf
journalsresaim,+IJRESM_V3_I7_70.pdf
 
IRJET- The Study on Evaluation of Cost Escalation in Infrastructure Proje...
IRJET-  	  The Study on Evaluation of Cost Escalation in Infrastructure Proje...IRJET-  	  The Study on Evaluation of Cost Escalation in Infrastructure Proje...
IRJET- The Study on Evaluation of Cost Escalation in Infrastructure Proje...
 
Infrastrcture project management
Infrastrcture project managementInfrastrcture project management
Infrastrcture project management
 
IRJET- Review on Study of Factors Affecting Quality of Construction Project
IRJET- Review on Study of Factors Affecting Quality of Construction ProjectIRJET- Review on Study of Factors Affecting Quality of Construction Project
IRJET- Review on Study of Factors Affecting Quality of Construction Project
 
76 s201905
76 s20190576 s201905
76 s201905
 
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
 
Introduction of Agile Project Management (APM) Methodology to a Railway and M...
Introduction of Agile Project Management (APM) Methodology to a Railway and M...Introduction of Agile Project Management (APM) Methodology to a Railway and M...
Introduction of Agile Project Management (APM) Methodology to a Railway and M...
 
IRJET- Study & Analysis of Subcontracting Practices in Infrastructure Project
IRJET- Study & Analysis of Subcontracting Practices in Infrastructure ProjectIRJET- Study & Analysis of Subcontracting Practices in Infrastructure Project
IRJET- Study & Analysis of Subcontracting Practices in Infrastructure Project
 
The role of time, cost and quality in project management
The role of time, cost and quality in project managementThe role of time, cost and quality in project management
The role of time, cost and quality in project management
 
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-ProjectIRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
 
IRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in ConstructionIRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in Construction
 
A Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsA Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction Projects
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 

Recently uploaded (20)

Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 

Analysis of Cost Over Run in Construction Projects

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 11 | Nov -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 1234 Analysis of Cost over run in construction Projects Aishwarya Prashant Patil1 1 M-Tech final Year Student of construction Management , Department of Project and construction management , MIT Art Design And Technology University, Pune, Maharashtra , India. -----------------------------------------------------------------------------***---------------------------------------------------------------------------- Abstract - Many projects experience cost overrun and there for exceed initial contract amount. The purpose of this research is to assess causes and effects of cost and time overruns in construction projects. The main aim of this paper is to identify the major reasons for cost overruns in construction projects in India as well as the critical success factors that are helping to avoid the cost overruns.Cost overruns occur in every construction project and the magnitude varies significantly from project to project. This leads to severe need of addressing the acute issue of construction cost overrun. The most common effects of cost overrun identified by this research were delay, and supplementary agreement or adversarial relations among stakeholders, and budget shortfall of project owners This paper describes the state of art of the research on cost overrun factors in the construction projects. Key Words: cost overrun, time, Construction projects, cause, effect, 1. INTRODUCTION The Indian construction industry is an integral part of country’s economy and its growth and a conduit for a substantial part of India’s development investment. The industry plays a pivotal role in developing the country’s infrastructure, a pre-requisite for high levels of economic growth. Most construction projects experience cost overrun and it put massive financial burden on the client or owner. As with construction industry anywhere in the world, the Indian construction sector also face a lot of challenges from land acquisition issues, adverse political and structural changes, shortage of talent, design and constructability issues, and rising material and labour costs. As a result of the current levels of material and labour cost inflation and the buoyant market conditions, contractors are increasing their average margins by between 6% and 9%. These increases are reflected in higher tender prices, particularly on key landmark developments, although on smaller projects contractors are more likely to absorb the increased costs to remain competitive Time and cost overruns have significant impact on the national economy. He argues that, if the completion of a project exceeds the planned schedule, the people as well as the economy have to wait for the provisions of public goods and services longer than is necessary and hence delays limit the growth potential of the economy. Similarly, cost overruns in public sector projects seem to reduce competitiveness of the economy. 1.2 Cost overrun It is the phenomenon in which the client has to spend more money for the completion of project than the originally estimated i.e. the project goes over the budget. 1.3 Schedule Overrun It is the phenomenon in which the project gets delayed beyond its expected completion time due to certain difficulties i.e. more time is required to finish the project than initially planned. Before you begin to format your paper, first write and save the content as a separate text file. Keep your text and graphic files separate until after the text has been formatted and styled. Do not use hard tabs, and limit use of hard returns to only one return at the end of a paragraph. Do not add any kind of pagination anywhere in the paper. Do not number text heads-the template will do that for you. 2.1 Time Overrun and Cost Overrun 2.1.1 2.1 Causes of Time Overrun Majority of infrastructure projects in India are affected by time overruns. These overruns vary from few months to as high as five or more years placing 1. The project viability at risk. Delays in land acquisition and site handover is the primary reason for time overruns in pre-execution phase Delays in land acquisition are driven by several factors. 2. Regulatory approvals from several agencies leading to delay in Construction. 3. Poor program management resulting in ineffective co-ordination with other projects and schedule delay Insufficient management of Project design/scope change is widely prevalent in the infrastructure sector availability of resources for
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 11 | Nov -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 1235 infrastructure sector is limited plans , specifications, etc are not received by the contractor in time. 2.2 Causes of Cost Overrun –  Availability of raw materials, allocation of sufficient time, cost of design phase, fraudulent prevention, bulk material purchase and by applying short term goals were marked as vital factors to be considered to overcome cost overrun.  cost variation in owner originated project than contractor or designer originated category. The major factors are design changes, incorrect evaluation of projects time and cost, risk and uncertainty related with projects, non- performance of subcontractors, conflict between project parties, fluctuation of rates, low skilled manpower, financing and payment.  unstable interest rate, complexity of works, lack of proper training and experience of project manager, disagreement in contract documentation, lack of appropriate software, inflation of prices, contract and specification interpretation disagreement, dependency on imported materials, unpredictable weather condition, projects fraud and corruption, weak regulation and control and unstable 3. METHODS TO AVOID COST OVERRUN- 3.1 The proactive strategy Measures were those which should be added in planning stage of project. Planning strategy includes 1. Efficient planning of strategies and management of site. 2. Proper supervision of project site. 3. Appropriate planning and arrangement of project 4. Organized inventory mechanism 3.2 organizational strategy 1. Appropriate prominence on previous experience 2. Regular coordination between associate parties. 3. Increase human resource in industry 4. Complete administration of contract and regular meeting about development of project. 5. Employing Proficient subcontractor and suppliers Attributing less weight to price and more weight to abilities By using channel for perfect information and communication is proactive and organizational strategy. Utilization of latest technology is a proactive and reactive strategy. Undertaking a preconstruction planning regarding the procedure. However all above factors are not similar to every project, factors varies from project to project but though some are conman in all projects so the study specific factors that lead to either good or poor performance individually can give more accurate results specially for small projects. 4. METHODOLOGY For analysis of cost overrun I have done case study of MJM hospital, Pune extension of construction work for 3 floor above Existing building. As site was situated in crowed area of city there are many problems faced by contractor. following factors are factors with their nature which I have observed while analysis. 1. Delay in Progress payment- It frequently happens. When contractor get the wind of financial crisis client is in, he may be induced to delay the construction work deliberately. 2. Inaccurate planning and scheduling of project by contractors – Often fails to to draw up practicable and user friendly “ work programmer due to lack of knowledge in construction management technique. Tends to work programmer which is not accurate but jst satisfies the requirements in condition of contracts. 3. Rainy whether Prevails over longer periods of year. The planning process (designing , estimating , sanctioning and procurement work etc) starts after the provisional budget get approved in march so much. So project may starts in rainy season as half of year is spend on above. 4. Non availability of experienced technical staff of contractor – At the binding stage, contractor claims to be having qualified staff. Do not employ adequate number of skilled technical staff. Also projects are handled by foreman not having adequate technical experience. Due to current demand, retention of technical staff is
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 11 | Nov -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 1236 difficult. Create a communication gap between consultant and contractor. 5. Excessive work in hand s of Contractors- Frequently happens. too many contracts can be awarded to same contractor by different client. As contractor tends to bid for as many contracts as possible, one may end up being awarded too many projects. No central unit receives contract awarding details. 6. Poor liquidity of contractors- Contractor having poor liquidity problem may win contract as financial status is not checked at tender evaluation, only go by bid price. No payment of mobilization advance makes matter worse. Delay in payment of progress payment aggravates the problem 7. Shortage of labours- Due to boom in construction industry demand has exceeded the supply. The potential labour force is not attracted to construction industry. Opportunities are available for skilled workers oversea at a much higher salary. 8. Delay in approving extra work and variation- The majority of engineers and contractors do not follow proper procedure and format for submission of extra work and variation for approval. Authority for approving extra work and variation is kept with the clients. Non delegation of authority for approving has made the process too long and tedious. 9. Poor site management and supervision of contractors- Many contractor are poor in planning , organizing , staffing, directing and controlling 10. Ineffective time management of contractor- Most of the projects are under-staff and contractor himself is handling planning, purchasing and supervision etc. contractors may be heavily burdened himself with internal and external communication conflict resolution , meeting and report preparation. 5. CONCLUSIONS The most significant factors causing time overrun is identified in this research based on perception of all three main parties to the contract namely client , consultant and contractor. 1. Delay in Progress payment. 2. Inaccurate planning and scheduling of project by contractors. 3. Rainy weather. 4. Non availability of experienced technical staff of contractor. 5. Excessive work in hand s of Contractors. 6. Poor liquidity of contractors. 7. Shortage of labours. 8. Delay in approving extra work and variation 9. Poor site management and supervision of contractors- 10. Ineffective time management of contractor- 6 Recommendation  Project planning should be properly done at starting phase of project.  Variation of material and labour rate must be considered while finalizing budget.  Proper study of all details of project should be done before planning.  Scope of project should be clear before Starting any project to avoid future cost overrun  Proper resource management should be done at site to avoid Resources should be ideally available on site  Sourcing of material should be technically and financially adequate..  Increase the speed of construction  Wastage of resource should be minimum  Resources should be properly utilized.  Proper Communication between all project participant should be there. . REFERENCES 1. Azhar, N., Farooqui, R. U., & Ahmed, S. M. (2008). Cost overrun factors in construction industry of Pakistan. Proceedings from First International Conference on Construction in Developing Countries. Flyvbjerg, B., Holm, M. K. S., & Buhl, S. L. (2003).
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 11 | Nov -2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 1237 2. Koushki, P. A., & Kartam, N. (2004). Impact of construction materials on project time and cost in Kuwait. Engineering, Construction and Management. Economics Journal, 11(2), 126-132. 3. Rahman, I. A., Memon, A. H., & Karim, A. T. A. (2013). Significant factors causing cost overruns in large construction projects in Malaysia. Journal of Applied Sciences, 13(2), 286-293. 4. N.Hamezah ,M.A.Khoiry,I . Arshad, N.M.Tawil and A.I. Che Ani (2011)―Causes of construction Delay Theoretical framework 5. H. P. Moura, J. C. Teixeira, and B. Pires, ―Dealing With Cost and Time in the Portuguese Construction Industry,‖ in CIB World Building Congress, 2007 BIOGRAPHIES Aishwarya Patil Mtech Final Year Student, Project and Construction Management Department, MIT Art , Design and Technology Universuty, Pune, Maharashtra, India.