International Journal of Research in Advent Technology, Vol.7, No.6S, June 2019
E-ISSN: 2321-9637
Available online at www.ijrat.org
16
doi: 10.32622/ijrat.76S201903
๏€ 
Abstractโ€”Most of the construction projects suffer from
cost and time overruns due to amultiplicity of factors. Earned
value management (EVM) is a project
performanceevaluation technique that has origins in
industrial engineering, but which has beenadapted for
application in project management. Earned Value Analysis
software isdeveloped in Visual studio 2008, Next
Comparison of selected parameters between M.SProject
2007, Primavera P6 and developed software is done.
Therefore, it can beconcluded that the software could be used
in a wide range of projects for Earned ValueAnalysis
calculation.During the construction project it has been
observed that certain causes may leadto delay in construction
activities. This will result in time and cost overrun in the
project.So it has become a major problem to complete the
project on schedule and within theestimated cost. As a
solution to this, the concept of construction project
management byEarned Value Management System (EVMS)
is evaluated.Earned Value Management is a powerful
methodology used in monitoring andcontrolling of the
project. EVMS is the project management technique
developed tomeasure the performance and progress of the
project based on the combination ofschedule, cost and work
performed. By using this technique, the project status can
beinvestigated in ongoing project at any stage which detects
whether the project is under orover budget and behind or
ahead of the planned schedule. Also the estimate cost
andtime required to complete the project from current
situation can be investigate.
I. INTRODUCTION
Constructions activity is one of the major scaling-down
sectors in India. Several construction companies possess to
stand facing heaps of harms directly to over budgets cost,
overtime and inopportune planning, delays in construction be
short of manpower, machinery and loads of other usual
tribulations during task execution. One of the major problems
are overflow of cost and over budgeted expenditure of
project. To over fall these problems, earned value analysis is
the procedure that fills up completely the above loopholes.
Manuscript revised May 13, 2019 and published on June 5, 2019
Chandrakala S ,Assistant Professor, Department of Civil Engineering,
SJCIT- Chickballapur- chanducharyas@gmail.com
Bhavya S ,Assistant Professor, Department of Civil Engineering, SJCIT-
Chickballapur- bhavya.s11689@gmail.com
Shashi Kumar N V ,Assistant Professor, Department of Civil Engineering,
SJCIT- Chickballapur- shashi02456@gmail.com
Kiran K M ,Assistant Professor, Department of Civil Engineering, SJCIT-
Chickballapur- kiranthribu@gmail.com
Expected to implementation of EVA plan ahead
administrator at their moment take part in the capability to
express, and cost, schedule and mission implementation of
their creation in a systematic, well-defined and
understandable method to fit necessities of employees,
director and customers.
Earn value management is a systematic method to be the
integration and measurement of schedule, cost and technical
progress of a task or project. EVM provides project managers
capability to examine detailed critical program, schedule
information, technical achievement and cost records. It
resembles a caution for the managers to be grateful for and
thorough knowledge issues by attractive opportune
counteractive course of action before they ride out of the
question to conquer. It operation helps in generous
achievement customary to the assessment of evolution report
of project and it the same operate about as a mandate device
to exchange with financial statement and time.
It deals with measuring implementation of task at evident
time intervals and reports that implementation to
organization for method control. After being paid such
monitored information, the concerned agency decides to
understand more action to control the project before it grows
to be insurmountable. Thus, monitoring and controlling is
generally critical part procedure throughout complete life of
the project. Earn value is a progress up conventional method
of cost bookkeeping. It has been seen that to be responsible
for protection of cost overwhelm, plan ahead organization
undergoes cost attenuation each by diminishing the plan
scope and quality or by giving extra. In this route with the
management of earn value analysis framework, plan goals are
accomplished in correct way.
II. LITERATURE REVIEW
B V. Birajdar, Amruta B. Vyas โ€œTracking of
Construction Projects by Earned Value Managementโ€
[1].
Proficient Management of undertakings in development
businesses are turning into a test with the progressing time. It
has turned into a worry for the venture directors to ensure that
the task is on plan and inside spending plan. EVA assesses
the task execution by incorporating both cost and time
perspectives consequently estimating the general advance.
This paper talks about how EVA is acquainted with a
continuous task on street works. It distinguishes the calendar
as well as cost overwhelms already and in this manner giving
a chance to directors in recognizing and controlling issues.
This examination addresses in recognizing and controlling
issues. This examination tends to both the expenses and the
advantages of earned esteem. The earned esteem ideas and
the related criteria are considered.
Analysis on Cost Controlling and Tracking of Residential
Building by EVM method using MS Project Software
Chandrakala S, Bhavya S, Shashi Kumar N V, Kiran K M
International Journal of Research in Advent Technology, Vol.7, No.6S, June 2019
E-ISSN: 2321-9637
Available online at www.ijrat.org
17
doi: 10.32622/ijrat.76S201903
GayatriVyas โ€œAnalysis of Cost Controlling Using Earned
Value Management in Construction Industriesโ€ [2].
How development tasks can be finished convenient and cost
viably is the consuming issue in the development business.
There have been a few examinations that are centered on this,
it has been seen that the following with shut observing of the
genuine advance of assignments from the earliest starting
point of the task and overseeing them utilizing earned esteem
idea will brings about impressive cost sparing and auspicious
fruition. This paper is cantered on idea and significance of
earned esteem administration (EVM). Additionally, it
incorporates components and execution pointers utilized for
following and anticipating the task that advantages venture
and eventually brings about undertaking achievement.
Current paper utilizes a contextual investigation, a case use of
EVA as a cost checking instrument. This contextual
investigation reaffirms the Advantages of utilizing EVA for
venture income examination and anticipating.
GanapathyRamasamy N, Sandhya Suresh โ€œAnalysis of
Performance Using Earned Value Analysisโ€ [3].
Development enterprises are confronting challenges step by
step. In the midst of every one of these difficulties it is
exceptionally urgent to enhance the execution of an
undertaking regarding Schedule and Cost. Earned Value
Analysis is an essential device in investigating the execution
of any development venture. It gauges the venture advance
and aides in recognizing the basic exercises consequently
expediting the undertaking plan. This paper demonstrates the
Earned Value Analysis done on a constant task in Kerala,
utilizing Microsoft Office Project. The investigation helped
in distinguishing the basic regions. It guaranteed that the
venture is on time and inside the financial plan.
J. Jayalakshmi, T. Subramani โ€œAnalysis of Cost
Controlling In Costruction Building by Earned Value
Method Using Primaveraโ€ [4].
The vast majority of the development ventures experience the
ill effects of cost and time invades because of an assortment
of elements. Earned esteem administration (EVM) is a
venture execution assessment strategy that has starting points
in mechanical designing, yet which has been adjusted for
application in venture administration. The earned esteem
investigation gives early signs of undertaking execution to
feature the requirement for inevitable remedial activity. This
investigation is to display and examine the primary
parameters associated with the count of Earned Value
Analysis (EVA) in the cost administration of common
development ventures. The motivation behind this paper is in
3-crease. Right off the bat, Earned value analysis
programming is created in MS Project 2007, server 2005,
primavera P6 of a parameters, it can be inferred that the
product could be utilized as a part of an extensive variety of
activities for Earned Value Analysis figuring.
VaishnaviTuljapurkar โ€œCost Controlling and Tracking
of a Construction project by Earned Value Mathodโ€ [5].
Earned Value Management (EVM) is a method that
conjectures the venture giving an early cautioning of cost and
calendar. It not only measures the undertaking execution but
rather likewise measure the advance of the timetable. It is a
viable apparatus to gauge cost, plan and execution of the
venture. The EVA is valuable in different fields, for example,
IT, Industries and Construction organizations and so on. The
estimation of Earned Value Analysis (EVA) is reliant on two
key zones i.e. Exact Cost data and even minded advance of
undertaking. In the event that these two key territories are
effective at that point advantage of the undertaking will get
esteemed. This paper compresses the development; essential
wordings of Earned esteem Analysis and viable utilization of
it in the development ventures by MS Project. There are
numerous approaches to actualize EVA in the development
venture. MS Project is a device to decide the EV and its
parameters in an effective route with precision and inside
time imperatives.
III. OBJECTIVES OF STUDY
The considerable objective of construction group is to
conclude the task or project as determined on record details
furthermore, inside the estimated with right manipulate of the
large amount of assets like money, materials, labour and
equipment and furthermore to complete the project with
quality.
1. Project planning is done to complete the task on time
and within budgeted cost.
2. To study Microsoft Project (MSP) software and to use
the same software for the execution of the on-going
project.
3. Analysis on schedule, cost, monitor and tracking of a
project by using Microsoft project.
4. Work development will be estimated based on the
project baseline created.
5. To recognize causes of potential schedule and cost
overruns slackness.
6. Costs management is be to used EVM to give up the
project activity in the estimated cost to attain elevated
profits.
7. Creating a WBS and project schedule in the MS
Project software.
8. Planned duration and actual duration was compared.
9. Co-relating the data after the WBS is prepared, with
the pattern plan and finding the motive for the delay
in time and rise in cost.
3.1 SCOPE OF THE STUDY
Earned value management (EVM) is a strategy that
impartially impresses objective achievement of work:
1. The task or project will always have fixed cost and
time, if the task is not completed on time which will
increases the total cost of project, to over slip delay
and to overthrow delay without influencing budget
and cost can be utilized and project management
preserve be made.
2. EVM is used to deduce the upcoming of the project
by doing the cost analysis and tracking of the project.
3. EVM observe the project by using old and present
progress of project by statistical methods.
4. By using EVM methods stakeholders will be
benefited.
5. At different stage of project we can get earned value
management calculations, actual cost and remaining
cost.
6. Cost unfathomable can be deducted by using EVM
and proper planning together smartly.
International Journal of Research in Advent Technology, Vol.7, No.6S, June 2019
E-ISSN: 2321-9637
Available online at www.ijrat.org
18
doi: 10.32622/ijrat.76S201903
Outline of scope of study is to do proper planning,
scheduling and updating of different activities, which is done
by using Microsoft Project software. After scheduling is done
resource will be allocated and a baseline is set and project is
updated, without affecting the complete project duration. At
last the tracking is done by actual start and finish.
.
IV. ABOUT THE CONSTRUCTION PROJECT
4.1 CONSTRUCTION SITE DETAILS
The Navanaamiplatina is located at
chokkanahallithanisandra main road, YelahankaHobli,
Bengaluru. It is a G+5 apartment with block named as C. it
has a total of 40 flats. The apartment is comprised of
premium 2.5 & 3 BHK flats. Project amenities, Swimming
pool, squash court, office space Multipurpose hall, guest
suite, gym and billiardsLift facilities are providedand Solar
facilities are provided.
4.1.1 Project Site Detailss
Land area = 29712sft , Total build up area
=60263sft, G+5 Floors , 40 exclusive units, Infinity pool with
deck65% of open space
4.1.2 Structural Details
Table 4.1 Structural Details of Project
Description Details
Total number of footings 128 no.
Total number of columns 145 no.
Total floor height 18.15m
Basement โ€“ 1st
floor 3.15m
1st
fllor to terrace 3.0/floor
4.1.3 Area Statements
Table 4.2 Details of Build-up Area
Sl.No Description No of
floors
Area
in Sft
Total
area in
Sft
1 Ground
floor
1 11155 11155.00
2 First floor โ€“
second
floor
2 9824 19648.00
3 Third floor
โ€“ fourth
floor
2 9894 19788.00
4 Fifth floor 1 9672 9672.00
TOTAL BUILD-UP AREA 60263.00
4.1.4 Flat Area Statement
Table 4.3 Details of Flat Area
Configuration Type Saleable Area (Sft)
2.5 BHK : 12 1129 โ€“ 1209 Sft
3 BHK : 28 โ€“ 1554 Sft
4.1.5 Project Construction Status in Percentage of
completion
Table 4.4 Status in Percentage of Completion
Sl
no
Description Start
date
Finish
date
% of
Completi
on
1 Sub structure 07.06.1
7
06.10.17 100%
2 Super
structure
07.10.1
7
20.05.18 90%
3 Block work 10.12.1
7
13.07.18 60%
4 Plastering 06.02.1
8
08.09.18 38%
5 Handover
building
25.12.18
4.1.6 Quantity of Material
Table 4.5 Quantity of materials
NavanaamiPlatina
Sl.No Descriptions Unit Noโ€™s Quantit
y
1 Concretee
PCC Concretee M3
1 620.00
M20 Concrete M3
1 1100.00
M25 Concrete M3
1 5850.00
M30 Concrete M3
1 612.00
2 Block Workss
100mm M2
1 2900.00
150mm M2
1 8350.00
200mm M2
1 1735.00
3 Plasterings
Ceiling M2
1 8500.00
Internal Walls M2
1 26000.0
0
Externall Walls M2
1 9800.00
9
4 Waterproofings
Water proofing
for terrace floors
Smt 950.00
Water proofing
workss
Toilet, Balcony
and Utility
flooring
Smt 2350.00
Retaining walls Smt 1000.00
Podiums Smt 1550.00
STP, UG Tank,
Pool and OHT
Smt 6580.00
5 Painting
For celling
surface
M2
1 7550.00
Emulsion paint
for external
surface
M2
1 9230.00
Emulsion paint
for internal wall
surface
M2
1 21400.0
0
Retaining wall
finish and
M2
1 7060.00
International Journal of Research in Advent Technology, Vol.7, No.6S, June 2019
E-ISSN: 2321-9637
Available online at www.ijrat.org
19
doi: 10.32622/ijrat.76S201903
basement celling
6 Tilling
Vitrifieds(605*6
05) mm
M2
1 7435.00
Anti-skids
(300*300) mms
M2
1 870.00
Ceramics
(450*300) mm
M2
1 3240.00
Kitchen
dadoes(350*250
) mm
M2
1 330.00
C block common
areas and
clubhouse
M2
1 1135.00
Lift M2
1 160.00
Staircase area
granite
M2
1 455.00
Top kitchen
counter
M2
1 415.00
7 Windowss
Utility door and
UPVC windows
M2
1 1085.00
UPVC
ventilatorss
M2
1 195.00
8 Doors
Main doors M2
1 198.57
Bed room doors M2
1 373.63
Toilet doors M2
1 325.35
Balcony doors M2
29.00
V. FINDINGS AND OBSERVATIONS
The navanaamiplatina construction project is 517 days and 7,
14, 25,578 rupees budgeted project and estimated to
complete on December 2018. This project is tracked three
duration to know about project performance picture, the
founded or obtained results are listed in below tables and in
below figure.
Table 5.1 Shows the Parameters Values after Tracking of
Project
EVM
Parameter
1st
tracking 2nd
tracking 3rd
tracking
Tracking
dates
26-Aug-201
7
26-Dec-201
7
16-April
-2018
Original
duration of
project
517 517 517
Remaining
durations
410 302 196
Budgeted
total cost of
project
7,14,25,578 7,14,25,578 7,14,25,
578
Planned
value
4182605 25080232 4434770
3
Earned
value
4125645 24858080 4331360
6
Actual cost 4230370 25104817 4816148
6
Schedule
performanc
e index
0.98 0.98 0.97
Schedule
variance
-56960 -222152 -103409
7
Cost
variance
-104725 -246737 -484788
0
Cost
performanc
e index
0.97 0.98 0.89
The various project elements or indicators were calculated.
The values were calculated by using following formulae.
SV = EV-PV
= 4125645-4182605
= -56960 rupees
CV = EV-AC
= 4125645-4230370
= -104725 rupees
SPI = EV/PV
= 0.98
CPI = EV/AC
= 0.97
Table 5.2 Cumulative Cost after Tracking from MS Project
EVM
Parameter
1st
tracking 2nd
tracking 3rd
tracking
Tracking
Date
26-Aug-2017 26-Dec-2017 16-Apr-2018
Planned
value cost
4182605 25080232 44347703
Cumulative
Planned
value cost
4182605 20897627 23450076
Earned
value cost
4125645 24858080 43313606
Cumulative
Earned
value cost
4125645 20732435 22581171
Actual cost 4230370 25104817 48161486
Cumulative
Actual cost
4230370 20874447 27287039
The CV and CPI represent the cost performance of a project.
The both vales are less than 1 means cost is overrun of project
(project is uneconomical in terms of cost).
The SV and SPI represent the time performance of a
project and the both values are less than 1 means project is
behind schedule
VI. CONCLUSION
Earned value provides a quick fore warning suggest to
managers to undertake the counteractive action. EVM allows
both cost and schedule analysis against objective work
performed. The client and customer are satisfied then the
project is successful and itโ€™s finished within planned and
planned budget. The project schedule and cost is interlinked
between each other. If we expenditure more property for
individual task, the task will complete within the duration. If
International Journal of Research in Advent Technology, Vol.7, No.6S, June 2019
E-ISSN: 2321-9637
Available online at www.ijrat.org
20
doi: 10.32622/ijrat.76S201903
we expenditure less property for the task it will take more
duration to complete the activity. So, properly allocate an
optimum resources and duration of a construction building
project to make it successful completion.
Construction management is necessity to operate the project
well manageable, controllable and vision able. The different
software tools are come into occupancy in that MS Project is
also one of programming software package. The project can
be monitored by a better way by using MS Project software.
The project is tracked on 3 times from 26-April-2017 to
26-Aug-2017, 26-Aug-2017 to 26-Dec-2017, 26-Dec-2017
to 16-April-2018, by tracking we obtained earned value
(EV), planned value (PV) and actual cost (AC), these 3 basic
shows the performance of a project by earned value
performance index.
๏‚ท While on 3rd tracking 196 days are remaining to
finish the task or activities, the cost performing 89%
(CPI 0.89) as budgeted cost it shows the project
budgeted cost is overrunning. And schedule
performing 98% (SPI .98) as planned value; it
shows the project is under running.
๏‚ท Cost variance of construction project is -4847880
rupees the negative sign shows cost of project is
overrun. If the cost variance is negative the project
is overrun or behind from planned value and cost
variance is positive project is underrun or ahead
from planned value and some troubles will creates in
the project.
๏‚ท 60% of planned schedule is finished.
๏‚ท Cost requires to finish remaining task is 3813783.
๏‚ท To finish project on schedule time duration the
project has to perform in 1.09% speed of planned
value of the project.
The resource sheet will provides better information of
resource estimates.
REFERENCES
[1] B.V Birajdar, Amrutha .B Vyas , "Tracking of Construction
Projects by Earned Value Manaement," IJERT, International
Journal of Engineering research and Technology, Vol. 05, pp.
162-169, March 2016.
[2] Gayatri Vyas, Sagar K. Bhosekar, "Cost Controlling Using Earned
Value Analysis in Construction Industries," IJET, International
Journal of Engineering and Technology, Vol. 01, pp. 164-171,
April 2012.
[3] Ganapathy Ramaswamy N, Sandhya Suresh, "Analysis of
Performance using Earned Value Analysis," IJSETR,
International Journal of Science Engineering and Technology
Research, Vol. 04, pp. 73-82, April 2015.
[4] Jayalakshmi, T. Subramani, "Analysis of Cost Controlling in
Construction Buikding by Earned Value Method using
Primavera," IJTRA, International Journal of Technology
Research and Applications,Vol. 04, pp. 145-153, June 2014.
[5] Vaishnavi Tuljapurkar, "Cost Control and Tracking of a
Construction Building by Earned Value Method," IJTRA,
Internal Journal of technology Research and Applications, Vol.
03, pp. 15-22, April 2015.
[6] Taran C. Bhagat, Parag S. Mhatme, "Cost Controlling and
Monitoring of Construction Project Through Earned Value
Management System," IJATES, International Journal of
Advanced technology in Engineering and Science,vol. 03, pp.
45-51, March 2015.
[7] Waris Ali khan, Arazi Idrus, "The Cost Monitoring of Construction
Projects Through Earned value Analysis," ICEFR, International
Conference on Economics and finance research,Vol. 04, pp.
251-259, 2011.
.

More Related Content

What's hot

Ijciet 10 01_075
Ijciet 10 01_075Ijciet 10 01_075
Ijciet 10 01_075
IAEME Publication
ย 
Efficient Planning Scheduling and Delay Analysis of Residential Project
Efficient Planning Scheduling and Delay Analysis of Residential ProjectEfficient Planning Scheduling and Delay Analysis of Residential Project
Efficient Planning Scheduling and Delay Analysis of Residential Project
IJERA Editor
ย 

What's hot (19)

Ijciet 10 01_075
Ijciet 10 01_075Ijciet 10 01_075
Ijciet 10 01_075
ย 
Efficient Planning Scheduling and Delay Analysis of Residential Project
Efficient Planning Scheduling and Delay Analysis of Residential ProjectEfficient Planning Scheduling and Delay Analysis of Residential Project
Efficient Planning Scheduling and Delay Analysis of Residential Project
ย 
Project Management overview talk 2021
Project Management overview talk  2021Project Management overview talk  2021
Project Management overview talk 2021
ย 
IRJET- Prediction Model of Factors Causing Increase in Overhead Cost in C...
IRJET-  	  Prediction Model of Factors Causing Increase in Overhead Cost in C...IRJET-  	  Prediction Model of Factors Causing Increase in Overhead Cost in C...
IRJET- Prediction Model of Factors Causing Increase in Overhead Cost in C...
ย 
Effective techniques in cost optimization of construction project an review
Effective techniques in cost optimization of construction project   an reviewEffective techniques in cost optimization of construction project   an review
Effective techniques in cost optimization of construction project an review
ย 
IRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET- A Study on Project Management Techniques to Avoid Project Failure
IRJET- A Study on Project Management Techniques to Avoid Project Failure
ย 
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERP
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERPSOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERP
SOLVING PROJECT ALLOCATION RESOURCE PROBLEMS WITH AEROSPACE ERP
ย 
Planning and Optimization of Resource Constrained Project Scheduling by using...
Planning and Optimization of Resource Constrained Project Scheduling by using...Planning and Optimization of Resource Constrained Project Scheduling by using...
Planning and Optimization of Resource Constrained Project Scheduling by using...
ย 
IRJET- Portfolio Management of Multiple Building Projects using EPPM
IRJET- 	  Portfolio Management of Multiple Building Projects using EPPMIRJET- 	  Portfolio Management of Multiple Building Projects using EPPM
IRJET- Portfolio Management of Multiple Building Projects using EPPM
ย 
iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...
ย 
Getting To Done - A Master Class Workshop
Getting To Done - A Master Class WorkshopGetting To Done - A Master Class Workshop
Getting To Done - A Master Class Workshop
ย 
Material Management Practices of โ€œFoundation Silver Springโ€ Residential Build...
Material Management Practices of โ€œFoundation Silver Springโ€ Residential Build...Material Management Practices of โ€œFoundation Silver Springโ€ Residential Build...
Material Management Practices of โ€œFoundation Silver Springโ€ Residential Build...
ย 
5 immutable principles and 5 processes in 60 seconds
5 immutable principles and 5 processes in 60 seconds5 immutable principles and 5 processes in 60 seconds
5 immutable principles and 5 processes in 60 seconds
ย 
Balanced Scorecard IT Strategy and Project Management
Balanced Scorecard IT Strategy and Project ManagementBalanced Scorecard IT Strategy and Project Management
Balanced Scorecard IT Strategy and Project Management
ย 
IRJET- Review Paper on โ€œBudget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on โ€œBudget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on โ€œBudget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on โ€œBudget and Schedule Overrun in the Construction Phase...
ย 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
ย 
Basis of Estimate Processes
Basis of Estimate ProcessesBasis of Estimate Processes
Basis of Estimate Processes
ย 
Ijciet 08 04_218
Ijciet 08 04_218Ijciet 08 04_218
Ijciet 08 04_218
ย 
Cost Effective Construction Techniques By Stephen Rayment
Cost Effective Construction Techniques By Stephen RaymentCost Effective Construction Techniques By Stephen Rayment
Cost Effective Construction Techniques By Stephen Rayment
ย 

Similar to 76 s201903

Efficient Indicators to Evaluate the Status of Software Development Effort Es...
Efficient Indicators to Evaluate the Status of Software Development Effort Es...Efficient Indicators to Evaluate the Status of Software Development Effort Es...
Efficient Indicators to Evaluate the Status of Software Development Effort Es...
IJMIT JOURNAL
ย 
5fn37j6h
5fn37j6h5fn37j6h
5fn37j6h
hesirong
ย 
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Mohammad Lemar ZALMAฤฐ
ย 

Similar to 76 s201903 (20)

A Review on Earned Value Management and Earned Schedule Method for Constructi...
A Review on Earned Value Management and Earned Schedule Method for Constructi...A Review on Earned Value Management and Earned Schedule Method for Constructi...
A Review on Earned Value Management and Earned Schedule Method for Constructi...
ย 
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
ย 
IRJET- Value Management
IRJET- Value ManagementIRJET- Value Management
IRJET- Value Management
ย 
IRJET- Planning, Scheduling, and Optimization of Labor Resources in the C...
IRJET-  	  Planning, Scheduling, and Optimization of Labor Resources in the C...IRJET-  	  Planning, Scheduling, and Optimization of Labor Resources in the C...
IRJET- Planning, Scheduling, and Optimization of Labor Resources in the C...
ย 
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
ย 
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
IDENTIFICATION OF FACTORS CAUSING TIME AND COST OVERRUN IN CONSTRUCTION PROJE...
ย 
Efficient Indicators to Evaluate the Status of Software Development Effort Es...
Efficient Indicators to Evaluate the Status of Software Development Effort Es...Efficient Indicators to Evaluate the Status of Software Development Effort Es...
Efficient Indicators to Evaluate the Status of Software Development Effort Es...
ย 
Resource scheduling in Construction Project Using Microsoft Project
Resource scheduling in Construction Project Using Microsoft ProjectResource scheduling in Construction Project Using Microsoft Project
Resource scheduling in Construction Project Using Microsoft Project
ย 
The role of time, cost and quality in project management
The role of time, cost and quality in project managementThe role of time, cost and quality in project management
The role of time, cost and quality in project management
ย 
PetroSync - Successful Project Cost Estimation & Control
PetroSync - Successful Project Cost Estimation & ControlPetroSync - Successful Project Cost Estimation & Control
PetroSync - Successful Project Cost Estimation & Control
ย 
COST CONTROL AND TRACKING OF A BUILDING BY EARNED VALUE METHOD
COST CONTROL AND TRACKING OF A BUILDING BY EARNED VALUE METHODCOST CONTROL AND TRACKING OF A BUILDING BY EARNED VALUE METHOD
COST CONTROL AND TRACKING OF A BUILDING BY EARNED VALUE METHOD
ย 
IRJET- A Study on Quantification of Factors Affecting the Quality of Construc...
IRJET- A Study on Quantification of Factors Affecting the Quality of Construc...IRJET- A Study on Quantification of Factors Affecting the Quality of Construc...
IRJET- A Study on Quantification of Factors Affecting the Quality of Construc...
ย 
Tracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value ManagementTracking a Typical Apartment Construction using Earned Value Management
Tracking a Typical Apartment Construction using Earned Value Management
ย 
An Integrated BIM System To Track The Time And Cost Of Construction Projects ...
An Integrated BIM System To Track The Time And Cost Of Construction Projects ...An Integrated BIM System To Track The Time And Cost Of Construction Projects ...
An Integrated BIM System To Track The Time And Cost Of Construction Projects ...
ย 
76 s201905
76 s20190576 s201905
76 s201905
ย 
5fn37j6h
5fn37j6h5fn37j6h
5fn37j6h
ย 
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
ย 
30 8948 prakash paper64 (edit ndit)
30 8948 prakash paper64 (edit ndit)30 8948 prakash paper64 (edit ndit)
30 8948 prakash paper64 (edit ndit)
ย 
30 8948 prakash paper64 (edit ndit)
30 8948 prakash paper64 (edit ndit)30 8948 prakash paper64 (edit ndit)
30 8948 prakash paper64 (edit ndit)
ย 
Construction Project Scheduling of MK Apartment using MS Project 2013
Construction Project Scheduling of MK Apartment using MS Project 2013Construction Project Scheduling of MK Apartment using MS Project 2013
Construction Project Scheduling of MK Apartment using MS Project 2013
ย 

More from IJRAT

More from IJRAT (20)

96202108
9620210896202108
96202108
ย 
97202107
9720210797202107
97202107
ย 
93202101
9320210193202101
93202101
ย 
92202102
9220210292202102
92202102
ย 
91202104
9120210491202104
91202104
ย 
87202003
8720200387202003
87202003
ย 
87202001
8720200187202001
87202001
ย 
86202013
8620201386202013
86202013
ย 
86202008
8620200886202008
86202008
ย 
86202005
8620200586202005
86202005
ย 
86202004
8620200486202004
86202004
ย 
85202026
8520202685202026
85202026
ย 
711201940
711201940711201940
711201940
ย 
711201939
711201939711201939
711201939
ย 
711201935
711201935711201935
711201935
ย 
711201927
711201927711201927
711201927
ย 
711201905
711201905711201905
711201905
ย 
710201947
710201947710201947
710201947
ย 
712201907
712201907712201907
712201907
ย 
712201903
712201903712201903
712201903
ย 

Recently uploaded

Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Christo Ananth
ย 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
KreezheaRecto
ย 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
SUHANI PANDEY
ย 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
Tonystark477637
ย 

Recently uploaded (20)

Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
ย 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
ย 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
ย 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
ย 
Vivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design SpainVivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design Spain
ย 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
ย 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
ย 
Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...
ย 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
ย 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
ย 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
ย 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
ย 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
ย 
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLPVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
ย 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
ย 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
ย 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
ย 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
ย 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
ย 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
ย 

76 s201903

  • 1. International Journal of Research in Advent Technology, Vol.7, No.6S, June 2019 E-ISSN: 2321-9637 Available online at www.ijrat.org 16 doi: 10.32622/ijrat.76S201903 ๏€  Abstractโ€”Most of the construction projects suffer from cost and time overruns due to amultiplicity of factors. Earned value management (EVM) is a project performanceevaluation technique that has origins in industrial engineering, but which has beenadapted for application in project management. Earned Value Analysis software isdeveloped in Visual studio 2008, Next Comparison of selected parameters between M.SProject 2007, Primavera P6 and developed software is done. Therefore, it can beconcluded that the software could be used in a wide range of projects for Earned ValueAnalysis calculation.During the construction project it has been observed that certain causes may leadto delay in construction activities. This will result in time and cost overrun in the project.So it has become a major problem to complete the project on schedule and within theestimated cost. As a solution to this, the concept of construction project management byEarned Value Management System (EVMS) is evaluated.Earned Value Management is a powerful methodology used in monitoring andcontrolling of the project. EVMS is the project management technique developed tomeasure the performance and progress of the project based on the combination ofschedule, cost and work performed. By using this technique, the project status can beinvestigated in ongoing project at any stage which detects whether the project is under orover budget and behind or ahead of the planned schedule. Also the estimate cost andtime required to complete the project from current situation can be investigate. I. INTRODUCTION Constructions activity is one of the major scaling-down sectors in India. Several construction companies possess to stand facing heaps of harms directly to over budgets cost, overtime and inopportune planning, delays in construction be short of manpower, machinery and loads of other usual tribulations during task execution. One of the major problems are overflow of cost and over budgeted expenditure of project. To over fall these problems, earned value analysis is the procedure that fills up completely the above loopholes. Manuscript revised May 13, 2019 and published on June 5, 2019 Chandrakala S ,Assistant Professor, Department of Civil Engineering, SJCIT- Chickballapur- chanducharyas@gmail.com Bhavya S ,Assistant Professor, Department of Civil Engineering, SJCIT- Chickballapur- bhavya.s11689@gmail.com Shashi Kumar N V ,Assistant Professor, Department of Civil Engineering, SJCIT- Chickballapur- shashi02456@gmail.com Kiran K M ,Assistant Professor, Department of Civil Engineering, SJCIT- Chickballapur- kiranthribu@gmail.com Expected to implementation of EVA plan ahead administrator at their moment take part in the capability to express, and cost, schedule and mission implementation of their creation in a systematic, well-defined and understandable method to fit necessities of employees, director and customers. Earn value management is a systematic method to be the integration and measurement of schedule, cost and technical progress of a task or project. EVM provides project managers capability to examine detailed critical program, schedule information, technical achievement and cost records. It resembles a caution for the managers to be grateful for and thorough knowledge issues by attractive opportune counteractive course of action before they ride out of the question to conquer. It operation helps in generous achievement customary to the assessment of evolution report of project and it the same operate about as a mandate device to exchange with financial statement and time. It deals with measuring implementation of task at evident time intervals and reports that implementation to organization for method control. After being paid such monitored information, the concerned agency decides to understand more action to control the project before it grows to be insurmountable. Thus, monitoring and controlling is generally critical part procedure throughout complete life of the project. Earn value is a progress up conventional method of cost bookkeeping. It has been seen that to be responsible for protection of cost overwhelm, plan ahead organization undergoes cost attenuation each by diminishing the plan scope and quality or by giving extra. In this route with the management of earn value analysis framework, plan goals are accomplished in correct way. II. LITERATURE REVIEW B V. Birajdar, Amruta B. Vyas โ€œTracking of Construction Projects by Earned Value Managementโ€ [1]. Proficient Management of undertakings in development businesses are turning into a test with the progressing time. It has turned into a worry for the venture directors to ensure that the task is on plan and inside spending plan. EVA assesses the task execution by incorporating both cost and time perspectives consequently estimating the general advance. This paper talks about how EVA is acquainted with a continuous task on street works. It distinguishes the calendar as well as cost overwhelms already and in this manner giving a chance to directors in recognizing and controlling issues. This examination addresses in recognizing and controlling issues. This examination tends to both the expenses and the advantages of earned esteem. The earned esteem ideas and the related criteria are considered. Analysis on Cost Controlling and Tracking of Residential Building by EVM method using MS Project Software Chandrakala S, Bhavya S, Shashi Kumar N V, Kiran K M
  • 2. International Journal of Research in Advent Technology, Vol.7, No.6S, June 2019 E-ISSN: 2321-9637 Available online at www.ijrat.org 17 doi: 10.32622/ijrat.76S201903 GayatriVyas โ€œAnalysis of Cost Controlling Using Earned Value Management in Construction Industriesโ€ [2]. How development tasks can be finished convenient and cost viably is the consuming issue in the development business. There have been a few examinations that are centered on this, it has been seen that the following with shut observing of the genuine advance of assignments from the earliest starting point of the task and overseeing them utilizing earned esteem idea will brings about impressive cost sparing and auspicious fruition. This paper is cantered on idea and significance of earned esteem administration (EVM). Additionally, it incorporates components and execution pointers utilized for following and anticipating the task that advantages venture and eventually brings about undertaking achievement. Current paper utilizes a contextual investigation, a case use of EVA as a cost checking instrument. This contextual investigation reaffirms the Advantages of utilizing EVA for venture income examination and anticipating. GanapathyRamasamy N, Sandhya Suresh โ€œAnalysis of Performance Using Earned Value Analysisโ€ [3]. Development enterprises are confronting challenges step by step. In the midst of every one of these difficulties it is exceptionally urgent to enhance the execution of an undertaking regarding Schedule and Cost. Earned Value Analysis is an essential device in investigating the execution of any development venture. It gauges the venture advance and aides in recognizing the basic exercises consequently expediting the undertaking plan. This paper demonstrates the Earned Value Analysis done on a constant task in Kerala, utilizing Microsoft Office Project. The investigation helped in distinguishing the basic regions. It guaranteed that the venture is on time and inside the financial plan. J. Jayalakshmi, T. Subramani โ€œAnalysis of Cost Controlling In Costruction Building by Earned Value Method Using Primaveraโ€ [4]. The vast majority of the development ventures experience the ill effects of cost and time invades because of an assortment of elements. Earned esteem administration (EVM) is a venture execution assessment strategy that has starting points in mechanical designing, yet which has been adjusted for application in venture administration. The earned esteem investigation gives early signs of undertaking execution to feature the requirement for inevitable remedial activity. This investigation is to display and examine the primary parameters associated with the count of Earned Value Analysis (EVA) in the cost administration of common development ventures. The motivation behind this paper is in 3-crease. Right off the bat, Earned value analysis programming is created in MS Project 2007, server 2005, primavera P6 of a parameters, it can be inferred that the product could be utilized as a part of an extensive variety of activities for Earned Value Analysis figuring. VaishnaviTuljapurkar โ€œCost Controlling and Tracking of a Construction project by Earned Value Mathodโ€ [5]. Earned Value Management (EVM) is a method that conjectures the venture giving an early cautioning of cost and calendar. It not only measures the undertaking execution but rather likewise measure the advance of the timetable. It is a viable apparatus to gauge cost, plan and execution of the venture. The EVA is valuable in different fields, for example, IT, Industries and Construction organizations and so on. The estimation of Earned Value Analysis (EVA) is reliant on two key zones i.e. Exact Cost data and even minded advance of undertaking. In the event that these two key territories are effective at that point advantage of the undertaking will get esteemed. This paper compresses the development; essential wordings of Earned esteem Analysis and viable utilization of it in the development ventures by MS Project. There are numerous approaches to actualize EVA in the development venture. MS Project is a device to decide the EV and its parameters in an effective route with precision and inside time imperatives. III. OBJECTIVES OF STUDY The considerable objective of construction group is to conclude the task or project as determined on record details furthermore, inside the estimated with right manipulate of the large amount of assets like money, materials, labour and equipment and furthermore to complete the project with quality. 1. Project planning is done to complete the task on time and within budgeted cost. 2. To study Microsoft Project (MSP) software and to use the same software for the execution of the on-going project. 3. Analysis on schedule, cost, monitor and tracking of a project by using Microsoft project. 4. Work development will be estimated based on the project baseline created. 5. To recognize causes of potential schedule and cost overruns slackness. 6. Costs management is be to used EVM to give up the project activity in the estimated cost to attain elevated profits. 7. Creating a WBS and project schedule in the MS Project software. 8. Planned duration and actual duration was compared. 9. Co-relating the data after the WBS is prepared, with the pattern plan and finding the motive for the delay in time and rise in cost. 3.1 SCOPE OF THE STUDY Earned value management (EVM) is a strategy that impartially impresses objective achievement of work: 1. The task or project will always have fixed cost and time, if the task is not completed on time which will increases the total cost of project, to over slip delay and to overthrow delay without influencing budget and cost can be utilized and project management preserve be made. 2. EVM is used to deduce the upcoming of the project by doing the cost analysis and tracking of the project. 3. EVM observe the project by using old and present progress of project by statistical methods. 4. By using EVM methods stakeholders will be benefited. 5. At different stage of project we can get earned value management calculations, actual cost and remaining cost. 6. Cost unfathomable can be deducted by using EVM and proper planning together smartly.
  • 3. International Journal of Research in Advent Technology, Vol.7, No.6S, June 2019 E-ISSN: 2321-9637 Available online at www.ijrat.org 18 doi: 10.32622/ijrat.76S201903 Outline of scope of study is to do proper planning, scheduling and updating of different activities, which is done by using Microsoft Project software. After scheduling is done resource will be allocated and a baseline is set and project is updated, without affecting the complete project duration. At last the tracking is done by actual start and finish. . IV. ABOUT THE CONSTRUCTION PROJECT 4.1 CONSTRUCTION SITE DETAILS The Navanaamiplatina is located at chokkanahallithanisandra main road, YelahankaHobli, Bengaluru. It is a G+5 apartment with block named as C. it has a total of 40 flats. The apartment is comprised of premium 2.5 & 3 BHK flats. Project amenities, Swimming pool, squash court, office space Multipurpose hall, guest suite, gym and billiardsLift facilities are providedand Solar facilities are provided. 4.1.1 Project Site Detailss Land area = 29712sft , Total build up area =60263sft, G+5 Floors , 40 exclusive units, Infinity pool with deck65% of open space 4.1.2 Structural Details Table 4.1 Structural Details of Project Description Details Total number of footings 128 no. Total number of columns 145 no. Total floor height 18.15m Basement โ€“ 1st floor 3.15m 1st fllor to terrace 3.0/floor 4.1.3 Area Statements Table 4.2 Details of Build-up Area Sl.No Description No of floors Area in Sft Total area in Sft 1 Ground floor 1 11155 11155.00 2 First floor โ€“ second floor 2 9824 19648.00 3 Third floor โ€“ fourth floor 2 9894 19788.00 4 Fifth floor 1 9672 9672.00 TOTAL BUILD-UP AREA 60263.00 4.1.4 Flat Area Statement Table 4.3 Details of Flat Area Configuration Type Saleable Area (Sft) 2.5 BHK : 12 1129 โ€“ 1209 Sft 3 BHK : 28 โ€“ 1554 Sft 4.1.5 Project Construction Status in Percentage of completion Table 4.4 Status in Percentage of Completion Sl no Description Start date Finish date % of Completi on 1 Sub structure 07.06.1 7 06.10.17 100% 2 Super structure 07.10.1 7 20.05.18 90% 3 Block work 10.12.1 7 13.07.18 60% 4 Plastering 06.02.1 8 08.09.18 38% 5 Handover building 25.12.18 4.1.6 Quantity of Material Table 4.5 Quantity of materials NavanaamiPlatina Sl.No Descriptions Unit Noโ€™s Quantit y 1 Concretee PCC Concretee M3 1 620.00 M20 Concrete M3 1 1100.00 M25 Concrete M3 1 5850.00 M30 Concrete M3 1 612.00 2 Block Workss 100mm M2 1 2900.00 150mm M2 1 8350.00 200mm M2 1 1735.00 3 Plasterings Ceiling M2 1 8500.00 Internal Walls M2 1 26000.0 0 Externall Walls M2 1 9800.00 9 4 Waterproofings Water proofing for terrace floors Smt 950.00 Water proofing workss Toilet, Balcony and Utility flooring Smt 2350.00 Retaining walls Smt 1000.00 Podiums Smt 1550.00 STP, UG Tank, Pool and OHT Smt 6580.00 5 Painting For celling surface M2 1 7550.00 Emulsion paint for external surface M2 1 9230.00 Emulsion paint for internal wall surface M2 1 21400.0 0 Retaining wall finish and M2 1 7060.00
  • 4. International Journal of Research in Advent Technology, Vol.7, No.6S, June 2019 E-ISSN: 2321-9637 Available online at www.ijrat.org 19 doi: 10.32622/ijrat.76S201903 basement celling 6 Tilling Vitrifieds(605*6 05) mm M2 1 7435.00 Anti-skids (300*300) mms M2 1 870.00 Ceramics (450*300) mm M2 1 3240.00 Kitchen dadoes(350*250 ) mm M2 1 330.00 C block common areas and clubhouse M2 1 1135.00 Lift M2 1 160.00 Staircase area granite M2 1 455.00 Top kitchen counter M2 1 415.00 7 Windowss Utility door and UPVC windows M2 1 1085.00 UPVC ventilatorss M2 1 195.00 8 Doors Main doors M2 1 198.57 Bed room doors M2 1 373.63 Toilet doors M2 1 325.35 Balcony doors M2 29.00 V. FINDINGS AND OBSERVATIONS The navanaamiplatina construction project is 517 days and 7, 14, 25,578 rupees budgeted project and estimated to complete on December 2018. This project is tracked three duration to know about project performance picture, the founded or obtained results are listed in below tables and in below figure. Table 5.1 Shows the Parameters Values after Tracking of Project EVM Parameter 1st tracking 2nd tracking 3rd tracking Tracking dates 26-Aug-201 7 26-Dec-201 7 16-April -2018 Original duration of project 517 517 517 Remaining durations 410 302 196 Budgeted total cost of project 7,14,25,578 7,14,25,578 7,14,25, 578 Planned value 4182605 25080232 4434770 3 Earned value 4125645 24858080 4331360 6 Actual cost 4230370 25104817 4816148 6 Schedule performanc e index 0.98 0.98 0.97 Schedule variance -56960 -222152 -103409 7 Cost variance -104725 -246737 -484788 0 Cost performanc e index 0.97 0.98 0.89 The various project elements or indicators were calculated. The values were calculated by using following formulae. SV = EV-PV = 4125645-4182605 = -56960 rupees CV = EV-AC = 4125645-4230370 = -104725 rupees SPI = EV/PV = 0.98 CPI = EV/AC = 0.97 Table 5.2 Cumulative Cost after Tracking from MS Project EVM Parameter 1st tracking 2nd tracking 3rd tracking Tracking Date 26-Aug-2017 26-Dec-2017 16-Apr-2018 Planned value cost 4182605 25080232 44347703 Cumulative Planned value cost 4182605 20897627 23450076 Earned value cost 4125645 24858080 43313606 Cumulative Earned value cost 4125645 20732435 22581171 Actual cost 4230370 25104817 48161486 Cumulative Actual cost 4230370 20874447 27287039 The CV and CPI represent the cost performance of a project. The both vales are less than 1 means cost is overrun of project (project is uneconomical in terms of cost). The SV and SPI represent the time performance of a project and the both values are less than 1 means project is behind schedule VI. CONCLUSION Earned value provides a quick fore warning suggest to managers to undertake the counteractive action. EVM allows both cost and schedule analysis against objective work performed. The client and customer are satisfied then the project is successful and itโ€™s finished within planned and planned budget. The project schedule and cost is interlinked between each other. If we expenditure more property for individual task, the task will complete within the duration. If
  • 5. International Journal of Research in Advent Technology, Vol.7, No.6S, June 2019 E-ISSN: 2321-9637 Available online at www.ijrat.org 20 doi: 10.32622/ijrat.76S201903 we expenditure less property for the task it will take more duration to complete the activity. So, properly allocate an optimum resources and duration of a construction building project to make it successful completion. Construction management is necessity to operate the project well manageable, controllable and vision able. The different software tools are come into occupancy in that MS Project is also one of programming software package. The project can be monitored by a better way by using MS Project software. The project is tracked on 3 times from 26-April-2017 to 26-Aug-2017, 26-Aug-2017 to 26-Dec-2017, 26-Dec-2017 to 16-April-2018, by tracking we obtained earned value (EV), planned value (PV) and actual cost (AC), these 3 basic shows the performance of a project by earned value performance index. ๏‚ท While on 3rd tracking 196 days are remaining to finish the task or activities, the cost performing 89% (CPI 0.89) as budgeted cost it shows the project budgeted cost is overrunning. And schedule performing 98% (SPI .98) as planned value; it shows the project is under running. ๏‚ท Cost variance of construction project is -4847880 rupees the negative sign shows cost of project is overrun. If the cost variance is negative the project is overrun or behind from planned value and cost variance is positive project is underrun or ahead from planned value and some troubles will creates in the project. ๏‚ท 60% of planned schedule is finished. ๏‚ท Cost requires to finish remaining task is 3813783. ๏‚ท To finish project on schedule time duration the project has to perform in 1.09% speed of planned value of the project. The resource sheet will provides better information of resource estimates. REFERENCES [1] B.V Birajdar, Amrutha .B Vyas , "Tracking of Construction Projects by Earned Value Manaement," IJERT, International Journal of Engineering research and Technology, Vol. 05, pp. 162-169, March 2016. [2] Gayatri Vyas, Sagar K. Bhosekar, "Cost Controlling Using Earned Value Analysis in Construction Industries," IJET, International Journal of Engineering and Technology, Vol. 01, pp. 164-171, April 2012. [3] Ganapathy Ramaswamy N, Sandhya Suresh, "Analysis of Performance using Earned Value Analysis," IJSETR, International Journal of Science Engineering and Technology Research, Vol. 04, pp. 73-82, April 2015. [4] Jayalakshmi, T. Subramani, "Analysis of Cost Controlling in Construction Buikding by Earned Value Method using Primavera," IJTRA, International Journal of Technology Research and Applications,Vol. 04, pp. 145-153, June 2014. [5] Vaishnavi Tuljapurkar, "Cost Control and Tracking of a Construction Building by Earned Value Method," IJTRA, Internal Journal of technology Research and Applications, Vol. 03, pp. 15-22, April 2015. [6] Taran C. Bhagat, Parag S. Mhatme, "Cost Controlling and Monitoring of Construction Project Through Earned Value Management System," IJATES, International Journal of Advanced technology in Engineering and Science,vol. 03, pp. 45-51, March 2015. [7] Waris Ali khan, Arazi Idrus, "The Cost Monitoring of Construction Projects Through Earned value Analysis," ICEFR, International Conference on Economics and finance research,Vol. 04, pp. 251-259, 2011. .