SlideShare a Scribd company logo
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 05 | May 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 7561
Equipment planning and management in road construction project
Aakash P. Mohane1, Harshita P. Ambre2
1Student M.Tech Construction Management, Department of Civil Engineering, Sandip University
2Assistant Professor, Department of Civil Engineering Sandip University
---------------------------------------------------------------------***----------------------------------------------------------------------
Abstract - Equipment management is defined as a
management system that is required in planning and
controlling the quality and quantity of the equipment,
punctual equipment placement, good price and the right
quantity as required. Construction is a business sector that
relies primarily on high utilization of constructionequipment.
This thesis presents the identification of problems of
construction equipment planning and management for road
projects. The past researchers focused on construction
equipment selection, acquisition, operation, maintenanceand
disposal or replacement. The data collection method is
integrated questionnaire, interview and case studies; a
descriptive and inferential statistical data analysis has also
been used. Interpretations and discussions were made on the
basis of the results from the analysis ofpastresearchworkand
questionnaire survey. Most respondents believed that their
companies have no documented construction equipment
planning and management policy; also the result indicated
that idle time, down time, poor equipment maintenance
practices are some of major problems that affect construction
equipment planning and management. Costoverrun isthefirst
ranked among the negative effects of construction equipment
planning and management problem. By enhancing the
effectiveness of utilizing equipment; extensive volume of work
can be completed within a shorter period of time and, more
importantly, within the project schedule. Equipment is thus
one of the key factors for improving contractor’s capabilities
in performing their work more effectively and efficiently.
Key Words: EquipmentPlanningand Management,
Road Construction, Optimization
1. INTRODUCTION
Construction is a business sector that relies primarily on
high utilization of construction equipment. Equipment is
thus one of the key factors for improving capabilities in
performing work more effectively and efficiently. To
function anyproject in smooth manner it is essential that an
engineer should have a detailed knowledge about the
equipment available and to direct it on a particular task. The
overall progress of the project depends upon how fast the
work is carried out. Hence it becomes a necessity to select
the equipment by considering all aspects of working
conditions of site. So it is necessary to make the proper
planning & management ofequipment’s available to use it in
an effective manner at minimum possible cost and with
maximum output productivity.
Currently in Nashik city the Road construction sector
plays an important role in short term trends, with more
frequent development, not only for the sector itself but also
for other economic activities as well. As a result, it is firmly
believed that the road construction industry needs an
effective resource management practice to retain
profitability and continue its dynamic contribution to the
growth of the country. The cost of equipment in a project
varies from 10% to 30% of the total cost of the project,
depending upon the extent of mechanization. In modern
fully mechanized projects the cost of equipment goes up to
30%. Proper planning, selection, procurement, installation,
operation, maintenance and equipment replacement policy
plays an important role in equipment management for the
successful completion of the project. With the growinguse of
machinery it has become necessary for construction
engineers to be thoroughly familiar with the Construction
application and upkeep of the wide range of the modern
equipment.
1.1 Equipment’s management
Equipment’s management is defined as a management
system that is required in planning and controlling the
quality and quantity of the equipment, punctual equipment
placement, good price and the right quantity as required
(Bailey and Cole, 1995).
The management of equipment’s by construction firms is an
enterprise that involves many people with diverse interest,
talents and background. The building team indirectly
constitutes the management team on building sites. This is
due to the role played by each member of the team in
relation to the successful erection of the building (Skyoles,
1974).
1.2 Key factors which governs construction
equipment management
Selection of equipment
Acquisition of Equipment
Operation
Productivity
Maintenance
Disposal
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 05 | May 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 7562
2. LITERATURE REVIEW
M. Manikandan, et al., (2018) analyzed and studied
construction equipment management with respect to
improve productivityHesuggestedimprovingproductivityit
is essential to improve the performance of construction
systems, productivity will be achieved through high
equipment availability which is influenced by equipment
reliability and maintainability[1].MekdimMathewos(2017)
studied the construction equipment planning and
management problems in road construction projects in
Addis Ababa city roads in Ethiopia. He carried out survey
where most of the respondents agreed that maintenance is
very important part of equipment management which
directly affects the cost of operation of any
equipment.[2].IliasNaskoudakisandKleopatra Petroutsatou
(2016) have done thematic review on construction
equipment in which he covers operator’s competence as an
important parameter for equipment management.[3].
Samson Mekbib Atnaw, et al., (2016) studieda casestudyon
road construction equipment management in Malaysia in
which they they concluded use of solutions methods based
on minimization of cost and maximization of profit modules
implementations will help in optimum decision making [4].
Kartik Shard Thete and Dhiraj Rajendra Baviskar (2016)
studied the Construction Equipment management in which
they gave more importance to selection of equipment and
discussed selection of equipment depends upon site
conditions, duration of work and its overall cost of
operation.[5]. Prasannasangeetha andA,Alan.S(2015)from
Coimbatore India gives great significance overacquisition of
[6]. Mr. Nilesh D. Chinchore and Prof. Pranay R. khare
(Dec.2014) from Pune University have given importance
regarding selection of equipment for highway construction
project in which experience in operation andmaintenanceis
essential. [7].Tsado, Theophilus Yies and Theophilus Yisa
Tsado (2014) from Nigeria studied Equipment maintenance
as an aspect of construction project profitability.[8].Major
Virender Singh Phogat and Ajit Pratap Singh (2013) from
BITS Pillani-India studied the multi criteria approach for
selection for equipment at hilly road region.[9]. Sri. Nuwan
Randunupura and Chandanie Hadiwattege (2013) studied
plant and equipment management to minimize delays in
road construction in which they have reviewed plant and
equipment selection practices [10].DavidJ.EdwardandGary
D. Holt (2009) studied the construction plant and
management in UK andgives special importancetowards the
operator anditscompetence[11].Douglas D.Gransberg,Calin
M. Popescu and Richard C. Ryan (2006) in their book
construction equipment management for engineers
estimators and owners gives verydetailedattentiontowards
acquisition of heavy equipment listing financial methods of
acquiring[12].
3. PROBLEM STATEMENT
Management of equipment’s have over the yearswasa great
problem to most firms in the construction industry. In
construction project operations, there is always a tendency
of mismanagement of equipment’s by construction firms.As
the size of the contract increases, however so do the scale of
activities concerning equipment’s management. During the
occurrence of high number of projects, most construction
firms focus on getting work done whiles neglecting the
management of equipment’s. The negligence of proper
equipment’s management contributes to several negative
consequences such as, breakages of equipment’s,
dissatisfaction by client, and reduction in the productivity of
workers, equipment’s wastage,highprojectcostanddelayin
the progress of work at hand,whichaffectsthemaximization
of limited resources. Most construction firms have given
little priorities to the setting up of a department which
oversees the management of their equipment’s resulting in
improper equipment’s management if there is any at all.
Mismanagement of equipment’s can be classified as loss
since it has adverse effects on construction projects. On the
small sites, equipment’s are managed by individuals with
little or no knowledge about the management of
equipment’s. It is therefore prudentforconstructionfirmsto
have a critical look on equipment’s management,sinceit has
a rippling effect on construction projects.
4. METHODOLOGY
The focus of this research is identifying major problems in
construction equipment planning and management, and
there effect on construction equipment productivity on
Nashik city road projects. Investigating causes and effects of
construction equipment planning and management
problems within domestic grade one contractors and
equipment rental companies participating in Nashik city
road projects. Therefore, the choice of the mixed research
method is justified as an appropriate research strategy. The
determination of the study sample and the techniques of
data collection are also described.
4.1 Survey study
the questionnaire survey was used to obtain information
about the identification of major construction equipment
planning and management problems, itscauses and effects
among parties which were participating in Nashik CityRoad
projects. This included domestic GradeOnecontractors. The
questions had a number of choices of possible answers
and the respondents selected whatever they feel was most
appropriate. In this research, the response of the
questionnaire data was prepared based on the scale of
percentage rating scale measurement of the agreement
towards each statement. The reason to adopting this simple
scale is as to provide simplicity for the respondent to
answer and to make evaluation of collected data easier to
evaluate; and to rank major integration problems as the
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 05 | May 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 7563
objective of this research
4.2 Case study 1- Shevgedarna-donwade road
asphalt road project
This road section is about 5km long and it is at early
construction stage. Only excavation work of side trench and
supplying of excavated material to side shoulder work has
been considered to examine OEE (overall equipment
effectiveness) of Tata Hitachi 120x excavator. The project is
in active stage and is handled by researcher itself. Data
collection and record keeping of site is done by researcher
personally. With respect to equipment utilization and its
management OEE of excavator is carried out. All the records
and data will be maintained in different registerformatfrom
which comparative analysis will be done to conclude most
effective and efficient equipment management policy to
adopt with respect to equipment selection, its operation
4.3 Case study 2- Sarul stone quarry
This stone quarry is located near Nashik-Mumbai highway
near sarul village. 50m x 40x hill section is used for blasting
purpose to obtain stone metal from it. Operation of loading
of blasted dubber (large size blasted stone) is analyzed to
obtain OEE of Tata Hitachi 200x excavator.
4.4 Case study 3- Suprabha stonecrusherandplant
Suprabha stone crusher and plant is a well-known stone
crusher in Nashik city situated at villolhi village. The
company owns stone crusherplant,readymixconcreteplant
and bitumen plants where large quantity of loading and
dumping operation is carried out with the help of CAT
Hindustan loader. OEE of Loader is carried out from the day
to day registered data keeping of the company
4.5 OEE (Overall equipment effectiveness)
By definition, OEE is a measure of value added to the
production by a certain machine in a production time. The
demand for increasing productivity in the current
competitive construction industry led to a need for
performance measurement system for the production
process. One of such a performance measurement tool
which measures different production losses and which
indicate area of process improvement is an Overall
Equipment Effectiveness (OEE) index. It is a tool designedto
distinguish factors contributing for productivity losses.
Knowing the three fundamental performance rate
Availability Rate (AR), the Performance Rate (PR) and
the Quality Rate (QR) will help to compute overall
equipment effectiveness index. These rates indicate the
degree to which the required output those equipment
production losses stated
Where; AR – Availability Rate
PR – Performance rate and
QR – Quality Rate
5. OBSERVATIONS AND CALCULATIONS
5.1 Case study 1: Shevgedarna-donwade road asphalt
road project
Table no 1: collected data for Tata Hitachi EX 120 model.
5.2 Case study 2: - Sarul stone quarry
Table no 2: Data for Tata Hitachi EX 200 model excavator
Type of equipment Excavator
Model Tata Hitachi Model EX 120
heaped bucket
capacity 0.8 cum
material type medium hard murrum
Ideal excavation
from manufacturer 11.6 cum/hr.
Work done (day 1)
excavation of side trench 37.5
cum
Hour reading start
time: 4262.9 hrs.
Hour reading end:4270.6(
320minuits)
work done (day 2)
formation of side shoulder 875
meters
Hour reading start
time: 4252 hrs.
Hour reading end:4258.6 (
400minuits )
Work done (day 3)
excavation of side trench
32.5cum
Hour reading start
time: 4258.6 hrs.
Hour reading end:4263 (
260minuits)
Type of equipment Excavator
Model Tata Hitachi Model EX 200
heaped bucket
capacity 1.2 cum
material type Blasted stone ( Dubber)
Ideal excavation
from manufacturer 20 cum/hr.
Work done (day 1) Loading operation 132m3
work done ( day 2) Loading operation 77.53 m3
work done ( day 2) Loading operation 122.38 m3
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 05 | May 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 7564
5.3 Case study 3: Suprabha stone crusher and plant
Table no 3: collected data for Hindustan wheel loader2021
6. RESULT AND DISCUSION
6.1 Questionnaire survey:
Questionnaire survey carried out shows current status of
road construction companies of Nashik city. There are
variation in responses of contractors and different
psychology seen behind the answers of contractors. From
the result it is clearly seen that there is lack of construction
management in most of the firms in Nashik city. Most of the
construction firms do not have separate equipment of
maintenance manager which result into poor equipment
practices and faces breakdown of equipmenttwicea month.
The analysis shows most of the firms are not getting
expected output from their equipment which result them
into less productivity. Most of the contractors prefer local
garages and fitters to minimize the maintenance cost.
Contractors mostly select equipment according to the spare
part availability and general experience to minimize
production and maintenance cost. From the result of
questionnaire it seems that equipment management is very
important and necessary to increase the productivity. Most
of the construction companies inNashik own the equipment
instead of going for rental option, Tata products shows
more reliability and favorite choice of contractors as the
cost of maintenance is low and suitability to Nashik region.
From the survey it has seem that most of the construction
firms in Nashik city do not have specific equipment
management policy. Overall result of questionnaire survey
shows lack of equipment management results into low
productivity and loss of time and money.
6.2 Case study 1 Shevgedarna- Donwade road project:
Table 4 shows the result for three days analysis of Overall
equipment effectiveness of excavator TATA EX 120 which
was performing side trench excavation and shoulder laying
work.
Table 4 OEE for excavator EX 120
The result analysis shows Availability rate 86.64%,
performance rate is 53.88% Quality rate is 83.9% and OEE
is 39%.
0.00%
20.00%
40.00%
60.00%
80.00%
100.00%
Day 1
Day 2
Day 3
Chart 2 OEE analyses for excavator Tata EX 120
6.3 Case study 2: - Sarul stone quarry
Table 5 how’s the result for three days analysis of overall
equipment effectiveness of excavator TATA EX 200 which
was performing loading of blasted stone work.
Table no 5: OEE for excavator EX 200
The result shows Availability rate 90.47,
performance rate 70.47%, quality rate 100% and
OEE is 62.66%
Type of equipment Wheel loader
Model Caterpillar-Hindustan 2021D
heaped bucket
capacity 2.5 cum
material type Crushed metal
Ideal loading by
manufacturer 20 cum/hr.
Work done (day 1) Loading operation 350m3
work done ( day 2) Loading operation 290 m3
work done ( day 2) Loading operation 410 m3
Index Day 1 Day 2 Day 3
Availability rate 88.23% 95.23% 76.47%
Performance rate 49.87% 54.25% 57.54%
Quality rate 77.33% 85.14% 89.23%
OEE 33% 45% 39%
Index Day 1 Day 2 Day 3
Availability rate 90.47% 90.47% 90.47%
Performance
rate 84.19% 49.34% 77.88%
Quality rate 100.00% 100.00% 100.00%
OEE 75% 44% 69%
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 05 | May 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 7565
0.00%
20.00%
40.00%
60.00%
80.00%
100.00%
120.00%
Day 1
Day 2
Day 3
Chart 3 OEE analyses for excavator Tata EX 200
6.4 Case study 3: Suprabha stone crusher and plant
Table 6.3 shows the result for three days analysis of overall
equipment effectiveness of CAT-Hindustan wheel loader
2021D which was performing loading of Crushed metal work.
Table no 6: OEE for Hindustan wheel loader 2021D
The result shows Availabilityrate83.33%, performance rate
50.43%, Quality rate 100% and OEE is 49.33%
0.00%
20.00%
40.00%
60.00%
80.00%
100.00%
120.00%
Day 1
Day 2
Day 3
Chart 3 OEE analyses for Hindustan loader 2021D
7. CONCLUSIONS
The result indicated that insufficient knowledge of
selection of equipment, equipment down time, poor
equipment maintenance practices, improper determination
of timing of replacement, poor training of equipment
operators, equipment breakdown, ignorance towards
maintenance of equipment, huge capital investment during
acquisition, misunderstanding the scope of work carried
out, unit cost of production and equipment suitability for
job condition were found to be the major problems that
affect construction equipment planning and management
on Nashik city projectsduringtheplanningand construction
process.
At Nashik city knowledge about construction equipment
planning and management policy is very little. Insufficient
training of professional workforces on construction
equipment planning and management is the major problem
at Nashik city road construction projects. So, this study
proved that most of sampled respondents majorly use only
one or two types of equipment planning and management
policy.
Proper maintenance of construction equipment is vital
to keep construction equipment in good and serviceable
condition. As the study revealed, 40% of the respondents
use planned preventive maintenance method while only
33% performs periodic maintenance, 27% contractor’s still
go for maintenance after breakdown of equipment shows
negligence towards maintenance activity. All types of
maintenances are critically needed to keep equipment in
good and serviceable condition. By periodically maintaining
equipment using planned preventive maintenance method,
different major failures of equipment can be prevented
because “prevention is better than cure”.Also it is better to
do corrective maintenance when necessary to increase the
efficiency of equipment. In addition, unplanned or
unscheduled maintenance is necessarily needed because,
equipment can break down suddenly. Therefore, it is
better to use allmaintenance methods to make equipment
more productive. 70% of the construction companiesdo not
keep maintenance record of the equipment’s by which it is
difficult to keep an eye on maintenance cost expenditure
result of this company’s faces loss in profitability.
Study concluded only 20% of the respondent have separate
maintenance staff at company office, which is necessary to
minimize maintenance cost. Most of the firms appoint
technical expert on site when needed which adds visiting
charges resulting into extra maintenance cost. Survey
concluded management, Technical staff and operator of the
equipment are equally responsible for management
problems in road construction sector. It shows equipment
planning and management problems can be solved if these
factors are organized.
The performance of equipment effectiveness is
evaluated based on actual on site measurement. This actual
onsite construction equipment effectiveness is evaluated by
overall equipment effectiveness (OEE) indexes. OEEanalysis
concluded there is major flaw in performance factor of the
equipment. All three equipment’s donotdeliveringexpected
output. OEE for Excavator EX 120 is only 39% which shows
lack of productivity and performance rate. OEE for EX 200
Excavator is 62.34% which is quite acceptable but it can be
improved as machine shows rate drop in performance rate
factor. OEE for loader is 49% which is very low as machine
fails in giving expected performance. Overall conclusion of
OEE Analysis shows all machines were available for more
time but because of lack in performance factor machine
showed low productivity. While quality factors depends
Index Day 1 Day 2 Day 3
Availability rate 73.91% 91.30% 84.78%
Performance rate 42.27% 68.16% 40.87%
Quality rate 100.00% 100.00% 100.00%
OEE 30% 61% 57%
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 05 | May 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 7566
upon the operator of the equipment and management of the
activity. As proved by the case study, actual on site
performance of equipment is very poor due to different
management problems. All the analyses show that, OEE of
construction equipment is 50% and below 50%. This
shows that, the equipment productivityrate is below half of
its capacity. To avoid or reduce construction equipment
planning and management problems it is necessary to
identify the major causes of the problem. The results of
analysis indicated that, huge capital investment at
acquisition phase and poor maintenance practice with
improper determination of economic life and timing for
replacement are the major causes of construction
equipment planning and management problems.
This causes of construction equipment planning and
management problems reflected negative effects on project
performance. loss in productivity of equipment, time
overrun, cost overrun and equipment related accidents are
some of the major effects of construction equipment
planning and management problems. Most effects, like loss
in productivity of equipment, time overrun, equipment
related accidents are reflected on cost overrun. This is why
cost overrun was ranked first with the highest negative
effect on performance of road projects.
8. RECOMMENDATIONS:
After detail investigation on construction equipment
planning and management problems its causes and effects,
recommendations can be forwarded to contractors. The
recommendation meantto diminishconstructionequipment
planning and management problems on Nashik city road
construction projects. The following recommendations are
forwarded offices:
8.1 Recommendations at management level:
[1] Develop construction equipment planning and
management policy to be used as a guideLine to use
equipment efficiently.
[2] Should give awareness training for site engineers
about equipment planning andmanagementpolicyand
how to manage equipment at project level.
[3] Collect data about the current status of construction
equipment and efficiency of equipmentatprojectlevel.
[4] Develop planned preventive maintenance method to
eliminate long down time of equipment.
[5] Develop optimization methods to use available
equipment resource effectively and efficiently; and
Management has to establish a training center, to train
unskilled and semi-skilled operators.
[6] Management has to update the equipment
management guideline to reconcile with the current
working condition and work load.
[7] Management has to implement the currently available
technologies regarding equipment.
Recommendations for maintenance of equipment:
[1] Implement preventive maintenance, corrective
maintenance and unscheduled maintenance
program to leading construction equipment.
[2] Provide maintenance by equipment operators,
through in-house equipment department, equipment
dealers and external dealers.
[3] Consider poor maintenance and use of non-original
parts as the main cause of machine failure during use.
[4] Wait until the failed machine is completely repairedand
ready for use.
Recommendation’s for operator’s level:
[1] Provide training for equipment operators through in-
house equipment department, equipment dealer or
external agencies.
[2] Consider poor operating procedure as a main cause of
equipment accidents.
[3] Allow an equipment operator to work with more than
one machine.
[4] Collect daily based data to measure the overall
equipment effectiveness.
[5] Identify major factors that cause idle timeof equipment.
REFERENCES
[1] M. Manikandan, Prof. M. Adhiyaman, Dr. K.C.PazhaniA
,”study and analysis of construction equipment
management used in construction projects for
improving productivity”, Department of Civil
Engineering, Sona college of technology, Salem, India,
Anna university Chennai-600032,2018.
[2] Mekdim Mathewos,”AStudy onConstructionEquipment
Planning and management problems in Road
Construction Project (A case study: The Addis Ababa
City Roads Authority)”, The School of Civil and
Environmental Engineering, Addis Ababa University,
Ethiopia, 2017.
[3] Ilias Naskoudakis, Kleopatra Petroutsatou “a thematic
review of the main research on construction equipment
over recent year”, Laboratory of construction
equipment and management, department of civil
engineering ,School of engineering, AristotleUniversity,
Thessaloniki, University campus,54124, Thessaloniki,
Greece, 2016.
[4] Samson Mekbib Atnaw, Lakhveer Singh, Fatwi
Yohaness Hagos, Abu Yousuf “road construction
equipment management: a case study on selected
industry”, IJETS, Malaysia, 2016.
[5] Kartik Shard Thete, Dhiraj Rajendra Baviskar
“Construction Equipment management,” IJSETR. 2016.
[6] Prasannasangeetha. A,Alan. S,“Equipmentmanagement
in construction sector”, RVS Technical Campus,
Coimbatore, India, 2015.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 05 | May 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 7567
[7] Mr. Nilesh D.Chinchore, Prof. PranayR.khare,“Planning
and Selection of Heavy Equipment in Civil Engineering,
Department of Civil Engineering”, SavitribaiPhulePune
University, pune, Maharashtra, India. Dec.2014.
[8] Tsado, Theophilus Yies, Theophilus Yisa Tsado
“Equipment maintenance: an effective aspect of
enhancing construction project profitability”, civil
engineering department, school of engineering and
engineering technology, Federal University of
Technology, P.M.B. 55, Minna, Niger State, Nigeria,2014
[9] Major Virender Singh Phogat, Ajit Pratap Singh,
“Selection of Equipment for construction of a Hilly Road
using Multi Criteria Approch”,BITSPilani-333031-India,
2013.
[10] Sri.NuwanRandunupura,ChandanieHadiwattege“Plant
and EquipmentManagement toMinimizeDelaysinRoad
Construction Projections”, Department of Building
Economics, University of Moratuwa, Sri Lanka., 2013.
[11] David J. Edward and Gary D. Holt, “construction plant
and management research: Thematic review, Journal of
Engineering Design and technology” , Department of
civil engineering, July 2009.
[12] Douglas D. Gransberg, Calin M. Popescu,RichardC.Ryan
“construction equipment management for engineer’s
estimators and owners”, civil and building Engineering,
Loughborough University, Loughborough, UK, 2006.

More Related Content

What's hot

IRJET- Productivity Improvement in Construction Industry using Automation Tec...
IRJET- Productivity Improvement in Construction Industry using Automation Tec...IRJET- Productivity Improvement in Construction Industry using Automation Tec...
IRJET- Productivity Improvement in Construction Industry using Automation Tec...
IRJET Journal
 
IRJET- Study & Analysis of Subcontracting Practices in Infrastructure Project
IRJET- Study & Analysis of Subcontracting Practices in Infrastructure ProjectIRJET- Study & Analysis of Subcontracting Practices in Infrastructure Project
IRJET- Study & Analysis of Subcontracting Practices in Infrastructure Project
IRJET Journal
 
IRJET- Study and Analysis of Risk Management Strategies in Construction P...
IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...
IRJET- Study and Analysis of Risk Management Strategies in Construction P...
IRJET Journal
 
IRJET-A Review of Impact on Labour Management in Construction Industry
IRJET-A Review of Impact on Labour Management in Construction IndustryIRJET-A Review of Impact on Labour Management in Construction Industry
IRJET-A Review of Impact on Labour Management in Construction Industry
IRJET Journal
 
introduction to construction management
 introduction to construction management introduction to construction management
introduction to construction management
Hira Atiq
 
IRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in ConstructionIRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in Construction
IRJET Journal
 
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET Journal
 
IRJET- Study to Condense Expenditure through Engineering Management of Wood P...
IRJET- Study to Condense Expenditure through Engineering Management of Wood P...IRJET- Study to Condense Expenditure through Engineering Management of Wood P...
IRJET- Study to Condense Expenditure through Engineering Management of Wood P...
IRJET Journal
 
IRJET- Study to Reduce Cost Price of Wood Products Manufacturing by Value Eng...
IRJET- Study to Reduce Cost Price of Wood Products Manufacturing by Value Eng...IRJET- Study to Reduce Cost Price of Wood Products Manufacturing by Value Eng...
IRJET- Study to Reduce Cost Price of Wood Products Manufacturing by Value Eng...
IRJET Journal
 
IRJET- A Study of Implementing Lean & Fast Tracking in Construction Proje...
IRJET-  	  A Study of Implementing Lean & Fast Tracking in Construction Proje...IRJET-  	  A Study of Implementing Lean & Fast Tracking in Construction Proje...
IRJET- A Study of Implementing Lean & Fast Tracking in Construction Proje...
IRJET Journal
 
Concurrent Engineering- for Environment & Sustainability
Concurrent Engineering- for Environment & SustainabilityConcurrent Engineering- for Environment & Sustainability
Concurrent Engineering- for Environment & Sustainability
IRJET Journal
 
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET Journal
 
Material Management Practices of “Foundation Silver Spring” Residential Build...
Material Management Practices of “Foundation Silver Spring” Residential Build...Material Management Practices of “Foundation Silver Spring” Residential Build...
Material Management Practices of “Foundation Silver Spring” Residential Build...
IRJET Journal
 
Factor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road projectFactor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road project
IRJET Journal
 
Assesing the various problems facing in arranging appropirate labour and qual...
Assesing the various problems facing in arranging appropirate labour and qual...Assesing the various problems facing in arranging appropirate labour and qual...
Assesing the various problems facing in arranging appropirate labour and qual...
eSAT Journals
 
Report on Planning & scheduling of a Minor bridge
Report on Planning & scheduling of a Minor bridgeReport on Planning & scheduling of a Minor bridge
Report on Planning & scheduling of a Minor bridge
Kundan Sanap
 
Knowledge and skill requirements in the installation of prefabricated members
Knowledge and skill requirements in the installation of prefabricated membersKnowledge and skill requirements in the installation of prefabricated members
Knowledge and skill requirements in the installation of prefabricated membersIAEME Publication
 
Construction Management (1st Lecture)
Construction Management (1st Lecture) Construction Management (1st Lecture)
Construction Management (1st Lecture)
Muhammad Aljalali
 
02 Construction Projects
02 Construction Projects02 Construction Projects
02 Construction Projects
akashpadole
 
Effective techniques in cost optimization of construction project an review
Effective techniques in cost optimization of construction project   an reviewEffective techniques in cost optimization of construction project   an review
Effective techniques in cost optimization of construction project an review
eSAT Journals
 

What's hot (20)

IRJET- Productivity Improvement in Construction Industry using Automation Tec...
IRJET- Productivity Improvement in Construction Industry using Automation Tec...IRJET- Productivity Improvement in Construction Industry using Automation Tec...
IRJET- Productivity Improvement in Construction Industry using Automation Tec...
 
IRJET- Study & Analysis of Subcontracting Practices in Infrastructure Project
IRJET- Study & Analysis of Subcontracting Practices in Infrastructure ProjectIRJET- Study & Analysis of Subcontracting Practices in Infrastructure Project
IRJET- Study & Analysis of Subcontracting Practices in Infrastructure Project
 
IRJET- Study and Analysis of Risk Management Strategies in Construction P...
IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...
IRJET- Study and Analysis of Risk Management Strategies in Construction P...
 
IRJET-A Review of Impact on Labour Management in Construction Industry
IRJET-A Review of Impact on Labour Management in Construction IndustryIRJET-A Review of Impact on Labour Management in Construction Industry
IRJET-A Review of Impact on Labour Management in Construction Industry
 
introduction to construction management
 introduction to construction management introduction to construction management
introduction to construction management
 
IRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in ConstructionIRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in Construction
 
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...
 
IRJET- Study to Condense Expenditure through Engineering Management of Wood P...
IRJET- Study to Condense Expenditure through Engineering Management of Wood P...IRJET- Study to Condense Expenditure through Engineering Management of Wood P...
IRJET- Study to Condense Expenditure through Engineering Management of Wood P...
 
IRJET- Study to Reduce Cost Price of Wood Products Manufacturing by Value Eng...
IRJET- Study to Reduce Cost Price of Wood Products Manufacturing by Value Eng...IRJET- Study to Reduce Cost Price of Wood Products Manufacturing by Value Eng...
IRJET- Study to Reduce Cost Price of Wood Products Manufacturing by Value Eng...
 
IRJET- A Study of Implementing Lean & Fast Tracking in Construction Proje...
IRJET-  	  A Study of Implementing Lean & Fast Tracking in Construction Proje...IRJET-  	  A Study of Implementing Lean & Fast Tracking in Construction Proje...
IRJET- A Study of Implementing Lean & Fast Tracking in Construction Proje...
 
Concurrent Engineering- for Environment & Sustainability
Concurrent Engineering- for Environment & SustainabilityConcurrent Engineering- for Environment & Sustainability
Concurrent Engineering- for Environment & Sustainability
 
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
 
Material Management Practices of “Foundation Silver Spring” Residential Build...
Material Management Practices of “Foundation Silver Spring” Residential Build...Material Management Practices of “Foundation Silver Spring” Residential Build...
Material Management Practices of “Foundation Silver Spring” Residential Build...
 
Factor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road projectFactor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road project
 
Assesing the various problems facing in arranging appropirate labour and qual...
Assesing the various problems facing in arranging appropirate labour and qual...Assesing the various problems facing in arranging appropirate labour and qual...
Assesing the various problems facing in arranging appropirate labour and qual...
 
Report on Planning & scheduling of a Minor bridge
Report on Planning & scheduling of a Minor bridgeReport on Planning & scheduling of a Minor bridge
Report on Planning & scheduling of a Minor bridge
 
Knowledge and skill requirements in the installation of prefabricated members
Knowledge and skill requirements in the installation of prefabricated membersKnowledge and skill requirements in the installation of prefabricated members
Knowledge and skill requirements in the installation of prefabricated members
 
Construction Management (1st Lecture)
Construction Management (1st Lecture) Construction Management (1st Lecture)
Construction Management (1st Lecture)
 
02 Construction Projects
02 Construction Projects02 Construction Projects
02 Construction Projects
 
Effective techniques in cost optimization of construction project an review
Effective techniques in cost optimization of construction project   an reviewEffective techniques in cost optimization of construction project   an review
Effective techniques in cost optimization of construction project an review
 

Similar to IRJET- Equipment Planning and Management in Road Construction Project

IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
IRJET Journal
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET Journal
 
IRJET-Influence of Material Management on Construction Project
IRJET-Influence of Material Management on Construction ProjectIRJET-Influence of Material Management on Construction Project
IRJET-Influence of Material Management on Construction Project
IRJET Journal
 
Construction Management Techniques to Complete the Project within Time Period...
Construction Management Techniques to Complete the Project within Time Period...Construction Management Techniques to Complete the Project within Time Period...
Construction Management Techniques to Complete the Project within Time Period...
IRJET Journal
 
Mechanized Construction- Relevance and Importance in India
Mechanized Construction- Relevance and Importance in IndiaMechanized Construction- Relevance and Importance in India
Mechanized Construction- Relevance and Importance in India
JIT KUMAR GUPTA
 
IRJET-Survey on Effects of Productivity of Equipment in Construction Projects
IRJET-Survey on Effects of Productivity of Equipment in Construction ProjectsIRJET-Survey on Effects of Productivity of Equipment in Construction Projects
IRJET-Survey on Effects of Productivity of Equipment in Construction Projects
IRJET Journal
 
Challenges in High-Rise Building Projects for Parameters of Project Managemen...
Challenges in High-Rise Building Projects for Parameters of Project Managemen...Challenges in High-Rise Building Projects for Parameters of Project Managemen...
Challenges in High-Rise Building Projects for Parameters of Project Managemen...
IRJET Journal
 
IRJET- Study of Innovative Technologies for Effective Construction and Manage...
IRJET- Study of Innovative Technologies for Effective Construction and Manage...IRJET- Study of Innovative Technologies for Effective Construction and Manage...
IRJET- Study of Innovative Technologies for Effective Construction and Manage...
IRJET Journal
 
IRJET- An Assessment of Role of Material Management in Construction Projects
IRJET- An Assessment of Role of Material Management in Construction ProjectsIRJET- An Assessment of Role of Material Management in Construction Projects
IRJET- An Assessment of Role of Material Management in Construction Projects
IRJET Journal
 
IRJET- Systematic Construction Equipment Handling in Construction Industr...
IRJET-  	  Systematic Construction Equipment Handling in Construction Industr...IRJET-  	  Systematic Construction Equipment Handling in Construction Industr...
IRJET- Systematic Construction Equipment Handling in Construction Industr...
IRJET Journal
 
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET Journal
 
Resource Optimization in Mivan Construction Project
Resource Optimization in Mivan Construction ProjectResource Optimization in Mivan Construction Project
Resource Optimization in Mivan Construction Project
IRJET Journal
 
Main Contractors' Strategies in Managing Construction Quality of Sub Contract...
Main Contractors' Strategies in Managing Construction Quality of Sub Contract...Main Contractors' Strategies in Managing Construction Quality of Sub Contract...
Main Contractors' Strategies in Managing Construction Quality of Sub Contract...
IRJET Journal
 
IRJET- Enhancement of Highway Project Performance using Lean Construction Method
IRJET- Enhancement of Highway Project Performance using Lean Construction MethodIRJET- Enhancement of Highway Project Performance using Lean Construction Method
IRJET- Enhancement of Highway Project Performance using Lean Construction Method
IRJET Journal
 
IMPORTANCE OF MANAGEMENT IN IMPROVING THE CONSTRUCTION PRODUCTIVITY
IMPORTANCE OF MANAGEMENT IN IMPROVING THE CONSTRUCTION PRODUCTIVITYIMPORTANCE OF MANAGEMENT IN IMPROVING THE CONSTRUCTION PRODUCTIVITY
IMPORTANCE OF MANAGEMENT IN IMPROVING THE CONSTRUCTION PRODUCTIVITY
IRJET Journal
 
A STUDY ON THE QUALITATIVE ANALYSIS OF MATERIALS MANAGEMENT IN KERALA CONSTRU...
A STUDY ON THE QUALITATIVE ANALYSIS OF MATERIALS MANAGEMENT IN KERALA CONSTRU...A STUDY ON THE QUALITATIVE ANALYSIS OF MATERIALS MANAGEMENT IN KERALA CONSTRU...
A STUDY ON THE QUALITATIVE ANALYSIS OF MATERIALS MANAGEMENT IN KERALA CONSTRU...
IRJET Journal
 
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET Journal
 
Review Application of value engineering in construction project.
Review Application of value engineering in construction project.Review Application of value engineering in construction project.
Review Application of value engineering in construction project.
IRJET Journal
 
PMIBC162001_PMIBC-16-2-001_Murari_Construction_Program_Management
PMIBC162001_PMIBC-16-2-001_Murari_Construction_Program_ManagementPMIBC162001_PMIBC-16-2-001_Murari_Construction_Program_Management
PMIBC162001_PMIBC-16-2-001_Murari_Construction_Program_ManagementMurari Thayi, PgMP, PMP
 
Assessment Of Construction Equipment Management Practice And Causes Of Proble...
Assessment Of Construction Equipment Management Practice And Causes Of Proble...Assessment Of Construction Equipment Management Practice And Causes Of Proble...
Assessment Of Construction Equipment Management Practice And Causes Of Proble...
Raquel Pellicier
 

Similar to IRJET- Equipment Planning and Management in Road Construction Project (20)

IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
IRJET-Analysis of Losses Due to Breakdown of Equipments in Construction.
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
 
IRJET-Influence of Material Management on Construction Project
IRJET-Influence of Material Management on Construction ProjectIRJET-Influence of Material Management on Construction Project
IRJET-Influence of Material Management on Construction Project
 
Construction Management Techniques to Complete the Project within Time Period...
Construction Management Techniques to Complete the Project within Time Period...Construction Management Techniques to Complete the Project within Time Period...
Construction Management Techniques to Complete the Project within Time Period...
 
Mechanized Construction- Relevance and Importance in India
Mechanized Construction- Relevance and Importance in IndiaMechanized Construction- Relevance and Importance in India
Mechanized Construction- Relevance and Importance in India
 
IRJET-Survey on Effects of Productivity of Equipment in Construction Projects
IRJET-Survey on Effects of Productivity of Equipment in Construction ProjectsIRJET-Survey on Effects of Productivity of Equipment in Construction Projects
IRJET-Survey on Effects of Productivity of Equipment in Construction Projects
 
Challenges in High-Rise Building Projects for Parameters of Project Managemen...
Challenges in High-Rise Building Projects for Parameters of Project Managemen...Challenges in High-Rise Building Projects for Parameters of Project Managemen...
Challenges in High-Rise Building Projects for Parameters of Project Managemen...
 
IRJET- Study of Innovative Technologies for Effective Construction and Manage...
IRJET- Study of Innovative Technologies for Effective Construction and Manage...IRJET- Study of Innovative Technologies for Effective Construction and Manage...
IRJET- Study of Innovative Technologies for Effective Construction and Manage...
 
IRJET- An Assessment of Role of Material Management in Construction Projects
IRJET- An Assessment of Role of Material Management in Construction ProjectsIRJET- An Assessment of Role of Material Management in Construction Projects
IRJET- An Assessment of Role of Material Management in Construction Projects
 
IRJET- Systematic Construction Equipment Handling in Construction Industr...
IRJET-  	  Systematic Construction Equipment Handling in Construction Industr...IRJET-  	  Systematic Construction Equipment Handling in Construction Industr...
IRJET- Systematic Construction Equipment Handling in Construction Industr...
 
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
 
Resource Optimization in Mivan Construction Project
Resource Optimization in Mivan Construction ProjectResource Optimization in Mivan Construction Project
Resource Optimization in Mivan Construction Project
 
Main Contractors' Strategies in Managing Construction Quality of Sub Contract...
Main Contractors' Strategies in Managing Construction Quality of Sub Contract...Main Contractors' Strategies in Managing Construction Quality of Sub Contract...
Main Contractors' Strategies in Managing Construction Quality of Sub Contract...
 
IRJET- Enhancement of Highway Project Performance using Lean Construction Method
IRJET- Enhancement of Highway Project Performance using Lean Construction MethodIRJET- Enhancement of Highway Project Performance using Lean Construction Method
IRJET- Enhancement of Highway Project Performance using Lean Construction Method
 
IMPORTANCE OF MANAGEMENT IN IMPROVING THE CONSTRUCTION PRODUCTIVITY
IMPORTANCE OF MANAGEMENT IN IMPROVING THE CONSTRUCTION PRODUCTIVITYIMPORTANCE OF MANAGEMENT IN IMPROVING THE CONSTRUCTION PRODUCTIVITY
IMPORTANCE OF MANAGEMENT IN IMPROVING THE CONSTRUCTION PRODUCTIVITY
 
A STUDY ON THE QUALITATIVE ANALYSIS OF MATERIALS MANAGEMENT IN KERALA CONSTRU...
A STUDY ON THE QUALITATIVE ANALYSIS OF MATERIALS MANAGEMENT IN KERALA CONSTRU...A STUDY ON THE QUALITATIVE ANALYSIS OF MATERIALS MANAGEMENT IN KERALA CONSTRU...
A STUDY ON THE QUALITATIVE ANALYSIS OF MATERIALS MANAGEMENT IN KERALA CONSTRU...
 
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project Failure
 
Review Application of value engineering in construction project.
Review Application of value engineering in construction project.Review Application of value engineering in construction project.
Review Application of value engineering in construction project.
 
PMIBC162001_PMIBC-16-2-001_Murari_Construction_Program_Management
PMIBC162001_PMIBC-16-2-001_Murari_Construction_Program_ManagementPMIBC162001_PMIBC-16-2-001_Murari_Construction_Program_Management
PMIBC162001_PMIBC-16-2-001_Murari_Construction_Program_Management
 
Assessment Of Construction Equipment Management Practice And Causes Of Proble...
Assessment Of Construction Equipment Management Practice And Causes Of Proble...Assessment Of Construction Equipment Management Practice And Causes Of Proble...
Assessment Of Construction Equipment Management Practice And Causes Of Proble...
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
IRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
IRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
IRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
IRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
IRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
IRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
IRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
IRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
SupreethSP4
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 

Recently uploaded (20)

RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 

IRJET- Equipment Planning and Management in Road Construction Project

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 05 | May 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 7561 Equipment planning and management in road construction project Aakash P. Mohane1, Harshita P. Ambre2 1Student M.Tech Construction Management, Department of Civil Engineering, Sandip University 2Assistant Professor, Department of Civil Engineering Sandip University ---------------------------------------------------------------------***---------------------------------------------------------------------- Abstract - Equipment management is defined as a management system that is required in planning and controlling the quality and quantity of the equipment, punctual equipment placement, good price and the right quantity as required. Construction is a business sector that relies primarily on high utilization of constructionequipment. This thesis presents the identification of problems of construction equipment planning and management for road projects. The past researchers focused on construction equipment selection, acquisition, operation, maintenanceand disposal or replacement. The data collection method is integrated questionnaire, interview and case studies; a descriptive and inferential statistical data analysis has also been used. Interpretations and discussions were made on the basis of the results from the analysis ofpastresearchworkand questionnaire survey. Most respondents believed that their companies have no documented construction equipment planning and management policy; also the result indicated that idle time, down time, poor equipment maintenance practices are some of major problems that affect construction equipment planning and management. Costoverrun isthefirst ranked among the negative effects of construction equipment planning and management problem. By enhancing the effectiveness of utilizing equipment; extensive volume of work can be completed within a shorter period of time and, more importantly, within the project schedule. Equipment is thus one of the key factors for improving contractor’s capabilities in performing their work more effectively and efficiently. Key Words: EquipmentPlanningand Management, Road Construction, Optimization 1. INTRODUCTION Construction is a business sector that relies primarily on high utilization of construction equipment. Equipment is thus one of the key factors for improving capabilities in performing work more effectively and efficiently. To function anyproject in smooth manner it is essential that an engineer should have a detailed knowledge about the equipment available and to direct it on a particular task. The overall progress of the project depends upon how fast the work is carried out. Hence it becomes a necessity to select the equipment by considering all aspects of working conditions of site. So it is necessary to make the proper planning & management ofequipment’s available to use it in an effective manner at minimum possible cost and with maximum output productivity. Currently in Nashik city the Road construction sector plays an important role in short term trends, with more frequent development, not only for the sector itself but also for other economic activities as well. As a result, it is firmly believed that the road construction industry needs an effective resource management practice to retain profitability and continue its dynamic contribution to the growth of the country. The cost of equipment in a project varies from 10% to 30% of the total cost of the project, depending upon the extent of mechanization. In modern fully mechanized projects the cost of equipment goes up to 30%. Proper planning, selection, procurement, installation, operation, maintenance and equipment replacement policy plays an important role in equipment management for the successful completion of the project. With the growinguse of machinery it has become necessary for construction engineers to be thoroughly familiar with the Construction application and upkeep of the wide range of the modern equipment. 1.1 Equipment’s management Equipment’s management is defined as a management system that is required in planning and controlling the quality and quantity of the equipment, punctual equipment placement, good price and the right quantity as required (Bailey and Cole, 1995). The management of equipment’s by construction firms is an enterprise that involves many people with diverse interest, talents and background. The building team indirectly constitutes the management team on building sites. This is due to the role played by each member of the team in relation to the successful erection of the building (Skyoles, 1974). 1.2 Key factors which governs construction equipment management Selection of equipment Acquisition of Equipment Operation Productivity Maintenance Disposal
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 05 | May 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 7562 2. LITERATURE REVIEW M. Manikandan, et al., (2018) analyzed and studied construction equipment management with respect to improve productivityHesuggestedimprovingproductivityit is essential to improve the performance of construction systems, productivity will be achieved through high equipment availability which is influenced by equipment reliability and maintainability[1].MekdimMathewos(2017) studied the construction equipment planning and management problems in road construction projects in Addis Ababa city roads in Ethiopia. He carried out survey where most of the respondents agreed that maintenance is very important part of equipment management which directly affects the cost of operation of any equipment.[2].IliasNaskoudakisandKleopatra Petroutsatou (2016) have done thematic review on construction equipment in which he covers operator’s competence as an important parameter for equipment management.[3]. Samson Mekbib Atnaw, et al., (2016) studieda casestudyon road construction equipment management in Malaysia in which they they concluded use of solutions methods based on minimization of cost and maximization of profit modules implementations will help in optimum decision making [4]. Kartik Shard Thete and Dhiraj Rajendra Baviskar (2016) studied the Construction Equipment management in which they gave more importance to selection of equipment and discussed selection of equipment depends upon site conditions, duration of work and its overall cost of operation.[5]. Prasannasangeetha andA,Alan.S(2015)from Coimbatore India gives great significance overacquisition of [6]. Mr. Nilesh D. Chinchore and Prof. Pranay R. khare (Dec.2014) from Pune University have given importance regarding selection of equipment for highway construction project in which experience in operation andmaintenanceis essential. [7].Tsado, Theophilus Yies and Theophilus Yisa Tsado (2014) from Nigeria studied Equipment maintenance as an aspect of construction project profitability.[8].Major Virender Singh Phogat and Ajit Pratap Singh (2013) from BITS Pillani-India studied the multi criteria approach for selection for equipment at hilly road region.[9]. Sri. Nuwan Randunupura and Chandanie Hadiwattege (2013) studied plant and equipment management to minimize delays in road construction in which they have reviewed plant and equipment selection practices [10].DavidJ.EdwardandGary D. Holt (2009) studied the construction plant and management in UK andgives special importancetowards the operator anditscompetence[11].Douglas D.Gransberg,Calin M. Popescu and Richard C. Ryan (2006) in their book construction equipment management for engineers estimators and owners gives verydetailedattentiontowards acquisition of heavy equipment listing financial methods of acquiring[12]. 3. PROBLEM STATEMENT Management of equipment’s have over the yearswasa great problem to most firms in the construction industry. In construction project operations, there is always a tendency of mismanagement of equipment’s by construction firms.As the size of the contract increases, however so do the scale of activities concerning equipment’s management. During the occurrence of high number of projects, most construction firms focus on getting work done whiles neglecting the management of equipment’s. The negligence of proper equipment’s management contributes to several negative consequences such as, breakages of equipment’s, dissatisfaction by client, and reduction in the productivity of workers, equipment’s wastage,highprojectcostanddelayin the progress of work at hand,whichaffectsthemaximization of limited resources. Most construction firms have given little priorities to the setting up of a department which oversees the management of their equipment’s resulting in improper equipment’s management if there is any at all. Mismanagement of equipment’s can be classified as loss since it has adverse effects on construction projects. On the small sites, equipment’s are managed by individuals with little or no knowledge about the management of equipment’s. It is therefore prudentforconstructionfirmsto have a critical look on equipment’s management,sinceit has a rippling effect on construction projects. 4. METHODOLOGY The focus of this research is identifying major problems in construction equipment planning and management, and there effect on construction equipment productivity on Nashik city road projects. Investigating causes and effects of construction equipment planning and management problems within domestic grade one contractors and equipment rental companies participating in Nashik city road projects. Therefore, the choice of the mixed research method is justified as an appropriate research strategy. The determination of the study sample and the techniques of data collection are also described. 4.1 Survey study the questionnaire survey was used to obtain information about the identification of major construction equipment planning and management problems, itscauses and effects among parties which were participating in Nashik CityRoad projects. This included domestic GradeOnecontractors. The questions had a number of choices of possible answers and the respondents selected whatever they feel was most appropriate. In this research, the response of the questionnaire data was prepared based on the scale of percentage rating scale measurement of the agreement towards each statement. The reason to adopting this simple scale is as to provide simplicity for the respondent to answer and to make evaluation of collected data easier to evaluate; and to rank major integration problems as the
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 05 | May 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 7563 objective of this research 4.2 Case study 1- Shevgedarna-donwade road asphalt road project This road section is about 5km long and it is at early construction stage. Only excavation work of side trench and supplying of excavated material to side shoulder work has been considered to examine OEE (overall equipment effectiveness) of Tata Hitachi 120x excavator. The project is in active stage and is handled by researcher itself. Data collection and record keeping of site is done by researcher personally. With respect to equipment utilization and its management OEE of excavator is carried out. All the records and data will be maintained in different registerformatfrom which comparative analysis will be done to conclude most effective and efficient equipment management policy to adopt with respect to equipment selection, its operation 4.3 Case study 2- Sarul stone quarry This stone quarry is located near Nashik-Mumbai highway near sarul village. 50m x 40x hill section is used for blasting purpose to obtain stone metal from it. Operation of loading of blasted dubber (large size blasted stone) is analyzed to obtain OEE of Tata Hitachi 200x excavator. 4.4 Case study 3- Suprabha stonecrusherandplant Suprabha stone crusher and plant is a well-known stone crusher in Nashik city situated at villolhi village. The company owns stone crusherplant,readymixconcreteplant and bitumen plants where large quantity of loading and dumping operation is carried out with the help of CAT Hindustan loader. OEE of Loader is carried out from the day to day registered data keeping of the company 4.5 OEE (Overall equipment effectiveness) By definition, OEE is a measure of value added to the production by a certain machine in a production time. The demand for increasing productivity in the current competitive construction industry led to a need for performance measurement system for the production process. One of such a performance measurement tool which measures different production losses and which indicate area of process improvement is an Overall Equipment Effectiveness (OEE) index. It is a tool designedto distinguish factors contributing for productivity losses. Knowing the three fundamental performance rate Availability Rate (AR), the Performance Rate (PR) and the Quality Rate (QR) will help to compute overall equipment effectiveness index. These rates indicate the degree to which the required output those equipment production losses stated Where; AR – Availability Rate PR – Performance rate and QR – Quality Rate 5. OBSERVATIONS AND CALCULATIONS 5.1 Case study 1: Shevgedarna-donwade road asphalt road project Table no 1: collected data for Tata Hitachi EX 120 model. 5.2 Case study 2: - Sarul stone quarry Table no 2: Data for Tata Hitachi EX 200 model excavator Type of equipment Excavator Model Tata Hitachi Model EX 120 heaped bucket capacity 0.8 cum material type medium hard murrum Ideal excavation from manufacturer 11.6 cum/hr. Work done (day 1) excavation of side trench 37.5 cum Hour reading start time: 4262.9 hrs. Hour reading end:4270.6( 320minuits) work done (day 2) formation of side shoulder 875 meters Hour reading start time: 4252 hrs. Hour reading end:4258.6 ( 400minuits ) Work done (day 3) excavation of side trench 32.5cum Hour reading start time: 4258.6 hrs. Hour reading end:4263 ( 260minuits) Type of equipment Excavator Model Tata Hitachi Model EX 200 heaped bucket capacity 1.2 cum material type Blasted stone ( Dubber) Ideal excavation from manufacturer 20 cum/hr. Work done (day 1) Loading operation 132m3 work done ( day 2) Loading operation 77.53 m3 work done ( day 2) Loading operation 122.38 m3
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 05 | May 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 7564 5.3 Case study 3: Suprabha stone crusher and plant Table no 3: collected data for Hindustan wheel loader2021 6. RESULT AND DISCUSION 6.1 Questionnaire survey: Questionnaire survey carried out shows current status of road construction companies of Nashik city. There are variation in responses of contractors and different psychology seen behind the answers of contractors. From the result it is clearly seen that there is lack of construction management in most of the firms in Nashik city. Most of the construction firms do not have separate equipment of maintenance manager which result into poor equipment practices and faces breakdown of equipmenttwicea month. The analysis shows most of the firms are not getting expected output from their equipment which result them into less productivity. Most of the contractors prefer local garages and fitters to minimize the maintenance cost. Contractors mostly select equipment according to the spare part availability and general experience to minimize production and maintenance cost. From the result of questionnaire it seems that equipment management is very important and necessary to increase the productivity. Most of the construction companies inNashik own the equipment instead of going for rental option, Tata products shows more reliability and favorite choice of contractors as the cost of maintenance is low and suitability to Nashik region. From the survey it has seem that most of the construction firms in Nashik city do not have specific equipment management policy. Overall result of questionnaire survey shows lack of equipment management results into low productivity and loss of time and money. 6.2 Case study 1 Shevgedarna- Donwade road project: Table 4 shows the result for three days analysis of Overall equipment effectiveness of excavator TATA EX 120 which was performing side trench excavation and shoulder laying work. Table 4 OEE for excavator EX 120 The result analysis shows Availability rate 86.64%, performance rate is 53.88% Quality rate is 83.9% and OEE is 39%. 0.00% 20.00% 40.00% 60.00% 80.00% 100.00% Day 1 Day 2 Day 3 Chart 2 OEE analyses for excavator Tata EX 120 6.3 Case study 2: - Sarul stone quarry Table 5 how’s the result for three days analysis of overall equipment effectiveness of excavator TATA EX 200 which was performing loading of blasted stone work. Table no 5: OEE for excavator EX 200 The result shows Availability rate 90.47, performance rate 70.47%, quality rate 100% and OEE is 62.66% Type of equipment Wheel loader Model Caterpillar-Hindustan 2021D heaped bucket capacity 2.5 cum material type Crushed metal Ideal loading by manufacturer 20 cum/hr. Work done (day 1) Loading operation 350m3 work done ( day 2) Loading operation 290 m3 work done ( day 2) Loading operation 410 m3 Index Day 1 Day 2 Day 3 Availability rate 88.23% 95.23% 76.47% Performance rate 49.87% 54.25% 57.54% Quality rate 77.33% 85.14% 89.23% OEE 33% 45% 39% Index Day 1 Day 2 Day 3 Availability rate 90.47% 90.47% 90.47% Performance rate 84.19% 49.34% 77.88% Quality rate 100.00% 100.00% 100.00% OEE 75% 44% 69%
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 05 | May 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 7565 0.00% 20.00% 40.00% 60.00% 80.00% 100.00% 120.00% Day 1 Day 2 Day 3 Chart 3 OEE analyses for excavator Tata EX 200 6.4 Case study 3: Suprabha stone crusher and plant Table 6.3 shows the result for three days analysis of overall equipment effectiveness of CAT-Hindustan wheel loader 2021D which was performing loading of Crushed metal work. Table no 6: OEE for Hindustan wheel loader 2021D The result shows Availabilityrate83.33%, performance rate 50.43%, Quality rate 100% and OEE is 49.33% 0.00% 20.00% 40.00% 60.00% 80.00% 100.00% 120.00% Day 1 Day 2 Day 3 Chart 3 OEE analyses for Hindustan loader 2021D 7. CONCLUSIONS The result indicated that insufficient knowledge of selection of equipment, equipment down time, poor equipment maintenance practices, improper determination of timing of replacement, poor training of equipment operators, equipment breakdown, ignorance towards maintenance of equipment, huge capital investment during acquisition, misunderstanding the scope of work carried out, unit cost of production and equipment suitability for job condition were found to be the major problems that affect construction equipment planning and management on Nashik city projectsduringtheplanningand construction process. At Nashik city knowledge about construction equipment planning and management policy is very little. Insufficient training of professional workforces on construction equipment planning and management is the major problem at Nashik city road construction projects. So, this study proved that most of sampled respondents majorly use only one or two types of equipment planning and management policy. Proper maintenance of construction equipment is vital to keep construction equipment in good and serviceable condition. As the study revealed, 40% of the respondents use planned preventive maintenance method while only 33% performs periodic maintenance, 27% contractor’s still go for maintenance after breakdown of equipment shows negligence towards maintenance activity. All types of maintenances are critically needed to keep equipment in good and serviceable condition. By periodically maintaining equipment using planned preventive maintenance method, different major failures of equipment can be prevented because “prevention is better than cure”.Also it is better to do corrective maintenance when necessary to increase the efficiency of equipment. In addition, unplanned or unscheduled maintenance is necessarily needed because, equipment can break down suddenly. Therefore, it is better to use allmaintenance methods to make equipment more productive. 70% of the construction companiesdo not keep maintenance record of the equipment’s by which it is difficult to keep an eye on maintenance cost expenditure result of this company’s faces loss in profitability. Study concluded only 20% of the respondent have separate maintenance staff at company office, which is necessary to minimize maintenance cost. Most of the firms appoint technical expert on site when needed which adds visiting charges resulting into extra maintenance cost. Survey concluded management, Technical staff and operator of the equipment are equally responsible for management problems in road construction sector. It shows equipment planning and management problems can be solved if these factors are organized. The performance of equipment effectiveness is evaluated based on actual on site measurement. This actual onsite construction equipment effectiveness is evaluated by overall equipment effectiveness (OEE) indexes. OEEanalysis concluded there is major flaw in performance factor of the equipment. All three equipment’s donotdeliveringexpected output. OEE for Excavator EX 120 is only 39% which shows lack of productivity and performance rate. OEE for EX 200 Excavator is 62.34% which is quite acceptable but it can be improved as machine shows rate drop in performance rate factor. OEE for loader is 49% which is very low as machine fails in giving expected performance. Overall conclusion of OEE Analysis shows all machines were available for more time but because of lack in performance factor machine showed low productivity. While quality factors depends Index Day 1 Day 2 Day 3 Availability rate 73.91% 91.30% 84.78% Performance rate 42.27% 68.16% 40.87% Quality rate 100.00% 100.00% 100.00% OEE 30% 61% 57%
  • 6. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 05 | May 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 7566 upon the operator of the equipment and management of the activity. As proved by the case study, actual on site performance of equipment is very poor due to different management problems. All the analyses show that, OEE of construction equipment is 50% and below 50%. This shows that, the equipment productivityrate is below half of its capacity. To avoid or reduce construction equipment planning and management problems it is necessary to identify the major causes of the problem. The results of analysis indicated that, huge capital investment at acquisition phase and poor maintenance practice with improper determination of economic life and timing for replacement are the major causes of construction equipment planning and management problems. This causes of construction equipment planning and management problems reflected negative effects on project performance. loss in productivity of equipment, time overrun, cost overrun and equipment related accidents are some of the major effects of construction equipment planning and management problems. Most effects, like loss in productivity of equipment, time overrun, equipment related accidents are reflected on cost overrun. This is why cost overrun was ranked first with the highest negative effect on performance of road projects. 8. RECOMMENDATIONS: After detail investigation on construction equipment planning and management problems its causes and effects, recommendations can be forwarded to contractors. The recommendation meantto diminishconstructionequipment planning and management problems on Nashik city road construction projects. The following recommendations are forwarded offices: 8.1 Recommendations at management level: [1] Develop construction equipment planning and management policy to be used as a guideLine to use equipment efficiently. [2] Should give awareness training for site engineers about equipment planning andmanagementpolicyand how to manage equipment at project level. [3] Collect data about the current status of construction equipment and efficiency of equipmentatprojectlevel. [4] Develop planned preventive maintenance method to eliminate long down time of equipment. [5] Develop optimization methods to use available equipment resource effectively and efficiently; and Management has to establish a training center, to train unskilled and semi-skilled operators. [6] Management has to update the equipment management guideline to reconcile with the current working condition and work load. [7] Management has to implement the currently available technologies regarding equipment. Recommendations for maintenance of equipment: [1] Implement preventive maintenance, corrective maintenance and unscheduled maintenance program to leading construction equipment. [2] Provide maintenance by equipment operators, through in-house equipment department, equipment dealers and external dealers. [3] Consider poor maintenance and use of non-original parts as the main cause of machine failure during use. [4] Wait until the failed machine is completely repairedand ready for use. Recommendation’s for operator’s level: [1] Provide training for equipment operators through in- house equipment department, equipment dealer or external agencies. [2] Consider poor operating procedure as a main cause of equipment accidents. [3] Allow an equipment operator to work with more than one machine. [4] Collect daily based data to measure the overall equipment effectiveness. [5] Identify major factors that cause idle timeof equipment. REFERENCES [1] M. Manikandan, Prof. M. Adhiyaman, Dr. K.C.PazhaniA ,”study and analysis of construction equipment management used in construction projects for improving productivity”, Department of Civil Engineering, Sona college of technology, Salem, India, Anna university Chennai-600032,2018. [2] Mekdim Mathewos,”AStudy onConstructionEquipment Planning and management problems in Road Construction Project (A case study: The Addis Ababa City Roads Authority)”, The School of Civil and Environmental Engineering, Addis Ababa University, Ethiopia, 2017. [3] Ilias Naskoudakis, Kleopatra Petroutsatou “a thematic review of the main research on construction equipment over recent year”, Laboratory of construction equipment and management, department of civil engineering ,School of engineering, AristotleUniversity, Thessaloniki, University campus,54124, Thessaloniki, Greece, 2016. [4] Samson Mekbib Atnaw, Lakhveer Singh, Fatwi Yohaness Hagos, Abu Yousuf “road construction equipment management: a case study on selected industry”, IJETS, Malaysia, 2016. [5] Kartik Shard Thete, Dhiraj Rajendra Baviskar “Construction Equipment management,” IJSETR. 2016. [6] Prasannasangeetha. A,Alan. S,“Equipmentmanagement in construction sector”, RVS Technical Campus, Coimbatore, India, 2015.
  • 7. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 05 | May 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 7567 [7] Mr. Nilesh D.Chinchore, Prof. PranayR.khare,“Planning and Selection of Heavy Equipment in Civil Engineering, Department of Civil Engineering”, SavitribaiPhulePune University, pune, Maharashtra, India. Dec.2014. [8] Tsado, Theophilus Yies, Theophilus Yisa Tsado “Equipment maintenance: an effective aspect of enhancing construction project profitability”, civil engineering department, school of engineering and engineering technology, Federal University of Technology, P.M.B. 55, Minna, Niger State, Nigeria,2014 [9] Major Virender Singh Phogat, Ajit Pratap Singh, “Selection of Equipment for construction of a Hilly Road using Multi Criteria Approch”,BITSPilani-333031-India, 2013. [10] Sri.NuwanRandunupura,ChandanieHadiwattege“Plant and EquipmentManagement toMinimizeDelaysinRoad Construction Projections”, Department of Building Economics, University of Moratuwa, Sri Lanka., 2013. [11] David J. Edward and Gary D. Holt, “construction plant and management research: Thematic review, Journal of Engineering Design and technology” , Department of civil engineering, July 2009. [12] Douglas D. Gransberg, Calin M. Popescu,RichardC.Ryan “construction equipment management for engineer’s estimators and owners”, civil and building Engineering, Loughborough University, Loughborough, UK, 2006.