International Journal of Civil Engineering and Technology (IJCIET)
Volume 10, Issue 1, January 2019, pp.
Available online at http://www.iaeme.com/IJCIET/issues.asp?JType=IJCIET&VType=10&IType=1
ISSN Print: 0976-6308 and ISSN Online: 0976
©IAEME Publication
APPLICATION OF PERT
INTEGRATION ON BUILD
Master Program of Civil
ABSTRACT
The job structure of the bottom (lower Structure) has the weight of the work
amounted to 8% of the total cost of the construction of high
delay in implementation
analysis conducted by using the Relative Important Index (RII) Obtained 15 influential
factors ie Comparison of measurement and prediction, the adequacy of the plan
Specifications, fix and schedules and plans, instrumentation and
monitoring, evaluation of static pole Data , Data collection, soil conditions, scope of
work, Issues, accuracy of data, problem identification, Solution Optimization,
validation projects, Improve communication, skilled workforce. While the resu
the analysis of the case study foundations work efficiency powerboats Obtained results
using PERT of 4.85% and optimization for quality using Six Sigma of 99. 56%.
Keywords: PERT Method, Six Sigma M
Cite this Article: Albert Eddy Husin, Application of Pert and Six Sigma Integration
On Building Pile Foundation
Technology (IJCIET), 10 (1), 2018, pp.
http://www.iaeme.com/IJCIET/issues.asp?JType=IJCIET&VType=10&IType=1
1. INTRODUCTION
High-rise building (High Rise building) is a multi
process of work on the implementation of high
obstacles often encountered is from the time that the delay of the project and of the quality of
that quality is not in accordance with the technical specifications required [1]. Resulted in the
loss of the project and construction failures.
Pile foundations are generally preferred when heavy structural loads have to be
transferred through weak subsoil to firm strata. The piles often penetrate through a
contaminated zone and then fully penetrate an underlying aquitard, possibly entering a deeper
underlying aquifer, to achieve higher bearing capacities [2]. Piling Works with methodology
Six Sigma has the DMAIC phases (
step was used a variety of methods and tools (tools), both quantitative and qualitative
IJMET/index.asp 307 editor@iaeme.com
International Journal of Civil Engineering and Technology (IJCIET)
Volume 10, Issue 1, January 2019, pp.307–314, Article ID: IJCIET_10_01_029
http://www.iaeme.com/IJCIET/issues.asp?JType=IJCIET&VType=10&IType=1
6308 and ISSN Online: 0976-6316
Scopus Indexed
APPLICATION OF PERT AND SIX SIGMA
INTEGRATION ON BUILDING PILE
FOUNDATION
Albert Eddy Husin
Civil Engineering, Mercu Buana University, Jakarta, Indonesia
The job structure of the bottom (lower Structure) has the weight of the work
amounted to 8% of the total cost of the construction of high-rise buildings, while the
of the work Reached 12%. The results of the statistical
analysis conducted by using the Relative Important Index (RII) Obtained 15 influential
factors ie Comparison of measurement and prediction, the adequacy of the plan
Specifications, fix and schedules and plans, instrumentation and
monitoring, evaluation of static pole Data , Data collection, soil conditions, scope of
work, Issues, accuracy of data, problem identification, Solution Optimization,
validation projects, Improve communication, skilled workforce. While the resu
the analysis of the case study foundations work efficiency powerboats Obtained results
using PERT of 4.85% and optimization for quality using Six Sigma of 99. 56%.
PERT Method, Six Sigma Method, Pile Foundation.
Albert Eddy Husin, Application of Pert and Six Sigma Integration
On Building Pile Foundation, International Journal of Civil Engineering and
, 10 (1), 2018, pp. 307–314.
http://www.iaeme.com/IJCIET/issues.asp?JType=IJCIET&VType=10&IType=1
rise building (High Rise building) is a multi-story building on land use is limited. In the
process of work on the implementation of high-rise building construction project, the
obstacles often encountered is from the time that the delay of the project and of the quality of
that quality is not in accordance with the technical specifications required [1]. Resulted in the
loss of the project and construction failures.
ions are generally preferred when heavy structural loads have to be
transferred through weak subsoil to firm strata. The piles often penetrate through a
contaminated zone and then fully penetrate an underlying aquitard, possibly entering a deeper
g aquifer, to achieve higher bearing capacities [2]. Piling Works with methodology
ix Sigma has the DMAIC phases (Define, Measure, Analyze, Improve, and Control) each
step was used a variety of methods and tools (tools), both quantitative and qualitative
editor@iaeme.com
http://www.iaeme.com/IJCIET/issues.asp?JType=IJCIET&VType=10&IType=1
AND SIX SIGMA
ING PILE
iversity, Jakarta, Indonesia
The job structure of the bottom (lower Structure) has the weight of the work
rise buildings, while the
esults of the statistical
analysis conducted by using the Relative Important Index (RII) Obtained 15 influential
factors ie Comparison of measurement and prediction, the adequacy of the plan
Specifications, fix and schedules and plans, instrumentation and performance
monitoring, evaluation of static pole Data , Data collection, soil conditions, scope of
work, Issues, accuracy of data, problem identification, Solution Optimization,
validation projects, Improve communication, skilled workforce. While the results of
the analysis of the case study foundations work efficiency powerboats Obtained results
using PERT of 4.85% and optimization for quality using Six Sigma of 99. 56%.
Albert Eddy Husin, Application of Pert and Six Sigma Integration
International Journal of Civil Engineering and
http://www.iaeme.com/IJCIET/issues.asp?JType=IJCIET&VType=10&IType=1
story building on land use is limited. In the
rise building construction project, the
obstacles often encountered is from the time that the delay of the project and of the quality of
that quality is not in accordance with the technical specifications required [1]. Resulted in the
ions are generally preferred when heavy structural loads have to be
transferred through weak subsoil to firm strata. The piles often penetrate through a
contaminated zone and then fully penetrate an underlying aquitard, possibly entering a deeper
g aquifer, to achieve higher bearing capacities [2]. Piling Works with methodology
Define, Measure, Analyze, Improve, and Control) each
step was used a variety of methods and tools (tools), both quantitative and qualitative
Albert Eddy Husin
http://www.iaeme.com/IJCIET/index.asp 308 editor@iaeme.com
methodologies while PERT. PERT is a project management tool that is used for scheduling,
organizing and coordinating the parts of the job that is in a project. In the process of the
construction project work trip this high-rise building, a problem frequently encountered.
On the application of the PERT method is common factors of delay in the project (delay)
such as: the availability of resources (Meshach 2013, the Bora in 2016), workers who do not
fit, construction equipment inadequate [3], environmental factors Project, project management
is not good [4], the lack of communication between crew good workers [5]. While the
application of the method Six Sigma is not maximized due to the factors of the failure of the
quality of a construction project including: project delays, errors in estimating costs
Insufficient resources on the project [5], the absence of risk management at project [6], and
the imbalance of work on each segment [5].
By understanding the key success factors are expected to apply their stakeholders
interested in the building project and contribute to science in education. The duration of a
project is determined by a system flow plan in which the duration of each task has an
expected value and a variance. Simplified PERT durations are subject to errors of greater than
10% when the skewness of the actual distribution is greater than 0.28 or less than 20.48 [7].
The aim of this research is to identify the key success factors of the application integration
PERT methods and methods Six Sigma on the implementation of the pile foundation
construction work in the building construction project in Indonesia and determine the key
factors of success were very influential or dominant (CSF) to application integration PERT
Methods and Methods Six Sigma on the implementation of the work pile foundation of high-
rise buildings in the building construction project in Indonesia. The scope of this study is the
perception of the data used is collected through a questionnaire derived from the contractor
and the consultant's study who operate in areas of Jakarta qualification large enterprises,
medium and small
2. REVIEW OF RESEARCH
Six Sigma is a new management tool that is used to replace Total Quality Management
(TQM), highly focused on quality control by studying the company's overall production
system. Having a goal to, reduce/eliminate production defects, cutting the time of
manufacture of the product, and eliminates the cost. Six Sigma also called a comprehensive
system, that is the strategy, discipline, and tools to achieve and support business success. Six
Sigma is called a strategy for focusing on improving customer satisfaction, is called discipline
for following the formal model, namely DMAIC (Define, Measure, Analyze, Improve,
Control).
DMAIC originally developed as part of the framework Six Sigma. It is an approach that is
proven to eliminate or reduce defect (disability) and improve the quality associated with
business metrics [8]. But in a construction project, it will require a good job scheduling so that
jobs can be run regularly. There are several methods that can be used to manage time and
project resources. One is the method PERT.
PERT is a method to determine the schedule and budget of the sources, so as a job that
has been determined in advance can be completed on time. PERT can keep managers aware
of and receive this information on a regular basis. More than, PERT is an excellent approach
to achieve the timely completion of the project. PERT method is known to exist in three
estimates of the duration of each activity: Optimistic estimate (to), Most likely estimate (tm)
and Pessimistic estimate (tp).
As a selected object in this research project, especially in sub-high-rise buildings under
the structure work. One of the most important and decisive parts in the high-rise building
projects ( high rise building) is part of the lower structure of the building function and
Application of Pert and Six Sigma Integration On Building Pile Foundation
http://www.iaeme.com/IJCIET/index.asp 309 editor@iaeme.com
usability of the pile foundation is to assign or transfer loads of construction on it ( upper
structure) to the bedrock which is located very deep.
2.1. Research methods
The study was conducted to analyze the understanding and identifying the barriers and assess
the effect of the application of PERT scheduling methods and methods Six Sigma on the
project of building a high degree on the quality and timing of the project. The study began by
defining the problem and the title of research supported by a literature review. Once it was
determined the concept and research hypothesis is the basis for selecting appropriate research
methods [10]. To find out understanding and identifying constraints in implementing the
scheduling and quality based on the method PERT and Six Sigma Methods on the project of
building high levels of quality and time, then the preparation of a research instrument in the
form of variables that are formulated in the form of questions (questionnaire). According to
[9].
Figure 1 Flow Chart the application of the PERT method and the Six Sigma method at the Pile work
The dominant constraint hereinafter is discussed on these findings to be deduced about the
understanding and the dominant factors that cause obstacles in implementing integration
methods PERT and Six Sigma to employment poles at high-rise building projects, continuing
the interview/discussion with experts/specialists, which will be concluded and suggestions.
2.2. Develop research instruments
Preparation of research instruments by using a questionnaire to the stages of preparation,
namely by identifying variables, the main factors, and sub-factors, classify and search the
most important factor, prepare statements in the points corresponding questions variables and
compile qualitative respondents with multilevel. The application of the PERT method
integration and the Six Sigma method on the implementation of high-rise building pile
foundation work can be seen in the following figure 1.
Albert Eddy Husin
http://www.iaeme.com/IJCIET/index.asp 310 editor@iaeme.com
2.3. Research variable
The initial stage of the RII analysis is to collect the questionnaire components to be
distributed to the respondents. All components are prepared based on previous similar
research. The questionnaire component consists of 3 parts including :
Variable
It is the main dimension taken from the research topic. Variables can be either theories or
research objects [6]. There are 2 independent variables and 1 dependent variable in this study,
namely:
• Independent variables: Six Sigma Method and PERT Method
• Bound Variables: The lower structure of a high-rise building.
Main Factor
• Is the main sub-dimension of the variable. The main variables are decomposed into smaller
sub-dimensions and each main factor has a sub-factor component. In this study, there were 7
main factors from 3 main variables including:
Six Sigma method variables: 5 Main factors (Define, Measure, Analysis, Improve, Control)
• PERT method variable: 3 Main factors (Scheduling, Resources, Project Scope)
• The variable structure under high-rise buildings: 3 Main factors (Work Preparation, Quality
and Time, Implementation)
Sub Factor
It is a sub-dimension of main factors. Subfactors are questions that will be answered and filled
out by respondents by giving a score to each item. In this study, there were 49 subfactors
scattered in 11 main factors. The distribution of sub-factors in each main factor is as follow
[11]:
• Main factors of the Six Sigma method, 15 sub-factors
• Main PERT method factor, 15 sub-factors
• Main factor The lower structure of multi-story building height, 11 sub-factors, a total of 41
sub-factors.
2.4. Identification of the key success factors
There are many supporting factors so that the implementation of the lower structure work of
the High-rise Building has been successfully implemented including, comparison of
measurements and predictions, Adequacy of plans and specifications, Improving schedules
and plans, Instrument and monitoring performance, and others.
Some of these studies were the longest in 2001 and the most recent in 2011. From these
numbers, the key success factors were applying the PERT method and the Six Sigma method
as much as 41 and grouped based on qualitative justification according to the equation of
factors or intentions. another there are 15 most important factors of sub-factors according to
the RII index rating.
Application of Pert and Six Sigma Integration On Building Pile Foundation
http://www.iaeme.com/IJCIET/index.asp 311 editor@iaeme.com
3. RESULTS AND DISCUSSION
3.1. Results and evaluation
At this stage, the results of all stages of statistical analysis are compiled and evaluated
regarding the most influential factors in the application of the Six Sigma estimation method
and the PERT method on the lower structure work of high-rise buildings. the most influential,
the most influential variable, the hypothesis decision is accepted.
Fhitung =
.( )
.( )
=
. .( )
.( . )
= 56,61
Where:
m = Number of free variables
n = number of respondents
Rules for testing significance:
If Fcount > Ftable, then H1 is accepted H0 is rejected
Fcount < Ftable, then H1 is rejected H0 is accepted
With a significance level of α = 0.05, the value of F table is as follows:
Ftable = F [(1-) (dk = m), (dk = n-m-1) (20)
= F [(1-0.05) (dk = 2), (dk = 38-2-1)
= F [(0.95), (2.35)],
this can be seen from Figure 2.
3.2. Case Study Validation
The acquired data was used to draw the connection between the outcome of this research to
the cost and duration of the project [13].
Figure 2 Pile Histogram
Albert Eddy Husin
http://www.iaeme.com/IJCIET/index.asp 312 editor@iaeme.com
Table 1. Duration of Pile Foundation Work Activities
Scope Of Work Human Resouces
and Tools
Coefficient Productivity Volume Duration/
Group
N
Group
Duration
Land Work
Excavation pile cap Excavator 0.0414 24.17 m3/hour 748.544 m3 5 days 1 5 days
Foundation Work
Cutting pile cap Worker 0.05 20 m/day 265.5 m3 14 days 1 14 days
Foreman 0.2
Handyman 0.1
Making work floor 10
cm
Handyman 1.2 2 m3/ day 18.71 m3 8 days 1 8 days
Foreman 0.2
Leader foreman 0.02
Worker 0.06
Vibrator 0.05
Bekisting Pile Cap Handyman 0.15 4 m2/ days 50.13 m2 13 days 1 13 days
Worker 0.005
Reinforced Pile Cap Handyman 0.01 2700.55 kg/
days
85067.43 kg 32 days 2 16 days
Foreman 0.005
Loader foreman 0.003
Worker 0.003
Casting Concrete fc 30
Mpa
Concrete mixer 0.631 11.9 m3/days 336.84 m3 31 days 1 31 days
The Pile Foundation used is a square concrete pile foundation with dimensions of 45x45
cm and a length of 15 cm. Project data in this study used for testing case study validation is
the AMARIS Hotel development project, located in Tangerang, obtained data made in table
form 5. And Scheduling data for activity description can be seen in table 2.
Figure 3. The Critical Path in Pile Foundation Work
From the data in the field, it can be analyzed the critical path for pile foundation work
activities as shown in the following figure 3.
Pile foundation data from the field are obtained and made in the following table 3.
Application of Pert and Six Sigma Integration On Building Pile Foundation
http://www.iaeme.com/IJCIET/index.asp 313 editor@iaeme.com
Table 2. Expected Time
Description Pessimistic Moderate Optimistic
Expected
Time
(Month)
Variance
Critical
Path
Variance
Land Work
Excavation of pile cap 2 5 10 5,33 1,78
Foundation Work
Erection 20 23 30 23,67 2,78 2,78
Cutting Pile’s Head 10 14 19 14,17 2,25 2,25
Work Floor 10 cm 6 8 13 8,50 1,36
Formwork Pile Cap 11 13 16 13,17 0,69
Steel Assembly Pile Cap 12 16 19 15,83 1,36 1,36
Fc 30 MPaConcrete Casting 27 31 36 31,17 2,25 2,25
Known :
Total Defect of Pile Foundation (D) = 216
Amount of Opportunity (O) = 5
Number of Points (U) = 30
Number of units per point = 5
Asked: DPMO?
PU = D / U = 216/30 = 7.20
DPU is the average defect produced on each floor
Table 3 Pile Foundation Data
No. Defect Pile Foundation Number of Defect Percentage (%)
1 Cracks on poles 26 12
2 Position of Pile (Slope) 50 23
3 Clay Soil Layer (On Location) 39 18
4 Total Capacity 58 27
4 Land Hard On Location 43 20
TOTAL 216 100
DPO = =
.
( )
= 0.00960
DPMO= 0.0096 x 1.000.000
= 9600
From the calculation of the data above and by using the Six Sigma method, defects
obtained or produced by pile foundation work with a DPMO value of 9600 equivalent to 4.31
Sigma with a yield of around 99.56% following from the Sigma value table. It can be
concluded that the construction of the project carrying out pile foundation work has a defect
value.
4. CONCLUSION
The application of PERT method scheduling method and Six Sigma method on the
implementation of high-rise building pile foundation work obtained 15 of the most important
and most influential factors, the influencing factors namely: Comparison of measurements
and predictions, Adequacy of Plans and Specifications, Improving schedules and plans,
instrumentation and performance monitoring, static pole data evaluation, data collection, soil
Albert Eddy Husin
http://www.iaeme.com/IJCIET/index.asp 314 editor@iaeme.com
conditions, scope of work, problems, data accuracy, problem identification, solution
optimization, project validation, improved communication, skilled workforce.
By applying the PERT method can optimize project time to 93,247 days or equal to 4.85%
from the time the original plan was 98 days.
From the calculation using the Six Sigma method, it can reduce the defect in the
implementation of pile foundation work with a DPMO value of 9600 DPMO equivalent to
4.31 Sigma with a yield of around 99.56%. Thus the research hypothesis by applying the Six
Sigma Method in carrying out pile foundation work can reduce defects.
REFERENCES
[1] Tong Guo, M.ASCE, Li, A., Wei, L., and Gu, Y. (2013), Horizontal Translocation of a
High-Rise Building: Case Study, Journal Of Performance Of Constructed Facilities ©
ASCE / MAY/JUNE 2013 235-242.
[2] Satyamurthy, R., Nataraj, M.S., McManis, K.L., and Boutwell, G.P. (2008), Investigations
of Pile Foundations in Brownfields, Journal Of Geotechnical And Geoenvironmental
Engineering © ASCE / October 2008 / 1469-1475
[3] Hutagaol, K. (2013). Pembelajaran kontekstual untuk meningkatkan Representasi
matematis siswa Sekolah Menengah Pertama. urnal Ilmiah Program Studi Matematika
STKIP Siliwangi Bandung, 2, 91. Retrieved from http://e-journal.stkipsiliwangi.ac.id
[4] Serpell, A. (1995). “Characterization of waste in building construction projects”. in
Alarcon, L.: Lean Construction, A.A. Balkema, Rotterdam.
[5] Suanda, B. (2011). Faktor Penyebab Keterlambatan Proyek. Retrieved 4 11, 2016, from
https://www.manajemenproyekindonesia.com/?=389
[6] Hinze, W. (2008). Gravity and Magnetic Exploration: Principle, Practices, and
Applications. New York: Cambridge University Press
[7] Wayne D. Cottrell,1 P.E. (1999), Simplified Program Evaluation And Review Technique
(PERT), Journal Of Construction Engineering And Management / January/February 1999.
[8] Lee, K.L. and Su, Y. (2013), Applying Six Sigma to Quality Improvement in
Construction, Journal Of Management In Engineering © ASCE / October 2013
[9] Husin, A. (2015). Model Aliansi Strategis Dalam Kemitraan Pemerintah Dan Swasta Pada
Mega Proyek Infrastruktur Berbasis Value Engineering Untuk Meningkatkan Nilai
Kelayakan Proyek, FT Universitas Indonesia.
[10] Riduwan. (2010). Skala Pengukuran Variabel-Variabel Penelitian. Bandung: Alfabeta.
[11] Husin A.E., Kussumardianadewi, B.D. (2018), Cost Performance Review On Value
Engineering Optimized Floor Cover Finishing Work Of High Rise Office Building,
International Journal of Scientific Research Engineering &Technology (IJSRET) Volume
7 Issue 11 823-832.
[12] Husin A.E and Priyanto, D. (2018), Lean Construction Based Tower Crane Requirement
Optimization In High Rise Building Construction Project, International Journal of
Scientific Research Engineering &Technology (IJSRET) Volume 7 Issue 10 738-743.
[13] Tong Guo, M.ASCE, Li, A., Wei, L., and Gu, Y. (2013), Horizontal Translocation of a
High-Rise Building: Case Study, Journal Of Performance Of Constructed Facilities ©
ASCE / MAY/JUNE 2013 235-242.

More Related Content

What's hot

Ijciet 10 01_075
Ijciet 10 01_075Ijciet 10 01_075
Ijciet 10 01_075
IAEME Publication
 
Risk Contingency Evaluation in International Construction Projects (Real Case...
Risk Contingency Evaluation in International Construction Projects (Real Case...Risk Contingency Evaluation in International Construction Projects (Real Case...
Risk Contingency Evaluation in International Construction Projects (Real Case...
IJLT EMAS
 
Efficient Planning Scheduling and Delay Analysis of Residential Project
Efficient Planning Scheduling and Delay Analysis of Residential ProjectEfficient Planning Scheduling and Delay Analysis of Residential Project
Efficient Planning Scheduling and Delay Analysis of Residential Project
IJERA Editor
 

What's hot (20)

Ijciet 10 01_075
Ijciet 10 01_075Ijciet 10 01_075
Ijciet 10 01_075
 
IRJET- A Study and Analysis of Construction Equipment Management used in ...
IRJET-  	  A Study and Analysis of Construction Equipment Management used in ...IRJET-  	  A Study and Analysis of Construction Equipment Management used in ...
IRJET- A Study and Analysis of Construction Equipment Management used in ...
 
76 s201903
76 s20190376 s201903
76 s201903
 
Risk Contingency Evaluation in International Construction Projects (Real Case...
Risk Contingency Evaluation in International Construction Projects (Real Case...Risk Contingency Evaluation in International Construction Projects (Real Case...
Risk Contingency Evaluation in International Construction Projects (Real Case...
 
Risk Management Technique of Ready Mix Concrete Plants
Risk Management Technique of Ready Mix Concrete PlantsRisk Management Technique of Ready Mix Concrete Plants
Risk Management Technique of Ready Mix Concrete Plants
 
IRJET- Productivity Improvement in Construction Industry using Automation Tec...
IRJET- Productivity Improvement in Construction Industry using Automation Tec...IRJET- Productivity Improvement in Construction Industry using Automation Tec...
IRJET- Productivity Improvement in Construction Industry using Automation Tec...
 
IRJET- Study on Buildability Factors Affecting Formwork Labour Productivity i...
IRJET- Study on Buildability Factors Affecting Formwork Labour Productivity i...IRJET- Study on Buildability Factors Affecting Formwork Labour Productivity i...
IRJET- Study on Buildability Factors Affecting Formwork Labour Productivity i...
 
IRJET- A Review Paper on Lean Management in Construction Sites
IRJET-  	  A Review Paper on Lean Management in Construction SitesIRJET-  	  A Review Paper on Lean Management in Construction Sites
IRJET- A Review Paper on Lean Management in Construction Sites
 
IRJET- Equipment Planning and Management in Road Construction Project
IRJET- Equipment Planning and Management in Road Construction ProjectIRJET- Equipment Planning and Management in Road Construction Project
IRJET- Equipment Planning and Management in Road Construction Project
 
IRJET- Equipment Planning and Management in Road Construction Project
IRJET- Equipment Planning and Management in Road Construction ProjectIRJET- Equipment Planning and Management in Road Construction Project
IRJET- Equipment Planning and Management in Road Construction Project
 
A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...
A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...
A Review On Quantified Impacts Of Construction Labour Productivity Towards Pr...
 
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
 
BIM-Based Cost Estimation/ Monitoring For Building Construction
BIM-Based Cost Estimation/ Monitoring For Building ConstructionBIM-Based Cost Estimation/ Monitoring For Building Construction
BIM-Based Cost Estimation/ Monitoring For Building Construction
 
A Review on Productivity Improvement in Construction Industry
A Review on Productivity Improvement in Construction IndustryA Review on Productivity Improvement in Construction Industry
A Review on Productivity Improvement in Construction Industry
 
Towards The Development of an Index to Measure the Performance of Multi-Produ...
Towards The Development of an Index to Measure the Performance of Multi-Produ...Towards The Development of an Index to Measure the Performance of Multi-Produ...
Towards The Development of an Index to Measure the Performance of Multi-Produ...
 
Efficient Planning Scheduling and Delay Analysis of Residential Project
Efficient Planning Scheduling and Delay Analysis of Residential ProjectEfficient Planning Scheduling and Delay Analysis of Residential Project
Efficient Planning Scheduling and Delay Analysis of Residential Project
 
Concurrent Engineering- for Environment & Sustainability
Concurrent Engineering- for Environment & SustainabilityConcurrent Engineering- for Environment & Sustainability
Concurrent Engineering- for Environment & Sustainability
 
IRJET- Optimization in Construction Management
IRJET-  	  Optimization in Construction ManagementIRJET-  	  Optimization in Construction Management
IRJET- Optimization in Construction Management
 
IRJET- Optimization of Machining Facility Layout by using Simulation: Cas...
IRJET-  	  Optimization of Machining Facility Layout by using Simulation: Cas...IRJET-  	  Optimization of Machining Facility Layout by using Simulation: Cas...
IRJET- Optimization of Machining Facility Layout by using Simulation: Cas...
 
Material Management Practices of “Foundation Silver Spring” Residential Build...
Material Management Practices of “Foundation Silver Spring” Residential Build...Material Management Practices of “Foundation Silver Spring” Residential Build...
Material Management Practices of “Foundation Silver Spring” Residential Build...
 

Similar to Ijciet 10 01_029

An Automated Input Data Management Approach for Discrete Event Simulation App...
An Automated Input Data Management Approach for Discrete Event Simulation App...An Automated Input Data Management Approach for Discrete Event Simulation App...
An Automated Input Data Management Approach for Discrete Event Simulation App...
IJERA Editor
 
Development of a web based decision support system for materials selection in...
Development of a web based decision support system for materials selection in...Development of a web based decision support system for materials selection in...
Development of a web based decision support system for materials selection in...
IAEME Publication
 
Success factors enhancing business performance of engineering procurement
Success factors enhancing business performance of engineering procurementSuccess factors enhancing business performance of engineering procurement
Success factors enhancing business performance of engineering procurement
IAEME Publication
 
Success factors enhancing business performance of engineering procurement c...
Success factors enhancing business performance of  engineering procurement  c...Success factors enhancing business performance of  engineering procurement  c...
Success factors enhancing business performance of engineering procurement c...
IAEME Publication
 
Earned Value Management for Design and Construction Project
Earned Value Management for Design and Construction ProjectEarned Value Management for Design and Construction Project
Earned Value Management for Design and Construction Project
ijtsrd
 

Similar to Ijciet 10 01_029 (20)

USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...
USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...
USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...
 
An Automated Input Data Management Approach for Discrete Event Simulation App...
An Automated Input Data Management Approach for Discrete Event Simulation App...An Automated Input Data Management Approach for Discrete Event Simulation App...
An Automated Input Data Management Approach for Discrete Event Simulation App...
 
Opportunities and Challenges of Modular Coordination: A Review
Opportunities and Challenges of Modular Coordination: A ReviewOpportunities and Challenges of Modular Coordination: A Review
Opportunities and Challenges of Modular Coordination: A Review
 
Review Application of value engineering in construction project.
Review Application of value engineering in construction project.Review Application of value engineering in construction project.
Review Application of value engineering in construction project.
 
Time, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsTime, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction Projects
 
IRJET-Influence of Material Management on Construction Project
IRJET-Influence of Material Management on Construction ProjectIRJET-Influence of Material Management on Construction Project
IRJET-Influence of Material Management on Construction Project
 
IRJET- Critical Chain Project Management in Construction Projects
IRJET- Critical Chain Project Management in Construction ProjectsIRJET- Critical Chain Project Management in Construction Projects
IRJET- Critical Chain Project Management in Construction Projects
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
 
Development of a web based decision support system for materials selection in...
Development of a web based decision support system for materials selection in...Development of a web based decision support system for materials selection in...
Development of a web based decision support system for materials selection in...
 
Study of Lean construction tools for Workflow Improvement -A Review
Study of Lean construction tools for Workflow Improvement -A ReviewStudy of Lean construction tools for Workflow Improvement -A Review
Study of Lean construction tools for Workflow Improvement -A Review
 
Element of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewElement of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A Review
 
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
 
Success factors enhancing business performance of engineering procurement
Success factors enhancing business performance of engineering procurementSuccess factors enhancing business performance of engineering procurement
Success factors enhancing business performance of engineering procurement
 
Success factors enhancing business performance of engineering procurement c...
Success factors enhancing business performance of  engineering procurement  c...Success factors enhancing business performance of  engineering procurement  c...
Success factors enhancing business performance of engineering procurement c...
 
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
 
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project Failure
 
IRJET- Enhancement of Highway Project Performance using Lean Construction Method
IRJET- Enhancement of Highway Project Performance using Lean Construction MethodIRJET- Enhancement of Highway Project Performance using Lean Construction Method
IRJET- Enhancement of Highway Project Performance using Lean Construction Method
 
Earned Value Management for Design and Construction Project
Earned Value Management for Design and Construction ProjectEarned Value Management for Design and Construction Project
Earned Value Management for Design and Construction Project
 
An Integrated BIM System To Track The Time And Cost Of Construction Projects ...
An Integrated BIM System To Track The Time And Cost Of Construction Projects ...An Integrated BIM System To Track The Time And Cost Of Construction Projects ...
An Integrated BIM System To Track The Time And Cost Of Construction Projects ...
 
A Framework to optimize Construction Site Layout Planning
A Framework to optimize Construction Site Layout PlanningA Framework to optimize Construction Site Layout Planning
A Framework to optimize Construction Site Layout Planning
 

More from IAEME Publication

A STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURS
A STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURSA STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURS
A STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURS
IAEME Publication
 
BROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURS
BROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURSBROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURS
BROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURS
IAEME Publication
 
GANDHI ON NON-VIOLENT POLICE
GANDHI ON NON-VIOLENT POLICEGANDHI ON NON-VIOLENT POLICE
GANDHI ON NON-VIOLENT POLICE
IAEME Publication
 
A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...
A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...
A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...
IAEME Publication
 
ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...
ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...
ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...
IAEME Publication
 
INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...
INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...
INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...
IAEME Publication
 
A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...
A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...
A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...
IAEME Publication
 
ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...
ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...
ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...
IAEME Publication
 
OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...
OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...
OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...
IAEME Publication
 
APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...
APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...
APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...
IAEME Publication
 

More from IAEME Publication (20)

IAEME_Publication_Call_for_Paper_September_2022.pdf
IAEME_Publication_Call_for_Paper_September_2022.pdfIAEME_Publication_Call_for_Paper_September_2022.pdf
IAEME_Publication_Call_for_Paper_September_2022.pdf
 
MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...
MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...
MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...
 
A STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURS
A STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURSA STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURS
A STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURS
 
BROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURS
BROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURSBROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURS
BROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURS
 
DETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONS
DETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONSDETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONS
DETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONS
 
ANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONS
ANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONSANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONS
ANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONS
 
VOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINO
VOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINOVOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINO
VOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINO
 
IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...
IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...
IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...
 
VISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMY
VISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMYVISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMY
VISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMY
 
A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...
A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...
A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...
 
GANDHI ON NON-VIOLENT POLICE
GANDHI ON NON-VIOLENT POLICEGANDHI ON NON-VIOLENT POLICE
GANDHI ON NON-VIOLENT POLICE
 
A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...
A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...
A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...
 
ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...
ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...
ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...
 
INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...
INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...
INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...
 
A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...
A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...
A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...
 
EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...
EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...
EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...
 
ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...
ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...
ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...
 
OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...
OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...
OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...
 
APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...
APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...
APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...
 
A MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENT
A MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENTA MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENT
A MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENT
 

Recently uploaded

electrical installation and maintenance.
electrical installation and maintenance.electrical installation and maintenance.
electrical installation and maintenance.
benjamincojr
 
Maher Othman Interior Design Portfolio..
Maher Othman Interior Design Portfolio..Maher Othman Interior Design Portfolio..
Maher Othman Interior Design Portfolio..
MaherOthman7
 
Artificial intelligence presentation2-171219131633.pdf
Artificial intelligence presentation2-171219131633.pdfArtificial intelligence presentation2-171219131633.pdf
Artificial intelligence presentation2-171219131633.pdf
Kira Dess
 

Recently uploaded (20)

Independent Solar-Powered Electric Vehicle Charging Station
Independent Solar-Powered Electric Vehicle Charging StationIndependent Solar-Powered Electric Vehicle Charging Station
Independent Solar-Powered Electric Vehicle Charging Station
 
Involute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdf
Involute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdfInvolute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdf
Involute of a circle,Square, pentagon,HexagonInvolute_Engineering Drawing.pdf
 
Interfacing Analog to Digital Data Converters ee3404.pdf
Interfacing Analog to Digital Data Converters ee3404.pdfInterfacing Analog to Digital Data Converters ee3404.pdf
Interfacing Analog to Digital Data Converters ee3404.pdf
 
CLOUD COMPUTING SERVICES - Cloud Reference Modal
CLOUD COMPUTING SERVICES - Cloud Reference ModalCLOUD COMPUTING SERVICES - Cloud Reference Modal
CLOUD COMPUTING SERVICES - Cloud Reference Modal
 
electrical installation and maintenance.
electrical installation and maintenance.electrical installation and maintenance.
electrical installation and maintenance.
 
Intro to Design (for Engineers) at Sydney Uni
Intro to Design (for Engineers) at Sydney UniIntro to Design (for Engineers) at Sydney Uni
Intro to Design (for Engineers) at Sydney Uni
 
Diploma Engineering Drawing Qp-2024 Ece .pdf
Diploma Engineering Drawing Qp-2024 Ece .pdfDiploma Engineering Drawing Qp-2024 Ece .pdf
Diploma Engineering Drawing Qp-2024 Ece .pdf
 
Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)
 
Artificial Intelligence in due diligence
Artificial Intelligence in due diligenceArtificial Intelligence in due diligence
Artificial Intelligence in due diligence
 
UNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxUNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptx
 
NO1 Best Powerful Vashikaran Specialist Baba Vashikaran Specialist For Love V...
NO1 Best Powerful Vashikaran Specialist Baba Vashikaran Specialist For Love V...NO1 Best Powerful Vashikaran Specialist Baba Vashikaran Specialist For Love V...
NO1 Best Powerful Vashikaran Specialist Baba Vashikaran Specialist For Love V...
 
litvinenko_Henry_Intrusion_Hong-Kong_2024.pdf
litvinenko_Henry_Intrusion_Hong-Kong_2024.pdflitvinenko_Henry_Intrusion_Hong-Kong_2024.pdf
litvinenko_Henry_Intrusion_Hong-Kong_2024.pdf
 
Software Engineering Practical File Front Pages.pdf
Software Engineering Practical File Front Pages.pdfSoftware Engineering Practical File Front Pages.pdf
Software Engineering Practical File Front Pages.pdf
 
History of Indian Railways - the story of Growth & Modernization
History of Indian Railways - the story of Growth & ModernizationHistory of Indian Railways - the story of Growth & Modernization
History of Indian Railways - the story of Growth & Modernization
 
Raashid final report on Embedded Systems
Raashid final report on Embedded SystemsRaashid final report on Embedded Systems
Raashid final report on Embedded Systems
 
Maher Othman Interior Design Portfolio..
Maher Othman Interior Design Portfolio..Maher Othman Interior Design Portfolio..
Maher Othman Interior Design Portfolio..
 
Artificial intelligence presentation2-171219131633.pdf
Artificial intelligence presentation2-171219131633.pdfArtificial intelligence presentation2-171219131633.pdf
Artificial intelligence presentation2-171219131633.pdf
 
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
 
analog-vs-digital-communication (concept of analog and digital).pptx
analog-vs-digital-communication (concept of analog and digital).pptxanalog-vs-digital-communication (concept of analog and digital).pptx
analog-vs-digital-communication (concept of analog and digital).pptx
 
Seismic Hazard Assessment Software in Python by Prof. Dr. Costas Sachpazis
Seismic Hazard Assessment Software in Python by Prof. Dr. Costas SachpazisSeismic Hazard Assessment Software in Python by Prof. Dr. Costas Sachpazis
Seismic Hazard Assessment Software in Python by Prof. Dr. Costas Sachpazis
 

Ijciet 10 01_029

  • 1. http://www.iaeme.com/IJMET/index. International Journal of Civil Engineering and Technology (IJCIET) Volume 10, Issue 1, January 2019, pp. Available online at http://www.iaeme.com/IJCIET/issues.asp?JType=IJCIET&VType=10&IType=1 ISSN Print: 0976-6308 and ISSN Online: 0976 ©IAEME Publication APPLICATION OF PERT INTEGRATION ON BUILD Master Program of Civil ABSTRACT The job structure of the bottom (lower Structure) has the weight of the work amounted to 8% of the total cost of the construction of high delay in implementation analysis conducted by using the Relative Important Index (RII) Obtained 15 influential factors ie Comparison of measurement and prediction, the adequacy of the plan Specifications, fix and schedules and plans, instrumentation and monitoring, evaluation of static pole Data , Data collection, soil conditions, scope of work, Issues, accuracy of data, problem identification, Solution Optimization, validation projects, Improve communication, skilled workforce. While the resu the analysis of the case study foundations work efficiency powerboats Obtained results using PERT of 4.85% and optimization for quality using Six Sigma of 99. 56%. Keywords: PERT Method, Six Sigma M Cite this Article: Albert Eddy Husin, Application of Pert and Six Sigma Integration On Building Pile Foundation Technology (IJCIET), 10 (1), 2018, pp. http://www.iaeme.com/IJCIET/issues.asp?JType=IJCIET&VType=10&IType=1 1. INTRODUCTION High-rise building (High Rise building) is a multi process of work on the implementation of high obstacles often encountered is from the time that the delay of the project and of the quality of that quality is not in accordance with the technical specifications required [1]. Resulted in the loss of the project and construction failures. Pile foundations are generally preferred when heavy structural loads have to be transferred through weak subsoil to firm strata. The piles often penetrate through a contaminated zone and then fully penetrate an underlying aquitard, possibly entering a deeper underlying aquifer, to achieve higher bearing capacities [2]. Piling Works with methodology Six Sigma has the DMAIC phases ( step was used a variety of methods and tools (tools), both quantitative and qualitative IJMET/index.asp 307 editor@iaeme.com International Journal of Civil Engineering and Technology (IJCIET) Volume 10, Issue 1, January 2019, pp.307–314, Article ID: IJCIET_10_01_029 http://www.iaeme.com/IJCIET/issues.asp?JType=IJCIET&VType=10&IType=1 6308 and ISSN Online: 0976-6316 Scopus Indexed APPLICATION OF PERT AND SIX SIGMA INTEGRATION ON BUILDING PILE FOUNDATION Albert Eddy Husin Civil Engineering, Mercu Buana University, Jakarta, Indonesia The job structure of the bottom (lower Structure) has the weight of the work amounted to 8% of the total cost of the construction of high-rise buildings, while the of the work Reached 12%. The results of the statistical analysis conducted by using the Relative Important Index (RII) Obtained 15 influential factors ie Comparison of measurement and prediction, the adequacy of the plan Specifications, fix and schedules and plans, instrumentation and monitoring, evaluation of static pole Data , Data collection, soil conditions, scope of work, Issues, accuracy of data, problem identification, Solution Optimization, validation projects, Improve communication, skilled workforce. While the resu the analysis of the case study foundations work efficiency powerboats Obtained results using PERT of 4.85% and optimization for quality using Six Sigma of 99. 56%. PERT Method, Six Sigma Method, Pile Foundation. Albert Eddy Husin, Application of Pert and Six Sigma Integration On Building Pile Foundation, International Journal of Civil Engineering and , 10 (1), 2018, pp. 307–314. http://www.iaeme.com/IJCIET/issues.asp?JType=IJCIET&VType=10&IType=1 rise building (High Rise building) is a multi-story building on land use is limited. In the process of work on the implementation of high-rise building construction project, the obstacles often encountered is from the time that the delay of the project and of the quality of that quality is not in accordance with the technical specifications required [1]. Resulted in the loss of the project and construction failures. ions are generally preferred when heavy structural loads have to be transferred through weak subsoil to firm strata. The piles often penetrate through a contaminated zone and then fully penetrate an underlying aquitard, possibly entering a deeper g aquifer, to achieve higher bearing capacities [2]. Piling Works with methodology ix Sigma has the DMAIC phases (Define, Measure, Analyze, Improve, and Control) each step was used a variety of methods and tools (tools), both quantitative and qualitative editor@iaeme.com http://www.iaeme.com/IJCIET/issues.asp?JType=IJCIET&VType=10&IType=1 AND SIX SIGMA ING PILE iversity, Jakarta, Indonesia The job structure of the bottom (lower Structure) has the weight of the work rise buildings, while the esults of the statistical analysis conducted by using the Relative Important Index (RII) Obtained 15 influential factors ie Comparison of measurement and prediction, the adequacy of the plan Specifications, fix and schedules and plans, instrumentation and performance monitoring, evaluation of static pole Data , Data collection, soil conditions, scope of work, Issues, accuracy of data, problem identification, Solution Optimization, validation projects, Improve communication, skilled workforce. While the results of the analysis of the case study foundations work efficiency powerboats Obtained results using PERT of 4.85% and optimization for quality using Six Sigma of 99. 56%. Albert Eddy Husin, Application of Pert and Six Sigma Integration International Journal of Civil Engineering and http://www.iaeme.com/IJCIET/issues.asp?JType=IJCIET&VType=10&IType=1 story building on land use is limited. In the rise building construction project, the obstacles often encountered is from the time that the delay of the project and of the quality of that quality is not in accordance with the technical specifications required [1]. Resulted in the ions are generally preferred when heavy structural loads have to be transferred through weak subsoil to firm strata. The piles often penetrate through a contaminated zone and then fully penetrate an underlying aquitard, possibly entering a deeper g aquifer, to achieve higher bearing capacities [2]. Piling Works with methodology Define, Measure, Analyze, Improve, and Control) each step was used a variety of methods and tools (tools), both quantitative and qualitative
  • 2. Albert Eddy Husin http://www.iaeme.com/IJCIET/index.asp 308 editor@iaeme.com methodologies while PERT. PERT is a project management tool that is used for scheduling, organizing and coordinating the parts of the job that is in a project. In the process of the construction project work trip this high-rise building, a problem frequently encountered. On the application of the PERT method is common factors of delay in the project (delay) such as: the availability of resources (Meshach 2013, the Bora in 2016), workers who do not fit, construction equipment inadequate [3], environmental factors Project, project management is not good [4], the lack of communication between crew good workers [5]. While the application of the method Six Sigma is not maximized due to the factors of the failure of the quality of a construction project including: project delays, errors in estimating costs Insufficient resources on the project [5], the absence of risk management at project [6], and the imbalance of work on each segment [5]. By understanding the key success factors are expected to apply their stakeholders interested in the building project and contribute to science in education. The duration of a project is determined by a system flow plan in which the duration of each task has an expected value and a variance. Simplified PERT durations are subject to errors of greater than 10% when the skewness of the actual distribution is greater than 0.28 or less than 20.48 [7]. The aim of this research is to identify the key success factors of the application integration PERT methods and methods Six Sigma on the implementation of the pile foundation construction work in the building construction project in Indonesia and determine the key factors of success were very influential or dominant (CSF) to application integration PERT Methods and Methods Six Sigma on the implementation of the work pile foundation of high- rise buildings in the building construction project in Indonesia. The scope of this study is the perception of the data used is collected through a questionnaire derived from the contractor and the consultant's study who operate in areas of Jakarta qualification large enterprises, medium and small 2. REVIEW OF RESEARCH Six Sigma is a new management tool that is used to replace Total Quality Management (TQM), highly focused on quality control by studying the company's overall production system. Having a goal to, reduce/eliminate production defects, cutting the time of manufacture of the product, and eliminates the cost. Six Sigma also called a comprehensive system, that is the strategy, discipline, and tools to achieve and support business success. Six Sigma is called a strategy for focusing on improving customer satisfaction, is called discipline for following the formal model, namely DMAIC (Define, Measure, Analyze, Improve, Control). DMAIC originally developed as part of the framework Six Sigma. It is an approach that is proven to eliminate or reduce defect (disability) and improve the quality associated with business metrics [8]. But in a construction project, it will require a good job scheduling so that jobs can be run regularly. There are several methods that can be used to manage time and project resources. One is the method PERT. PERT is a method to determine the schedule and budget of the sources, so as a job that has been determined in advance can be completed on time. PERT can keep managers aware of and receive this information on a regular basis. More than, PERT is an excellent approach to achieve the timely completion of the project. PERT method is known to exist in three estimates of the duration of each activity: Optimistic estimate (to), Most likely estimate (tm) and Pessimistic estimate (tp). As a selected object in this research project, especially in sub-high-rise buildings under the structure work. One of the most important and decisive parts in the high-rise building projects ( high rise building) is part of the lower structure of the building function and
  • 3. Application of Pert and Six Sigma Integration On Building Pile Foundation http://www.iaeme.com/IJCIET/index.asp 309 editor@iaeme.com usability of the pile foundation is to assign or transfer loads of construction on it ( upper structure) to the bedrock which is located very deep. 2.1. Research methods The study was conducted to analyze the understanding and identifying the barriers and assess the effect of the application of PERT scheduling methods and methods Six Sigma on the project of building a high degree on the quality and timing of the project. The study began by defining the problem and the title of research supported by a literature review. Once it was determined the concept and research hypothesis is the basis for selecting appropriate research methods [10]. To find out understanding and identifying constraints in implementing the scheduling and quality based on the method PERT and Six Sigma Methods on the project of building high levels of quality and time, then the preparation of a research instrument in the form of variables that are formulated in the form of questions (questionnaire). According to [9]. Figure 1 Flow Chart the application of the PERT method and the Six Sigma method at the Pile work The dominant constraint hereinafter is discussed on these findings to be deduced about the understanding and the dominant factors that cause obstacles in implementing integration methods PERT and Six Sigma to employment poles at high-rise building projects, continuing the interview/discussion with experts/specialists, which will be concluded and suggestions. 2.2. Develop research instruments Preparation of research instruments by using a questionnaire to the stages of preparation, namely by identifying variables, the main factors, and sub-factors, classify and search the most important factor, prepare statements in the points corresponding questions variables and compile qualitative respondents with multilevel. The application of the PERT method integration and the Six Sigma method on the implementation of high-rise building pile foundation work can be seen in the following figure 1.
  • 4. Albert Eddy Husin http://www.iaeme.com/IJCIET/index.asp 310 editor@iaeme.com 2.3. Research variable The initial stage of the RII analysis is to collect the questionnaire components to be distributed to the respondents. All components are prepared based on previous similar research. The questionnaire component consists of 3 parts including : Variable It is the main dimension taken from the research topic. Variables can be either theories or research objects [6]. There are 2 independent variables and 1 dependent variable in this study, namely: • Independent variables: Six Sigma Method and PERT Method • Bound Variables: The lower structure of a high-rise building. Main Factor • Is the main sub-dimension of the variable. The main variables are decomposed into smaller sub-dimensions and each main factor has a sub-factor component. In this study, there were 7 main factors from 3 main variables including: Six Sigma method variables: 5 Main factors (Define, Measure, Analysis, Improve, Control) • PERT method variable: 3 Main factors (Scheduling, Resources, Project Scope) • The variable structure under high-rise buildings: 3 Main factors (Work Preparation, Quality and Time, Implementation) Sub Factor It is a sub-dimension of main factors. Subfactors are questions that will be answered and filled out by respondents by giving a score to each item. In this study, there were 49 subfactors scattered in 11 main factors. The distribution of sub-factors in each main factor is as follow [11]: • Main factors of the Six Sigma method, 15 sub-factors • Main PERT method factor, 15 sub-factors • Main factor The lower structure of multi-story building height, 11 sub-factors, a total of 41 sub-factors. 2.4. Identification of the key success factors There are many supporting factors so that the implementation of the lower structure work of the High-rise Building has been successfully implemented including, comparison of measurements and predictions, Adequacy of plans and specifications, Improving schedules and plans, Instrument and monitoring performance, and others. Some of these studies were the longest in 2001 and the most recent in 2011. From these numbers, the key success factors were applying the PERT method and the Six Sigma method as much as 41 and grouped based on qualitative justification according to the equation of factors or intentions. another there are 15 most important factors of sub-factors according to the RII index rating.
  • 5. Application of Pert and Six Sigma Integration On Building Pile Foundation http://www.iaeme.com/IJCIET/index.asp 311 editor@iaeme.com 3. RESULTS AND DISCUSSION 3.1. Results and evaluation At this stage, the results of all stages of statistical analysis are compiled and evaluated regarding the most influential factors in the application of the Six Sigma estimation method and the PERT method on the lower structure work of high-rise buildings. the most influential, the most influential variable, the hypothesis decision is accepted. Fhitung = .( ) .( ) = . .( ) .( . ) = 56,61 Where: m = Number of free variables n = number of respondents Rules for testing significance: If Fcount > Ftable, then H1 is accepted H0 is rejected Fcount < Ftable, then H1 is rejected H0 is accepted With a significance level of α = 0.05, the value of F table is as follows: Ftable = F [(1-) (dk = m), (dk = n-m-1) (20) = F [(1-0.05) (dk = 2), (dk = 38-2-1) = F [(0.95), (2.35)], this can be seen from Figure 2. 3.2. Case Study Validation The acquired data was used to draw the connection between the outcome of this research to the cost and duration of the project [13]. Figure 2 Pile Histogram
  • 6. Albert Eddy Husin http://www.iaeme.com/IJCIET/index.asp 312 editor@iaeme.com Table 1. Duration of Pile Foundation Work Activities Scope Of Work Human Resouces and Tools Coefficient Productivity Volume Duration/ Group N Group Duration Land Work Excavation pile cap Excavator 0.0414 24.17 m3/hour 748.544 m3 5 days 1 5 days Foundation Work Cutting pile cap Worker 0.05 20 m/day 265.5 m3 14 days 1 14 days Foreman 0.2 Handyman 0.1 Making work floor 10 cm Handyman 1.2 2 m3/ day 18.71 m3 8 days 1 8 days Foreman 0.2 Leader foreman 0.02 Worker 0.06 Vibrator 0.05 Bekisting Pile Cap Handyman 0.15 4 m2/ days 50.13 m2 13 days 1 13 days Worker 0.005 Reinforced Pile Cap Handyman 0.01 2700.55 kg/ days 85067.43 kg 32 days 2 16 days Foreman 0.005 Loader foreman 0.003 Worker 0.003 Casting Concrete fc 30 Mpa Concrete mixer 0.631 11.9 m3/days 336.84 m3 31 days 1 31 days The Pile Foundation used is a square concrete pile foundation with dimensions of 45x45 cm and a length of 15 cm. Project data in this study used for testing case study validation is the AMARIS Hotel development project, located in Tangerang, obtained data made in table form 5. And Scheduling data for activity description can be seen in table 2. Figure 3. The Critical Path in Pile Foundation Work From the data in the field, it can be analyzed the critical path for pile foundation work activities as shown in the following figure 3. Pile foundation data from the field are obtained and made in the following table 3.
  • 7. Application of Pert and Six Sigma Integration On Building Pile Foundation http://www.iaeme.com/IJCIET/index.asp 313 editor@iaeme.com Table 2. Expected Time Description Pessimistic Moderate Optimistic Expected Time (Month) Variance Critical Path Variance Land Work Excavation of pile cap 2 5 10 5,33 1,78 Foundation Work Erection 20 23 30 23,67 2,78 2,78 Cutting Pile’s Head 10 14 19 14,17 2,25 2,25 Work Floor 10 cm 6 8 13 8,50 1,36 Formwork Pile Cap 11 13 16 13,17 0,69 Steel Assembly Pile Cap 12 16 19 15,83 1,36 1,36 Fc 30 MPaConcrete Casting 27 31 36 31,17 2,25 2,25 Known : Total Defect of Pile Foundation (D) = 216 Amount of Opportunity (O) = 5 Number of Points (U) = 30 Number of units per point = 5 Asked: DPMO? PU = D / U = 216/30 = 7.20 DPU is the average defect produced on each floor Table 3 Pile Foundation Data No. Defect Pile Foundation Number of Defect Percentage (%) 1 Cracks on poles 26 12 2 Position of Pile (Slope) 50 23 3 Clay Soil Layer (On Location) 39 18 4 Total Capacity 58 27 4 Land Hard On Location 43 20 TOTAL 216 100 DPO = = . ( ) = 0.00960 DPMO= 0.0096 x 1.000.000 = 9600 From the calculation of the data above and by using the Six Sigma method, defects obtained or produced by pile foundation work with a DPMO value of 9600 equivalent to 4.31 Sigma with a yield of around 99.56% following from the Sigma value table. It can be concluded that the construction of the project carrying out pile foundation work has a defect value. 4. CONCLUSION The application of PERT method scheduling method and Six Sigma method on the implementation of high-rise building pile foundation work obtained 15 of the most important and most influential factors, the influencing factors namely: Comparison of measurements and predictions, Adequacy of Plans and Specifications, Improving schedules and plans, instrumentation and performance monitoring, static pole data evaluation, data collection, soil
  • 8. Albert Eddy Husin http://www.iaeme.com/IJCIET/index.asp 314 editor@iaeme.com conditions, scope of work, problems, data accuracy, problem identification, solution optimization, project validation, improved communication, skilled workforce. By applying the PERT method can optimize project time to 93,247 days or equal to 4.85% from the time the original plan was 98 days. From the calculation using the Six Sigma method, it can reduce the defect in the implementation of pile foundation work with a DPMO value of 9600 DPMO equivalent to 4.31 Sigma with a yield of around 99.56%. Thus the research hypothesis by applying the Six Sigma Method in carrying out pile foundation work can reduce defects. REFERENCES [1] Tong Guo, M.ASCE, Li, A., Wei, L., and Gu, Y. (2013), Horizontal Translocation of a High-Rise Building: Case Study, Journal Of Performance Of Constructed Facilities © ASCE / MAY/JUNE 2013 235-242. [2] Satyamurthy, R., Nataraj, M.S., McManis, K.L., and Boutwell, G.P. (2008), Investigations of Pile Foundations in Brownfields, Journal Of Geotechnical And Geoenvironmental Engineering © ASCE / October 2008 / 1469-1475 [3] Hutagaol, K. (2013). Pembelajaran kontekstual untuk meningkatkan Representasi matematis siswa Sekolah Menengah Pertama. urnal Ilmiah Program Studi Matematika STKIP Siliwangi Bandung, 2, 91. Retrieved from http://e-journal.stkipsiliwangi.ac.id [4] Serpell, A. (1995). “Characterization of waste in building construction projects”. in Alarcon, L.: Lean Construction, A.A. Balkema, Rotterdam. [5] Suanda, B. (2011). Faktor Penyebab Keterlambatan Proyek. Retrieved 4 11, 2016, from https://www.manajemenproyekindonesia.com/?=389 [6] Hinze, W. (2008). Gravity and Magnetic Exploration: Principle, Practices, and Applications. New York: Cambridge University Press [7] Wayne D. Cottrell,1 P.E. (1999), Simplified Program Evaluation And Review Technique (PERT), Journal Of Construction Engineering And Management / January/February 1999. [8] Lee, K.L. and Su, Y. (2013), Applying Six Sigma to Quality Improvement in Construction, Journal Of Management In Engineering © ASCE / October 2013 [9] Husin, A. (2015). Model Aliansi Strategis Dalam Kemitraan Pemerintah Dan Swasta Pada Mega Proyek Infrastruktur Berbasis Value Engineering Untuk Meningkatkan Nilai Kelayakan Proyek, FT Universitas Indonesia. [10] Riduwan. (2010). Skala Pengukuran Variabel-Variabel Penelitian. Bandung: Alfabeta. [11] Husin A.E., Kussumardianadewi, B.D. (2018), Cost Performance Review On Value Engineering Optimized Floor Cover Finishing Work Of High Rise Office Building, International Journal of Scientific Research Engineering &Technology (IJSRET) Volume 7 Issue 11 823-832. [12] Husin A.E and Priyanto, D. (2018), Lean Construction Based Tower Crane Requirement Optimization In High Rise Building Construction Project, International Journal of Scientific Research Engineering &Technology (IJSRET) Volume 7 Issue 10 738-743. [13] Tong Guo, M.ASCE, Li, A., Wei, L., and Gu, Y. (2013), Horizontal Translocation of a High-Rise Building: Case Study, Journal Of Performance Of Constructed Facilities © ASCE / MAY/JUNE 2013 235-242.