This document discusses earned value management (EVM) as an effective tool for tracking and controlling construction project costs and schedules. EVM integrates cost, schedule and technical performance by comparing the planned cost of work scheduled to the actual cost of work performed. The document provides background on EVM, including its history and use in various industries. It then discusses how EVM establishes a cost baseline and calculates variances to analyze project performance and identify potential issues needing corrective action in order to complete projects on time and on budget.
Project management tools and techniques- tutorsindia.comTutors India
In this topic, we have discussed the project management tools and techniques. The present article helps the USA, the UK, Europe and the Australian students pursuing their master’s degree to identify the best project management tools and techniques, which are usually considered to be challenging. Tutors India offers UK dissertation in various Domains.
When you Order any reflective report at Tutors India, we promise you the following
Plagiarism free
Always on Time
Outstanding customer support
Written to Standard
Unlimited Revisions support
High-quality Subject Matter Experts.
Contact:
Website: www.tutorsindia.com
Email: info@tutorsindia.com
United Kingdom: +44-1143520021
India: +91-4448137070
Whatsapp Number: +91-8754446690
Reference: http://bit.ly/2v6tBB6
Efficient Planning Scheduling and Delay Analysis of Residential ProjectIJERA Editor
Planning and scheduling have become an essential part of any project for the timely and economical completion of the project. A proper construction schedule can be used for different purposes. By using construction schedule to predict project completion, contractors can adjust crew size, shifts or equipment to speed or slow the progress. All the construction projects will vary from each other in size. All the projects have time constraint. Delay in completion of project will increase the overall cost of the project. Small projects can be managed efficiently manually; whereas large projects are not so large projects can be better handled by the use of computers. Many types of software are available with the help of which project management can be done easily. Large quantities of different kinds of resources are also required for execution and the risk is more in the case of projects. So planning and scheduling of activities for construction of big projects is essential. In this study, an effort is made in planning, scheduling and delay analysis updating of various activities, which is done by using MS Project and MS Excel software, manpower of each activity is determined and allocation is done using the software. Labor requirement for each activity is calculated from standards obtained from site. An updated schedule, which helps to finish the project well in time with optimum resources and update helps in delay analysis, is under the scope of this study.
Planning and Optimization of Resource Constrained Project Scheduling by using...IRJET Journal
This document presents a study on optimizing the scheduling of construction projects using a genetic algorithm approach. It discusses traditional project scheduling methods like critical path method that do not consider resource constraints. The study aims to develop a genetic algorithm model to minimize the duration of a residential building project given resource constraints. It describes conducting a questionnaire survey to identify critical delay factors. The genetic algorithm is applied to optimize the schedule obtained from Microsoft Project, reducing the duration from 185 days to 172 days. The genetic algorithm approach provides a more effective scheduling solution than traditional methods.
This document discusses using earned value management (EVM) to control costs and schedules on construction projects. It begins with an abstract that describes EVM as a project performance evaluation technique adapted from industrial engineering. The document then discusses how EVM software was developed in Visual Studio 2008 to perform earned value analysis calculations and compare results to Microsoft Project and Primavera P6. It concludes the software could be useful for a wide range of projects requiring EVM analysis. Next, it reviews literature on using EVM to track construction projects, control costs in the construction industry, analyze project performance, and control costs and track a construction project through earned value analysis. The objectives of the study are then stated as concluding the project as planned in terms
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET Journal
This document discusses project management techniques to avoid project failure. It begins with an introduction to project management and definitions of key terms. The literature review then summarizes several academic papers on topics related to project failure such as identifying common causes of failure, project performance measurement, and techniques for scheduling projects with uncertainty. The conclusion reiterates that project management techniques must be tailored to the specific project and region, and that further research is needed to enhance understanding of avoiding project failure.
IRJET- Planning, Scheduling, and Optimization of Labor Resources in the C...IRJET Journal
This document discusses planning, scheduling, and optimizing labor resources for the construction of a residential apartment building using Primavera P6 software. It describes how the software was used to plan and schedule each activity through critical path method. To address potential lack of required labor resources, labor resource leveling, smoothing, and overtime working techniques were used to optimize resource allocation. Using these techniques, the total project duration was changed from 935 days to 1011 days with leveling, remained at 935 days with smoothing, and was reduced to 748 days with overtime working, all while maintaining the total labor units and completing the project on schedule.
A REVIEW ON FACTORS INFLUENCING CONSTRUCTION PROJECT SCHEDULINGIAEME Publication
Construction scheduling is a complex and challenging task demanding an in depth
expertise. Consideration of several factors, their influences and likely impact on the
schedule need a thorough understanding. It is mostly experience based knowledge in
the form of heuristics, available with the experienced schedulers. In this connection
this study mainly discusses the factors influencing construction scheduling and
techniques through a comparative study of various international construction
projects. About 40 relevant articles published over the last 25 years have been
reviewed. However, each and every limited formalized knowledge is available in
theoretical form, which is interesting to many researchers for many decades, a
comprehensive research is made and a comparative study on the literatures was
carried out and presented in this paper. The main aim of the paper is to highlight the
major factors which are to be mainly considered for the successful completion of the
project.
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET Journal
This document discusses project management techniques that can be used to avoid project failure. It analyzes responses from project managers on reasons for project failure and how to ensure success. Some key findings are:
- Poor planning, unrealistic timelines and cost estimates, and lack of clear objectives are common reasons for failure.
- Successful projects meet scope, time and cost goals while satisfying stakeholders.
- Techniques like CPM, PERT, Gantt charts and MS Project help managers monitor progress and implement corrective actions to get projects back on track if issues arise.
Project management tools and techniques- tutorsindia.comTutors India
In this topic, we have discussed the project management tools and techniques. The present article helps the USA, the UK, Europe and the Australian students pursuing their master’s degree to identify the best project management tools and techniques, which are usually considered to be challenging. Tutors India offers UK dissertation in various Domains.
When you Order any reflective report at Tutors India, we promise you the following
Plagiarism free
Always on Time
Outstanding customer support
Written to Standard
Unlimited Revisions support
High-quality Subject Matter Experts.
Contact:
Website: www.tutorsindia.com
Email: info@tutorsindia.com
United Kingdom: +44-1143520021
India: +91-4448137070
Whatsapp Number: +91-8754446690
Reference: http://bit.ly/2v6tBB6
Efficient Planning Scheduling and Delay Analysis of Residential ProjectIJERA Editor
Planning and scheduling have become an essential part of any project for the timely and economical completion of the project. A proper construction schedule can be used for different purposes. By using construction schedule to predict project completion, contractors can adjust crew size, shifts or equipment to speed or slow the progress. All the construction projects will vary from each other in size. All the projects have time constraint. Delay in completion of project will increase the overall cost of the project. Small projects can be managed efficiently manually; whereas large projects are not so large projects can be better handled by the use of computers. Many types of software are available with the help of which project management can be done easily. Large quantities of different kinds of resources are also required for execution and the risk is more in the case of projects. So planning and scheduling of activities for construction of big projects is essential. In this study, an effort is made in planning, scheduling and delay analysis updating of various activities, which is done by using MS Project and MS Excel software, manpower of each activity is determined and allocation is done using the software. Labor requirement for each activity is calculated from standards obtained from site. An updated schedule, which helps to finish the project well in time with optimum resources and update helps in delay analysis, is under the scope of this study.
Planning and Optimization of Resource Constrained Project Scheduling by using...IRJET Journal
This document presents a study on optimizing the scheduling of construction projects using a genetic algorithm approach. It discusses traditional project scheduling methods like critical path method that do not consider resource constraints. The study aims to develop a genetic algorithm model to minimize the duration of a residential building project given resource constraints. It describes conducting a questionnaire survey to identify critical delay factors. The genetic algorithm is applied to optimize the schedule obtained from Microsoft Project, reducing the duration from 185 days to 172 days. The genetic algorithm approach provides a more effective scheduling solution than traditional methods.
This document discusses using earned value management (EVM) to control costs and schedules on construction projects. It begins with an abstract that describes EVM as a project performance evaluation technique adapted from industrial engineering. The document then discusses how EVM software was developed in Visual Studio 2008 to perform earned value analysis calculations and compare results to Microsoft Project and Primavera P6. It concludes the software could be useful for a wide range of projects requiring EVM analysis. Next, it reviews literature on using EVM to track construction projects, control costs in the construction industry, analyze project performance, and control costs and track a construction project through earned value analysis. The objectives of the study are then stated as concluding the project as planned in terms
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET Journal
This document discusses project management techniques to avoid project failure. It begins with an introduction to project management and definitions of key terms. The literature review then summarizes several academic papers on topics related to project failure such as identifying common causes of failure, project performance measurement, and techniques for scheduling projects with uncertainty. The conclusion reiterates that project management techniques must be tailored to the specific project and region, and that further research is needed to enhance understanding of avoiding project failure.
IRJET- Planning, Scheduling, and Optimization of Labor Resources in the C...IRJET Journal
This document discusses planning, scheduling, and optimizing labor resources for the construction of a residential apartment building using Primavera P6 software. It describes how the software was used to plan and schedule each activity through critical path method. To address potential lack of required labor resources, labor resource leveling, smoothing, and overtime working techniques were used to optimize resource allocation. Using these techniques, the total project duration was changed from 935 days to 1011 days with leveling, remained at 935 days with smoothing, and was reduced to 748 days with overtime working, all while maintaining the total labor units and completing the project on schedule.
A REVIEW ON FACTORS INFLUENCING CONSTRUCTION PROJECT SCHEDULINGIAEME Publication
Construction scheduling is a complex and challenging task demanding an in depth
expertise. Consideration of several factors, their influences and likely impact on the
schedule need a thorough understanding. It is mostly experience based knowledge in
the form of heuristics, available with the experienced schedulers. In this connection
this study mainly discusses the factors influencing construction scheduling and
techniques through a comparative study of various international construction
projects. About 40 relevant articles published over the last 25 years have been
reviewed. However, each and every limited formalized knowledge is available in
theoretical form, which is interesting to many researchers for many decades, a
comprehensive research is made and a comparative study on the literatures was
carried out and presented in this paper. The main aim of the paper is to highlight the
major factors which are to be mainly considered for the successful completion of the
project.
IRJET- A Study on Project Management Techniques to Avoid Project FailureIRJET Journal
This document discusses project management techniques that can be used to avoid project failure. It analyzes responses from project managers on reasons for project failure and how to ensure success. Some key findings are:
- Poor planning, unrealistic timelines and cost estimates, and lack of clear objectives are common reasons for failure.
- Successful projects meet scope, time and cost goals while satisfying stakeholders.
- Techniques like CPM, PERT, Gantt charts and MS Project help managers monitor progress and implement corrective actions to get projects back on track if issues arise.
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-ProjectIRJET Journal
This document discusses planning and scheduling a multi-storied building construction project using Microsoft Project software. It begins with an abstract that outlines the objectives of studying scheduling methods for multi-story buildings and applying MS Project software to plan and schedule a hypothetical 7-story residential building. The document then provides background on the benefits of effective project planning and scheduling for reducing construction time and costs. It describes the key aspects and features of MS Project for developing schedules, assigning resources to tasks, tracking progress, managing budgets, and analyzing workloads. The methodology section outlines the steps for using MS Project to plan and schedule the hypothetical building project within time and resource constraints to complete it on schedule.
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET Journal
This document summarizes a study that planned and scheduled the construction of a multi-story residential building using Microsoft Project software and applied material management techniques. The study categorized building materials using ABC analysis to prioritize those with the greatest cost impact. Scheduling the project in Microsoft Project and analyzing material usage helped optimize costs and duration to increase construction efficiency. Applying material management principles such as inventory control and efficient procurement supported timely material availability and reduced waste.
iEVM (Integrated Earned Value Management) An approach for integrating quality...IRJET Journal
This document proposes a new model called integrated earned value management (iEVM) that aims to address limitations in how traditional earned value management (EVM) accounts for quality in projects. Specifically, EVM treats quality as implicitly part of scope but iEVM would explicitly include quality as a fourth factor integrated alongside time, scope and cost. The model utilizes the concept of cost of quality to more accurately monitor, control and predict projects, especially complex IT projects where rework is common and can impact earned value calculations.
Traditional project management methods are based on scientific principles considered “normal science,” but lack a theoretical basis for this approach. These principles make use of linear step–wise refinement of the project management processes using a planning–as–management paradigm. Plans made in this paradigm are adjusted by linear feedback methods. These plans cannot cope with the multiple interacting and continuously changing technology and market forces. They behave as a linear, deterministic, Closed–Loop control system.
EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...Sibo Kanyambari Aimable
Risks are very common in construction sector. Risk is the Possibility of suffering loss and the impact on the involved parties. According to APM (2006), all projects are inherently risky because they are unique, constrained, complex, based on assumptions, and performed by people. As a result, project risk management methods must be built into the management of projects and should be used throughout the project lifecycle.
Many construction projects fail because organizations assume that all the projects would succeed and they therefore do not identify, analyze, and provide mitigation or contingencies for the risk elements involved in the project.
Society desires that all projects should be performing and has become less tolerant of failure (Edwards and Bowen, 2005). Pressure is exerted on project managers to minimize the chance of project failure. This increasing pressure for performance which suggests that it is prudent for anyone involved in a project to be concerned about the associated risks and how they can be effectively managed.
Traditionally, performance of a project is analyzed on the criteria of quality, budget and time of completion. Two more criteria to determine the performance of a project were added by Kerzner (2001). Firstly, the project would effectively and efficiently manage risks and, secondly, it should be accepted by the customer.
It is known that the cause of the projects failure can be directly related to the extent of risk management methods undertaken. Besides, the level of risk management methods undertaken during project lifecycle impacts directly on the performance or otherwise of the project. Furthermore, using risk management methods effectively to manage risk should be continuously undertaken throughout the project lifecycle to enhance project performance. Risk management methods are thus an important tool to cope with such substantial risks in projects performance.
The main objective of the enquiry work that underpins this research is to investigate the effect of risk management methods on project performance. In this paper, a case study of RSSB multi-storey already executed project is considered.
The document discusses risk factors that influence construction procurement performance in Nigeria. It identifies 20 risk factors through a literature review. A questionnaire was distributed to construction professionals to evaluate the significance of these factors. Corruption, conflict of interest, ineffective project feasibility studies, and lack of transparency were found to be the most significant factors limiting procurement performance. Communication barriers and unconfidential tender evaluations were considered less important. The findings can help improve risk management and procurement systems in Nigeria to enhance overall project performance.
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...IRJET Journal
This document discusses a study that aimed to identify factors influencing equipment productivity in construction projects. A literature review was conducted to understand previous research on this topic. A questionnaire survey of 20 construction organizations was also carried out to collect data on factors affecting equipment productivity. The responses were analyzed using the Relative Importance Index method. The results showed that the major factor affecting equipment productivity is the lack of operator ability due to issues related to the operator/human. The study provides recommendations to improve equipment productivity in the construction industry.
IRJET- The Impact of Effective Planning on Project Success – A Literature ReviewIRJET Journal
This document is a literature review that examines the relationship between project planning and project success. It summarizes several studies that show a consistent positive correlation between higher quality project planning and better project outcomes related to cost, schedule and efficiency. Specifically, the literature review finds that:
1) Studies in the construction industry show that higher levels of pre-project planning, as measured by completeness scores, are correlated with a higher probability of projects meeting financial goals, schedule goals, and design goals.
2) One study found that construction projects with a planning completeness score above 200 (on a 1000 point scale) were more likely to meet budget, schedule and quality targets compared to projects with scores below 200.
3) The literature
Insights on Research Techniques towards Cost Estimation in Software Design IJECEIAES
This document summarizes research on techniques for cost estimation in software design. It begins by describing common cost estimation techniques like Constructive Cost Modeling (COCOMO) and Function Point Analysis. It then analyzes research trends in cost estimation, effort estimation, and fault prediction based on literature from 2010 to present. Fewer than 50 papers were found related to overall cost estimation, less than 25 for effort estimation, and only 9 for fault prediction. The document then reviews existing research addressing general cost estimation, enhancement of Function Point Analysis, statistical modeling approaches, cost estimation for embedded systems, and estimation for fourth generation languages and NASA projects. Most techniques use COCOMO or extend existing models with techniques like fuzzy logic, neural networks, or statistical
A survey was conducted on construction project risk management. The results showed that respondents felt the most important things were risk identification and mitigation, analyzing competitors' risks, and ensuring risks are distributed fairly between contracting parties. The Construction Project Risk Management Asia 2011 conference will provide answers to questions on managing risks, with case studies from major infrastructure projects. Attendees can register by email or phone.
Project Scheduling: Survey and Research PotentialsEditor IJCATR
project scheduling is very critical topic in project management. Resource constrained project scheduling problem (RCPSP) consists of activities that must be scheduled based on dependencies relationships and priorities of activities. In the recent years there have been many survey papers around the area of project scheduling, as many researchers developed both exact and heuristic scheduling schemes. This paper give an over view around the resource constrained project scheduling problem (RCPSP).
Forecasting cost and schedule performanceGlen Alleman
This document discusses the importance of statistical forecasting for project performance in the presence of uncertainty. Some key points:
- Current Earned Value Management techniques treat metrics like SPI/CPI as single point estimates without accounting for underlying variances, missing important statistical information.
- Forecasts of future performance using current EV techniques are linear, non-risk adjusted projections that ignore the statistical nature of past performance data.
- Statistical time series analysis of past performance data from the Central Repository can provide probabilistic forecasts with confidence intervals, increasing the probability of project success.
- All project activities have natural uncertainties that impact the probability of cost, schedule and technical performance. Understanding these statistical behaviors is crucial for credible forecast
Senstivity Analysis of Project Scheduling using Fuzzy Set TheoryIRJET Journal
This document discusses using fuzzy set theory to analyze delays in construction project scheduling. It presents fuzzy logic as an approach to estimate delays using linguistic values for factors like weather (good, medium, bad) and labor experience (high, medium, low). These membership values can help determine the total effect on project duration from different reasons. This technique allows understanding total delay through critical path method and program evaluation review technique. The main advantage is this approach can be implemented in existing computer programs for project scheduling to consider delays from external factors.
Earned Value Management (EVM) is a technique
that forecasts the project giving an early warning of cost &
schedule. It not onely measures the project performance but also
measure the progress of the schedule. It is an effective tool to
measure cost, schedule & performance of the project. The EVA is
useful in various fields such as IT, Industries and Construction
companies etc.
The value of Earned Value Analysis (EVA) is dependent on
two key areas i.e. Precise Cost information and pragmatic
progress of project. If these two key areas are efficient then
benefit of the project will definitely get valued. This paper
summarizes the evolution, basic terminologies of Earned value
Analysis and effective use of it in the construction industries by
MS Project. There are many ways to implement EVA in the
construction project. MS Project is a tool to determine the EV
and its parameters in an efficient way with accuracy and within
time constraints.
Making decision in the presence of uncertainty requires estimating the impact of the outcome of those decisions. Here;s a collection of resources can can be used to guide that process
Forecasting cost and schedule performanceGlen Alleman
For credible decisions to be made, we need confidence intervals on all the numbers we use to make decisions.
These confidence intervals come from the underlying statistics and the related probabilities.
Statistical forecasting, using time series analysis of past performance, is mandatory for any credible discussion of project performance in the future.
IRJET-Survey on Effects of Productivity of Equipment in Construction ProjectsIRJET Journal
This document summarizes a study on the effects of equipment productivity in construction projects. The study aimed to identify key factors influencing equipment productivity and their impacts on projects. A literature review identified six main effects: cost overrun, delay, disputes, loss of equipment productivity, equipment accidents, and work suspensions. Questionnaires were distributed to construction professionals who rated each effect. The relative importance index method was used to analyze the data and rank the effects. Delay was found to be the most important effect, followed by cost overrun and disputes. The findings provide insight into improving equipment productivity and minimizing impacts on construction projects.
Schedule feasibility refers to the likelihood that a project can be completed within its planned timeframe. It is important because it ensures a project is finished before becoming obsolete or unnecessary. Schedule feasibility can be calculated using operations research methods and shown through Gantt and PERT charts, which display the probability of meeting deadlines.
Project appraisal involves a critical examination of all aspects of a proposed project to analyze prospective costs and benefits and determine if committing resources is desirable. It is carried out through internal and external appraisal and considers social, economic, environmental, financial, administrative, commercial, and technical aspects. The appraisal process involves preliminary steps like reviewing documents for completeness and accuracy before analyzing aspects in detail to evaluate a project's viability.
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...IRJET Journal
This document discusses controlling and monitoring construction projects using the earned value method. It begins with an introduction to the importance of controlling and monitoring construction projects. It then discusses the methodology of earned value analysis, including defining earned value, variances, and the five steps to set up an earned value system and four steps to use the information generated. Key aspects of earned value discussed include using it as a uniform measure of project progress, its role in cost performance analysis, and how it is calculated based on planned value, earned value, and actual costs.
IRJET- Portfolio Management of Multiple Building Projects using EPPMIRJET Journal
This document discusses portfolio management of multiple building construction projects using Primavera EPPM P6v16.1 software. It analyzes 4 commercial building projects, calculating quantities and scheduling activities. The projects were planned, scheduled and baseline budgets created in Primavera P6. A portfolio of the projects was then prepared to evaluate cash flow, optimize resource use, reduce warehousing and administrative costs. Prior research on using Primavera P6 for project planning, scheduling and monitoring is also reviewed. The objective is to develop the project portfolio and analyze cash flow using the Primavera software.
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-ProjectIRJET Journal
This document discusses planning and scheduling a multi-storied building construction project using Microsoft Project software. It begins with an abstract that outlines the objectives of studying scheduling methods for multi-story buildings and applying MS Project software to plan and schedule a hypothetical 7-story residential building. The document then provides background on the benefits of effective project planning and scheduling for reducing construction time and costs. It describes the key aspects and features of MS Project for developing schedules, assigning resources to tasks, tracking progress, managing budgets, and analyzing workloads. The methodology section outlines the steps for using MS Project to plan and schedule the hypothetical building project within time and resource constraints to complete it on schedule.
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET Journal
This document summarizes a study that planned and scheduled the construction of a multi-story residential building using Microsoft Project software and applied material management techniques. The study categorized building materials using ABC analysis to prioritize those with the greatest cost impact. Scheduling the project in Microsoft Project and analyzing material usage helped optimize costs and duration to increase construction efficiency. Applying material management principles such as inventory control and efficient procurement supported timely material availability and reduced waste.
iEVM (Integrated Earned Value Management) An approach for integrating quality...IRJET Journal
This document proposes a new model called integrated earned value management (iEVM) that aims to address limitations in how traditional earned value management (EVM) accounts for quality in projects. Specifically, EVM treats quality as implicitly part of scope but iEVM would explicitly include quality as a fourth factor integrated alongside time, scope and cost. The model utilizes the concept of cost of quality to more accurately monitor, control and predict projects, especially complex IT projects where rework is common and can impact earned value calculations.
Traditional project management methods are based on scientific principles considered “normal science,” but lack a theoretical basis for this approach. These principles make use of linear step–wise refinement of the project management processes using a planning–as–management paradigm. Plans made in this paradigm are adjusted by linear feedback methods. These plans cannot cope with the multiple interacting and continuously changing technology and market forces. They behave as a linear, deterministic, Closed–Loop control system.
EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...Sibo Kanyambari Aimable
Risks are very common in construction sector. Risk is the Possibility of suffering loss and the impact on the involved parties. According to APM (2006), all projects are inherently risky because they are unique, constrained, complex, based on assumptions, and performed by people. As a result, project risk management methods must be built into the management of projects and should be used throughout the project lifecycle.
Many construction projects fail because organizations assume that all the projects would succeed and they therefore do not identify, analyze, and provide mitigation or contingencies for the risk elements involved in the project.
Society desires that all projects should be performing and has become less tolerant of failure (Edwards and Bowen, 2005). Pressure is exerted on project managers to minimize the chance of project failure. This increasing pressure for performance which suggests that it is prudent for anyone involved in a project to be concerned about the associated risks and how they can be effectively managed.
Traditionally, performance of a project is analyzed on the criteria of quality, budget and time of completion. Two more criteria to determine the performance of a project were added by Kerzner (2001). Firstly, the project would effectively and efficiently manage risks and, secondly, it should be accepted by the customer.
It is known that the cause of the projects failure can be directly related to the extent of risk management methods undertaken. Besides, the level of risk management methods undertaken during project lifecycle impacts directly on the performance or otherwise of the project. Furthermore, using risk management methods effectively to manage risk should be continuously undertaken throughout the project lifecycle to enhance project performance. Risk management methods are thus an important tool to cope with such substantial risks in projects performance.
The main objective of the enquiry work that underpins this research is to investigate the effect of risk management methods on project performance. In this paper, a case study of RSSB multi-storey already executed project is considered.
The document discusses risk factors that influence construction procurement performance in Nigeria. It identifies 20 risk factors through a literature review. A questionnaire was distributed to construction professionals to evaluate the significance of these factors. Corruption, conflict of interest, ineffective project feasibility studies, and lack of transparency were found to be the most significant factors limiting procurement performance. Communication barriers and unconfidential tender evaluations were considered less important. The findings can help improve risk management and procurement systems in Nigeria to enhance overall project performance.
IRJET-Identification of Factors Influencing Equipment Productivity in Constru...IRJET Journal
This document discusses a study that aimed to identify factors influencing equipment productivity in construction projects. A literature review was conducted to understand previous research on this topic. A questionnaire survey of 20 construction organizations was also carried out to collect data on factors affecting equipment productivity. The responses were analyzed using the Relative Importance Index method. The results showed that the major factor affecting equipment productivity is the lack of operator ability due to issues related to the operator/human. The study provides recommendations to improve equipment productivity in the construction industry.
IRJET- The Impact of Effective Planning on Project Success – A Literature ReviewIRJET Journal
This document is a literature review that examines the relationship between project planning and project success. It summarizes several studies that show a consistent positive correlation between higher quality project planning and better project outcomes related to cost, schedule and efficiency. Specifically, the literature review finds that:
1) Studies in the construction industry show that higher levels of pre-project planning, as measured by completeness scores, are correlated with a higher probability of projects meeting financial goals, schedule goals, and design goals.
2) One study found that construction projects with a planning completeness score above 200 (on a 1000 point scale) were more likely to meet budget, schedule and quality targets compared to projects with scores below 200.
3) The literature
Insights on Research Techniques towards Cost Estimation in Software Design IJECEIAES
This document summarizes research on techniques for cost estimation in software design. It begins by describing common cost estimation techniques like Constructive Cost Modeling (COCOMO) and Function Point Analysis. It then analyzes research trends in cost estimation, effort estimation, and fault prediction based on literature from 2010 to present. Fewer than 50 papers were found related to overall cost estimation, less than 25 for effort estimation, and only 9 for fault prediction. The document then reviews existing research addressing general cost estimation, enhancement of Function Point Analysis, statistical modeling approaches, cost estimation for embedded systems, and estimation for fourth generation languages and NASA projects. Most techniques use COCOMO or extend existing models with techniques like fuzzy logic, neural networks, or statistical
A survey was conducted on construction project risk management. The results showed that respondents felt the most important things were risk identification and mitigation, analyzing competitors' risks, and ensuring risks are distributed fairly between contracting parties. The Construction Project Risk Management Asia 2011 conference will provide answers to questions on managing risks, with case studies from major infrastructure projects. Attendees can register by email or phone.
Project Scheduling: Survey and Research PotentialsEditor IJCATR
project scheduling is very critical topic in project management. Resource constrained project scheduling problem (RCPSP) consists of activities that must be scheduled based on dependencies relationships and priorities of activities. In the recent years there have been many survey papers around the area of project scheduling, as many researchers developed both exact and heuristic scheduling schemes. This paper give an over view around the resource constrained project scheduling problem (RCPSP).
Forecasting cost and schedule performanceGlen Alleman
This document discusses the importance of statistical forecasting for project performance in the presence of uncertainty. Some key points:
- Current Earned Value Management techniques treat metrics like SPI/CPI as single point estimates without accounting for underlying variances, missing important statistical information.
- Forecasts of future performance using current EV techniques are linear, non-risk adjusted projections that ignore the statistical nature of past performance data.
- Statistical time series analysis of past performance data from the Central Repository can provide probabilistic forecasts with confidence intervals, increasing the probability of project success.
- All project activities have natural uncertainties that impact the probability of cost, schedule and technical performance. Understanding these statistical behaviors is crucial for credible forecast
Senstivity Analysis of Project Scheduling using Fuzzy Set TheoryIRJET Journal
This document discusses using fuzzy set theory to analyze delays in construction project scheduling. It presents fuzzy logic as an approach to estimate delays using linguistic values for factors like weather (good, medium, bad) and labor experience (high, medium, low). These membership values can help determine the total effect on project duration from different reasons. This technique allows understanding total delay through critical path method and program evaluation review technique. The main advantage is this approach can be implemented in existing computer programs for project scheduling to consider delays from external factors.
Earned Value Management (EVM) is a technique
that forecasts the project giving an early warning of cost &
schedule. It not onely measures the project performance but also
measure the progress of the schedule. It is an effective tool to
measure cost, schedule & performance of the project. The EVA is
useful in various fields such as IT, Industries and Construction
companies etc.
The value of Earned Value Analysis (EVA) is dependent on
two key areas i.e. Precise Cost information and pragmatic
progress of project. If these two key areas are efficient then
benefit of the project will definitely get valued. This paper
summarizes the evolution, basic terminologies of Earned value
Analysis and effective use of it in the construction industries by
MS Project. There are many ways to implement EVA in the
construction project. MS Project is a tool to determine the EV
and its parameters in an efficient way with accuracy and within
time constraints.
Making decision in the presence of uncertainty requires estimating the impact of the outcome of those decisions. Here;s a collection of resources can can be used to guide that process
Forecasting cost and schedule performanceGlen Alleman
For credible decisions to be made, we need confidence intervals on all the numbers we use to make decisions.
These confidence intervals come from the underlying statistics and the related probabilities.
Statistical forecasting, using time series analysis of past performance, is mandatory for any credible discussion of project performance in the future.
IRJET-Survey on Effects of Productivity of Equipment in Construction ProjectsIRJET Journal
This document summarizes a study on the effects of equipment productivity in construction projects. The study aimed to identify key factors influencing equipment productivity and their impacts on projects. A literature review identified six main effects: cost overrun, delay, disputes, loss of equipment productivity, equipment accidents, and work suspensions. Questionnaires were distributed to construction professionals who rated each effect. The relative importance index method was used to analyze the data and rank the effects. Delay was found to be the most important effect, followed by cost overrun and disputes. The findings provide insight into improving equipment productivity and minimizing impacts on construction projects.
Schedule feasibility refers to the likelihood that a project can be completed within its planned timeframe. It is important because it ensures a project is finished before becoming obsolete or unnecessary. Schedule feasibility can be calculated using operations research methods and shown through Gantt and PERT charts, which display the probability of meeting deadlines.
Project appraisal involves a critical examination of all aspects of a proposed project to analyze prospective costs and benefits and determine if committing resources is desirable. It is carried out through internal and external appraisal and considers social, economic, environmental, financial, administrative, commercial, and technical aspects. The appraisal process involves preliminary steps like reviewing documents for completeness and accuracy before analyzing aspects in detail to evaluate a project's viability.
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...IRJET Journal
This document discusses controlling and monitoring construction projects using the earned value method. It begins with an introduction to the importance of controlling and monitoring construction projects. It then discusses the methodology of earned value analysis, including defining earned value, variances, and the five steps to set up an earned value system and four steps to use the information generated. Key aspects of earned value discussed include using it as a uniform measure of project progress, its role in cost performance analysis, and how it is calculated based on planned value, earned value, and actual costs.
IRJET- Portfolio Management of Multiple Building Projects using EPPMIRJET Journal
This document discusses portfolio management of multiple building construction projects using Primavera EPPM P6v16.1 software. It analyzes 4 commercial building projects, calculating quantities and scheduling activities. The projects were planned, scheduled and baseline budgets created in Primavera P6. A portfolio of the projects was then prepared to evaluate cash flow, optimize resource use, reduce warehousing and administrative costs. Prior research on using Primavera P6 for project planning, scheduling and monitoring is also reviewed. The objective is to develop the project portfolio and analyze cash flow using the Primavera software.
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...IRJET Journal
This document discusses planning, scheduling, and allocating resources for a multi-storied residential building project using Oracle's Primavera P6 software. It begins with an abstract that outlines the importance of project management tools in the growing construction industry. It then provides background on project management, planning, scheduling, and the benefits of Primavera P6, which include quick scheduling, identifying floats and critical paths, customizable reports, and resource allocation. The document aims to demonstrate the advantages of using Primavera P6 for construction project management.
Activity schedule and affective control of component based projecteSAT Journals
Abstract Abstract The overall performance of any organizations depends on the way the project is managed and scheduled. The successful implementation of one or two big or complex project does not indicate that this organization will perform In the same way in future. Component based implementation of software development projects in the automotive industry have to face the rapid strategies for the use of the latest technologies that would provide the success of this type of projects, namely the frequency of change requirements during the life cycle. The cost and time for software testing was analyzed and to avoid delays in the project and more to cope with disturbances caused by changing requirements in the each phase of the project life cycle. Using of Component Based Software Engineering(CBSE) in software company, the implementation of any software project has become easy but the integration of available component or their use is the not only skill of project manager but the delivery of project in time is a required.. The project manager ensure the success of their project as a competitive advantage and establish such a system which will work with limited resources and available time. The project management tools and techniques i.e. Critical Path Methods(CPM) or Program Evaluation and Review Techniques (PERT) are used in reality as the most valuable and are planned to be used in the component based software testing system. This research result point out that there is a huge difference between planned and unplanned testing project. It also shows that the time of testing can be reduced with increase of cost of failure as a result the company may decide the benefit from that project. Analysis of the results allows to determine dependencies between level of company’s maturity level in project management, used project management tools and techniques, and values gained by the company from project management time to time with measured risk factor. Key Words: K Component Base Software Engineering(CBSE), CPM, PERT, Project life cycle, planned or unplanned project
12 Terms You Should Know | Project Management Fundamentals
12 key terms that we think everyone should know (from beginners to experts)
12 key project management terms that she thinks everyone involved with projects should know. No longer get confused when confronted with unfamiliar terms
#projectmanagement #terms #tips #Tamdeed
The document discusses Project Evaluation Review Technique (PERT), a project management tool used to analyze tasks, time required, and critical paths. It describes various project management methodologies like PRINCE2, Agile, and Critical Path Method (CPM) that are suited for different types of projects. Finally, it discusses setting up an organizational structure and quality management process for a project.
The role of time, cost and quality in project managementIRJET Journal
This document discusses the roles of time, cost, and quality in project management. It states that these three factors are interrelated and impact each other, making it difficult for project managers to balance them. The document reviews literature that analyzed how planning, monitoring, and controlling impact the timely completion of construction projects. It also discusses how tools like Microsoft Project and Primavera P6 can help optimize schedules, budgets, and quality. Overall, the document examines the relationships between time, cost, and quality in project management and how effectively managing these key factors is important for project success.
This document discusses delay analysis in construction projects. It defines delay as exceeding the planned completion date of a project. Delay can increase costs and negatively impact other tasks. Project management software like Microsoft Project can help track task start and end dates to analyze causes of delay. The document outlines objectives of project management, including completing projects on time and on budget. It also discusses using tools like time sheets for time management and tracking costs. Quality management and risk management are also important aspects of ensuring project success. Overall, the key is properly planning, scheduling, and monitoring tasks to minimize delays.
Harvard University Theories Tools and Techiques in Project Managagement Prese...write4
1. The document discusses several tools and techniques used in project management including Maylor's 4Ds framework, Gantt charts, critical path analysis, risk analysis, and Prince2 methodology.
2. Maylor's 4Ds involves defining a project, designing how to achieve its objectives, doing the required work, and delivering the final results. Gantt charts visually map out tasks and timelines while critical path analysis identifies the longest path of tasks.
3. Risk analysis evaluates potential risks through assessing likelihood and impact, and Prince2 provides a standardized approach with defined stages, controls, and products. The document compares these different project management methods.
Harvard University Theories Tools and Techiques in Project Managagement Prese...write31
1. The document discusses several tools and techniques used in project management including Maylor's 4Ds framework, Gantt charts, critical path analysis, risk analysis, and Prince2 methodology.
2. Maylor's 4Ds involves defining a project, designing how to achieve its objectives, doing the required work, and delivering the final results. Gantt charts visually map out tasks and timelines while critical path analysis identifies the longest path of tasks.
3. Risk analysis evaluates potential risks through assessing likelihood and impact, and Prince2 provides a standardized approach with defined stages, controls, and products. The document compares these different project management methods.
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...IRJET Journal
This document discusses using earned value analysis (EVA) to analyze the cost of a road construction project in India. It provides background on the importance of transportation infrastructure and project management principles like time and cost control. The document then describes EVA concepts like planned value, earned value, and actual cost. It outlines the objectives and methodology of analyzing an industrial road construction project as a case study using the Primavera P6 scheduling software to calculate EVA parameters and determine if the project is on time and on budget. Finally, it reviews related literature on using EVA and project management software for construction cost analysis and monitoring.
Efficient Indicators to Evaluate the Status of Software Development Effort Es...IJMIT JOURNAL
Development effort is an undeniable part of the project management which considerably influences the
success of project. Inaccurate and unreliable estimation of effort can easily lead to the failure of project.
Due to the special specifications, accurate estimation of effort in the software projects is a vital
management activity that must be carefully done to avoid from the unforeseen results. However numerous
effort estimation methods have been proposed in this field, the accuracy of estimates is not satisfying and
the attempts continue to improve the performance of estimation methods. Prior researches conducted in
this area have focused on numerical and quantitative approaches and there are a few research works that
investigate the root problems and issues behind the inaccurate effort estimation of software development
effort. In this paper, a framework is proposed to evaluate and investigate the situation of an organization in
terms of effort estimation. The proposed framework includes various indicators which cover the critical
issues in field of software development effort estimation. Since the capabilities and shortages of
organizations for effort estimation are not the same, the proposed indicators can lead to have a systematic
approach in which the strengths and weaknesses of organizations in field of effort estimation are
discovered
Assessment of Project Monitoring and Control Techniques in Ondo State Agency ...Dr. Amarjeet Singh
The document discusses project monitoring and control techniques used by Ondo State Agency for Road Maintenance and Construction (OSARMCO) in Nigeria. It found that OSARMCO primarily uses Program Evaluation and Review Technique (PERT) for time/schedule control. Survey respondents agreed that PERT is effective at identifying critical project activities and monitoring planned vs. actual progress. They also agreed it is effective and reliable for meeting set project delivery dates. The study concluded PERT and other monitoring techniques help OSARMCO meet project objectives when used for cost and schedule control.
Impact assessment of factors affecting information technology projects in riv...eSAT Publishing House
IJRET : International Journal of Research in Engineering and Technology is an international peer reviewed, online journal published by eSAT Publishing House for the enhancement of research in various disciplines of Engineering and Technology. The aim and scope of the journal is to provide an academic medium and an important reference for the advancement and dissemination of research results that support high-level learning, teaching and research in the fields of Engineering and Technology. We bring together Scientists, Academician, Field Engineers, Scholars and Students of related fields of Engineering and Technology
This document discusses planning and scheduling a residential construction project using Primavera project management software. It begins with an introduction to project management challenges in the construction industry like delays and cost overruns. The methodology section outlines the steps taken: studying the site, creating an actual schedule in Primavera, identifying constraints, reducing constraints, and optimizing labor resources. Two modified schedules are presented that interconnect activities properly and increase resources to reduce the project duration by 5-7 months compared to the actual schedule. The results analyze schedule improvements and reduced costs. It concludes that Primavera helps manage work, reduce risks, and ensure successful project completion on time and within budget.
This document discusses project planning and scheduling. It begins by defining project planning as breaking down a project into definable tasks, establishing logical relationships between tasks, and estimating resources, time and costs required. The document then discusses several key aspects of project planning and scheduling including work breakdown structures, network diagrams, critical path analysis and scheduling techniques. It also discusses factors that affect project scheduling such as time, manpower and materials. The document concludes by emphasizing the importance of planning for successfully completing projects on time and within budget while meeting quality requirements.
This document provides an overview of project management. It defines what a project is, common project terms, and what project management entails. It describes the typical roles and responsibilities of a project manager. It then outlines the standard steps in project management, including initiation, planning, executing, monitoring and controlling, and closing. It discusses why projects fail and how to measure project success. Finally, it notes some common project constraints.
This document discusses the importance of monitoring and evaluation in ensuring successful project completion. It defines monitoring as assessing progress against plans and evaluation as analyzing project effects and impact. The document outlines key roles of monitoring and evaluation such as identifying issues, facilitating decision making, and assessing goals. It also discusses challenges like overreliance on external consultants and not incorporating lessons learned. The document emphasizes that monitoring and evaluation are important project management tools that should be applied appropriately to improve outcomes.
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...IRJET Journal
This document discusses planning and scheduling a residential construction project using Microsoft Project. It summarizes the key steps:
1) The activities of constructing two residential blocks were planned and scheduled in MSP, including allocating resources, determining task relationships, and generating a Gantt chart.
2) The total baseline duration of the project was estimated to be 632 days with a total cost of Rs. 154,394,081.
3) Planning and scheduling the project in MSP allowed determining the critical path and monitoring project progress and costs.
IRJET- Identification of Constraints and there Impact on Construction Pro...IRJET Journal
This document discusses identifying constraints that impact construction project schedules. It begins with an abstract that outlines identifying major constraints using the Relative Importance Index (RII) method and analyzing their impact on project schedules using Microsoft Project software.
The document then describes the research methodology, which includes preparing questionnaires to identify constraints, conducting a survey, analyzing the results with RII to determine governing constraints, and rescheduling the project to assess impact of delays. A literature review is also provided on studying factors that cause delays and techniques for reducing constraints. The objectives are to schedule a building project, identify high-impact constraints with RII, and determine total project duration considering constraint impacts.
Similar to Earned Value Management for Design and Construction Project (20)
‘Six Sigma Technique’ A Journey Through its Implementationijtsrd
The manufacturing industries all over the world are facing tough challenges for growth, development and sustainability in today’s competitive environment. They have to achieve apex position by adapting with the global competitive environment by delivering goods and services at low cost, prime quality and better price to increase wealth and consumer satisfaction. Cost Management ensures profit, growth and sustainability of the business with implementation of Continuous Improvement Technique like Six Sigma. This leads to optimize Business performance. The method drives for customer satisfaction, low variation, reduction in waste and cycle time resulting into a competitive advantage over other industries which did not implement it. The main objective of this paper ‘Six Sigma Technique A Journey Through Its Implementation’ is to conceptualize the effectiveness of Six Sigma Technique through the journey of its implementation. Aditi Sunilkumar Ghosalkar "‘Six Sigma Technique’: A Journey Through its Implementation" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-8 | Issue-1 , February 2024, URL: https://www.ijtsrd.com/papers/ijtsrd64546.pdf Paper Url: https://www.ijtsrd.com/other-scientific-research-area/other/64546/‘six-sigma-technique’-a-journey-through-its-implementation/aditi-sunilkumar-ghosalkar
Edge Computing in Space Enhancing Data Processing and Communication for Space...ijtsrd
Edge computing, a paradigm that involves processing data closer to its source, has gained significant attention for its potential to revolutionize data processing and communication in space missions. With the increasing complexity and data volume generated by modern space missions, traditional centralized computing approaches face challenges related to latency, bandwidth, and security. Edge computing in space, involving on board processing and analysis of data, offers promising solutions to these challenges. This paper explores the concept of edge computing in space, its benefits, applications, and future prospects in enhancing space missions. Manish Verma "Edge Computing in Space: Enhancing Data Processing and Communication for Space Missions" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-8 | Issue-1 , February 2024, URL: https://www.ijtsrd.com/papers/ijtsrd64541.pdf Paper Url: https://www.ijtsrd.com/computer-science/artificial-intelligence/64541/edge-computing-in-space-enhancing-data-processing-and-communication-for-space-missions/manish-verma
Dynamics of Communal Politics in 21st Century India Challenges and Prospectsijtsrd
Communal politics in India has evolved through centuries, weaving a complex tapestry shaped by historical legacies, colonial influences, and contemporary socio political transformations. This research comprehensively examines the dynamics of communal politics in 21st century India, emphasizing its historical roots, socio political dynamics, economic implications, challenges, and prospects for mitigation. The historical perspective unravels the intricate interplay of religious identities and power dynamics from ancient civilizations to the impact of colonial rule, providing insights into the evolution of communalism. The socio political dynamics section delves into the contemporary manifestations, exploring the roles of identity politics, socio economic disparities, and globalization. The economic implications section highlights how communal politics intersects with economic issues, perpetuating disparities and influencing resource allocation. Challenges posed by communal politics are scrutinized, revealing multifaceted issues ranging from social fragmentation to threats against democratic values. The prospects for mitigation present a multifaceted approach, incorporating policy interventions, community engagement, and educational initiatives. The paper conducts a comparative analysis with international examples, identifying common patterns such as identity politics and economic disparities. It also examines unique challenges, emphasizing Indias diverse religious landscape, historical legacy, and secular framework. Lessons for effective strategies are drawn from international experiences, offering insights into inclusive policies, interfaith dialogue, media regulation, and global cooperation. By scrutinizing historical epochs, contemporary dynamics, economic implications, and international comparisons, this research provides a comprehensive understanding of communal politics in India. The proposed strategies for mitigation underscore the importance of a holistic approach to foster social harmony, inclusivity, and democratic values. Rose Hossain "Dynamics of Communal Politics in 21st Century India: Challenges and Prospects" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-8 | Issue-1 , February 2024, URL: https://www.ijtsrd.com/papers/ijtsrd64528.pdf Paper Url: https://www.ijtsrd.com/humanities-and-the-arts/history/64528/dynamics-of-communal-politics-in-21st-century-india-challenges-and-prospects/rose-hossain
Assess Perspective and Knowledge of Healthcare Providers Towards Elehealth in...ijtsrd
Background and Objective Telehealth has become a well known tool for the delivery of health care in Saudi Arabia, and the perspective and knowledge of healthcare providers are influential in the implementation, adoption and advancement of the method. This systematic review was conducted to examine the current literature base regarding telehealth and the related healthcare professional perspective and knowledge in the Kingdom of Saudi Arabia. Materials and Methods This systematic review was conducted by searching 7 databases including, MEDLINE, CINHAL, Web of Science, Scopus, PubMed, PsycINFO, and ProQuest Central. Studies on healthcare practitioners telehealth knowledge and perspectives published in English in Saudi Arabia from 2000 to 2023 were included. Boland directed this comprehensive review. The researchers examined each connected study using the AXIS tool, which evaluates cross sectional systematic reviews. Narrative synthesis was used to summarise and convey the data. Results Out of 1840 search results, 10 studies were included. Positive outlook and limited knowledge among providers were seen across trials. Healthcare professionals like telehealth for its ability to improve quality, access, and delivery, save time and money, and be successful. Age, gender, occupation, and work experience also affect health workers knowledge. In Saudi Arabia, healthcare professionals face inadequate expert assistance, patient privacy, internet connection concerns, lack of training courses, lack of telehealth understanding, and high costs while performing telemedicine. Conclusions Healthcare practitioners telehealth perceptions and knowledge were examined in this systematic study. Its collection of concerned experts different personal attitudes and expertise would help enhance telehealths implementation in Saudi Arabia, develop its healthcare delivery alternative, and eliminate frequent problems. Badriah Mousa I Mulayhi | Dr. Jomin George | Judy Jenkins "Assess Perspective and Knowledge of Healthcare Providers Towards Elehealth in Saudi Arabia: A Systematic Review" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-8 | Issue-1 , February 2024, URL: https://www.ijtsrd.com/papers/ijtsrd64535.pdf Paper Url: https://www.ijtsrd.com/medicine/other/64535/assess-perspective-and-knowledge-of-healthcare-providers-towards-elehealth-in-saudi-arabia-a-systematic-review/badriah-mousa-i-mulayhi
The Impact of Digital Media on the Decentralization of Power and the Erosion ...ijtsrd
The impact of digital media on the distribution of power and the weakening of traditional gatekeepers has gained considerable attention in recent years. The adoption of digital technologies and the internet has resulted in declining influence and power for traditional gatekeepers such as publishing houses and news organizations. Simultaneously, digital media has facilitated the emergence of new voices and players in the media industry. Digital medias impact on power decentralization and gatekeeper erosion is visible in several ways. One significant aspect is the democratization of information, which enables anyone with an internet connection to publish and share content globally, leading to citizen journalism and bypassing traditional gatekeepers. Another aspect is the disruption of conventional media industry business models, as traditional organizations struggle to adjust to the decrease in advertising revenue and the rise of digital platforms. Alternative business models, such as subscription models and crowdfunding, have become more prevalent, leading to the emergence of new players. Overall, the impact of digital media on the distribution of power and the weakening of traditional gatekeepers has brought about significant changes in the media landscape and the way information is shared. Further research is required to fully comprehend the implications of these changes and their impact on society. Dr. Kusum Lata "The Impact of Digital Media on the Decentralization of Power and the Erosion of Traditional Gatekeepers" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-8 | Issue-1 , February 2024, URL: https://www.ijtsrd.com/papers/ijtsrd64544.pdf Paper Url: https://www.ijtsrd.com/humanities-and-the-arts/political-science/64544/the-impact-of-digital-media-on-the-decentralization-of-power-and-the-erosion-of-traditional-gatekeepers/dr-kusum-lata
Online Voices, Offline Impact Ambedkars Ideals and Socio Political Inclusion ...ijtsrd
This research investigates the nexus between online discussions on Dr. B.R. Ambedkars ideals and their impact on social inclusion among college students in Gurugram, Haryana. Surveying 240 students from 12 government colleges, findings indicate that 65 actively engage in online discussions, with 80 demonstrating moderate to high awareness of Ambedkars ideals. Statistically significant correlations reveal that higher online engagement correlates with increased awareness p 0.05 and perceived social inclusion. Variations across colleges and a notable effect of college type on perceived social inclusion highlight the influence of contextual factors. Furthermore, the intersectional analysis underscores nuanced differences based on gender, caste, and socio economic status. Dr. Kusum Lata "Online Voices, Offline Impact: Ambedkar's Ideals and Socio-Political Inclusion - A Study of Gurugram District" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-8 | Issue-1 , February 2024, URL: https://www.ijtsrd.com/papers/ijtsrd64543.pdf Paper Url: https://www.ijtsrd.com/humanities-and-the-arts/political-science/64543/online-voices-offline-impact-ambedkars-ideals-and-sociopolitical-inclusion--a-study-of-gurugram-district/dr-kusum-lata
Problems and Challenges of Agro Entreprenurship A Studyijtsrd
Noting calls for contextualizing Agro entrepreneurs problems and challenges of the agro entrepreneurs and for greater attention to the Role of entrepreneurs in agro entrepreneurship research, we conduct a systematic literature review of extent research in agriculture entrepreneurship to overcome the study objectives of complications of agro entrepreneurs through various factors, Development of agriculture products is a key factor for the overall economic growth of agro entrepreneurs Agro Entrepreneurs produces firsthand large scale employment, utilizes the labor and natural resources, This research outlines the problems of Weather and Soil Erosions, Market price fluctuation, stimulates labor cost problems, reduces concentration of Price volatility, Dependency on Intermediaries, induces Limited Bargaining Power, and Storage and Transportation Costs. This paper mainly devoted to highlight Problems and challenges faced for the sustainable of Agro Entrepreneurs in India. Vinay Prasad B "Problems and Challenges of Agro Entreprenurship - A Study" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-8 | Issue-1 , February 2024, URL: https://www.ijtsrd.com/papers/ijtsrd64540.pdf Paper Url: https://www.ijtsrd.com/other-scientific-research-area/other/64540/problems-and-challenges-of-agro-entreprenurship--a-study/vinay-prasad-b
Comparative Analysis of Total Corporate Disclosure of Selected IT Companies o...ijtsrd
Disclosure is a process through which a business enterprise communicates with external parties. A corporate disclosure is communication of financial and non financial information of the activities of a business enterprise to the interested entities. Corporate disclosure is done through publishing annual reports. So corporate disclosure through annual reports plays a vital role in the life of all the companies and provides valuable information to investors. The basic objectives of corporate disclosure is to give a true and fair view of companies to the parties related either directly or indirectly like owner, government, creditors, shareholders etc. in the companies act, provisions have been made about mandatory and voluntary disclosure. The IT sector in India is rapidly growing, the trend to invest in the IT sector is rising and employment opportunities in IT sectors are also increasing. Therefore the IT sector is expected to have fair, full and adequate disclosure of all information. Unfair and incomplete disclosure may adversely affect the entire economy. A research study on disclosure practices of IT companies could play an important role in this regard. Hence, the present research study has been done to study and review comparative analysis of total corporate disclosure of selected IT companies of India and to put forward overall findings and suggestions with a view to increase disclosure score of these companies. The researcher hopes that the present research study will be helpful to all selected Companies for improving level of corporate disclosure through annual reports as well as the government, creditors, investors, all business organizations and upcoming researcher for comparative analyses of level of corporate disclosure with special reference to selected IT companies. Dr. Vaibhavi D. Thaker "Comparative Analysis of Total Corporate Disclosure of Selected IT Companies of India" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-8 | Issue-1 , February 2024, URL: https://www.ijtsrd.com/papers/ijtsrd64539.pdf Paper Url: https://www.ijtsrd.com/other-scientific-research-area/other/64539/comparative-analysis-of-total-corporate-disclosure-of-selected-it-companies-of-india/dr-vaibhavi-d-thaker
The Impact of Educational Background and Professional Training on Human Right...ijtsrd
This study investigated the impact of educational background and professional training on human rights awareness among secondary school teachers in the Marathwada region of Maharashtra, India. The key findings reveal that higher levels of education, particularly a master’s degree, and fields of study related to education, humanities, or social sciences are associated with greater human rights awareness among teachers. Additionally, both pre service teacher training and in service professional development programs focused on human rights education significantly enhance teacher’s knowledge, skills, and competencies in promoting human rights principles in their classrooms. Baig Ameer Bee Mirza Abdul Aziz | Dr. Syed Azaz Ali Amjad Ali "The Impact of Educational Background and Professional Training on Human Rights Awareness among Secondary School Teachers" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-8 | Issue-1 , February 2024, URL: https://www.ijtsrd.com/papers/ijtsrd64529.pdf Paper Url: https://www.ijtsrd.com/humanities-and-the-arts/education/64529/the-impact-of-educational-background-and-professional-training-on-human-rights-awareness-among-secondary-school-teachers/baig-ameer-bee-mirza-abdul-aziz
A Study on the Effective Teaching Learning Process in English Curriculum at t...ijtsrd
“One Language sets you in a corridor for life. Two languages open every door along the way” Frank Smith English as a foreign language or as a second language has been ruling in India since the period of Lord Macaulay. But the question is how much we teach or learn English properly in our culture. Is there any scope to use English as a language rather than a subject How much we learn or teach English without any interference of mother language specially in the classroom teaching learning scenario in West Bengal By considering all these issues the researcher has attempted in this article to focus on the effective teaching learning process comparing to other traditional strategies in the field of English curriculum at the secondary level to investigate whether they fulfill the present teaching learning requirements or not by examining the validity of the present curriculum of English. The purpose of this study is to focus on the effectiveness of the systematic, scientific, sequential and logical transaction of the course between the teachers and the learners in the perspective of the 5Es programme that is engage, explore, explain, extend and evaluate. Sanchali Mondal | Santinath Sarkar "A Study on the Effective Teaching Learning Process in English Curriculum at the Secondary Level of West Bengal" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-8 | Issue-1 , February 2024, URL: https://www.ijtsrd.com/papers/ijtsrd62412.pdf Paper Url: https://www.ijtsrd.com/humanities-and-the-arts/education/62412/a-study-on-the-effective-teaching-learning-process-in-english-curriculum-at-the-secondary-level-of-west-bengal/sanchali-mondal
The Role of Mentoring and Its Influence on the Effectiveness of the Teaching ...ijtsrd
This paper reports on a study which was conducted to investigate the role of mentoring and its influence on the effectiveness of the teaching of Physics in secondary schools in the South West Region of Cameroon. The study adopted the convergent parallel mixed methods design, focusing on respondents in secondary schools in the South West Region of Cameroon. Both quantitative and qualitative data were collected, analysed separately, and the results were compared to see if the findings confirm or disconfirm each other. The quantitative analysis found that majority of the respondents 72 of Physics teachers affirmed that they had more experienced colleagues as mentors to help build their confidence, improve their teaching, and help them improve their effectiveness and efficiency in guiding learners’ achievements. Only 28 of the respondents disagreed with these statements. With majority respondents 72 agreeing with the statements, it implies that in most secondary schools, experienced Physics teachers act as mentors to build teachers’ confidence in teaching and improving students’ learning. The interview qualitative data analysis summarized how secondary school Principals use meetings with mentors and mentees to promote mentorship in the school milieu. This has helped strengthen teachers’ classroom practices in secondary schools in the South West Region of Cameroon. With the results confirming each other, the study recommends that mentoring should focus on helping teachers employ social interactions and instructional practices feedback and clarity in teaching that have direct measurable impact on students’ learning achievements. Andrew Ngeim Sumba | Frederick Ebot Ashu | Peter Agborbechem Tambi "The Role of Mentoring and Its Influence on the Effectiveness of the Teaching of Physics in Secondary Schools in the South West Region of Cameroon" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-8 | Issue-1 , February 2024, URL: https://www.ijtsrd.com/papers/ijtsrd64524.pdf Paper Url: https://www.ijtsrd.com/management/management-development/64524/the-role-of-mentoring-and-its-influence-on-the-effectiveness-of-the-teaching-of-physics-in-secondary-schools-in-the-south-west-region-of-cameroon/andrew-ngeim-sumba
Design Simulation and Hardware Construction of an Arduino Microcontroller Bas...ijtsrd
This study primarily focuses on the design of a high side buck converter using an Arduino microcontroller. The converter is specifically intended for use in DC DC applications, particularly in standalone solar PV systems where the PV output voltage exceeds the load or battery voltage. To evaluate the performance of the converter, simulation experiments are conducted using Proteus Software. These simulations provide insights into the input and output voltages, currents, powers, and efficiency under different state of charge SoC conditions of a 12V,70Ah rechargeable lead acid battery. Additionally, the hardware design of the converter is implemented, and practical data is collected through operation, monitoring, and recording. By comparing the simulation results with the practical results, the efficiency and performance of the designed converter are assessed. The findings indicate that while the buck converter is suitable for practical use in standalone PV systems, its efficiency is compromised due to a lower output current. Chan Myae Aung | Dr. Ei Mon "Design Simulation and Hardware Construction of an Arduino-Microcontroller Based DC-DC High-Side Buck Converter for Standalone PV System" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-8 | Issue-1 , February 2024, URL: https://www.ijtsrd.com/papers/ijtsrd64518.pdf Paper Url: https://www.ijtsrd.com/engineering/mechanical-engineering/64518/design-simulation-and-hardware-construction-of-an-arduinomicrocontroller-based-dcdc-highside-buck-converter-for-standalone-pv-system/chan-myae-aung
Sustainable Energy by Paul A. Adekunte | Matthew N. O. Sadiku | Janet O. Sadikuijtsrd
Energy becomes sustainable if it meets the needs of the present without compromising the ability of future generations to meet their own needs. Some of the definitions of sustainable energy include the considerations of environmental aspects such as greenhouse gas emissions, social, and economic aspects such as energy poverty. Generally far more sustainable than fossil fuel are renewable energy sources such as wind, hydroelectric power, solar, and geothermal energy sources. Worthy of note is that some renewable energy projects, like the clearing of forests to produce biofuels, can cause severe environmental damage. The sustainability of nuclear power which is a low carbon source is highly debated because of concerns about radioactive waste, nuclear proliferation, and accidents. The switching from coal to natural gas has environmental benefits, including a lower climate impact, but could lead to delay in switching to more sustainable options. “Carbon capture and storage” can be built into power plants to remove the carbon dioxide CO2 emissions, but this technology is expensive and has rarely been implemented. Leading non renewable energy sources around the world is fossil fuels, coal, petroleum, and natural gas. Nuclear energy is usually considered another non renewable energy source, although nuclear energy itself is a renewable energy source, but the material used in nuclear power plants is not. The paper addresses the issue of sustainable energy, its attendant benefits to the future generation, and humanity in general. Paul A. Adekunte | Matthew N. O. Sadiku | Janet O. Sadiku "Sustainable Energy" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-8 | Issue-1 , February 2024, URL: https://www.ijtsrd.com/papers/ijtsrd64534.pdf Paper Url: https://www.ijtsrd.com/engineering/electrical-engineering/64534/sustainable-energy/paul-a-adekunte
Concepts for Sudan Survey Act Implementations Executive Regulations and Stand...ijtsrd
This paper aims to outline the executive regulations, survey standards, and specifications required for the implementation of the Sudan Survey Act, and for regulating and organizing all surveying work activities in Sudan. The act has been discussed for more than 5 years. The Land Survey Act was initiated by the Sudan Survey Authority and all official legislations were headed by the Sudan Ministry of Justice till it was issued in 2022. The paper presents conceptual guidelines to be used for the Survey Act implementation and to regulate the survey work practice, standardizing the field surveys, processing, quality control, procedures, and the processes related to survey work carried out by the stakeholders and relevant authorities in Sudan. The conceptual guidelines are meant to improve the quality and harmonization of geospatial data and to aid decision making processes as well as geospatial information systems. The established comprehensive executive regulations will govern and regulate the implementation of the Sudan Survey Geomatics Act in all surveying and mapping practices undertaken by the Sudan Survey Authority SSA and state local survey departments for public or private sector organizations. The targeted standards and specifications include the reference frame, projection, coordinate systems, and the guidelines and specifications that must be followed in the field of survey work, processes, and mapping products. In the last few decades, there has been a growing awareness of the importance of geomatics activities and measurements on the Earths surface in space and time, together with observing and mapping the changes. In such cases, data must be captured promptly, standardized, and obtained with more accuracy and specified in much detail. The paper will also highlight the current situation in Sudan, the degree to which survey standards are used, the problems encountered, and the errors that arise from not using the standards and survey specifications. Kamal A. A. Sami "Concepts for Sudan Survey Act Implementations - Executive Regulations and Standards" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-8 | Issue-1 , February 2024, URL: https://www.ijtsrd.com/papers/ijtsrd63484.pdf Paper Url: https://www.ijtsrd.com/engineering/civil-engineering/63484/concepts-for-sudan-survey-act-implementations--executive-regulations-and-standards/kamal-a-a-sami
Towards the Implementation of the Sudan Interpolated Geoid Model Khartoum Sta...ijtsrd
The discussions between ellipsoid and geoid have invoked many researchers during the recent decades, especially during the GNSS technology era, which had witnessed a great deal of development but still geoid undulation requires more investigations. To figure out a solution for Sudans local geoid, this research has tried to intake the possibility of determining the geoid model by following two approaches, gravimetric and geometrical geoid model determination, by making use of GNSS leveling benchmarks at Khartoum state. The Benchmarks are well distributed in the study area, in which, the horizontal coordinates and the height above the ellipsoid have been observed by GNSS while orthometric heights were carried out using precise leveling. The Global Geopotential Model GGM represented in EGM2008 has been exploited to figure out the geoid undulation at the benchmarks in the study area. This is followed by a fitting process, that has been done to suit the geoid undulation data which has been computed using GNSS leveling data and geoid undulation inspired by the EGM2008. Two geoid surfaces were created after the fitting process to ensure that they are identical and both of them could be counted for getting the same geoid undulation with an acceptable accuracy. In this respect, statistical operation played an important role in ensuring the consistency and integrity of the model by applying cross validation techniques splitting the data into training and testing datasets for building the geoid model and testing its eligibility. The geometrical solution for geoid undulation computation has been utilized by applying straightforward equations that facilitate the calculation of the geoid undulation directly through applying statistical techniques for the GNSS leveling data of the study area to get the common equation parameters values that could be utilized to calculate geoid undulation of any position in the study area within the claimed accuracy. Both systems were checked and proved eligible to be used within the study area with acceptable accuracy which may contribute to solving the geoid undulation problem in the Khartoum area, and be further generalized to determine the geoid model over the entire country, and this could be considered in the future, for regional and continental geoid model. Ahmed M. A. Mohammed. | Kamal A. A. Sami "Towards the Implementation of the Sudan Interpolated Geoid Model (Khartoum State Case Study)" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-8 | Issue-1 , February 2024, URL: https://www.ijtsrd.com/papers/ijtsrd63483.pdf Paper Url: https://www.ijtsrd.com/engineering/civil-engineering/63483/towards-the-implementation-of-the-sudan-interpolated-geoid-model-khartoum-state-case-study/ahmed-m-a-mohammed
Activating Geospatial Information for Sudans Sustainable Investment Mapijtsrd
Sudan is witnessing an acceleration in the processes of development and transformation in the performance of government institutions to raise the productivity and investment efficiency of the government sector. The development plans and investment opportunities have focused on achieving national goals in various sectors. This paper aims to illuminate the path to the future and provide geospatial data and information to develop the investment climate and environment for all sized businesses, and to bridge the development gap between the Sudan states. The Sudan Survey Authority SSA is the main advisor to the Sudan Government in conducting surveying, mappings, designing, and developing systems related to geospatial data and information. In recent years, SSA made a strategic partnership with the Ministry of Investment to activate Geospatial Information for Sudans Sustainable Investment and in particular, for the preparation and implementation of the Sudan investment map, based on the directives and objectives of the Ministry of Investment MI in Sudan. This paper comes within the framework of activating the efforts of the Ministry of Investment to develop technical investment services by applying techniques adopted by the Ministry and its strategic partners for advancing investment processes in the country. Kamal A. A. Sami "Activating Geospatial Information for Sudan's Sustainable Investment Map" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-8 | Issue-1 , February 2024, URL: https://www.ijtsrd.com/papers/ijtsrd63482.pdf Paper Url: https://www.ijtsrd.com/engineering/information-technology/63482/activating-geospatial-information-for-sudans-sustainable-investment-map/kamal-a-a-sami
Educational Unity Embracing Diversity for a Stronger Societyijtsrd
In a rapidly changing global landscape, the importance of education as a unifying force cannot be overstated. This paper explores the crucial role of educational unity in fostering a stronger and more inclusive society through the embrace of diversity. By examining the benefits of diverse learning environments, the paper aims to highlight the positive impact on societal strength. The discussion encompasses various dimensions, from curriculum design to classroom dynamics, and emphasizes the need for educational institutions to become catalysts for unity in diversity. It highlights the need for a paradigm shift in educational policies, curricula, and pedagogical approaches to ensure that they are reflective of the diverse fabric of society. This paper also addresses the challenges associated with implementing inclusive educational practices and offers practical strategies for overcoming barriers. It advocates for collaborative efforts between educational institutions, policymakers, and communities to create a supportive ecosystem that promotes diversity and unity. Mr. Amit Adhikari | Madhumita Teli | Gopal Adhikari "Educational Unity: Embracing Diversity for a Stronger Society" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-8 | Issue-1 , February 2024, URL: https://www.ijtsrd.com/papers/ijtsrd64525.pdf Paper Url: https://www.ijtsrd.com/humanities-and-the-arts/education/64525/educational-unity-embracing-diversity-for-a-stronger-society/mr-amit-adhikari
Integration of Indian Indigenous Knowledge System in Management Prospects and...ijtsrd
The diversity of indigenous knowledge systems in India is vast and can vary significantly between different communities and regions. Preserving and respecting these knowledge systems is crucial for maintaining cultural heritage, promoting sustainable practices, and fostering cross cultural understanding. In this paper, an overview of the prospects and challenges associated with incorporating Indian indigenous knowledge into management is explored. It is found that IIKS helps in management in many areas like sustainable development, tourism, food security, natural resource management, cultural preservation and innovation, etc. However, IIKS integration with management faces some challenges in the form of a lack of documentation, cultural sensitivity, language barriers legal framework, etc. Savita Lathwal "Integration of Indian Indigenous Knowledge System in Management: Prospects and Challenges" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-8 | Issue-1 , February 2024, URL: https://www.ijtsrd.com/papers/ijtsrd63500.pdf Paper Url: https://www.ijtsrd.com/management/accounting-and-finance/63500/integration-of-indian-indigenous-knowledge-system-in-management-prospects-and-challenges/savita-lathwal
DeepMask Transforming Face Mask Identification for Better Pandemic Control in...ijtsrd
The COVID 19 pandemic has highlighted the crucial need of preventive measures, with widespread use of face masks being a key method for slowing the viruss spread. This research investigates face mask identification using deep learning as a technological solution to be reducing the risk of coronavirus transmission. The proposed method uses state of the art convolutional neural networks CNNs and transfer learning to automatically recognize persons who are not wearing masks in a variety of circumstances. We discuss how this strategy improves public health and safety by providing an efficient manner of enforcing mask wearing standards. The report also discusses the obstacles, ethical concerns, and prospective applications of face mask detection systems in the ongoing fight against the pandemic. Dilip Kumar Sharma | Aaditya Yadav "DeepMask: Transforming Face Mask Identification for Better Pandemic Control in the COVID-19 Era" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-8 | Issue-1 , February 2024, URL: https://www.ijtsrd.com/papers/ijtsrd64522.pdf Paper Url: https://www.ijtsrd.com/engineering/electronics-and-communication-engineering/64522/deepmask-transforming-face-mask-identification-for-better-pandemic-control-in-the-covid19-era/dilip-kumar-sharma
Streamlining Data Collection eCRF Design and Machine Learningijtsrd
Efficient and accurate data collection is paramount in clinical trials, and the design of Electronic Case Report Forms eCRFs plays a pivotal role in streamlining this process. This paper explores the integration of machine learning techniques in the design and implementation of eCRFs to enhance data collection efficiency. We delve into the synergies between eCRF design principles and machine learning algorithms, aiming to optimize data quality, reduce errors, and expedite the overall data collection process. The application of machine learning in eCRF design brings forth innovative approaches to data validation, anomaly detection, and real time adaptability. This paper discusses the benefits, challenges, and future prospects of leveraging machine learning in eCRF design for streamlined and advanced data collection in clinical trials. Dhanalakshmi D | Vijaya Lakshmi Kannareddy "Streamlining Data Collection: eCRF Design and Machine Learning" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-8 | Issue-1 , February 2024, URL: https://www.ijtsrd.com/papers/ijtsrd63515.pdf Paper Url: https://www.ijtsrd.com/biological-science/biotechnology/63515/streamlining-data-collection-ecrf-design-and-machine-learning/dhanalakshmi-d
How to Manage Your Lost Opportunities in Odoo 17 CRMCeline George
Odoo 17 CRM allows us to track why we lose sales opportunities with "Lost Reasons." This helps analyze our sales process and identify areas for improvement. Here's how to configure lost reasons in Odoo 17 CRM
This presentation includes basic of PCOS their pathology and treatment and also Ayurveda correlation of PCOS and Ayurvedic line of treatment mentioned in classics.
How to Fix the Import Error in the Odoo 17Celine George
An import error occurs when a program fails to import a module or library, disrupting its execution. In languages like Python, this issue arises when the specified module cannot be found or accessed, hindering the program's functionality. Resolving import errors is crucial for maintaining smooth software operation and uninterrupted development processes.
This document provides an overview of wound healing, its functions, stages, mechanisms, factors affecting it, and complications.
A wound is a break in the integrity of the skin or tissues, which may be associated with disruption of the structure and function.
Healing is the body’s response to injury in an attempt to restore normal structure and functions.
Healing can occur in two ways: Regeneration and Repair
There are 4 phases of wound healing: hemostasis, inflammation, proliferation, and remodeling. This document also describes the mechanism of wound healing. Factors that affect healing include infection, uncontrolled diabetes, poor nutrition, age, anemia, the presence of foreign bodies, etc.
Complications of wound healing like infection, hyperpigmentation of scar, contractures, and keloid formation.
it describes the bony anatomy including the femoral head , acetabulum, labrum . also discusses the capsule , ligaments . muscle that act on the hip joint and the range of motion are outlined. factors affecting hip joint stability and weight transmission through the joint are summarized.
How to Setup Warehouse & Location in Odoo 17 InventoryCeline George
In this slide, we'll explore how to set up warehouses and locations in Odoo 17 Inventory. This will help us manage our stock effectively, track inventory levels, and streamline warehouse operations.
Walmart Business+ and Spark Good for Nonprofits.pdfTechSoup
"Learn about all the ways Walmart supports nonprofit organizations.
You will hear from Liz Willett, the Head of Nonprofits, and hear about what Walmart is doing to help nonprofits, including Walmart Business and Spark Good. Walmart Business+ is a new offer for nonprofits that offers discounts and also streamlines nonprofits order and expense tracking, saving time and money.
The webinar may also give some examples on how nonprofits can best leverage Walmart Business+.
The event will cover the following::
Walmart Business + (https://business.walmart.com/plus) is a new shopping experience for nonprofits, schools, and local business customers that connects an exclusive online shopping experience to stores. Benefits include free delivery and shipping, a 'Spend Analytics” feature, special discounts, deals and tax-exempt shopping.
Special TechSoup offer for a free 180 days membership, and up to $150 in discounts on eligible orders.
Spark Good (walmart.com/sparkgood) is a charitable platform that enables nonprofits to receive donations directly from customers and associates.
Answers about how you can do more with Walmart!"
A review of the growth of the Israel Genealogy Research Association Database Collection for the last 12 months. Our collection is now passed the 3 million mark and still growing. See which archives have contributed the most. See the different types of records we have, and which years have had records added. You can also see what we have for the future.
This slide is special for master students (MIBS & MIFB) in UUM. Also useful for readers who are interested in the topic of contemporary Islamic banking.
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...PECB
Denis is a dynamic and results-driven Chief Information Officer (CIO) with a distinguished career spanning information systems analysis and technical project management. With a proven track record of spearheading the design and delivery of cutting-edge Information Management solutions, he has consistently elevated business operations, streamlined reporting functions, and maximized process efficiency.
Certified as an ISO/IEC 27001: Information Security Management Systems (ISMS) Lead Implementer, Data Protection Officer, and Cyber Risks Analyst, Denis brings a heightened focus on data security, privacy, and cyber resilience to every endeavor.
His expertise extends across a diverse spectrum of reporting, database, and web development applications, underpinned by an exceptional grasp of data storage and virtualization technologies. His proficiency in application testing, database administration, and data cleansing ensures seamless execution of complex projects.
What sets Denis apart is his comprehensive understanding of Business and Systems Analysis technologies, honed through involvement in all phases of the Software Development Lifecycle (SDLC). From meticulous requirements gathering to precise analysis, innovative design, rigorous development, thorough testing, and successful implementation, he has consistently delivered exceptional results.
Throughout his career, he has taken on multifaceted roles, from leading technical project management teams to owning solutions that drive operational excellence. His conscientious and proactive approach is unwavering, whether he is working independently or collaboratively within a team. His ability to connect with colleagues on a personal level underscores his commitment to fostering a harmonious and productive workplace environment.
Date: May 29, 2024
Tags: Information Security, ISO/IEC 27001, ISO/IEC 42001, Artificial Intelligence, GDPR
-------------------------------------------------------------------------------
Find out more about ISO training and certification services
Training: ISO/IEC 27001 Information Security Management System - EN | PECB
ISO/IEC 42001 Artificial Intelligence Management System - EN | PECB
General Data Protection Regulation (GDPR) - Training Courses - EN | PECB
Webinars: https://pecb.com/webinars
Article: https://pecb.com/article
-------------------------------------------------------------------------------
For more information about PECB:
Website: https://pecb.com/
LinkedIn: https://www.linkedin.com/company/pecb/
Facebook: https://www.facebook.com/PECBInternational/
Slideshare: http://www.slideshare.net/PECBCERTIFICATION
Chapter wise All Notes of First year Basic Civil Engineering.pptxDenish Jangid
Chapter wise All Notes of First year Basic Civil Engineering
Syllabus
Chapter-1
Introduction to objective, scope and outcome the subject
Chapter 2
Introduction: Scope and Specialization of Civil Engineering, Role of civil Engineer in Society, Impact of infrastructural development on economy of country.
Chapter 3
Surveying: Object Principles & Types of Surveying; Site Plans, Plans & Maps; Scales & Unit of different Measurements.
Linear Measurements: Instruments used. Linear Measurement by Tape, Ranging out Survey Lines and overcoming Obstructions; Measurements on sloping ground; Tape corrections, conventional symbols. Angular Measurements: Instruments used; Introduction to Compass Surveying, Bearings and Longitude & Latitude of a Line, Introduction to total station.
Levelling: Instrument used Object of levelling, Methods of levelling in brief, and Contour maps.
Chapter 4
Buildings: Selection of site for Buildings, Layout of Building Plan, Types of buildings, Plinth area, carpet area, floor space index, Introduction to building byelaws, concept of sun light & ventilation. Components of Buildings & their functions, Basic concept of R.C.C., Introduction to types of foundation
Chapter 5
Transportation: Introduction to Transportation Engineering; Traffic and Road Safety: Types and Characteristics of Various Modes of Transportation; Various Road Traffic Signs, Causes of Accidents and Road Safety Measures.
Chapter 6
Environmental Engineering: Environmental Pollution, Environmental Acts and Regulations, Functional Concepts of Ecology, Basics of Species, Biodiversity, Ecosystem, Hydrological Cycle; Chemical Cycles: Carbon, Nitrogen & Phosphorus; Energy Flow in Ecosystems.
Water Pollution: Water Quality standards, Introduction to Treatment & Disposal of Waste Water. Reuse and Saving of Water, Rain Water Harvesting. Solid Waste Management: Classification of Solid Waste, Collection, Transportation and Disposal of Solid. Recycling of Solid Waste: Energy Recovery, Sanitary Landfill, On-Site Sanitation. Air & Noise Pollution: Primary and Secondary air pollutants, Harmful effects of Air Pollution, Control of Air Pollution. . Noise Pollution Harmful Effects of noise pollution, control of noise pollution, Global warming & Climate Change, Ozone depletion, Greenhouse effect
Text Books:
1. Palancharmy, Basic Civil Engineering, McGraw Hill publishers.
2. Satheesh Gopi, Basic Civil Engineering, Pearson Publishers.
3. Ketki Rangwala Dalal, Essentials of Civil Engineering, Charotar Publishing House.
4. BCP, Surveying volume 1
How to Make a Field Mandatory in Odoo 17Celine George
In Odoo, making a field required can be done through both Python code and XML views. When you set the required attribute to True in Python code, it makes the field required across all views where it's used. Conversely, when you set the required attribute in XML views, it makes the field required only in the context of that particular view.
Earned Value Management for Design and Construction Project
1. @ IJTSRD | Available Online @ www.ijtsrd.com | Volume – 2 | Issue – 5 | Jul-Aug 2018 Page: 1482
ISSN No: 2456 - 6470 | www.ijtsrd.com | Volume - 2 | Issue – 5
International Journal of Trend in Scientific
Research and Development (IJTSRD)
International Open Access Journal
Earned Value Management for Design and Construction Project
Khalid Mohiuddin Khan1
, Mr. Masoom Reza2
1
Design Engineer, 2
Assistant Professor
Department of Civil Engineering, Al-Falah School of Engineering and Technology,
Al-Falah University, Dhauj, Faridabad, Haryana, India
ABSTRACT
In most of the construction projects it has been notice
that certain causes may lead to delay in construction
activities. This will make time/schedule and
cost/budget overrun in the project. Thus, it has
become a major and challenging problem to complete
the project on schedule and within the estimated cost.
To solve this problem, the concept of construction
project management by Earned Value Management
System (EVMS) is evaluated. Earned Value
Management (EVM) is a technique that finds the
stage at which cost and time overrun; EVM technique
acts as an early warning and alarming system for
budget and schedule.
It not only measures the project performance but also
measure the progress of the schedule. In our study we
have done Earn Value analysis of a construction
project which was completed in the year of 2017,
based on project data (BOQ, Actual Budget, and
Schedule) and inputs which have been collected we
are able to perform EVA by using Microsoft Project.
The analysis helps in finding out the deviations both
in cost as well as in time i.e. schedule variance and
cost variance. It is an effective tool to measure cost,
schedule & performance of the project. The EVA is
useful in various fields such as IT, Industries and
Construction companies etc. This paper summarizes
the evolution, basic terminologies of Earned Value
Analysis and effective use of it in the construction
industries by Microsoft Project.
KEYWORDS: Earned Value Analysis, Cost
Monitoring, Schedule Monitoring and Microsoft
project
1. INTRODUCTION
1.1 GENERAL:
In the age of construction and development, the
project manager needs strict controlling and tracking
of the construction project. Monitoring and Tracking
of project is the most important element in project
management. It concerns with measuring the progress
performance of Project at a certain period and time
interval and reports that performance to the
organization for process control. After getting such
tracked information, the concerned authority decides
to take further action to control and command the
project before it becomes impregnable. Thus,
monitoring, tracking and controlling are most
important component process throughout the entire
life of the project.
The progress of under-construction project can be
evaluated by using a different conventional approach
like day to day monitoring/tracking, monthly or
weekly or biweekly management review meetings,
performance reviews, key performance indicators,
project audit reports etc. In these conventional
approaches, usually, there are two data sources, the
budget (or planned) expenditures, and the actual
expenditures. The comparison of budget versus actual
expenditures merely indicates what was planned to be
spent versus what was actually spent at any given
time and also, how much has been produced. With
this approach, there is no way to determine the
physical amount of work performed. It does not
indicate anything about what has actually been
produced for the amount of money spent nor whether
it is being produced at the rate, or according to the
schedule, originally planned. Based on these
limitations of conventional performance measurement
tools, this paper discusses earned value analysis
2. International Journal of Trend in Scientific Research and Development (IJTSRD) ISSN: 2456-6470
@ IJTSRD | Available Online @ www.ijtsrd.com | Volume – 2 | Issue – 5 | Jul-Aug 2018 Page: 1483
(EVA) technique as an effective tool for tracking and
controlling of construction projects. It is a project
control method which integrates the cost, schedule
and technical performance. Many public-sector
contractors are working on project-oriented principle
or project to project basis. Problems in completing
project are often related to on time and on budget
completion and for public sector contractors, there is
more publicity when something goes wrong and
unplanned. Hence, public sector agencies are
demanding on EVMs. EVM is a approach to help
project manager and projects come to successful
completion whether projects are from construction
industries, information technology, software
development or Hospitality Industry. EVM is treated
as one of the most useful, powerful and productive
concepts used for managing today’s complex projects
in private, commercial or public-sector environments.
It has the ability to combine measurements of scope,
schedule, and costs. It is a single integrated
multifunctional system. Using EVM the project
controller can assess how ahead or behind schedule
the project and if the project is over budget or under
budget.
1.2 OBJECTIVE:
The Earned Value method or technique has been
developed as a tool or technique to track and control
the project. It is helpful and useful for getting a
project’s status at any stage (Whether it is lag behind
or away of schedule? Whether is it out-off or under
budget or estimate?) and the scale of current variances
from the plan. Moreover, it helps a project manager to
make decisions and make comparisons on the final
effect of the project in the manner of cost and, to
some extent, in the manner of time and duration, by
comparing present trends.
This technique is very simple and unique: it presumes
a simplified model of a project or work, and the
estimation require nothing but few and four basic
arithmetic operations and elements like addition,
subtraction, multiplication and division. Because of its
ease of working and simple arithmetic calculations,
with progressive and real time results this technique
has been accredited as a very effective and useful tool
by many project managers, companies and public-
sector agencies and has become a bench mark and
standard in project management and operations. This
technique is very versatile enough, it can be work and
applied on any type of project of any sector it can
work from defence sector and helps in making their
strategies to small as well as big IT projects. The
analysis in this method can be initiated on any level
hierarchy of work and work breakdown structure and
can be used by clients, researchers, scholars and
contractors.
The method, work very accurately and efficiently, but
requires a consistent approach for collection of data
and algorithms on project cost and progress (on
weekly and biweekly basis) and the findings are to be
processed immediately.
1. The main objective of using EVA technique is to
find out and detect any mismatch during any stage
of construction as soon as possible, so that there is
plenty of time in hand of project managers to
asses if the mismatch is dangerous for the project
and, if necessary, precautions and corrective
actions can be taken.
2. To find out the reason behind the delay of project,
with respect to project budget and project
schedule.
3. Analyse the actual profit and loss of the project.
2. LITERATURE REVIEW
2.1 GENERAL:
Literature Review pertaining to similar studies
conducted all over the world is collected from various
sources to determine the feasibility and scope of the
work. Similar studies undertaken are as follows:
➢ T. Subramani, D. S. Stephan Jabasingh, J.
Jayalakshmi (2014): Discuss the main
parameters involved in the calculation and
analysis of Earn value analysis and cost
controlling in construction project by using
software like Primavera and MS projects. [1]
➢ Ray W. Stratton, EVP (2007): Discuss about the
earn schedule, earn schedule analysis for
estimating the completion date of the construction
project and also compare the conventional method
of scheduling and budgeting. [2]
➢ Dr. Arun Dhawale1 Vaishnavi Tuljapurkar
(2015): In this paper discussion is done on Cost
control and tracking of a building construction
project by earned value method. The Earn Value
Analysis is dependent on two key areas i.e. precise
cost information and pragmatic progress of
project. If two key areas are efficient for a project
to get benefitted. [3]
➢ Andrew Fernans Tom1, Sachin Paul (2013):
The present study deals with the project
monitoring process of “Standard Design Factory”.
3. International Journal of Trend in Scientific Research and Development (IJTSRD) ISSN: 2456-6470
@ IJTSRD | Available Online @ www.ijtsrd.com | Volume – 2 | Issue – 5 | Jul-Aug 2018 Page: 1484
A comparison between the planned progress of
construction work and actual progress is
performed in this study using project management
software Primavera P6 to make the calculations
easy. [4]
➢ ANUJ DUBEY (2015): In this paper the
discussion is on Cost over-runs and time over-runs
are prevalent in most of the projects carried out in
developing nations such as India. There may be
multiple reasons for these overruns. In order to
reduce them, there should be efficient use of the
construction software’s available in the market.
This paper emphasises the use of these software’s
to reduce these issues by the use of a scientific
technique called earned value analysis. [5]
➢ Ms. Radhika R. Gupta, Prof. Parag S.
Mahatme, Prof. Taran C. Bhagat (2015): This
paper discusses the cost controlling and
monitoring of construction project through earned
value management system their benefits and
future scope. On comparing Earned Value
Management method to traditional management,
traditional management does not allow for
analysis of physical amount of work performed.
Earn value management allows both schedule cost
analysis against physical work performed. [6]
➢ Shu CHEN and Xueqing ZHANG (2012): The
review undertaken in this paper covers popular
research directions in the EVM area. The paper
introduces a description of the background of
EVM, including its terminologies, performance
analysis and forecasting measures, and advantages
as well as disadvantages of EVM. The
classification system made for organizing the
retrieved studies is developed. In empirical
studies, case studies were used to highlight the
driving and impeding factors for effective
implementation of EVM while a large number of
project data analysed to portray the behaviours of
CPI and investigate the accuracy of cost
forecasting techniques. In non-empirical studies,
models and simulation methods have been used to
improve the capability of EVM. [7]
➢ Rajesh Ganpat Virle and Sumedh Y Mhaske
(2013): Earned Value Management is a powerful
methodology that helps executive, project
manager, program manager and other stakeholders
of the project to manage the project more
effectively. Earned Schedule is an important
extension to EVM that allows EVM metrics to be
transformed to time or duration metrics to enhance
the evaluation of project schedule performance,
forecast the duration needed to complete the
project. [8]
➢ Sandhya Suresh, Ganapathy Ramasamy N
(2015): This paper discusses the Analysis of
Project Performance Using Earned Value Analysis
EVM provides more perception about the costs
and other elements of scope, risks, performance
etc. It inspires the management team to pay more
attention to cost, schedule and progress with more
intensity and optimizes the project. [9]
➢ Lipke Walt et al (2007): In project management
Institute (USA), Earned Value and Earned
Schedule was applied and study was carried on by
Lipke Walt. It has been concluded that EVM with
ES provides incredible management information
which helps in project management.
➢ Knedrik et al (2004): Said EVM is complex but
it has a simple foundation. It helps in tracking the
performance of a project by simple arithmetical
calculation, for projects of larger volume software
like MS project can be used
2.2 HISTORY:
Every project manager focuses on the point that the
project should be within the budget and within the
cost and how could this be done. It may happen that
project may be out-off time or out-off budget, to
calculate this time versus budget consequences expert
mathematical tools are required. So, to overcome this
problem Earn Value Management is the technique to
be applied in the construction, IT, defence and
hospitality sectors etc. In 1960s, but it has become an
important branch of project management and value
engineering. Project management research
investigating the contribution of EVM to project
success suggests a moderately strong positive
relationship. Implementations of EVM can be scaled
to fit projects of all sizes and complexities.
Every project manager and project controller efforts
that the project should be within the budget, within
the cost, within planned schedule and how this could
be achieved. Possibilities may happen that project
may be over schedule or over budget, to calculate this
effective mathematic tool and complex algorithms are
required. So, to handle this problem EVA is the
technique to be applied in the construction projects
and other projects too. EVM emerged as a financial
analysis tools specialty in United States Government
programs in the 1960s, but it has since become a
significant and an effective branch of project
management, project controlling, and cost
4. International Journal of Trend in Scientific Research and Development (IJTSRD) ISSN: 2456-6470
@ IJTSRD | Available Online @ www.ijtsrd.com | Volume – 2 | Issue – 5 | Jul-Aug 2018 Page: 1485
engineering. Project management research
investigating the contribution of EVM to project
success suggests a moderately strong positive
proportion. EVM technique can be implemented to
projects of all ranges, sizes and intricacies.
The origin of EVM occurred in industrial
development at the end of the 20th century, this
method is based significantly on the principle of
"earned time" the concept took root in the United
States Department of Defence in the 1960s. This came
from the original concept called PERT/COST, but it
was considered overly cumbersome (not very
adaptable) by project managers who were mandated
to use it, and many variations of it began to proliferate
among various procurement programs. In the late
1980s and early 1990s, EVM comes as a project
management technique to be understood and used by
managers and executives, not just by EVM specialists.
In 1989, EVM leadership was elevated to the
Undersecretary of Defence for Acquisition, thus
making EVM an essential element of program
management and procurement. The construction
industry was an early and quick commercial adopter
of EVM. The EVM used very commonly and
accelerated in the 1990s. In 1999, the Performance
Management Association merged with the Project
Management Institute (PMI) to become PMI’s first
college, the College of Performance Management.
The United States Office of Management and Budget
began to mandate and recommend the use of EVM
across all public-sector agencies, and, for the first
time, for certain internally managed projects (not only
contractors and govt agencies).
2.3 DESCRIPTION:
Earned Value analysis is a method of performance
measurement. Earned Value is a program
management technique that uses “work in progress”
to indicate what will happen to work in the future.
Earned value management is an “early warning
system” for planning and controlling the project cost
performances. EVM establish work packages earned
value baseline by integrating project scope, time
schedule and cost objectives. This baseline is called as
cost control and is used for performance evaluation of
a project on a given date.
Earned Value analysis is a method and technique of
performance evaluation and measurement. Earned
Value is a program management-based technique that
uses “work in progress” and used to indicate what will
happen to work in the future (can be calculated on
basis interpolation). Earned value management is an
“early warning and alarming system” for planning,
controlling and monitoring the project cost
performances and benefits. EVM establish work
packages earned value baseline by integrating project
scope, time schedule and cost objectives. This
baseline is called as cost control and is used for
performance evaluation of a project on a given date.
Analysis of deviation and trends from the baseline
provides the cost related information’s for problem
determination, current and past trend analysis and
corrective actions such as re-planning, re-allocating
and revising the cost and budget and re-scheduling.
Earned value analysis serves two main purposes.
➢ It analyses and determines cost changes which are
resulting in duration and budget over-run or
under-run so that timely precautionary actions are
taken such as revision and modification of cash
flow, reevaluating financial projections, trends
and forecast and project success and profitability
projections.
➢ Analysis of deviation from the baseline data using
earned value technique and systems gives a
variety of variances and deviations which are used
to provide and determine the current status of the
project, to initiate corrective actions and to
forecast future success trends.
2.4 BASIC TERMINOLOGY:
The basic terms associated with Earned Value
Management:
➢ Budgeted Cost for Work Scheduled (BCWS) /
Planned Value (PV): It is the amount of money
budgeted to be spent at a particular point in time.
➢ Budgeted Cost for Work Performed (BCWP) /
Earned Value (EV): It is the amount of work in
terms of cost that is actually accomplished at a
particular point of time with respect to the planned
value.
➢ Actual Cost of Work Performed (ACWP) /
Actual Cost (AC): It is the actual amount of
money spent for the corresponding planned and
earned value.
➢ Cost Variance (CV): It helps to measure project
performance. Cost variance (CV) indicates how
much over or under budget the project is. A
positive value indicates a favourable condition and
a negative value indicates an unfavourable
condition It is the difference between Earned
Value and Actual Cost.
5. International Journal of Trend in Scientific Research and Development (IJTSRD) ISSN: 2456-6470
@ IJTSRD | Available Online @ www.ijtsrd.com | Volume – 2 | Issue – 5 | Jul-Aug 2018 Page: 1486
CV = EV – AC
➢ Schedule Variance (SV): It indicates how much
ahead or behind schedule the project is. A positive
value indicates a favorable condition and a
negative value indicates an unfavourable
condition. It is the difference between Earned
Value and Planned Value.
SV = EV – PV
➢ Cost Performance Index (CPI): It is a measure
of cost efficiency on a project. A value equal to or
greater than one indicates a favorable condition
and a value less than one indicate an unfavourable
condition. It is the ratio between Earned Value
and Actual cost.
CPI = EV / AC
If CPI < 1: The project is running over budget,
If CPI >1: The project is running under budget,
If CPI=1: the project is running on a budget.
➢ Schedule Performance Index (SPI): It is a
measure of schedule efficiency on a project. An
SPI equal to or greater than one indicates a
favourable condition and a value of less than one
indicates an unfavourable condition. It is the ratio
between Earned Value and Planned Value.
SPI = EV / PV
If SPI < 1: The project is running behind planned
schedule,
If SPI >1: The project is running ahead of planned
schedule,
If SPI=1: the project is running on planned
schedule.
➢ Critical Ratio (CR): It is the product of Cost
Performance Index and Schedule Performance
Index. It indicates the overall performance of the
Project with respect to both cost and time.
CR= CPI * SPI
➢ Estimation at Completion (BAC): It’s a
prediction of the total project cost based upon the
current trends in project performance. It is the
ratio of the Budget at completion and cost
performance index.
EAC= BAC / CPI
➢ Variance at Completion (VAC): It is the
difference between the planned budgets at the
beginning of the project to the Estimate at
Completion. This value denotes how much more
profit or loss the contractor will make on that
Project.
VAC= BAC-EAC
➢ Time Estimate at Completion (EACt): It
predicts the completion time of a Project based on
its current performance.
EACt = (BAC / SPI) / (BAC / months)
2.5 S-CURVE:
“S Curves” are great mathematical tool to track
project progress in terms of time and cost and it is
also known as a time-cost curve. It is a graphical
representation of financial forecast, cash flow of a
project. It is derived from activity usage profile, and it
shows an S-like shape, flatter at the beginning and end
and steeper in the middle. This shows that costs
involved in the project are low in the beginning as
well as in the end, whereas it increases at a rapid rate
when the project is in its middle stage. EVM is
graphically represented as below
Figure 1 S-CURVE EVM
2.5 ADVANTAGES OF EVMS:
1. EVA can be done weekly, bi-weekly and
periodically; management tries to make sure that
all the project parameters are on track.
2. It is used to measure and predict progress of
ongoing project.
3. It is the only method which tracks the project and
work in terms of progress, duration/time and
cost/money.
4. It helps the project manager to make the project to
be on time and on a budget.
5. The cost performance index (CPI) and schedule
performance index (SPI) provides an early
warning signal.
6. It can be applied to any construction project and
other project at any time and it gives impressive
results in large construction project.
7. Time to time performance measurement makes
sure that steps can be taken to the bring project
back on track as per planned schedule.
6. International Journal of Trend in Scientific Research and Development (IJTSRD) ISSN: 2456-6470
@ IJTSRD | Available Online @ www.ijtsrd.com | Volume – 2 | Issue – 5 | Jul-Aug 2018 Page: 1487
2.6 DISADVANTAGE / DRAWBACKS OF
EVMS:
1. In Earn Value management system and analysis
quality doesn’t take in to consideration.
2. To solve and make relationship between cost,
duration and budget complex calculations are to
be solve which can be done by software.
3. EVA is required to be carried out at different
stages as the uncertainty may occur anytime
throughout the project.
3. METHODOLOGY
3.1 GENERAL
The construction and operations projects have become
so large and complex, it become very difficult to find
out the actual progress of project at any time by using
conventional methods and calculations. To solve this
many IT companies have started developing software
for project management which helps in doing
complex calculation in very simple manner, project
management and planning software such as
Primavera P6, Microsoft Project, etc. are very
popular.
3.2 METHODOLOGY FOR EARN VALUE
ANALYSIS
Our study and analysis involve Earned value analysis
of the building project using Microsoft Project. The
progress at the site must be incorporated in the
Microsoft Project schedule and updated. These
updates need to be thoroughly monitored using
Microsoft Project. The work breakdown structure
(WBS) for the project is created and several activities
are identified. The following recommended steps for
the successful implementation of earned value
analysis:
TABLE 3.1 STEPS IN EARN VALUE ANALYSIS
S. No Steps
1 Create Project
2 Define WBS
3 Creating Calendars
4 Define Activities
5 Appoint Activity Durations
6 Assign Logic Links
7 Perform Scheduling
8 Allocating Resources/budgeting
9 Creating Baselines
10 Updating Schedule
11 Earned value analysis
Steps involved in monitoring and controlling of the
project in Microsoft Project are:
1. Creating new projects:
The project is created under the respective divisions in
Enterprise Project Structure (EPS) and assigned the
person in charge from Organisation Breakdown
Structure (OBS) to it. The project can be given
planned start and must finish dates. The project is
assigned a calendar which can be global, resource or
project calendar.
2. Define Work breakdown structure (WBS):
WBS is a hierarchy of project that must be
accomplished to complete a project. Each WBS
element may contain more detailed WBS levels,
activities, or both.
3. Creating Calendars:
Calendars are the most important source for defining
the baseline and for tracking to project i.e. the project
is behind the schedule or not. It can be created as a
global, resource or project calendar.
4. Defining activities:
Activities are the fundamental work elements of a
project and form the lowest level of a WBS and are
the smallest subdivision of a project. An activity has
the following characteristics like activity ID, name,
start and finish dates, activity calendar, activity type,
activity codes, constraints, expenses, predecessor and
successor relationships, resources and roles etc.
5. Defining activity duration:
When planning the work, the duration is entered in the
original duration field. The actual duration can only
be entered for the activities, which are completed.
6. The relationship between activities:
To form a network, the activities should be connected
to each other, which is done by assigning preceding
and succeeding activities with a significant
relationship to the activities.
A. Finish to Start (FS) relationship.
B. Finish to Finish (FF) relationship.
C. Start to Start (SS) relationship.
D. Start to Finish (SF) relationship.
7. Perform scheduling:
Scheduling is to perform that all the activities must be
schedule as according to the relationship between the
various activities. It is simply performed by pressing
the F9 button.
8. Allocating resources and budget:
Resources are allocated in the resource sheet as a
labourer, material, and non-labour resources and the
price is allocated to the various resources as per unit.
Labour and non-labour resources are always time-
7. International Journal of Trend in Scientific Research and Development (IJTSRD) ISSN: 2456-6470
@ IJTSRD | Available Online @ www.ijtsrd.com | Volume – 2 | Issue – 5 | Jul-Aug 2018 Page: 1488
based, and material resources such as consumable
items, use a unit of measure which can be specified.
Resources are different than expenses. While
resources can be time-based and generally extend
across multiple activities or projects, expenses are
one-time expenditures for non-reusable items required
by activities. After defining resources, they are to be
allocated to their respective activities. While Budget
is to be allocated from the expense tab to various
activities.
9. Creating baselines:
A simple baseline plan is a complete copy of the
original schedule which provides a target against
which a project’s performance is tracked.
10. Updating schedule:
A. If the project is progressing exactly as planned,
then only needed to estimate progress.
B. If the project is not progressing as planned many
activities are starting out-of-sequence, actual
resource use is exceeding planned use, and then
update should be done for activities and resources
individually.
C. Most projects contain some activities that progress
as planned and some which do not. In this case,
the best method is to combine the two updating
methods.
11. Preliminary steps to be done in updating:
Choose project, maintain baseline. Then add and save
a copy of current project as a new baseline B1. Then
choose project baseline as B1 and assign primary
baseline as B1.
12. Daily updates to be made:
A. Start date and end date
Choose the activity to be updated. Then in the activity
details window, select the status tab. Then tick mark
started if the activity has been started and select the
date. Tick mark finished if the activity has been
finished and select the finish date.
B. Resource
Inactivity details window, select resource tab. Then
select the resources which are to be added to the
particular activity
C. Code
Inactivity details window, select code tab. Then select
the activity code for each resource.
D. Notebook
Inactivity details window, select notebook tab. Select
the topic which we want to note and write the details
in notebook topic.
E. Steps
In activity details window, select steps tab. Then if the
activity has any steps update the activity in percentage
complete and put a tick mark if the activity has been
completed.
F. Feedback
Inactivity details window, select feedback tab. Then
the details for the resources have to be mentioned in
feedback.
G. Work products and documents (WPs & Docs)
In activity details window, select the WPS & Docs
tab. Then the drawings, documents, specifications
have to be uploaded here.
13. Weekly updates to be made:
A. Threshold
In the directory, bar chooses threshold tab. Then 3
variances are to be monitored regularly; finished date
variance, start date, variance, and cost variance.
B. Issues
In the directory, bar chooses project issues. The
values which fall outside the threshold values are
indicated in the issues. The contractor also has to add
issues if there are any.
C. Reports
Choose tools. Then choose the data date which we
want to update the progress. All the activities done in
that week has to be selected. Then select update
progress.
14. Earned value:
Earned value is a method or technique use to
determine project performance according to both
project value, duration and schedule. The technique
makes comparison between the budgeted cost of the
work to the actual cost. The earned value of the work
or project has been estimated after including the
actual cost of each activity inclusive of expenditures.
In Microsoft Project, the Earned Value Analysis is
done by adding columns of planned value, actual
value, budgeted value, cost variance, schedule
variance, cost variance, budget at completion, and
variance at completion and estimate at completion. So
from the data obtained by the Microsoft Project, we
do the analysis according to the process as mentioned
in the literature review and according to that, we plan
for the remaining project.
3.3 CORRECTIVE ACTIONS:
In the case of time over-run, we have to review the
schedule of activities, re-examine their
interdependencies, explore the possibilities of
crashing the activities in the critical path, by
increasing/reallocating available resources, draw
revised schedule in an attempt to minimize the
8. International Journal of Trend in Scientific Research and Development (IJTSRD) ISSN: 2456-6470
@ IJTSRD | Available Online @ www.ijtsrd.com | Volume – 2 | Issue – 5 | Jul-Aug 2018 Page: 1489
slippage. This has to be a continuous process rather
than a one-time correction.
In the case of cost overrun, we review the
planned/budgeted cost estimates to complete the
project and possibilities of cost reduction by
crashing/decompression of activities, postponing
allocation of resources to non-critical activities to the
extent possible, reduction in resources considered
redundant and other feasible means. In real life
situations, we are sometimes confronted with the
problem of matching the schedule with limited
resources, e.g. manpower, funds, etc. In such a case
we reallocate resources to activities, in order of
priority, most critical activity getting the top priority
in the matter. The attempt would be to redistribute the
resources without incurring time overrun. If
impossible, we would try to keep it to the least
possible value.
3.4 ORGANIZATIONAL BREAKDOWN
STRUCTURE OR OBS
OBS is a hierarchical model describing the
established organizational framework for project
planning, resource management, time and expense
tracking, cost allocation, revenue/profit reporting, and
work management. The OBS for the undertaking
Project is shown below: -
Figure 2 Organisational Breakdown Structure
9. International Journal of Trend in Scientific Research and Development (IJTSRD) ISSN: 2456-6470
@ IJTSRD | Available Online @ www.ijtsrd.com | Volume – 2 | Issue – 5 | Jul-Aug 2018 Page: 1490
4. EARN VALUE ANALYSIS
4.1 SCHEDULING
From the bill of quantities, we have prepared the schedule of the project. In the schedule, we assign the
relationship to all the activities related to the project and define the code for the work breakdown structure
WBS.
Figure 2: WBS1
Figure 3: Work Breakdown Structure
4.2 RESOURCE ALLOCATION
All the resource is allocated according to the resource sheet and BOQ, which will further help in finding out the
actual cost of the project. In the below table the reinforcement and concrete quantity of every floor are
calculated as per the drawings available from the site and BOQ.
10. International Journal of Trend in Scientific Research and Development (IJTSRD) ISSN: 2456-6470
@ IJTSRD | Available Online @ www.ijtsrd.com | Volume – 2 | Issue – 5 | Jul-Aug 2018 Page: 1491
Table 4.1: Quantity of every floor are calculated as per the drawings
Floor Reinforcement Concrete
Ground Floor
76.62-ton column
82.48-ton slab
250 cum M50 column
1200 cum M40 Slab
First Floor
38.07-ton column
41.87-ton slab
150 cum M50 column
450 cum M40 Slab
Second Floor
36.61-ton column
57.67-ton slab
200 cum M50 column
600 cum M40 Slab
Third Floor
28.33-ton column
57.61-ton slab
200 cum M50 column
600 cum M40 Slab
Fourth Floor
29.10-ton column
58.25-ton slab
200 cum M50 column
600 cum M40 Slab
Five Floor
28.83-ton column
58.19-ton slab
200 cum M50 column
600 cum M40 Slab
Six Floor
28.65-ton column
58.52-ton slab
200 cum M50 column
600 cum M40 Slab
Seventh Floor
28.65-ton column
60.62-ton slab
200 cum M50 column
630 cum M40 Slab
Eighth Floor
28.65-ton column
58.52-ton slab
200 cum M50 column
600 cum M40 Slab
Ninth Floor
28.65-ton column
58.52-ton slab
200 cum M50 column
600 cum M40 Slab
Tenth Floor
28.65-ton column
58.52-ton slab
200 cum M50 column
600 cum M40 Slab
Eleventh Floor
28.65-ton column
60.62-ton slab
200 cum M50 column
630 cum M40 Slab
Twelfth Floor
28.65-ton column
58.52-ton slab
200 cum M50 column
600 cum M40 Slab
Thirteenth Floor
28.65-ton column
58.52-ton slab
200 cum M50 column
600 cum M40 Slab
Fourteenth Floor
28.65-ton column
60.62-ton slab
200 cum M50 column
630 cum M40 Slab
Fifteenth Floor
28.65-ton column
58.52-ton slab
200 cum M50 column
600 cum M40 Slab
Sixteenth Floor
28.65-ton column
58.52-ton slab
200 cum M50 column
600 cum M40 Slab
4.3 TARGET AND DELAYS
Earned Value Analysis required both the baseline completion date which we also refer as the completion date
as mentioned in the master schedule and the actual completion at which actual work had been completed on the
site. As it helps us to know that our project is running as per the master schedule or not. This tells us that which
activities take more time and which are the most critical activities and according to this the further catch-up
plan was prepared to bring the project within the dates mentioned in the master schedule.
11. International Journal of Trend in Scientific Research and Development (IJTSRD) ISSN: 2456-6470
@ IJTSRD | Available Online @ www.ijtsrd.com | Volume – 2 | Issue – 5 | Jul-Aug 2018 Page: 1492
Table 4.2: Catch-Up Plan as Per Schedule Master Schedule
Activity Baseline Completion Actual completion Remarks
Excavation 16.09.2015 Completed Completed
Soiling 24.12.2015 Completed Completed
PCC 24.12.2015 Completed Completed
Raft (East side) 24.01.2016 24.01.2016 Completed
Raft ( West Side) 21.02.2016 21.02.2016 Completed
Retaining wall 19.02.2016 25.03.2016 Completed
GF - Slab casting 15-03-2016 20.03.2016 Completed ( 5 days delay)
FF – Slab casting 27.03.2016 05.04.2016 Completed ( 9 days delay)
SF – Slab casting 08.04.2016 20.04.2016 Completed ( 12 days delay)
TF – Slab casting 20.04.2016 04.05.2016 Completed ( 14 days delay)
Fourth Floor Slab 03.05.2016 16.05.2016 Completed ( 13 days delay)
Fifth Floor Slab 15.05.2016 31.05.2016 Completed ( 16 days delay)
Sixth floor slab 27.05.2016 06.12.2016 Completed (16 days delay)
Seventh floor slab 08.06.2016 22.06.2016 Completed (14 days delay)
Eighth-floor slab 20.06.2016 02.07.2016 Completed (12 days delay)
Ninth floor slab 02.07.2016 12.07.2016 Completed (10 days delay)
Tenth-floor slab 14.07.2016 22.07.2016 Completed (8 days delay)
Eleventh floor slab 26.07.2016 08.01.2016 Completed (6 days delay)
Twelfth-floor slab 07.08.2016 13.08.2016 Completed (6 days delay)
Thirteen-floor slab 20.08.2016 24.08.2016 Completed (4 days delay)
Fourteenth floor slab 01.09.2016 04.09.2016 Completed (3 days delay)
Fifteenth floor slab 13.09.2016 15.09.2016 Completed (2 days delay)
Sixteenth floor slab 25.09.2016 26.09.2016 Completed (1-day delay)
Terrace floor slab 08.10.2016 07.10.2016 Completed (1 day earlier)
4.4 CATCH UP PLAN
Initially the project was running in time as per the planned schedule, the project got delayed from the ground
floor slab and up to the sixth floor the delay was up to 14 days from the master schedule, so to catch the project
on time as well as cost this catch-up plan is implemented so that the project can be completed on time. As per
the revised catch-up plan we were able to catch the delayed schedule with the master schedule at the
completion of the sixteenth-floor slab.
Figure 4: Crushing of Activities
12. International Journal of Trend in Scientific Research and Development (IJTSRD) ISSN: 2456-6470
@ IJTSRD | Available Online @ www.ijtsrd.com | Volume – 2 | Issue – 5 | Jul-Aug 2018 Page: 1493
In the above figure, we crunched the column and the shear wall activity from seven days to six days, by using
aluminium formwork instead of steel formwork for the shear wall formwork and the slab reinforcement from
six days to five days by deploying the steel fitter and fitter helper from the diagonal directions, hence the slab
cycle was reduced from twelve days to ten days. The picture shown below is showing when we are going to
catch-up the milestone finish date
Figure 5: Catch-up Plan
4.5 LABOUR PRODUCTIVITY
The labor productivity of the typical 2nd floor with the duration and the quantity is calculated and according to
the output of the labor productivity of the 2nd floor, we counted the number of labors for the upper floor taking
the same productivity up to the 4th
floor.
Table 4.3: Labour Productivity
Sr.
No.
Activity Quantity Duration No of Labour Labour
Productivity
1. Columns and shear wall
reinforcement
36.61 ton 5 days Steel fitter=40
Fitter helper=20
15.25 kg/hr
2. Column and shear wall shuttering 1670 m2 5 Carpenter= 14
Helper= 7
1.98 m2/hr
3. Slab and Beam Reinforcement 57.67 ton 5 Steel fitter= 50
Fitter helper=
30
18.02kg/hr
4. Slab and Beam Shuttering 2800 m2 7 Carpenter= 25
Helper = 15
1.4 m2/hr
13. International Journal of Trend in Scientific Research and Development (IJTSRD) ISSN: 2456-6470
@ IJTSRD | Available Online @ www.ijtsrd.com | Volume – 2 | Issue – 5 | Jul-Aug 2018 Page: 1494
Afterwards due to the delay in shear wall activity we replaced the steel formwork with the standard ballax so
that it helps in increasing the labour productivity for the shear wall from 1.98 sq.m per hour to 2.48 sq.m per
hour, which helps us to do the required amount of shuttering work within 4days and with the same number of
labour. As it comes in the panel so first time just coupled them according to the required size so that it can be
similarly used in all typical floors helps in fastening the work.
4.6 TRACKING OF PROJECT IN THE MIDDILE OF THE WORK
Construction of a Basement + GROUND FLOOR+ 16 floors residential building of Total Floor Area -36374.05
Sqm (Basement – 3593.14 Sqm + GF – 1238 Sqm +Upper floors – about2100 Sqm)
Total Built up Area – 27892.67 Sqm (as per Architectural drawings issued for info) The residential building has
parking in the basement and at the ground floor Basement – 5450 mm; 4250 mm for upper floors. The budget
of the building is around Rs. 250,596,083.95. The duration for completion of the work is 20 months.
Table 4.4: Project Budget Complete
Sr.
No
Reporting period Work Progress Planned Value
PV
Earned Value Actual Cost
1 1/4/2015 to
18/8/2015
Pre-construction phase 830,000.00 830,000.00 830,000.00
2 19/8/2015 to
31/12/2016
Sub-Structure 9,297,360.00 9,297,360.00 9,297,360.00
3 1/01/2016 to
28/2/2016
Up-to Ground Floor Slab
R/f
18,998,620.00 18,998,620.00 18,998,620.00
4 1/03/2016 to
30/4/2016
Up-to 4th
Floor Column
Casting
64,860,951.69 64,860,951.69 65,111,166.69
5 1/05/2016 to
30/6//2016
Up-to 9th
Floor Column
Casting
113,261,210.29 113,261,210.29 113,511,543.57
6 1/07/2016 to
31/8/2016
Up-to 14th
Slab
Reinforcement
169,183,015.24 169,183,015.24 169,191,172.19
7 1/09/2016 to
31/10/2016
Up-to 4th
LMR Slab 234,098,021.45 234,098,021.45 233,993,733.24
8 1/11/2016 to
31/12/2016
Finishing Work 239,707,188.11 239,707,188.11 239,602,115.53
9 1/01/2017 to
05/2/2017
Handing over 249,596,083.00 249,596,083.00 249,491,795.74
Table 4.5: Earned Value of Project
Actual budgeted cost
(Baseline cost)
Rs. 250,596,083.95
Estimate at Completion Rs. 250,491,385.91
Variance at completion Rs. 104,698.04
4.7.1 EVM FROM 1-APRIL-15 to 18-AUGUST-
15 PRE-CONSTRUCTION
EAC ACWP BCWP
Rs.
250,596,083.95
Rs.
830,000.00
Rs.
830,000.00
Figure 6: EVM from 1-April-15 to 18-August-15
14. International Journal of Trend in Scientific Research and Development (IJTSRD) ISSN: 2456-6470
@ IJTSRD | Available Online @ www.ijtsrd.com | Volume – 2 | Issue – 5 | Jul-Aug 2018 Page: 1495
TASK NAME
➢ Pre-construction plan
➢ Execution
➢ Substructure
➢ Excavation
➢ Footing / raft work/retaining wall (basement
Floor. Slab)
➢ Retaining wall
➢ Basement slab
Table 4.6: EVM Analysis (1-April-15 to 18-August-
15)
S. No TERMINOLOGY AMOUNT
1 EAC Rs. 250,596,083.95
2 BCWS Rs. 830,000.00
3 BCWP Rs. 830,000.00
4 ACWP Rs. 830,000.00
5 CV Rs. 0
6 SV Rs. 248,766,083.95
7 VAC Rs. 0
4.7.2 EVM FROM 19-AUGUST-15 to 31-
DECEMBER-15 SUBSTRUCTURE
PROGRESS
EAC ACWP BCWP
Rs.
250,596,083.95
Rs.
9,297,360.00
Rs.
9,297,360.00
Figure 7: EVM from 19-August-15 to 31-
December-15
TASK NAME
➢ Execution
➢ Substructure
➢ Excavation
➢ Footing / raft work/retaining wall (basement floor.
Slab)
➢ Retaining wall
➢ Execution
Table 4.7: EVM Analysis (19-August-15 to 31-
December-15)
S. No TERMINOLOGY AMOUNT
1 EAC Rs. 250,596,083.95
2 BCWS Rs. 9,297,360.00
3 BCWP Rs. 9,297,360.00
4 ACWP Rs. 9,297,360.00
5 CV Rs. 0
6 SV (Rs. 241,298,723.95)
7 VAC Rs. 0
4.7.3 EVM FROM 1-JANUARY-16 to 28-FEB-16
SUPERSTRUCTURE PROGRESS
EAC ACWP BCWP
Rs.
250,596,083.95
Rs.
18,998,620.00
Rs.
18,998,620.00
Figure 8: EVM from 1-January-16 to 28-
February-16
TASK NAME
➢ Substructure
➢ Excavation
➢ Footing / raft work/retaining wall (basement floor.
Slab)
Table 4.8: EVM Analysis (1-January-16 to 28-
February-16)
S. No TERMINOLOGY AMOUNT
1 EAC Rs. 250,596,083.95
2 BCWS Rs. 18,998,620.00
3 BCWP Rs. 18,998,620.00
4 ACWP Rs. 18,998,620.00
5 CV Rs. 0
6 SV Rs. 230,597,463.95
7 VAC Rs. 0
16. International Journal of Trend in Scientific Research and Development (IJTSRD) ISSN: 2456-6470
@ IJTSRD | Available Online @ www.ijtsrd.com | Volume – 2 | Issue – 5 | Jul-Aug 2018 Page: 1497
4.7.7 EVM FROM 1-SEPTEMBER-16 to 31-
OCTOBER-16 SUPERSTRUCTURE
PROGRESS
EAC ACWP BCWP
Rs.
250,608,516.82
Rs.
233,993,733.24
Rs.
234,098,021.45
Figure 12: EVM from 1-September-16 to 31-
October-16
TASK NAME
➢ 15th
Floor Slab
➢ 16th
Floor Slab
➢ Terrace Slab
➢ LMR Slab
➢ Staircase Railing
➢ Flooring And Cladding Work
Table 4.12: EVM Analysis (1-September-16 to 31-
October-16)
S. No TERMINOLOGY AMOUNT
1 EAC Rs. 250,484,539.79
2 BCWS Rs. 234,098,021.45
3 BCWP Rs. 234,098,021.45
4 ACWP Rs. 233,993,733.24
5 CV Rs. 104,288.20
6 SV (Rs. 15,498,062.50)
7 VAC Rs. 111,544.16
4.7.8 EVM FROM 1-NOVEMBER-16 to 31-
DECEMBER-16 SUPERSTRUCTURE
PROGRESS
EAC ACWP BCWP
Rs.
250,487,115.53
Rs.
239,602,899.91
Rs.
239,707,188.11
Figure 13: EVM from 1-November-16 to 31-
December-16
TASK NAME
➢ Water Tank
➢ Parapet Wall - RCC - 1.50 M Ht.
➢ Block work
➢ Internal Plaster/GVP Finish
➢ Façade Work
Table 4.13: EVM Analysis (1-November-16 to 31-
December-16)
S.No TERMINOLOGY AMOUNT
1 EAC Rs. 250,487,115,.53
2 BCWS Rs. 239,707,188.11
3 BCWP Rs. 239,707,188.11
4 ACWP Rs. 239,602,115.53
5 CV Rs. 104,288.20
6 SV (Rs. 9,888,895.83)
7 VAC Rs. 108,968.42
4.7.9 EVM FROM 1-JANUARY-17 to 12-
FEBRUARY-17 HANDING OVER
EAC ACWP BCWP
Rs.
249,596,083.95
Rs.
249,491,795.74
Rs.
249,596,083.95
Figure 14: EVM from 1-January-17 to 12-
February-17
TASK NAME
➢ Application Submission For Statutory Approval
To Gift City
➢ Statutory Approvals From Gift City
➢ Fire NOC
➢ LEED Certification
➢ Completion Certificate
➢ OC of the Building
17. International Journal of Trend in Scientific Research and Development (IJTSRD) ISSN: 2456-6470
@ IJTSRD | Available Online @ www.ijtsrd.com | Volume – 2 | Issue – 5 | Jul-Aug 2018 Page: 1498
Table 4.14: EVM Analysis (1-January-16 to 12-
February-17)
S. No TERMINOLOGY AMOUNT
1 EAC Rs. 250,487,115.53
2 BCWS Rs. 249,596,083.90
3 BCWP Rs. 249,596,083.90
4 ACWP Rs. 249,491,795.74
5 CV Rs. 104,288.20
6 SV -
7 VAC Rs. 104,698.04
4.8 EARN VALUE OF OVERALL PROJECT
The projects earned value based on the status date. If
the actual cost (ACWP) is higher than earned value
(BCWP), then the project is over budget. If planned
value (BCWS) is higher than earned value, then the
project is behind schedule.
BCWS ACWP BCWP
Rs.
249,596,083.95
Rs.
249,491,795.74
Rs.
249,596,083.95
Figure 15: EVM of Overall Project
In the above graph, the budgeted cost of work
scheduled is Rs.249,596,083.95 but through the
proper monitoring and the Earned Value Analysis, we
are able to complete the project activities under the
budgeted allocated i.e. Actual cost of work performed
is Rs. 249,491,795.74.
The project goes over budget for the month of April
2016 by (Rs. 250,215.00) and so the variance at
completion is (Rs. 968,058.96). Through the proper
planning and the new catch-up plan, we are able to
complete the project on time and under the budgeted
cost at an additional profit of. Rs.104,288.20.
Figure 16: Earned value in Microsoft Project
18. International Journal of Trend in Scientific Research and Development (IJTSRD) ISSN: 2456-6470
@ IJTSRD | Available Online @ www.ijtsrd.com | Volume – 2 | Issue – 5 | Jul-Aug 2018 Page: 1499
Figure 17: Resource sheet in Microsoft Project
Figure 18: Resource Allocation and Slippage from baseline schedule
19. International Journal of Trend in Scientific Research and Development (IJTSRD) ISSN: 2456-6470
@ IJTSRD | Available Online @ www.ijtsrd.com | Volume – 2 | Issue – 5 | Jul-Aug 2018 Page: 1500
Figure 19: Labour Productivity
4.8 LIMITATIONS OF OUR STUDY
In our project study, we have not included special
works involving specially nominated sub-contractor.
The additional sub-activities of the HVAC work is not
included in our study work.
➢ For some work, we have taken the cost of material
as per tender rate which is quite low as it was
provided by the client and the site is located in a
SEZ area so there is a relaxation in the taxes in the
material.
➢ We have taken the rate of facade material as per
the current market rate.
➢ In the budgeting, we have not included the cost of
Project manager, construction manager, and site
engineer.
➢ We track and monitor the project at a regular
period of 2 months.
As due to the limitations of the study material which
we gathered from the site, we are not able to include
the budget for certain work in the budgeting of the
activities, so the earned value report is not having any
part of such certain activities like the appointment of
vendor and contractor’s profit.
4.9 SEQUENCING OF THE WORK DONE IN
OUR PROJECT
A. Review of BOQ – We obtained the BOQ from the
GIFT site, the BOQ comprises of schedule of
different activities and the approximate quantities.
The total estimated cost of the project is
anticipated from the BOQ as per the quantities and
rate
B. Organization Breakdown Structure (OBS)
C. Scheduling – With the help of Bill of Quantity
(BOQ) in Microsoft Project (MSP)
D. Resource Sheet- Machinery, Manpower, and
Materials
E. Planning – Material and manpower requirement as
per quantities are given in Tender document
F. Resource allocation – All the resource is allocated
with the help of BOQs and R.A. bills
G. Budgeting
H. Tracking and monitoring as per the baseline
schedule
I. Preparation of the catch-up plan
J. Again track the project till the completion of the
project
K. Prepare Earned Value Report
L. Conclusion.
20. International Journal of Trend in Scientific Research and Development (IJTSRD) ISSN: 2456-6470
@ IJTSRD | Available Online @ www.ijtsrd.com | Volume – 2 | Issue – 5 | Jul-Aug 2018 Page: 1501
5. CONCLUSIONS AND FUTURE SCOPE
5.1 CONCLUSION
As our study for applying the Earn Value
Management on construction project which was
completed in 2017, from preliminary study project
details and technical review of papers related to Earn
Value Management, we conclude that Earned Value
Management helps to do the particular project within
the stipulated time and cost and it has a huge future
scope in the construction industry.
Through the earned value report of our project, it has
been observed that our project is on schedule to the
ground floor slab and it starts delay from the ground
floor slab casting so it causes an increase in the
project cost and time as well. First, the delay was 5
days and the delay goes on up to 16 days continuous
up to 5th
floor until the catch-up plan was
implemented which crunch down the activities of
column and shear wall by 1 day and slab
reinforcement by 1 day so that we are able to catch up
the master baseline schedule dates.
➢ First, the cause of the delay was the shear wall
shuttering activity which was done by steel
formwork and after knowing it is one of the
reason for the delay it got replaced by the standard
ballax sheet. Secondly, it takes a lot of time for the
slab and beam reinforcement so there is a change
in the pattern of work as 2 different teams of steel
fitter and helper are assigned diagonally to
complete the work and provide the front to the
post-tensioning work and this helps to reduce the
slab reinforcement activity by 1 day. Initially
Shortage of labours though for completing the
project within time and budget the more skilled
labours are arranged.
➢ By doing all the above-mentioned techniques we
are able to complete the project within the time
but due to the certain delay and crunching of
activity project, there is a cost variance of Rs.
104,288.20 positive means we completed our
project with an additional profit of Rs 104,288.20
Through the proper tracking and monitoring, we are
able to come down the variance at completion which
is Rs. 968,058.96 negative up to the month of April to
Rs 104,698.24 positive at the completion of the
project means we have done our project activities
under the actual cost allocated for those activities.
According to the above data, we conclude that Earned
Value Management helps to do the particular project
within the stipulated time and cost and it has a huge
future scope in the construction industry.
5.2 FUTURE SCOPE
The concept of Earned value management or Earn
Value Technique, it involves two terms from the
study for the better monitoring and tracking of the
actual completion date of the project.
1. Earned Schedule: The Earned Schedule value can
be graphically determined by finding the point
Earned Value at a given time meets the Planned
Value curve. The projection of this point on the
time axis (horizontal coordinate) then defines the
Earned Schedule.
Figure 2 S-CURVES
2. Earned Duration: The new technique, Earned
Duration Management (EDM), eliminates the use
of cost data in the scheduling context. The Earned
Duration (ED) concept (Khamooshi & Golafshani,
2014) was created to address the shortcomings of
Earned Schedule due to the usage of cost-based
data as proxies for assessing the schedule
performance of projects. Its foundation lies in the
exclusive usage of time-based data for the
generation of physical progress indicators. Thus,
schedule performance indicators become free
from any dependency on planned cost values, and
therefore, are no longer influenced by them.
The concept of schedule monitoring and control as
one of the most important functions of project and
program management has not been fully exploited.
EVM was originally developed as a cost management
and control tool which was extended to track the
schedule as well. EVM and its derivatives (e.g.
Earned Schedule) use cost as a proxy to measure
schedule performance to control the duration of the
project. While there is a correlation between schedule,
cost, quality, and scope of a project, using cost to
control duration has proven to be misleading.